JPS60207749A - Supply-order determining apparatus - Google Patents

Supply-order determining apparatus

Info

Publication number
JPS60207749A
JPS60207749A JP6065384A JP6065384A JPS60207749A JP S60207749 A JPS60207749 A JP S60207749A JP 6065384 A JP6065384 A JP 6065384A JP 6065384 A JP6065384 A JP 6065384A JP S60207749 A JPS60207749 A JP S60207749A
Authority
JP
Japan
Prior art keywords
parts
machine
order
input
production line
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP6065384A
Other languages
Japanese (ja)
Inventor
Hideaki Kobayashi
秀明 小林
Takashi Onari
大成 尚
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hitachi Ltd
Original Assignee
Hitachi Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hitachi Ltd filed Critical Hitachi Ltd
Priority to JP6065384A priority Critical patent/JPS60207749A/en
Publication of JPS60207749A publication Critical patent/JPS60207749A/en
Pending legal-status Critical Current

Links

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B23MACHINE TOOLS; METAL-WORKING NOT OTHERWISE PROVIDED FOR
    • B23QDETAILS, COMPONENTS, OR ACCESSORIES FOR MACHINE TOOLS, e.g. ARRANGEMENTS FOR COPYING OR CONTROLLING; MACHINE TOOLS IN GENERAL CHARACTERISED BY THE CONSTRUCTION OF PARTICULAR DETAILS OR COMPONENTS; COMBINATIONS OR ASSOCIATIONS OF METAL-WORKING MACHINES, NOT DIRECTED TO A PARTICULAR RESULT
    • B23Q41/00Combinations or associations of metal-working machines not directed to a particular result according to classes B21, B23, or B24
    • B23Q41/02Features relating to transfer of work between machines

Abstract

PURPOSE:To improve the machine operation rate in a mixed production line by determining the part supply order, timing, etc. for increasing the machine operation rate in the production line according to the input information supplied from terminal apparatuses, by an arithmetic means into which production information is memorized. CONSTITUTION:The production information such as working procedure, used machinery, working time, buffer amount, etc. is memorized beforehand into a controller 80. On the basis of the production schedule for the kind of products, time, amount, etc. which is supplied from a host controller 9, the input-order calculation instruction is input from an input/output apparatus 7, and the feeding order, timing, etc. of parts which are optimum for minimizing the inoperative time of each machine 41-44 are calculated according to the prescribed processing procedures, and indicated as the working instruction for the input/output apparatus 7 and registered into the controller 9. Then, necessary parts are delivered from the part group in a part wavehouse 1 according to the working instruction, and after arranged by an arranging apparatus 2 according to the optimum supply order determined by the controller 80, the parts are transported to each machine 41-44 through transport lines 3.

Description

【発明の詳細な説明】 〔発明の利用分野〕 本発明は多品種の混合生産ラインにおいて機械の稼動率
を高めるように部品の投入順序を決定する投入順序決定
装置に関する。
DETAILED DESCRIPTION OF THE INVENTION [Field of Application of the Invention] The present invention relates to a loading order determining device for determining the loading order of parts so as to increase the operating rate of machines in a multi-product mixed production line.

〔発明の背景〕[Background of the invention]

従来の多品種少量の混合生産ラインにおいては、部品ご
との加工・組立等の作業時間が異なるため、投入部品の
作業干渉による機械の不稼動時間(作業待ちの遊休時間
、次機械が作業中のため当該機械が停止するブロッキン
グ時間等)が発注しやすいという欠点があった。このた
め省力化や品質向上等の目的でこのような製造職場を自
動化しようとすると、これらの機械の不稼動時間の発生
により自動化の効果が低下する障害を生じていた。
In conventional mixed production lines for high-mix, low-volume production, work times for processing and assembly differ for each part. Therefore, there was a drawback that it was easy to place an order (blocking time during which the machine stopped, etc.). Therefore, when attempting to automate such a manufacturing workplace for the purpose of saving labor or improving quality, there has been a problem in that the effectiveness of automation is reduced due to the occurrence of downtime of these machines.

〔発明の目的〕[Purpose of the invention]

本発明の目的は上記した従来技術の欠点をなくし、多品
種の混合生産ラインにおいて機械の稼動率を高めるよう
に部品の投入順序を高速かつ自動的に決定する投入順序
決定装置を提供するにある。
SUMMARY OF THE INVENTION An object of the present invention is to eliminate the above-mentioned drawbacks of the prior art and to provide a loading order determining device that quickly and automatically determines the loading order of parts so as to increase the operating rate of machines in a multi-product mixed production line. .

