JPS608393B2 - Piping construction method - Google Patents

Piping construction method

Info

Publication number
JPS608393B2
JPS608393B2 JP13158678A JP13158678A JPS608393B2 JP S608393 B2 JPS608393 B2 JP S608393B2 JP 13158678 A JP13158678 A JP 13158678A JP 13158678 A JP13158678 A JP 13158678A JP S608393 B2 JPS608393 B2 JP S608393B2
Authority
JP
Japan
Prior art keywords
piping
equipment
pump
construction
model
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired
Application number
JP13158678A
Other languages
Japanese (ja)
Other versions
JPS5560779A (en
Inventor
孝 内山
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Toshiba Corp
Original Assignee
Tokyo Shibaura Electric Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Tokyo Shibaura Electric Co Ltd filed Critical Tokyo Shibaura Electric Co Ltd
Priority to JP13158678A priority Critical patent/JPS608393B2/en
Publication of JPS5560779A publication Critical patent/JPS5560779A/en
Publication of JPS608393B2 publication Critical patent/JPS608393B2/en
Expired legal-status Critical Current

Links

Description

【発明の詳細な説明】 本発明は、例えば原子力プラントの建設における配管の
施工方法に関する。
DETAILED DESCRIPTION OF THE INVENTION The present invention relates to a method of constructing piping in the construction of, for example, a nuclear power plant.

まず従来の原子力プラント建設における配管の施工方法
について述べる。
First, we will discuss the piping construction method used in conventional nuclear plant construction.

原子力プラント建設における機器、配管の裾付、施工は
機器を配管施工の為の起点として、工事を行う為に当該
機器は、裾付場所が確保されるとすぐに搬入し、裾付が
おこなわれる。例えば、原子力プラントの最地下階に据
付をされる非常用ポンプは、第1図に示す如く全長約1
1肌に達する大型の堅型ポンプであるが、裾付場所と基
礎1が完成したならば、基礎上面のはつりレベル出しを
行なって、ソールプレート2を設定する。
In the construction of equipment and piping in nuclear plant construction, the equipment is used as the starting point for piping construction, and as soon as the hemming area is secured, the equipment is brought in and the hemming is carried out. . For example, an emergency pump installed on the lowest basement floor of a nuclear power plant has a total length of about 1 cm, as shown in Figure 1.
Although it is a large, rigid pump that reaches 1 skin, once the hemming area and the base 1 are completed, the top surface of the base is leveled and the sole plate 2 is set.

工場試験を完了したポンプ3を現地へ分解輸送する。現
地では先ず、ィンベラ及びケーシング4を裾付、続いて
配管との接続部となる吸込み/ズル及び吐出しノズルが
取り付けたポンプ本体5を据付て、芯出しを高精度にお
こなう。次に該ポンプ本体の吸込みノズル、吐出しノズ
ルを基点に配管bの裾付をおこなう。一般にポンプ3と
配管bは、分解搬出が出来るようにボルト締めになって
おり、このボルトを締める事によりポンプ3と配管bは
据付を完了する。続いて取付けた配管に順次配管7を継
ぎ足して溶接をする。配管の溶接が完了したならば配管
の水圧試験と、配管洗浄をおこなうための準備をおこな
う。ポンプ内に洗浄水を入れても堅型ポンプのため水の
循環が出来ない事、ポンプが水圧試験圧力にもたない事
からポンプをバイパスする必要があるため、配管bは、
ポンプのノズルとの取合部分を両端フランジにしてある
ので、これを外しポンプ本体を独立させる。配管側は、
第2図に示したような仮設配管8を製作し、配管7に接
続し、両者をボルト締めする。このようにして水圧試験
と配管洗浄を実施し、完了したならば配管8を取外し、
配管bを復旧しポンプ3とを固定する。この後ポンプ3
にモーター9を搭載し、ポンプのィンベラとを接続し固
定する。モータのターミナル台に電線管を配置し、ケー
ブルを通線した上で電源盤、制御盤との電気テストをお
こない、ポンプ運転へと作業が進められる。従来の配管
の施工方法は上述のようであったがこのような方法では
次のような重大な欠点があった。
Pump 3, which has completed factory testing, will be disassembled and transported to the site. At the site, first, the invera and casing 4 are hemmed, and then the pump body 5 with the suction/zzle and discharge nozzle that will be connected to the piping is installed, and centering is performed with high precision. Next, the piping b is hemmed using the suction nozzle and discharge nozzle of the pump body as reference points. Generally, the pump 3 and piping b are bolted together so that they can be disassembled and transported, and by tightening these bolts, the installation of the pump 3 and piping b is completed. Next, pipes 7 are successively added to the installed pipes and welded. Once welding of the piping is completed, we will prepare the piping for a water pressure test and cleaning the piping. Even if cleaning water is poured into the pump, water cannot be circulated because it is a vertical pump, and the pump cannot hold up to the water pressure test pressure, so it is necessary to bypass the pump, so piping b is
The part that connects to the pump nozzle has flanges on both ends, so remove them and make the pump body independent. On the piping side,
Temporary piping 8 as shown in FIG. 2 is manufactured, connected to piping 7, and both are bolted together. In this way, perform the water pressure test and pipe cleaning, and once completed, remove the pipe 8,
Restore piping b and fix pump 3. After this pump 3
A motor 9 is mounted on the motor 9, and the pump's invera is connected and fixed. After placing the conduit on the motor terminal block and running the cable, electrical tests are conducted with the power supply panel and control panel, and work begins on pump operation. The conventional piping construction method is as described above, but this method has the following serious drawbacks.

