JPS5985042A - Continuous vertical soil discharger - Google Patents
Continuous vertical soil dischargerInfo
- Publication number
- JPS5985042A JPS5985042A JP57193599A JP19359982A JPS5985042A JP S5985042 A JPS5985042 A JP S5985042A JP 57193599 A JP57193599 A JP 57193599A JP 19359982 A JP19359982 A JP 19359982A JP S5985042 A JPS5985042 A JP S5985042A
- Authority
- JP
- Japan
- Prior art keywords
- sand
- earth
- soil
- chain
- strut
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02F—DREDGING; SOIL-SHIFTING
- E02F7/00—Equipment for conveying or separating excavated material
Landscapes
- Engineering & Computer Science (AREA)
- Mining & Mineral Resources (AREA)
- Civil Engineering (AREA)
- General Engineering & Computer Science (AREA)
- Structural Engineering (AREA)
Abstract
Description
【発明の詳細な説明】
本発明は垂直掘削工事、特に大規模の竪穴掘削等におい
て地盤面下を連続的に掘削し、その掘削土砂を連続的に
地表に排出する連続垂直排土装置
削排土装置に関する。Detailed Description of the Invention The present invention is a continuous vertical earth removal device that continuously excavates below the ground surface in vertical excavation work, especially large-scale vertical hole excavation, and continuously discharges the excavated soil to the ground surface. Concerning soil equipment.
従来地下掘削工事において掘削土砂を垂直に地上に搬出
するには一般にパケットエレベータが広く用いられてい
るが、これは下部土砂積載部と垂直搬送部と上部土砂排
出部を鉄骨等で一体構造に組立て、これを掘削現場に設
置し掘削土砂を下部土砂積載部に投入1−1回動するチ
ェーンに一定間隔で取付けられたパケットで連続的に地
上に搬送1.上部土砂排出部で排出部る構造のものであ
る。この構造の垂直搬送装置は地下鉄道工事や下水道工
事等のど2〈−宇の深度で水平に掘削が行われる場合に
は装置の変更なく工事の継続が可能で便利であるが、大
規模構造物の基礎工事等のように大深度の地盤掘下げを
行う場合には地盤の掘下げに伴って垂直搬送部を下部に
継足し延長1.これと共に下部土砂積載部も下部に移設
しなければならない。従来この継足しは垂直搬送部を一
時吊持i−下部土砂積載部を取外し別の場所に仮置し、
垂直搬送部構造を継足し再び下部土砂積載部を取付ける
等の方法が行われ、この為大きな労力を要し、又掘削工
事の中断等労力、時間の損失、工事費の増大を招いてい
た。Conventionally, packet elevators have been widely used in underground excavation work to transport excavated soil vertically to the surface, but these elevators have a lower earth loading section, a vertical transport section, and an upper earth discharge section assembled into an integrated structure using steel frames, etc. This is installed at the excavation site, and the excavated soil is loaded into the lower soil loading section and transported to the ground continuously by packets attached at regular intervals to a chain that rotates 1-1. The structure is such that the upper sediment discharge section is the discharge section. This structure of vertical conveying equipment is useful when horizontal excavation is being carried out at a depth of 2㎜, such as underground railway construction or sewerage construction, because it allows construction to continue without changing the equipment, but it is useful for large-scale structures. When excavating the ground to a great depth, such as in foundation work, a vertical conveyor section is added to the lower part of the ground as the ground is excavated.1. At the same time, the lower earth and sand loading section must also be relocated to the lower part. Conventionally, this replenishment involves temporarily suspending the vertical conveying section, removing the lower earth and sand loading section, and temporarily placing it in another location.
Methods such as adding the vertical conveying section structure and reattaching the lower earth and sand loading section have been used, which requires a large amount of labor and also causes a loss of labor, time, and increased construction costs due to interruptions in excavation work.
これらの諸問題を解消すべく、本特許出願人は特願昭5
5−150561号の如き移動可能な連続垂直掘削排土
装置を提案した。In order to solve these problems, the applicant of this patent filed a patent application filed in 1973.
