JPS60175631A - Building method for retaining wall - Google Patents

Building method for retaining wall

Info

Publication number
JPS60175631A
JPS60175631A JP3296484A JP3296484A JPS60175631A JP S60175631 A JPS60175631 A JP S60175631A JP 3296484 A JP3296484 A JP 3296484A JP 3296484 A JP3296484 A JP 3296484A JP S60175631 A JPS60175631 A JP S60175631A
Authority
JP
Japan
Prior art keywords
retaining wall
steel
concrete
bedrock
forms
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP3296484A
Other languages
Japanese (ja)
Inventor
Susumu Oota
進 太田
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to JP3296484A priority Critical patent/JPS60175631A/en
Publication of JPS60175631A publication Critical patent/JPS60175631A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/02Retaining or protecting walls
    • E02D29/0258Retaining or protecting walls characterised by constructional features
    • E02D29/0275Retaining or protecting walls characterised by constructional features cast in situ

Abstract

PURPOSE:To safely build a retaining wall without excavating a bedrock, by a method wherein an H-steel is erected from a foundation along a bedrock, forms are supported and secured to the H-steel through support holding materials, and concrete is placed between the forms and the bedrock. CONSTITUTION:A foundation groove 11 is excavated in the lower part of the slanted face of slope of a bedrock A, and an H-steel 12, erected along the face of slope of the bedrock A, is disposed and concrete is placed to form a foundation 13. Forms 14 are located outside the H-steel 12, and the H-steel 12 and the forms 14 are secured by means of support holding materials 15. Concrete is poured between the bedrock A and the forms 14, and after the concrete is cured, the forms 14 are removed to build a retaining wall 16. This enables the H-steel to aid in first protection during construction and permits elimination of excavation of a face of slope.

Description

【発明の詳細な説明】 )、 この発明は、山崩れ等の災害を防止するため\ 
に設ける擁壁の構築方法に関するものである。
[Detailed Description of the Invention] ), This invention is aimed at preventing disasters such as landslides\
This article relates to a method of constructing a retaining wall.

山崩れQこよる災害の発生を防止するため、地山の斜面
を擁壁で保護することが行なわれており、擁壁の構築工
法として、もたれ式1法が多く採用されている。
In order to prevent disasters caused by landslides, retaining walls are used to protect the slopes of the ground, and the Lean Type 1 method is often adopted as a construction method for retaining walls.

従来のもたれ式擁壁工法には、第1図シこ示した地山ア
ンカー埋込みによる片面型枠方式と、第2図に示した余
堀掘削による両面型枠方式の、二種がある。
There are two types of conventional leaning retaining wall construction methods: a single-sided formwork method by embedding ground anchors as shown in FIG. 1, and a double-sided formwork method by excavating extra moats as shown in FIG.

前者の片面型枠方式は、地山Aの軟岩にロックアンカー
1を打込み、このアンカー1に連結した支保材2を介し
て型枠3を支持し、型枠3と地山A間Gこコンクリート
を打設することOこよりmm4を構築するものである。
In the former single-sided formwork method, a rock anchor 1 is driven into the soft rock of the ground A, the formwork 3 is supported via the supporting material 2 connected to the anchor 1, and the concrete is placed between the formwork 3 and the ground A. The concrete is to be constructed with a diameter of 0 mm4.

しかし、このような片面型枠方式は、アンカー1の打込
みのだめGこ軟岩が必要になり、軟岩の少ない条件では
施工が行なえないと共に、法勾配が高い場合崩壊の心配
があるため、アンカーGこ強度をもたせなければならな
い。
However, such a single-sided formwork method requires soft rock to drive the anchor 1 into, and construction cannot be carried out in conditions with little soft rock, and there is a risk of collapse if the slope is high. It must have strength.

また、後者の両面型枠方式は、地山Aを適当な量だけ予
掘した後、セパレータ5で間隔を保持した内外型枠6.
7を立て込み、この型枠をサポート8を介して地山Aで
支持した状態で、両型枠間Gこコンクリートを打設して
擁壁4を構築し、型枠6.7を解体した後、擁壁4と地
山Aの間に土砂を埋戻すものである。
In addition, in the latter double-sided formwork method, after pre-excavating the ground A by an appropriate amount, the inner and outer formworks 6 are separated by separators 5.
7 was erected, and this formwork was supported by ground mass A via support 8, concrete was poured between both formworks to construct retaining wall 4, and formwork 6.7 was dismantled. After that, earth and sand is backfilled between the retaining wall 4 and the ground A.

