JPS60176426A - Load amount controller - Google Patents

Load amount controller

Info

Publication number
JPS60176426A
JPS60176426A JP59029477A JP2947784A JPS60176426A JP S60176426 A JPS60176426 A JP S60176426A JP 59029477 A JP59029477 A JP 59029477A JP 2947784 A JP2947784 A JP 2947784A JP S60176426 A JPS60176426 A JP S60176426A
Authority
JP
Japan
Prior art keywords
load
power
trip
amount
load amount
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP59029477A
Other languages
Japanese (ja)
Inventor
金井 治樹
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Toshiba Corp
Original Assignee
Toshiba Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Toshiba Corp filed Critical Toshiba Corp
Priority to JP59029477A priority Critical patent/JPS60176426A/en
Publication of JPS60176426A publication Critical patent/JPS60176426A/en
Pending legal-status Critical Current

Links

Landscapes

  • Supply And Distribution Of Alternating Current (AREA)

Abstract

(57)【要約】本公報は電子出願前の出願データであるた
め要約のデータは記録されません。
(57) [Summary] This bulletin contains application data before electronic filing, so abstract data is not recorded.

Description

【発明の詳細な説明】 〔発明の技術分野〕 本発明は互いに異なる複数の電源系統の並列運転によシ
、複数の負荷からなる負荷群(二対して電力を供給する
際の負荷量制御装置4二関する。
[Detailed Description of the Invention] [Technical Field of the Invention] The present invention provides a load amount control device for supplying electric power to a load group (two groups) consisting of a plurality of loads, for parallel operation of a plurality of different power supply systems. 42 related.

〔発明の技術的背景とその間融点〕[Technical background of the invention and its melting point]

近年電力系統においては、負荷群に対する信頼性の高い
電力供給を確保するため、電源系統として買電系統と自
家発電系統とを用意し、これらを並列運転して運用する
ことが行なわれている。この場合、買電系統にはデマン
ド監視装置を設け、需要′電力が設定値である契約電力
な上廻わらないように監視制御している。一般にこの種
のデマンド監視制御装置は、契約電力に対する負荷監視
又は、負荷制御のみで、例えば買電側変圧器の故障に伴
う電源側トリップ発往時(過電流などによる引きはずし
)における負荷遮断は、別途負荷選択遮断シーケンスに
よって行ってお夛、相互の関連はなかった。
In recent years, in electric power systems, in order to ensure a highly reliable power supply to a load group, a power purchasing system and a private power generation system have been prepared as power supply systems, and these systems are operated in parallel. In this case, a demand monitoring device is installed in the power purchasing system to monitor and control the demand power so that it does not exceed the set value of the contracted power. In general, this type of demand monitoring and control device only monitors or controls the load on contract power, and for example, load shedding when the power supply side trips due to a failure in the purchasing side transformer (trip due to overcurrent, etc.) This was done through a separate load selection sequence, but there was no correlation between them.

つまシ変圧器あるいは、自家発電機故障によシミ源側の
トリップが発生すれば、系統下の負荷を遮断し、系統下
の2次波及停電を防止していた。
If a trip occurred on the stain source side due to a failure of the tamashi transformer or private generator, the load under the system would be cut off, preventing secondary power outages within the system.

このためその系統下の負荷は全て遮断され、電力デマン
ドシステムからみると、余裕がある場合でも、前述のよ
うな事故による工場操業率の低下は、しかたのないもの
であった。
As a result, all loads under that system were cut off, and even if there was some margin from the perspective of the power demand system, the reduction in factory operating rates due to the above-mentioned accident was unavoidable.

〔発明の目的〕[Purpose of the invention]

本発明の目的は、電源系統の事故発生時においても該当
する負荷群を一律にしゃ断することなく、その負荷群に
おける限界負荷量を維持することにより、事故波及を防
止しながら工場操業度の低下を防止し、しかもデマンド
監視制御との連けいをとることによシ、常に契約電力内
における最適負荷量を保つことができる負荷量制御装置
を提供することにある。
The purpose of the present invention is to maintain the limit load of the load group without uniformly cutting off the corresponding load group even when an accident occurs in the power supply system, thereby reducing the factory operating rate while preventing the accident from spreading. It is an object of the present invention to provide a load amount control device that can prevent this and can always maintain the optimum load amount within the contract power by linking with demand monitoring control.