〔発明の概要〕[Summary of the invention]

本発明は、複数の機械が設置された生産ラインにおいて
、各機械での処理を行なう部品(素材を含む)の投入順
序計算指示および計算結果にもとづく作業指示を行なう
端末装置を配置し、予め作業手順、使用機械1作業時間
等の生産情報を記憶した電子計算機(記憶および演算手
段)により上記端末装置からの入力情報に応じて生産ラ
インにおける機械の稼動率を高めるに最適な部品の投入
順序、時期等を所定の処理手順により高速かつ自動的に
決定し、かつこの結果を端末装置に作業指示として出力
し、この作業指示に従って各機械へ部品を搬送する最初
の投入開始地点での部品の整列および搬送(投入)を行
なうようにしたことを特徴とする投入順序決定装置であ
る。
The present invention is a production line in which a plurality of machines are installed, and a terminal device is disposed to calculate the input order of parts (including materials) to be processed by each machine and to give work instructions based on the calculation results. An electronic computer (storage and calculation means) that stores production information such as procedures, working hours per machine used, etc., is used to determine the optimum order of inserting parts to increase the operating rate of the machines on the production line according to the input information from the terminal device; Alignment of parts at the initial loading start point where the timing etc. are determined quickly and automatically using a predetermined processing procedure, the results are output as work instructions to a terminal device, and the parts are transported to each machine according to the work instructions. This is a loading order determining device characterized by carrying out (loading) and conveying (loading).

〔発明の実施例〕[Embodiments of the invention]

以下に本発明の一実施例を図面により説明する。 An embodiment of the present invention will be described below with reference to the drawings.

矛1図は本発明による投入順序決定装置の一実施例を示
す生産ライン構成ブロック図である。
Figure 1 is a production line configuration block diagram showing an embodiment of the input order determining device according to the present invention.

矛1図において、本製造職場の生産ラインは部品(また
は素材)倉庫1と、部品を最適な投入順序に並べる整列
装置2と、各部品を各部品の処理を行なう機械に搬送す
る搬送ライン3と、各部品の処理を行なう複数の機械4
1〜44と、各機械間の仕掛装置!(バッファ)51〜
53と、処理が完了した完成部品を収納する完成品倉庫
6等とを備えている。さらに部品倉庫1と整列装置2は
入出力装置(端末装置)7を有するコントローラ(電子
計算機)80によって制御される一方、各機械41〜4
4は各コントローラ(電子計算機)81〜84によって
制御され、かつ各コントローラ80〜84はホストコン
トローラ(ホスト電子計算機)9によって管理・制御さ
れる。なお、これらの各コントローラ80〜84を使用
せずに、ホストコントローラ9のみにより集中制御され
る構成であってもよい。
In Figure 1, the production line of this manufacturing workplace includes a parts (or material) warehouse 1, an alignment device 2 that arranges parts in the optimal input order, and a transport line 3 that transports each part to a machine that processes each part. and multiple machines 4 that process each part.
1 to 44 and the in-process devices between each machine! (Buffer) 51~
53, and a finished product warehouse 6 for storing finished parts that have been processed. Furthermore, the parts warehouse 1 and the alignment device 2 are controlled by a controller (electronic computer) 80 having an input/output device (terminal device) 7, while each machine 41 to 4
4 is controlled by each controller (electronic computer) 81 to 84, and each controller 80 to 84 is managed and controlled by a host controller (host computer) 9. Note that the configuration may be such that the controllers 80 to 84 are not used and the host controller 9 centrally controls the host controller 9 alone.

このような構成の製造職場の生産ラインにおける投入順
序決定等動作をつぎに説明する。まずコントローラ80
は予め作業手順、使用機械。
Next, operations such as determining the input order in the production line of a manufacturing workplace with such a configuration will be explained. First, controller 80
is the work procedure and machine used in advance.

