JPS5841374B2 - Foundation pile stabilization method and device - Google Patents
Foundation pile stabilization method and deviceInfo
- Publication number
- JPS5841374B2 JPS5841374B2 JP4265979A JP4265979A JPS5841374B2 JP S5841374 B2 JPS5841374 B2 JP S5841374B2 JP 4265979 A JP4265979 A JP 4265979A JP 4265979 A JP4265979 A JP 4265979A JP S5841374 B2 JPS5841374 B2 JP S5841374B2
- Authority
- JP
- Japan
- Prior art keywords
- pile
- ground
- hollow
- tip
- friction cutter
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired
Links
Landscapes
- Piles And Underground Anchors (AREA)
- Placing Or Removing Of Piles Or Sheet Piles, Or Accessories Thereof (AREA)
Description
【発明の詳細な説明】 本発明は、一般に、くい基礎工法に関するものである。[Detailed description of the invention] TECHNICAL FIELD The present invention generally relates to pile foundation construction methods.
従来、くい基礎工法としては、ドロップハンマまたはデ
ィーゼルハンマ等で、くいの頭部を直接打撃して、くい
を設置する工法、およびバイブロハンマ等の振動および
共振の力を利用して、くいを設置する工法が採用されて
いた。Conventional pile foundation construction methods include installing piles by directly hitting the head of the pile with a drop hammer or diesel hammer, and installing piles using the vibration and resonance force of a vibro hammer. method was used.
しかし、これらの工法は、最近の大きな社会問題となっ
ている騒音および振動公害を伴うため、近年では、くい
の設置地盤を掘削した後、セメントミルク等を注入し、
そこに、くいを建て込むセメントミルク注入工法、およ
び中空くいの中空部にスクリューオーガ等を挿入し、く
い先端の地盤を掘削し、その掘削土をくいの中空部を経
て排土するとともに、くいを地盤中に沈設する中掘工法
が施工されるようになった。However, these construction methods involve noise and vibration pollution, which have become major social problems in recent years, so in recent years, after excavating the ground where the piles are to be installed, cement milk, etc. is poured into the construction method.
There, the cement milk injection method involves building piles, and inserting a screw auger etc. into the hollow part of the hollow pile, excavating the ground at the tip of the pile, and discharging the excavated soil through the hollow part of the pile. The medium excavation method, in which the material is sunk into the ground, has begun to be used.
これらの工法は、無振動無騒音工法であるので、公害問
題の解消に寄与するものであるが、前者のセメントミル
ク注入工法は、地盤の掘削、セメントミルクの注入およ
びくいの建て込みの各工程が同時に行なわれず、そのた
めに、多くの施工時間がかかり、また掘削孔壁が崩壊し
、かつくいの継ぎ足しが困難である点で、近年のくいの
長尺化の傾向には、不向きである。Since these construction methods are vibration-free and noise-free construction methods, they contribute to resolving pollution problems. However, the former cement milk injection method requires each step of excavating the ground, pouring cement milk, and erecting piles. This method is not suitable for the recent trend toward longer piles, as the piles are not carried out at the same time, which requires a lot of construction time, and the walls of the borehole collapse, making it difficult to add thicker piles.
次に後者の中掘工法は、くい設置地盤をオーガ等で、か
き乱すため、くい外周と地盤との間の局面摩擦力が失わ
れ、さらに掘削土の削り屑であるスライムの処理が充分
に行なわれず、そのスライムの蓄積等でくい先端地盤が
軟弱化し、その結果、充分な支持力が打撃工法に比べ期
待できない欠点を有していた。Secondly, in the latter method, the ground where the pile is installed is disturbed with an auger, etc., so the surface friction force between the outer circumference of the pile and the ground is lost, and the slime, which is the shavings of the excavated soil, is not sufficiently disposed of. However, the soil at the tip of the pile becomes soft due to the accumulation of slime, etc., and as a result, it has the disadvantage that sufficient bearing capacity cannot be expected compared to the impact method.
