JPH09174392A - Progress supervising system - Google Patents

Progress supervising system

Info

Publication number
JPH09174392A
JPH09174392A JP34051495A JP34051495A JPH09174392A JP H09174392 A JPH09174392 A JP H09174392A JP 34051495 A JP34051495 A JP 34051495A JP 34051495 A JP34051495 A JP 34051495A JP H09174392 A JPH09174392 A JP H09174392A
Authority
JP
Japan
Prior art keywords
progress
line
work
date
scheduled
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP34051495A
Other languages
Japanese (ja)
Inventor
Yoshinori Yamaguchi
良則 山口
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Fujitsu Ltd
Original Assignee
Fujitsu Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Fujitsu Ltd filed Critical Fujitsu Ltd
Priority to JP34051495A priority Critical patent/JPH09174392A/en
Publication of JPH09174392A publication Critical patent/JPH09174392A/en
Pending legal-status Critical Current

Links

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02PCLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
    • Y02P90/00Enabling technologies with a potential contribution to greenhouse gas [GHG] emissions mitigation
    • Y02P90/02Total factory control, e.g. smart factories, flexible manufacturing systems [FMS] or integrated manufacturing systems [IMS]
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02PCLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
    • Y02P90/00Enabling technologies with a potential contribution to greenhouse gas [GHG] emissions mitigation
    • Y02P90/30Computing systems specially adapted for manufacturing

Landscapes

  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)
  • Multi-Process Working Machines And Systems (AREA)
  • General Factory Administration (AREA)
  • Control By Computers (AREA)

Abstract

PROBLEM TO BE SOLVED: To visually indicate the progress of work of which plural work items is executed in parallel by providing progress supervising figure display means for output displaying a progress supervising figure including a calender line, schedule line on which each actual result line is superposed and progress line. SOLUTION: Progress supervising figure display means 106 output displays a progeress supervising figure including a calender line, planning line on which each actual result line is superposed and a progress line. Progress ratio calculating means 102d stores each progress ratio calculated corresponding to each finished work number in input information storing means 101 corresponding to each finished work number. Progress line editing means 105 reserves the progress line corresponding to each progress checking date as a history and it is displayed on the progress supervising figure.

Description

【発明の詳細な説明】Detailed Description of the Invention

【0001】[0001]

【発明の属する技術分野】本発明は進捗管理システムに
関し、特に複数の作業項目を並行して実行し、且つ各作
業項目が複数の作業工程に区分され、区分された各作業
工程を順次達成することにより、一つの作業項目が完了
する如き作業の、進捗状況を管理するに有効な進捗管理
システムの改良に関する。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a progress management system, and more particularly to executing a plurality of work items in parallel, dividing each work item into a plurality of work steps, and successively achieving each of the divided work steps. Therefore, the present invention relates to improvement of a progress management system effective for managing the progress of a work such that one work item is completed.

【0002】[0002]

【従来の技術】図6は従来ある進捗管理図を例示する図
である。図6に示される進捗管理図は、複数の機能
(F)〔個々の機能(F)を(FA)、(FB )等と称
する、以下同様〕を具備する情報処理システムのプログ
ラムの開発作業の進捗状況を管理することを目的とした
ものであり、各機能(F)を実現する為のプログラムを
並行して開発するもので、各機能(F)が作業項目に相
当する。
2. Description of the Related Art FIG. 6 is a diagram illustrating a conventional progress management chart. The progress management chart shown in FIG. 6 shows the development of a program for an information processing system having a plurality of functions (F) [individual functions (F) are called (F A ), (F B ), etc.] The purpose is to manage the progress of work, a program for realizing each function (F) is developed in parallel, and each function (F) corresponds to a work item.

【0003】各機能(F)は、それぞれ複数の開発工程
に区分されており、機能(FA )および(FB )は、機
能設計(FD)、詳細設計(DD)、コーディング・フ
ァイル化(MK)等に区分され、機能(FC )は機能設
計(FD)および詳細設計(DD)に区分され、機能
(FD )は基本設計(BD)、機能設計(FD)および
詳細設計(DD)に区分されている。
Each function (F) is divided into a plurality of development processes, and the functions (F A ) and (F B ) are the functional design (FD), detailed design (DD), and coding file ( is divided into MK) or the like, function (F C) is partitioned into functional design (FD) and detailed design (DD), function (F D) basic design (BD), the functional design (FD) and the detailed design (DD ).

【0004】図6に示される進捗管理図には、全機能
(F)に共通にカレンダ線(CL)が設けられており、
また各機能(F)に対応して、それぞれ予定線(PL)
および実績線(RL)が設けられている。
In the progress management chart shown in FIG. 6, a calendar line (CL) is provided commonly to all functions (F),
The planned line (PL) for each function (F)
And a performance line (RL) is provided.

【0005】カレンダ線(CL)には、開発期間におけ
る暦日が表示されており、各予定線(PL)および実績
線(RL)の時間軸の役割を果たす。またカレンダ線
(CL)上には、開発途中で進捗状況を検査する進捗チ
ェック日(CT)が、複数箇所〔図6においては7月1
3日(=CT1 )、8月3日(=CT2 )および8月1
7日(=CT3 )〕に記入されている。
The calendar line (CL) displays calendar days in the development period, and serves as a time axis for each schedule line (PL) and actual line (RL). Also, on the calendar line (CL), there are multiple progress check dates (CT) for inspecting the progress status during the development (July 1 in FIG. 6).
3rd (= CT 1 ), 3rd August (= CT 2 ) and 1st August
7th (= CT 3 )].

【0006】各予定線(PL)は、各開発工程毎の開始
予定日および終了予定日により区分されている。例えば
機能(FA )に対応する予定線(PLA )は、7月31
日が機能設計(FD)の終了予定日、8月1日が詳細設
計(DD)の開始予定日、8月15日が詳細設計(D
D)の終了予定日、8月16日がコーディング・ファイ
ル化(MK)の開始予定日、8月31日がコーディング
・ファイル化(MK)の終了予定日であることを示す。
Each schedule line (PL) is divided by a scheduled start date and a scheduled end date for each development process. For example, the scheduled line (PL A ) corresponding to the function (F A ) is July 31
The day is the planned end date of the functional design (FD), the August 1 is the scheduled start date of the detailed design (DD), and the August 15 is the detailed design (D)
The scheduled end date of D), August 16 is the scheduled start date of coding file (MK), and August 31 is the scheduled end date of coding file (MK).

【0007】また各実績線(RL)は、最新の進捗チェ
ック日(CT)において、目下作業中の開発工程の消化
作業量が、該開発工程の全作業量に対する比率〔以後進
捗率(GR)と称する〕で示されている。
Further, each performance line (RL) is such that, on the latest progress check date (CT), the ratio of the amount of work consumed in the development process currently being worked to the total amount of work of the development process [progress rate (GR) hereafter] Is called].

【0008】なお全作業量を完了した開発工程に関して
は、完了日に完了点(FP)が実績線(RL)上に記入
されている。図6に示される進捗管理図は、進捗チェッ
ク日(CT2 =8月3日)に対応する実績線(RL)が
示されており、例えは機能(FA )に対応する実績線
(RL A )は、機能設計(FD)の開発工程が予定線
(PL)通りに完了し、詳細設計(DD)の開発工程が
進捗チェック日(CT2 )において20%消化されてい
ることを示している。
Regarding the development process in which the total amount of work is completed
Indicates the completion point (FP) on the performance line (RL) on the completion date
Have been. The progress management chart shown in Fig. 6 is a progress check
Ku day (CTTwo= Actual line (RL) corresponding to (August 3)
It is shown, for example, the function (FA) Corresponding to the actual line
(RL A) Indicates that the development process of functional design (FD) is a planned line
Completed according to (PL), detailed design (DD) development process
Progress check date (CTTwo20% digested in
Which indicates that.

