JPS61172927A - Method of building underground structure - Google Patents

Method of building underground structure

Info

Publication number
JPS61172927A
JPS61172927A JP60013467A JP1346785A JPS61172927A JP S61172927 A JPS61172927 A JP S61172927A JP 60013467 A JP60013467 A JP 60013467A JP 1346785 A JP1346785 A JP 1346785A JP S61172927 A JPS61172927 A JP S61172927A
Authority
JP
Japan
Prior art keywords
wall
sheathing
earth retaining
retaining wall
underground structure
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP60013467A
Other languages
Japanese (ja)
Inventor
Masatoshi Niwa
丹羽 正俊
Isao Tezuka
功 手塚
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Ohbayashi Gumi Ltd
Obayashi Corp
Original Assignee
Ohbayashi Gumi Ltd
Obayashi Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Ohbayashi Gumi Ltd, Obayashi Corp filed Critical Ohbayashi Gumi Ltd
Priority to JP60013467A priority Critical patent/JPS61172927A/en
Publication of JPS61172927A publication Critical patent/JPS61172927A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/045Underground structures, e.g. tunnels or galleries, built in the open air or by methods involving disturbance of the ground surface all along the location line; Methods of making them

Landscapes

  • Engineering & Computer Science (AREA)
  • Environmental & Geological Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Underground Structures, Protecting, Testing And Restoring Foundations (AREA)
  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

PURPOSE:To decrease the excessive wall thickness of a lining wall, by a method wherein the lining wall is built to a sheathing wall, built in a manner to surround an underground tank, with a specified gap therebetween, and a pressurized air is fed in the gap. CONSTITUTION:A sheathing wall 12 is built under a ground surface 10 in a manner to surround the surrounding of an underground tank by an underground continuous wall construction method. The inside surrounded with the sheathing wall 12 is excavated, and a lining wall 14 is built between the corresponding sheathing walls 12 with a gap part 16 therebetween. Pressurized fluid is fed in the gap part 16 from a pressurizing device 20, e.g., compressor, through a piping 18, the sheathing wall 12 is pressed against the ground 10 side to correct deformation. A solidifying agent is poured in the gap part 16 between the lining wall 14 and the sheathing wall 12 to integrally form the lining wall 14 and the sheathing wall 12. This enables prevention of excessive planing of the lining wall.

Description

【発明の詳細な説明】 (産業上の利用分野) この発明は、石油、LNG、LPGなどを地下に貯蔵す
る地下タンクなどの地下構造物、特に土留壁を用いて構
築されるコンクリート製地下構造物の構築工法に関する
Detailed Description of the Invention (Field of Industrial Application) This invention relates to underground structures such as underground tanks for storing petroleum, LNG, LPG, etc. underground, particularly concrete underground structures constructed using earth retaining walls. Concerning methods of constructing things.

(従来技術と問題点) 周知のように、地下構造物、例えば地下タンクを構築す
る場合、構築される地下タンクの周囲を囲繞するように
して土留壁が形成される。
(Prior Art and Problems) As is well known, when constructing an underground structure such as an underground tank, an earth retaining wall is formed to surround the underground tank to be constructed.

この種の土留壁は通常地下タンク本体が形成された後に
撤去する仮設壁とする場合が多いが、本体壁の一部とし
て用いる試みもなされている。
This type of earth retaining wall is usually a temporary wall that is removed after the underground tank body is formed, but attempts have also been made to use it as a part of the main body wall.

ここで、本体壁として土留壁を使用する際に以下に示す
問題があった。
Here, when using an earth retaining wall as the main body wall, there were the following problems.

すなわち、構築された土留壁の内部を掘削して本体を形
成する際には、適宜個所に切梁を設けて行っているが、
土留壁には周囲の土水圧が加わっているため、程度の差
があるにしろ殆ど変形しており、そのまま本体壁として
使用するには、信頼性上問題があった。
In other words, when excavating the inside of the constructed retaining wall to form the main body, struts are installed at appropriate locations.
Because the earth retaining wall is subjected to surrounding earth water pressure, most of the walls are deformed to varying degrees, and there are reliability problems in using them as they are as the main wall.

一方、本体の内巻壁の設計においては、上述した如き問
題があるため、周囲の土水圧などの作用荷重がすべてこ
れに作用するものとして行っている。
On the other hand, in the design of the inner wall of the main body, due to the above-mentioned problems, it is assumed that all applied loads such as surrounding earth water pressure act on it.

このため、壁厚が大きくなるなど過剰設計となる傾向が
あって、経済的な面でも問題があった。
For this reason, there was a tendency for excessive design, such as increased wall thickness, and there was also an economical problem.

