JPS61169554A - Construction of ceiling and floor structure - Google Patents
Construction of ceiling and floor structureInfo
- Publication number
- JPS61169554A JPS61169554A JP60008866A JP886685A JPS61169554A JP S61169554 A JPS61169554 A JP S61169554A JP 60008866 A JP60008866 A JP 60008866A JP 886685 A JP886685 A JP 886685A JP S61169554 A JPS61169554 A JP S61169554A
- Authority
- JP
- Japan
- Prior art keywords
- ceiling
- materials
- concrete
- slab
- floor
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Landscapes
- Vehicle Interior And Exterior Ornaments, Soundproofing, And Insulation (AREA)
Abstract
(57)【要約】本公報は電子出願前の出願データであるた
め要約のデータは記録されません。(57) [Summary] This bulletin contains application data before electronic filing, so abstract data is not recorded.
Description
【発明の詳細な説明】
〔産業上の利用分野〕
本発明は、建築物の天井・床構造体を築造する方法に関
する。DETAILED DESCRIPTION OF THE INVENTION [Field of Industrial Application] The present invention relates to a method of constructing a ceiling/floor structure of a building.
従来、建築物の天井e床構造体の築造は、例えば第3図
に示すよ5K、柱材(図示せず)間に架け渡した大梁材
1間に小梁材2を架け渡し、この大梁材1および小梁材
2の上面に上階スラブ3を一体形成した後、上階スラブ
3の下方に床下配線用ダクト4やその他の配管類を配設
し、この配管類を覆うようにし天井仕上材5を天井吊り
ボルト6、ハンガー7、野縁受8および野縁9等により
上階スラ゛プ3に取り付ける方法がとられている。Conventionally, in the construction of a ceiling e-floor structure for a building, for example, as shown in FIG. After the upper floor slab 3 is integrally formed on the upper surface of the material 1 and the small beam material 2, the underfloor wiring duct 4 and other piping are arranged below the upper floor slab 3, and the ceiling is installed to cover the piping. A method is used for attaching the finishing material 5 to the upper floor slope 3 using ceiling hanging bolts 6, hangers 7, edge brackets 8, edges 9, and the like.
上記従来の築造方法によれば、以下に述べる種々の問題
がある。According to the above conventional construction method, there are various problems described below.
(υ 床下配線用ダクト等の配管類および天井仕上材等
の天井材の取り付は作業を、各梁材および上階スラブの
コンクリートの硬化後でなければ行うことができず1.
工期が長(なる。(υ Installation of pipes such as underfloor wiring ducts and ceiling materials such as ceiling finishing materials cannot be carried out until after the concrete of each beam material and upper floor slab has hardened.1.
The construction period is long.
(2)配管類および天井材の取り付は作業が、下階から
の脚立等を用いた上向き姿勢となるので、これらの作業
が困難となって施工に多大の時間を必要とする。(2) The installation of piping and ceiling materials requires work from the lower floor in an upward position using a stepladder, etc., which makes these tasks difficult and requires a great deal of time.
(!l) 築造後に間仕切壁の位置の変更を行い、自
動ドア等の重量物を設置する場合は、天井材の強度が小
さいため、野縁等の天井下地材を補強する必要がある。(!l) If the position of partition walls is changed after construction and heavy objects such as automatic doors are installed, the strength of the ceiling material is low, so it is necessary to reinforce the ceiling base material such as the veranda.
また、同様に築造後に床下配線用ダクト等の変更が生じ
た場合、その変更作業が天井内の困難な作業となり、(
2)で述べた問題が生ずる。Similarly, if changes are made to the underfloor wiring ducts, etc. after construction, the changes will be difficult work inside the ceiling.
The problem mentioned in 2) arises.
本発明は、上記問題点を解決するため、空調用給気孔、
埋込型照明器具および天井仕上材を設けたスラブ材を適
宜に離隔して柱材間に架け渡し、前記相隣るスラブ材間
にコンクリートを充填してスラブ材の上面に水平な貫通
孔を有しかっ梁成の等しい大梁および小梁を鉄筋コンク
リートによりスラブ材と一体に形成した後、その下面(
天井仕上材を取り付け、前記スラブ材およびコンクリー
トの上面に梁の梁成より低い束材を立設し、前記束材上
に床板材を梁の上面と一致するように取り外し自在に敷
設するものである。In order to solve the above problems, the present invention provides air conditioning air supply holes,
Slabs with recessed lighting equipment and ceiling finishing materials are placed between the pillars with appropriate distance between them, and concrete is filled between the adjacent slabs to form horizontal through holes on the top surface of the slabs. After forming large beams and small beams of equal beam size and integrally with the slab material using reinforced concrete, their lower surfaces (
Ceiling finishing materials are installed, bundled materials lower than the beam height of the beams are erected on the top surface of the slab material and concrete, and floor board materials are removably laid on the bundled materials so as to match the top surface of the beams. be.