【0009】以下同様に、機能(FB )に対応する実績
線(RLB )は、機能設計(FD)の開発工程が予定線
(PL)より遅れて進捗チェック日(CT2 )に完了
し、詳細設計(DD)の開発工程が進捗チェック日(C
2 )において未着手〔=0%〕であることを示してお
り、また機能(FC )に対応する実績線(RLC )は、
機能設計(FD)の開発工程が89%消化されているこ
とを示しており、更に機能(FD )に対応する実績線
(RLD )は、基本設計(BD)の開発工程が予定線
(PL)より早く完了し、機能設計(FD)の開発工程
が進捗チェック日(CT2 )において32%消化されて
いることを示している。
[0009] Similarly, the function actual line corresponding to (F B) (RL B) is completed functional design development process is expected to line (FD) (PL) than delayed progress check Date (CT 2) , The detailed design (DD) development process progress check date (C
T 2) shows that it is not started [0%] in, also functions (actual line corresponding to F C) (RL C) is
Development process of functional design (FD) shows that is 89% digested, further functional performance line corresponding to the (F D) (RL D) the development process of the basic design (BD) is scheduled line ( It is completed earlier than PL) and shows that the development process of the functional design (FD) has been completed by 32% on the progress check date (CT 2 ).

【0010】[0010]

【発明が解決しようとする課題】以上の説明から明らか
な如く、従来ある進捗管理図においては、各実績線(R
L)は、最新の進捗チェック日(CT2 =8月3日)に
おける各機能(F)に対応するの開発作業の進捗状況を
数値で示しているが、予定に対する進捗程度を視覚的に
把握することが困難であると共に、前回の進捗チェック
日(CT1 =7月13日)から今回の進捗チェック日
(CT2 =8月3日)迄に、どの程度進捗があったかが
表示されていない為、前回の進捗チェック日(CT1
7月13日)に出力された進捗管理図を保存して置き、
両図を比較しなければ判明せず、更に各機能(F)の
内、特に進捗の遅延しているものを把握することが困難
である等の問題があった。
As is apparent from the above description, in the conventional progress management chart, each performance line (R
L) shows the progress status of the development work corresponding to each function (F) on the latest progress check date (CT 2 = August 3rd) numerically, but visually grasps the degree of progress against the schedule. It is difficult to do, and how much progress has been made from the last progress check date (CT 1 = July 13) to this progress check date (CT 2 = August 3) is not displayed. Therefore, the last progress check date (CT 1 =
Save the progress chart output on July 13th)
There is a problem in that it cannot be found unless the two figures are compared, and it is difficult to grasp the progress of each function (F) that is particularly delayed.

【0011】本発明は、複数の作業項目を並行して実行
する作業の進捗状況を視覚的に明示可能な進捗管理図を
生成することを目的とする。
It is an object of the present invention to generate a progress control chart in which the progress of a work for executing a plurality of work items in parallel can be visually specified.

【0012】[0012]

【課題を解決するための手段】図1は本発明の原理図で
ある。図1において、100は本発明の対象となる進捗
管理システムである。
FIG. 1 is a diagram illustrating the principle of the present invention. In FIG. 1, reference numeral 100 is a progress management system to which the present invention is applied.

【0013】101は、本発明により進捗管理システム
(100)に設けられた入力情報記憶手段である。10
2は、本発明により進捗管理システム(100)に設け
られた進捗率算出手段である。
Reference numeral 101 is an input information storage means provided in the progress management system (100) according to the present invention. 10
Reference numeral 2 is a progress rate calculating means provided in the progress management system (100) according to the present invention.

【0014】103は、本発明により進捗管理システム
(100)に設けられた予定線編集手段である。104
は、本発明により進捗管理システム(100)に設けら
れた実績線編集手段である。
Reference numeral 103 is a schedule line editing means provided in the progress management system (100) according to the present invention. 104
Is a performance line editing means provided in the progress management system (100) according to the present invention.

【0015】105は、本発明により進捗管理システム
(100)に設けられた進捗線編集手段である。106
は、本発明により進捗管理システム(100)に設けら
れた進捗管理図表示手段である。
Reference numeral 105 is a progress line editing means provided in the progress management system (100) according to the present invention. 106
Is a progress management chart display means provided in the progress management system (100) according to the present invention.

【0016】入力情報記憶手段(101)は、並行して
実行される複数の作業項目を構成する各作業工程の開始
予定日(ST)と終了予定日(ET)と、各作業工程の
予定仕事数(NP )と、各作業項目の各作業工程の進捗
状況を検査する進捗チェック日(CT)と、各進捗チェ
ック日(CT)に検査した実際の消化仕事数(NR )と
を入力された場合に、入力された各情報を記憶する。
The input information storage means (101) includes a scheduled start date (ST) and a scheduled end date (ET) of each work process constituting a plurality of work items to be executed in parallel, and a scheduled work of each work process. Enter the number (N P ), progress check date (CT) to check the progress of each work process of each work item, and the actual number of completed work (N R ) inspected on each progress check date (CT) If the information is input, the input information is stored.

【0017】進捗率算出手段(102)は、各作業項目
の各作業工程毎の消化仕事数(NR)が入力情報記憶手
段(101)に記憶される度に、該消化仕事数(NR
と対応する予定仕事数(NP )とを入力情報記憶手段
(101)から抽出し、予定仕事数(NP )に対する前
記消化仕事数(NR )の比率により進捗率(GR)を算
出する。
The progress rate calculation means (102), when the number of digested work (N R ) for each work process of each work item is stored in the input information storage means (101), the number of consumed work (N R) )
And extracted from the corresponding scheduled job number (N P) input information storage means (101) to calculate a progress rate (GR) by the ratio of scheduled work number (N P) the digestion work number for (N R) .

【0018】予定線編集手段(103)は、各作業項目
毎の各作業工程の開始予定日(ST)および終了予定日
(ET)を入力情報記憶手段(101)から抽出し、各
工程開始予定日(ST)および工程終了予定日(ET)
を、暦日の基準となるカレンダ線(CL)に対応させて
直線上に配列し、最初の作業工程の開始予定日(ST)
と、最後の作業工程の終了予定日(ET)とを所定の表
示形式の直線で結ぶ予定線(PL)を、各作業項目毎に
編集する。
The schedule line editing means (103) extracts the scheduled start date (ST) and scheduled finish date (ET) of each work process for each work item from the input information storage means (101) and plans each process start. Date (ST) and Scheduled End Date (ET)
Are arranged on a straight line corresponding to the calendar line (CL) that serves as the calendar date, and the scheduled start date (ST) of the first work process
And a planned line (PL) that connects a scheduled end date (ET) of the last work process with a straight line in a predetermined display format are edited for each work item.

【0019】実績線編集手段(104)は、予定線編集
手段(103)が編集した各作業項目毎の予定線(P
L)上の、各作業工程毎の工程開始予定日(ST)と工
程終了予定日(ET)との間の区間を当該作業工程の全
予定仕事数(NP )に対応させ、進捗率算出手段(10
2)が算出した進捗率(GR)を示す進捗点(GP)
を、該作業工程の開始予定日(ST)を起点として記入
し、予定線(PL)上の最初の作業工程の開始予定日
(ST)から最新の進捗点(GP)迄の区間を、予定線
(PL)に重畳して予定線(PL)と異なる表示形式の
直線で結ぶ実績線(RL)を、各作業項目毎に編集す
る。
The actual line editing means (104) edits the scheduled line (P) for each work item edited by the scheduled line editing means (103).
L) on, to correspond to the total scheduled work section number of the working process during the working steps each step scheduled start date and (ST) process scheduled end date and (ET) (N P), progress rate calculation Means (10
Progress point (GP) showing progress rate (GR) calculated by 2)
Is entered starting from the scheduled start date (ST) of the work process, and the section from the scheduled start date (ST) of the first work process to the latest progress point (GP) on the planned line (PL) is scheduled. A performance line (RL) that is superimposed on the line (PL) and is connected by a straight line having a display format different from the planned line (PL) is edited for each work item.

【0020】進捗線編集手段(105)は、カレンダ線
(CL)上に各進捗チェック日(CT)を記入し、各作
業項目毎に編集された実績線(RL)を重畳した予定線
(PL)を、カレンダ線(CL)を暦日の基準として並
行にて配置した後、カレンダ線(CL)上の各進捗チェ
ック日(CT)と、各実績線(RL)を重畳した予定線
(PL)上に記入された各進捗チェック日(CT)に対
応する進捗点(GP)とを順次連結する進捗線(GL)
を編集する。
The progress line editing means (105) writes each progress check date (CT) on the calendar line (CL), and a planned line (PL) on which a track record line (RL) edited for each work item is superimposed. ) Are arranged in parallel with the calendar line (CL) as the reference of the calendar day, and then the planned line (PL) in which each progress check date (CT) on the calendar line (CL) and each actual line (RL) are superimposed. ) Progress line (GL) that sequentially connects the progress points (GP) corresponding to each progress check date (CT) entered above
Edit.

