JP5948068B2 - Pile construction method with anchors - Google Patents

Pile construction method with anchors Download PDF

Info

Publication number
JP5948068B2
JP5948068B2 JP2012019006A JP2012019006A JP5948068B2 JP 5948068 B2 JP5948068 B2 JP 5948068B2 JP 2012019006 A JP2012019006 A JP 2012019006A JP 2012019006 A JP2012019006 A JP 2012019006A JP 5948068 B2 JP5948068 B2 JP 5948068B2
Authority
JP
Japan
Prior art keywords
pile
anchor
guide tube
excavation
construction method
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
JP2012019006A
Other languages
Japanese (ja)
Other versions
JP2013155577A (en
Inventor
秀和 重松
秀和 重松
博 宮城
博 宮城
和敏 枝
和敏 枝
啓民 中里
啓民 中里
稔孝 猪股
稔孝 猪股
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Kurosawa Construction Co Ltd
Asahi Kasei Construction Materials Corp
Original Assignee
Kurosawa Construction Co Ltd
Asahi Kasei Construction Materials Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Kurosawa Construction Co Ltd, Asahi Kasei Construction Materials Corp filed Critical Kurosawa Construction Co Ltd
Priority to JP2012019006A priority Critical patent/JP5948068B2/en
Publication of JP2013155577A publication Critical patent/JP2013155577A/en
Application granted granted Critical
Publication of JP5948068B2 publication Critical patent/JP5948068B2/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Description

本発明は、アンカーを併用した杭の施工方法に関する。さらに詳述すると、本発明は、コンクリート杭、鋼管コンクリート杭、鋼管杭等の既製杭のプレボーリング工法の改良に関する。   The present invention relates to a pile construction method using an anchor in combination. More specifically, the present invention relates to an improvement in a pre-boring method for a ready-made pile such as a concrete pile, a steel pipe concrete pile, and a steel pipe pile.

地盤中に施工された杭の引き抜き耐力を向上させるべく、当該杭の中にアンカーを設置するという施工方法が提案されている。また、このような施工方法において、杭周面のセメント硬化体にアンカーが悪影響を及ぼさないように、アンカーとセメント硬化体を非接触にする方法も提案されている(例えば特許文献1参照)。   In order to improve the pulling-out strength of a pile constructed in the ground, a construction method of installing an anchor in the pile has been proposed. In addition, in such a construction method, a method has been proposed in which the anchor is not contacted with the cement cured body so that the anchor does not adversely affect the cement cured body on the circumferential surface of the pile (see, for example, Patent Document 1).

特開2007−239420号公報JP 2007-239420 A

しかし、特許文献1のごとき施工方法においては、中空であってその先端部が閉塞された既製杭を用いていたことから、以下のような問題が生じている。すなわち、(1)既製杭を沈設する際、該杭に浮力が作用することから、これを抑えるため中空部に水を入れなければならず、したがってその後には排水する必要も生じる。(2)既製杭内にアンカーを挿入する際、当該アンカーの先端(下端)を杭先端の中心へ導くため、当該中心の周囲に例えば擂鉢状に傾斜する等のガイドが必要である。(3)アンカーを挿通させるための通路を形成するべく、固化後のセメント構造体に孔を穿つと、セメント構造体としての発現強度が損なわれることがある。   However, in the construction method as in Patent Document 1, the following problems are caused because a pre-made pile that is hollow and has a closed end is used. That is, (1) When a ready-made pile is sunk, buoyancy acts on the pile, so that water must be poured into the hollow portion in order to suppress this, and therefore there is also a need to drain after that. (2) When an anchor is inserted into a ready-made pile, in order to guide the tip (lower end) of the anchor to the center of the tip of the pile, a guide that tilts in a bowl shape around the center is necessary. (3) If a hole is made in the cement structure after solidification so as to form a passage through which the anchor is inserted, the expression strength as the cement structure may be impaired.

