JPS61136161A - Working process planning systsem for individual production - Google Patents

Working process planning systsem for individual production

Info

Publication number
JPS61136161A
JPS61136161A JP59257381A JP25738184A JPS61136161A JP S61136161 A JPS61136161 A JP S61136161A JP 59257381 A JP59257381 A JP 59257381A JP 25738184 A JP25738184 A JP 25738184A JP S61136161 A JPS61136161 A JP S61136161A
Authority
JP
Japan
Prior art keywords
product
production
parts
date
information
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP59257381A
Other languages
Japanese (ja)
Other versions
JPH06101005B2 (en
Inventor
Hiroaki Sugihara
弘章 杉原
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Mitsubishi Electric Corp
Original Assignee
Mitsubishi Electric Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Mitsubishi Electric Corp filed Critical Mitsubishi Electric Corp
Priority to JP25738184A priority Critical patent/JPH06101005B2/en
Publication of JPS61136161A publication Critical patent/JPS61136161A/en
Publication of JPH06101005B2 publication Critical patent/JPH06101005B2/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02PCLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
    • Y02P90/00Enabling technologies with a potential contribution to greenhouse gas [GHG] emissions mitigation
    • Y02P90/02Total factory control, e.g. smart factories, flexible manufacturing systems [FMS] or integrated manufacturing systems [IMS]
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02PCLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
    • Y02P90/00Enabling technologies with a potential contribution to greenhouse gas [GHG] emissions mitigation
    • Y02P90/30Computing systems specially adapted for manufacturing

Abstract

PURPOSE:To continue the production of all prodcucts until the designated date for end of production of each product in consideration of the effects given to the processes of each parts with each other, by setting a working process plan with the allocation of working processes done in the order of working dates according to the number of margin days and the working time in each process in case each parts of plural products is produced through each process. CONSTITUTION:The commend of production is newly given to a product A while some processes of each parts are already started or completed with some products. thus the informations on the parts constitution and the working process of the product A are supplied together with the indicated date for the start of production and the indicated date for end of production for the product A. Then both the earliest and latest start dates are calculated for each process based on the information on the scheduled working data and working time, etc. at a factory stored in a memory 11. When these inflormation are obtained, the overall factory working process schedule is set and all products that can be started on the scheduled day for production are selected. then the parts are allocated as the process jobs in the order of smaller maring days and within the range of the working time on the relevant day. Such procedures are applied to all stages.

Description

【発明の詳細な説明】 〔産業上の利用分野〕 この発明は、個別生産すなわち一品ごとに異なる品種の
製品を製造する工場において、各工程における作業順序
を、工程情報を基に決定する加工工程計画方式に関する
ものである。
[Detailed Description of the Invention] [Field of Industrial Application] This invention relates to a processing process in which the work order in each process is determined based on process information in a factory that manufactures products of different types for each item. It concerns planning methods.

〔従来の技術〕[Conventional technology]

従来、仕事の計画立案には幾つかの方法が提案されてき
た。そのなかでも、個別生産においては、第5図に示さ
tLるようなpHi:RTと呼ばれる方式がよく使用さ
れてきた方法の1つであり、例えば講映社株式会社発行
のブルーパックスの[計画の科学J(B、7よりに示さ
れている。
Conventionally, several methods have been proposed for work planning. Among these, in individual production, the method called pHi:RT as shown in Figure 5 is one of the methods that has been often used. Science J (B, 7).

図において、(2f)は用紙、(ココ)はこの用紙(λ
l)上に書かれた矢印、(コ3)はこの矢印(2コ)の
両端に示す丸であり、丸(,2J、)と矢印(ユ2)の
組合わせで仕事の全体計画を表現して用紙(コl)上に
書いていた。
In the figure, (2f) is paper, and (here) is this paper (λ
l) The arrow written above (C3) is the circle shown at both ends of this arrow (2J), and the combination of the circle (,2J,) and the arrow (Y2) represents the overall plan of the work. and wrote it on a piece of paper.

