JPS5949973B2 - Construction methods for foundations such as abutments and piers - Google Patents
Construction methods for foundations such as abutments and piersInfo
- Publication number
- JPS5949973B2 JPS5949973B2 JP6638480A JP6638480A JPS5949973B2 JP S5949973 B2 JPS5949973 B2 JP S5949973B2 JP 6638480 A JP6638480 A JP 6638480A JP 6638480 A JP6638480 A JP 6638480A JP S5949973 B2 JPS5949973 B2 JP S5949973B2
- Authority
- JP
- Japan
- Prior art keywords
- footing
- side wall
- position corresponding
- retaining member
- top plate
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired
Links
Landscapes
- Foundations (AREA)
Description
【発明の詳細な説明】
この発明は、地中に埋設されたフーチングに支持される
型の橋台や橋脚等の基礎の施工方法に関する。DETAILED DESCRIPTION OF THE INVENTION The present invention relates to a method for constructing foundations such as bridge abutments and piers that are supported by footings buried underground.
河用沿等に構築される高架橋等においては、概して地盤
が軟弱であるために、第1図に示す如く、底部を開放し
た箱状のフーチング部1aを地中に設け、その上に橋台
あるいは橋脚の柱部分1bを立設することが行なわれる
。In elevated bridges constructed along river banks, etc., the ground is generally soft, so as shown in Figure 1, a box-shaped footing 1a with an open bottom is installed underground, and abutments or abutments are placed on top of it. The column portion 1b of the pier is erected.
この場合、問題となるのが、そのフーチング部1aを含
む地中部分の施工方法を如何にするかということである
。In this case, the problem is how to construct the underground portion including the footing portion 1a.
従来においては、地表にて予め形成された箱状フーチン
グ部材を、いわゆるケーソン工法によって沈設する方法
が採られていたが、しかし、このケーソン工法は、良く
知られているように、高圧下でQ危験作業を伴い、また
作業能率が極めて悪いという問題がある。Conventionally, a box-shaped footing member previously formed on the ground surface was deposited using the so-called caisson construction method. However, as is well known, this caisson construction method There is a problem that it involves dangerous work and that work efficiency is extremely poor.
この発明は、以上のような問題を鑑みてなされたもので
、その目的とするところは、上記フーチング部を含む橋
台あるいは橋脚の基礎部分、特に地中部分な、従来のケ
ーソン工法によらずに、従来よりも安全にかつ効率よく
設けることができる施工方法を提供することにある。This invention was made in view of the above-mentioned problems, and its purpose is to improve the foundation part of the bridge abutment or pier including the footing, especially the underground part, without using the conventional caisson construction method. The object of the present invention is to provide a construction method that can be installed more safely and efficiently than before.
以下、この発明の実施例を添附図面を参照しながら説明
する。Embodiments of the present invention will be described below with reference to the accompanying drawings.
第2図a = hおよび第3図a−hは、この発明に係
る橋台、橋脚基礎の施工方法の各段階を順を追って示し
たものである。FIGS. 2a=h and 3a-h sequentially show each step of the method for constructing a bridge abutment and pier foundation according to the present invention.
同図に示した方法では、まず、第2図aおよび第3図a
に示すように、河用2内の基礎設置予定位置に作業用地
用の盛土3を設ける。In the method shown in the figure, first, Figure 2a and Figure 3a
As shown in Figure 2, an embankment 3 for the work site will be provided at the planned location of the foundation within the river 2.
さらに、その盛土3の上に作業用床4を構築し、これか
ら設けようとするフーチング部5の側壁部相当位置の地
表にガイドトレンチ6を設ける。Further, a working floor 4 is constructed on the embankment 3, and a guide trench 6 is provided on the ground surface at a position corresponding to the side wall of the footing 5 to be provided.