そこで、本発明は、従来技術における種々の課題を踏まえ、排水工程がなく、杭にアンカーのガイドを設ける必要がなく、尚かつセメント構造体の発現強度を確保することができるようにした、アンカーを併用した杭の施工方法を提供することを目的とする。   Therefore, the present invention is based on various problems in the prior art, there is no drainage process, there is no need to provide an anchor guide on the pile, and the anchor strength that can secure the expression strength of the cement structure can be secured. It aims at providing the construction method of the pile which used together.

かかる課題を解決するべく本発明者が想到するに至った本発明は、地盤をプレボーリングし、該プレボーリングによる掘削孔に硬化剤を投入し、両端が開口した筒状の杭と、該杭内に配置される筒状のガイド管とを掘削孔中に建て込み、ガイド管にアンカーを挿通し、該アンカーを施工することを特徴とするものである。   The present invention, which has been conceived by the present inventor in order to solve such problems, is a cylindrical pile in which the ground is pre-bored, a hardening agent is introduced into a drilling hole by the pre-boring, and both ends are opened, and the pile A cylindrical guide pipe disposed inside is built in the excavation hole, an anchor is inserted into the guide pipe, and the anchor is constructed.

本発明にかかる施工方法では、先端・基端ともに開放された両端開口の筒状杭を利用することから、当該杭に浮力が作用することなく沈設させることができる。このため、杭の中空部に水を入れる必要がないし、排水する必要もない。   In the construction method according to the present invention, since a cylindrical pile having both ends opened at both the distal end and the proximal end is used, the pile can be laid without any buoyancy acting thereon. For this reason, it is not necessary to put water into the hollow part of a pile, and it is not necessary to drain.

また、本発明にかかる施工方法では、杭の内側へ建て込まれるガイド管を利用し、該ガイド管にアンカーを挿通することによって杭の内側にアンカーを設置することとしている。したがって、杭にガイドを設ける必要がない。   Moreover, in the construction method according to the present invention, a guide pipe built inside the pile is used, and the anchor is installed inside the pile by inserting the anchor through the guide pipe. Therefore, it is not necessary to provide a guide on the pile.

さらに、本発明にかかる施工方法では、硬化剤の固化後、ガイド管にアンカーを挿通すればよく、固化後のセメント構造体にアンカー挿通孔を穿つようなことは不要である。このため、固化後のセメント構造体の発現強度を確保しやすい。   Furthermore, in the construction method according to the present invention, the anchor may be inserted into the guide tube after the hardening agent is solidified, and it is not necessary to make an anchor insertion hole in the cement structure after solidification. For this reason, it is easy to ensure the expression strength of the cement structure after solidification.

このような施工方法においては、杭とガイド管とを一体化して掘削孔中に建て込むことができる。あるいは、杭を掘削孔中に先に建て込み、その後、該杭内にガイド管を建て込むこともできる。   In such a construction method, the pile and the guide pipe can be integrated and built in the excavation hole. Alternatively, the pile can be built in the excavation hole first, and then the guide tube can be built in the pile.

また、このような施工方法においては、ガイド管として、該ガイド管の振れを抑制する振れ止め部材が形成されているものを用いることが好ましい。   Moreover, in such a construction method, it is preferable to use a guide tube in which an anti-sway member that suppresses the shake of the guide tube is formed.

また、ガイド管を、該ガイド管の先端を閉塞させた状態で掘削孔中に建て込むことも好ましい。この場合には、ガイド管の閉塞した先端をドリルで打ち抜いた後、アンカーを該ガイド管に挿通させることがさらに好ましい。   It is also preferable to build the guide tube into the excavation hole with the tip of the guide tube blocked. In this case, it is more preferable that the closed end of the guide tube is punched out with a drill and the anchor is inserted through the guide tube.

本発明によれば、排水工程をなくし、杭にアンカーのガイドを設けることを不要とし、尚かつセメント構造体の発現強度を確保することができる。   According to the present invention, it is possible to eliminate the drainage process, make it unnecessary to provide anchor guides on the pile, and secure the expression strength of the cement structure.