まず、配管を開始するにあたり、当該機器を先行して建
屋への立入が可能になる最つとも早い時期に裾付る必要
があること。
First, when starting piping, it is necessary to install the equipment in advance at the earliest possible time when it is possible to enter the building.

この結果、機器を裾付けてから、試験運転に至るまで、
およそ2増欧ケ月もの間現地の環境条件の悪い状態の中
に裾付られたまま1こなっており、この間特に、定期的
運転等は実施出来ないため、品質管理上好ましい状態で
ない事。特に先の例で説明した堅型ポンプの場合、地下
室でなおかつ岩盤内に11凧も下にビットが設けられた
中に据付るため「湿気、水溜り等でポンプのケーシング
ィンベラ等に錆が発生したり変形したりする事もあり、
再び試験運転開始前に分解、点検を必要とする事。また
配管を施工するために直接必要となるのは第1図のポン
プ本体5のみであるが、当部品のみの工場出荷は現実に
困難な為、ポンプ全体として、早い時期から高度な品質
管理のもとに製作し、工場性能テストを実施して出荷さ
れる。現地においては配管施工に必要のないモー夕等の
部品は、工場又は、現地倉庫に、2項攻ケ月保管するこ
ととなり、性能維持、品質管理を徹底する為には多大の
費用と工がかかること。更に高額な機器を早い時期から
製作しなければならないため、材料費、製作費の発生と
投資がプラント建設工程上相当早い時期に生ずるため経
営上好ましい状態でない事。また、配管の水圧試験なら
びに洗浄においてはポンプ本体に通水出来ないため「ポ
ンプ本体を一時的に配管から隔離し「 このための仮設
の配管を必要とし「かつ工数が余分に発生すること。
As a result, from the installation of the equipment to the test run,
The plant has been stuck in poor local environmental conditions for about two months, and as regular operations cannot be carried out during this period, the situation is not favorable for quality control. In particular, in the case of the vertical pump explained in the previous example, since it is installed in a basement and in bedrock with a bit installed at the bottom, the pump's casing and other parts may rust due to humidity and water accumulation. may occur or deform,
Disassembly and inspection are required before test operation begins again. In addition, only the pump body 5 shown in Figure 1 is directly required to construct the piping, but since it is actually difficult to ship only this part from the factory, the pump as a whole must undergo advanced quality control from an early stage. The products are manufactured based on the original specifications and shipped after undergoing factory performance tests. Parts such as mowers that are not required for piping construction locally must be stored at the factory or on-site warehouse for several months, which requires a great deal of cost and labor to maintain performance and ensure quality control. thing. Furthermore, since expensive equipment must be manufactured from an early stage, material and manufacturing costs and investments occur quite early in the plant construction process, which is not a favorable situation for business management. Additionally, during water pressure tests and cleaning of piping, since water cannot flow through the pump body, it is necessary to temporarily isolate the pump body from the piping, requiring temporary piping for this purpose and requiring additional man-hours.

これらの数種の要因がプラント建設工期上、長期化の一
因になっている事があげられる。本発明はこのような欠
点を取り除き品質の向上、作業能率の向上、費用の大中
な低減、建設工期の大中な短縮を図る配管施工方法を得
ることを目的としたものである。
These several factors are contributing factors to the lengthening of the plant construction period. It is an object of the present invention to provide a piping construction method that eliminates these drawbacks, improves quality, improves work efficiency, significantly reduces costs, and significantly shortens construction period.

本発明の特徴は「配管施工にあたって基準となる当該機
器を直接に使用せず「当該機器を模擬した高精度の模型
を製作し、これを配管施工前に現地に梶付て配管施工「
水圧試験「配管洗浄をおこなった後、本模型を撤去しそ
の後に本来の機器を据付ることによってプラント建設を
おこなうものである。以下図面により÷本発明の一実施
例を説明する。
The feature of the present invention is that ``a high-precision model that simulates the equipment is manufactured without directly using the equipment that serves as a standard for piping construction, and this is carried to the site before piping construction.
Water Pressure Test: After cleaning the pipes, the model is removed and the original equipment is then installed to construct the plant. An embodiment of the present invention will be described below with reference to the drawings.

