JPS5855285B2 - Corrosion protection method for structures in bank protection work and corrosion protection cover used therefor - Google Patents
Corrosion protection method for structures in bank protection work and corrosion protection cover used thereforInfo
- Publication number
- JPS5855285B2 JPS5855285B2 JP2400178A JP2400178A JPS5855285B2 JP S5855285 B2 JPS5855285 B2 JP S5855285B2 JP 2400178 A JP2400178 A JP 2400178A JP 2400178 A JP2400178 A JP 2400178A JP S5855285 B2 JPS5855285 B2 JP S5855285B2
- Authority
- JP
- Japan
- Prior art keywords
- steel pipe
- corrosion
- cylindrical cover
- pipe pile
- cover
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired
Links
Description
【発明の詳細な説明】
本発明は、海岸、河川湖沼等の護岸工事にpける構築物
に防蝕処理を効果的に与える方法と、その方法を実施す
る上で用いられる防蝕カバーに関するものである。DETAILED DESCRIPTION OF THE INVENTION The present invention relates to a method for effectively imparting anti-corrosion treatment to structures used in revetment work for seashores, rivers, lakes, etc., and a corrosion-resistant cover used in carrying out the method.
海岸、河Ill湖沼等の護岸構築物は、水位の変動によ
って乾湿交互の影響を受けることは避は得ないことであ
る。It is inevitable that shore protection structures such as coasts, rivers, lakes, and marshes are affected by alternating wet and dry conditions due to fluctuations in water level.
海岸では潮位や波浪の変化により、河川では主として流
量変化により、また湖沼等にあっては、貯水状態の変化
によって護岸部分の水中にある部分と水面より上にある
部分が常に変化することは周知の通りである。It is well known that the parts of the seawall that are underwater and the parts that are above the water surface constantly change due to changes in the tide level and waves on the coast, mainly due to changes in the flow rate in rivers, and changes in water storage conditions in lakes and marshes. It is as follows.
一方護岸工事の構築物は主として鋼板等の矢板類や鋼管
杭等の打込み部材を以って成り、これらにあっては、常
時水面より上にある部分と常時水中にある部分とは比較
的腐蝕を受けることは少いが、乾湿交互の状態にかかれ
る部分は、酸化され易くこれによって腐蝕する。On the other hand, structures for bank protection work mainly consist of sheet piles such as steel plates and driven members such as steel pipe piles, and the parts that are always above the water surface and the parts that are always underwater are relatively free from corrosion. Although this is not often the case, parts that are exposed to alternating wet and dry conditions are susceptible to oxidation and corrosion due to this.
このために、変動水位の領域を超える部分に対し何等か
の防蝕工事を施さないと経年的な護岸機能を維持できな
いことになる。For this reason, the bank protection function cannot be maintained over time unless some kind of anti-corrosion work is carried out in areas that exceed the area of fluctuating water levels.
この防蝕工事には、主としてプラスチック製のカバーが
用いられ、プラスチックに固有の耐腐蝕性が活用される
ことになる。For this corrosion protection work, plastic covers are mainly used, and the inherent corrosion resistance of plastics is utilized.
然しプラスチックそれ自体は鋼板や鋼管等のように外部
からの衝撃に対し高い強度を有しないので、一般にこの
種防蝕用に供せられるプラスチックとしては、ファイバ
ーリインフォーストプラスチック(繊維強化樹脂:FR
Pと略称される)が用いられ、更にこれを用いてその強
化構造が施されるのが普通である。However, plastic itself does not have high strength against external impacts like steel plates and pipes, so fiber reinforced plastic (FR: FR) is generally used as a plastic for this type of corrosion protection.
(abbreviated as P) is used, and the reinforcing structure is usually provided using this.
鋼管を用いた施設、例えば、護岸、桟橋支柱等にあって
最も普通に用いられて米た構造は、上記水位変動領域で
あるその上限及び下限を超える範囲に亘って円筒状のF
RPカバーを嵌込み占位させ、鋼管との間隙に適当なス
ペーサーを介在させてかき、且つ該筒状カバーの下端で
適当なモルタル流失対策ヲ構してかいて鋼管とカバーと
の間にモルタルを注入充填し、これを固化させたもので
ある。The most commonly used structure in facilities using steel pipes, such as seawalls and pier supports, is a cylindrical F-shaped structure that extends beyond the upper and lower limits of the above water level fluctuation range.
The RP cover is fitted and positioned, an appropriate spacer is interposed in the gap with the steel pipe, and an appropriate measure against mortar flow is provided at the lower end of the cylindrical cover to prevent mortar from flowing between the steel pipe and the cover. is injected and filled, and this is solidified.