A movable continuous vertical excavation and removal device such as No. 5-150561 was proposed.
以下本発明に係る連続垂直掘削排土装置の移動機構の一
実施例を図面に基づき説明する。第 ′1図において、
1は掘削地点の地表面で、まず地盤の掘下げに伴う湧水
を阻止する為掘削現場の周囲に現場の地質条件に応じて
止水壁2を潜没する。一方接止水壁2に近い位置に案内
支柱3を鉛直にかつ柱頭を地表面より適当長さ突出させ
て打設するが、最終深度まで掘削を行った時、該案内支
柱3が伺自立1−でいるよう予定掘削深度より深く打設
する。本実施例では後述するように案内支柱3は座屈強
度をもたせる為に第3図に示すごとくプレーシング3a
・・・にて係着した二本の鋼管パイル3b、3cを使用
する。DESCRIPTION OF THE PREFERRED EMBODIMENTS An embodiment of a moving mechanism for a continuous vertical excavation and removal device according to the present invention will be described below with reference to the drawings. In Figure '1,
Reference numeral 1 indicates the ground surface at the excavation site, and first, a water-stop wall 2 is hidden around the excavation site in accordance with the geological conditions of the site in order to prevent water from springing as the ground is dug down. On the other hand, a guide post 3 is installed vertically in a position close to the water stop wall 2 with the column head protruding an appropriate length from the ground surface, but when excavation is carried out to the final depth, the guide post 3 becomes freestanding 1 -The excavation depth shall be deeper than the planned excavation depth. In this embodiment, as will be described later, in order to provide buckling strength, the guide column 3 is provided with a placing 3a as shown in FIG.
Two steel pipe piles 3b and 3c that are tied together are used.
この打設方法は適宜の方法を用いうるが無理な打設を避
けて予めアースオーガ等で鉛直孔を掘削1−7、これに
上記二本の鋼管パイル3b、3cで組立てた案内支柱3
を垂下挿入して埋設する方法も週択される。次いで一般
の掘削機で案内支柱3の周囲を掘り下げて下部土砂積載
部4を設置するべく深度H1の小堅穴を掘削する。この
深度H1け下部土砂積載部4のホッパ4aの高さおよび
使用される掘削機の種類等に応じて適宜設定されるが、
本出願人の設計例では約8mが適当とされた。Any suitable method can be used for this installation, but to avoid forced installation, a vertical hole 1-7 is drilled in advance using an earth auger, etc., and the guide column 3 is assembled with the two steel pipe piles 3b and 3c.
A method of inserting and burying the material hanging down is also selected. Next, a general excavator is used to dig around the guide post 3 and a small hole with a depth H1 is excavated in order to install the lower earth and sand loading section 4. This depth is set appropriately depending on the height of the hopper 4a of the lower earth and sand loading section 4 and the type of excavator used.
In the applicant's design example, approximately 8 m was considered appropriate.
次に案内支柱3に沿って案内上下可能な架台4bに、下
部土砂積載部4を据付ける。この場合の下部土砂積載部
4の位置調節は、その架台4bの摺動係止機構5a、5
bを上記案内支柱3に挿通降下させて深度H□の穴底の
レベ/I/ 12に位置させた後、摺動係止機構5a、
5bを案内支柱3に係止する。一方地表部には先に潜没
した止水壁2の周縁部に支構12を立設し、これと案内
支柱3の頭端に上部土砂排出部6を水平架設し、下部土
砂積載部4と案内支柱3と上部土砂排出部6で構成され
る搬送構造にチェーン7・・・、搬送容器8・・・等を
取付は搬送装置を組立てる。ここで下部土砂積載部4は
摺動係止機構5a、5bによってその重量を案内支柱3
で支持されるので穴底のレベル1aにおける地盤が軟弱
不整であっても基礎工事の必要なく下部土砂積載部4を
設置できる。このようにして地表面1の表土前を適当な
掘削機を用いて掘削し7、矢印a方向にこれをホッパ4
aへ投入する。掘削が進んで掘削レベルがB、Cになる
に従って矢印す、cの方向にホッパ投入を行い、か〈;
〜て周囲の止水壁2に至るレベルfatでの掘削排土を
終了する。Next, the lower earth and sand loading section 4 is installed on a pedestal 4b that can be guided up and down along the guide column 3. In this case, the position adjustment of the lower earth and sand loading section 4 is performed by sliding locking mechanisms 5a and 5 of the pedestal 4b.