作業時間、バッファ量等の生産情報を記憶しておき、ホ
ストコントローラ9かう与えられた生産機種1時期、量
等の生産計画に基づき、入出力装置7から投入順序計算
指示を入力すること圧より、所定の処理手順(後の矛6
図)により各機械41〜44の不稼動時間を最小化する
ような一定期間内に処理を行なう部品の最適な投入順序
、時期等を計算し、この結果を入出力装置7へ作業指示
として表示するととも忙、ホストコントローラ9に登録
する。ついでこの作業指示に従い自動倉庫等の部品倉庫
1に収納されている部品群から必要部品を出庫し、整列
装置2によってさきにコントローラ80で決定された最
適投入順序に従い出庫部品を整列した後、搬送ライン乙
により処理を行なう各機械41〜44へ搬送される。こ
うして各機械41〜44での処理が完了した完成部品は
完成品倉庫6へ収納されるとともに、その実績情報が各
コントローラ81〜84およびホストコントローラ9へ
登録される。
By memorizing production information such as working time and buffer amount, and inputting input order calculation instructions from the input/output device 7 based on the production plan such as the given production model, timing, quantity, etc. from the host controller 9. , predetermined processing procedure (later 6
(Fig.) calculates the optimal input order and timing of parts to be processed within a certain period of time to minimize the downtime of each machine 41 to 44, and displays the results as work instructions on the input/output device 7. Then, it is busy and registered in the host controller 9. Next, according to this work instruction, the necessary parts are taken out from a group of parts stored in a parts warehouse 1 such as an automated warehouse, and after being arranged by the sorting device 2 in accordance with the optimum input order determined by the controller 80, the parts are transported. It is transported by line B to each machine 41 to 44 for processing. The finished parts that have been processed in each of the machines 41 to 44 are stored in the finished product warehouse 6, and their performance information is registered in each of the controllers 81 to 84 and the host controller 9.

また、各機械41−4の故障もしくは特急品、欠品等に
よる投入順序変更の必要性が生じた場合には、入出力装
置7から再度投入順序1時期を入力することにより、再
度投入順序1時期等の計算を行ない、この結果に基づく
作業指示に従い必要部品の出庫、整列、搬送等の同様の
動作を繰り返す。
In addition, if it becomes necessary to change the loading order due to a failure of each machine 41-4 or due to urgent items, missing items, etc., inputting the loading order 1 timing again from the input/output device 7 allows the loading order 1 to be changed again. Calculation of timing, etc. is performed, and similar operations such as unloading, arranging, and transporting necessary parts are repeated in accordance with work instructions based on the results.

矛2図は矛1図の機械の不稼動時間である遊休時間およ
びブロッキング時間を考慮した部品の最適投入順序決定
方法を例示する説明図である。なお、1′F2図はm台
の機械を有するフローショップ型の生産ラインにおいて
、n個の部品の処理を行なう場合の処理の流れを各機械
およびバッファごと忙各部品の作業時間で示したもので
、各機械間のバッファ量はそれぞれ1の場合の例である
。矛2図において、機械の遊休時間とは例えば機械2に
おいて部品1の処理が終了してから次の部品2が到着す
るまでの作業待ちの不稼動時間を指し、ブロッキング時
間とは例えば機械1において部品4の処理が終了した後
もバッファ1および機械2が共に詰っているので部品4
が機械1にとどまっていて機械1が停止している不稼動
時間を指す。
Figure 2 is an explanatory diagram illustrating a method for determining the optimum loading order of parts in consideration of the idle time and blocking time, which are non-operating times of the machine shown in Figure 1. In addition, Figure 1'F2 shows the processing flow when processing n parts in a flow shop type production line with m machines, in terms of the working time of each part for each machine and buffer. In this example, the buffer amount between each machine is 1. In Figure 2, the idle time of a machine refers to, for example, the idle time of machine 2 waiting for work from the end of processing part 1 until the arrival of the next part 2, and the blocking time refers to, for example, the idle time of machine 2. Even after the processing of part 4 is finished, both buffer 1 and machine 2 are clogged, so part 4
refers to the downtime during which machine 1 remains in machine 1 and machine 1 is stopped.