本発明の防蝕方法も個々の鋼管杭についてはこの一般的
防蝕構造の例に倣うものではあるが、個個に打込1れた
鋼管杭相互の間の隙間をなくして波浪や水流等によって
護岸部が削られたり崩壊することを未然に防止するのに
役立つ新規な方法を提供するものであって、殊に擁壁と
なる護岸主体たる打込み鋼管杭の列線より内側、つ1す
、鋼管杭の打設ラインより陸上側で列設鋼管杭の隙間か
ら打設ラインの内側に侵入する水が護岸主体たる鋼管杭
擁壁によって土留めされている土砂類を侵蝕したり崩壊
させたりすることのないように配慮しである。The corrosion protection method of the present invention also follows the example of this general corrosion protection structure for individual steel pipe piles, but it eliminates the gaps between the individually driven steel pipe piles and prevents seawalls from being damaged by waves, water currents, etc. The present invention provides a new method that helps to prevent parts from being scraped or collapsed, and is particularly useful for preventing steel pipe piles from being scraped or collapsing on the inner side of the rows of driven steel pipe piles, which are the main component of retaining walls. On the land side of the pile driving line, water that enters the inside of the driving line through gaps between rows of steel pipe piles will not erode or collapse the earth and sand that is retained by the steel pipe pile retaining wall, which is the main part of the seawall. This is a consideration.
更に、そのような防蝕と、土砂の侵蝕崩壊防止との両目
的を一挙に解決するに当って、本発明では単一種類の筒
状カバーによって広く施工現場に固有の条件や、施工上
腕は得ぬ工事上の条件を克服するようになされた点に重
要な特徴を有し、寸法の異なる多種類の円筒状カバーを
準備し、施工現場へ持ち込むという生産上の煩雑さや現
場作業の複雑性を改善するものである。Furthermore, in order to solve both of the objectives of corrosion prevention and prevention of erosion and collapse of earth and sand at once, the present invention uses a single type of cylindrical cover that can widely accommodate the conditions unique to the construction site and the advantages of construction work. The important feature is that it has been designed to overcome the construction conditions that require it, and the production process of preparing and transporting various types of cylindrical covers with different dimensions to the construction site, as well as the complexity of on-site work. It is something to improve.
以下図面に示すところから、本発明を更に詳しく説明す
ると、第1図は理想的状態で鋼管杭が擁壁を形成してい
る護岸例を示している。The present invention will be explained in more detail from what is shown in the drawings below. Fig. 1 shows an example of a seawall in which steel pipe piles form a retaining wall in an ideal state.
図中11は打込1れた鋼管杭であり、これらは総て均等
な中心間隔Sを以って打込1れてあ・す、これら各鋼管
杭11に嵌込1れたFRP円筒カバー12は何れも同じ
直径Rを有し、各円筒カバー12は互に隣れる円筒カバ
ー12と密接を保ち、各鋼管杭11と各円筒カバー12
との間にはモルタル等の結着固化材13が注入充填され
て一体化され、その結果防蝕工事を施工した後の護岸擁
壁には海水や水が水側Wより陸側りに入り込む余地のな
いように形成されている。In the figure, reference numeral 11 indicates driven steel pipe piles, and these are all driven with equal center spacing S. FRP cylindrical covers are fitted into each of these steel pipe piles 11. 12 have the same diameter R, each cylindrical cover 12 is in close contact with the adjacent cylindrical cover 12, and each steel pipe pile 11 and each cylindrical cover 12 are in close contact with each other.
A binding and solidifying material 13 such as mortar is injected and integrated between the walls, and as a result, there is room for seawater and water to enter from the water side W to the land side of the seawall after the corrosion protection work has been carried out. It is formed so that there is no
従ってこの場合には、準備すべきFRP円筒カバー12
の外径Rと、打込み鋼管杭11の中心間間隔Sとの間に
は、
R=S
の関係が与えられるから、鋼管杭の打込み間隔に相当す
る外径をもった円筒カバーを多数準備すれば用が足りる
ことは自明である。Therefore, in this case, the FRP cylindrical cover 12 to be prepared
Since the relationship R=S is given between the outer diameter R of the driven steel pipe piles 11 and the center-to-center spacing S of the driven steel pipe piles 11, it is necessary to prepare a large number of cylindrical covers with outer diameters corresponding to the driven spacing of the steel pipe piles. It is self-evident that this is sufficient.