After inserting and lowering the guide column 3 into the guide column 3 and positioning it at level /I/12 at the bottom of the hole of depth H□, the sliding locking mechanism 5a,
5b is locked to the guide column 3. On the other hand, on the ground surface, a support structure 12 is erected around the peripheral edge of the water stop wall 2 that was submerged earlier, and an upper earth and sand discharge section 6 is installed horizontally on this and the head end of the guide column 3, and a lower earth and sand loading section 4 Then, chains 7 . . . , transportation container 8 , etc. are attached to the transportation structure composed of the guide column 3 and the upper earth and sand discharge section 6 to assemble the transportation device. Here, the lower earth and sand loading section 4 transfers its weight to the guide column 3 by sliding locking mechanisms 5a and 5b.
Even if the ground at level 1a at the bottom of the hole is soft and uneven, the lower earth and sand loading section 4 can be installed without the need for foundation work. In this way, the front of the topsoil on the ground surface 1 is excavated using an appropriate excavator 7, and the excavation is carried out in the direction of arrow a to the hopper 4.
Insert into a. As the excavation progresses and the excavation level reaches B and C, the hopper is loaded in the directions of arrows A and C, and
The excavation and removal at level fat reaching the surrounding water stop wall 2 is completed.
次に後述する方法で下部土砂積載部4をその下面が掘削
出来るだけの適当高さ上昇させ摺動係止機構5a、5b
で案内支柱3に係止保持させ、下部土砂積載部4の下面
を第1回の小堅穴を掘削したのと同様に深度H2まで掘
下げ、このレベル1bに下部土砂積載部4を降下係止す
る、この時の下部土砂積載部4の一時上昇の高さ、5−
及び第2回小整孔の掘下げ深度H2は使用する掘削機械
の種類と性能に応じて適宜選定されるが、本出願人の設
計例においては一時上昇高さを4m1上記深度H2を6
mとすることが適当と認められたので以下の実施例説明
はこの寸法に基づいて記述する。Next, the lower earth and sand loading section 4 is raised to an appropriate height that allows the lower surface to be excavated by a method to be described later.
The bottom surface of the lower earth and sand loading section 4 is dug down to depth H2 in the same way as the first small hole was excavated, and the lower earth and sand loading section 4 is lowered and locked at this level 1b. At this time, the height of the temporary rise of the lower earth and sand loading section 4, and the digging depth H2 of the second small hole preparation are selected as appropriate depending on the type and performance of the excavation machine to be used, but the present application In the human design example, the temporary elevation height is 4 m1 and the above depth H2 is 6 m.
Since it has been recognized that it is appropriate to set the dimension to m, the following embodiments will be described based on this dimension.
下部土砂積載部4の案内支柱3に沿う摺動上下に伴うチ
ェーン長の伸縮は上部土砂排出部6上の末端鎖車6aの
移動によって対応される。Expansion and contraction of the chain length as the lower earth and sand loading section 4 slides up and down along the guide column 3 is handled by the movement of the end chain wheel 6a on the upper earth and sand discharge section 6.