地盤を掘削し、掘削孔に杭を建て込むまでの工程を(A)〜(D)の順に示す図である。It is a figure which shows the process until it excavates the ground and builds a pile in an excavation hole in order of (A)-(D). 図1に引き続き、ガイド管を建て込むところからアンカー定着部を形成するまでの工程を(E)〜(H)の順に示す図である。It is a figure which shows the process from the place where a guide pipe | tube is built to forming an anchor fixing | fixed part following FIG. 1 in order of (E)-(H). 図2に引き続き、ガイド管を建て込むところからアンカー定着部を形成するまでの工程を(I)〜(J)の順に示す図である。FIG. 3 is a diagram illustrating steps from the construction of the guide tube to the formation of the anchor fixing portion in the order of (I) to (J) following FIG. 2.

以下、本発明の構成を図面に示す実施の形態の一例に基づいて詳細に説明する。   Hereinafter, the configuration of the present invention will be described in detail based on an example of an embodiment shown in the drawings.

図1〜図3に本発明にかかるアンカーを併用した杭の施工方法の一実施形態を示す。本発明にかかる施工方法は、地盤Gをプレボーリングし、該プレボーリングによる掘削孔4に硬化剤5,6を投入し、両端が開口した筒状の杭1と、該杭1内に配置される筒状のガイド管3とを掘削孔4中に建て込み、硬化材5,6の固化後、ガイド管3にアンカー2を挿通し、該アンカー2を施工するというものである。杭1の具体例としては、コンクリート杭、鋼管コンクリート杭、鋼管杭などといった、先端・基端ともに開放された筒状の既製杭が挙げられる。   1 to 3 show an embodiment of a pile construction method using an anchor according to the present invention. In the construction method according to the present invention, the ground G is pre-bored, the hardeners 5 and 6 are put into the excavation hole 4 by the pre-boring, and the cylindrical pile 1 having both ends opened, and the pile 1 are disposed in the pile 1. The cylindrical guide tube 3 is built in the excavation hole 4, and after the hardened materials 5 and 6 are solidified, the anchor 2 is inserted into the guide tube 3 and the anchor 2 is installed. Specific examples of the pile 1 include cylindrical ready-made piles whose both ends and base ends are open, such as concrete piles, steel pipe concrete piles, steel pipe piles, and the like.

図1等において、符号11はオーガーモータ(図示省略)により回転駆動され、杭1を沈設する掘削孔4を掘削するための掘削ロッドである。この掘削ロッド11の下端部には掘削ビット12が設けられている。   In FIG. 1 etc., the code | symbol 11 is an excavation rod for excavating the excavation hole 4 which is rotationally driven by an auger motor (illustration omitted) and sinks the pile 1. FIG. A drill bit 12 is provided at the lower end of the drill rod 11.

掘削ロッド11は内部が中空の構造であり、液体等を通じるための配管を兼ねている。この掘削ロッド11が先行掘削する際、その下端部ノズルからエアーや水、掘削液などを噴出するように構成されている。また、掘削ビット12の下端部には、掘削刃13が設けられている(図1参照)。   The excavation rod 11 has a hollow structure and also serves as a pipe for passing a liquid or the like. When this excavation rod 11 excavates in advance, air, water, excavation liquid, etc. are ejected from the lower end nozzle. Moreover, the excavation blade 13 is provided in the lower end part of the excavation bit 12 (refer FIG. 1).

このような掘削ロッド11および掘削ビット12を用いて地盤Gをプレボーリングし、掘削孔4に杭1およびアンカー2を施工する様子を以下に示す(図1(A)等参照)。   A state in which the ground G is pre-bored using the excavation rod 11 and the excavation bit 12 and the pile 1 and the anchor 2 are constructed in the excavation hole 4 is shown below (see FIG. 1A, etc.).

まず、杭1の芯の位置に掘削ロッド11の下端に設けられた掘削ビット12の軸芯を合わせる。次に、図示しないオーガーモータを回転駆動して掘削ロッド11を回転させ、所定の深度まで地盤Gを掘削する。   First, the shaft core of the excavation bit 12 provided at the lower end of the excavation rod 11 is aligned with the core position of the pile 1. Next, an auger motor (not shown) is rotated to rotate the excavation rod 11 and excavate the ground G to a predetermined depth.