つ1り護岸主体となる打込み鋼管杭は正確に均等間隔を
以って配置されているので、このような鋼管杭11の列
線を以って施工され、または施工されている場合にあっ
ては、同一の直径からなる円筒カバー12の一種類多数
を予め準備し、各杭11に嵌込んで、円筒カバー12相
互の間に隙間のできないようにすることが可能となる。The driven steel pipe piles that form the main part of the revetment are arranged at exactly equal intervals, so if the steel pipe piles 11 are constructed or are being constructed along the row lines of the steel pipe piles 11, In this case, it is possible to prepare a large number of one type of cylindrical covers 12 having the same diameter in advance and fit them onto each pile 11 so that there are no gaps between the cylindrical covers 12.
然し乍ら、現実には、このように理想的配列を以って鋼
管杭を打込むことは至難であり、または打込1れた状態
にあることも殆んどなく、打込み部分の地下構造によっ
て岩床その他の影響から不斉−な間隔を生じてし−t5
ものである。However, in reality, it is extremely difficult to drive steel pipe piles in such an ideal arrangement, or they are almost never completely driven, and the underground structure of the driven part is difficult to drive, and the piles are not easily driven into the rock bed. Other influences may cause asymmetric spacing.
It is something.
その極端な実例を第2図を以って示しである。An extreme example of this is shown in FIG.
現実の施工作業では第2図のようなひどい不均分間隔と
なることはないが、同図では、本発明をより理解し易い
ように極端な例を以って示しである。In actual construction work, such severe unequal spacing as shown in FIG. 2 does not occur, but this figure shows an extreme example to make it easier to understand the present invention.
この場合、本来意図した鋼管杭11の打込み間隔Sに対
し、施工現場の状況や、施工作業によって不可避の人為
的誤差の結果、各鋼管杭11の中心間隔は、
S1〆S2/S3/・・・・・・・・・・・・となり、
このような状態にあっては用いるべき防蝕カバー12に
ついてその外径を一律には定め得ないこととなる。In this case, as a result of the construction site conditions and unavoidable human errors due to construction work, the center spacing of each steel pipe pile 11 is S1〆S2/S3/... with respect to the originally intended driving interval S of the steel pipe piles 11.・・・・・・・・・・・・
In such a situation, it is not possible to uniformly determine the outer diameter of the corrosion-resistant cover 12 to be used.
そこで、本発明では、従前円筒カバーを以って防蝕工事
に供していた思想から脱脚し、長径aと短径すとを有す
る楕円形または長円形の断面形状から成る筒状カバーC
を採用することにした。Therefore, in the present invention, we have departed from the idea that conventional cylindrical covers were used for corrosion protection work, and have developed a cylindrical cover C having an elliptical or oblong cross-sectional shape having a major axis a and a minor axis.
I decided to adopt.
その詳細は第3A図及び第3B図に拡大横断平面図を以
って示しであるが、倒れの場合も中心を過ぎる直径がそ
の方向によって異なり、最大径がaであり最小径がbで
あるような非円形断面をもっている。The details are shown in enlarged cross-sectional plan views in Figures 3A and 3B, but even in the case of collapse, the diameter passing the center varies depending on the direction, and the maximum diameter is a and the minimum diameter is b. It has a non-circular cross section.
第3A図及び第3B図にあ・いて、22は筒状カバーC
の筒状壁であり、32はその下端部に一体的に形成し、
または別体を以って取付けた底体であり、同底体32に
は、鋼管杭11の外径Pより僅かに大きな真円形の透孔
52をあけである。In Fig. 3A and Fig. 3B, 22 is a cylindrical cover C.
is a cylindrical wall, 32 is integrally formed at the lower end thereof,
Alternatively, the bottom body 32 is attached as a separate body, and the bottom body 32 has a perfectly circular through hole 52 slightly larger than the outer diameter P of the steel pipe pile 11.
そして透孔52の周縁には合成ゴムその他の弾力性ある
環状または環状に配置されるシール部材42を接着また
はボルト締め等によって接合しである。A sealing member 42 made of synthetic rubber or other elastic material and arranged in an annular or annular shape is bonded to the periphery of the through hole 52 by adhesive, bolting, or the like.
シール部材42の内径rと、鋼管杭11のの外径Pと、
透孔52の孔径りとの関係は、となっている。The inner diameter r of the seal member 42, the outer diameter P of the steel pipe pile 11,
The relationship with the hole diameter of the through hole 52 is as follows.