なお、近年スクリューオーガのシャフトを利用してオー
ガ先端からセメントミルク等の硬化剤を噴射させて、く
い先端部分を硬化剤で球根状に包み、くい先端部周辺地
盤を補強することで支持力を得ようとする工夫がなされ
てきているが、まだ、くい周面摩擦力の回復の工夫がな
されておらず、したがって、まだ、くいの安定設置とは
いえない状況である。In addition, in recent years, the shaft of a screw auger has been used to inject a hardening agent such as cement milk from the tip of the auger, wrapping the tip of the pile in a bulbous shape and reinforcing the ground around the tip of the pile to increase its supporting capacity. Although efforts have been made to achieve this, no measures have been taken to recover the friction force on the pile's circumferential surface, and therefore the situation is still far from being able to say that the pile is installed stably.
本発明の目的は、上記欠点を解消し、施工時間が比較的
に短く、かつくい外周と地盤とを硬化剤で容易に一体化
できる基礎くいの安定法およびそのための装置を提供す
ることである。It is an object of the present invention to provide a method for stabilizing foundation piles that eliminates the above-mentioned drawbacks, allows for relatively short construction time, and allows easy integration of the hard outer periphery and the ground using a hardening agent, and a device therefor. .
上記目的を遠戚するために本発明によれば、以下のよう
な基礎くい安定法およびその装置が提供される。In order to achieve the above object, the present invention provides the following basic pile stabilization method and device.
(1)中空くいの先端部に当る地盤を掘削し、その掘削
土を、くい中空部を経て排土するとともに、くいを地盤
中に沈設する中掘工法を施工するに際し、硬化剤噴出装
置を収容し、かつくい先端部外周に取付けたフリクショ
ンカッタによって、くい沈設中のくい外周と地盤との間
の摩擦力を切るとともに、くいを沈設し、くいが所定位
置に達したとき、上記硬化剤噴出装置のみを、くい外周
に沿ってその長手方向に引き上げるとともに、上記硬化
剤噴出装置から硬化剤を噴出させ、くい外周と地盤との
間に硬化剤を充填することを特徴とする基礎くいの安定
法。(1) When carrying out the hollow excavation method, in which the ground corresponding to the tip of a hollow pile is excavated, the excavated soil is discharged through the hollow part of the pile, and the pile is sunk into the ground, a hardening agent injection device is used. A friction cutter attached to the outer periphery of the stiff tip of the pile cuts the frictional force between the outer periphery of the pile and the ground while the pile is being lowered, and when the pile reaches the specified position, the hardening agent A foundation pile characterized in that only the spouting device is pulled up in the longitudinal direction along the outer periphery of the pile, and the hardener is jetted from the hardener spouting device to fill the space between the outer periphery of the pile and the ground. Stability method.
(2)沈設すべき中空くいの先端部外周に取付けるため
のフリクションカッタと、上記フリクションカッタ内に
収容され、かつ上記フリクションカッタから取り外され
て、くい外周に沿ってその長手方向において移動できる
硬化剤噴出装置と、上記硬化剤噴出装置の移動を行なう
ための機構とよりなることを特徴とする基礎くいを安定
させるための装置。(2) A friction cutter to be attached to the outer periphery of the tip of the hollow pile to be sunk, and a hardening agent that is housed in the friction cutter and can be removed from the friction cutter and moved in the longitudinal direction along the outer periphery of the pile. 1. A device for stabilizing a foundation pile, comprising a jetting device and a mechanism for moving the curing agent jetting device.
次に本発明の実施例を、図面を参照して以下に説明する
。Next, embodiments of the present invention will be described below with reference to the drawings.
第1,5,6および7図に示したように、フリクション
カッタ1は、中空くいPの先端部外周に嵌合できる環形
のフリクションカッタ本体2と、くいPの先端面に当る
平板部分3とよりなり、フリクションカッタ本体2は、
その内部に空洞部分4を有し、空洞部分4の上部は開口
5され、空洞部分4の下部には、環形本体2の円周に沿
って複数の硬化剤出口6が設けられ、出口6の下面には
、下方のみに開くことができる弁7がピン8によって軸
着されている。As shown in Figures 1, 5, 6, and 7, the friction cutter 1 includes an annular friction cutter body 2 that can fit around the outer periphery of the tip of a hollow pile P, and a flat plate portion 3 that comes into contact with the tip surface of the pile P. The friction cutter body 2 consists of
It has a hollow part 4 inside thereof, the upper part of the hollow part 4 is opened 5, and the lower part of the hollow part 4 is provided with a plurality of curing agent outlets 6 along the circumference of the annular body 2, and each of the outlets 6 is A valve 7 that can be opened only downward is pivotally attached to the lower surface by a pin 8.