本発明は、上述した如き従来の問題点に鑑みてなされた
ものであって、その目的とするところは、従来仮設壁と
して構築していた土留壁を本体壁として有効に利用でき
るとともに、内巻壁の適正な設計が可能となる地下構造
物の構築1法を提供するところにある。
The present invention has been made in view of the conventional problems as described above, and its purpose is to make it possible to effectively use the earth retaining wall, which was conventionally constructed as a temporary wall, as the main body wall, and to The purpose of this invention is to provide a method for constructing an underground structure that enables appropriate wall design.

(問題点を解決するための手段) 上記目的を達成するため、この発明は、構築される地下
構造物の周囲を囲w4ツるようにして土留壁を形成した
後、この土留壁の内側に地下構造物の内巻壁を形成する
地下構造物の構築工法において、前記内巻壁は土留壁と
の間に空隙部を画成して形成するとともに、この空隙部
内に圧力を導入することを特徴とする。
(Means for Solving the Problems) In order to achieve the above object, the present invention forms an earth retaining wall around an underground structure to be constructed, and then the inner side of the earth retaining wall is In an underground structure construction method that forms an inner wall of an underground structure, the inner wall is formed by defining a gap between it and the earth retaining wall, and pressure is introduced into this gap. Features.

(発明の作用) 土留壁と内巻壁との間に画成された空隙部に圧力を加え
ると、土留壁は地盤側に押し戻され、施工時の応力が緩
和され、変形がなくなる。
(Operation of the invention) When pressure is applied to the gap defined between the earth retaining wall and the inner wall, the earth retaining wall is pushed back toward the ground, the stress during construction is alleviated, and deformation is eliminated.

(実施例) 以下、この発明の好適な実施例について添附図面を参照
にして詳細に説明する。
(Embodiments) Hereinafter, preferred embodiments of the present invention will be described in detail with reference to the accompanying drawings.

第1図および第2図は、この発明に係る地下構造物の構
築工法の一実施例を示している。
FIGS. 1 and 2 show an embodiment of the method for constructing an underground structure according to the present invention.

同図に示す構築工法は、地下タンクを構築する場合に適
用したものであって、まず、地盤面10の下に地中連続
壁工法などによって、構築される地下タンクの周囲を囲
繞するようにして土留壁12を形成する。
The construction method shown in the figure is applied when constructing an underground tank. First, the underground tank to be constructed is surrounded by a continuous underground wall construction method under the ground surface 10. Then, the earth retaining wall 12 is formed.

次いで、土留壁12で囲んだ内部を適宜切梁などを設置
して掘削するとともに、その内側に逆巻工法により内巻
壁14を形成する。
Next, the inside surrounded by the earth retaining wall 12 is excavated by appropriately installing struts, etc., and the inner wall 14 is formed inside thereof by the reverse winding method.

ここで、本発明の工法では、上記土留壁12の内側面と
内巻壁14との外側面との間に空隙部16が画成される
ように内巻壁14を設ける。
Here, in the construction method of the present invention, the inner wall 14 is provided so that a gap 16 is defined between the inner surface of the retaining wall 12 and the outer surface of the inner wall 14.

空隙部16は、第1図に示すように、内巻壁14の外側
面を取り囲むように連続した状態でもよく、また、内巻
壁14と土留壁12とを部分的に連結して分断された状
態で複数に画成してもよい。
As shown in FIG. 1, the void 16 may be continuous so as to surround the outer surface of the inner wall 14, or may be separated by partially connecting the inner wall 14 and the retaining wall 12. It is also possible to define a plurality of images in the same state.

そして、内巻壁14の底部に底版部を構築した後、上記
空隙部16に配管18とコンプレッサなどの加圧装置2
0を設置する。
After constructing a bottom plate section at the bottom of the inner wall 14, a piping 18 and a pressurizing device 2 such as a compressor are inserted into the void section 16.
Set 0.

なお、加圧装置20の始動前に上記空隙部16の上端開
口には、例えばゴムなどの充填材を挿入して閉塞してお
く。
Note that before starting the pressurizing device 20, the upper end opening of the cavity 16 is closed by inserting a filler such as rubber, for example.

しかる後、加圧装置20を駆動して圧縮空気を送り込み
、空隙部16内に圧力Aを導入する。この圧力は、土留
壁12に加わる周囲の上、水圧などの作用荷重に見合っ
た大きさとする。
Thereafter, the pressurizing device 20 is driven to send compressed air to introduce pressure A into the cavity 16. This pressure should be of a magnitude commensurate with the loads applied to the earth retaining wall 12, such as the surrounding area and water pressure.