〔発明の概要〕[Summary of the invention]

本発明は互いに異なる複数の電源系統の並列運転により
、複数の負荷からなる負荷群に対して電力を供給する除
の負荷量制御装置に関するもので。
The present invention relates to a load amount control device for supplying electric power to a load group consisting of a plurality of loads through parallel operation of a plurality of different power supply systems.

第2図で示すように、前記複数の電力系統のいずれか一
方の需要電力量を入力しこれを設定値と比較するデマン
ド監視手段と、前記複数の電力系統のいずれかにトリッ
プが発生した場合そのトリップ発生系統がどれかを割シ
出すトリップ場所側ル出し手段と、上記トリップ発生時
そのトリップ発生系統から給電されていた負荷群の限界
負荷量をその負荷群に対する残シの電源系統容量を基に
決定しかつトリップが発生していない場合はデマンド監
視袋にの比較結果に基づきその需要電力量を前記設定値
に近づけるためのしゃ断負荷量または投入負荷量を決定
する負荷量決定手段と、この負荷量決定手段によシ決定
された負荷量を満足すべくしゃ断対象負荷または投入対
象負荷を決定する手段とを備え、上記決定された負荷に
対ししゃ断または投入指令を出力することによシ、運転
負荷量を最適値に保つものである。
As shown in FIG. 2, there is a demand monitoring means for inputting the amount of electricity demanded from one of the plurality of power systems and comparing it with a set value, and a case where a trip occurs in one of the plurality of power systems. A means for determining which system is causing the trip, and calculating the limit load amount of the load group that was being supplied with power from the system that caused the trip when the trip occurred, and the capacity of the remaining power system for that load group. load amount determining means for determining a cut-off load amount or an input load amount for bringing the demanded power amount closer to the set value based on the comparison result with the demand monitoring bag when a trip has not occurred; means for determining a load to be cut off or a load to be turned on in order to satisfy the load amount determined by the load amount determining means; , to maintain the operating load at an optimal value.

〔発明の実施例〕[Embodiments of the invention]

以下本発明を図面に示す一実施例を参照して詳細に説明
する。
The present invention will be described in detail below with reference to an embodiment shown in the drawings.

第1図は本発明装置と被制御対象である電力系統との関
係を示している。図において、1.2は1号、2号の各
変圧器で、その1次側は変圧器1次しゃ断器3.4を介
し、さらに買電系しゃ断器5、同断路器6および取引用
変圧変流器MOFを介して図示しない送電線に接続され
ている。なお取引用電力測定装置MOFには電力量計W
Hが接続されており、所定の需要電力毎にパルスを発生
する。
FIG. 1 shows the relationship between the device of the present invention and the power system that is the object to be controlled. In the figure, 1.2 is each transformer No. 1 and No. 2, and the primary side of the transformer is connected via the transformer primary breaker 3.4, and further connected to the power purchase system breaker 5, the same disconnector 6, and the transaction It is connected to a power transmission line (not shown) via a current transformer MOF. Note that the transaction power measurement device MOF includes a power meter W.
H is connected and generates a pulse every predetermined demand power.

一方、7.8は1号、2号の各自家発電機で、その出力
端は発電機しゃ断器9.10を介して母線11゜12に
夫々接続されている。
On the other hand, reference numeral 7.8 denotes No. 1 and No. 2 private generators, the output ends of which are connected to bus bars 11 and 12 through generator circuit breakers 9 and 10, respectively.

また、上記1号、2号変圧器1.2の2次側は、変圧器
2次しゃ断器13 、14、連系しゃ断器15 、16
および17 、1.8を介し、これよシ母線断路器19
 、20を介して母線11に、かつ母線断路器21 、
22を介して母線12に夫々接続されている。さらに、
上記母線11 、12は母線断路器圀、24により連系
され、この各断路器23 、24間には、負荷群しゃ断
器25を介して第1の負荷9群26が接続されている。
In addition, the secondary sides of the No. 1 and No. 2 transformers 1.2 are transformer secondary circuit breakers 13 and 14, and interconnection circuit breakers 15 and 16.
and 17, 1.8, this is the bus disconnector 19
, 20 to the busbar 11, and the busbar disconnector 21,
22 to the bus bar 12, respectively. moreover,
The buses 11 and 12 are interconnected by a bus disconnector 24, and a first group of nine loads 26 is connected between each of the disconnectors 23 and 24 via a load group breaker 25.

