JPS61106817A - Method of replacing ground with crushed stones - Google Patents
Method of replacing ground with crushed stonesInfo
- Publication number
- JPS61106817A JPS61106817A JP22927484A JP22927484A JPS61106817A JP S61106817 A JPS61106817 A JP S61106817A JP 22927484 A JP22927484 A JP 22927484A JP 22927484 A JP22927484 A JP 22927484A JP S61106817 A JPS61106817 A JP S61106817A
- Authority
- JP
- Japan
- Prior art keywords
- soft soil
- crushed stones
- water
- crushed
- replaced
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D3/00—Improving or preserving soil or rock, e.g. preserving permafrost soil
- E02D3/02—Improving by compacting
- E02D3/08—Improving by compacting by inserting stones or lost bodies, e.g. compaction piles
Abstract
Description
【発明の詳細な説明】
産業上の利用分野
本発明は、軟弱地盤を砕石によ多置換し、安定した地盤
を形成するものである。DETAILED DESCRIPTION OF THE INVENTION Field of Industrial Application The present invention replaces soft ground with crushed stones to form stable ground.
発明が解決しようとする問題点
護岸や構造物基礎は正常時には安定し、その機能を果し
ているが、地震時には震動によって、軟弱土は変形また
は液状化して倒壊し、護岸や基礎工機能を失うことがあ
る。Problems that the invention aims to solve During normal times, seawalls and structure foundations are stable and perform their functions, but during earthquakes, the soft soil deforms or liquefies due to vibrations and collapses, causing loss of bankwall and foundation functions. There is.
上記地盤に対しては、構造物自身の改築または地盤の改
良が必要である。For the above-mentioned ground, it is necessary to reconstruct the structure itself or improve the ground.
従来地盤改良工法として、軟弱土を除去し良質土と置換
する方法、軟弱土に安定剤を注入する土の強化方法とが
ある。Conventional ground improvement methods include removing soft soil and replacing it with good quality soil, and strengthening soil by injecting stabilizers into the soft soil.
本発明は置換工法であるが、その特徴は次次のとお)で
ある。The present invention is a replacement method, and its features are as follows.
(1)軟弱土の除去は、一般的掘削によらないで、水流
によって土粒子を釜揚内に導き、釜揚に設けた水中サン
ドポンプによって除去する。(1) To remove soft soil, instead of using general excavation, soil particles are guided into the kamaage by water flow and removed by a submersible sand pump installed in the kamaage.
(2)事前に軟弱土に盛られた砕石等は除去された軟弱
土に相当する量だけ1.沈降する。(2) Crushed stones, etc. that were piled up on the soft soil in advance will be removed in an amount equivalent to the soft soil removed. Sediment.
(3) (1)及び(2)の連続操作によって不安定
な軟弱土は安定した砕石等によって置換される。(3) By the continuous operation of (1) and (2), unstable soft soil is replaced with stable crushed stone, etc.
本発明の利点は
(1)置換作業中に既設構造物の安定を害するようなこ
とはない。Advantages of the present invention are (1) the stability of the existing structure is not compromised during the replacement work;
(2)置換作業中の騒音振動が極めて小さい。(2) Noise and vibration during replacement work are extremely small.
(3)薬液を全く使用しないので無公害である。(3) No pollution as no chemicals are used.
問題点を解決するだめの手段および実施例本発明は、地
盤改良範囲を鋼矢板等で囲繞し、囲い矢板中に揚排水ス
リット釜揚を設け、釜揚と矢板間に砕石を盛り上げる。Means and Embodiments for Solving Problems The present invention surrounds the ground improvement area with steel sheet piles, etc., provides a pumping and drainage slit kettle in the surrounding sheet pile, and piles up crushed stone between the kettle and the sheet pile.
然る後、砕石上に注水し、その注入水を釜揚内のサンド
ポンプによつて汲み上げる。注入水は砕石と軟弱土との
境界面を魂度をもって釜揚内に流入する。流入水は土粒
子を釜揚内に運び、流入土粒子は砕石によって置換され
る。After that, water is injected onto the crushed stone, and the injected water is pumped up by a sand pump inside the pot. The injected water flows through the interface between crushed stone and soft soil into the pot. The inflowing water carries soil particles into the kettle, and the inflowing soil particles are replaced by crushed stone.
以下実施例を図面を用い説明する。Examples will be described below with reference to the drawings.