次に第5図に示した従来の計画立案の作成の仕方を説明
丁Φ。まず、仕事の計画立案を行う場合、仕事の内容を
時系列的に分析し、図示のようく作業ユニットごとにa
、b、・・・・・・jと分解し、作業ユニットを矢印(
22)で、作業ユニットと作業ユニットの結合点を丸(
2J)で書き、分解した作業ユニットを互いに関連付け
ながら仕事の全体計画を表現していた。
Next, we will explain how to create a conventional plan as shown in Figure 5. First, when planning work, the content of the work is analyzed in chronological order, and a
, b, ......j, and the work units are indicated by arrows (
22), circle the connection point between the work units (
2J) and expressed the overall work plan by relating the disassembled work units to each other.

〔発明が解決しようとする問題点〕[Problem that the invention seeks to solve]

第5図に示したPERTを用いた従来の計画立案手法は
、ブルーパックスの「計画の科学」によると、元々ミサ
イルの開発計画のために生まれたものであり、ダムやビ
ルの連設などに用いられて力を発揮している。このよう
にPERTは単一の大きな目標の実現に対して非常に有
効な方法であるが、−品ものの製品複数個の製造が、異
なる時期に着手され、異なる時期に完了しなければなら
ない個別生産の製造工場では、条件が異なるという問題
があった。換言すると、各工程が有限な機械、人、時間
などの資源で構成されているため、ある製品の製造は必
ず他の製品の製造に影響を与え、PERTだけではこの
影響を考慮した複数個の製品の工程計画が非常に立て難
いという問題点があった。
According to Blue Pax's "Science of Planning," the conventional planning method using PERT shown in Figure 5 was originally developed for missile development plans, and was used for projects such as the construction of dams and buildings. It is used and exerts its power. In this way, PERT is a very effective method for achieving a single large goal; There was a problem with different conditions at the manufacturing plants. In other words, since each process is made up of limited resources such as machines, people, and time, the manufacturing of one product will always affect the manufacturing of other products, and PERT alone cannot solve the problem of multiple processes that take this influence into account. The problem was that it was very difficult to plan the product process.

この発明は、このような問題点を解決するためになされ
たもので、−品ものの複数個の製品の各部品が、有限な
資源で構成される各工程をまりって製造さlするとき、
互いに与える影響をも考慮して、かつ全製品が各々の具
造完了指示日までに製造完了となることを0指した加工
工程計画方式を提供することを目的とする。
This invention was made to solve these problems.
It is an object of the present invention to provide a processing process planning method that takes into account mutual influences and that all products are completed by their respective manufacturing completion instruction dates.

〔問題点を解決するための手段〕[Means for solving problems]

この発明に係る個別生産におけろ加工工程計画方式は、
製造しようとする製品各々について、部品ごとの各工程
の最早着手日と最遅着手日乞算出し、全ての!J品の各
部品の工程の着手、完了状況を考慮しながら、工場の稼
動予定日に沿って、順次各工程ごとに着手可能な部品を
全て選び出し、最遅着手日までの日数すなわち余裕日数
の少ない工程からその臼の作業とし′C割り振り、加工
工程計画を立てろものである。
The processing process planning method in individual production according to this invention is as follows:
For each product you plan to manufacture, calculate the earliest and latest start dates for each process for each part, and calculate all! While considering the start and completion status of each part of the J product's process, we sequentially select all the parts that can be started for each process in accordance with the scheduled start date of the factory, and calculate the number of days until the latest start date, that is, the number of remaining days. It is best to allocate work to the mill from a small number of steps and create a processing process plan.

〔作用〕[Effect]

この発明におい−Cは、d数製品の各部品の各工程の中
で、工程ごとに着手可能な部品2選び出し、余裕日数の
少ないものから早く着手するように加工工程計画を立て
る。
In this invention, -C selects two parts that can be started for each process from among each process of each part of the d number of products, and creates a processing process plan so that the parts with the least number of spare days are started first.