さらにまた、上記変圧器2次しゃ断器13および14と
連系しや断器15および16との間には、負荷群しゃ断
器27および拐を介して第2および第3の負荷群29お
よび30が接続されている。なお図において、0.闇は
投入状態、01口は開放状態にあることを夫々表わす。
Furthermore, second and third load groups 29 and 30 are connected between the transformer secondary circuit breakers 13 and 14 and the interconnection circuit breakers 15 and 16 via a load group circuit breaker 27 and a is connected. In the figure, 0. Darkness represents a closed state, and 01 mouth represents an open state.

また、上記各負荷群26 、29 、30は夫々複数の
負荷よシ成るものである。
Each of the load groups 26, 29, and 30 is composed of a plurality of loads.

31は本発明の負荷選択しゃ断装置であり、前記電力系
統からその計測値入力(アナログ量)A、状態、故障入
力(デジタル量)Bおよび受要電力量(パルス)Dを入
力し、かつ電力系統に対してしゃ断出力Cを出力するよ
うにしている。ここで、計測値入力人としては1号、2
号変圧器1.2の出力1号、2号自家発電機7.8の発
電々力、および各負荷電力を入力し、また状態、故障人
力Bとしてはしゃ断器、断路器機器運転(開、閉)状態
入力、トリップ故障入力(リレー出力)を夫々入力する
ものである。なお、各負荷群26 、29 、30から
は、図示しない各負荷の運転状態に相当する各負荷弁の
しゃ断器状態信号のみが入力される。
Reference numeral 31 denotes a load selection cutoff device of the present invention, which inputs the measured value input (analog amount) A, status, fault input (digital amount) B, and required power amount (pulse) D from the power grid, and A cutoff output C is output to the grid. Here, the measurement value input persons are No. 1 and No. 2.
Input the output power of the No. 1 transformer 1.2, the generated power of the No. 2 private generator 7.8, and each load power, and also input the state and failure human power B as the breaker and disconnector equipment operation (open, (closed) status input and trip failure input (relay output). In addition, from each load group 26, 29, 30, only the breaker state signal of each load valve corresponding to the operating state of each load (not shown) is input.

また需要電力量りとしては電力量計WHの出力バルスを
入力する。
Furthermore, the output pulse of the power meter WH is inputted as the power demand measurement.

第2図は、上記中央情報処理装置3Jが果す各機能を手
段として示すブロック図である。図において、41はデ
マンド監視手段で、第1図に示す受電点に設けた電力量
計WHからのパルスを計数しておシ、予め設定した監視
同期毎に第3図で示す動作を実行する。すなわち、前記
パルス計数値からその時点における需要電力(受電々カ
)WRを計算しくステップ4111、設定値である″電
力会社との契約電力WKと比較し、デマンド終了時点に
おいて、需要電力WRが契約電力WKをオーバーするが
否かを判定(ステップ412)する。その結果、オーバ
ーしない場合はデマンド正常をセット(ステップ413
)、オーバーする場合はデマンドオーバーをセット(ス
テップ414 )L、終了する。
FIG. 2 is a block diagram showing each function performed by the central information processing unit 3J as means. In the figure, 41 is a demand monitoring means that counts pulses from the electricity meter WH installed at the power receiving point shown in Fig. 1, and executes the operation shown in Fig. 3 at each preset monitoring synchronization. . That is, the demand power (received power) WR at that point is calculated from the pulse count value, and in step 4111, it is compared with the set value "contract power WK with the electric power company, and at the end of the demand, the demand power WR is the contracted power." It is determined whether or not the power WK is exceeded (step 412).As a result, if the power WK is not exceeded, the demand is set to normal (step 413).
), if the demand exceeds, set the demand over (step 414) L, and end.