第3図a; bは、配管の基準となるポンプ等の高精度
に作られた模型を示す図である。この模型1川ま当該機
器そのものの模型ではなく「(外形をそのまままねたの
ではなく)配管嬢続部のフランジ等の位置、大きさ、及
び裾付ボルト等の設置位置が正確に製作されておれば良
い。
Figures 3a and 3b are diagrams showing highly precisely made models of pumps and the like that serve as piping standards. This model is not a model of the equipment itself; rather, it is manufactured with the exact position and size of flanges, etc. of piping connections, and the installation positions of hem bolts, etc. (instead of copying the external shape as is). It's fine if you have it.

すなわち、当該機器の配管接続部の構造・機能を有した
2つの接続部16を、水圧試験・洗浄に耐えうる配管1
7により、2つの接続面の面間距離を精度よく保ちなが
ら溶接し、これを鋼材よりなる台18で接続部のレベル
左右方向の寸法等を正確にして固定したものである。次
に本模型10を配管施工に先だち、当該機器の為に設定
された基礎11の上に精度よく据付を行ない、配管の施
工の基準点として配管12の施工を行なう。
In other words, the two connecting parts 16 that have the structure and function of the piping connecting parts of the device are connected to the piping 1 that can withstand water pressure tests and cleaning.
7, the two connecting surfaces are welded while maintaining the distance between the surfaces with high accuracy, and this is fixed on a table 18 made of steel with accurate horizontal and horizontal dimensions of the connecting portion. Next, prior to piping construction, this model 10 is accurately installed on the foundation 11 set for the equipment in question, and the piping 12 is constructed as a reference point for piping construction.

配管が完了し配管の水圧試験・洗浄は、本模型を利用し
そのまま模型10内に通水して行なう。そして、水圧試
験・洗浄完了後に適切な時期を選定して、本模型10を
取り外し、当該機器の裾付を行なう。この時、当初に述
べたように充分機器の配管接続部の精度をもった模型構
造であるので、機器裾付において、接続部取合において
問題がないのは明確である。以上の説明のように本発明
を実施することにより「前述の大型ポンプ据付例に見ら
れる機器の保管、この保管に関連して生じてくる、保管
場所の手配、保管期間中の品質管理・メンテナンス等の
緒問題が解決されるとともに、配管水圧試験・配管洗浄
時期における機器をバイパスさせる仮設配管を不要なも
のとする。
After the piping is completed, the water pressure test and cleaning of the piping is performed by directly passing water through the model 10 using this model. Then, after completing the water pressure test and cleaning, select an appropriate time to remove the model 10 and hem the device. At this time, as stated at the beginning, since the model structure has sufficient precision for the piping connections of the equipment, it is clear that there will be no problems in attaching the equipment and fitting the connections. As explained above, by implementing the present invention, "storage of the equipment seen in the above-mentioned large pump installation example, arrangement of storage space, quality control and maintenance during the storage period" that occur in connection with this storage. In addition to solving these problems, it also eliminates the need for temporary piping to bypass equipment during piping water pressure testing and piping cleaning.

また、機器搬入においても、最も適切な必要時間を総合
工程の中で選べると同時に「工場における機器の試験と
現場における機器の試験までの期間が短かし、ものとな
る為、機器の性能確保においても有利となる。
In addition, when it comes to bringing in equipment, the most appropriate time required can be selected within the overall process, and at the same time, the period between equipment testing at the factory and equipment testing at the site is shortened, ensuring equipment performance. It is also advantageous in

また仮設の配管の取付撤去がなくなり、工数の低減が実
現できる。高価な機器を早い時期に製造する事も不要と
なり、費用の発生も経済面から好ましい状態になる。
Additionally, there is no need to install or remove temporary piping, reducing man-hours. There is no need to manufacture expensive equipment at an early stage, and costs are also favorable from an economic point of view.

これら種々の効果の総合によりプラント建設工期の大中
な短縮費用の低減を実現することは容易に理解できる。
It is easy to understand that the combination of these various effects will significantly shorten the plant construction period and reduce costs.

以上本発明をその具体例について説明したが本発明は「
これら特定の実施例に限定されるものでく、本発明の
精神も逸脱しないで幾多の変化、変形がなし得ることは
勿論である。
Although the present invention has been described above with reference to specific examples thereof, the present invention is
It goes without saying that the present invention is not limited to these specific embodiments, and that many changes and modifications can be made without departing from the spirit of the present invention.