〔実施例〕〔Example〕

以下、この発明の一実施例を図について説明するO 第2図は工場の構成を示す概念図であり、図において(
1)は工場の加工現場、(2aハ(2b)・・(2j)
は加工現場(すな構成する各工程、(3)は加工現場(
1)に−接する工程計画管理部門であり、第2図では製
品人を構成する部品0/、0コ及び03が各工程を渡っ
て加工される様子が矢線(りで示されている。これら以
外にも図示しない他の製品の多くの部品が各工程を渡っ
ている。
Hereinafter, one embodiment of the present invention will be explained with reference to the drawings.
1) is a factory processing site, (2ac(2b)...(2j)
is the processing site (each of the constituent processes, (3) is the processing site (
This is the process planning management department that is in contact with 1), and in FIG. 2, arrows show how parts 0/, 0ko, and 03 that make up the product are processed through each process. In addition to these, many parts of other products (not shown) pass through each process.

第1図は、加工現場(/〕の加工の流れを工程計画管理
部門(3)でコントロールするために加工工程計画を立
てるだめの処理フローであり、製品一つずつについて各
部品の各工程ごとに最早着手日、最遅着手日を算出し、
既に製造着手している製品については実績入力を行い、
禾完成の製品全部についての加工工程計画を立でる様子
を示しでいる。
Figure 1 shows the processing flow for creating a processing process plan to control the processing flow at the processing site (/) in the process planning management department (3). Calculate the earliest start date and latest start date,
For products that have already started manufacturing, enter the actual results.
It shows how a processing plan is created for all finished products.

中間情報及び加エエ8 fiI画情報は記憶装置(ll
)に貯えられる。
Intermediate information and modification 8 fiI image information are stored in a storage device (ll
).

第3図は、工程計画管理部門(3)の主要部をなす情報
処理装置(10)の−例を示す構成図であり、入出力装
置(/3)を介して入力された情報は中央処理装置(/
λ)で処理された後記憶装置(ll)に貯えられろ。ま
た、記憶装置(11)に貯えられた情報を基にして、中
央処理装置(lコ)で算出された工場全体の加工工程計
画情報などは、記憶装置(//)に貯えられるほか、必
要に応じて出力装置(l<zンから出力される。
FIG. 3 is a block diagram showing an example of the information processing device (10) that forms the main part of the process planning management department (3), and the information input via the input/output device (/3) is centrally processed. Device(/
λ) and then stored in the storage device (ll). In addition, processing process planning information for the entire factory calculated by the central processing unit (lco) based on the information stored in the storage device (11) is stored in the storage device (//) as well as other information as needed. is output from the output device (l<zn) according to

第V図は第二図に例示した製品Aに関する各部品の加工
工程情報を示す表であり、これらは第3図の入出力装f
lc13)を介して記憶装置(//)に入力される。
Figure V is a table showing the processing process information for each part regarding product A illustrated in Figure 2, and these are
lc13) to the storage device (//).

次に、これらにより、工場全体の加工工程計画を立てる
場合の手順を第1図にメついて説明する。
Next, the procedure for creating a machining process plan for the entire factory based on these will be explained with reference to FIG.

−例として、既に幾つかの製品について、その各々の部
品の幾つかの工程が着手されていたり完了していたりす
る状態で、新たに第二図及び第V図に示された製品Aに
ついて製造指令が来たとき、工場全体の加工工程計画を
立てる場合、新たに着手しなければならない製品Aにつ
いては、製品Aの部品構成及び第V図に示した加工工程
情報を入カシ(ステップBi)、製品Aの製造着手指示
日及び製造完了指示日を入力する(ステップ3.2)。
- For example, when some processes for each part of several products have already been started or completed, product A shown in Figures 2 and 5 is newly manufactured. When a command is received and a machining process plan is created for the entire factory, for product A that must be newly started, input the component configuration of product A and the machining process information shown in Figure V (step Bi). , the date of instruction to start manufacturing and the date of instruction to complete manufacturing for product A are input (step 3.2).

そして、予め工場の稼動計画が決ったときなどに入力済
みで(ステップS3)、記憶装置(11)に記憶させで
ある工場稼動予定日及び稼動時間などの情報とともに、
各工程ごとの最早着手日及び最遅着手日を算出する(ス
テップS<<)。
Then, along with information such as the scheduled factory operating date and operating hours, which have already been input when the factory operating plan has been decided in advance (step S3) and are stored in the storage device (11),
The earliest start date and latest start date for each process are calculated (step S<<).

