JPS60128830A - Load selection breaking unit - Google Patents

Load selection breaking unit

Info

Publication number
JPS60128830A
JPS60128830A JP58236843A JP23684383A JPS60128830A JP S60128830 A JPS60128830 A JP S60128830A JP 58236843 A JP58236843 A JP 58236843A JP 23684383 A JP23684383 A JP 23684383A JP S60128830 A JPS60128830 A JP S60128830A
Authority
JP
Japan
Prior art keywords
power
load
trip
cutoff
input
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP58236843A
Other languages
Japanese (ja)
Inventor
金井 治樹
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Toshiba Corp
Original Assignee
Toshiba Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Toshiba Corp filed Critical Toshiba Corp
Priority to JP58236843A priority Critical patent/JPS60128830A/en
Publication of JPS60128830A publication Critical patent/JPS60128830A/en
Pending legal-status Critical Current

Links

Landscapes

  • Supply And Distribution Of Alternating Current (AREA)

Abstract

(57)【要約】本公報は電子出願前の出願データであるた
め要約のデータは記録されません。
(57) [Summary] This bulletin contains application data before electronic filing, so abstract data is not recorded.

Description

【発明の詳細な説明】 〔発明の技術分野〕 本発明は並列運転される買電系統と自家発電系統から負
荷群へ電力を供給する電力系統において、特に系統運転
用状態に応じたきめ細かな負荷しゃ断を行ない得るよう
にした負荷選択しゃ断装置に関する。
[Detailed Description of the Invention] [Technical Field of the Invention] The present invention relates to a power system that supplies power to a load group from a power purchase system and a private power generation system that are operated in parallel, and in particular, to provide detailed load control according to the system operation status. The present invention relates to a load selective cutoff device that can perform cutoff.

〔発明の技術的背景〕[Technical background of the invention]

近年電力系統においては、負荷群に対する信頼性の高い
電力供給を確保するため、買電系統と自家発電系統とを
並列運転して運用することが行なわれている。
In recent years, in electric power systems, in order to ensure highly reliable power supply to load groups, power purchasing systems and private power generation systems have been operated in parallel.

第1図は、この種の電力系統の構成例を示したものであ
る。図において、1,2は1号、2号の各変圧器で、そ
の1次側は変圧器1次しゃ断器3,4を介し、さらに買
電系しゃ断器5および同断路器6を介して図示しない送
電線に接続されている。一方、7,8は1号、2号の各
自家発電機で、その出力端は発電機しゃ断器9゜10を
介して母線11.12に夫々接続されている。
FIG. 1 shows an example of the configuration of this type of power system. In the figure, 1 and 2 are transformers No. 1 and No. 2, and their primary side is connected via transformer primary circuit breakers 3 and 4, and further through power purchase system circuit breaker 5 and power purchase system circuit breaker 6. It is connected to a power transmission line (not shown). On the other hand, 7 and 8 are private generators No. 1 and No. 2, the output ends of which are respectively connected to bus bars 11 and 12 via generator circuit breakers 9 and 10.

また、上記1号、2号変圧器1,2の2次側は、変圧器
2次しゃ断器13.14、連糸しゃ断器15.16およ
び17.18を介し、これより母線断路器19.20を
介して母線11に、かつ母線断路器21.22を介して
母線12に夫々接続されている。さらに、上記母線11
゜12は母線断路器23.24により連系され、この各
断路器23.24間には負荷群しゃ断器25を介して第
1の負荷群26が接続されている。さらにまた、上記変
圧器2次しゃ断器13および14と連系しゃ断器15お
よび16との間には、負荷群しゃ断器27および28を
介して第2および第3の負荷群29および30が接続さ
れている。なお図において、・、−は投入状態、01口
は開放状態にあることを夫々表わすものである。また、
上記各負荷群26.29゜30は夫々複数の負荷より成
るものである。
Further, the secondary side of the No. 1 and No. 2 transformers 1 and 2 is connected to the busbar disconnector 19. 20 to the busbar 11 and via busbar disconnectors 21, 22 to the busbar 12, respectively. Furthermore, the bus bar 11
12 are interconnected by bus disconnectors 23 and 24, and a first load group 26 is connected between each of these disconnectors 23 and 24 via a load group breaker 25. Furthermore, second and third load groups 29 and 30 are connected between the transformer secondary circuit breakers 13 and 14 and the grid circuit breakers 15 and 16 via load group circuit breakers 27 and 28. has been done. In the figure, . and - represent a closed state, and port 01 represents an open state, respectively. Also,
Each of the load groups 26.29.30 is composed of a plurality of loads.