硬化剤噴出装置9は、環形フリクションカッタ本体2の
上部開口5から空洞部分4内に収容できる環形であり、
その内部に空洞部分10を有し、空洞部分10の下部に
は、その円周に沿って等間隔に複数の硬化剤噴出口11
が設けられ、空洞部分10の上部には、硬化剤注入口1
2が設けられ、注入口12には、硬化剤注入ホース13
の下端が連結され、注入ホース13の上端には、適宜の
硬化剤源(図示を省略する)が連結される。The curing agent ejecting device 9 has an annular shape that can be accommodated in the hollow portion 4 from the upper opening 5 of the annular friction cutter body 2,
It has a hollow part 10 inside, and a plurality of curing agent spouts 11 are provided at equal intervals along the circumference at the lower part of the hollow part 10.
A curing agent injection port 1 is provided in the upper part of the cavity portion 10.
A curing agent injection hose 13 is provided at the injection port 12.
A suitable curing agent source (not shown) is connected to the upper end of the injection hose 13 .
硬化剤噴出装置9の上部には、ワイヤ14の下端が連結
され、ワイヤ14の上端は適宜の巻揚機15に連結され
ている。The lower end of the wire 14 is connected to the upper part of the curing agent injection device 9, and the upper end of the wire 14 is connected to a suitable hoist 15.
なお、第8および9図は、硬化剤噴出装置の変形を示す
。Note that FIGS. 8 and 9 show modifications of the curing agent jetting device.
次に本発明による基礎くいの安定法の施工順序を以下に
説明する。Next, the construction order of the method for stabilizing foundation piles according to the present invention will be explained below.
先ず、第1図に示したように、フリクションカッタ本体
2の空洞部分4内に硬化剤噴出装置9を収容したフリク
ションカッタ1の環形フリクション本体2を中空くいP
の先端部外周に嵌合し、中空くいPの先端面にフリクシ
ョンカッタ1の平板部分3を当てておき、開閉できるビ
ット16を先端に有するスクリューオーガ17を、くい
Pの中空部に挿入し、くいPを地盤G上に建て、オーガ
17の先端から水を噴射させながら、くいPの先端部に
当る地盤Gをオーガ17によって掘削し、掘削土をくい
中空部を経て排土するとともに、くいを地盤中に沈設す
る。First, as shown in FIG. 1, the annular friction body 2 of the friction cutter 1, which houses the hardening agent injection device 9 in the hollow portion 4 of the friction cutter body 2, is inserted into the hollow peg P.
The flat plate part 3 of the friction cutter 1 is fitted onto the outer periphery of the tip of the hollow pile P, and the flat plate part 3 of the friction cutter 1 is placed against the tip surface of the hollow pile P, and the screw auger 17 having a bit 16 that can be opened and closed at the tip is inserted into the hollow part of the pile P. A pile P is built on the ground G, and while water is injected from the tip of the auger 17, the ground G corresponding to the tip of the pile P is excavated by the auger 17, and the excavated soil is discharged through the hollow part of the pile. is sunk into the ground.
上記くい沈設中に、フリクションカッタ1は、その平板
部分3がくい先端面に当てであるので、くい沈設ととも
に、フリクションカッタ本体2も地盤中に押し込まれ、
これによって、くい外周の地盤が外側方へ押され、した
がってフリクションカッタ本体2を取り付けた部分より
上方のくい外周すなわちくい外周の大部分と地盤との間
の摩擦力が生じないので、くいPは、容易に沈設される
。During the pile sinking, the friction cutter 1 rests its flat plate portion 3 against the tip of the pile, so the friction cutter main body 2 is also pushed into the ground as the pile is sunk.