既に着手している製品については、着手する前に同様の
算出を行い、工程着手、工程完了などの実績入力が行わ
れ(ステップsr )、この清報も含めて記憶装置(/
/)に記憶、保持される。
For products that have already been started, similar calculations are performed before the start, and results such as process start and process completion are entered (step sr), and this update information is also stored in the storage device (/
/) is stored and retained.

このような情報が揃ったうえで、工場全体の加工工程計
画を立てることKなる。その手法として    ・は、
例えば明日からの計画を立てる場合、今日までの工程着
手、工程完了などの実績を全て行った後、計画上の日付
を明日にしくステップ5b)1.1つの工程に関し、そ
の日に着手可能な全ての部品を選びだす(ステップ37
)。そして余裕日数の少ない部品からその日の稼動時間
の範囲内で、その工程の作業として割り振る(ステップ
sg)。
Once this information is gathered, it is necessary to create a processing plan for the entire factory. As a method,
For example, when making a plan starting tomorrow, after checking all the actual results such as process start and process completion up to today, set the planning date to tomorrow.Step 5b) (Step 37)
). Then, parts with the least number of spare days are assigned as work for that process within the operating hours of that day (step sg).

これをすべての工程について行う。Do this for all processes.

次に、割り振ったこれらの作業が全て計画どおり終了す
るものとして、割り振りについては、直後の工程を調べ
、条件が整えば直後の工程を着手可能としたう丸で(ス
テップSq)、計画上の日付を1日進め(ステップ51
0)、全期間について済んでいなければ同じ作業を繰り
返すが(ステツブ87〜570)、済んでいftf7j
らば終了とするO このようにして、既に着手している製品と、新だに着手
しようとする製品Aとを含めた全ての製品についての加
工工程計画ができあがり、その結果は、例えば出力装置
(/II)によって出力され、各工程が示される。
Next, assuming that all of the assigned tasks will be completed as planned, we will examine the next process and, if the conditions are right, we will be able to start the next process (step Sq). Advance the date by one day (step 51)
0), if the entire period has not been completed, the same work will be repeated (steps 87 to 570), but if it has been completed, ftf7j
In this way, the machining process plans for all products, including the products that have already been started and the product A that is about to start, are completed, and the results are displayed on the output device, for example. (/II) to show each step.

ここでは或る部品の或る工程における滞在日数は第V図
に示したような形で加工工程情報の一部として与えられ
る場合について述べたが、加工工程情報の一部として与
えられる加工時間から一定の算出式によって滞在日数を
算出してもよい。
Here, we have described the case where the number of days a certain part stays in a certain process is given as part of the machining process information in the form shown in Figure V. The length of stay may be calculated using a certain formula.

〔発明の効果〕〔Effect of the invention〕

以上のように、この発明によれば、−品ものの複a個の
製品の各部品が各工程をまわって製造されるとき、各工
程における余裕日数及び稼動時間を基とに稼動8順に割
り振って加工工程計画を立てるので、各部品の各工程が
互いに与える影響をも考慮してかつ全製品が各々の製造
完了指示日までに製造完了となることを目指した加工工
程計画を立て、製造現場に示すことによってスムーズな
製造が行え、工程確保を目指すことができろという効果
がある。
As described above, according to the present invention, when each part of a plurality of products is manufactured through each process, the parts are allocated in the order of 8 operations based on the number of spare days and operation time in each process. Since we create a processing process plan, we create a processing process plan that takes into account the effects of each process for each part on each other, and aims to complete manufacturing of all products by the specified manufacturing completion date, and then proceed to the manufacturing site. This has the effect of ensuring smooth manufacturing and ensuring process reliability.