その後、掘削ロッド11を上下に移動させながら、地上に設置されたバッチャープラント(図示省略)から掘削ロッド11の内部配管に例えば硬化体材料の一例としてセメントミルク等の根固め液5を供給し、配管先端のノズルから掘削孔4内に根固め液5を注入して根固め部(根固め球根)を形成する。ここで例示したセメントミルクは根固め用のセメント硬化体用スラリーの一例にすぎず、この他、セメント粉体等を利用してもよい。セメント粉体は掘削時等に使用される水や地盤G内に含まれる水と混合されてスラリーと化すことができる。また、セメントミルクの注入中は掘削ビット12を例えば3回程度上下させることによってセメントミルクを攪拌することが望ましい。   Thereafter, while moving the excavating rod 11 up and down, a rooting liquid 5 such as cement milk is supplied to the internal piping of the excavating rod 11 from a batcher plant (not shown) installed on the ground. Then, a root hardening liquid 5 is injected into the excavation hole 4 from the nozzle at the tip of the pipe to form a root hardening part (root hardening bulb). The cement milk illustrated here is only an example of a slurry for cement hardening body for root hardening, and other cement powder may be used. The cement powder can be mixed with water used during excavation or the like and water contained in the ground G to form a slurry. Further, it is desirable to stir the cement milk by raising and lowering the excavation bit 12 about three times during the injection of the cement milk.

その後、掘削ビット12を引き上げながら、杭周固定液6を注入する(図1(B)参照)。杭周固定液6としては、例えばセメントミルクを用いることができる。なお、杭周固定液6および上述の根固め液5として、同じ配合(一例として、水セメント比60%)のセメントミルクを用いることができる。ただし、本実施形態では、根固め液5については掘削体積あたり70〜100%の量を注入し、杭周固定液6については掘削体積あたり10〜30%の量を注入することとし、根固め液5のほうが固化後の強度が高くなるようにしている。   Then, the pile periphery fixing liquid 6 is inject | poured, pulling up the excavation bit 12 (refer FIG. 1 (B)). As the pile periphery fixing liquid 6, for example, cement milk can be used. In addition, as the pile circumference fixing liquid 6 and the above-described root hardening liquid 5, cement milk having the same composition (as an example, a water cement ratio of 60%) can be used. However, in the present embodiment, 70 to 100% of the excavation volume is injected for the root hardening liquid 5, and 10 to 30% of the excavation volume is injected for the pile circumference fixing liquid 6 to solidify the root. The liquid 5 has a higher strength after solidification.

掘削孔4から掘削ビット12を引き上げたら(図1(C)参照)、杭1を所定の深さまで建て込んで沈設する(図1(D)参照)。杭1は、必要に応じて複数本が順次継がれながら沈設される。   When the excavation bit 12 is pulled up from the excavation hole 4 (see FIG. 1 (C)), the pile 1 is built to a predetermined depth and set (see FIG. 1 (D)). The piles 1 are laid while a plurality of piles 1 are successively connected as necessary.

次に、杭1の内側(中空部)へガイド管3を建て込む(図2(E)参照)。本実施形態では先端が閉塞した状態のガイド管3を採用し、該閉塞した先端から掘削孔4内に建て込むようにしている。こうした場合、掘削孔4内に注入された根固め液5や杭周固定液6がガイド管3に入り込むことがない。   Next, the guide tube 3 is built into the inside (hollow part) of the pile 1 (see FIG. 2E). In the present embodiment, the guide tube 3 having a closed end is employed, and the guide tube 3 is built into the excavation hole 4 from the closed end. In such a case, the root hardening liquid 5 and the pile circumference fixing liquid 6 injected into the excavation hole 4 do not enter the guide pipe 3.