このような楕円形断面または長円形断面からなる筒状カ
バーCは、その底体32に鋼管杭11の外径Pより僅か
に大きな孔径をもつ透孔52を有するので、鋼管杭11
に対して常法の如く嵌込み作業を行うと無理なく嵌装さ
れ、鋼管杭11を中心に適宜回動させ得る状態となる。The cylindrical cover C having such an elliptical or oblong cross section has a through hole 52 in its bottom body 32 with a hole diameter slightly larger than the outer diameter P of the steel pipe pile 11.
If the fitting operation is carried out as usual, the fitting will be done without any difficulty, and it will be possible to rotate the steel pipe pile 11 as appropriate.
この際内径rが鋼管杭11の外径Pよりも小さなシール
部材42は、第4図に示すように嵌込みと同時にめくり
上げられて反曲し、鋼管杭11との密接を保つ。At this time, the seal member 42, whose inner diameter r is smaller than the outer diameter P of the steel pipe pile 11, is flipped up and curved at the same time as it is fitted, as shown in FIG. 4, to maintain close contact with the steel pipe pile 11.
第4図は、互に隣れる2本の鋼管杭11に対して本発明
の筒状カバー〇を嵌込んだ状態を一部縦断正面図を以っ
て示しである。FIG. 4 is a partially longitudinal front view showing a state in which the cylindrical cover 〇 of the present invention is fitted into two adjacent steel pipe piles 11.
筒状カバー〇は、第4図K>いて、水位変動の最上限を
WHLで示し、その最下限をWLLで示す高さの領域H
を超えてその上方及び下方に亘って占位するように位置
づけ、適当な懸吊乃至支持手段、例えば筒状カバーCの
外側からこれを支持するか、筒状カバーCの上縁に予め
取付けて釦く懸吊フックを利用して支持し、鋼管杭11
と筒状カバーCとの間にモルタル等の結着固化材13を
注入充填して鋼管杭11と筒状カバーCとの一体固結化
を行うが、本発明の方法では、このモルタル等の結着固
化材13の充填に先立って、各鋼管杭11に嵌込んだ筒
状カバー〇を夫々の鋼管杭11の周囲で回動し、第2図
に示すように互に隣れる筒状カバーCが互に密接するよ
うに位置定めをする。The cylindrical cover 〇 is located in the height area H shown in Fig. 4 K>, with the highest limit of water level fluctuation indicated by WHL and the lowest limit indicated by WLL.
It is positioned so as to extend above and below the cylindrical cover C, and is supported by appropriate suspension or support means, for example, from the outside of the cylindrical cover C, or by being attached in advance to the upper edge of the cylindrical cover C. Support using a button hanging hook, steel pipe pile 11
The steel pipe pile 11 and the cylindrical cover C are integrally consolidated by injecting and filling a binding and solidifying material 13 such as mortar between the steel pipe pile 11 and the cylindrical cover C, but in the method of the present invention, this mortar etc. Prior to filling the binding and solidifying material 13, the cylindrical covers fitted into each steel pipe pile 11 are rotated around each steel pipe pile 11, and the cylindrical covers adjacent to each other are separated as shown in FIG. Position C so that they are in close contact with each other.
第2図及び第4図にかいて符号Qで示しである部分は、
互に隣れる筒状カバーC2Cが互に垂直な線で接触する
部分である。The part indicated by the symbol Q in FIGS. 2 and 4 is
This is a portion where adjacent cylindrical covers C2C contact each other along a perpendicular line.
このような相互接触をさせた状態で各鋼管杭11と筒状
カバーCとの間に適当なスペーサー23を介在させてか
き、更に必要あれば陸側りに各筒状カバーCに対して外
側より圧接する土砂を緩く埋め込んで各筒状カバーCの
向きが変らぬように保持してかく。In this state of mutual contact, an appropriate spacer 23 is interposed between each steel pipe pile 11 and the cylindrical cover C, and if necessary, an outer spacer is placed between each steel pipe pile 11 and the cylindrical cover C on the land side. Loosely embed earth and sand that will press against the cover to hold each cylindrical cover C so that its orientation does not change.
