JPS5931319A - Construction of strip footing for building - Google Patents

Construction of strip footing for building

Info

Publication number
JPS5931319A
JPS5931319A JP57139358A JP13935882A JPS5931319A JP S5931319 A JPS5931319 A JP S5931319A JP 57139358 A JP57139358 A JP 57139358A JP 13935882 A JP13935882 A JP 13935882A JP S5931319 A JPS5931319 A JP S5931319A
Authority
JP
Japan
Prior art keywords
foundation
general
ventilation opening
vent
strip footing
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP57139358A
Other languages
Japanese (ja)
Inventor
Koji Hamada
耕治 浜田
Ginichi Shigaraki
信楽 銀一
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Misawa Homes Co Ltd
Original Assignee
Misawa Homes Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Misawa Homes Co Ltd filed Critical Misawa Homes Co Ltd
Priority to JP57139358A priority Critical patent/JPS5931319A/en
Publication of JPS5931319A publication Critical patent/JPS5931319A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures
    • E02D27/01Flat foundations
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures
    • E02D27/01Flat foundations
    • E02D27/013Shuttering specially adapted therefor
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures
    • E02D27/01Flat foundations
    • E02D27/016Flat foundations made mainly from prefabricated concrete elements

Landscapes

  • Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Foundations (AREA)
  • Building Environments (AREA)

Abstract

PURPOSE:To simplify the carrying-in operation of materials for a strip footing by a method in which other vent ports and the rising portion of strip footing for general foundation are formed by leaving a vent port serving as a path through which materials are carried in, and lastly, the vent port serving as the path is constructed. CONSTITUTION:A strip footing 11 is constructed of vent ports 11a, 11b, 11c, and 11d and a general fundation 11e. The vent ports 11a, 11b, 11c, and 11d are provided with a vent port 12 having a vent port iron-bar set unit 16 with an iron bar lattice 15. When concrete is placed for the vent port 11a and the general foundation 11e, plates (not illustrated) are laid across excavated trenches (not illustrated) for the vent ports 11b, 11c, and 11d to form a path 19, and by utilizing the path 19, materials necessary for constructing a strip footing 11 are carried in. After the completion of construction of the foundation 11e and the vent port 11a, the vent ports 11b and 11c are constructed and lastly the vent port 11d is constructed to complete the construction of the strip footing 11.

Description

【発明の詳細な説明】 本発明はa染布基礎の第1イ¥築方法に関する。[Detailed description of the invention] The present invention relates to a first method for constructing a dyed fabric foundation.

従来、建築物を築造するだめの基礎を槽ぐへする際には
、建築物を築造しようとする敷地全面にわたって、一度
に基礎を構築する方法が採られている。そして、この時
t1q築される基礎1は第1図に示すようにまず根切υ
を行なった後、根切i’i’# 2の底部に栗石等を敷
きQめ突き固め、その上に型枠3.4を設置、次にコン
クリートカート等でコンクリートを運び込みコンクリー
トを打設して完成きれる。
Conventionally, when laying the foundation for building a building, a method has been adopted in which the foundation is constructed all at once over the entire site on which the building is to be constructed. At this time, the foundation 1 to be built t1q is first cut by root cutting υ, as shown in Figure 1.
After doing this, lay chestnut stone, etc. at the bottom of Nekiri i'i'# 2 and tamp it down, set formwork 3.4 on top of it, then transport the concrete with a concrete cart etc. and pour the concrete. It can be completed.