スラブ材間にコンクリートを充填し、かつコンクリート
の下面に天井仕上材を取り付けることにより、空調用給
気孔を備えた下階の天井が完成する。また、上階の床と
下階の天井との間の大梁材と小梁材の梁部によって仕切
られた空間は、水平貫通孔によって互いに連通するので
、束材上に床板材を取り外し自在に敷設することKより
、上階の床が下階の天井と相俟って床下配線等の自由度
の高い二重床形式のフリーアクセスフロア−となる。By filling concrete between the slab materials and attaching ceiling finishing material to the underside of the concrete, the ceiling of the lower floor equipped with air conditioning ventilation holes is completed. In addition, the space partitioned by the beams of the large and small beams between the floor of the upper floor and the ceiling of the lower floor communicates with each other through horizontal through-holes, making it possible to freely remove the floorboards on the bundled materials. Due to the installation, the upper floor works together with the lower floor ceiling to form a double-floor free access floor with a high degree of freedom for underfloor wiring, etc.
以下、本発明の実施例を図面に基づいて説明する。 Embodiments of the present invention will be described below based on the drawings.
第1図は本発明の一実施例に係る天井Φ床構造体を示す
断面図、第2図は第1図における■−■線矢視断面図で
ある。FIG. 1 is a sectional view showing a ceiling Φ floor structure according to an embodiment of the present invention, and FIG. 2 is a sectional view taken along the line ■-■ in FIG.
図において柱材(図示せず)間に、ブレキャストコンク
リートからなる多数のスラブ材10を適宜に離隔して架
け渡す。In the figure, a large number of slab members 10 made of precast concrete are placed between pillar members (not shown) at appropriate distances.
なお、スラブ材10には、上下方向へ複数の空調用給気
孔11をあらかじめ所要位置に貫設し、また、スラブ材
10の下面には、下階の埋込型照明器具12および天井
仕上材13をあらかじめ取り付け、ついで、相隣るスラ
ブ材10間K、これらのスラブ材1oと相俟って下階の
天井スラブを形成するため、コンクリート14を充填す
るとともに、スラブ材10の上面に、空調用通気孔また
は床下配線挿通孔等として機能する水平に貫設した複数
の貫通孔15.16を有しかつ梁成の等しい大梁17お
よび小梁18を鉄筋コンクリートによりスラブ材1oと
一体化して形成する。Note that the slab material 10 has a plurality of air conditioning air supply holes 11 vertically penetrated through it at predetermined positions, and the lower surface of the slab material 10 is equipped with a recessed lighting fixture 12 on the lower floor and a ceiling finishing material. 13 is installed in advance, and then, in order to form the ceiling slab of the lower floor together with the adjacent slab materials 10 K and these slab materials 1o, concrete 14 is filled, and on the upper surface of the slab materials 10, A large beam 17 and a small beam 18 having a plurality of horizontally extending through holes 15 and 16 that function as air conditioning ventilation holes or underfloor wiring insertion holes, etc., and having the same beam thickness are formed by integrating the slab material 1o with reinforced concrete. do.
スラブ材10間のコンクリート14の硬化後その下面に
天井仕上材19を取り付け、この天井材19の取り付け
と並行してスラブ材1oおよびコンクリート14の上面
に、梁17.18の梁成より適宜に低い多数の束材2o
を立設して、これらの束材20上に方形の多数の床板材
21を梁17.18の上面と一致させて取り外し自在に
敷設する。After the concrete 14 between the slab materials 10 has hardened, a ceiling finishing material 19 is attached to the lower surface of the concrete 14, and in parallel with the installation of the ceiling material 19, the upper surfaces of the slab materials 1o and the concrete 14 are appropriately coated with beams 17 and 18. Low multiple bundle materials 2o
are erected, and a large number of rectangular floorboards 21 are removably laid on these bundles 20 in alignment with the upper surfaces of the beams 17 and 18.
以上のように本発明によれば、従来技術に比し、以下の
効果が得られる。As described above, according to the present invention, the following effects can be obtained compared to the conventional technology.
(1) スラブ材に空調用給気孔、埋込型照明器具お
よび天井仕上材があらかじめ設けられているので、従来
のように天井下地材を組み立てる必要がなく、スラブ材
間のコンクリートの硬化抜上の下面に天井仕上材を取り
付けることにより、下階の天井が短期間に完成する。(1) Air conditioning air supply holes, recessed lighting equipment, and ceiling finishing material are pre-installed on the slab material, so there is no need to assemble the ceiling base material as in the past, and the hardening of the concrete between the slab materials is eliminated. By attaching ceiling finishing material to the underside of the building, the ceiling of the lower floor can be completed in a short period of time.
(′2)床下配線等の配管類の配管作業が下向き姿勢と
なるので、これらの施工を容易にして短期間にしかも精
度よく行うことができる。('2) Since piping work such as underfloor wiring is performed in a downward position, these works can be easily carried out in a short period of time and with high precision.