第1図、第2図において、1は海2に面した既設護岸で
ある。護岸1の前面の海底は地震時に液状化する緩い砂
層であシこれを砕石で置換して、護岸1を補強しようと
するものである。先ず地盤置換すべき区域を鋼矢板4を
建込んで仮囲いを設け、囲い中央部に排水スリット釜揚
5を建込む。In Figures 1 and 2, 1 is the existing seawall facing the sea 2. The seabed in front of the seawall 1 is a loose sand layer that liquefies during an earthquake, and this is replaced with crushed stone to strengthen the seawall 1. First, a temporary enclosure is provided by erecting steel sheet piles 4 in the area where the ground is to be replaced, and a drainage slit kettle 5 is built in the center of the enclosure.
この場合、鋼矢板4および釜揚5は置換される地盤深さ
あるいはそれ以上の深さに建込む必要がある。排水スリ
ット釜揚5は円筒形をなし、下端部寄シには水と土粒子
は透過するが、砕石は透過しない寸法のスリット6を穿
設しておき、下端部に+6.、 、 ij # *
”j−y )” g y 7’ 7 t Rt L”C
k < o Hr 1゛鋼矢板4の仮囲の内部に砕石8
を盛シ上げ、仮囲の外側に設置した注水ポンプ9を動か
して海水を砕石8上に注入する。海水は砕石8層を透過
し軟弱±3の表面に達し、軟弱土3を同伴して泥水とな
ってスリット6を通って釜揚5に流れ込む。この泥水を
排水サンドポンプ7で汲上げ送泥パイプ10を経由して
除去する。軟弱土3が除去された空間には、表面に盛上
げた砕石8が沈下し、第3図のごとく軟弱±3が砕石8
によって置換される。In this case, the steel sheet piles 4 and the pot lifts 5 need to be built at the depth of the ground where they will be replaced or deeper. The drainage slit kettle 5 has a cylindrical shape, and has a slit 6 at its lower end that allows water and soil particles to pass through, but does not allow crushed stone to pass through. , , ij #*
"j-y)" g y 7' 7 t Rt L"C
k < o Hr 1゛Crushed stone 8 inside the temporary enclosure of steel sheet pile 4
is raised and a water injection pump 9 installed outside the temporary enclosure is operated to inject seawater onto the crushed stones 8. The seawater passes through the 8 layers of crushed stones and reaches the surface of the soft soil 3, which turns into muddy water accompanied by the soft soil 3 and flows into the pot 5 through the slit 6. This muddy water is pumped up by a drainage sand pump 7 and removed via a mud feeding pipe 10. In the space where the soft soil 3 was removed, the crushed stone 8 piled up on the surface sinks, and as shown in Figure 3, the soft soil ±3 is crushed stone 8.
replaced by
置換が終了しだら鋼矢板4および釜揚5を撤去する。な
お、置換後の砕石日の高さは鋼矢板の高さまで積上げる
ことができる。Once the replacement is complete, the steel sheet piles 4 and the kettle 5 are removed. The crushed stone after replacement can be piled up to the height of the steel sheet pile.
作用・効果
この発明は以上の構成からなる。この工法は軟弱土を水
流に同伴して除去し、除去したあと1では地盤表面に載
置した砕石が沈下して置換される。Function/Effect This invention consists of the above configuration. In this construction method, soft soil is removed along with the flow of water, and after removal, crushed stone placed on the ground surface sinks and is replaced.
従って従来の軟弱土を掘削除去す−る方法と異なり周囲
の既設構造物、例えば実施例の既設護岸のように置換す
る軟弱土に近接したものでも、その安定性を損なう恐れ
は全くない。またこの工法は騒 □・音・振動を発
生せず、薬液による環境汚染も起ら、ない。Therefore, unlike the conventional method of excavating and removing soft soil, there is no risk of impairing the stability of surrounding existing structures, even if they are close to the soft soil to be replaced, such as the existing revetment in the embodiment. In addition, this construction method does not generate noise, noise, or vibration, and there is no environmental pollution caused by chemical solutions.
なおこの工法は前記実施例のほか、陸上の軟弱土の置換
にも適用できることは勿論である。It goes without saying that this construction method can also be applied to the replacement of soft soil on land in addition to the above embodiments.
図面はこの工法の実施例を示すものであって、第1図、
第2図は置換前の平面図および縦断面図第3図は置換後
の縦断面図である。
1・・既設護岸、2・・海、3・・軟弱土、4・・鋼矢
板、5・・排水スリット釜揚、6・・スリット、7・・
排水サンドポンプ、8・・砕石、9・・注水ポンプ、1
0・・送泥パイプ。
第1場
第2図
nThe drawings show an example of this construction method, and are shown in Figure 1.