斯くして、モルタル等の結着固化材13を注入充填して
その固化を持つと、各鋼管杭11とこれらに嵌込1れた
各筒状カバーCとは夫々一体的に結着し、乾湿交互の状
態に曝される鋼管杭11の部分は、その外周がプラスチ
ック等の耐腐蝕性の筒状カバーCによって覆われること
になるから、鋼管杭11は経年的な腐蝕から保護される
ことになり、施工された鋼管杭11の列線より陸側りに
ある列線背後に本格的な土砂充填を行い、衝き固めを施
すことによって所要の護岸工事を終了させることができ
る。In this way, when the binding and solidifying material 13 such as mortar is injected and solidified, each steel pipe pile 11 and each cylindrical cover C fitted therein are integrally bound, respectively. The outer periphery of the portion of the steel pipe pile 11 that is exposed to alternating dry and wet conditions is covered with a corrosion-resistant cylindrical cover C made of plastic or the like, so that the steel pipe pile 11 is protected from corrosion over time. Then, the required bank protection work can be completed by carrying out full-scale filling of earth and sand behind the row line on the landward side of the row line of the constructed steel pipe piles 11 and performing ramming.
図に示したものは、護岸工事の一例を示したものである
。The figure shown is an example of bank protection construction.
且つ本発明方法の実施の態様を解り易くするために例示
したが、現実の護岸工事の構築作業にあっては、その多
くが、鋼管杭11の列線より陸側りの部分で、列設され
る鋼管杭11を支持体としてこれに沿う矢板が打込1れ
土留めの役を果すようにしてあり、そのような構築実施
の態様においても、本発明方法は難なく施工され得るこ
とは容易に理解されよう。In addition, although the method of the present invention has been illustrated to make it easier to understand, in actual construction work for seawall work, most of the construction work is done in rows on the landward side of the row line of the steel pipe piles 11. The steel pipe piles 11 are used as supports, and sheet piles are driven along the piles 11 to serve as earth retainers, and it is easy to see that the method of the present invention can be easily implemented even in such construction implementation mode. be understood.
本発明によれば、第2図に示すところとこれに関連する
説明とから既に明らかなように、各鋼管杭11の打込み
によってその列線が正確には一線をなさないようなこと
になっていても、また、各鋼管杭11の打込み間隔S1
.S2.S3・・・が夫夫不揃いで不等間隔となってい
たとしても、各鋼管杭11に嵌込んだ筒状カバーCを適
宜鋼管杭11の外壁の周囲に沿って適当に回動して、外
側に占位すべき各筒状カバーC相互の間を隙間なく列装
することができ、“この調整は、所要の鋼管杭11の打
込み間隔Sが長径aと短径すとの間にあるように造られ
た筒状カバー〇を選定することにより、長径aと短径す
の差の範囲を活用して適当に行うことができる。According to the present invention, as is already clear from the view shown in FIG. 2 and the related explanation, the row lines of the steel pipe piles 11 do not line up exactly as they are driven. However, the driving interval S1 of each steel pipe pile 11
.. S2. Even if S3... are not aligned and are spaced unevenly, the cylindrical cover C fitted into each steel pipe pile 11 can be appropriately rotated along the outer wall of the steel pipe pile 11. The cylindrical covers C to be placed on the outside can be arranged in a row without gaps between each other, and this adjustment is performed so that the required driving interval S of the steel pipe piles 11 is between the major axis a and the minor axis. By selecting the cylindrical cover 〇 made in this manner, it is possible to carry out the process appropriately by utilizing the range of the difference between the major axis a and the minor axis a.
そして、互に密接列装した筒状カバーCによって護岸面
には隙間を生ずることなく所期の工事を遂行できるから
隙間から侵入する水や波浪によって鋼管杭の列L::に
かける陸側りの土砂の流失や岸の崩壊 防ぐこと
ができて極めて有益である。The cylindrical covers C arranged closely together enable the desired construction work to be carried out without creating gaps on the seawall surface, so water and waves that enter through the gaps can damage the land side of the rows of steel pipe piles L. This is extremely beneficial as it can prevent sediment from being washed away and banks from collapsing.
第4図に示した実施例では、注入するモルタル等の結着
固化材13が、筒状カバー〇の下端より無為に流失して
し1わないように、筒状カバーCの下端に壁体部と一体
に形成した底体32を設けてあって、これに鋼管杭11
の外径Pより僅かに大きな孔径りをもった透孔52をあ
けるとともにとの透孔52の周縁に沿う環状の有弾性シ
ール部材42を設け、同シール部材420通常の内径r
を鋼管杭11の外径Pより僅かに小さくした構成をとっ
ているが、この態様だけが注入充填するモルタル等の結
着固化材13の流失を防ぐ実例と解すべきではない。In the embodiment shown in FIG. 4, a wall is attached to the lower end of the cylindrical cover C so that the binding and hardening material 13 such as mortar to be injected is not washed away from the lower end of the cylindrical cover C. A bottom body 32 is provided integrally with the steel pipe pile 11.