(3) 築造後に間仕切壁の位置の変更およびこれに
伴う床下配線等の配管類の変更が生じた場合であっても
、従来のように天井下地材の補強や脚立等による上向き
姿勢での作業等を行5必要がな(、変更作業を容易にし
てかつ短期間に行うことができる。(3) Even if there is a change in the position of a partition wall after construction, or a corresponding change in piping such as underfloor wiring, work must be done in an upward position using a stepladder, etc., as in the past, by reinforcing the ceiling base material. etc., are not necessary in line 5 (this makes the change work easier and can be done in a short period of time.
第1図は本発明の一実施例罠係る天井・床構造体の断面
図、第2図は第1図における■−■線矢視断面図、第3
図は従来技術の断面図である。
10・・・スラブ材 11・・・空調用給気孔 12・
・・埋込型照明器具 13・・・天井仕上材 14・・
・コンク17−)15.16・・・貫通孔 17・・・
大梁18・・・小梁 19・・・天井仕上材 20・・
・横架材21・・・床板材
出願人 株式会社 間 組
第3図Fig. 1 is a sectional view of a ceiling/floor structure according to an embodiment of the present invention; Fig. 2 is a sectional view taken along the line ■-■ in Fig. 1;
The figure is a sectional view of the prior art. 10...Slab material 11...Air conditioning supply hole 12.
...Recessed lighting fixtures 13...Ceiling finishing materials 14...
・Conc 17-)15.16...Through hole 17...
Large beam 18...Small beam 19...Ceiling finishing material 20...
・Horizontal material 21...Floor board material applicant Hazama Gumi Co., Ltd. Figure 3
Claims (1)
たスラブ材を適宜に離隔して柱材間に架け渡し、前記相
隣るスラブ材間にコンクリートを充填してスラブ材の上
面に水平な貫通孔を有しかつ梁部の等しい大梁および小
梁を鉄筋コンクリートによりスラブ材と一体に形成した
後、その下面に天井仕上材を取り付け、前記スラブ材お
よびコンクリートの上面に梁の梁成より低い束材を立設
し、前記束材上に床板材を梁の上面と一致するように取
り外し自在に敷設する天井・床構造体の築造方法。Slabs equipped with air conditioning air supply holes, recessed lighting fixtures, and ceiling finishing materials are placed between pillars at appropriate distances, and concrete is filled between the adjacent slabs to cover the top surface of the slabs. After forming large beams and small beams with horizontal through-holes and equal beam parts integrally with a slab material using reinforced concrete, ceiling finishing material is attached to the lower surface of the beam, and the beam structure of the beam is attached to the upper surface of the slab material and concrete. A method of constructing a ceiling/floor structure in which a low bundle of materials is erected, and a floorboard material is removably laid on the bundle of materials so as to match the upper surface of a beam.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP60008866A JPS61169554A (en) | 1985-01-21 | 1985-01-21 | Construction of ceiling and floor structure |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP60008866A JPS61169554A (en) | 1985-01-21 | 1985-01-21 | Construction of ceiling and floor structure |
Publications (1)
Publication Number | Publication Date |
---|---|
JPS61169554A true JPS61169554A (en) | 1986-07-31 |
Family
ID=11704612
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP60008866A Pending JPS61169554A (en) | 1985-01-21 | 1985-01-21 | Construction of ceiling and floor structure |
Country Status (1)
Country | Link |
---|---|
JP (1) | JPS61169554A (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH0231654U (en) * | 1988-08-25 | 1990-02-28 |
-
1985
- 1985-01-21 JP JP60008866A patent/JPS61169554A/en active Pending
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH0231654U (en) * | 1988-08-25 | 1990-02-28 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
US4468911A (en) | System for forming structural concrete | |
US5163258A (en) | Method for arranging lines in a floor level to be divided up into smaller rooms and elements suitable for this method | |
JP3827431B2 (en) | Construction method of clean room building | |
JPS61169554A (en) | Construction of ceiling and floor structure | |
EP1726728B1 (en) | Method of erecting a partition wall integrated with a concrete floor | |
JPH11196525A (en) | Wiring method in unit constructing method | |
JPS61169553A (en) | Construction of ceiling and floor structure | |
JPS61162655A (en) | Ceiling and floor structure of building | |
JPS61162654A (en) | Ceiling and floor structure of building | |
GB2258668A (en) | Improvements in or relating to ceilings. | |
JPS6073937A (en) | Construction of floor or wall surface of building | |
JPH0320875B2 (en) | ||
JPS62264245A (en) | Room partitioning wall structure | |
JPH078676Y2 (en) | Building floor structure | |
RU1861U1 (en) | MULTI-STOREY BUILDING | |
JPH01102156A (en) | Slab structure | |
US829671A (en) | Partition construction. | |
JPS63261038A (en) | Floor structure of intelligent building | |
JP3516749B2 (en) | Under-floor wall structure of building | |
JPH05280141A (en) | Building frame employing hole-equipped pc board | |
JPS62296044A (en) | Small beam united pc floor panel | |
JPH07189403A (en) | Ceiling panel and construction method for housing | |
JPH10205035A (en) | Floor structure of precast reinforced concrete | |
JPH0350058B2 (en) | ||
JPH0681499A (en) | Method for installing toilet unit |