また、該ガイド管3の振れを抑制する振れ止め部材7が杭1またはガイド管3に形成されていれば、ガイド管3の振れを抑制して杭の軸芯にガイド管3の軸芯を合わせることができるため好適である。例えば本実施形態では、径方向に延びる振れ止め部材7をガイド管3の外周面に設けておき、該振れ止め部材7をガイド管3の内周面に当接させることによってガイド管3の振れを抑制している(図2(E)参照)。振れ止め部材7は、周方向においては例えば3方向に120度おきに配置されている。これら振れ止め部材7は、軸方向においてはガイド管3の互いに離間した2箇所の位置に配置されていることが好ましい(図2(E)参照)。   Moreover, if the steadying member 7 which suppresses the shake of the guide tube 3 is formed in the pile 1 or the guide tube 3, the guide tube 3 is restrained from being shaken and the shaft core of the guide tube 3 is attached to the shaft core of the pile. It is preferable because they can be combined. For example, in the present embodiment, a steady-state stabilization member 7 extending in the radial direction is provided on the outer peripheral surface of the guide tube 3, and the steady-state stabilization member 7 is brought into contact with the inner peripheral surface of the guide tube 3 to thereby prevent the guide tube 3 from shaking. (See FIG. 2E). The steadying member 7 is arranged at intervals of 120 degrees in, for example, three directions in the circumferential direction. These steadying members 7 are preferably arranged at two positions spaced apart from each other in the guide tube 3 in the axial direction (see FIG. 2E).

数日ないし数週間程度が経過し、根固め液5や杭周固定液6が固化した後、杭1の杭頭周辺の根切りを行い、当該杭頭を掘り出す(図2(F)参照)。   After several days to several weeks have passed and the root hardening liquid 5 and the pile fixing liquid 6 have solidified, the roots around the pile head of the pile 1 are cut and the pile head is excavated (see FIG. 2 (F)). .

次に、ドリル8をガイド管3内に挿通させ、ガイド管3の閉塞した先端を打ち抜き、さらに所定深さまでアンカー孔41を掘削する(図2(G)参照)。このとき、アンカー孔41の崩壊を防ぐために図示しないケーシングを併用して掘削しても良い。次に、ドリル8の先端よりグラウト材を注入し、注入後、ドリル8を回収する。その後、連結部材2aをガイド管3内に挿通し、先端部をグラウト材に定着させてアンカー定着部2bを形成する(図2(H)参照)。更に、必要に応じて連結部材2aに設けられた中空部等よりグラウト材を加圧注入しても良い。   Next, the drill 8 is inserted into the guide tube 3, the closed end of the guide tube 3 is punched out, and the anchor hole 41 is excavated to a predetermined depth (see FIG. 2G). At this time, in order to prevent the anchor hole 41 from collapsing, a casing (not shown) may be used for excavation. Next, a grout material is injected from the tip of the drill 8, and after the injection, the drill 8 is recovered. Thereafter, the connecting member 2a is inserted into the guide tube 3, and the tip portion is fixed to the grout material to form the anchor fixing portion 2b (see FIG. 2 (H)). Furthermore, you may inject | pour a grout material by pressure from the hollow part etc. which were provided in the connection member 2a as needed.

続いて、杭頭にコンクリート製等の構造物50を造成する(図3(I)参照)。その後、構造物50に挿通された状態のアンカー2を引っ張り、ナット51等により該アンカー2を構造物50に定着させる(図3(J)参照)。この結果、構造物50は、杭1に支持され、尚かつアンカー2により下方への引っ張り力を受けた状態で固定される。   Subsequently, a structure 50 made of concrete or the like is created on the pile head (see FIG. 3I). Thereafter, the anchor 2 inserted through the structure 50 is pulled, and the anchor 2 is fixed to the structure 50 with a nut 51 or the like (see FIG. 3J). As a result, the structure 50 is supported by the pile 1 and is fixed in a state of receiving a downward pulling force by the anchor 2.

ここまで説明した本実施形態の施工方法によれば、施工時に排水する手間がない。すなわち、従来工法においては、既製杭を沈設する際、該杭に浮力が作用することから、これを抑えるため中空部に水を入れなければならず、その後には排水する必要が生じていたのに対し、本実施形態では、先端・基端ともに開放された両端開口の筒状杭1を採用していることから、沈設の際に当該杭1に浮力が作用することがない(図1(D)等参照)。したがって、杭1の中空部に水を入れる必要がないし、排水する必要もなく、これらの作業に要していた手間がかからない。   According to the construction method of the present embodiment described so far, there is no time for draining during construction. In other words, in the conventional construction method, when the ready-made piles are laid, buoyancy acts on the piles, so in order to suppress this, water has to be put into the hollow part, and then it has been necessary to drain it. On the other hand, in this embodiment, since the cylindrical pile 1 of both ends opening opened at both the distal end and the proximal end is adopted, buoyancy does not act on the pile 1 when set up (FIG. 1 ( D) etc.). Therefore, it is not necessary to put water into the hollow portion of the pile 1, and it is not necessary to drain water, so that the labor required for these operations is not required.