しかしながら、地形や周囲の状況等から建め物が築造さ
れる敷地を利用して基礎1のtlIriに必要な資料や
器具を敷地内に運び込まなければならない場合や第2図
に示すように外部布基礎5の内部に内Eflb布基礎6
や独立基礎7が有る場合には、外部布基礎5−1だ良い
が、特に内部布基礎6、独立基?#7をtM’Jする際
に、コンクリートその他殺側や器具を外部布基礎5をま
たぐようにして搬入しなければならないため、外部布基
礎5の型枠4が邪魔になって、質相や器具の搬入作条が
非常に面倒であるという欠点がある。
However, due to the topography and surrounding conditions, there are cases where materials and equipment necessary for foundation 1 tlIri must be carried into the site using the site where the building is being constructed, or where external construction is required as shown in Figure 2. Eflb cloth foundation 6 inside the foundation 5
If there is an independent foundation 7, an external foundation 5-1 is fine, but especially an internal foundation 6, an independent foundation? When carrying out tM'J of #7, concrete, other materials, and equipment must be carried in such a way as to straddle the external fabric foundation 5, so the formwork 4 of the external fabric foundation 5 gets in the way and the quality and quality The disadvantage is that the process of transporting the equipment is very troublesome.

本発明は上記事情に鑑みてなされたもので、その目的と
するところは、建築物が築造される敷地内に基礎の構築
に必要な負相や器具を搬入する場合に、負相や器具を搬
入するのが容易にできる建築布基礎の構築方法を提供す
ることにある。以下、図面を参照して本発明を具体的に
説明する。
The present invention has been made in view of the above-mentioned circumstances, and its purpose is to transport the negative phase and equipment necessary for constructing a foundation into the site where a building is constructed. An object of the present invention is to provide a method for constructing a building fabric foundation that can be easily transported. Hereinafter, the present invention will be specifically explained with reference to the drawings.

第3図ないし第6図は本発明の一実施例を示すもので、
11ばコンクリートでできた布幕(triであり、この
布幕礎工1は換気口部11a、llb、110、lid
と一般基礎ff1i 11 eに分れている。
3 to 6 show an embodiment of the present invention,
11 is a cloth curtain (TRI) made of concrete, and this cloth curtain foundation 1 has ventilation openings 11a, llb, 110, lid.
and general basics ff1i 11e.

そして、換気口部11&、llb、llc、1lclは
換気[:J12を形成する部分であシ、ぞの内rtt+
には平行に股りられた2本の鉄筋工3.14に、鉄筋も
しくは鉄線が格子状に般けられた鉄筋格子15を取シ付
けた構成になっている換気口部配筋ユニット16が設け
られている。また、換気口部11aと一般基礎部lie
のコンク!J−ト’l″J設の1県には、換気口部11
b、110、lidは根切u417を−またぐように板
材18を敷いてN+’+路19として使用される。そし
て、一般基礎部lieは換気口12を形成する以外の布
基礎11の部分であシ、その内部には、2本の横筋20
に縦筋21が梯子状に組み台わされた構成になっている
一般基礎部配筋ユニット22が設けられている。さらに
、この一般基礎部配筋ユニット22の下部にはr91定
の間隔で設けられた差し筋23が上記根切溝17の底部
に栗石と砂利を敞きつめ、突きli’21めた栗石層2
4に差し込まれており/一般基礎部配筋ユニット22の
上部には所定の間隔でアンカーボルト25が般けられて
いる。ざらにまた、布基礎11はフーチング部26と立
上9部27とに分けられ、フーチング部26は型枠28
の間にコンクリートを流し込んで形成されるとともに立
上り部27は型枠290間にコンクリートを流し込んで
形成される。
The ventilation openings 11&, llb, llc, and 1lcl are the parts that form the ventilation [:J12].
A ventilation opening reinforcement unit 16 is constructed by attaching a reinforcing bar grid 15 in which reinforcing bars or wires are laid out in a lattice shape to two parallel reinforcing bars 3.14. It is provided. In addition, the ventilation opening part 11a and the general foundation part lie
Conch! In one prefecture of J-t'l''J installation, ventilation opening part 11
b, 110, and lid are used as the N+'+ road 19 by laying a board 18 so as to straddle the root cut U417. The general foundation part lie is a part of the cloth foundation 11 other than the part forming the ventilation opening 12, and inside thereof there are two horizontal stripes 20.
A general foundation reinforcement unit 22 is provided in which vertical reinforcements 21 are assembled in a ladder shape. Further, in the lower part of this general foundation reinforcement unit 22, insert reinforcements 23 provided at regular intervals are filled with chestnut stone and gravel at the bottom of the root cutting groove 17, and a layer of chestnut stone is formed. 2
Anchor bolts 25 are inserted at predetermined intervals in the upper part of the general foundation reinforcement unit 22. Roughly speaking, the cloth foundation 11 is divided into a footing part 26 and a rising part 27, and the footing part 26 is connected to the formwork 28.
The rising portion 27 is formed by pouring concrete between the molds 290.