【0021】進捗管理図表示手段(106)は、カレン
ダ線(CL)、各実績線(RL)を重畳した予定線(P
L)、並びに進捗線(GL)を含む進捗管理図を、出力
表示する。
The progress control chart display means (106) is a schedule line (P) in which the calendar line (CL) and each performance line (RL) are superposed.
L) and a progress management chart including a progress line (GL) are output and displayed.

【0022】なお進捗率算出手段(102)は、各消化
仕事数(NR )に対応して算出した各進捗率(GR)
を、各消化仕事数(NR )に対応して入力情報記憶手段
(101)に記憶させることが考慮される。
The progress rate calculation means (102) calculates each progress rate (GR) corresponding to each digested work number (N R ).
Is considered to be stored in the input information storage means (101) in correspondence with each number of digestion work (N R ).

【0023】また進捗線編集手段(105)は、各進捗
チェック日(CT)に対応する進捗線(GL)を履歴と
して保存して置き、進捗管理図表示手段(106)が表
示する進捗管理図上に並行して表示することが考慮され
る。
The progress line editing means (105) saves and stores a progress line (GL) corresponding to each progress check date (CT) as a history, and the progress management chart displayed by the progress management chart display means (106). It is considered to display them side by side.

【0024】また予定線編集手段(103)は、予定線
(PL)を並行した二本の並行線で表現し、実績線編集
手段(104)は、予定線(PL)上の実績線(RL)
に相当する範囲の並行線間を黒く塗潰すことで、実績線
(RL)を予定線(PL)に重畳して表現することが考
慮される。
Further, the planned line editing means (103) expresses the planned line (PL) by two parallel lines, and the actual line editing means (104) expresses the actual line (RL) on the planned line (PL). )
It is considered to represent the actual line (RL) by superimposing it on the planned line (PL) by blackening the space between parallel lines in the range corresponding to.

【0025】更に進捗管理図表示手段(106)は、遠
隔に設置された複数の端末装置のディスプレイ上に表示
することが考慮される。従って、本進捗管理システムが
出力表示する進捗管理図によれば、各作業項目毎の各進
捗チェック日における進捗率が記録保存される為、過去
の各進捗チェック日間での進捗状況も視覚的に把握可能
となり、また各作業項目の各進捗チェック日に対応する
進捗点が進捗線により連結され、記録保存される為、作
業項目相互間の遅延状況が視覚的に把握可能となり、更
に実績線が予定線に重畳されて表示される為、各作業項
目毎に予定に対する実績の進捗状況がより直接的に把握
可能となると共に、表示も簡素化され、当該進捗管理図
の効用が大幅に向上する。
Further, it is considered that the progress control chart display means (106) displays on the display of a plurality of terminal devices installed remotely. Therefore, according to the progress management chart output and displayed by this progress management system, since the progress rate on each progress check day for each work item is recorded and saved, the progress status on each progress check day in the past is visually displayed. It is possible to grasp, and the progress points corresponding to each progress check date of each work item are linked by a progress line and recorded and saved, so it is possible to visually grasp the delay status between work items, and further the actual line Since it is displayed superimposed on the schedule line, it is possible to more directly grasp the progress status of the actual results for each work item for each schedule, the display is simplified, and the utility of the progress management chart is greatly improved. .

【0026】[0026]

【発明の実施の形態】以下、本発明の実施形態を図面に
より説明する。図2は本発明の実施形態による進捗管理
システムを示す図であり、図3は図2における進捗管理
図編集処理を例示する図であり、図4は本発明の実施形
態による進捗管理図(その一)を示す図であり。図5は
本発明の実施形態による進捗管理図(その二)を示す図
である。なお、全図を通じて同一符号は同一対象物を示
す。
BEST MODE FOR CARRYING OUT THE INVENTION Embodiments of the present invention will be described below with reference to the drawings. 2 is a diagram showing a progress management system according to an embodiment of the present invention, FIG. 3 is a diagram illustrating a progress management diagram editing process in FIG. 2, and FIG. 4 is a progress management diagram according to the embodiment of the present invention (part thereof). FIG. FIG. 5 is a diagram showing a progress management diagram (No. 2) according to the embodiment of the present invention. The same reference numerals indicate the same objects throughout the drawings.

【0027】図2においては、図1における進捗管理シ
ステム(100)として、共通サーバ(1)および複数
の端末装置(2)から構成される進捗管理システムが示
されている。
FIG. 2 shows a progress management system (100) shown in FIG. 1, which is a progress management system including a common server (1) and a plurality of terminal devices (2).

【0028】共通サーバ(1)は、処理部(3)および
記憶部(4)から構成されている。記憶部(4)内に
は、各機能(F)に対応する工程管理テーブル(機能
F)(41)が設けられ、また処理部(3)内には、入
出力制御部(31)、格納部(32)、抽出部(3
3)、進捗率算出部(34)および進捗管理図表示部
(35)が設けられ、また進捗管理図表示部(35)内
には、予定線編集部(351)、実績線編集部(35
2)および進捗線編集部(353)が設けられている。
The common server (1) comprises a processing section (3) and a storage section (4). A process control table (function F) (41) corresponding to each function (F) is provided in the storage unit (4), and an input / output control unit (31) and a storage unit are stored in the processing unit (3). Part (32), extraction part (3
3), a progress rate calculation unit (34) and a progress management chart display unit (35) are provided, and in the progress management chart display unit (35), a schedule line editing unit (351) and a performance line editing unit (35) are provided.
2) and a progress line editing unit (353) are provided.

【0029】なお格納部(32)および抽出部(33)
と、各工程管理テーブル(機能F)(41)とは、図1
における入力情報記憶手段(101)に相当し、また進
捗率算出部(34)は、図1における進捗率算出手段
(102)に相当し、また予定線編集部(351)、実
績線編集部(352)、進捗線編集部(353)はそれ
ぞれ図1における予定線編集手段(103)、実績線編
集手段(104)および進捗線編集手段(105)に相
当し、更に進捗管理図表示部(35)は、図1における
進捗管理図表示手段(106)に相当する。
The storage section (32) and the extraction section (33)
And each process management table (function F) (41) are as shown in FIG.
1 corresponds to the input information storage means (101), the progress rate calculation section (34) corresponds to the progress rate calculation means (102) in FIG. 1, a planned line editing section (351), and a performance line editing section (). 352) and the progress line editing unit (353) correspond to the planned line editing unit (103), the performance line editing unit (104) and the progress line editing unit (105) in FIG. 1, respectively, and the progress management diagram display unit (35). ) Corresponds to the progress management chart display means (106) in FIG.

【0030】図2乃至図5においても、本進捗管理シス
テムは、図6におけると略同様に、八種類の機能
(FA )乃至(FH )を具備する情報処理システムのプ
ログラムの開発作業の進捗状況を管理することを目的と
し、各機能(F)が作業項目に相当し、また各機能
(F)は、図6におけると同様に、基本設計(BD)、
機能設計(FD)、詳細設計(DD)、コーディング・
ファイル化(MK)、単体試験(CT)等の開発工程
(RS)に区分されているものとする。
2 to 5, the progress management system of the present invention is similar to that of FIG. 6, and is used for the development work of the program of the information processing system having eight kinds of functions (F A ) to (F H ). For the purpose of managing the progress, each function (F) corresponds to a work item, and each function (F) has a basic design (BD), as in FIG.
Functional design (FD), detailed design (DD), coding
It shall be divided into the development process (RS) such as file conversion (MK) and unit test (CT).

【0031】かかる開発作業の進捗管理を開始するに先
立ち、各機能(FA )乃至(FH )毎の各開発工程(R
S)の開始予定日(ST)、終了予定日(ET)および
予定仕事数(NP )が、例えば端末装置(21 )のキー
ボード(211 )から入力されると、共通サーバ(1)
は、入力された各種情報を、処理部(3)内の入出力制
御部(31)および格納部(32)を介して記憶部
(4)内に設けられている各工程管理テーブル(4
A )乃至(41H )内の所定領域に順次格納する。
Prior to starting the progress management of the development work, each development process (R) for each function (F A ) to (F H )
When the scheduled start date (ST), the scheduled end date (ET) and the planned number of jobs (NP) of S ) are input from the keyboard (21 1 ) of the terminal device (2 1 ), for example, the common server (1)
Is a process management table (4) provided in the storage unit (4) via the input / output control unit (31) and the storage unit (32) in the processing unit (3).
The data is sequentially stored in a predetermined area within 1 A ) to (41 H ).