即ち原動機6bによって駆動されチェーン7・・・を回
動する末端鎖車6aは台車6C上に設置され、該台車6
Cは上部土砂排出部6の上面に並設されたレール6d上
に載り、上部土砂排出部6の左端に固設窟れた原動機6
eによって正逆駆動される鎖車6fと右端に固設された
鎖車6gに掛回された両側の台車移動用チェーン611
によって左又は右方へ牽引移動しうるようになっている
。この台車6Cは通常搬送時は上部土砂排出部6のほぼ
中央り位置にあり、下部土砂積載部4が当初の設置レベ
ルから4m上昇される=6−
時はこれに追従り、てD位置から左方4mのE位置に移
動され、当初設置レベルから6m降下される時はD位置
よh6m右方のF位置に移動されてチェーン7・・・の
緊張を一定に保ち鎖車よりの脱落等の不具合を防止する
。下部土砂積載部4を深度T−T 、から深度H2のレ
ベル1bに降下17たらこわ、を摺動係止機構5a、5
bで係止L、次の降下に備えてチェーン7・・・の継足
1.及び搬送容器8・・・の補充取付けを行う。これに
は後述するごとく下部土砂積載部4の架台4bの上部に
取付けられたチェーン保持機構9を用いて足場9aにお
いてチェーン7・・・を保持して保持部の直上で切断し
、次に掘削すべき6m分のチェーンを切断部の上方のチ
ェ−ン7・・・各条に継足す。That is, the end chain wheel 6a, which is driven by the prime mover 6b and rotates the chain 7..., is installed on the trolley 6C,
C is a prime mover 6 which is mounted on a rail 6d arranged in parallel on the upper surface of the upper earth and sand discharge part 6 and is fixedly installed at the left end of the upper earth and sand discharge part 6.
A chain 611 for moving the cart on both sides is wound around the chain wheel 6f which is driven in forward and reverse directions by e, and the chain wheel 6g fixed at the right end.
It can be towed to the left or right. During normal transportation, this trolley 6C is located at approximately the center of the upper earth and sand discharge section 6, and when the lower earth and sand loading section 4 is raised 4 m from the initial installation level = 6-, it follows this and moves from position D. When it is moved to position E, 4m to the left, and lowered 6m from the initial installation level, it is moved from position D to position F, 6m to the right, to keep the tension of chain 7 constant and prevent it from falling off from the chain wheel. prevent problems. When the lower earth and sand loading section 4 is lowered from the depth T-T to the level 1b at the depth H2, the sliding locking mechanisms 5a and 5 are lowered.
Lock L at b, and connect leg 1 of chain 7 in preparation for the next descent. and replenishment of the transport containers 8... As described later, the chain holding mechanism 9 attached to the upper part of the pedestal 4b of the lower earth and sand loading section 4 is used to hold the chain 7 on the scaffold 9a and cut it directly above the holding section, and then excavation Add 6 meters of chain to each chain 7 above the cut point.
そ1.て上部土砂排出部6の右端F位置に移動せられて
いた台車6Cを6m左方のE位置に復せは継足12チエ
ーンは引上げられてその下端は丁度切断保持された。チ
ェーン上端に一致1〜容易に係合接続出来る。このチェ
ーン引上げに伴って遂次搬送容器8・・・を追加取付け
ていく。このように12で次の掘削排土工程が準備され
、順次以上のごときサイクルを繰返1〜で所定の深度づ
つ段階的に掘下げて、予定深度に達して掘削工事を完了
中るのである。案内支柱3は予定掘削深度より深く打設
されているので周囲が掘削されても最後寸で自立を保っ
ており、掘削工事が終了1〜たら案内支柱を引抜き装置
で取払い、その後の構築工事を行う。Part 1. When the trolley 6C, which had been moved to the right end F position of the upper earth and sand discharge section 6, was returned to the E position 6 m to the left, the joint leg chain 12 was pulled up and its lower end was just cut and held. It can be easily engaged and connected to the upper end of the chain. As the chain is pulled up, additional conveyance containers 8 are sequentially attached. In this way, the next excavation and earth removal process is prepared in step 12, and the above-mentioned cycles are repeated in sequence to gradually dig down to a predetermined depth in steps 1 through 1. When the planned depth is reached, the excavation work is completed. Since the guide column 3 is driven deeper than the planned excavation depth, it remains independent at its last dimension even if the surrounding area is excavated.When the excavation work is completed, the guide column 3 is removed with a pulling device and the subsequent construction work is carried out. I do.