さてかかる構成において、買電系統と自家発電系統とを
並列運転して各負荷群26,29゜30に電力を供給し
ている状態で、ある特定の機器に故障が起ってトリップ
が発生した場合には、図示しないシーケンス回路により
予め決められた個別機器のトリップによる負荷しゃ断A
?ターンを基に負荷しゃ断を行なって、系統下の2次波
及停電を避けるようにしている。つまり、例えばいま1
号変圧器1に故障が起ってその1次しゃ断器3がトリッ
プされた場合には、当該故障機器に連系されている負荷
群しゃ断器27をしゃ断して第2の負荷群29をしゃ断
するようにしている。
Now, in this configuration, while the power purchase system and the private power generation system are operating in parallel to supply power to each load group 26, 29, 30, a failure occurs in a particular piece of equipment and a trip occurs. In some cases, load cutoff A is performed by tripping individual equipment predetermined by a sequence circuit (not shown).
? Load shedding is performed based on turns to avoid secondary ripple power outages in the grid. In other words, for example, now 1
When a failure occurs in the No. 1 transformer 1 and its primary breaker 3 is tripped, the load group breaker 27 connected to the failed equipment is disconnected and the second load group 29 is disconnected. I try to do that.

〔背景技術の問題点〕[Problems with background technology]

然乍ら、この場合には)IJ、f発生時の現在負荷容量
を考慮に入れず負荷しゃ断パターンに基づく負荷しゃ断
を行なっていることから、場合によっては余剰電力があ
るにもかかわらず必要以上に負荷をしゃ断してしまい、
当該負荷運転の停止によって工場操業等に悪影曽を及ぼ
す恐れがある。
However, in this case) load shedding is performed based on the load shedding pattern without taking into account the current load capacity at the time of IJ, f occurrence, so in some cases even though there is surplus power, more than necessary power is used. I cut off the load,
There is a risk that the suspension of the load operation will have a negative impact on factory operations, etc.

〔発明の目的〕[Purpose of the invention]

本発明は上記のような問題を解決するために成されたも
ので、その目的は系統連用状態に応じた必要十分な負荷
しゃ断を行ない系統下の操業への影暢を最少限とし、か
つ系統下の2次波及停電を防止することが可能な負荷選
択しゃ断装置を提供することにある。
The present invention was made in order to solve the above-mentioned problems, and its purpose is to perform necessary and sufficient load shedding according to the grid connection status, minimize the impact on the operation under the grid, and It is an object of the present invention to provide a load selection breaker capable of preventing secondary spillover power outages.

〔発明の概要〕[Summary of the invention]

上記目的を達成するために本発明では、前述した電力系
統におけるトリップ故障発生時に、トリップ系統下のト
リップ直前の全負荷電力から残りの正常機器でまかなえ
る保持容量を差引いた過負荷容量分の負荷を予定の優先
度に従って順次しゃ断することにより、系統運用状態に
見合った負荷選択しゃ断を行なうようにしたことを特徴
とする。
In order to achieve the above object, in the present invention, when a trip failure occurs in the power system described above, the load is calculated by subtracting the holding capacity that can be covered by the remaining normal equipment from the full load power immediately before the trip under the trip system. The system is characterized in that the load is selectively cut off in accordance with the system operation status by sequentially cutting off the load according to the scheduled priority.

〔発明の実施例〕[Embodiments of the invention]

以下、本発明を図面に示す一実施例について説明する。 Hereinafter, an embodiment of the present invention shown in the drawings will be described.