A through hole 52 having a diameter slightly larger than the outer diameter P of the through hole 52 is formed, and an annular elastic seal member 42 is provided along the periphery of the through hole 52, and the seal member 420 has a normal inner diameter r.
Although the structure is such that the diameter P is slightly smaller than the outer diameter P of the steel pipe pile 11, this embodiment should not be interpreted as the only example of preventing the pouring and filling of the bonding and solidifying material 13, such as mortar, from being washed away.
第5図に筒状カバーCの他の実例を示しである。FIG. 5 shows another example of the cylindrical cover C.
同図による筒状カバーCの横断平面図及び、これを用い
た場合の第6図の一部縦断正面図からも解るように、強
い弾性と注入充填されるモルタル等の結着固化材13の
荷重に対する支持力を失わない限りでは、前記実施例に
かける底体32に代ってシール部材62によってこれを
行ってもよい。As can be seen from the cross-sectional plan view of the cylindrical cover C shown in the same figure and the partially longitudinal front view shown in FIG. This may be achieved by using the sealing member 62 in place of the bottom body 32 of the embodiment described above, as long as the ability to support the load is not lost.
シール部材62は、それ自体に鋼管杭11の外径より僅
かに小さな外径をもつ透孔72を穿ってあり、シール部
材62の外周縁は、直接筒状カバーCの筒壁の内側に接
合されている。The seal member 62 itself has a through hole 72 with an outer diameter slightly smaller than the outer diameter of the steel pipe pile 11, and the outer peripheral edge of the seal member 62 is directly joined to the inside of the cylindrical wall of the cylindrical cover C. has been done.
このような構成によれば、鋼管杭11への嵌込みによっ
て前記透孔72の周縁部は事実上めくり上げられて透孔
72の口径が拡大され、反曲したシール部材62によっ
て注入充填されるモルタル等の結着固化材13は流失す
ることなく保持される。According to such a configuration, when the steel pipe pile 11 is fitted into the steel pipe pile 11, the peripheral edge of the through hole 72 is virtually flipped up, the diameter of the through hole 72 is expanded, and the curved seal member 62 is injected and filled. The binding and solidifying material 13 such as mortar is retained without being washed away.
以上述べるように、本発明の方法によれば、既設の護岸
構築物に対しても、新たに構築される護岸の工事にも、
不可避とされる鋼管杭の不斉−間隔打込み作業によく適
合させて、防蝕機能を発揮させ得る他、防蝕工事によっ
て杭間侵入の水による岸の土砂流失及び岸の崩壊を防ぐ
ことが可能でよく所期の目的を達成し、実用上稗益する
ところが多大であり、特に打込み鋼管杭の配列間隔に応
じて数種類もの防蝕用の刀バーを用意する必要なく、よ
く一種類の筒状カバーを以って工事に適応させることが
できるのである。As described above, according to the method of the present invention, both existing seawall structures and newly constructed seawalls can be constructed.
It is well suited for the unavoidable uneven spacing work of driving steel pipe piles, and can exhibit a corrosion-preventing function. In addition, corrosion-proofing work can prevent mud from washing away on the shore and collapse of the shore due to water entering between the piles. It often achieves the intended purpose and has many practical advantages.In particular, it is often possible to use one type of cylindrical cover instead of having to prepare several types of corrosion-proofing bars depending on the arrangement spacing of driven steel pipe piles. Therefore, it can be adapted to construction work.