そして、第2図すおよび第3図すに示すように、地表か
ら上記フーチング部5の側壁部5aの上端相当位置に達
し、かつ上記フーチング側壁部5aの延長方向に相当す
る位置に沿って開削された溝孔8を設ける。Then, as shown in Figures 2 and 3, an excavation is made from the ground surface to a position corresponding to the upper end of the side wall 5a of the footing 5 and along a position corresponding to the extending direction of the footing side wall 5a. A slotted hole 8 is provided.
次に、第2図Cおよび第3図Cに示すように、上記溝孔
8の外側内壁面8aに沿って土留部材9を設けた後、上
記溝孔8を上記フーチング側壁部5aの下端部相当位置
へ向かってさらに掘進して延長する。Next, as shown in FIG. 2 C and FIG. Excavate further towards the appropriate location and extend it.
ここで、上記溝孔8の掘削は、例えばケリー掘削機を用
いてすべて地表から行うことができる。Here, the trench hole 8 can be excavated entirely from the ground surface using, for example, a Kelly excavator.
また、上記土留部材9として(′!、上記溝孔8とほぼ
同じ長さの鋼板、■鋼による矢板等を密に並設して設け
る。In addition, as the earth retaining member 9, ('!) steel plates having approximately the same length as the groove hole 8, (2) steel sheet piles, etc. are arranged closely in parallel.
なお、この実施例では、上記溝孔8を一挙に設けずに、
後述する連続壁とともに何回かに分けて設けられ、最終
的に上記フーチング部5の側壁部5aの全体が構成され
るようになっている。In addition, in this embodiment, the above-mentioned slot holes 8 are not provided all at once.
Together with a continuous wall, which will be described later, it is provided in several parts, and finally the entire side wall part 5a of the footing part 5 is constructed.
以上のようにしてフーチング側壁部5aの下端部相当位
置まで延長された溝孔8内には、第2図dおよび第3図
dに示すように、地表から鉄筋篭が挿入されたコンクリ
ートが打設されて、上記フーチング5の側壁部5aの一
部が形成される。As shown in FIGS. 2d and 3d, concrete with reinforcing bar cages inserted from the ground is poured into the groove 8 which has been extended to a position corresponding to the lower end of the footing side wall 5a as described above. A part of the side wall portion 5a of the footing 5 is formed.
そして、第2図eおよび第3図eに示すようにさらに他
の部分について、溝孔8の掘削、土留部材9の設置、鉄
筋コンクリートの打ち込み等の一連の作業を繰り返すこ
とにより、環状に閉じた断面を有し且つ一体化された側
壁部5aの全体が形成される。Then, as shown in Figures 2e and 3e, a series of operations such as digging trenches 8, installing earth retaining members 9, and pouring reinforced concrete are repeated for other parts to form a closed ring. A whole side wall portion 5a having a cross section and being integrated is formed.
ここで、注目すべきことは、第3図eに示すように、上
記側壁部5aの上端は、後述するフーチング部5の頂板
部5bの相当位置に突出するとともに、上記土留部材9
の下端部を上記溝孔8の外側内壁面との間に挾むように
して形成されていることである。What should be noted here is that, as shown in FIG.
The lower end portion of the groove hole 8 is sandwiched between the outer inner wall surface of the groove hole 8 and the outer inner wall surface of the groove hole 8.
このことにより、頂板部5bと側壁部5aとの一体性が
強化され、例えば鉄道用の橋脚のように変動荷重が加わ
る場合に好適なフーチング構造となるとともに、開口1
1を掘削する際にも土留部材9によって地山の崩落を効
果的に防止できる。This strengthens the integrity of the top plate portion 5b and the side wall portion 5a, resulting in a footing structure suitable for cases where fluctuating loads are applied, such as on railway piers, and the opening 1
Even when digging 1, the earth retaining member 9 can effectively prevent the collapse of the earth.