【0032】なお各機能(FA )乃至(FH )の、最初
の開発工程(RS)の開始予定日(ST)は何れも7月
1日とし、最後の開発工程(RS)の終了予定日(E
T)は何れも9月30日とする。
The scheduled start date (ST) of the first development process (RS) of each of the functions (F A ) to (F H ) is July 1, and the final development process (RS) is scheduled to end. Day (E
All of T) shall be September 30th.

【0033】各工程管理テーブル(41A )乃至(41
H )への入力情報の格納が完了すると、共通サーバ
(1)は、最初に処理部(3)内の進捗管理図表示部
(35)を起動する。
Each process control table (41 A ) to (41 A )
When the storage of the input information in H ) is completed, the common server (1) first activates the progress management chart display unit (35) in the processing unit (3).

【0034】起動された進捗管理図表示部(35)は、
記憶部(4)内の各工程管理テーブル(41A )乃至
(41H )を参照し、格納済の最も早い開発工程(R
S)の開始予定日(ST=7月1日)と、最も遅い開発
工程(RS)の終了予定日(ET=9月30日)とを含
む、図4に示される如きカレンダ線(CL)を編集させ
る。
The started progress control chart display section (35)
The earliest stored development process (R) is referred to by referring to each process control table (41 A ) to (41 H ) in the storage unit (4).
Calendar line (CL) as shown in FIG. 4, including the scheduled start date of (S) (ST = July 1st) and the scheduled finish date of the latest development process (RS) (ET = September 30th). To edit.

【0035】また開発過程における進捗チェック日(C
T)が決定済〔例えば第一回(CT 1 )が7月13日、
第二回(CT2 )が8月3日、第三回(CT3 )が8月
17日〕の場合には、各進捗チェック日(CT1 )乃至
(CT3 )をカレンダ線(CL)上に記入する〔図3ス
テップS1〕。
The progress check date (C
T) has been decided [eg, the first (CT 1) Is July 13,
Second time (CTTwo) On 3rd August (CT)Three) Is August
17th], each progress check date (CT1) Or
(CTThree) On the calendar line (CL) [Fig.
Step S1].

【0036】次に共通サーバ(1)は、処理部(3)内
の進捗管理図表示部(35)に設けられている予定線編
集部(351)を起動する。起動された予定線編集部
(351)は、記憶部(4)内の各工程管理テーブル
(41A )乃至(41H )を参照し、それぞれ格納され
ている各開発工程(RS)の開始予定日(ST)および
終了予定日(ET)を抽出し、カレンダ線(CL)を基
準として各機能(FA )乃至(FH )毎に直線上に配列
した後、並行する二本の直線により接続し、図4に示さ
れる如く、各機能(FA )乃至(FH )毎の予定線(P
A )乃至(PLH )を編集する〔ステップS2〕。
Next, the common server (1) activates the schedule line editing unit (351) provided in the progress management chart display unit (35) in the processing unit (3). The started schedule line editing unit (351) refers to each process management table (41 A ) to (41 H ) in the storage unit (4) to start each development process (RS) stored therein. After extracting the day (ST) and the scheduled end date (ET) and arranging them on a straight line for each function (F A ) to (F H ) based on the calendar line (CL), two parallel lines are used. Connected, as shown in FIG. 4, a planned line (P) for each function (F A ) to (F H ).
L A ) to (PL H ) are edited [step S2].

【0037】以上の状態では、各予定線(PLA )乃至
(PLH )を構成する各二並行直線間は白抜きの状態に
あり、また各開発工程(RS)の工程終了予定日(E
T)を示す完了点(FP)が、白抜きの逆三角形で表示
されている。
In the above-mentioned state, the two parallel straight lines forming each of the planned lines (PL A ) to (PL H ) are in a blank state, and the scheduled process end date (E) of each development process (RS) is
The completion point (FP) indicating T) is displayed by a white inverted triangle.

【0038】かかる状態で、最初の進捗チェック日(C
1 =7月13日)が到来すると、各機能(FA )乃至
(FH )の現時点における各開発工程(RS)の消化仕
事数(NRA1 )乃至(NRH1 )を検査し、進捗チェック
日(CT1 )および各開発工程(RS)毎の消化仕事数
(NRA1 )乃至(NRH1 )を、任意の端末装置(2)か
ら入力すると、共通サーバ(1)は、入力された進捗チ
ェック日(CT1 )を各工程管理テーブル(41A )乃
至(41H )の進捗履歴領域の先頭に格納すると共に、
一緒に入力された各開発工程(RS)毎の消化仕事数
(NRA1 )乃至(NRH1 )を、それぞれ対応する工程管
理テーブル(41A )乃至(41H )の、進捗チェック
日(CT1 )および各対応する開発工程(RS)に対応
する領域に格納する〔図3ステップS3〕。
In this state, the first progress check date (C
(T 1 = July 13), the number of digestion work (N RA1 ) to (N RH1 ) of each development process (RS) at the present time of each function (F A ) to (F H ) is inspected, and progress is made. When the check date (CT 1 ) and the number of digesting work (N RA1 ) to (N RH1 ) for each development process (RS) are input from any terminal device (2), the common server (1) is input. The progress check date (CT 1 ) is stored at the beginning of the progress history area of each process control table (41 A ) to (41 H ), and
The number of digestion work (N RA1 ) to (N RH1 ) for each development process (RS) entered together is used to check the progress check date (CT 1 ) of the corresponding process control tables (41 A ) to (41 H ). ) And each corresponding development process (RS) in the area [step S3 in FIG. 3].

【0039】例えば、機能(FA )に対応しては、最初
の開発工程(RS)が機能設計(FD)であるので、進
捗チェック日(CT1 )および消化仕事数(NRA1
が、機能(FA )および機能設計(FD)と共に入力さ
れると、工程管理テーブル(41A )の機能設計(F
D)および進捗チェック日(CT1 )に対応する領域
に、消化仕事数(NRA1 )が格納される。
For example, for the function (F A ), since the first development process (RS) is the functional design (FD), the progress check date (CT 1 ) and the number of digested work (N RA1 )
Is input together with the function (F A ) and the function design (FD), the function design (F A ) of the process control table (41 A ) is input.
In the area corresponding to D) and the progress check date (CT 1 ), the number of exhausted work (N RA1 ) is stored.

【0040】他の機能(FB )乃至(FH )に対応して
も、機能(FA )と同様に、入力された消化仕事数(N
RB1 )乃至(NRH1 )が、それぞれ工程管理テーブル
(41 B )乃至(41H )の進捗チェック日(CT1
および指定開発工程(RS)対応領域に格納される。
Other functions (FB) To (FH) Corresponding to
Function (FA), The number of input digestion work (N
RB1) Through (NRH1) Is the process control table
(41 B) To (41H) Progress check date (CT1)
And the designated development process (RS) corresponding area.

【0041】進捗チェック日(CT1 )および各消化仕
事数(NRA1 )乃至(NRH1 )が入力し終わると、共通
サーバ(1)は、対象作業を構成する機能(FA )乃至
(F H )の中から一機能〔例えば機能(FA )〕を選択
した後〔ステップS4〕、処理部(3)内の進捗率算出
部(34)を起動する。
Progress check date (CT1) And digesters
Number of events (NRA1) Through (NRH1) Is complete, common
The server (1) has a function (FA) Or
(F H)) One function [for example, function (FA)〕choose
After that [step S4], the progress rate in the processing unit (3) is calculated.
The section (34) is activated.

【0042】起動された進捗率算出部(34)は、選出
された機能(FA )に対応する工程管理テーブル(41
A )を参照し、進捗チェック日(CT1 )に対応する消
化仕事数(NRA1 )が、機能設計(FD)のみに対応し
て格納されていることを確認すると、消化仕事数(N
RA1 )と、機能設計(FD)の予定仕事数(NPAFD)と
を抽出し、予定仕事数(NPAFD)に対する消化仕事数
(NRA1 )の比率で進捗率(GRA1=NRA1 ÷NPAFD
を算出する〔ステップS5〕。
The activated progress rate calculation section (34) operates the process control table (41) corresponding to the selected function (F A ).
When referring to ( A ) and confirming that the number of completed work (N RA1 ) corresponding to the progress check date (CT 1 ) is stored corresponding to only the functional design (FD), the number of completed work (N RA1 )
RA1 ) and the planned work number (N PAFD ) of the functional design (FD) are extracted, and the progress rate (GR A1 = N RA1 ÷ N) is obtained by the ratio of the number of digested work (N RA1 ) to the planned work number (N PAFD ). PAFD )
Is calculated [step S5].