矛2図により第1図の部品の最適な投入順序を決定する
方法について説明する。ここで部品の最適な投入順序と
は各機械の稼動率をできるだけ高めることを目的とする
ものであるから、各機械の不稼動時間を最小化する部品
の投入順序を決定すればよいことになる。また、この投
入順序の計算はできるだけ短時間に自動的に行なうのが
好ましい。そこで本実施例では才2図に示すように各機
械の不稼動時間である遊休時間およびブロッキング時間
を減少して、生産ライン全体の線屑要時間を最小化する
部品の投入順序および時期等を、入出力装置7の投入順
序計算指示によりコントローラ80が所定の処理手順に
より高速かつ自動的に計算して、その結果を作業指示と
して入出力装置7へ出力して表示する。
A method for determining the optimal order of inputting the parts shown in FIG. 1 will be explained using FIG. 2. Here, the optimal order of loading parts is aimed at increasing the operating rate of each machine as much as possible, so it is sufficient to determine the order of loading parts that minimizes the downtime of each machine. . Further, it is preferable that this calculation of the input order be automatically performed in as short a time as possible. Therefore, in this embodiment, as shown in Figure 2, the order and timing of parts introduction are determined to reduce the idle time and blocking time, which are the non-operating time of each machine, and to minimize the time required for scrapping the entire production line. In response to input order calculation instructions from the input/output device 7, the controller 80 performs high-speed and automatic calculations according to a predetermined processing procedure, and outputs the results as work instructions to the input/output device 7 for display.

つぎに第3図は牙1図および、1′F2図の部品の最適
投入順序決方法の処理手順を例示するフローチャートで
ある。矛3図により、本実施例で投入順序の計算をでき
るだけ短時間に自動的に行なうことも考慮のうえ採用し
た各機械の不稼動時間を減少させる部品の最適投入順序
決定方法の具体的な処理手順について説明する。
Next, FIG. 3 is a flowchart illustrating the processing procedure of the method for determining the optimum input order of the parts shown in FIGS. 1 and 1'F2. Figure 3 shows the specific process of determining the optimal loading order of parts to reduce the downtime of each machine, which was adopted in this embodiment with consideration given to automatically calculating the loading order in as short a time as possible. Explain the procedure.

ステップ81で、まず2機械の場合に部品の最適な投入
順序を決定するのに有効であるJohnsonルールを
3機械以上の生産ライン忙適用するために、全生産ライ
ンをある機械たとえば好ましくは最大作業量(作業時間
)の機械の前後で2分割して2グループ化する。
In step 81, first, in order to apply the Johnson rule, which is effective for determining the optimal loading order of parts in the case of two machines, to a production line with three or more machines, all production lines are connected to a certain machine, for example, preferably with the maximum work load. Divide into two groups before and after the machine according to the amount (work time).

ステップS2で、この2グループ化した各機械群につい
て、全生産ラインを2機械として次式の判定規準のJo
hnsonルールにより遊休時間を最小化する部品の投
入順序を初期解としてめる。すなわち次の判定規準: m1n(Pi、1. Pi+1.2 )<m1n(PL
+1. 1. Pj2)が成立する時に、部品iは部品
i+1に先行させる。但し、Pj、j は部品iの機械
jにおける作業時間である。
In step S2, for each machine group divided into two groups, Jo
Based on the hnson rule, the order of introducing parts that minimizes idle time is determined as an initial solution. That is, the following criterion: m1n(Pi, 1. Pi+1.2 )<m1n(PL
+1. 1. When Pj2) is satisfied, part i is made to precede part i+1. However, Pj,j is the working time of part i in machine j.

ステップ3で、この初期解で得られた投入順序を更に改
良するために、全体の対象部品の順序を部分的に分割し
て投入順序をめてゆくように、初期解をもとに全体の対
象部品の順序を部分的に分割する。この分割は短時間に
投入順序計算を行なうためのもので、その分割数は要求
計算速度および解の精度に応じて任意に決定する。
In step 3, in order to further improve the insertion order obtained with this initial solution, the overall order of the target parts is divided into parts and the insertion order is determined based on the initial solution. Partially divide the order of target parts. This division is used to perform input order calculations in a short time, and the number of divisions is arbitrarily determined depending on the required calculation speed and solution accuracy.

ステップS4で、この分割した対象部品について、各機
械ごとの遊休時間およびブロッキング時間を最小化する
投入順序をめる。なお、遊休時間If、 jおよびブロ
ッキング時1dJBi、jは次式で表わされる。
In step S4, for the divided target parts, a loading order is determined that minimizes the idle time and blocking time for each machine. Note that the idle time If,j and the blocking time 1dJBi,j are expressed by the following equations.