As a result, the ground around the outer circumference of the pile is pushed outward, and therefore no frictional force is generated between the outer circumference of the pile above the part where the friction cutter body 2 is attached, that is, the majority of the outer circumference of the pile, and the ground. , easily submerged.
なお、その間、硬化剤出口6の弁7は、土圧によって閉
じられている。Meanwhile, the valve 7 of the curing agent outlet 6 is closed by earth pressure.
次に第2図に示したように、くいPが所定位置に達した
とき、ワイヤ14を引き上げることによって、第3図に
示したように、硬化剤噴出装置9は、フリクションカッ
タ1の空洞部分4の開口5から抜かれて、くい外周に沿
ってその長手方向に引き上げられるとともに、硬化剤噴
出装置9の硬化剤噴出口11からセメントミルク等の硬
化剤Mが噴出される。Next, as shown in FIG. 2, when the peg P reaches a predetermined position, by pulling up the wire 14, the hardening agent injection device 9 is released into the hollow part of the friction cutter 1, as shown in FIG. The hardener M such as cement milk is pulled out from the opening 5 of the pile and pulled up in the longitudinal direction along the outer periphery of the stake, and the hardener M such as cement milk is jetted from the hardener spout 11 of the hardener jetter 9.
なお、その間に、オーガ17を弓き上げる。Meanwhile, the auger 17 is raised.
次に硬化剤噴出装置を地上へ引き上げると、第4図に示
したように、くい外周と地盤との間に硬化剤Mが充填さ
れ、このようにして基礎くいは安定される。Next, when the hardening agent injection device is lifted to the ground, hardening agent M is filled between the outer periphery of the pile and the ground, as shown in FIG. 4, and the foundation pile is thus stabilized.
以上の説明から了解できるように、本発明によれば、地
盤の掘削およびくい建て込みが同時に行なわれ、しかも
、くいの沈設は、容易に行なわれるので、施工時間が短
縮され、またくい先端部分の外側部分およびくい外周と
地盤との間の部分に硬化剤が充填されて、くい周面の摩
擦力が回復されるので、充分な支持力が得られる。As can be understood from the above explanation, according to the present invention, the excavation of the ground and the erection of piles are carried out at the same time, and furthermore, the laying of piles is easily carried out, so the construction time is shortened, and the tip of the pile is The outer part of the pile and the part between the outer periphery of the pile and the ground are filled with a hardening agent to restore the frictional force on the peripheral surface of the pile, so that sufficient supporting force can be obtained.
また本発明によれば、くい先端部に当る地盤の掘削が、
くい沈設に先行し、かつこの地盤が泥水化サレるので、
フリクションカッタ本体が受ける地盤抵抗は少なく、く
いの沈設は容易に行なわれる。Further, according to the present invention, the excavation of the ground that corresponds to the tip of the pile is
Prior to the pile installation, the ground will turn into muddy water.
The friction cutter body receives little ground resistance, and the piles can be easily sunk.
さらに、くい外周の地盤は、フリクションカッタ本体に
よって掘削されているので、その後に行なわれるくい外
周と地盤との間の硬化剤注入充填には、高圧力を必要と
せず、したがって硬化剤注入管等は、金属管とする必要
がなく、ゴムホースで足りる。Furthermore, since the ground around the pile's periphery is excavated by the friction cutter body, high pressure is not required for the subsequent injection and filling of the hardening agent between the pile's outside periphery and the ground, so hardening agent injection pipes, etc. There is no need to use a metal tube; a rubber hose will suffice.
さらに本発明によれば、フリクションカッタは、くいの
先端に取り付けるための構造を有するに過ぎないので、
構造簡単であり、また硬化剤噴出装置は、回収できるた
めに、繰り返し使用でき、全体としては経済的なもので
ある。Furthermore, according to the present invention, since the friction cutter only has a structure for attaching to the tip of the stake,
The structure is simple, and since the curing agent injection device can be recovered, it can be used repeatedly and is economical as a whole.