42はトリップ場所割出し手段で、第1図の電力系統に
おける各電源系統、すなわち変圧器1.2および自家発
電i7.8を主体とし、それらに対応する各しゃ断器を
含む系統のいずれかに故障が発生し、対応するしゃ断器
がトリップ動作した場合、どの電源系統がトリップした
かを割シ出すものである。すなわち、電力系統側からは
各機器毎の状態・故障信号Aが入力されておシ、中央情
報処理装置31では、この信号Aを常時走査している。
Reference numeral 42 denotes a trip location determining means that detects a trip location in any one of the power supply systems in the power system shown in FIG. When a failure occurs and the corresponding circuit breaker trips, it is possible to determine which power supply system has tripped. That is, the status/failure signal A for each device is input from the power system side, and the central information processing unit 31 constantly scans this signal A.

従って第4図で示すように、トリップ発生時は故障発生
機器に該当するトリップ信号が検知される(ステップ4
2j)。そして、このトリップ信号から該当するトリッ
プ発生場所iを割シ出しくステップ422)終了する。
Therefore, as shown in Fig. 4, when a trip occurs, a trip signal corresponding to the faulty equipment is detected (step 4).
2j). Then, the corresponding trip occurrence location i is determined from this trip signal. Step 422) ends.

43は負荷量決定手段で、前記デマンド監視手段41か
らデマンド情報が与えられ、またトリップ割シ出し手段
42からはトリップ発住場所割シ出し情報が与えられる
。さらに電力系統例からは、各機器毎の状態信号および
現在の使用電力値等が入力されている。この負荷量決定
手段43は、予め設定された制御周期毎に処理を実行す
るが、前述のトリップ発生時は、上記制御周期にかかわ
らず、処理が開始される。従って、第5図で示す如く、
まずこの処理がトリップ発生による起動か否かを判定(
ステップ431)する。その結果、トリップ発生による
起動であれば、割シ出された場所(トリップ発生系統)
iによシ、そのトリップ発生系統iから給電されている
負荷群を選定し、この負荷群に対する残シの電源系統の
容量から限界負荷量L1を決定する(ステップ432)
。例えは、第1図の電力系統にて変圧器1を含む電源系
統でトリップが午じた場合、その電源系統から給電され
ている負荷群29が選定される。そしてこの負荷群29
に対して給電している残りの電源系統、すなわち、自家
発電PVJ7を含む電源系統の容量から、この負荷群2
9にて運転を継続できる限界負荷iLiを決定する。そ
して最終的には、トリップ時に運転中の負荷容量から上
記限界負荷量Liを差し引き、しゃ断負荷容量を決定す
る。
Reference numeral 43 denotes a load determining means, to which demand information is given from the demand monitoring means 41, and trip originating place calculating information is given from the trip calculating means 42. Further, from the power system example, status signals and current power usage values for each device are input. This load amount determining means 43 executes the process at each preset control cycle, but when the above-mentioned trip occurs, the process is started regardless of the control cycle. Therefore, as shown in Figure 5,
First, determine whether this process is started due to a trip (
Step 431). As a result, if the activation is due to a trip, the assigned location (trip generation system)
According to i, a load group that is supplied with power from the trip generation system i is selected, and a limit load L1 is determined from the capacity of the remaining power supply system for this load group (step 432).
. For example, if a trip occurs in the power system including the transformer 1 in the power system shown in FIG. 1, the load group 29 that is supplied with power from that power system is selected. And this load group 29
This load group 2 is calculated from the capacity of the remaining power supply system that supplies power to
In step 9, the limit load iLi at which the operation can be continued is determined. Finally, the limit load amount Li is subtracted from the load capacity under operation at the time of trip to determine the cutoff load capacity.