Ii、7口8i、j −Ti−1,j Bi’、jコTi、j −Ci、j 但し、8i、jは部品皿の機械jにおける作業開始時刻
、Ci、jは同じく作業完了時刻、Ti 、 jは同じ
(搬送可能時刻である。
Ii, 7 mouths 8i, j -Ti-1,j Bi', j koTi, j -Ci, j However, 8i, j are the work start times in machine j for the parts tray, Ci, j are the work completion times, Ti and j are the same (transferable time).

ステップS5で、ついで投入順序を決定する全対象部品
について、ステップs3およびs4の処理を行なう。
In step S5, the processes of steps s3 and s4 are performed for all target parts whose input order is to be determined.

ステップS6で、以上の処理により、全対象部品の最適
な投入順序が決定される。
In step S6, the optimum input order for all target parts is determined through the above processing.

なお、このようにしてコントローラ8oにより決定され
た結果を入出力装置7に作業指示として出力し、この作
業指示に従って各機械へ部品を搬送する最初の投入地点
での部品の出庫、整列、搬送(投入)が行なわれる。
The results determined by the controller 8o in this manner are output as work instructions to the input/output device 7, and according to these work instructions, parts are unloaded, aligned, and transported at the initial input point to be transported to each machine. input) is carried out.

以上のようにして本実施例の処理手順により投入順序を
めると、短時間に精度よく部品の最適な投入順序を決定
することができる。
By determining the loading order using the processing procedure of this embodiment as described above, it is possible to determine the optimum loading order of parts with high precision in a short time.

〔発明の効果〕〔Effect of the invention〕

以上に説明したように、本発明の投入順序決定装置によ
れば、機械の部品ごとの作業時間が異なる多品種の混合
生産ラインにgいて、各機械の不稼動時間を減少する部
品の最適な投入順序が人手を要することなく、高速かつ
自動的に決定でき、これにより各機械の稼動率が向上し
て製造職場の自動化の効果をより高めることができる。
As explained above, according to the input order determining device of the present invention, when a multi-product mixed production line where the working time for each machine part is different, the optimum part selection method can be used to reduce the downtime of each machine. The input order can be determined quickly and automatically without the need for human intervention, which improves the operating rate of each machine and further enhances the effectiveness of automation in the manufacturing workplace.

【図面の簡単な説明】[Brief explanation of the drawing]

矛1図は本発明による投入順序決定装置の一実施例を示
す生産ライン構成ブロック図、矛2図は矛1図の最適投
入順序決定方法の説明側図、矛3図は矛1図の最適投入
順序決定方法の処理手順例フローチャートである。 1・・・部品倉庫、2・・・整列装置、3・・・搬送ラ
イン、41〜44・・・機械、51〜53・・・仕掛品
fl場(バッファ)、6・・・完成品倉庫、7・・・入
出力装置(端末装置)、80〜84・・・コントローラ
(′FIL子計算機)、9・・・ホストコントローラ(
ポスト電子計算機)。 代理人fP埋士 局 慣 男 大
Figure 1 is a production line configuration block diagram showing an embodiment of the feeding order determining device according to the present invention, Figure 2 is a side view illustrating the method for determining the optimum feeding order in Figure 1, and Figure 3 is a diagram showing the optimal loading order determination method in Figure 1. It is a flowchart of an example of a processing procedure of a method of determining an input order. 1... Parts warehouse, 2... Sorting device, 3... Conveyance line, 41-44... Machine, 51-53... Work-in-progress fl field (buffer), 6... Finished product warehouse , 7... Input/output device (terminal device), 80-84... Controller ('FIL child computer), 9... Host controller (
post-electronic computer). Agent fP Burial Officer Tsutomuo Dai

Claims (1)