【0043】次に共通サーバ(1)は、処理部(3)内
の進捗管理図表示部(35)に設けられている実績線編
集部(352)を起動する。起動された実績線編集部
(352)は、進捗率算出部(34)が算出した進捗率
(GRA1)を用いて、機能(FA )に対応する予定線
(PLA )上に、進捗点(GPA1)の位置を、次の過程
で決定する。
Next, the common server (1) activates the performance line editing unit (352) provided in the progress management chart display unit (35) in the processing unit (3). The started performance line editing unit (352) uses the progress rate (GR A1 ) calculated by the progress rate calculating unit (34) to make progress on the planned line (PL A ) corresponding to the function (F A ). The position of the point (GP A1 ) is determined in the next process.

【0044】即ち、予定線(PLA )上の機能設計(F
A )に対応する区間を予定仕事数(NPAFD)、即ち機
能設計(FD)における進捗率(GRA )の100%に
対応させ、機能設計(FD)の工程開始予定日(ST)
から進捗率算出部(34)が算出した進捗率(GRA1
だけ工程終了予定日(ET)の方向に移動した位置を進
捗点(GPA1)と決定する。
[0044] In other words, the planned line (PL A) on the functional design (F
The section corresponding to D A ) corresponds to the planned number of jobs (N PAFD ), that is, 100% of the progress rate (GR A ) in the functional design (FD), and the process start scheduled date (ST) of the functional design (FD)
Progress rate (GR A1 ) calculated by the progress rate calculation unit (34) from
The position moved toward the scheduled process end date (ET) is determined as the progress point (GP A1 ).

【0045】次に実績線編集部(352)は、予定線
(PLA )の機能設計(FD)に相当する区間の内、工
程開始予定日(ST)から進捗点(GPA1)迄の区間の
み、予定線(PLA )の二並行直線間を黒く塗潰し、実
績線(RLA1)として編集する〔ステップS6〕。
Next, the performance line editing unit (352) is a section from the planned process start date (ST) to the progress point (GP A1 ) in the section corresponding to the functional design (FD) of the planned line (PL A ). Only, the space between the two parallel lines of the planned line (PL A ) is painted black and edited as the actual line (RL A1 ) [step S6].

【0046】即ち実績線(RLA1)は、編集済の予定線
(PLA )に重畳して編集されたこととなる。なお実績
線(RL)上に完了点(FP)が存在した場合には、完
了点(FP)も黒く塗潰す〔機能(FD )に対応する実
績線(RLD1)参照〕。
That is, the actual line (RL A1 ) is edited by being superimposed on the edited planned line (PL A ). Note that if the completion point on actual line (RL) (FP) was present, completion point (FP) is also crush black paint [Function actual line corresponding to the (F D) (RL D1) refer to Fig.

【0047】以上で選出された機能(FA )に関する実
績線(RLA1)の編集が終了すると、共通サーバ(1)
は、残る機能(FB )乃至(FH )の中から次の一機能
〔例えば機能(FB )〕を選択し〔ステップS3〕、前
述と同様の過程により、機能(FB )に対応する実績線
(RLB1)を編集し、以下同様にして、総ての機能(F
A )乃至(FH )の実績線(RLA1)乃至(RLH1)を
編集し終わる迄、ステップS3乃至S6の過程を繰返
す。
When the editing of the performance line (RL A1 ) relating to the function (F A ) selected above is completed, the common server (1)
The next one function from among the remaining functional (F B) to (F H) [e.g. function (F B)] to select the [Step S3], corresponding to the process similar to that described above, function (F B) Edit the performance line (RL B1 ) that you want to edit, and do the same for all the functions (F
The steps S3 to S6 are repeated until the performance lines (RL A1 ) to (RL H1 ) of A ) to (F H ) are edited.

【0048】総ての機能(FA )乃至(FH )に関する
実績線(RLA1)乃至(RLH1)を編集し終わると、共
通サーバ(1)は、処理部(3)内の進捗管理図表示部
(35)に設けられている進捗線編集部(353)を起
動する。
When the performance lines (RL A1 ) to (RL H1 ) for all the functions (F A ) to (F H ) are edited, the common server (1) manages the progress management in the processing unit (3). The progress line editing unit (353) provided in the diagram display unit (35) is activated.

【0049】起動された進捗線編集部(353)は、カ
レンダ線(CL)上に記入されている今回の進捗チェッ
ク日(CT1 )と、各機能(FA )乃至(FH )に対応
する実績線(RLA1)乃至(RLH1)上に記入されてい
る進捗点(GPA1)乃至(GPB1)とを、図4に示す如
く、順次直線で連結し、進捗線(GL1 )を編集する
〔ステップS8〕。
The activated progress line editing unit (353) corresponds to the present progress check date (CT 1 ) entered on the calendar line (CL) and each function (F A ) to (F H ). The progress points (GP A1 ) to (GP B1 ) entered on the performance lines (RL A1 ) to (RL H1 ) are sequentially connected in a straight line as shown in FIG. 4, and the progress line (GL 1 ) Is edited [step S8].

【0050】以上でカレンダ線(CL)、各機能
(FA )乃至(FH )に対応する予定線(PLA )乃至
(PLH )、進捗チェック日(CT1 )に対応する進捗
点(GPA1)乃至(GPH1)、実績線(RLA1)乃至
(RLH1)、進捗線(GL1 )の編集が終了すると、共
通サーバ(1)は、処理部(3)内の入出力制御部(3
1)を介して各端末装置(2)に各種編集情報を転送
し、図4に示される如き進捗管理図(その一)を、ディ
スプレイ(22)上に表示させる〔ステップS9〕。
As described above, the calendar line (CL), the planned lines (PL A ) to (PL H ) corresponding to the respective functions (F A ) to (F H ), and the progress points (CT 1 ) corresponding to the progress check date (CT 1 ). When editing of GP A1 ) to (GP H1 ), performance lines (RL A1 ) to (RL H1 ) and progress line (GL 1 ) is completed, the common server (1) controls the input / output of the processing unit (3). Division (3
Various editing information is transferred to each terminal device (2) via 1), and a progress management chart (part 1) as shown in FIG. 4 is displayed on the display (22) [step S9].

【0051】図4に示される進捗管理図(その一)を観
察すると、各機能(FA )乃至(F H )に関する進捗状
況が、進捗線(GL1 )により明示されている。即ち機
能(FC )および(FE )に関する進捗点(GPC1)お
よび(GPE1)がカレンダ線(CL)上の進捗チェック
日(CT1 )と略同位置に在ることから、機能(FC
および(FE )に関する機能設計(FD)は略予定通り
進捗しており、進捗率(GRC1)および(CRE1)がそ
れぞれ約35%および約45%を示している。
View the progress management chart (part 1) shown in FIG.
When you think about it, each function (FA) To (F H) Status
Situation is progress line (GL1). That is, the machine
Noh (FC) And (FE) About progress point (GPC1)
And (GPE1) Is the progress check on the calendar line (CL)
Day (CT1), It is in the same position, so the function (FC)
And (FEThe functional design (FD) for
Progress is being made, and the progress rate (GRC1) And (CRE1)
It shows about 35% and about 45%, respectively.

【0052】また機能(FD )に関する基本設計(B
D)は、進捗チェック日(CT1 )より先〔即ち工程終
了予定日(ET)に近く〕に在ることから、機能
(FD )に関する基本設計(BD)は予定以上に進捗し
ており、且つ進捗点(GPD1)が基本設計(BD)の完
了点(FPB )と一致しており完了点(FPB )も黒く
塗潰されていることから、機能(FD )に関する基本設
計(BD)が、進捗チェック日(CT1 )迄に完了して
いることが認識される。
[0052] The function (F D) on the basic design (B
D) is, from the fact that there prior to the progress check date (CT 1) [that is close to the process scheduled end date (ET)], function (F D) on the basic design (BD) is on track to more than planned and since the progress point (GP D1) is crushed completion point (FP B) and matched to and completion point (FP B) also black coating of the basic design (BD), function (F D) on the basic design It is recognized that (BD) has been completed by the progress check date (CT 1 ).