ところで、第1図に示す如く、複数のキャタピラ10の
上に板16を設け、更にその上にトラバーサ11を設け
、このトラバーサ11の上に上部土砂排出部6の支構1
2を設ける。複数のキャタピラ10の移動作業によって
、上部土砂排出部6全体が次の作業現場に移動させるこ
とが出来る。By the way, as shown in FIG. 1, a plate 16 is provided on a plurality of caterpillars 10, a traverser 11 is further provided on the plate 16, and a support 1 of the upper earth and sand discharge section 6 is mounted on the traverser 11.
2 will be provided. By moving the plurality of caterpillars 10, the entire upper dirt discharge section 6 can be moved to the next work site.
このキャタピラ10による移動によってレールによる移
動方式より費用を低減化することが出来る。Movement by the caterpillar 10 can reduce costs compared to a movement method using rails.
次にチェーン保持機構9について第4図に基づいて説明
すると、該保持機構9は下部土砂積載部4の架台4bの
上部にチェーン7・・・を取囲んで設けられた立方形鉄
骨枠組構造のチェーン畔足し足場9aの中に組立てられ
たもので、上下鉄骨枠の間に対向して立設されたネジ柱
9b。Next, the chain holding mechanism 9 will be explained based on FIG. 4. The holding mechanism 9 has a cubic steel frame structure that is provided on the top of the pedestal 4b of the lower earth and sand loading section 4 to surround the chains 7. A screw column 9b is assembled in the chain scaffolding 9a and is erected between the upper and lower steel frames to face each other.
9bとこれに螺合されたナツ)9C,9cによって支承
されてネジ柱9b、9b上を上下摺動しつる一対のハン
ガ9d、9dと、この上面の半円四部に支承されて両ハ
ンガ9d、9dに掛渡された二本の受棒9e、9e及び
これに掛渡されるチェーン7・・・の並列条数により二
本乃至四本のかんぬき9f、9f・・・で構成され、こ
のようなチェーン保持機構がチェーン7・・・の並列垂
直部に対応i−で3組設けられる。チェーン7・・・を
切断・継足す際はナツ)9C,9Cを回してハンガ9d
、9dの位置を調節し、図示のようにチェーンのリンク
の間隙にかんぬき9f。A pair of hangers 9d and 9d are supported by the screw columns 9c and 9c and slide up and down on the screw columns 9b, and both hangers 9d are supported by the four semicircular parts on the upper surface of the hangers. , 9d, and two to four bars 9f, 9f... depending on the number of parallel threads of the two receiving rods 9e, 9e and the chain 7..., which are wrapped around them. Three sets of chain holding mechanisms are provided corresponding to the parallel vertical portions of the chains 7 . When cutting or adding chain 7..., turn Natsu) 9C and 9C and hanger 9d.
, 9d, and insert bolts 9f into the gaps between the chain links as shown.
9f・・・を挿通し、ナツ)9c、9cfr:若干上昇
方向に回すとかんぬき9f、9f・・・より下方のチェ
ーンの荷重は該チェーン保持機構9によって支持され、
かんぬき9f、9f・・・上方直近の9−
チェーンは張力が著1〜く緩和されるのでチェーンのビ
ンの抜法は安全かつ容易に行われる。父、チェーン継足
し後はナンド9Cを下降方向に回すとかんぬき9f、9
f・・・に掛っている荷重は取除かれかんぬき9f、9
f・・・は容易に抜去することが出来る。9c, 9cfr: When the bolts 9c, 9cfr: are slightly turned in the upward direction, the load of the chain below the bolts 9f, 9f... is supported by the chain holding mechanism 9,
Bolts 9f, 9f... Since the tension on the 9-chain closest to the top is significantly alleviated, the chain can be removed safely and easily. Dad, after adding the chain, turn the Nand 9C in the downward direction and the bolts 9F, 9
The load on f... is removed and the bolts 9f, 9
f... can be easily removed.