空隙部16内に導入された圧力Aは、第2図に示すよう
に、土留壁12と内巻壁14の両方に作用し、土留壁1
2は地盤10側に押し戻され、施工時の応力が緩和され
、変形が矯正されるみ一方、内巻壁14は圧力Aによっ
て内方に押されることになるが、この作用圧は上述のよ
うに土留壁12の作用荷重と同じである。
As shown in FIG. 2, the pressure A introduced into the cavity 16 acts on both the earth retaining wall 12 and the inner wall 14.
2 is pushed back toward the ground 10 side, the stress during construction is alleviated, and the deformation is corrected.On the other hand, the inner wall 14 is pushed inward by the pressure A, but this working pressure is as described above. This is the same as the acting load of the earth retaining wall 12.

従って、内巻壁14には、土留壁12の施工時の作用荷
重が直接作用しているのと同じ状態となり、何ら問題は
ない。
Therefore, the inner winding wall 14 is in the same state as if the load applied during construction of the earth retaining wall 12 is directly acting on it, and there is no problem.

そして、圧力Aの作用によって土留壁12の変形が矯正
されると、空隙部16内に例えばモルタルなどの固化材
を注入して、土留壁12と内巻壁14とを一体化して工
事が終了する。
When the deformation of the earth retaining wall 12 is corrected by the action of the pressure A, a solidifying material such as mortar is injected into the cavity 16 to integrate the earth retaining wall 12 and the inner wall 14, and the construction is completed. do.

この場合、固化材の注入によって空隙部16が徐々に小
さくなり、内圧が上昇する慣れがあるため、空隙部16
内に圧力計を設置し、空隙部16内の圧力Aが常時維持
できるように加圧装置20の圧力を調整することが望ま
しい。
In this case, since the void 16 gradually becomes smaller due to the injection of the solidifying material and the internal pressure increases, the void 16
It is desirable to install a pressure gauge inside and adjust the pressure of the pressurizing device 20 so that the pressure A inside the cavity 16 can be maintained at all times.

さて、上述した如く構成された地下構造物の構築工法で
は、空隙部16内に導入された圧力Aによって、土留壁
12が矯正された状態で内巻壁14と一体化されるため
、土留壁12を地下構造物の本体壁として、高信頼性の
下に有効に利用できる。
Now, in the construction method of the underground structure configured as described above, the earth retaining wall 12 is straightened and integrated with the inner wall 14 by the pressure A introduced into the cavity 16. 12 can be effectively used with high reliability as the main body wall of an underground structure.

この結果、内巻壁14は従来のように過剰設計にする必
要がなくなり、適正な設計が行われる。
As a result, the inner winding wall 14 does not need to be over-designed as in the conventional case, and an appropriate design can be performed.

なお、空隙部16内に導入する圧力Aは、上述した実施
例のように、圧縮空気を送り込むことだけでなく、例え
ば、土留壁12と内巻壁14とを一体化するために空隙
部16内に充填・注入されるモルタルなどの固化材に圧
力を加え、同化材を介して行ってもよい。
Note that the pressure A introduced into the cavity 16 is applied not only to feed compressed air as in the above-described embodiment, but also to, for example, apply pressure A to the cavity 16 in order to integrate the earth retaining wall 12 and the inner wall 14. Pressure may be applied to the solidifying material such as mortar that is filled and injected into the container, and the solidifying material may be passed through the assimilating material.

また、地下構造物としては、地下タンクだけでなく他の
構造物であってもよい。
Further, the underground structure may be not only an underground tank but also other structures.

(発明の効果) 以上、実施例で詳細に説明したように、この発明に係る
地下構造物の構築工法によれば、従来仮設用として考え
られていた土留壁を本体壁の一部分として有効に利用で
きるため、内巻壁の壁圧を適正なものとできるなどの優
れた効果が得られる。
(Effects of the Invention) As described above in detail in the examples, according to the construction method of an underground structure according to the present invention, the earth retaining wall, which was conventionally considered for temporary construction, can be effectively used as a part of the main body wall. As a result, excellent effects such as making it possible to keep the wall pressure of the inner winding wall appropriate can be obtained.