【0053】一方、機能(FA )、(FB )、
(FF )、(FG )および(FH )に関する進捗点(G
A1)、(GPB1)、(GPF1)、(GPG1)および
(GPH1)がカレンダ線(CL)上の進捗チェック日
(CT1 )より前〔即ち工程開始予定日(ST)に近
く〕に在ることから、機能(FA )、(FB )および
(FH )に関する機能設計(FD)、並びに機能
(FF )および(FG )に関する基本設計(BD)は予
定より進捗が遅れており、機能(FA )および(FB
の機能設計(FD)は進捗率(GRA1)および(G
B1)がそれぞれ約40%を示し、また機能(FF )の
基本設計(BD)は進捗率(GRF1)が約80%を示
し、遅延程度も僅少であるが、特に機能(FG )の基本
設計(BD)は進捗率(GRG1)が約70%を示し、ま
た機能(FH )の機能設計(FD)の進捗率(GRH1
が約35%を示し、最も遅延していることが判明する。
On the other hand, the functions (F A ), (F B ),
Progress Points (G) for (F F ), (F G ) and (F H ).
P A1 ), (GP B1 ), (GP F1 ), (GP G1 ) and (GP H1 ) are before the progress check date (CT 1 ) on the calendar line (CL) [that is, the process start date (ST)] since near], function (F a), from the basic design (BD) is planned about (F B) and (F H) for functional design (FD), as well as functional (F F) and (F G) Progress is slow and functions (F A ) and (F B )
The functional design (FD) of is the progress rate (GR A1 ) and (G
R B1 ) shows about 40% each, and the basic design (BD) of the function (F F ) shows a progress rate (GR F1 ) of about 80%, and the delay is very small, but especially the function (F G) ), The progress rate (GR G1 ) of the basic design (BD) is about 70%, and the progress rate (GR H1 ) of the functional design (FD) of the function (F H ).
Shows about 35%, which proves to be the most delayed.

【0054】以上により、進捗チェック日(CT1 )に
おける各機能(FA )乃至(FH )の進捗状況が、進捗
管理図に明示されることとなる。以下同様にして、当該
開発作業が進捗し、進捗チェック日(CT2 =8月3
日)および(CT3 =8月17日)が到来すると、前述
と同様の過程で、各機能(FA )乃至(FH )の各開発
工程(RS)の進捗状況が検査され、進捗チェック日
(CT)および各機能(F)毎および各開発工程(R
S)毎の消化仕事数(N R )が、それぞれ対応する開発
工程(RS)と共に端末装置(2)から入力されると、
共通サーバ(1)は、前述と同様の過程により、入力情
報を各工程管理テーブル(41)に格納した後、進捗率
(GR)の算出、進捗点(GP)の位置決定、実績線
(RL)および進捗線(GL)の編集を実行し、得られ
た進捗管理図を端末装置(2)に出力表示する。
From the above, the progress check date (CT1)
Each function (FA) To (FH) Is the progress
It will be clearly indicated on the control chart. Similarly in the following
As the development work progresses, the progress check date (CTTwo= August 3
Days) and (CTThree= August 17th)
Each function (FA) To (FH) Each development
Process (RS) progress status is inspected, progress check date
(CT) and each function (F) and each development process (R
Number of digestive work for each S) (N R) Is the corresponding development
When input from the terminal device (2) together with the process (RS),
The common server (1) processes the input information by the same process as described above.
After storing the report in each process control table (41), the progress rate
(GR) calculation, progress point (GP) position determination, performance line
(RL) and progress line (GL) are edited,
The progress control chart is output and displayed on the terminal device (2).

【0055】図5に示される進捗管理図(その二)は、
第三回の進捗チェック日(CT3 =8月17日)におけ
る検査結果の各消化仕事数(NR )を入力した後に、各
端末装置(2)に出力表示される進捗管理図が示されて
いる。
The progress management chart (2) shown in FIG.
After inputting each digestive work number (N R ) of the inspection result on the third progress check date (CT 3 = August 17), the progress control chart output and displayed on each terminal device (2) is displayed. ing.

【0056】図5に示される進捗管理図(その二)に
は、進捗チェック日(CT3 =8月17日)における検
査結果により編集された実績線(RLA3)乃至(R
H3)および進捗線(GL3 )のみならず、過去二回の
進捗チェック日(CT1 =7月13日)および(CT2
=8月3日)における検査結果を示す進捗線(GL1
および(GL2 )も併せて表示される為、各進捗チェッ
ク日(CT1 )、(CT2 )および(CT3 )の間にお
ける各機能(F)の進捗状況も併せて認識可能となる。
In the progress management chart (2) shown in FIG. 5, the performance lines (RL A3 ) to (R A3 ) to (R) edited by the inspection results on the progress check date (CT 3 = August 17) are shown.
L H3 ) and progress line (GL 3 ), as well as the past two progress check dates (CT 1 = July 13) and (CT 2
= Progress line (GL 1 ) showing the inspection result on August 3)
Since and and (GL 2 ) are also displayed, the progress status of each function (F) between each progress check date (CT 1 ), (CT 2 ) and (CT 3 ) can also be recognized.

【0057】即ち図5に示される進捗管理図(その二)
を観察すると、機能(FA )および(FB )に就いて
は、第一回の進捗チェック日(CT1 =7月13日)以
降、順調に進捗し、何れも詳細設計(DD)を完了済で
略予定に達しており、機能(F C )に就いても当初より
順調に進捗して機能設計(FD)を完了済で、詳細設計
(DD)も予定以上に進捗している。
That is, the progress management chart shown in FIG. 5 (No. 2)
Observe the function (FA) And (FB)
Is the first progress check date (CT1= 13th July)
Descending, progressing smoothly, both completed detailed design (DD)
The schedule has been reached, and the function (F C) From the beginning
Completed functional design (FD) with good progress and detailed design
(DD) is progressing more than expected.

【0058】一方機能(FD )に就いては、機能設計
(FD)が第二回の進捗チェック日(CT2 =8月3
日)以降進捗が停止し、予定より大幅に遅延しており、
至急対策を講ずる必要があることを示している。
[0058] On the other hand function in regard to (F D), functional design (FD) is the second times of progress check date (CT 2 = 8 May 3
The progress has stopped since then, and it has been significantly delayed from the schedule,
It indicates that urgent measures need to be taken.

【0059】また機能(FE )に就いては、第二回の進
捗チェック日(CT2 =8月3日)に続いて遅延が見受
けられるが、第二回の進捗チェック日(CT2 =8月3
日)から今回の進捗チェック日(CT3 =8月17日)
迄に挽回しつつあることが示されている。
Regarding the function ( FE ), there is a delay following the second progress check date (CT 2 = August 3), but the second progress check date (CT 2 = August 3
From today) to this progress check date (CT 3 = August 17)
It is shown that it is recovering by now.

【0060】また機能(FF )に就いては、第二回の進
捗チェック日(CT2 =8月3日)以降も順調に進捗
し、機能設計(FD)も完了し、予定通りの進捗を示し
ている。
Regarding the function (F F ), the progress progresses smoothly after the second progress check date (CT 2 = August 3), the function design (FD) is completed, and the progress is as planned. Is shown.

【0061】また機能(FG )に就いては、第二回の進
捗チェック日(CT2 =8月3日)以前の進捗停滞によ
り、今回の進捗チェック日(CT3 =8月17日)にお
いても大幅の遅延が見受けられるが、第二回の進捗チェ
ック日(CT2 =8月3日)以降、進捗に挽回の傾向が
見受けられることが示されている。
Regarding the function (F G ), the progress check date (CT 3 = August 17) of this time is due to the progress delay before the second progress check date (CT 2 = August 3). However, there is a significant delay, but it is shown that there is a tendency for recovery to progress after the second progress check date (CT 2 = August 3).

【0062】更に機能(FH )に就いては、一応順調に
進捗しているが、第一回の進捗チェック日(CT1 =7
月13日)に見受けられた若干の遅延が、今回の進捗チ
ェック日(CT3 =8月17日)に於いても見受けられ
ることが示されている。
Regarding the function (F H ), the progress is steadily progressing, but the first progress check date (CT 1 = 7)
It has been shown that a slight delay that was seen on the 13th of each month) can be seen on this progress check day (CT 3 = August 17th).