また、従来工法においては、既製杭内にアンカーを挿入する際、当該アンカーの先端(下端)を杭先端の中心へ導くためのガイドが必要であり、例えば杭の一部を擂鉢状として厚くする等の必要があるのに対し、本実施形態では、杭1の内側へ建て込まれるガイド管3を利用し、該ガイド管3にアンカー(連結部材2a)を挿通するという構成にしたことから、杭1にガイドを設ける必要がない。したがって、厚さ均一の単純な形状の杭1を用いることができる。   In addition, in the conventional method, when inserting an anchor into a ready-made pile, a guide for guiding the tip (lower end) of the anchor to the center of the tip of the pile is necessary. For example, a part of the pile is thickened as a bowl shape. In the present embodiment, the guide tube 3 built inside the pile 1 is used, and the anchor (connecting member 2a) is inserted into the guide tube 3 in the present embodiment. There is no need to provide a guide on the pile 1. Therefore, the pile 1 having a simple shape with a uniform thickness can be used.

しかも、上述のようなガイド管3によれば、アンカー2と杭1等との縁を切った状態とすることができる。すなわち、このガイド管3は、アンカー2の連結部材2aの周囲を覆っており、根固め液5および杭周固定液6と連結部材2aとを分離した状態に保つ(図2(F)、(G)等参照)。この結果、アンカー2の連結部材2aは、先端(下端)側をアンカー定着部2a、基端(上端)側をナット51にそれぞれ固着される一方で、それらの中間においてはセメントミルク等で固着されていない非接触の状態となる。したがって、アンカー2の伸縮による杭1への影響をなくすことができる。また、アンカー2による十分な引っ張り力を構造物50に作用させ、杭1の引き抜き耐力を向上させることができる。   And according to the above guide tubes 3, the edge of the anchor 2 and the pile 1 etc. can be made into the cut state. That is, the guide tube 3 covers the periphery of the connecting member 2a of the anchor 2 and keeps the root-setting liquid 5 and the pile circumference fixing liquid 6 and the connecting member 2a separated (FIG. 2 (F), ( G) etc.). As a result, the connecting member 2a of the anchor 2 is fixed to the anchor fixing portion 2a on the distal end (lower end) side and to the nut 51 on the proximal end (upper end) side, while being fixed with cement milk or the like between them. Not in contact. Therefore, the influence on the pile 1 due to the expansion and contraction of the anchor 2 can be eliminated. Moreover, sufficient pulling force by the anchor 2 can be applied to the structure 50, and the pulling-out strength of the pile 1 can be improved.

さらに、上述のようなガイド管3を利用する本実施形態の施工方法においては、固化後の根固め液5や杭周固定液6に孔を穿つといった作業をせずとも、アンカー2の連結部材2aを挿通させるためのスペースを確保することができる(図2(F)、(G)等参照)。したがって、根固め液5や杭周固定液6に孔を穿つ従来工法と比較して、固化後のセメント構造体の発現強度を確保しやすい。   Furthermore, in the construction method of the present embodiment using the guide tube 3 as described above, the connecting member of the anchor 2 can be obtained without drilling a hole in the root hardening liquid 5 and the pile fixing liquid 6 after solidification. A space for inserting 2a can be ensured (see FIGS. 2F and 2G). Therefore, it is easy to secure the expression strength of the cement structure after solidification, as compared with the conventional method in which holes are made in the root hardening liquid 5 and the pile circumference fixing liquid 6.