【図面の簡単な説明】[Brief explanation of drawings]

第1図はこの発明に係る構築工法の一実施例を示す説明
図、第2図は第1図の要部拡大図である。 10・・・地 盤     12・・・土留壁14・・
・内巻壁     16・・・空隙部A・・・・・・圧
 力
FIG. 1 is an explanatory diagram showing an embodiment of the construction method according to the present invention, and FIG. 2 is an enlarged view of the main part of FIG. 1. 10...Ground 12...Earth retaining wall 14...
・Inner wall 16...Gap part A...Pressure

Claims (3)

【特許請求の範囲】[Claims] (1)構築される地下構造物の周囲を囲繞するようにし
て土留壁を形成した後、該土留壁の内側に該地下構造物
の内巻壁を形成する地下構造物の構築工法において、該
内巻壁は該土留壁との間に間隙部を画成して形成すると
ともに、該空隙部内に圧力を導入することを特徴とする
地下構造物の構築工法。
(1) An underground structure construction method in which an earth retaining wall is formed to surround the underground structure to be constructed, and then an inner wall of the underground structure is formed inside the earth retaining wall. A construction method for an underground structure, characterized in that the inner wall is formed by defining a gap between it and the earth retaining wall, and pressure is introduced into the gap.
(2)上記圧力の導入は加圧エアーで行なうことを特徴
とする特許請求の範囲第1項記載の地下構造物の構築工
法。
(2) The method for constructing an underground structure according to claim 1, wherein the pressure is introduced using pressurized air.
(3)上記圧力の導入は上記空隙部内に充填され上記土
留壁と内巻壁とを一体化させる固化材を介して行なわれ
ることを特徴とする特許請求の範囲第1項記載の地下構
造物の構築工法。
(3) The underground structure according to claim 1, wherein the pressure is introduced through a solidifying material that is filled into the void and integrates the earth retaining wall and the inner wall. construction method.
JP60013467A 1985-01-29 1985-01-29 Method of building underground structure Pending JPS61172927A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP60013467A JPS61172927A (en) 1985-01-29 1985-01-29 Method of building underground structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP60013467A JPS61172927A (en) 1985-01-29 1985-01-29 Method of building underground structure

Publications (1)

Publication Number Publication Date
JPS61172927A true JPS61172927A (en) 1986-08-04

Family

ID=11833943

Family Applications (1)

Application Number Title Priority Date Filing Date
JP60013467A Pending JPS61172927A (en) 1985-01-29 1985-01-29 Method of building underground structure

Country Status (1)

Country Link
JP (1) JPS61172927A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2008230849A (en) * 2006-12-06 2008-10-02 Shimizu Corp Low-temperature rock reservoir and its construction method
CN103510572A (en) * 2012-06-29 2014-01-15 中国有色金属工业第六冶金建设有限公司 Construction method of water getting vertical shaft under complex geological condition

Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS59114336A (en) * 1982-12-22 1984-07-02 Taisei Corp Construction of underground structure

Patent Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS59114336A (en) * 1982-12-22 1984-07-02 Taisei Corp Construction of underground structure

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2008230849A (en) * 2006-12-06 2008-10-02 Shimizu Corp Low-temperature rock reservoir and its construction method
CN103510572A (en) * 2012-06-29 2014-01-15 中国有色金属工业第六冶金建设有限公司 Construction method of water getting vertical shaft under complex geological condition

Similar Documents

Publication Publication Date Title
EP1375754B1 (en) A packing apparatus and method for soil nailing
JPS61172927A (en) Method of building underground structure
WO2022021523A1 (en) Prefabricated component, end tensioning device of prefabricated component, and tensioning method
KR101029320B1 (en) Rock bolt and fixation method the rock bolt
KR101024604B1 (en) Pressure type reinforced unit soil nailing using inclined member and wrinkle-pipe
JP2730705B2 (en) Improvement method for soft ground
CN210597398U (en) Dog-ear type two-phase underground continuous wall cold joint waterproof construction
JP3647798B2 (en) Construction method of mountain retaining work and bag body therefor
KR101217488B1 (en) Extension structure of pile foundation
JP3644652B2 (en) Continuous wall method
JPH094365A (en) Long pipe prelining construction for tunnel and long pipe prelining pile
JP3637511B2 (en) Crack prevention method in high pressure gas storage facility in bedrock.
JPS5811270A (en) Constructing of tank made of concrete
JPH0784840B2 (en) Steel segment and tunnel construction method using steel segment
JP2002332634A (en) Cast-in-place steel pipe concrete pile and its execution method
JPH0197724A (en) Repairing of lining of horseshoe-shaped existing tunnel
JP2915257B2 (en) How to install steel shoring
JP2584608Y2 (en) Ground anchor free length sealing device
JP3275191B2 (en) Mountain retaining method
JPS6131599A (en) Tunnel covering construction method
JPH09184136A (en) Bearing plate and stabilization method for cut slope using the bearing plate
JPH0618158Y2 (en) Arched concrete plug
JPS58138869A (en) Construction of underground tank using underground continuous wall
JPH0711636A (en) Construction work of pile by use of existing pile
JPH08193497A (en) Segment having bag