第2図は、本発明を前述した第1図の電力系統に適用し
た場合の構成例を示すものであり、第1図と同一部分に
は同一符号を付してその説明を省略し、ここでは異なる
部分についてのみ述べる。
FIG. 2 shows an example of the configuration when the present invention is applied to the power system shown in FIG. 1, and the same parts as in FIG. Now, I will only discuss the different parts.

図において、31′は本発明の負荷選択しゃ断装置であ
り、前記電力系統からその計測値入力(アナログ量)A
および状態、故障入力(デジタル量)Bを入力し、かつ
電力系統に対゛してし中断出力Cを出力するようにして
いる。ここで、計測値入力Aとしては1号、2号変圧器
1,2の出力である買電々力、1号、2号自家発電機7
.8の発電々力である自家発電々力、および各負荷電力
を人力し、また状態、故障人力Bとしてはしゃ断器、断
路器機器運転(開、閉)状態入力、トリップ故障入力(
リレー出力)を夫夫人力するものである。
In the figure, 31' is a load selection cutoff device of the present invention, and its measurement value input (analog amount) A
, status, and fault input (digital quantity) B are input, and an interruption output C is outputted to the power grid. Here, as the measured value input A, the purchased power which is the output of the No. 1 and No. 2 transformers 1 and 2, the No. 1 and No. 2 private generators 7
.. In-house power generation power, which is the power generation power in step 8, and each load power are manually generated, and the state and failure power B are inputs of circuit breaker and disconnector device operation (open, close) status inputs, and trip failure inputs (
relay output).

第3図は、上記負荷選択しゃ断装置31の構成例を機能
ブロック図にて示したものである。
FIG. 3 shows a functional block diagram of an example of the configuration of the load selection cutoff device 31.

図において、32は上記計測値入力Aおよび状態、故障
人力Bを一定周期で入力処理する入力処理手段、33は
この入力処理手段32により入力される計測値人力Aと
、状態、故障人力Bの中の状態入力との内容のうち最新
のものを順次更新記憶すると共に、上記1号、2号変圧
器1.2および1号、2号自家発電機7,8の各管理限
界値を予め格納する記憶手段である。ここで、状態人力
Bによる断路器およびしゃ断器の運転(開、閉)状態の
組み合せを基に、各負荷群26.29.30への電力供
給パターンを予め決定しておく。
In the figure, 32 is an input processing means for inputting and processing the measured value input A, the state, and the faulty human power B at a constant cycle, and 33 is the input processing means for inputting the measured value input A, the state, and the faulty human power B input by this input processing means 32. The latest status input contents are sequentially updated and stored, and each control limit value of the above-mentioned No. 1 and No. 2 transformers 1.2 and No. 1 and No. 2 private generators 7 and 8 is stored in advance. It is a storage means for Here, the power supply pattern to each load group 26, 29, and 30 is determined in advance based on the combination of the operating state (open, closed) of the disconnector and the circuit breaker by the state human power B.

また、34は上記入力処理手段32からの故障入力(ト
リップ故障入力)を検知した場合に、当該トリップによ
ってどの機器(変圧器、自家発電機)が影響を受けるか
を検索するトリップ系統検索手段である。35は、この
トリップ系統検索手段34により検索されたトリップ系
統下のトリップ直前の全負荷電力を、上記記憶手段33
に記憶された内容を基に算出する負荷電力算出手段であ
る。36は、上記トリップ系統検索手段34により検索
されたトリップ系統下の残り機器(変圧器、自家発電機
)でまかなえる保持容量(電力量)を、上記記憶手段に
格納された内容を基に算出する保持容量算出手段である
Further, 34 is a trip system search means for searching which equipment (transformer, private generator) is affected by the trip when a fault input (trip fault input) from the input processing means 32 is detected. be. 35 stores the full load power immediately before the trip under the trip system searched by the trip system search means 34 in the storage means 33.
This is load power calculation means that calculates based on the contents stored in the. 36 calculates the holding capacity (power amount) that can be covered by the remaining equipment (transformer, private generator) under the trip system searched by the trip system search means 34, based on the content stored in the storage means. This is a holding capacity calculation means.