なお、上述の実施形態は本発明の好適な実施の一例ではあるがこれに限定されるものではなく本発明の要旨を逸脱しない範囲において種々変形実施可能である。例えば上述した各実施形態では、杭1を所定の深さまで建て込んで沈設し(図1(D)参照)、その後、杭1の内側へガイド管3を建て込むようにしたが(図2(E)参照)、この他、杭1とガイド管3とを一体化して掘削孔4中に建て込むこともできる。   The above-described embodiment is an example of a preferred embodiment of the present invention, but is not limited thereto, and various modifications can be made without departing from the scope of the present invention. For example, in each of the above-described embodiments, the pile 1 is built and set to a predetermined depth (see FIG. 1 (D)), and then the guide tube 3 is built inside the pile 1 (FIG. 2 ( In addition, the pile 1 and the guide pipe 3 can be integrated into the excavation hole 4.

本発明は、コンクリート杭、鋼管コンクリート杭、鋼管杭等の既製杭のプレボーリング工法に適用して好適なものである。   The present invention is suitable for application to pre-boring methods for ready-made piles such as concrete piles, steel pipe concrete piles, steel pipe piles and the like.

1…杭
2…アンカー
3…ガイド管
4…掘削孔
5…根固め液(硬化剤)
6…杭周固定液(硬化剤)
7…振れ止め部材
G…地盤
DESCRIPTION OF SYMBOLS 1 ... Pile 2 ... Anchor 3 ... Guide pipe 4 ... Drilling hole 5 ... Root hardening liquid (hardening agent)
6 ... Pile circumference fixing liquid (hardening agent)
7 ... rest member G ... ground

Claims (4)

地盤をプレボーリングし、
該プレボーリングによる掘削孔に硬化剤を投入し、
両端が開口した筒状の杭と、該杭内に配置される筒状のガイド管とを前記掘削孔中に建て込む際、前記ガイド管として、該ガイド管の振れを抑制する振れ止め部材が形成されているものを用い、
前記杭を前記掘削孔中に先に建て込み、その後、該杭内に前記ガイド管を建て込み、
前記ガイド管にアンカーを挿通し、該アンカーを施工することを特徴とする、アンカーを併用した杭の施工方法。
Pre-boring the ground,
Put a hardener into the drilling hole by the pre-boring,
A tubular pile with the both ends being opened, when no write build a cylindrical guide tube disposed within該杭in the wellbore, as the guide tube, member stop shake suppressing deflection of the guide tube Using what is formed,
Like an anchor before the pile in the borehole, and then, only write built the guide tube in the該杭,
A method for constructing a pile using an anchor, wherein the anchor is inserted into the guide tube and the anchor is constructed.
前記ガイド管を、該ガイド管の先端を閉塞させた状態で前記掘削孔中に建て込むことを特徴とする、請求項1に記載のアンカーを併用した杭の施工方法。 Said guide tube, characterized in that Tatekomu in the wellbore while being closed the distal end of the guide tube, the construction method of the pile in combination an anchor according to claim 1. 地盤をプレボーリングし、
該プレボーリングによる掘削孔に硬化剤を投入し、
両端が開口した筒状の杭と、該杭内に配置される筒状のガイド管とを、前記ガイド管については該ガイド管の先端を閉塞させた状態で前記掘削孔中に建て込み、
前記ガイド管にアンカーを挿通し、該アンカーを施工することを特徴とする、アンカーを併用した杭の施工方法。
Pre-boring the ground,
Put a hardener into the drilling hole by the pre-boring,
A tubular pile which opposite open ends, and a cylindrical guide tube disposed within該杭, while the said guide tube obtained by closing the tip of the guide tube, seen write built in the wellbore ,
A method for constructing a pile using an anchor , wherein the anchor is inserted into the guide tube and the anchor is constructed.
前記ガイド管の閉塞した先端をドリルで打ち抜いた後、前記アンカーを該ガイド管に挿通させることを特徴とする、請求項2または3に記載のアンカーを併用した杭の施工方法。 The method for constructing a pile using the anchor according to claim 2 or 3 , wherein the anchor is inserted into the guide tube after the closed end of the guide tube is punched out with a drill.
JP2012019006A 2012-01-31 2012-01-31 Pile construction method with anchors Active JP5948068B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2012019006A JP5948068B2 (en) 2012-01-31 2012-01-31 Pile construction method with anchors