上記のように構成された布基礎11の構築を行なう県!
、自について説明する。まず建築物が築造される敷地内
全域にわたって根切シを行ない、根切溝17の底部に栗
石と砂利を敷きつめ突き固めて栗石層24を形1uする
。そ(2て、一般基礎部txeの栗石層24の上に一般
基礎部配筋ユニット22を設けるとともに、布基礎11
の栗石層24σ〕上に型枠28を設けた後ツコンクリー
トを運び込み、=ンクリート拐設を行なってフーチング
部26を構築する。さらに、換気口部11b、110.
11aの根切溝17をまたぐように板拐18を敷いて、
通路19を形成し布基礎11の構築に必要な資料や器具
を搬入した後、一般基礎部110の型枠29を設置it
するとともに、換気口部11aに換械ロ部配筋ユ=ット
16と型枠29を設置し7、第3図において、右上から
左下にかけて、順次コンクリートを打設し立」ユリ部2
7を!F4 IQする。このようにして換気口部11a
と一般基礎部lieの構築が終わると、次に換気口部1
1bに換気口部配筋ユニット16と型枠29を設置し、
かつコンクリートを打設して立上り部27を$1/f 
’4Sする。
The prefecture that will construct the cloth foundation 11 configured as above!
, explain about yourself. First, root cutting is carried out over the entire area of the site where the building is to be constructed, and chestnut stone and gravel are spread and compacted at the bottom of the root cutting groove 17 to form a chestnut stone layer 24 1u. (2) The general foundation reinforcement unit 22 is installed on the chestnut layer 24 of the general foundation txe, and the cloth foundation 11
After a formwork 28 is provided on the rock layer 24σ], concrete is brought in and concrete is removed to construct the footing portion 26. Further, ventilation port portions 11b, 110.
Lay the board 18 so as to straddle the root cutting groove 17 of 11a,
After forming the passage 19 and bringing in the materials and equipment necessary for constructing the cloth foundation 11, the formwork 29 of the general foundation part 110 is installed.
At the same time, the replacement reinforcement unit 16 and the formwork 29 were installed in the ventilation opening part 11a, and concrete was poured in order from the upper right to the lower left in Figure 3.
7! F4 IQ. In this way, the ventilation opening part 11a
After the construction of the general foundation part 1 is completed, next is the ventilation opening part 1.
Install the ventilation opening reinforcement unit 16 and formwork 29 on 1b,
And concrete is poured and the rising part 27 is $1/f.
'4S.

換気口部11bの構築が終わると、さらに換気口部11
0に換気口部配筋ユニット16と型枠29を設置道して
、かつコンクリートを打設して立上り部27を構築する
。そして、換気口部11Qの構へ七が終わると、(9)
気[1部11(lにも同様の作業をイーiない、換気[
−1部lidの立上シ部を構築する。
When the construction of the ventilation port part 11b is completed, the ventilation port part 11
0, the ventilation opening reinforcement unit 16 and the formwork 29 are installed, and concrete is poured to construct the rising part 27. Then, when the seventh step to the ventilation opening section 11Q is completed, (9)
Ventilation
- Build the start-up section of the first section lid.

最後に、コンクリートが固化したら型枠2B、29を取
り外し、布基礎11を完成する。
Finally, once the concrete has solidified, formworks 2B and 29 are removed, and the cloth foundation 11 is completed.