これに対し、トリップ発生によらない通常の制御周期毎
の起動であれば、前記デマンド情報を判定する(ステッ
プ433)。その結果、デマンド正常(契約電力以下)
であれば、契約電力を超過しない範囲で、あとどれだけ
の負荷を運転できるかを演算し、投入負荷容量LoNを
決定する(ステップ434)。一方、デマンドオーバー
の場合は、需要電力を契約電力以内に納めるためには、
どれだけの負荷を停止すればよいかを演算し、しゃ断負
荷容景LOFFを決定する(ステップ435)。
On the other hand, if the activation is not based on the occurrence of a trip but is performed every normal control cycle, the demand information is determined (step 433). As a result, demand is normal (less than contract power)
If so, calculate how much more load can be operated without exceeding the contracted power, and determine the applied load capacity LoN (step 434). On the other hand, in the case of demand over, in order to keep the demand power within the contract power,
It calculates how much load needs to be stopped and determines the cut-off load condition LOFF (step 435).

44は投入/しゃ断対象決定手段で、前記負荷量決定手
段43にて決定された狗荷iLiまたはり。N、LOF
Fおよび予め各負荷毎に設定した優先順位等に基づいて
投入またはしゃ断対象負荷を決定する。
Reference numeral 44 denotes input/cutoff target determining means for determining the load iLi or the amount determined by the load amount determining means 43. N.LOF
The load to be turned on or cut off is determined based on F and priorities etc. set for each load in advance.

この処理は各負荷群26 、29 、30毎に行う。従
って第6図で示すように、各負荷群用のカウンタjをク
リアする(ステップ441)。次に処理を行うj番目の
負荷群か、前記トリップ発生系統から給電されていた負
荷群か否かを判定する(ステップ442)。この負荷群
が仮にトリップ系統から給電されていた負荷群である場
合は、その負荷群の各負荷毎に予め設定しである優先度
およびしゃ断許可/不許可条件を基に、前記限界負荷1
HLi内に抑えるためのしゃ断負荷容量に相当する容量
の負荷を、しゃ断対象として決定する(ステップ443
)。
This process is performed for each load group 26, 29, and 30. Therefore, as shown in FIG. 6, the counter j for each load group is cleared (step 441). Next, it is determined whether it is the j-th load group to be processed or the load group that has been supplied with power from the trip generation system (step 442). If this load group is a load group that has been supplied with power from the trip system, the limit load 1
A load whose capacity corresponds to the cutoff load capacity to be suppressed within HLi is determined as the load to be cut off (step 443
).

これに対し、j番目の負荷群が、トリップ発生系統の負
荷群でない場合は、その負荷群(ブロックともいう)の
限界電力や、優先度および前述の投入負荷it LoN
またはしゃ断食荷量LOFFに従って投入対象またはし
ゃ断対象を決定する(ステップ444、445.446
 )。ここで、投入またはしゃ断対象と決定された機器
には、1機器/1ビットで要求マークをセットしておく
。これらの決定後、カウンタjをインクリメントしくス
テップQ7)、全ての負荷群について処理を実行したか
を判定しくステップ448L末だであればステップ44
2に戻シ、済であれば終了する。
On the other hand, if the j-th load group is not the load group of the trip generation system, the limit power of that load group (also called block), the priority, and the input load it LoN
Alternatively, the input target or the shutoff target is determined according to the shutoff load amount LOFF (steps 444, 445, and 446).
). Here, a request mark is set for the devices determined to be turned on or cut off, with 1 device/1 bit. After these decisions are made, the counter j is incremented in step Q7), and it is determined whether the processing has been executed for all load groups.If it is the end of step 448L, step 44
Return to step 2, and if done, exit.

45は投入/しゃ断信号出力手段で、前記投入/しゃ断
対象決定手段44にて決定された対象機器毎にセットさ
れている要求ビットを取り出し、該当する機器に、投入
またはしゃ断指令を出力する。
Reference numeral 45 denotes an on/off signal output means, which takes out the request bit set for each target device determined by the on/off target determining means 44 and outputs an on/off command to the corresponding device.

ここで、上記出力に当っては、トリップ発生(二よる負
荷しゃ断の方がスピードを要求されるため。
Here, regarding the above output, a trip occurs (because the two-way load shedding requires more speed).