さらに、37は上記負荷電力算出手段35にて算出され
た全負荷電力と、上記保持容量算出手段36にて算出さ
れた保持容量との差分により過負荷容量を算出する過負
荷容量算出手段である。38はこの過負荷容量算出手段
37にて算出された過負荷容量を基に、これに見合った
しゃ断容量となるように上記トリップ系統下の負荷群の
中から予め定められたしゃ断優先度に従ってしゃ断対象
負荷を決定するしゃ断対象決定手段である。39は、こ
のしゃ断対象決定手段38にて決定された該当負荷に対
してしゃ断出力Cを出力する出力処理手段である。
Furthermore, 37 is an overload capacity calculation means for calculating an overload capacity based on the difference between the total load power calculated by the load power calculation means 35 and the holding capacity calculated by the holding capacity calculation means 36. . Based on the overload capacity calculated by the overload capacity calculation means 37, 38 performs a breaker according to a predetermined breaker priority from among the load groups under the trip system so that the breaker capacity corresponds to the overload capacity calculated by the overload capacity calculation means 37. This is a cutoff target determining means that determines the target load. Reference numeral 39 denotes an output processing means for outputting a cutoff output C for the load determined by the cutoff target determining means 38.

次に、かかる構成の負荷選択しゃ新装M31ノ作用につ
いて、第4図のフローチャートを用いて述べる。
Next, the operation of the newly installed M31 when selecting a load having such a configuration will be described using the flowchart shown in FIG.

いま、負荷選択しゃ断装置31には電力系統より、その
計測値入力A、状態人力Bがその入力処理手段32を介
して一定周期で入力され、その内容が記憶手段33内に
順次更新して記憶される。
Currently, the measured value input A and the state human power B are inputted to the load selection cutoff device 31 from the power grid at a constant cycle via the input processing means 32, and the contents are sequentially updated and stored in the storage means 33. be done.

かかる状態から、いま例えば電力系統の1号変圧器1が
故障してその1次側しゃ断器3がトリ、プされると、第
4図のステラf81.8:tで入力処理手段32からの
故障人力Bを検知し9− て、当該トリップにより影響を受ける機器が1号発電機
7であることが検索される。すると、つぎにステップS
3で負荷電力算出手段35により、記憶手段33の内容
から上記トリップ系統下のトリップ直前の全負荷電力L
(ここでは第2の負荷群29の全負荷電力)が算出され
る。
In such a state, if, for example, the No. 1 transformer 1 of the power system fails and its primary side breaker 3 is tripped, the output from the input processing means 32 at Stella f81.8:t in FIG. When the faulty human power B is detected, it is searched that the equipment affected by the trip is the No. 1 generator 7. Then, step S
3, the load power calculation means 35 calculates the total load power L immediately before the trip under the trip system from the contents of the storage means 33.
(here, the total load power of the second load group 29) is calculated.

また、ステップS4で保持容量算出手段36により、記
憶手段33の内容から上記トリップ系統下の残り機器で
まかなえる保持容量LH(ここでは1号自家発電機7の
管理限界値)が算出される。さらに、ステラfs5で過
負荷容置算出手段32により、上記全負荷電力りと保持
容量LHとの差分(L −LH)である過負荷容量り、
が算出され、しゃ断容量(= Lc)が決定される。
Further, in step S4, the holding capacity calculation means 36 calculates the holding capacity LH (here, the control limit value of the No. 1 private generator 7) that can be covered by the remaining equipment under the trip system from the contents of the storage means 33. Furthermore, in Stella fs5, the overload capacity calculating means 32 calculates the overload capacity, which is the difference (L - LH) between the full load power and the holding capacity LH.
is calculated, and the breaking capacity (=Lc) is determined.