【特許請求の範囲】 1、 複数の機械により複数の部品(素材を含む)の処
理を行た5生産ラインにおいて、各機械での処理を行な
う部品の投入順序計算指示および計算結果に基づく作業
指示を行なう端末装置と、あらかじめ部品の作業手順、
使用機械1作業時間等の生産情報を記憶する記憶手段と
、上記端末装置からの入力情報に応じて上記記憶手段に
記憶された生産情報から所定の処理手順により、生産ラ
インにおける各機械の不稼動時間を減少せしめる最適な
部品の投入順序、時期等を決定し、その結果を上記端末
装置に作業指示として出力する演算手段と、該作業指示
に従って各機械へ部品を搬送する最初の投入地点での部
品の整列、搬送を行な5手段とを備えた投入順序決定装
置。 2 複数の機械により複数の部品(素材を含む)の処理
を行なう生産ラインにおいて、各機械での処理を行なう
部品の投入順序指示および計算結果に基づく作業指示を
行rx 5端末装置と、あらかじめ部品の作業手順、使
用機械。 作業時間等の生産情報を記憶する記憶手段と、上記端末
装置からの入力情報に応じて上記記憶手段に記憶された
生産情報から所定の処理手順により、生産ラインを特定
の機械の前佐で2分割した各機械群につき各機械の遊休
時間を減少せしめる部品の投入順序を初期解として決定
し、かつ該初期解を基に全生産ラインの全対象部品忙つ
いての各機械ごとの遊休時間およびブロッキング時間を
減少せしめる部品の投入順序を改良解として決定するこ
とにより、生産ラインにおける各機械の不稼動時間を減
少せしめる最適な部品の投入順序、時期等を決定し、そ
の結果を上記端末装置に作業指示として出力する演算手
段と、該作業指示に従って各機械へ部品を搬送する最初
の投入地点での部品の整列、搬送を行Tx ウ手段とを
備えた投入順序決定装置。 & 複数の機械により複数の部品(素材を含む)の処理
を行なう生産ラインにおいて、各機械での処理を行なう
部品の投入順序計算指示および計算結果に基づく作業指
示を行なう端末装置と、あらかじめ部品の作業手順、使
用機械1作業時間等の生産情報を記憶する記憶手段と、
上記端末装置からの入力情報に応じて上記記憶手段に記
憶された生産情報から所定の処理手順により、生産ライ
ンを特定の機械の前後で2分割した各機械群につぎ各機
械の遊休時間を減少せしめる部品の投入順序を初期解と
して決定し、かつ該初期解を基に全生産ラインの全対象
部品の順序を複数部分に分割した対象部品についての各
機械ごとの遊休時間およびブロッキング時間を減少せし
める部品の投入順序を改良解として決定することにより
、生産ラインにおける各機械の不稼動時間を減少せしめ
る最適な部品の投入順序。 時期等を決定し、その結果を上記端末装置圧作業指示と
して出力する演算手段と、該作業指示に従って各機械へ
部品を搬送する最初の投入地点での部品の整列、搬送を
行なう手段とを備えた投入順序決定装置。 4、上記生産ラインを特定の機械の前後で2分割する特
定の機械は最大作業時間の機械である特許請求の範囲中
吟噸+セ忰矛3項記載の投入順序決定装置。 5、上記初期解はJohnsonルールによりめる特許
請求の範酢オキ喚嗜去按矛3項記載の役人順序決定装置
[Scope of Claims] 1. In five production lines in which multiple parts (including materials) are processed by multiple machines, instructions for calculating the input order of parts to be processed by each machine and work instructions based on the calculation results Terminal equipment that performs the process, work procedures for parts,
A storage means for storing production information such as the working hours of each machine used, and a predetermined processing procedure based on the production information stored in the storage means according to the input information from the terminal device, the non-operation of each machine on the production line. A calculation means that determines the optimal order and timing of parts input to reduce time and outputs the results as work instructions to the terminal device, and a calculation means at the initial input point that transports the parts to each machine according to the work instructions. A loading order determining device equipped with five means for arranging and transporting parts. 2. On a production line where multiple parts (including materials) are processed by multiple machines, instructions are given for the input order of parts to be processed by each machine and work instructions based on calculation results. Work procedures and machines used. A storage means for storing production information such as working hours, and a predetermined processing procedure for controlling the production line in two directions from the production information stored in the storage means in accordance with the input information from the terminal device. For each divided machine group, determine the input order of parts that reduces the idle time of each machine as an initial solution, and based on the initial solution, calculate the idle time and blocking of each machine for all target parts of all production lines. By determining the order of parts introduction that reduces time as an improved solution, the optimum order and timing of parts introduction that reduces the downtime of each machine on the production line is determined, and the results are sent to the terminal device mentioned above. A loading order determining device comprising: arithmetic means for outputting instructions; and means for arranging and transporting parts at a first loading point for conveying parts to each machine according to the work instructions. & In a production line where multiple parts (including materials) are processed by multiple machines, there is a terminal device that gives calculation instructions for the input order of parts to be processed by each machine and work instructions based on the calculation results, and a storage means for storing production information such as work procedures and working hours per machine used;
The production line is divided into two groups before and after a specific machine, and the idle time of each machine is reduced by a predetermined processing procedure based on the production information stored in the storage means in accordance with the input information from the terminal device. The input order of the parts to be released is determined as an initial solution, and based on the initial solution, the order of all target parts on all production lines is divided into multiple parts to reduce the idle time and blocking time for each machine for the target parts. By determining the order of parts introduction as an improved solution, the optimum order of parts introduction is determined to reduce the downtime of each machine on the production line. A calculation means for determining the timing, etc. and outputting the result as the terminal device pressure work instruction, and a means for arranging and transporting the parts at the initial input point for transporting the parts to each machine according to the work instruction. input order determining device. 4. The input order determining device according to claim 3, wherein the specific machine that divides the production line into two parts before and after the specific machine is the machine with the maximum working time. 5. The official order determining device according to claim 3, wherein the initial solution is based on the Johnson rule.
JP6065384A 1984-03-30 1984-03-30 Supply-order determining apparatus Pending JPS60207749A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP6065384A JPS60207749A (en) 1984-03-30 1984-03-30 Supply-order determining apparatus