【図面の簡単な説明】[Brief explanation of the drawing]

第1図は最終配管施工状態を示す説明図、第2図は第1
図配管の水圧試験、洗浄をおこなう場合の従来の方法に
よる状態を示す平面図「第3図a,bは本発明の配管施
工方法に使用する模型の一実施例を示す側面図及び正面
図、第4図は本発明による模型を用いての配管施工例の
状態を示す説明図である。 10……模型、12・・・・・・配管。 第1図 第2図 第3図 第4図
Figure 1 is an explanatory diagram showing the final piping construction state, Figure 2 is the
Figure 3A and b are side and front views showing an embodiment of the model used in the piping construction method of the present invention; Fig. 4 is an explanatory diagram showing an example of piping construction using a model according to the present invention. 10...Model, 12...Piping. Fig. 1 Fig. 2 Fig. 3 Fig. 4

Claims (1)

【特許請求の範囲】[Claims] 1 配管施行にあたって、配管に接続される機器の接続
構造を正確に模擬し、加えて所定の試験圧力に耐え得る
強度の貫通孔を有する模型を機器据付け位置に設置した
後、所定の配管施工をし、且つその後水圧試験及び洗浄
を実施した後、前記模型を撤去し、その位置に前記機器
を据付けて施工を完了する配管施工方法。
1. When constructing piping, a model that accurately simulates the connection structure of the equipment connected to the piping and has through-holes strong enough to withstand the specified test pressure is installed at the equipment installation location, and then the specified piping construction is carried out. A piping construction method in which, after carrying out a water pressure test and cleaning, the model is removed and the equipment is installed in its place to complete the construction.
JP13158678A 1978-10-27 1978-10-27 Piping construction method Expired JPS608393B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP13158678A JPS608393B2 (en) 1978-10-27 1978-10-27 Piping construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP13158678A JPS608393B2 (en) 1978-10-27 1978-10-27 Piping construction method

Publications (2)

Publication Number Publication Date
JPS5560779A JPS5560779A (en) 1980-05-08
JPS608393B2 true JPS608393B2 (en) 1985-03-02

Family

ID=15061508

Family Applications (1)

Application Number Title Priority Date Filing Date
JP13158678A Expired JPS608393B2 (en) 1978-10-27 1978-10-27 Piping construction method

Country Status (1)

Country Link
JP (1) JPS608393B2 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP3528101A1 (en) 2018-02-14 2019-08-21 Wacom Co., Ltd. Electronic circuit of electronic pen and electronic pen

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP6073564B2 (en) * 2012-03-28 2017-02-01 日本バルカー工業株式会社 Piping workability evaluation test equipment

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP3528101A1 (en) 2018-02-14 2019-08-21 Wacom Co., Ltd. Electronic circuit of electronic pen and electronic pen

Also Published As

Publication number Publication date
JPS5560779A (en) 1980-05-08

Similar Documents

Publication Publication Date Title
CN109914462B (en) Positioning support for embedding steel column foundation bolt and construction method
CN208517944U (en) A kind of Metro station excavation bracing members axle power autocompensation installation
CN208379596U (en) Foundation pit supporting construction
CN111058661B (en) Modular assembly type machine room pipeline construction method
CN207568169U (en) Suitable for the deep basal pit outer wall of basement PC template systems under the conditions of null field ground
CN103669634A (en) Construction method and structure with damping wall poured later
JPS608393B2 (en) Piping construction method
CN114139997A (en) Integrated electromechanical installation construction process based on BIM and DPMA management
CN210152028U (en) Bolt joint method cell cube GRC curtain wall construction
CN207228148U (en) A kind of single-pipe tower precast splice type basis
CN103590419A (en) Assembled type adjustable high-voltage reactor foundation
CN104806024A (en) Seamless welding-free construction method of patterned steel plate
JPH0196500A (en) Large capacity multiple spindle centrifugal air compressor
CN211821025U (en) Template for quickly positioning and installing pipeline bracket
CN220539221U (en) Hole template piece fixed knot constructs
CN215981153U (en) Fixing, transporting and bearing integrated device for assembly type pipeline module
CN215803126U (en) Novel wall connecting piece of side-buried type
CN203594047U (en) Assembly type adjustable high-voltage electric reactor foundation
CN110253451B (en) Modularized rapid installation method of shot blasting machine of normalizing pickling line
JPS59177429A (en) Underground reinforced concrete structure
CN219870252U (en) Bearing capacity detection device of support frame body
CN214090940U (en) Outer shear wall is wall spare drawknot instrument even
JPH10103019A (en) Installing method for power train apparatus and power plant being installed by this method
JPH0112889B2 (en)
JPS6335387Y2 (en)