【0063】以上の説明から明らかな如く、本発明の実
施形態によれば、進捗管理図上に、各機能(F)の予定
線(PL)に重畳して各進捗チェック日(CT)におけ
る検査結果に基づき実績線(RL)および進捗線(G
L)が表示される為、各種情報が簡易に表示されると共
に、各機能(F)の中で特に予定より遅延している機能
(F)が明示されると共に、過去の進捗チェック日(C
T)における検査結果を示す進捗線(GL)も併せ表示
される為、各進捗チェック日(CT)の間での進捗状況
も、視覚的に認識可能となり、進捗管理上の問題も容易
に認識可能となる。
As is apparent from the above description, according to the embodiment of the present invention, the inspection on each progress check date (CT) is superimposed on the schedule line (PL) of each function (F) on the progress management chart. Results line (RL) and progress line (G
Since L) is displayed, various information is displayed in a simple manner, and the function (F) that is particularly delayed from the plan among the respective functions (F) is clearly indicated, and the past progress check date (C
Since the progress line (GL) showing the inspection result in (T) is also displayed, the progress status between each progress check date (CT) can be visually recognized, and problems in progress management can be easily recognized. It will be possible.

【0064】なお、図2乃至図5はあく迄本発明の一実
施形態に過ぎず、例えば各工程管理テーブル(41)は
各進捗チェック日(CT)に対応して消化仕事数
(NR )のみを保存するものに限定されることは無く、
進捗率算出部(34)により算出された進捗点(GP)
も併せ保存させることにより、過去の進捗線(GL)を
容易に表示可能とする等、他に幾多の変形が考慮される
が、何れの場合にも本発明の効果は変わらない。また進
捗管理図の表現形式は図示されるものに限定されること
は無く、例えば予定線(PL)と実績線(RL)との合
成を、図示されるものの代わりに、予定線(PL)を細
い実線で示し、実績線(RL)を太い実線を重畳させる
等、他に幾多の変形が考慮されるが、何れの場合にも本
発明の効果は変わらない。また本発明の対象とする進捗
管理システム(100)は、図示される共通サーバ
(1)および複数の端末装置(2)から構成されるもの
に限定されることは無く、例えば共通サーバ(1)から
各端末装置(2)へ各工程管理テーブル(41)に格納
済の諸情報を転送し、各端末装置(2)で進捗管理図を
編集・表示する等、他に幾多の変形が考慮されるが、何
れの場合にも本発明の効果は変わらない。また本発明の
対象とする作業は、図示される機能(FA )乃至
(FH)を具備する情報処理システムのプログラムの開
発作業に限定されることは無く、他に幾多の変形が考慮
されるが、何れの場合にも本発明の効果は変わらない。
[0064] Note that only one embodiment of the present invention up to 2 to 5 understand, for example, the process management table (41) is digested job number corresponding to each progress check date (CT) (N R) It is not limited to storing only,
Progress point (GP) calculated by the progress rate calculation unit (34)
Also, by saving them together, a number of other modifications can be taken into consideration, such as making it possible to easily display past progress lines (GL), but the effect of the present invention does not change in any case. In addition, the representation format of the progress management chart is not limited to that shown in the figure, and for example, the combination of the planned line (PL) and the actual line (RL) may be replaced by the planned line (PL) instead of the illustrated one. A number of other modifications are considered, such as a thin solid line and a track line (RL) superimposed with a thick solid line, but the effect of the present invention does not change in any case. The progress management system (100) to which the present invention is applied is not limited to the common server (1) and the plurality of terminal devices (2) shown in the figure. For example, the common server (1). From the terminal to each terminal device (2), various information stored in each process control table (41) is transferred, and each terminal device (2) edits / displays the progress control chart. However, the effect of the present invention does not change in any case. Further, the work targeted by the present invention is not limited to the development work of the program of the information processing system having the illustrated functions (F A ) to (F H ), and many other modifications are considered. However, the effect of the present invention does not change in any case.

【0065】[0065]

【発明の効果】以上、本発明によれば、本進捗管理シス
テムが出力表示する進捗管理図によれば、各作業項目毎
の各進捗チェック日における進捗率が記録保存される
為、過去の各進捗チェック日間での進捗状況も視覚的に
把握可能となり、また各作業項目の各進捗チェック日に
対応する進捗点が進捗線により連結され、記録保存され
る為、作業項目相互間の遅延状況が視覚的に把握可能と
なり、更に実績線が予定線に重畳されて表示される為、
各作業項目毎に予定に対する実績の進捗状況がより直接
的に把握可能となると共に、表示も簡素化され、当該進
捗管理図の効用が大幅に向上する。
As described above, according to the present invention, according to the progress management chart output and displayed by the present progress management system, since the progress rate on each progress check date for each work item is recorded and saved, each past progress rate can be saved. The progress status during the progress check day can also be visually grasped, and the progress points corresponding to each progress check day of each work item are linked by a progress line and recorded and saved, so there is no delay between work items. Since it is possible to visually grasp, and the actual line is displayed superimposed on the planned line,
For each work item, it is possible to more directly grasp the progress status of the actual result with respect to the schedule, the display is simplified, and the utility of the progress management chart is significantly improved.

【図面の簡単な説明】[Brief description of the drawings]

【図1】 本発明の原理図FIG. 1 is a principle diagram of the present invention.

【図2】 本発明の実施形態による進捗管理システムFIG. 2 is a progress management system according to an embodiment of the present invention.

【図3】 図2における進捗管理図編集処理FIG. 3 is a progress management diagram editing process in FIG.

【図4】 本発明の実施形態による進捗管理図(その
一)
FIG. 4 is a progress management chart (part 1) according to the embodiment of the present invention.

【図5】 本発明の実施形態による進捗管理図(その
二)
FIG. 5 is a progress management chart (part 2) according to the embodiment of the present invention.

【図6】 従来ある進捗管理図[Figure 6] Conventional progress management chart

【符号の説明】[Explanation of symbols]

1 共通サーバ 2 端末装置 3 処理部 4 記憶部 21 キーボード 22 ディスプレイ 31 入出力制御部 32 格納部 33 抽出部 34 進捗率算出部 35 進捗管理図表示部 41 工程管理テーブル 100 進捗管理システム 101 入力情報記憶手段 102 進捗率算出手段 103 予定線編集手段 104 実績線編集手段 105 進捗線編集手段 106 進捗管理図表示手段 351 予定線編集部 352 実績線編集部 353 進捗線編集部 1 common server 2 terminal device 3 processing unit 4 storage unit 21 keyboard 22 display 31 input / output control unit 32 storage unit 33 extraction unit 34 progress rate calculation unit 35 progress management diagram display unit 41 process management table 100 progress management system 101 input information storage Means 102 Progress rate calculating means 103 Schedule line editing means 104 Actual line editing means 105 Progress line editing means 106 Progress control chart display means 351 Schedule line editing section 352 Actual line editing section 353 Progress line editing section

Claims (5)