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP6065384A JPS60207749A (en) 1984-03-30 1984-03-30 Supply-order determining apparatus

Publications (1)

Publication Number Publication Date
JPS60207749A true JPS60207749A (en) 1985-10-19

Family

ID=13148507

Family Applications (1)

Application Number Title Priority Date Filing Date
JP6065384A Pending JPS60207749A (en) 1984-03-30 1984-03-30 Supply-order determining apparatus

Country Status (1)

Country Link
JP (1) JPS60207749A (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH01109060A (en) * 1987-10-19 1989-04-26 Nec Corp Production schedule forming device
JPH01109059A (en) * 1987-10-23 1989-04-26 Hitachi Ltd Production controller
JPH01121155A (en) * 1987-11-04 1989-05-12 Nec Corp Production scheduling system
JPH03149162A (en) * 1989-10-30 1991-06-25 Nec Corp Synchronous production scheduling planning device
JPH03196948A (en) * 1989-12-25 1991-08-28 Matsushita Electric Works Ltd Production planning preparation method

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH01109060A (en) * 1987-10-19 1989-04-26 Nec Corp Production schedule forming device
JPH01109059A (en) * 1987-10-23 1989-04-26 Hitachi Ltd Production controller
JPH01121155A (en) * 1987-11-04 1989-05-12 Nec Corp Production scheduling system
JPH03149162A (en) * 1989-10-30 1991-06-25 Nec Corp Synchronous production scheduling planning device
JPH03196948A (en) * 1989-12-25 1991-08-28 Matsushita Electric Works Ltd Production planning preparation method

Similar Documents

Publication Publication Date Title
EP1426842B1 (en) Production cell comprising an information processing device for commanding work tasks
JPS60207749A (en) Supply-order determining apparatus
JP2800795B2 (en) Production control method and production control device
JPH0812026A (en) Manufacture management in factory comprising plural manufacturing processes
JPS62173155A (en) Input control optimization system
JPS5815651A (en) Machining apparatus
JPS61232026A (en) Production system for pressed articles
JP4119588B2 (en) Work production ratio controller
JP3319779B2 (en) Processing system
JPH05218177A (en) Semiconductor fabrication control system
JP2666291B2 (en) Production equipment using automated guided vehicles
JP3081019B2 (en) Injection control system
JPH0241857A (en) Method and device for deciding proper work time in plural work
JPS62274310A (en) Physical distribution control system
JPH01216755A (en) Device for controlling production line
JP3016814B2 (en) Processing schedule creation device
JPS5882654A (en) Work sequence control method at production site
JPH02230408A (en) Transport controller
JPS62216006A (en) Sheet metal working cam
JP2684135B2 (en) How to supply / collect parts
JPH01307803A (en) Inter-subsystem control system of production order progress management file
JP2782950B2 (en) Synchronous delivery instruction method in production equipment
JPH0223405A (en) Automatic trial cutting controller
JPH06730A (en) Production indication device for subassembly line
JPH054703A (en) Automatic supplying method of material