【図面の簡単な説明】[Brief explanation of the drawing]

第1図シエこの発明の一実施例を示す処理フロー図、第
二図は工場の構成を示す概念図、第3図は情報処理装置
の一例を示すブロック図、第V図は製品Aに関する各部
品の加工工程情報の表を示す図、第5図は製品AK関す
る従来の計画立案の説関口である。 (υ・・加工現場、(コ&)<コbバ2c)(,2d)
(λe)(2f)C2g)(コhJ(コ1バ2J)・・
工程、(3)・・工程計画管理部門、(す・・矢線、(
10)・・情報処理装置、(//)・・記憶装置、(1
2)・・中央処理装置、(/J)・・入出力装置、(l
<z)・・出力装置。 なお、各図中、同一符号は同−又は相当部分を示す。 氾2図 ゛ 1 I −−J
FIG. 1 is a process flow diagram showing an embodiment of the present invention, FIG. 2 is a conceptual diagram showing the configuration of a factory, FIG. 3 is a block diagram showing an example of an information processing device, and FIG. FIG. 5, which is a diagram showing a table of processing process information for parts, is an introduction to conventional planning regarding product AK. (υ... processing site, (ko&)<kobba2c) (,2d)
(λe)(2f)C2g)(kohJ(ko1ba2J)...
Process, (3)...Process planning management department, (S...Arrow, (
10)...Information processing device, (//)...Storage device, (1
2)... Central processing unit, (/J)... Input/output device, (l
<z)...Output device. In each figure, the same reference numerals indicate the same or corresponding parts. Flood 2 Figure 1 I --J

Claims (1)

【特許請求の範囲】 一品ごとに異なる品種の製品を製造する工場において、 或る品種の製品の部品構成と、各部品の加工工程情報す
なわち加工工程順及び工程ごとの加工時間とを入力する
第1の手段と、 その品種の製品の製造着手指示日及び製造完了指示日を
入力する第2の手段と、 工場の稼動予定日及び各稼動予定日の稼動時間を入力す
る第3の手段と、 上記第1の手段ないし上記第3の手段によつて入力され
た情報によつて、その部品だけを作る場合のその部品の
全ての部品の全ての工程の最早着手日及び最遅着手日を
算出する第4の手段と、毎日、製造中の製品についてど
の製品のどの部品のどの工程に着手して、どの工程が完
了したかを入力する第5の手段と、 工場で製造中の全ての製品について、上記第1の手段な
いし上記第5の手段によつて得られた情報などを記憶し
、取り出す第6の手段と、 この第6の手段によつて得られた情報のうち、着手可能
な工程を選び出す第7の手段と、 この第7の手段で得られた情報を、各工程ごとに上記第
3の手段で得られた稼動予定日に割り振るとき、上記第
4の手段で得られた最遅着手日までの工場稼動日数すな
わち余裕日数の少ない部品から、上記第3の手段で得ら
れたその日の稼動時間内で割り振る加工工程計画を立て
る第8の手段と、 割り振つたものの後工程を調べ、条件が整つていれば着
手可能として、上記第6の手段により記憶させる第9の
手段と、 を備え、工場全体で製造中の全製品が各々の製造完了指
示日までに製造完了となることを目指した加工工程計画
を立てることを特徴とする個別生産における加工工程計
画方式。
[Claims] In a factory that manufactures products of different types for each item, there is a process for inputting the component configuration of a certain type of product and processing process information for each part, that is, the order of processing steps and processing time for each process. a second means for inputting a production start date and a production completion instruction date for the product of the type; and a third means for inputting a scheduled factory operation date and operating hours for each scheduled operation date; Based on the information input by the first means to the third means, calculate the earliest start date and latest start date of all processes for all parts of that part when only that part is manufactured. a fourth means for inputting information on which process of which part of which product has been started and which process has been completed for each product being manufactured each day; a sixth means for storing and retrieving the information obtained by the first to fifth means; and a sixth means for storing and retrieving information obtained by the sixth means; A seventh means for selecting a process; and when allocating the information obtained by this seventh means to each process on the scheduled operating date obtained by the third means, An eighth means of creating a processing process plan that allocates parts within the operating hours of the day obtained by the third method above, starting from parts with fewer factory operating days, that is, fewer spare days, until the latest start date, and post-processing of the allocated ones. and a ninth means for storing the information as if it is possible to start if the conditions are met by the sixth means, and all products being manufactured in the entire factory are completed by the respective manufacturing completion instruction dates. A processing process planning method for individual production that is characterized by creating a processing process plan that aims to achieve the following.
JP25738184A 1984-12-07 1984-12-07 Machining process plan creation device for individual production Expired - Lifetime JPH06101005B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP25738184A JPH06101005B2 (en) 1984-12-07 1984-12-07 Machining process plan creation device for individual production