次に、しゃ断対象決定手段38により上記し中断容量り
、となるように、上記トリップ系統下の負荷群(ここで
は第2の負荷群29)の中から予定のしゃ断優先度に従
ってしゃ断対象負荷が決定される。すなわち、まずステ
、71′S6で初期値を0とし、ステップS7では第5
図に示10− す如き負荷選択しゃ断テーブルを、優先度量が0のもの
からnまでをサーチする。つぎに、ステラf88.89
では五番目の負荷が、運転状態でかつオペレータからの
指示がしゃ断許可になっているかをチェックし、これが
妥当である時はこの1番目の負荷をしゃ断対象として決
定し、また妥当でない時は次ポイントへ移行する。
Next, the load to be cut off is determined by the cutoff target determining means 38 according to the scheduled cutoff priority from the load group under the trip system (in this case, the second load group 29), so that the above-mentioned cutoff capacity is determined. It is determined. That is, first, in step 71'S6, the initial value is set to 0, and in step S7, the fifth value is set to 0.
A load selection cutoff table such as 10- shown in the figure is searched for priority quantities from 0 to n. Next, Stella f88.89
Next, check whether the fifth load is in operation and the instruction from the operator is to allow shutoff. If this is appropriate, this first load is determined to be shut off, and if it is not appropriate, the next load is selected. Move to points.

さらに、ステップSx0.S11では上記過負荷容量L
cから決定された量番目の負荷容量り。
Furthermore, step Sx0. In S11, the above-mentioned overload capacity L
The load capacity of the amount determined from c.

の差分(L、−L、)をめ、しゃ断対象と決定された量
番目の負荷のしゃ断出力が、出力処理手段39を介しし
ゃ断出力Cとして送出され、ステラf812では次ポイ
ントへ移行する。以上の作用は、ステップ813で上記
過負荷容量Lcが量番目負荷しゃ断により満たされる(
0となる)か、若しくはサーチカウンターlがサイズオ
ーバーになる時まで繰り返して行なわれ、この状態とな
った時にステップ814でMTする。
Based on the difference (L, -L,), the cutoff output of the load determined as the cutoff target is sent out as the cutoff output C via the output processing means 39, and the Stellar f812 moves to the next point. The above action is such that the overload capacity Lc is satisfied by the load cutoff in step 813 (
0) or until the search counter l becomes oversized, and when this state is reached, MT is performed in step 814.

上述のようにして負荷しゃ断を実施することにより、系
統の現在負荷容量を考慮して必要十分な過負荷のみをし
ゃ断し、系統下の不要しゃ断が避けられることになる。
By carrying out load shedding as described above, only the necessary and sufficient overload is cut off in consideration of the current load capacity of the grid, and unnecessary cutoffs under the grid can be avoided.

尚、上記において故障人力Bとしては、過電流検出等に
よるリレー出力の他に重故障検知による検知出力等を用
いることもできる。
In addition, in the above, as the failure human power B, in addition to the relay output due to overcurrent detection, etc., a detection output due to serious failure detection, etc. can also be used.

また、負荷電力算出は系統からの計測値入力Aを用いて
行なったが、機器固有の固定値としてもよい。この場合
には、この機器の使用状態(開/閉9運転/停止)と組
み合わせ、閉または運転ならば固有値を、開または停止
ならば0を用いるようにすればよい。
Further, although the load power calculation was performed using the measured value input A from the grid, it may be a fixed value specific to the equipment. In this case, in combination with the usage status of this device (open/closed 9 running/stopped), the characteristic value may be used if it is closed or running, and 0 if it is open or stopped.

〔発明の効果〕〔Effect of the invention〕

以上説明したように本発明によれば、系統のトリップ故
障発生時に、トリップ系統下のトリップ直前の全負荷電
力からの残りの正常機器でまかなえる保持容量を差引い
た過負荷容量分の負荷を予定の優先度に従って順次しゃ
断するようにしたので、系統運用状態に応じた必要十分
な負荷しゃ断を行ない系統下の操業への影豐を最小限と
し、かつ系統下の2次波及停電を確実に防止することが
可能な極めて信頼性の高い負荷選択し中断装置が提供で
きる。
As explained above, according to the present invention, when a trip failure occurs in the grid, the load is calculated by subtracting the holding capacity that can be covered by the remaining normal equipment from the full load power immediately before the trip under the trip system to the scheduled overload capacity. Since the load is cut off sequentially according to the priority, necessary and sufficient load is cut off according to the system operation status, minimizing the impact on the operation under the grid, and reliably preventing secondary spillover power outages under the grid. An extremely reliable load selection and interruption device capable of doing this can be provided.