この後、第2図fおよび第3図fに示すように上記土留
部材9で囲繞された部分を切ぼり10を設けながら開削
して、地表から上記フーチング部5の上端部相当位置に
達する開口11を掘削する。After this, as shown in FIGS. 2f and 3f, the area surrounded by the earth retaining member 9 is excavated while providing a cutout 10, and an opening reaching from the ground surface to a position corresponding to the upper end of the footing 5 is created. Excavate 11.
そして、第2図gおよび第3図gに示すように、上記開
口11の底部に上記フーチング側壁部5aの上端部と連
結する頂板部5bを一体として設け、しかる後に、上記
頂板部5bの上部に橋脚の柱部分5cを立設するととも
に、上記土留部材9および切ぼり10を除去して上記開
口11を埋め戻す。Then, as shown in FIGS. 2g and 3g, a top plate part 5b is integrally provided at the bottom of the opening 11 to connect with the upper end of the footing side wall part 5a, and then an upper part of the top plate part 5b is installed. The pillar portion 5c of the pier is erected, the earth retaining member 9 and the cutout 10 are removed, and the opening 11 is backfilled.
さらに、前述した作業用地用盛土3を除去することによ
り、第2図りおよび83図りに示す如く、河川2の中に
施工された橋脚基礎を完成することができる。Furthermore, by removing the aforementioned work land embankment 3, the pier foundation constructed in the river 2 can be completed, as shown in the second drawing and the 83rd drawing.
以上のように、と9発明による橋台や橋脚基礎の施工方
法は、橋台、橋脚等の基礎部材であるフーチングを地中
に設けるのに際して、まず、地表から上記フーチング側
壁部の上端部相当位置に達し、かつ上記フーチング側壁
部の延長方向に相当する位置に沿って開閉された溝孔を
設け、次に上記溝孔の外側内壁部面に沿ってこの溝孔と
略略同−長さを有する土留部材を設けた後、上記溝孔を
上記フーチング側壁部の下端部相当位置へ向かってさら
に掘進して延長し、この延長部分の地中内に)−チング
の側壁部を構成する環状の閉じた断面を有し、且つその
上端がフーチングの頂板部相当位置に突出するとともに
、上記土留部材の下端部を上記溝孔の外側内壁面との間
に挾むようにして一体化された連続壁を形成し、この後
、上記土留部材で囲繞された部分を切ばりを設けながら
開削して、地表から上記フーチングの上端部相当位置に
達する開口を設け、この開口の底部に上記フーチング側
壁部の上端部と連結する頂板部を一体として形成し、し
かる後、」己頂板部の上部に橋台または橋脚の柱部分を
設けるとともに、上記土留部材および切ばりを除去して
上記開口を埋め戻すことを特徴とするもので、これによ
り従来のケーソン工法には全(よらないで、殆ど地表か
らの作業だけでもって、河川等の悪立地条件下でも、安
全にかつ効率良く橋台や橋脚基礎を構築することができ
る。As described above, in the method for constructing bridge abutments and pier foundations according to the invention, when a footing, which is a foundation member of an abutment, a bridge pier, etc., is installed in the ground, first, from the ground surface to a position corresponding to the upper end of the side wall of the footing. A groove is provided which is opened and closed along a position corresponding to the extending direction of the footing side wall, and then an earth retaining hole having approximately the same length as the groove is provided along the outer inner wall surface of the groove. After installing the member, the groove hole is further excavated and extended toward a position corresponding to the lower end of the side wall of the footing. forming an integrated continuous wall having a cross section, the upper end of which protrudes to a position corresponding to the top plate of the footing, and the lower end of the earth retaining member being sandwiched between the outer inner wall surface of the groove; After this, the area surrounded by the earth retaining member is excavated while providing a cutting beam to create an opening that reaches from the ground surface to a position corresponding to the upper end of the footing, and the bottom of this opening is connected to the upper end of the side wall of the footing. The method is characterized in that a top plate portion is integrally formed, and then, a pillar portion of an abutment or a bridge pier is provided on the top of the top plate portion, the earth retaining member and the cut beam are removed, and the opening is backfilled. As a result, bridge abutments and pier foundations can be constructed safely and efficiently even in poor location conditions such as rivers, without relying entirely on the conventional caisson construction method, and by mostly working from the ground.