第7図で示すように、まずトリップ発生による負荷しゃ
断か否かを判定する(ステップ451)。トリップ発生
によるものであれば前記要求ビットを取シ出しくステッ
プ452)、該当する機器にしゃ断指令を出力する(ス
テップ453)。その後、各負荷群毎に処理を行うため
、負荷群用のカウンタjをクリアする(ステップ454
)。そして3番目の負荷群につき、トリップ発生系統に
ょカ給電されていた負荷群か否かを判定しくステップ4
55)トリップ発生に無関係の負荷群であれば、要求ビ
ットを取シ出しくステップ456)、該当する機器に投
入またはしゃ断指令を出力する(ステップ457)。上
記出力後カウンタjをインクリメントしくステップ45
8 )、全ての負荷群について処理を終だかを判定する
(ステップ459)。その結果床だであればステップ4
55に戻シ、済であれば終了する。なお、ステップ45
5の判定で、トリップ発生系統から給電を受けていた負
荷群と判定(N)した場合は、この負荷群は全に処理さ
れているため・ステップ455に飛ぶ。
As shown in FIG. 7, first, it is determined whether the load is cut off due to the occurrence of a trip (step 451). If it is due to the occurrence of a trip, the request bit is extracted (step 452), and a shutoff command is output to the corresponding device (step 453). After that, in order to process each load group, the load group counter j is cleared (step 454).
). Then, for the third load group, it is determined whether or not the load group was supplied with power from the trip generating system.Step 4
55) If the load group is unrelated to the occurrence of the trip, the request bit is extracted (step 456), and a turn-on or cut-off command is output to the relevant equipment (step 457). After the above output, increment the counter j in step 45.
8), it is determined whether processing has been completed for all load groups (step 459). If the result is the floor, step 4
Return to step 55, and if completed, end. Note that step 45
If it is determined in step 5 that the load group was receiving power from the trip generating system (N), this load group has been completely processed and the process jumps to step 455.

〔発明の効果〕〔Effect of the invention〕

以上のように本発明によればトリップ発生時にオンライ
ン計算にょシ必要な分だけ負荷しゃ断するので事故拡大
を防止しながら工場操業率への影響を少なくできる。ま
た電力デマンド制御と一体化したため、トリップ発生後
も、他のブロックにて操業可能な機器があれば、投入で
きるのでデマンド枠内にて、操業率向上が可能となる。
As described above, according to the present invention, when a trip occurs, the load is cut off by the amount necessary for online calculation, so that it is possible to prevent the spread of accidents and reduce the impact on the factory operating rate. Furthermore, since it is integrated with power demand control, even after a trip occurs, if there is equipment that can be operated in another block, it can be brought in, making it possible to improve the operating rate within the demand framework.

さらに平常時は電力テマンドにより負荷しゃ断及び投入
を行うため、オペレータは対応操作が少なくなり、自動
化、省人化が進むといった効果を生じる。
Furthermore, in normal times, the load is cut off and turned on by power control, which reduces the number of operations required by the operator, resulting in the effects of greater automation and labor savings.

【図面の簡単な説明】[Brief explanation of drawings]

第1図は本発明により制御される電力系統を主体と1−
て示した系統図、第2図は本発明による負荷量制御装置
の一実施例を示すブロック図、第3図、第4図、第5図
、第6図、第7図は本発明の詳細な説明するフローチャ
ートである。 4J ・デマンド監視手段、42トリップ場所割シ出し
手段、43・・・弁荷量決定手段、44・・投入/しゃ
断対象決定手段、 (7317)代理人 弁理士側 近 憲 佑 (ほか1
名)第1図 第3図4を 第4図 第5図 第6図
Figure 1 mainly shows the power system controlled by the present invention and 1-
2 is a block diagram showing an embodiment of the load amount control device according to the present invention, and FIGS. 3, 4, 5, 6, and 7 are details of the present invention. This is a flowchart explaining the process. 4J - Demand monitoring means, 42 Trip location determining means, 43... Valve load determining means, 44... Turning on/shutoff target deciding means, (7317) Agent: Kensuke Chika, patent attorney (and 1 more)
Figure 1 Figure 3 Figure 4 Figure 4 Figure 5 Figure 6

Claims (1)