【図面の簡単な説明】[Brief explanation of the drawing]

第1図は買電系統と自家発電系統から成る電力系統を示
す構成図、第2図は本発明を適用した電力系統を示す構
成図、第3図は本発明の一実施例を示す機能ブロック図
、第4図および第5図は同実施例の作用を説明するため
のフローチャート図およびテーブル図である。 1.2・・・変圧器、3 、4 、5 、9 、10,
13゜74 、7’ s 、 I e 、 J 7 、
 J s 、 z 5r 27128・・・し中断器、
6.19.20.21.22゜23.24・・・新路器
、7.8・・・自家発電機、11.12・・・母線、2
6,29.30・・・負荷群、31・・・負荷選択しゃ
断装置、32・・・入力処理手段、33・・・記憶手段
、34・・・トリップ系統保護手段、35・・・負荷電
力算出手段、36・・・保持容凰算出手段、31・・・
過負荷容量算出手段、38・・・しゃ断対象決定手段、
39・・・出力処理手段。 第4図 トリ・ンフ’ St 四 S2 3 トゝん Lc 55 i=Q S6 シー52″i″ S7 7−フ;°レナ 8 −はりが N V 510 しく=L(Lp 第5図
Fig. 1 is a block diagram showing an electric power system consisting of a power purchasing system and a private power generation system, Fig. 2 is a block diagram showing an electric power system to which the present invention is applied, and Fig. 3 is a functional block diagram showing an embodiment of the present invention. FIG. 4, and FIG. 5 are a flow chart diagram and a table diagram for explaining the operation of the same embodiment. 1.2...Transformer, 3, 4, 5, 9, 10,
13゜74, 7's, Ie, J7,
J s, z 5r 27128... interrupter,
6.19.20.21.22゜23.24... New road equipment, 7.8... Private generator, 11.12... Bus bar, 2
6,29.30...Load group, 31...Load selection breaker, 32...Input processing means, 33...Storage means, 34...Trip system protection means, 35...Load power Calculation means, 36... Retention capacity calculation means, 31...
Overload capacity calculation means, 38... cutoff target determination means,
39...Output processing means. Figure 4 Triumph' St 4 S2 3 TonLc 55 i=Q S6 Sea 52''i'' S7 7-F;

Claims (1)

【特許請求の範囲】 変圧器を有する買電系統と、自家発電機を有する自家発
電系統とを並列運転して複数の負荷群へ電力を供給する
電力系統において、前記変圧器出力、自家発電機発電々
力、各負荷電力等の計測値入力およびしゃ断器、断路器
機器運転状態、トリップ故障等の状態、故障入力を一定
周期で入力処理する入力処理手段と、この入力処理手段
により入力される計測値入力および状態入力の最新の内
容を順次更新記憶すると共に、前記変圧器、1叔発電機
の管理限界値を予め格納する記憶手段と、前記入力処理
手段からの故障入力を検知した場合に、当該トリップ故
障によりどの機器が影譬を受けるか全検索するトリップ
系統検索手段と、このトリップ系統検索手段により検索
された卜1J 、 f系統下のトリップ直前の全負荷電
力を前記記憶手段の内容を基に算出す1− る負荷電力算出手段と、前記トリップ系統検索手段によ
り検索されたトリップ系統下の残り機器でまかなえる保
持容量を前記記憶手段の内容を基に算出する保持容量算
出手段と、前記全負荷電力と保持容量との差分により過
負荷容量を算出する過負荷容量算出手段と、この過負荷
容量を基にこれに見合ったしゃ断容量となるように、前
記トリップ系統下の負荷群の中から予め定められたしゃ
断優先庫に従ってしゃ断対象負荷を決定するしゃ断対象
決定手段と、このしゃ断対象決定手段により決定された
対象負荷に対してしゃ断出力を出力する出力処理手一段
とを具備したことを特徴とする負荷選択しゃ断装置。
[Scope of Claims] In a power system that supplies power to a plurality of load groups by operating a power purchasing system having a transformer and a private power generation system having a private generator in parallel, the output of the transformer and the private power generator are operated in parallel. an input processing means for inputting and processing measured value inputs of power generation power, each load power, etc., operating status of circuit breakers, disconnecting switch equipment, states such as trip failures, and failure inputs at a constant cycle; and input processing means input by the input processing means. a storage means for sequentially updating and storing the latest contents of measured value inputs and status inputs, and storing in advance control limit values of the transformer and the first uncle generator; and when a failure input from the input processing means is detected; , a trip system search means for searching all the devices affected by the trip failure, and the contents of the storage means for storing the full load power immediately before the trip under the 1J, f system searched by the trip system search means. a load power calculation means that calculates the load power based on 1-; a storage capacity calculation means that calculates the storage capacity that can be covered by the remaining equipment under the trip system searched by the trip system search means based on the contents of the storage means; Overload capacity calculation means for calculating overload capacity from the difference between the full load power and the holding capacity; The device is equipped with a cutoff target determining means for determining a load to be cut off in accordance with a predetermined cutoff priority storage, and an output processing means for outputting a cutoff output for the target load determined by the cutoff target determining means. Features a load selection breaker.
JP58236843A 1983-12-15 1983-12-15 Load selection breaking unit Pending JPS60128830A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP58236843A JPS60128830A (en) 1983-12-15 1983-12-15 Load selection breaking unit