以上詳述したように、本発明による連続掘削排土装置の
移動機構は従来の装置の如く、倒れかの止水壁2の内側
に設ける側壁構築期間中、上記土砂排出部6の稼動停止
というサイクルタイムにおける不経済を回避することが
出来るものであるから全掘削工程が一体構成の下に連続
的に高能率に行われ、工期短縮ひいてはコスト低減に役
立ち、特に大規模垂直掘削工事において極めて大なる効
果を具現するものである。As described in detail above, the moving mechanism of the continuous excavation and earth removal device according to the present invention is similar to the conventional device, and during the construction period of the side wall provided inside the water stop wall 2 of the collapsed area, the operation of the earth and sand discharge section 6 is stopped. Since it is possible to avoid diseconomies in cycle time, the entire excavation process is carried out continuously and highly efficiently in an integrated structure, which helps shorten the construction period and reduce costs, especially in large-scale vertical excavation works. It embodies the following effect.
図面は本発明による連続垂直押削排士工法及び装置の一
実施例を示し、第1図は本装置の全体概要及び工法を説
明する概略側面図、第2図は下部土砂積載部架台の構造
の概要を示す斜視説明図、第3図は摺動係止機構の要部
側面図及びこのX−X線に沿う横断面図、第4図はチェ
ーン保持機構の斜視説明図、第5図は上部土砂排出部の
概略側面図である。第6図は本移動機構を概念的に説明
1−だ移動機構概要図である。
3・・・案内支柱 3b、3c・・・鋼管パイル4・
・・下部土砂積載部 5a、5b・・・摺動係止機構
6・・・上部土砂排出部 6a・・・末端鎖車
6C・・・台車 7・・・チェーン 8・・・搬
送容器 9・・・チェーン保持機構 10・・・キ
ャタピラ 11・・・トラバーサ 12・・・支構
13・・・支柱 14・・・支柱 15・・・移動
支持装置 16・・・板
特許出願人 晋行機工株式会社
特開昭59−85042 (5)
手続補正書(方式)
1.事件の表示 特願昭57−193599号2、発明
の名称 連続垂直排土装置
3、手続をする者
事件との関係 特許出願人
名 称 晋行機工株式会社
4、代理人
居 所 東京都板橋区大和町14番15号6、補正の
対象
(1)願書
(2)明細書
(3)図面
(4)代理権を証明する書面
7、補正の内容
(1)別紙の通り
(4)別紙の通りThe drawings show an embodiment of the continuous vertical pressing method and device according to the present invention, FIG. 1 is a schematic side view illustrating the overall outline of the device and the method, and FIG. 2 shows the structure of the lower earth and sand loading section frame. 3 is a side view of the main parts of the sliding locking mechanism and a cross-sectional view taken along line X-X, FIG. 4 is a perspective view of the chain holding mechanism, and FIG. FIG. 3 is a schematic side view of the upper sediment discharge section. FIG. 6 is a schematic diagram of the moving mechanism for conceptually explaining the present moving mechanism. 3...Guide support 3b, 3c...Steel pipe pile 4.
...Lower earth and sand loading section 5a, 5b...Sliding locking mechanism 6...Upper earth and sand discharge section 6a...End chain wheel
6C... Trolley 7... Chain 8... Transport container 9... Chain holding mechanism 10... Caterpillar 11... Traverser 12... Support 13... Support 14... Support 15 ...Movement support device 16...Plate patent applicant Shingyo Kiko Co., Ltd. JP-A-59-85042 (5) Procedural amendment (method) 1. Indication of the case: Japanese Patent Application No. 57-193599 2, Title of the invention: Continuous vertical earth removal device 3, Person conducting the procedure Relationship with the case: Name of the patent applicant: Shingyo Kiko Co., Ltd. 4, Agent residence: Yamato, Itabashi-ku, Tokyo Town 14-15 No. 6, Subject of amendment (1) Application (2) Specification (3) Drawings (4) Document certifying power of attorney 7, Contents of amendment (1) As per attached sheet (4) As per attached sheet
Claims (1)
に土砂積載部を配し7、一方該案内支柱の上部開放端近
傍に土砂排出部を設け、土砂積載部、案内支柱及び土砂
排出部のそれぞれに渡って連続的に移動して土砂の積載
、運搬及び排出を行うことの可能なコンベア装置を張架
したことがらたる連続垂直排土装置において、少なくと
も案内支柱の上部に位置する土砂排出部が他の部分と分
離・独立してその支構の走行装置により移動し他の掘削
現場の案内支柱に係続し得るように1−たことを特徴と
する連続垂直排土装置。An earth and sand loading part is arranged near the ground surface of a guide post driven to a predetermined depth in the ground7, and a earth and sand discharge part is provided near the upper open end of the guide pillar, and the earth and sand loading part, the guide support and the earth and sand discharge part are connected to each other. In a continuous vertical earth removal device, which is constructed of a conveyor system that can continuously move across each section to load, transport, and discharge earth and sand, an earth and sand discharge section located at least above the guide column. 1. A continuous vertical earth removal device, characterized in that: (1) the continuous vertical earth removal device is moved by a traveling device of its support separately and independently from other parts, and can be connected to a guide support at another excavation site.