なお、布基礎11の内部に独立基礎がある場合には、一
般基礎部11θや換気口部tiaの構築と同時に独立基
礎を構築すればよい。
In addition, when there is an independent foundation inside the cloth foundation 11, what is necessary is just to construct an independent foundation at the same time as construction of the general foundation part 11(theta) and the ventilation opening part tia.

以上説明1−だように、本発明は資料(り入用の通路I
hとすべき換気口部を残して順次イlj i’pj碌の
立上り部を形成シフ、最後に通路の出入口とたった換気
口部の布基礎の立上シ部を形成1して布^1]^を朴1
集1“るようにしたものであるから、建処物か築造され
る敷」(IL内に基礎の構築に必要な資料や器具を搬入
する場合に、質相や器具を搬入するのが容易にできると
いう優れた効果を有する。
As explained above in Explanation 1, the present invention
Leaving the ventilation opening part that should be h, form the rising part of Ilj i'pj in sequence, and finally form the rising part of the cloth foundation of the entrance and exit of the passage and the ventilation opening part 1 and cloth ^1 ]^Park 1
Collection 1: "Because it is designed to be built, it is easy to carry materials and equipment necessary for constructing a foundation into the IL." It has the excellent effect of being able to

【図面の簡単な説明】[Brief explanation of drawings]

第1図は従来の基礎を示す断面図、第2図は従来の基礎
を示す斜視図、第3図ないしt+x 6図は本発明の一
実施例を示すもので、第3図は基礎の完成時の状態の余
1祝図、第り図は基礎の一部分をjnj路として使用し
ている状胛のrfl視図、m5図は換気口部の正面図、
第6図は第5図のM−■純に沿う断面図である。 11・・・・・布基礎、16・・・・・換気口部配筋ユ
ニット、17・・・・・根切溝、19・・・・・通路、
22・・・・・一般基礎部配筋ユ=ット、26・曲フー
チング部、27・・・・・立上り部、11 FL、  
1 l b、  11 c、  11 d・・・・・換
気口部、11θ・・・・・一般基礎部。 出願人 ミザワポーム株式会社 第四j
Figure 1 is a sectional view showing a conventional foundation, Figure 2 is a perspective view showing a conventional foundation, Figures 3 to 6 show an embodiment of the present invention, and Figure 3 is a completed foundation. The remaining 1st and 3rd drawings are RFL views of the structure in which part of the foundation is used as a roadway, and M5 is a front view of the ventilation opening.
FIG. 6 is a sectional view taken along the line M-■ in FIG. 5. 11... Cloth foundation, 16... Ventilation opening reinforcement unit, 17... Root cut groove, 19... Passage,
22...General foundation reinforcement unit, 26. Curved footing part, 27...Rising part, 11 FL,
1 l b, 11 c, 11 d...ventilation opening section, 11θ... general foundation section. Applicant Mizawa Pom Co., Ltd. 4th J

Claims (1)

【特許請求の範囲】[Claims] 建築の布基礎を構築する方法であって、予め換気口部の
換気口部配筋ユニットと該換気口…;を除く一般基礎部
の一般基礎部配筋ユニットとを形成しておき、布基礎を
構築する根切mlを掘削し、その根切溝にまず′上記一
般基礎ffl!配筋ユニットを設置して布基礎のフーチ
ング部にコンクリートを打設し、資I゛搬入用の通路と
すべき換気口部を残して順次上記換気口部配筋ユニット
を設置するとともに、資旧搬入用の通路とずべき換気口
部以外の換気口1’tls及び一般基礎部の布基礎の立
上シ部を形成し、最後に通路となった換気口部に上記換
気口とをIh徴とする建築布基礎の構築方法。
A method for constructing a cloth foundation for a building, in which a ventilation opening reinforcement unit for a ventilation opening and a general foundation reinforcement unit for a general foundation excluding the ventilation opening are formed in advance, and Excavate the root cutting ml to construct the root cutting groove, and first install the above general foundation ffl! Reinforcement units are installed and concrete is poured into the footings of the cloth foundation, and the ventilation opening reinforcement units are installed one after another, leaving the ventilation openings that should be used as passageways for bringing in materials. 1'tls of the ventilation openings other than the ventilation openings that should be placed in the passageway for delivery and the rising part of the cloth foundation of the general foundation part are formed, and finally the above ventilation openings are installed in the ventilation opening part that becomes the passageway. How to construct a building fabric foundation.
JP57139358A 1982-08-11 1982-08-11 Construction of strip footing for building Pending JPS5931319A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP57139358A JPS5931319A (en) 1982-08-11 1982-08-11 Construction of strip footing for building