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP58236843A JPS60128830A (en) 1983-12-15 1983-12-15 Load selection breaking unit

Publications (1)

Publication Number Publication Date
JPS60128830A true JPS60128830A (en) 1985-07-09

Family

ID=17006612

Family Applications (1)

Application Number Title Priority Date Filing Date
JP58236843A Pending JPS60128830A (en) 1983-12-15 1983-12-15 Load selection breaking unit

Country Status (1)

Country Link
JP (1) JPS60128830A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS6311027A (en) * 1986-03-03 1988-01-18 株式会社東芝 Power system controller
JP2006060885A (en) * 2004-08-18 2006-03-02 Mitsubishi Electric Corp Power distribution system supervisory control system

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS6311027A (en) * 1986-03-03 1988-01-18 株式会社東芝 Power system controller
JP2006060885A (en) * 2004-08-18 2006-03-02 Mitsubishi Electric Corp Power distribution system supervisory control system

Similar Documents

Publication Publication Date Title
Karlsson et al. Wide area system monitoring and control-terminology, phenomena, and solution implementation strategies
BRPI0617832B1 (en) fault protection system and method of providing coordinated fault protection for a distribution line by coupling a source to a load
US5737166A (en) Protective equipment in a bipolar HVDC station
US6671151B2 (en) Network protector relay and method of controlling a circuit breaker employing two trip characteristics
US20220229099A1 (en) Device, system, and method for performing an online-update of a two-port equivalent
JPS60128830A (en) Load selection breaking unit
US20210111586A1 (en) Electric power system transducer failure monitor and measurement recovery
Wagle et al. Concise Definition of the Overcurrent Protection System for CIGRE European Medium Voltage Benchmark Network
Maleki et al. An adaptive and decentralized protection scheme for microgrid protection
Teo A computer aided system to automate the restoration of electrical power supply
JPS6367416B2 (en)
Traqa-de-Almeida Substation interlocking and sequence switching using a digital computer
Ivanković et al. Line differential protection with synchrophasor data in WAMPAC system in control room
Tornqvist et al. Overview of ICT components and its application in electric power systems
KR101900302B1 (en) Judging device for protector's non tripping review point of distribution network with distributed generation
CN112039083B (en) Control method and device for load transfer across bypass buses
Arya et al. Multi-objective fault section estimation in distribution systems using elitist NSGA
JP2021158759A (en) Power receiving and transforming facility capable of changing reception voltage, transformer, and reception voltage changing method
JP2921034B2 (en) System failure section judgment device
Ozdemir et al. A new active failure simulation approach for distribution system reliability assessment
JPS63316617A (en) Faulty facility judging system
JPS6134833Y2 (en)
JPH01174222A (en) Device for recovery from accident in power system
CN111342429A (en) Main transformer equipment protection system
Draber Reliability-oriented design of a distributed control system for high-voltage switchgear stations