また軟弱地盤における施工に対しては、例えば、くい周
辺地盤が軟弱のために削孔壁が崩壊し、通常であれば、
くい外周と地盤との間に硬化剤を充填することが不可能
である場合でも、本発明によれば、硬化剤噴出装置の上
昇によって、崩壊土砂を押し上げ、その後の空間に硬化
剤を充填することができる。In addition, for construction on soft ground, for example, the hole wall may collapse due to the soft ground surrounding the pile, and normally,
Even when it is impossible to fill the space between the outer periphery of the pile and the ground with the hardening agent, according to the present invention, the hardening agent ejecting device is raised to push up the collapsed soil and fill the space afterward with the hardening agent. be able to.
また、最近の中掘工法におけるくい先端根固め工法に本
発明を併用すれば、くい設置範囲全域にわたって硬化剤
を充填することができる。Furthermore, if the present invention is used in combination with the recent pile tip hardening method in the medium excavation method, it is possible to fill the entire area of the pile installation area with the hardening agent.
第1図は、本発明による基礎くい安定法の最初の工程中
の状況を示す地盤、中空くいおよびフリクションカッタ
の一部縦断面図であり、第2図は、くいが所定位置へ達
したときの状況を示す地盤、中空くいおよびフリクショ
ンカッタの一部縦断面図であり、第3図は、硬化剤噴出
装置の引き上げ、および硬化剤噴出中の状況を示す地盤
、中空くい、フリクションカッタおよび硬化剤噴出装置
の一部縦断面図であり、第4図は、基礎くい安定法の施
工終了後の状況を示す地盤、中空くいおよびフリクショ
ンカッタの一部縦断面図であり、第5図は、フリクショ
ンカッタの底面図であり、第6図は、中空くい、フリク
ションカッタおよび硬化剤噴出装置の一部縦断面図であ
り、第7図は、同上の一部縦断面図であり、第8図は、
硬化剤噴出装置の変形、中空くいおよびフリクションカ
ッタの一部縦断面図であり、第9図は、硬化剤噴出装置
の別の変形の縦断面図である。
1・・・・・・フリクションカッタ、4・・・・・・フ
リクションカッタの空洞部分、5・・・・・・空洞部分
4の開口、6・・・・・・硬化剤出口、9・・・・・・
硬化剤噴出装置、14・・・・・・硬化剤噴出装置の移
動を行なうための機構、P・・・・・・中空くい、G・
・・・・・地盤、M・・・・・・硬化剤。FIG. 1 is a partial vertical cross-sectional view of the ground, hollow pile, and friction cutter showing the situation during the first step of the foundation pile stabilization method according to the present invention, and FIG. FIG. 3 is a partial longitudinal cross-sectional view of the ground, hollow pile, and friction cutter showing the condition of the ground, hollow pile, and friction cutter, and FIG. FIG. 4 is a partial longitudinal sectional view of the soil, hollow pile, and friction cutter showing the situation after the foundation pile stabilization method is completed; FIG. FIG. 6 is a bottom view of the friction cutter, FIG. 6 is a partial vertical cross-sectional view of the hollow pile, friction cutter, and hardening agent jetting device, FIG. 7 is a partial vertical cross-sectional view of the same as above, and FIG. teeth,
FIG. 9 is a partial vertical cross-sectional view of a modification of the hardening agent jetting device, a hollow peg, and a friction cutter, and FIG. 9 is a longitudinal cross-sectional view of another modification of the hardening agent jetting device. DESCRIPTION OF SYMBOLS 1... Friction cutter, 4... Hollow part of friction cutter, 5... Opening of hollow part 4, 6... Curing agent outlet, 9...・・・・・・
Hardening agent jetting device, 14...Mechanism for moving the hardening agent jetting device, P...Hollow pile, G.
...Ground, M...Hardening agent.