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP57139358A JPS5931319A (en) 1982-08-11 1982-08-11 Construction of strip footing for building

Publications (1)

Publication Number Publication Date
JPS5931319A true JPS5931319A (en) 1984-02-20

Family

ID=15243463

Family Applications (1)

Application Number Title Priority Date Filing Date
JP57139358A Pending JPS5931319A (en) 1982-08-11 1982-08-11 Construction of strip footing for building

Country Status (1)

Country Link
JP (1) JPS5931319A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS6286232A (en) * 1985-10-11 1987-04-20 Mitsui Constr Co Ltd Foundation structure for building
JP2022074648A (en) * 2020-11-05 2022-05-18 株式会社エルフホールデイングス Construction method of underground beam

Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS607406U (en) * 1983-06-27 1985-01-19 株式会社 豊善金属 Turnbuckle

Patent Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS607406U (en) * 1983-06-27 1985-01-19 株式会社 豊善金属 Turnbuckle

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS6286232A (en) * 1985-10-11 1987-04-20 Mitsui Constr Co Ltd Foundation structure for building
JP2022074648A (en) * 2020-11-05 2022-05-18 株式会社エルフホールデイングス Construction method of underground beam

Similar Documents

Publication Publication Date Title
US4005582A (en) Method of constructing underground concrete walls and reinforcement cage therefor
CN110056722A (en) A kind of drainage pipeline and its construction method
CN108166531A (en) Basic alter-pouring strips mould plate and the construction method for pouring post-cast strip
CN107558603A (en) A kind of assembled arthitecutral structure system and its construction method
US4055927A (en) Concrete walls and reinforcement cage therefor
CN110080287A (en) A kind of assembled flat-top has the open cutting construction method of column underground structure
CN110080295A (en) A kind of lid of assembled vault greatly across no column underground structure digs full-reverse construction method
CN114215114A (en) Cantilever plate peripheral water distribution construction structure and construction method
KR100758504B1 (en) Method of construction for underground diaphragm wall and underground diaphragm wall structure
CN109778903A (en) A kind of detachable assembling type reinforced concrete retaining wall structure and construction method
CN210768799U (en) Main body structure construction system at intersection of main line tunnel and construction transverse channel
JPS5931319A (en) Construction of strip footing for building
KR101974826B1 (en) The Precast Pile Having Interlocking Secant and The Earth Retaining Wall Method Constructed by It's Continuous Pile
CN110080288A (en) A kind of open cutting construction method of assembled vault greatly across no column underground structure
CN206220558U (en) Old City Wall door opening ruggedized construction
CN215210384U (en) Slip form concrete pouring device for drainage ditch
CN210768793U (en) Two-lining construction system at intersection of main tunnel and double-layer construction transverse channel
CN208870043U (en) On the anti-pit accident across existing tunnel ruggedized construction
CN207265620U (en) A kind of cable installation support of armored concrete electric power pipe trench
JPH09151470A (en) Work execution method for underground structure
CN206477251U (en) Transverse prestress overall with reinforced concrete bridge deck plate prefab-form system
JPH03228921A (en) Execution method for concrete foundation work
CN211816452U (en) Underground garage backfill soil foundation post-cast strip seals earlier and constructs structure afterwards
JPH10299003A (en) Foundation work using precast concrete member
JP2539736B2 (en) Fabric foundation construction method and formwork support used for it