この両面型枠方式は、余堀作業が必要になるため、作業
能率が悪いという問題がある。
This double-sided formwork method has the problem of poor work efficiency because it requires over-drilling work.

また、両方式は共に、通常の作業者に対する保安的な要
素が全くないため、作業中の山崩れによる人身災害があ
とをたたないのが現状であり、山崩れに対して少しでも
安全に作業ができる防止対策の出現が望まれている。
In addition, both methods have no safety elements for ordinary workers, so there are many personal injuries caused by landslides during work, and it is necessary to work as safely as possible against landslides. It is hoped that preventive measures will emerge.

しかも両方式は、型枠の支持に他山を利用するため、地
層や地質の条件によっては施工が困難昏こなると共に、
高い擁壁を構築するには更に工期が長くかかるといった
欠点がある。
Moreover, both types use other mountains to support the formwork, which can make construction difficult and difficult depending on the strata and geological conditions.
The disadvantage is that building a high retaining wall requires a longer construction period.

この発明は、上記のような欠点や問題点を解消するため
になされたものであり、作業の安全性が高く、工期の短
縮化及び施工コストの低減を図ることができる擁壁の構
築方法を提供するのが目的である。
This invention was made in order to eliminate the above-mentioned drawbacks and problems, and provides a method for constructing a retaining wall that has high work safety, shortens the construction period, and reduces construction costs. The purpose is to provide.

この発明の構成は、擁壁構築位置の基礎部分に型鋼を立
て込み、この型鋼を支持体Gこして外側型枠を立て込み
、他山と型枠の間にコンクリートを打設することにより
、型鋼を埋殺しにしたもたれ式擁壁を構築するようにし
たものである。
The structure of this invention is to erect a molded steel into the foundation part of the retaining wall construction position, use this molded steel as a support G to erect the outer formwork, and pour concrete between the other pile and the formwork. A leaning-type retaining wall was constructed by burying the shaped steel.

以下、この発明を添付図面の第3図乃至第6図に示す実
施例に基づいて説明する。
Hereinafter, the present invention will be explained based on the embodiments shown in FIGS. 3 to 6 of the accompanying drawings.

先ず、擁壁を構築したい位置の下部【こ基礎用の溝11
を掘削し、第4図のようOこ、この溝11内から地山A
の傾斜法面Oこ沿って各種型鋼、例えばH型鋼12を配
置し、溝11内にコンクリートを打設することにより、
基礎13を構築してH型鋼12を立て込む。
First, create a groove at the bottom of the location where you want to build the retaining wall [this is the foundation groove 11].
As shown in Figure 4, the ground A is excavated from within this trench 11.
By arranging various types of steel, such as H-shaped steel 12, along the inclined slope O, and pouring concrete into the groove 11,
Build the foundation 13 and erect the H-shaped steel 12.

上記H型鋼12′7よ、構築せんとする擁壁の高さや厚
みGこ応じたものを用いればよく、例えば高さが630
0ffmの擁壁を構築する場合、198×99鯖や20
0X100Wffの断面形状を有し、長さ5mのH型鋼
を、1mの間隔で並べて立て込んで行く。
The above H-shaped steel 12'7 may be used depending on the height and thickness G of the retaining wall to be constructed, for example, the height is 630 mm.
When constructing a retaining wall of 0ffm, 198 x 99 mackerel and 20
H-beams with a cross-sectional shape of 0 x 100 Wff and 5 m in length are placed side by side at 1 m intervals.

次に、H型鋼12群の外側Oこ外側型枠14を配置し、
第5図のように、各型枠14を支保材15でH型鋼12
に固定化することにより、地山Aの傾斜に沿う外側型枠
14を組立てる。
Next, the outer formwork 14 of the 12 groups of H-beam steels is placed,
As shown in FIG. 5, each formwork 14 is
The outer formwork 14 that follows the slope of the ground A is assembled by fixing it to the ground.