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP25738184A JPH06101005B2 (en) 1984-12-07 1984-12-07 Machining process plan creation device for individual production

Publications (2)

Publication Number Publication Date
JPS61136161A true JPS61136161A (en) 1986-06-24
JPH06101005B2 JPH06101005B2 (en) 1994-12-12

Family

ID=17305595

Family Applications (1)

Application Number Title Priority Date Filing Date
JP25738184A Expired - Lifetime JPH06101005B2 (en) 1984-12-07 1984-12-07 Machining process plan creation device for individual production

Country Status (1)

Country Link
JP (1) JPH06101005B2 (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS6357159A (en) * 1986-08-28 1988-03-11 Mitsubishi Electric Corp Work sequence indication system
JPS63298665A (en) * 1987-05-29 1988-12-06 Kanebo Ltd Production planning device
JPH01166202A (en) * 1987-12-01 1989-06-30 Internatl Business Mach Corp <Ibm> Automatic production release system
JPH02310703A (en) * 1989-05-26 1990-12-26 Chugoku Nippon Denki Software Kk Process managing device
EP1158379A2 (en) * 2000-05-25 2001-11-28 Fuji Photo Film Co., Ltd. Print schedule planning method, print schedule planning system and print schedule planning program storage medium

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS6357159A (en) * 1986-08-28 1988-03-11 Mitsubishi Electric Corp Work sequence indication system
JPS63298665A (en) * 1987-05-29 1988-12-06 Kanebo Ltd Production planning device
JPH01166202A (en) * 1987-12-01 1989-06-30 Internatl Business Mach Corp <Ibm> Automatic production release system
JPH02310703A (en) * 1989-05-26 1990-12-26 Chugoku Nippon Denki Software Kk Process managing device
EP1158379A2 (en) * 2000-05-25 2001-11-28 Fuji Photo Film Co., Ltd. Print schedule planning method, print schedule planning system and print schedule planning program storage medium
EP1158379A3 (en) * 2000-05-25 2006-08-16 Fuji Photo Film Co., Ltd. Print schedule planning method, print schedule planning system and print schedule planning program storage medium

Also Published As

Publication number Publication date
JPH06101005B2 (en) 1994-12-12

Similar Documents

Publication Publication Date Title
JP4587246B2 (en) Computerized supply chain planning methodology
JPH09153090A (en) Method and device for forming working process production plan
JPH03116237A (en) Knowledge processing method
JPS61136161A (en) Working process planning systsem for individual production
JP2007213141A (en) Personnel distribution system, personnel distribution method, personnel distribution program, and recording medium with the program recorded thereon
JPS60258606A (en) Automatic programming system
JPS62224562A (en) Display device for process control data
KR102315373B1 (en) Construction process navigation providing method
JP2002055710A (en) Process chart editing system
JPH05174030A (en) Job shop scheduling expert system
JPH0373257A (en) Production scheduling device
JPH01121155A (en) Production scheduling system
JPH04233073A (en) Method for piling-up loads
JPH02236769A (en) Schedule preparing device
JPH03161250A (en) Production scheduling device
JPH07182420A (en) Production planning device
JPH09174392A (en) Progress supervising system
JPH07168881A (en) Work control system
JP7353420B1 (en) Scheduling device, scheduling method, and scheduling program
JP2527266B2 (en) Scheduling method in knowledge-based system
JPH09282373A (en) Schedule control method
JPH09216146A (en) Preparation method of working plan for multiple automatic machine tools
JP2953223B2 (en) Scheduling planning equipment
JPH08137949A (en) Method for changing plan of gantt chart
CN114926013A (en) Contract set batch production control method, device, equipment and storage medium