Claims (1)
を、くい中空部を経て排土するとともに、くいを地盤中
に沈設する中掘工法を施工するに際し、硬化剤噴出装置
を収容し、かつくい先端部外周に取付けたフリクション
カッタによって、くい沈設中のくい外周と地盤との間の
摩擦力を切るとともに、くいを沈設し、くいが所定位置
に達したとき、上記硬化剤噴出装置のみを、くい外周に
沿ってその長手方向に引き上げるとともに、上記硬化剤
噴出装置から硬化剤を噴出させ、くい外周と地盤との間
に硬化剤を充填することを特徴とする基礎くいの安定法
。 2 沈設すべき中空(いの先端部外周に取付けるための
フリクションカッタと、上記フリクションカッタ内に収
容され、かつ上記フリクションカッタから取り外されて
、くい外周に沿ってその長手方向において移動できる硬
化剤噴出装置と、上記硬化剤噴出装置の移動を行なうた
めの機構とよりなることを特徴とする基礎くいを安定さ
せるための装置。[Claims] 1. When carrying out the hollow excavation method in which the ground corresponding to the tip of a hollow pile is excavated, the excavated soil is discharged through the hollow part of the pile, and the pile is sunk into the ground, hardening is required. A friction cutter that houses the agent ejecting device and is attached to the outer circumference of the tip of the pile cuts the frictional force between the outer circumference of the pile and the ground while the pile is being set, and when the pile reaches the specified position. , characterized in that only the hardening agent jetting device is pulled up in the longitudinal direction along the outer periphery of the pile, the hardening agent is jetted from the hardening agent jetting device, and the hardening agent is filled between the outer periphery of the pile and the ground. A method for stabilizing foundation piles. 2. A friction cutter to be attached to the outer periphery of the tip of the hollow pile to be sunk, and a curing agent jet that is housed in the friction cutter and can be removed from the friction cutter and moved in the longitudinal direction along the outer periphery of the pile. 1. A device for stabilizing a foundation pile, comprising: a device; and a mechanism for moving the curing agent jetting device.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP4265979A JPS5841374B2 (en) | 1979-04-09 | 1979-04-09 | Foundation pile stabilization method and device |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP4265979A JPS5841374B2 (en) | 1979-04-09 | 1979-04-09 | Foundation pile stabilization method and device |
Publications (2)
Publication Number | Publication Date |
---|---|
JPS55136327A JPS55136327A (en) | 1980-10-24 |
JPS5841374B2 true JPS5841374B2 (en) | 1983-09-12 |
Family
ID=12642130
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP4265979A Expired JPS5841374B2 (en) | 1979-04-09 | 1979-04-09 | Foundation pile stabilization method and device |
Country Status (1)
Country | Link |
---|---|
JP (1) | JPS5841374B2 (en) |
-
1979
- 1979-04-09 JP JP4265979A patent/JPS5841374B2/en not_active Expired
Also Published As
Publication number | Publication date |
---|---|
JPS55136327A (en) | 1980-10-24 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
US3354657A (en) | Method for installing anchoring or supporting columns in situ | |
JP2008075266A (en) | Method of constructing pile | |
JP4811176B2 (en) | Construction method of ready-made piles | |
JP5948068B2 (en) | Pile construction method with anchors | |
US3736757A (en) | Cast-in-situ concrete piles | |
JP4872561B2 (en) | Construction method of ready-made piles | |
JPS5841374B2 (en) | Foundation pile stabilization method and device | |
JPS59126821A (en) | Erection work of foundation pile | |
JPS6115209B2 (en) | ||
KR0148168B1 (en) | Woorking method of underground foundation wall | |
JP6634251B2 (en) | Pile foundation structure, ready-made pile burying device, method of constructing pile foundation structure using said ready-made pile burying device | |
JPS6046210B2 (en) | Horizontal force reinforcement pile construction method and its equipment | |
JPS5853131B2 (en) | Foundation pile stabilization method and device | |
KR19990048467A (en) | Auger pile method using expandable mortar | |
JP3965451B2 (en) | Pile burying method | |
JP2001090060A (en) | Driving method for pile and constructing method for cut- off wall using the method | |
JPS6147929B2 (en) | ||
KR900005913B1 (en) | Base stake inflated in bump state at lower end there of and its construction | |
JPH0325121A (en) | Sinking of pile in inner drilling pile method | |
JP3946525B2 (en) | Construction method of steel pipe soil cement pile | |
JP2004204517A (en) | Pile burying method | |
JPH0626036A (en) | Concrete pile installation method by inner excavation | |
JPH0440491B2 (en) | ||
JPH10266199A (en) | Installation method for double filling pipe with tip packer and steel core mortar pole | |
JP2006183319A (en) | Prefabricated pile construction method |