この後、第6図のように、外側型枠14と地山Aとの間
Gこ形成された空間内Oこ生コンクリートを打設し、コ
ンクリート凝固後に型枠14を解体すれば、第3図に示
すようQこ、地山Aの傾斜面にもたれた擁壁16ができ
上や。
After that, as shown in Fig. 6, fresh concrete is placed in the space formed between the outer formwork 14 and the ground A, and after the concrete solidifies, the formwork 14 is dismantled. As shown in the figure, a retaining wall 16 leaning against the slope of the ground A has been completed.

前記H型鋼12は、擁壁16の内部に埋殺しの状態にな
り、擁壁16の補強材となる。
The H-shaped steel 12 is buried inside the retaining wall 16 and serves as a reinforcing material for the retaining wall 16.

なお、H型鋼12は市販されている長さが大官5〜10
m+こなっているので、この長さよりも高い擁壁16を
構築するには、前記の工程を第1段階とし、型枠14の
上部外側【こステージ足場を組み、H型鋼12の上端に
新たなH型鋼を溶接やボルト止によって継足したのち、
外側型枠を組立てて第2段目のコンクリートを打設すれ
ばよい。
In addition, the commercially available length of H-shaped steel 12 is 5 to 10 mm.
m+, so in order to construct a retaining wall 16 higher than this length, the above process should be the first step. After adding H-shaped steel by welding or bolting,
All you have to do is assemble the outer formwork and pour the second stage of concrete.

ま1こ、第5図に示すように、作業時の安全性をより向
上させるため、地山Aの法面に金網17やワイヤーを張
設すると共Qこ、法面に沿って配置するH型鋼12と法
面の間に支持部材18を介在させ、H型鋼12の配置作
業が容易に行なえるようをこしてもよい。
As shown in Fig. 5, in order to further improve safety during work, wire mesh 17 and wires are stretched on the slope of the ground A, and wire meshes 17 and wires are placed along the slope. A support member 18 may be interposed between the steel section 12 and the slope to facilitate the placement of the H section steel 12.

以上のように、この発明によると、上記のような構成で
あるので、以下に列挙する効果がある。
As described above, according to the present invention, since it has the above configuration, it has the following effects.

(1)先ず型鋼を立て込み、この型鋼を支持体として組
立てた型枠と地山との間にコンクリートを打設して擁壁
を構築するようQこしたので、立込んだ型鋼が山崩れに
対する第1次防護となり、特に下段部での作業Qこ対し
ては山崩れに対する不安感が軽減でき、万一の場合、型
鋼Qこすがるなりよじ登るなり、待避場所が確保できる
(1) First, we erected the shaped steel and used the shaped steel as a support to place concrete between the assembled formwork and the ground to construct a retaining wall. This provides the first level of protection, and can reduce anxiety about landslides, especially when working at the lower level, and in the event of an emergency, you can secure a place to evacuate by scraping or climbing over the shaped steel.

(2)型鋼を埋殺しQこするので、荷重支持強度の優れ
た擁壁を構築することができる。
(2) Since the shaped steel is buried and Q-rubbed, a retaining wall with excellent load-bearing strength can be constructed.

(3) 地山の法面゛Qこ何ら掘削を行なう必要がない
ので、風化岩、硬岩、土砂等、地質に何ら関係なく擁壁
を構築することができる。
(3) Since there is no need to excavate the slope of the ground, a retaining wall can be constructed regardless of the geology, such as weathered rock, hard rock, earth and sand.

(4)型鋼の立て込み後に型枠を組立て、型枠と地山間
にコンクリートを打設するようにしたので、使用する資
材が少なくて済み、施工能率も大幅に向上する。
(4) Since the formwork is assembled after the form steel is erected and concrete is poured between the formwork and the ground, fewer materials are used and construction efficiency is greatly improved.

ちなみOこ、同一形状の擁壁において従来の地山アンカ
ー埋込による片面型枠方式は28日、余掘り掘削方式は
21の日数を要したものが、この発明の構築方法では1
3日で完成させることができた。
By the way, for retaining walls of the same shape, the conventional one-sided formwork method by embedding ground anchors took 28 days, and the extra excavation method took 21 days, but with the construction method of this invention, it took only 1 day.
I was able to complete it in 3 days.

(5)工期の短縮化により、労働力の削減が可能になり
、施エコヌトの大幅なコストダウンが実現できる。
(5) By shortening the construction period, it is possible to reduce the labor force, and a significant cost reduction can be achieved.