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2012019006A JP5948068B2 (en) 2012-01-31 2012-01-31 Pile construction method with anchors

Publications (2)

Publication Number Publication Date
JP2013155577A JP2013155577A (en) 2013-08-15
JP5948068B2 true JP5948068B2 (en) 2016-07-06

Family

ID=49051045

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2012019006A Active JP5948068B2 (en) 2012-01-31 2012-01-31 Pile construction method with anchors

Country Status (1)

Country Link
JP (1) JP5948068B2 (en)

Families Citing this family (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103643682B (en) * 2013-11-28 2015-09-09 杭州江润科技有限公司 A kind of pre stressed empty piped piles foundation pit enclosure structure and construction method
CN104674802B (en) * 2015-01-26 2016-03-09 重庆大学 Prestressing force rubble anchorage pile and landslide control construction method thereof
KR101698457B1 (en) * 2016-06-29 2017-01-23 주식회사 보강테크 Multi pile construction method for strengthening weak soil
JP7332447B2 (en) 2019-11-27 2023-08-23 花王株式会社 Piling construction method

Family Cites Families (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP4512859B2 (en) * 1999-04-30 2010-07-28 三谷セキサン株式会社 Method of burying ready-made piles in pile holes
JP2002146784A (en) * 2000-11-10 2002-05-22 Mitani Sekisan Co Ltd Ground anchoring method using existing pile
JP2007239420A (en) * 2006-03-13 2007-09-20 Kumagai Gumi Co Ltd Structure of foundation for preventing floating of structure, its execution method and structure of pile used for its foundation or execution method
JP5145738B2 (en) * 2007-03-15 2013-02-20 株式会社大林組 Seismic construction method for structures, seismic structure for structures

Also Published As

Publication number Publication date
JP2013155577A (en) 2013-08-15

Similar Documents

Publication Publication Date Title
CN204959746U (en) Expand integral type stock soon
JP5274145B2 (en) Cast-in-place pile and its construction method
JP4623574B2 (en) How to build a pile
JP5948068B2 (en) Pile construction method with anchors
JP5075091B2 (en) Casting method for cast-in-place piles
JP4946695B2 (en) Construction method of double pipe type pile head structure
JP5742058B2 (en) Method for increasing horizontal resistance of precast concrete pile foundation
JP4811176B2 (en) Construction method of ready-made piles
JP6329794B2 (en) Pile extraction method
JP5698316B2 (en) Construction method of foundation pile
JP5075090B2 (en) Cast-in-place pile construction method and cast-in-place pile
JP4476230B2 (en) Steel pipe pile rooting method
JP4872561B2 (en) Construction method of ready-made piles
JP5075094B2 (en) Construction method and foundation structure of foundation structure in structure
DK2925934T3 (en) Process for making a pile
JP5606727B2 (en) Foundation pile
JP4341029B2 (en) Pile foundation method
JP4517236B2 (en) Pile hole drilling method
JP6656972B2 (en) Removal method of solidified material from pile head of ready-made pile
JPH06287943A (en) Foot protection method for tip of foundation pile and cylindrical foundation pile
JP4167251B2 (en) Steel pipe pile and its rooting method
JP6634251B2 (en) Pile foundation structure, ready-made pile burying device, method of constructing pile foundation structure using said ready-made pile burying device
JP4475845B2 (en) Pile construction method
JP4179949B2 (en) Pile rotation method
JP2005240395A (en) Rotary embedding method for pile

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20150128

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20151015

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20151020

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20151218

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20160506

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20160606

R150 Certificate of patent or registration of utility model

Ref document number: 5948068

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

S111 Request for change of ownership or part of ownership

Free format text: JAPANESE INTERMEDIATE CODE: R313117

S531 Written request for registration of change of domicile

Free format text: JAPANESE INTERMEDIATE CODE: R313531

R350 Written notification of registration of transfer

Free format text: JAPANESE INTERMEDIATE CODE: R350