【特許請求の範囲】[Claims] 互いに異なる複数の電源系統の並列運転によシ、複数の
負荷からなる負荷群に対して電力を供給する際の負荷量
制御装置において、前記複数の電力系統のいずれか一方
の需要電力量を入力しこれを設定値と比較するデマンド
監視手段と、前記複数の電力系統のいずれかにトリップ
が発生した場合そのトリップ発生系統がどれかを割)出
すトリップ場所割シ出し手段と、上記トリップ発往時そ
のトリップ発生系統から給電されていた負荷群の限界負
荷量をその負荷群に対する残ルの電源系統答量を基に決
定しかつトリップが発生していない場合はデマンド監視
装置の比較結果に基づきその需要電力量を前記設定値に
近づけるためのしゃ断負荷量または投入負荷量を決定す
る負荷量決定手段と、この負荷量決定手段によシ決定さ
れた負荷蓋を満足すべくしゃ断対象負荷または投入対象
負荷を決定する手段とを備えた負荷量制御装置。
For parallel operation of a plurality of power supply systems that are different from each other, in a load amount control device when supplying power to a load group consisting of a plurality of loads, the amount of power demanded by one of the plurality of power supply systems is inputted. demand monitoring means for comparing this with a set value; trip location determining means for determining which system the trip occurred in when a trip occurs in any of the plurality of power systems; The limit load amount of the load group that was supplied with power from the trip generation system is determined based on the remaining power supply system response capacity for that load group, and if no trip has occurred, the limit load amount is determined based on the comparison result of the demand monitoring device. Load amount determining means for determining a cutoff load amount or input load amount to bring the demand power amount close to the set value, and a load to be cut off or input load to satisfy the load lid determined by the load amount determination means. A load amount control device comprising means for determining a load.
JP59029477A 1984-02-21 1984-02-21 Load amount controller Pending JPS60176426A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP59029477A JPS60176426A (en) 1984-02-21 1984-02-21 Load amount controller

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP59029477A JPS60176426A (en) 1984-02-21 1984-02-21 Load amount controller

Publications (1)

Publication Number Publication Date
JPS60176426A true JPS60176426A (en) 1985-09-10

Family

ID=12277164

Family Applications (1)

Application Number Title Priority Date Filing Date
JP59029477A Pending JPS60176426A (en) 1984-02-21 1984-02-21 Load amount controller

Country Status (1)

Country Link
JP (1) JPS60176426A (en)

Similar Documents

Publication Publication Date Title
CN110783946B (en) Method for locating phase faults in a microgrid
Fouad et al. Dynamic security assessment practices in North America
Billinton et al. Composite generation and transmission system adequacy evaluation including protection system failure modes
Allen et al. Flexible high-speed load shedding using a crosspoint switch
JP4203030B2 (en) Power system step-out separation method and apparatus
Yunus et al. A combined zone-3 relay blocking and sensitivity-based load shedding for voltage collapse prevention
JP2003061247A (en) Device for calculating section load in distribution line
JPS60176426A (en) Load amount controller
JP4046674B2 (en) Distribution system protection system
Bostwick et al. Relay protection of tapped transmission lines
JP2007159188A (en) Power reception/distribution supervisory control system and its method
Malozyomov et al. Improvement of method of setting digital protection devices in straight dc power networks
CN207475174U (en) A kind of coincidence brake control device of breaker
JP2008278662A (en) Bus protective relaying device
Hill et al. Upgrading power system protection
JPH0728505B2 (en) Automatic control system for power distribution equipment
JP2645013B2 (en) Power system accident recovery system
JPH0454828A (en) Distribution system facility schedule assisting system
KR200347633Y1 (en) Hardware structure of intelligent electronic device for fault detection and selective auto-reclosure
Malozyomov et al. Digital protection systems in DC networks
Thararak et al. Research Article Implementation of Optimal Protection Coordination for Microgrids with Distributed Generations Using Quaternary Protection Scheme
Castillo et al. Systems interconnection and voltage stability protection schemes increase power transfer limits and prevent regional blackouts at Panama's transmission system
JPS60128830A (en) Load selection breaking unit
JPH02136044A (en) Station bus switching control system
JPH0779532A (en) Method and unit for protecting ac/dc converter