第1図は理想的な状態で打込み作業の行われた鋼管杭の
列線に対して同一径の防蝕用円筒カバーが適用される理
想例を説明する護岸工事構築例を示す説明用平面図、第
2図は本発明による防蝕工事の実例を示す平面図、第3
A図及び第3B図は本発明方法の実施に供される防蝕用
の筒状カバーの実例を示す拡大横断平面図、第4図は本
発明方法を実施した護岸用構築物の一部を縦断して示す
正面図、第5図は防蝕用の筒状カバーの他の実例を示す
拡大横断平面図、第6図はこの筒状カバーを用いた実例
を示す護岸用構築物の一部を縦断して示す正面図である
。
11・・・鋼管杭、12・・・防蝕用円筒カバー、13
・・・結着固化材、−・a・・・長径、b・・・短径、
C・・・防蝕用筒状カバー、D・・・透孔52の孔径、
L・・・陸側、W・・・水側、Q・・・筒状カバーCの
相互の接触部、22・・・筒状壁、32・・・底体、4
2・・・シール部材、52・・・透孔、62・・・シー
ル部材、72・・・透孔、S・・・鋼管杭11の等しい
間隔、S1v S2 p S3・・・鋼管杭11の不揃
いな間隔、P・・・・・・鋼管杭11の外径R・・・・
・・防蝕用円筒カバーの外径、r・・・・・・シール部
材の内径。FIG. 1 is an explanatory plan view showing an example of construction of a seawall construction, which illustrates an ideal example in which corrosion-protective cylindrical covers of the same diameter are applied to rows of steel pipe piles that have been driven under ideal conditions; Fig. 2 is a plan view showing an example of corrosion prevention work according to the present invention;
Figures A and 3B are enlarged cross-sectional plan views showing examples of corrosion-resistant cylindrical covers used in the method of the present invention, and Figure 4 is a longitudinal cross-sectional view of a part of the seawall structure in which the method of the present invention was implemented. FIG. 5 is an enlarged cross-sectional plan view showing another example of a corrosion-resistant cylindrical cover, and FIG. FIG. 11... Steel pipe pile, 12... Corrosion prevention cylindrical cover, 13
... binding solidifying material, - a... major axis, b... minor axis,
C... Corrosion-proofing cylindrical cover, D... Hole diameter of through hole 52,
L...land side, W...water side, Q...mutual contact part of cylindrical cover C, 22... cylindrical wall, 32... bottom body, 4
2... Seal member, 52... Through hole, 62... Seal member, 72... Through hole, S... Equal spacing of steel pipe piles 11, S1v S2 p S3... Steel pipe piles 11 Irregular intervals, P... Outer diameter R of steel pipe pile 11...
...Outer diameter of the corrosion-proof cylindrical cover, r...Inner diameter of the sealing member.
Claims (1)
多数の鋼管杭を以って不斉−な列線となっている護岸部
に対し、長径と短径をもつ非円形断面の耐蝕性筒状カバ
ーを各鋼管杭に嵌込み、嵌込んだ該筒状カバーの各々を
各鋼管杭の周囲で回動し、互に隣れる該筒状カバーを相
互に密着させて各鋼管杭とこれに嵌込まれた該筒状カバ
ーの各々との間にモルタル等の結着材を注入充填してこ
れらを一体に固化させることを特徴とする護岸工事の構
築物に対する防蝕方法。 2 不等間隔を以って打込1れ、または打込1れている
多数の鋼管杭を以って不斉−な列線となっている護岸部
に対し各鋼管杭に嵌込1れる耐蝕性筒状カバーであって
、該筒状カバーは長径と短径とを具備し、上記嵌込みの
後に各鋼管杭の周囲を回動することにより互に隣れる嵌
込み筒状カバーとの間に隙間なく互に密着させ得るよう
に構成されていることを特徴とする護岸工事の構築物に
用いる防蝕用カバー。 3 耐蝕性筒状カバーが、その下端に底体を具工、同底
体には嵌込むべき鋼管杭の外径より僅かに大きな孔径の
円形の透孔をめけである特許請求の範囲第2項に記載の
護岸工事の構築物に用いる防蝕用カバー。 4 耐蝕性筒状カバーが、その下端に底体を具え同底体
には嵌込むべき鋼管杭の外径より僅かに大きな孔径の円
形の透孔をあけてあり、その周縁に嵌込むべき鋼管杭の
外径より僅かに小さな内径をもつ環状をなすシール材を
具備させてなる特許請求の範囲第2項に記載の護岸工事
の構築物に用いる防蝕用カバー。 5 耐蝕性筒状カバーが、その下端に有弾性の底体を具
え、同底体には嵌込むべき鋼管杭の外径より僅かに小さ
な孔径の円形の透孔をあけである特許請求の範囲第2項
に記載の護岸工事の構築物に用いる防蝕カバー。[Scope of Claims] 1. For a revetment part where a large number of steel pipe piles are driven at irregular intervals or are driven in rows in asymmetric rows, A corrosion-resistant cylindrical cover with a non-circular cross section having a short diameter of A seawall construction work characterized by injecting and filling a binding material such as mortar between each steel pipe pile and each of the cylindrical covers fitted into each pile to solidify them together. Corrosion prevention method for structures. 2.For revetment areas where a large number of steel pipe piles are driven at uneven intervals or are driven in uneven rows, each steel pipe pile is inserted into the pile. A corrosion-resistant cylindrical cover, the cylindrical cover has a major axis and a minor axis, and is rotated around each steel pipe pile after the above-mentioned fitting, so that the cylindrical cover is connected to the adjacent fitting cylindrical cover. A corrosion-resistant cover for use in a structure for bank protection work, characterized in that it is configured so that it can be brought into close contact with each other without any gaps. 3. The corrosion-resistant cylindrical cover is provided with a bottom body at its lower end, and the bottom body is provided with a circular through hole having a diameter slightly larger than the outer diameter of the steel pipe pile into which it is to be fitted. Corrosion-prevention cover used for structures for bank protection work described in Section 1. 