【特許請求の範囲】[Claims] 【請求項1】 並行して実行される複数の作業項目を構
成する各作業工程の開始予定日と終了予定日と、各作業
工程の予定仕事数と、各作業項目の各作業工程の進捗状
況を検査する進捗チェック日と、各進捗チェック日に検
査した実際の消化仕事数とを入力された場合に、入力さ
れた各情報を記憶する入力情報記憶手段と、 前記各作業項目の各作業工程毎の消化仕事数が前記入力
情報記憶手段に記憶される度に、該消化仕事数と対応す
る予定仕事数とを前記入力情報記憶手段から抽出し、前
記予定仕事数に対する前記消化仕事数の比率により進捗
率を算出する進捗率算出手段と、 前記各作業項目毎の各作業工程の開始予定日および終了
予定日を前記入力情報記憶手段から抽出し、前記各工程
開始予定日および工程終了予定日を、暦日の基準となる
カレンダ線に対応させて直線上に配列し、最初の作業工
程の開始予定日と、最後の作業工程の終了予定日とを所
定の表示形式の直線で結ぶ予定線を、各作業項目毎に編
集する予定線編集手段と、 前記予定線編集手段が編集した前記各作業項目毎の予定
線上の、各作業工程毎の工程開始予定日と工程終了予定
日との間の区間を当該作業工程の全予定仕事数に対応さ
せ、前記進捗率算出手段が算出した進捗率を示す進捗点
を、該作業工程の開始予定日を起点として記入し、前記
予定線上の、最初の作業工程の開始予定日から最新の進
捗点迄の区間を、前記予定線に重畳して前記予定線と異
なる表示形式の直線で結ぶ実績線を、各作業項目毎に編
集する実績線編集手段と、 前記カレンダ線上に各進捗チェック日を記入し、前記各
作業項目毎に編集された前記実績線を重畳した予定線
を、前記カレンダ線を暦日の基準として並行に配置した
後、前記カレンダ線上の各進捗チェック日と、前記各実
績線を重畳した予定線上に記入された各進捗チェック日
に対応する進捗点とを順次連結する進捗線を編集する進
捗線編集手段と、 前記カレンダ線、各実績線を重畳した予定線、並びに進
捗線を含む進捗管理図を出力表示する進捗管理図表示手
段とを設けることを特徴とする進捗管理システム。
1. A scheduled start date and a scheduled finish date of each work process constituting a plurality of work items to be executed in parallel, a planned number of jobs of each work process, and a progress status of each work process of each work item. An input information storage unit that stores each piece of input information when a progress check date for inspecting and an actual number of digested work inspected on each progress check day are input, and each work step of each work item Each time the number of digested jobs for each is stored in the input information storage means, the number of digested jobs and the corresponding scheduled number of jobs are extracted from the input information storage means, and the ratio of the number of digested jobs to the scheduled number of jobs is extracted. A progress rate calculating means for calculating a progress rate by means of: and a scheduled start date and a scheduled finish date of each work process for each work item are extracted from the input information storage means, and a scheduled start date and a scheduled finish date of each process Is the standard for calendar days For each work item, a schedule line that connects the planned start date of the first work process and the planned finish date of the last work process with a straight line in a predetermined display format is arranged for each work item. The schedule line editing means to be edited, and the section between the scheduled process start date and the scheduled process end date for each work process on the schedule line for each work item edited by the schedule line editing means are defined as A progress point indicating the progress rate calculated by the progress rate calculating means in correspondence with the total number of scheduled jobs is entered starting from the scheduled start date of the work process, and the scheduled start date of the first work process on the schedule line. To the latest progress point, the result line editing means for editing, for each work item, a result line that is connected to the planned line by a straight line having a display format different from that of the planned line, and each line on the calendar line. Enter the progress check date and edit for each of the above work items. After arranging the planned line on which the collected actual line is collected in parallel with the calendar line as a calendar day reference, each progress check date on the calendar line and the planned line on which the actual line is superimposed are written. A progress line editing means for editing a progress line that sequentially connects progress points corresponding to each progress check date, and a progress control chart including the calendar line, a planned line on which each performance line is superimposed, and a progress line are output and displayed. And a progress management system for displaying progress management charts.
【請求項2】 前記進捗率算出手段は、各消化仕事数に
対応して算出した各進捗率を、前記各消化仕事数に対応
して前記入力情報記憶手段に記憶させることを特徴とす
る請求項1記載の進捗管理システム。
2. The progress rate calculation means stores each progress rate calculated corresponding to each number of exhausted work in the input information storage means corresponding to each number of exhausted work. The progress management system according to item 1.
【請求項3】 前記進捗線編集手段は、前記各進捗チェ
ック日に対応する進捗線を履歴として保存して置き、前
記進捗管理図表示手段が表示する進捗管理図上に並行し
て表示とすることを特徴とする請求項1記載の進捗管理
システム。
3. The progress line editing means saves and stores a progress line corresponding to each progress check date as a history, and displays the progress lines in parallel on the progress management chart displayed by the progress management chart display means. The progress management system according to claim 1, wherein:
【請求項4】 前記予定線編集手段は、予定線を並行し
た二本の並行線で表現し、前記実績線編集手段は、前記
予定線上の実績線に相当する範囲の並行線間を黒く塗潰
すことで、前記実績線を前記予定線に重畳して表現する
ことを特徴とする請求項1記載の進捗管理システム。
4. The planned line editing means expresses the planned line by two parallel lines which are parallel to each other, and the actual line editing means paints a black color between the parallel lines in a range corresponding to the actual line on the planned line. The progress management system according to claim 1, wherein the achievement line is superimposed and expressed on the planned line by crushing.
【請求項5】 前記進捗管理図表示手段は、遠隔に設置
された複数の端末装置のディスプレイ上に表示すること
を特徴とする請求項1記載の進捗管理システム。
5. The progress management system according to claim 1, wherein the progress management chart display means displays on a display of a plurality of remotely installed terminal devices.
JP34051495A 1995-12-27 1995-12-27 Progress supervising system Pending JPH09174392A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP34051495A JPH09174392A (en) 1995-12-27 1995-12-27 Progress supervising system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP34051495A JPH09174392A (en) 1995-12-27 1995-12-27 Progress supervising system

Publications (1)

Publication Number Publication Date
JPH09174392A true JPH09174392A (en) 1997-07-08

Family

ID=18337712

Family Applications (1)

Application Number Title Priority Date Filing Date
JP34051495A Pending JPH09174392A (en) 1995-12-27 1995-12-27 Progress supervising system

Country Status (1)

Country Link
JP (1) JPH09174392A (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2005165789A (en) * 2003-12-03 2005-06-23 Pioneer Electronic Corp Progress management support device, progress management support method, progress management support program, and recording medium
US6918089B2 (en) 2000-07-11 2005-07-12 Honda Giken Kogyo Kabushiki Kaisha Schedule management system
WO2007142282A1 (en) * 2006-06-09 2007-12-13 Rakuten, Inc. Service registration processing system, card image providing device, card image providing method, and card image providing program
EP3779625A4 (en) * 2018-03-27 2022-04-06 Kabushiki Kaisha Toshiba Visualization system

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US6918089B2 (en) 2000-07-11 2005-07-12 Honda Giken Kogyo Kabushiki Kaisha Schedule management system
JP2005165789A (en) * 2003-12-03 2005-06-23 Pioneer Electronic Corp Progress management support device, progress management support method, progress management support program, and recording medium
WO2007142282A1 (en) * 2006-06-09 2007-12-13 Rakuten, Inc. Service registration processing system, card image providing device, card image providing method, and card image providing program
EP3779625A4 (en) * 2018-03-27 2022-04-06 Kabushiki Kaisha Toshiba Visualization system
US11442435B2 (en) 2018-03-27 2022-09-13 Kabushiki Kaisha Toshiba Visualization system

Similar Documents

Publication Publication Date Title
US20030233387A1 (en) Work-process status monitoring system, recording medium therefor, and work-process status monitoring and display apparatus
JP2008299762A (en) Production management program
US20080126165A1 (en) Dynamic overlay metrics
JPH09174392A (en) Progress supervising system
Kannan et al. Developing a maintenance value stream map
JPS62224562A (en) Display device for process control data
JPS59214964A (en) Conversational scheduling system
Browne et al. The design and validation of a digital simulation model for job shop control decision making
JP2006202082A (en) Production line management system, production line management program, recording medium, and method for managing production line
JP4177234B2 (en) Production planning device and production planning method
JP2013250713A (en) Schedule management device and its management method and management program and schedule management system having the same
CN115168337A (en) Manufacturing information processing method and system based on parameterized process data structure
JP4133680B2 (en) Holiday acquisition status management device
JP6993772B2 (en) Production plan creation system, production plan creation method, program and information processing equipment
JPS61136161A (en) Working process planning systsem for individual production
JPH0373257A (en) Production scheduling device
JPH03161250A (en) Production scheduling device
JP5268400B2 (en) Process management system
JPH0926998A (en) Method for obtaining quality related information on metal band in manufacturing plant and device therefor
JP2007041794A (en) Production circumstance display device
JP7353420B1 (en) Scheduling device, scheduling method, and scheduling program
JP2005092382A (en) Redesign support system, redesign method, redesign support program, and recording medium with the same recorded
JPH06332909A (en) Plan managing system
JP2003141239A (en) Work state management system
JPH0721264A (en) Scheduling method

Legal Events

Date Code Title Description
A02 Decision of refusal

Free format text: JAPANESE INTERMEDIATE CODE: A02

Effective date: 20020827