【図面の簡単な説明】[Brief explanation of drawings]

第1図と第2図は従来の施工方法の異なった例を示す縦
断面図、第3図はこの発明の施工方法によって構築した
擁壁の縦断面図、第4図と第5図及び第6図は同上の施
工順序を示す工程図である。 12・H型鋼、13 基礎、14・・外側型枠、15・
・・支保材、16・・・擁壁 特許出願人 太 1) 進 同 代理人 鎌 1)文 二 第1図
Figures 1 and 2 are vertical cross-sectional views showing different examples of conventional construction methods, Figure 3 is a vertical cross-sectional view of a retaining wall constructed using the construction method of the present invention, Figures 4, 5, and Figure 6 is a process diagram showing the construction order of the same as above. 12. H-shaped steel, 13. Foundation, 14..Outer formwork, 15.
...Shoring material, 16...Retaining wall patent applicant Tai 1) Shindo Agent Kama 1) Bun 2 Figure 1

Claims (1)

【特許請求の範囲】[Claims] 擁壁を構築せんとする位置の基礎部に型鋼を、立て込み
、この型鋼を支持体Qこして外側型枠を組立て、次に地
山と外側型枠の間にコンクリートを打設して型鋼を埋殺
しにした擁壁を形成することを特徴とする擁壁の構築方
法。
A steel mold is built into the foundation at the location where the retaining wall is to be constructed, and this steel mold is passed through the support Q to assemble the outer formwork.Next, concrete is poured between the ground and the outer formwork, and the steel mold is assembled. A method for constructing a retaining wall characterized by forming a retaining wall in which the retaining wall is completely buried.
JP3296484A 1984-02-22 1984-02-22 Building method for retaining wall Pending JPS60175631A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP3296484A JPS60175631A (en) 1984-02-22 1984-02-22 Building method for retaining wall

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP3296484A JPS60175631A (en) 1984-02-22 1984-02-22 Building method for retaining wall

Publications (1)

Publication Number Publication Date
JPS60175631A true JPS60175631A (en) 1985-09-09

Family

ID=12373596

Family Applications (1)

Application Number Title Priority Date Filing Date
JP3296484A Pending JPS60175631A (en) 1984-02-22 1984-02-22 Building method for retaining wall

Country Status (1)

Country Link
JP (1) JPS60175631A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2018053592A1 (en) * 2016-09-23 2018-03-29 Dome Consulting Australia Pty Ltd Method of constructing a retaining wall

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2018053592A1 (en) * 2016-09-23 2018-03-29 Dome Consulting Australia Pty Ltd Method of constructing a retaining wall

Similar Documents

Publication Publication Date Title
US6280121B1 (en) Reinforced retaining wall
US5582492A (en) Method and apparatus for an anchored earth restraining wall
CN111560962A (en) Backfill area foundation pit supporting structure and construction method thereof
US6616380B1 (en) Subterranean structures and methods for constructing subterranean structures
JP2000008394A (en) Construction method for underground structure such as underground pit for installation of parking lot
KR100289256B1 (en) Tunnel construction method in shallow toffee area
JP2000265484A (en) CONSTRUCTION METHOD FOR UNDERGROUND STRUCTURE BY PCa PILE UNDERGROUND WALL
JP2000352296A (en) Method o constructing passage just under underground structure
JPS60175631A (en) Building method for retaining wall
JP2000144769A (en) Method of landslide protection work for preparing housing lot
JPH0559728A (en) Sheathing work above underground structure
JP2554507B2 (en) Underground space construction method
JPS5851092B2 (en) Earth retaining installation method using advance shoring frame
JPH04115024A (en) Sheathing method
JP2523234B2 (en) Anchor retaining wall
CN111648375B (en) Inner supporting structure based on shear wall as support
JPH01315520A (en) Underground outer wall constructing method for superstructure
JPS6286242A (en) Reverse casting consttructin method
JP3613618B2 (en) Construction method of leaning type retaining wall consisting of foundation bottom plate of horizontal pile.
JP2658692B2 (en) Earth retaining method for deep excavation
JPS6272817A (en) Construction of retaining wall concurrently serving as sheathing
JPS59233028A (en) Residential land formation work on sloped ground
JP2663085B2 (en) Construction method of spiral underground structure
JPH05140940A (en) Sheathing method in large depth excavation
JPS6172126A (en) Method of building protection wall body