4. The corrosion-resistant cylindrical cover has a bottom body at its lower end, and the bottom body has a circular through hole with a diameter slightly larger than the outer diameter of the steel pipe pile to be fitted into, and the steel pipe to be fitted to the periphery of the hole. 3. A corrosion-protective cover for use in a structure for bank protection work according to claim 2, which is provided with an annular sealing material having an inner diameter slightly smaller than the outer diameter of the pile. 5. Claims in which the corrosion-resistant cylindrical cover is provided with an elastic bottom body at its lower end, and the bottom body is provided with a circular through-hole having a diameter slightly smaller than the outer diameter of the steel pipe pile into which it is to be fitted. Corrosion-proof cover used for the structure of the bank protection work described in paragraph 2.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2400178A JPS5855285B2 (en) | 1978-03-01 | 1978-03-01 | Corrosion protection method for structures in bank protection work and corrosion protection cover used therefor |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2400178A JPS5855285B2 (en) | 1978-03-01 | 1978-03-01 | Corrosion protection method for structures in bank protection work and corrosion protection cover used therefor |
Publications (2)
Publication Number | Publication Date |
---|---|
JPS54117130A JPS54117130A (en) | 1979-09-11 |
JPS5855285B2 true JPS5855285B2 (en) | 1983-12-09 |
Family
ID=12126320
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP2400178A Expired JPS5855285B2 (en) | 1978-03-01 | 1978-03-01 | Corrosion protection method for structures in bank protection work and corrosion protection cover used therefor |
Country Status (1)
Country | Link |
---|---|
JP (1) | JPS5855285B2 (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH09292U (en) * | 1996-07-15 | 1997-05-20 | ホシザキ電機株式会社 | Insulated box structure in refrigeration equipment |
Families Citing this family (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPS60123625A (en) * | 1983-12-08 | 1985-07-02 | Watanabe Tsuguhiko | Installation method for preventing corrosion of stay rod |
-
1978
- 1978-03-01 JP JP2400178A patent/JPS5855285B2/en not_active Expired
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH09292U (en) * | 1996-07-15 | 1997-05-20 | ホシザキ電機株式会社 | Insulated box structure in refrigeration equipment |
Also Published As
Publication number | Publication date |
---|---|
JPS54117130A (en) | 1979-09-11 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
AU2006272973A2 (en) | An artificial reef and a method of constructing an artificial reef | |
JPS5855285B2 (en) | Corrosion protection method for structures in bank protection work and corrosion protection cover used therefor | |
JP2009114722A (en) | Repairing and reinforcing structure for aguatic construction | |
JP4109431B2 (en) | Aquatic structure with water play room | |
JP2547932B2 (en) | Mooring columns for floating piers and floating structures | |
US3662559A (en) | Anchorage for boat docks | |
JPH11256553A (en) | Manufacture of artificial bank | |
KR200413124Y1 (en) | Hexapod for prevention against wave abrasion of structure in water | |
JPH09296427A (en) | Structure in water area and construction method thereof | |
GB2297343A (en) | Bag for structuring a dike | |
JPH0551918A (en) | Operation caisson | |
KR100737108B1 (en) | Interlinkage erosion shield device of revetment structure fundamental reinforcement unit materials | |
JP5408725B2 (en) | Symbiotic revetment panel material and symbiotic revetment | |
JPH0426499Y2 (en) | ||
JPH01230808A (en) | Protective buffer body | |
JPH0258614A (en) | Wall body made of steel pipe pile and its constructing method and spacer | |
KR100788950B1 (en) | Hexapod for prevention against wave abrasion of structure in water | |
JPH09158152A (en) | Arch type floating breakwater | |
JP3510366B2 (en) | How to build underwater structures | |
JPS6344007A (en) | Earthquake-proof reinforcing construction for previously constructed structure | |
JP2001003335A (en) | Natural stone connection block and natural stone connection structure | |
JP3030571B2 (en) | Outer shell of offshore structure and construction method of offshore structure | |
JPS58160420A (en) | Levee body using king post | |
JPS62276112A (en) | Artificial reef and its manufacture | |
JPS6237408A (en) | Scour-proof construction for embankment |