Priority Applications (2)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP57193599A JPS5985042A (en) | 1982-11-02 | 1982-11-02 | Continuous vertical soil discharger |
ZA832392A ZA832392B (en) | 1982-11-02 | 1983-04-05 | Method of continuously excavating ground and conveying excavated earth in the vertical direction |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP57193599A JPS5985042A (en) | 1982-11-02 | 1982-11-02 | Continuous vertical soil discharger |
Publications (1)
Publication Number | Publication Date |
---|---|
JPS5985042A true JPS5985042A (en) | 1984-05-16 |
Family
ID=16310628
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP57193599A Pending JPS5985042A (en) | 1982-11-02 | 1982-11-02 | Continuous vertical soil discharger |
Country Status (2)
Country | Link |
---|---|
JP (1) | JPS5985042A (en) |
ZA (1) | ZA832392B (en) |
-
1982
- 1982-11-02 JP JP57193599A patent/JPS5985042A/en active Pending
-
1983
- 1983-04-05 ZA ZA832392A patent/ZA832392B/en unknown
Also Published As
Publication number | Publication date |
---|---|
ZA832392B (en) | 1986-07-30 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
USRE34620E (en) | Trenching apparatus and methods of forming inground retaining walls | |
CN109488347B (en) | Excavation construction method for special stratum chamber | |
US4401206A (en) | Arrangement for continuously excavating ground and conveying excavated earth in the vertical direction | |
CN114483056B (en) | Method for treating collapse roof caving hole of high-speed railway shallow-buried tunnel within 15m of height of collapse cavity | |
CN110106867A (en) | Manual digging pile construction method between railcar station track | |
JPS5985042A (en) | Continuous vertical soil discharger | |
EP0250286B1 (en) | Underground mining process using downwardly directed stoping and caving, and installation for carrying this out | |
US4133581A (en) | Method of strip mining with cable supported conveyor | |
CN112962707B (en) | Equipment for foundation excavation construction and excavation construction process | |
CN111577294B (en) | Reverse-construction tunnel portal of steep rock mass in complex terrain and construction method | |
JPS59185236A (en) | Method and apparatus for continuous and vertical excavation and soil-moving work | |
KR830001908B1 (en) | Vertical excavating arrangement | |
US620101A (en) | Art of constructing tunnels | |
RU2130552C1 (en) | Method for protection of interchamber pillars from destruction | |
RU2783828C1 (en) | Device for strengthening earth structures | |
JPS58204233A (en) | Method and apparatus for continuous vertical excavation and soil moving work with crusher | |
GB1603817A (en) | Lining of tunnels and excavations and constructing walls | |
SU1682563A1 (en) | Method for working thick steep and inclined coal seams | |
RU97105521A (en) | METHOD FOR DEVELOPING A POWERFUL STEEL COAL COAL LAYER BY HORIZONTAL LAYERS | |
US1696421A (en) | Method of and apparatus for supporting the side walls of excavations | |
JP2620111B2 (en) | Excavation construction method for long space | |
SU817271A1 (en) | Fence of isolating fill-in strip | |
SU1714131A1 (en) | Method of mining flat stratified mineral deposits | |
SU1728488A1 (en) | Method of mining coal seams | |
JPS6378928A (en) | Continuous and vertical soil discharger for pit in steel tower foundation |