また、この方法によって構築された基礎は、−体化され
た閉合断面の側壁部に、頂板部が一体として形成される
とともに、側壁部の上端が頂板部に突出して形成される
ため、沈設されるケーソンと同等もしくはそれ以上の大
きな剛性が得られ、変動荷重の大きい鉄道用橋脚などに
好適であって例えば、特公昭43−8856号公報に見
られるように、ケーシングと場所打ち杭で形成される基
礎とは耐力が相違するとともに、基礎の一部として土中
に残置されるケーシングの腐蝕の問題もない。In addition, in the foundation constructed by this method, the top plate part is integrally formed with the side wall part of the closed cross section that has been converted into a body, and the upper end of the side wall part is formed to protrude from the top plate part, so it cannot be sunk. It has a rigidity equal to or greater than that of a caisson, and is suitable for railway bridge piers with large fluctuating loads. The bearing strength is different from other foundations, and there is no problem of corrosion of the casing left in the soil as part of the foundation.
第1図は橋脚の基礎部分を示す一部破断斜視間第2メa
からhはこの発明による施工方法の実施例を各段階を追
って示す断面図、第3図aからhは第2図aからhの各
断面図にそれぞれ対応する平面図である。
1a・・・・・・フーチング部、1b・・・・・・柱部
分、2・・・・・・河川、3・・・・・・盛土、4・・
・・・・作業用床、5・・・・・・フーチング部、5a
・・・・・・側壁部、5b・・・・・・頂板部、5c・
・・・・・柱部分、6・・・・・・ガイドトレンチ、8
・・・・・・溝孔、9・・・・・・土留部材、10・・
・・・・切ばり、11・・・・・・開口。Figure 1 is a partially broken perspective view showing the foundation of the pier.
to h are sectional views showing each step of an embodiment of the construction method according to the present invention, and FIGS. 3a to 3h are plan views corresponding to the sectional views of FIGS. 2a to h, respectively. 1a...Footing part, 1b...Column part, 2...River, 3...Embankment, 4...
...Working floor, 5...Footing part, 5a
...Side wall part, 5b...Top plate part, 5c.
...Column part, 6...Guide trench, 8
...Groove, 9...Earth retaining member, 10...
...Kiribari, 11...Opening.
Claims (1)
設けるのに際して、まず、地表から上記フーチング側壁
部の上端部相当位置に達しかつ上記フーチング側壁部の
延長方向に相当する位置に沿って開削された溝孔を設け
、次に上記溝孔の外側内壁部面に沿ってこの溝孔と略同
−長さを有する土留部材を設けた後、上記溝孔を上記フ
ーチング側壁部の下端部相当位置へ向かってさらに掘進
して延長し、この延長部分の地中内にフーチングの側壁
部を構成する環状の閉じた断面を有し、且つその上端が
フーチング頂板部相当位置に突出するとともに、上記土
留部材の下端部を上記溝孔の外側内壁面との間に挾むよ
うにして一体化された連続壁を形成し、この後、上記土
留部材で囲繞された部分を切ばりを設けながら、開削し
て地表から手記フーチングの上端部相当位置に達する開
口を設け、この開口の底部に上記フーチング側壁部の上
端部と連結する頂板部を一体として形成し、しかる後に
、上記頂板部の上部に橋台または橋脚の柱部分を設ける
とともに、上記土留部材および切ばりを除去して上記開
口を哩め戻すことを特徴とする橋台、橋脚等の基礎の施
工方法。1. When installing a footing, which is a base member for an abutment, a bridge pier, etc., underground, first, excavation is carried out from the ground surface to a position corresponding to the upper end of the footing side wall and along a position corresponding to the extension direction of the footing side wall. After providing a retaining member having approximately the same length as the groove along the outer inner wall surface of the groove, The extension section is further excavated and extended into the ground, and has an annular closed cross section that constitutes the side wall of the footing, and its upper end protrudes to a position corresponding to the top plate of the footing, and the above-mentioned An integrated continuous wall is formed by sandwiching the lower end of the earth retaining member with the outer inner wall surface of the groove, and then the part surrounded by the earth retaining member is excavated while providing a cut beam. An opening that reaches from the ground surface to a position corresponding to the upper end of the footing is provided, and a top plate portion that connects to the upper end of the footing side wall is integrally formed at the bottom of this opening, and then a bridge abutment or pier is installed on the top of the top plate portion. A method for constructing a foundation for an abutment, a bridge pier, etc., characterized by providing a pillar portion, removing the earth retaining member and the cut beam, and then leaning back the opening.