FIG. 2 is a plan view and longitudinal sectional view before replacement, and FIG. 3 is a longitudinal sectional view after replacement. 1. Existing seawall, 2. Sea, 3. Soft soil, 4. Steel sheet pile, 5. Drainage slit kettle, 6. Slit, 7.
Drainage sand pump, 8... crushed stone, 9... water injection pump, 1
0...Sludge pipe. Scene 1 Figure 2 n
Claims (1)
含む)を盛り、水流を利用して軟弱土と砕石を置換し安
定な地盤を形成する地盤砕石置換工法。(1) A crushed stone replacement method in which crushed stone (including gravel or slag) is piled up on the surface of unstable soft soil, and water flow is used to replace the soft soil and crushed stone to form a stable ground.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP22927484A JPS61106817A (en) | 1984-10-31 | 1984-10-31 | Method of replacing ground with crushed stones |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP22927484A JPS61106817A (en) | 1984-10-31 | 1984-10-31 | Method of replacing ground with crushed stones |
Publications (1)
Publication Number | Publication Date |
---|---|
JPS61106817A true JPS61106817A (en) | 1986-05-24 |
Family
ID=16889540
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP22927484A Pending JPS61106817A (en) | 1984-10-31 | 1984-10-31 | Method of replacing ground with crushed stones |
Country Status (1)
Country | Link |
---|---|
JP (1) | JPS61106817A (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103437337A (en) * | 2013-08-21 | 2013-12-11 | 国家电网公司 | Method for reinforcing soft soil foundation in cushion layer replacement mode |
Citations (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPS5130382A (en) * | 1974-09-09 | 1976-03-15 | Nippon Telegraph & Telephone | KINZOKUSHIISUOMOT SUPURASUCHITSUKUHIFUKUTSUSHINKEEBURU NO SETSUZOKUHOHO |
JPS58138816A (en) * | 1982-02-10 | 1983-08-17 | Hasegawa Komuten Co Ltd | Inprovement work for soft ground |
-
1984
- 1984-10-31 JP JP22927484A patent/JPS61106817A/en active Pending
Patent Citations (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPS5130382A (en) * | 1974-09-09 | 1976-03-15 | Nippon Telegraph & Telephone | KINZOKUSHIISUOMOT SUPURASUCHITSUKUHIFUKUTSUSHINKEEBURU NO SETSUZOKUHOHO |
JPS58138816A (en) * | 1982-02-10 | 1983-08-17 | Hasegawa Komuten Co Ltd | Inprovement work for soft ground |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103437337A (en) * | 2013-08-21 | 2013-12-11 | 国家电网公司 | Method for reinforcing soft soil foundation in cushion layer replacement mode |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
KR20210029069A (en) | Underwater concrete block structure and construruction method therefor | |
JP3518379B2 (en) | Construction method for underwater structures | |
JP2008019561A (en) | Construction method of countermeasure against liquefaction under breakwater caused by creation of underground wall | |
JPS61106817A (en) | Method of replacing ground with crushed stones | |
JP2002121754A (en) | Method for constructing underwater foundation | |
JPH0649840A (en) | Construction method of steel pipe foundation pile for preventing liquefaction | |
KR100621410B1 (en) | Dry Construction Method of Underwater Structure Using Watertight Caisson | |
JP2000130065A (en) | Construction method for vertical shaft | |
JPH07268878A (en) | Method for immersing caisson and structure of cutting face of caisson | |
JP3357319B2 (en) | Piping destruction prevention reinforcement method of existing embankment and piping destruction prevention reinforcement structure of existing embankment | |
JP2531328B2 (en) | How to build a bank | |
JP2784314B2 (en) | How to set up an open caisson | |
JP3387398B2 (en) | How to penetrate caisson foundation | |
JP2000130066A (en) | Construction method for vertical shaft | |
JPH059945A (en) | Underground skeleton constructing method | |
JP2556380B2 (en) | Construction method of revetment structure | |
JPS61155514A (en) | Placement work of mass concrete | |
JPH10121448A (en) | Pollution preventing caison for dredging and dredging method | |
Wen-wei | Experiments, methods of applying grouted jetted precast concrete sheet piles | |
JPS60175611A (en) | Reclaiming method | |
SU1514860A1 (en) | Method of erecting earth dam on alluvia-covered rock bed | |
JPH10114957A (en) | Method of sand boiling-preventive construction in excavation work of shaft, etc. | |
JPS62233326A (en) | Column line-type water-permeable wall construction work | |
JPH0612012B2 (en) | Tsukishima construction method | |
JPS61155513A (en) | Placement work of mass-concrete |