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP6638480A JPS5949973B2 (en) | 1980-05-21 | 1980-05-21 | Construction methods for foundations such as abutments and piers |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP6638480A JPS5949973B2 (en) | 1980-05-21 | 1980-05-21 | Construction methods for foundations such as abutments and piers |
Publications (2)
Publication Number | Publication Date |
---|---|
JPS56163323A JPS56163323A (en) | 1981-12-15 |
JPS5949973B2 true JPS5949973B2 (en) | 1984-12-05 |
Family
ID=13314268
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP6638480A Expired JPS5949973B2 (en) | 1980-05-21 | 1980-05-21 | Construction methods for foundations such as abutments and piers |
Country Status (1)
Country | Link |
---|---|
JP (1) | JPS5949973B2 (en) |
-
1980
- 1980-05-21 JP JP6638480A patent/JPS5949973B2/en not_active Expired
Also Published As
Publication number | Publication date |
---|---|
JPS56163323A (en) | 1981-12-15 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
KR102195504B1 (en) | Construction method for Eearth self-retaining wall using reinforcing member and CIP construction method | |
CN108867723A (en) | The method of frame structure building rectification and underground increasing layer | |
KR102195510B1 (en) | Construction method for earth self-retaining wall using reinforcing member and PHC pile | |
CN106988337A (en) | Reinforcing method for reducing uneven settlement of strip-shaped shallow foundation house | |
US2317016A (en) | Bridge foundation and method of making same | |
JP2868651B2 (en) | Earth retaining method above existing underground structure | |
KR102252011B1 (en) | Composite Pile Using Angled Channel With Different Strength Steels | |
KR102195496B1 (en) | Pile for earth self-retaining wall using cast in place concrete pile with double I beam | |
JPS5949973B2 (en) | Construction methods for foundations such as abutments and piers | |
KR102194381B1 (en) | Pile for Earth self-retaining wall using double I beam | |
JPH1077644A (en) | Earthquake resisting pile foundation construction method | |
CN205557573U (en) | Underground structure | |
JPS5949974B2 (en) | Construction methods for foundations such as abutments and piers | |
JPH0721196B2 (en) | Reverse construction method of underground structure | |
JPH0768707B2 (en) | Open caisson method | |
JPH01226921A (en) | Earthquake-proof reinforced revetment construction | |
JP7480069B2 (en) | How to reinforce existing revetments | |
KR102649959B1 (en) | Longitudinal and lateral integration structure of pile and structure manufactured using the same | |
JP3228199U (en) | Construction structure of earth retaining support | |
JP2876265B2 (en) | Sheet pile for underground continuous wall and underground continuous wall method | |
JPS6018769B2 (en) | Construction method of underground structure | |
JP4283194B2 (en) | Wave-absorbing structure, method for constructing wave-absorbing structure | |
KR102194388B1 (en) | Construction method for earth self-retaining wall using reinforcing member and Soil retaining plate construction method | |
JPS5920822B2 (en) | Seismic reinforcement method for embankments | |
KR102194394B1 (en) | Construction method for earth self-retaining wall using reinforcing member and SCW construction method |