JPS58138814A - Construction of underwater structure - Google Patents

Construction of underwater structure

Info

Publication number
JPS58138814A
JPS58138814A JP57018910A JP1891082A JPS58138814A JP S58138814 A JPS58138814 A JP S58138814A JP 57018910 A JP57018910 A JP 57018910A JP 1891082 A JP1891082 A JP 1891082A JP S58138814 A JPS58138814 A JP S58138814A
Authority
JP
Japan
Prior art keywords
concrete
wall
underwater
formwork
construction
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP57018910A
Other languages
Japanese (ja)
Other versions
JPS62292B2 (en
Inventor
Chikao Kato
加藤 親男
Tametoshi Ueda
上田 為敏
Shinsuke Sakai
堺 信介
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
JFE Steel Corp
Original Assignee
Kawasaki Steel Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Kawasaki Steel Corp filed Critical Kawasaki Steel Corp
Priority to JP57018910A priority Critical patent/JPS58138814A/en
Publication of JPS58138814A publication Critical patent/JPS58138814A/en
Publication of JPS62292B2 publication Critical patent/JPS62292B2/ja
Granted legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B17/00Artificial islands mounted on piles or like supports, e.g. platforms on raisable legs or offshore constructions; Construction methods therefor

Landscapes

  • Engineering & Computer Science (AREA)
  • General Engineering & Computer Science (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Revetment (AREA)

Abstract

PURPOSE:To simply construct an underwater structure in a short time by a method in which outer concrete walls previously molded on the land are installed along steel pipe piles and then concrete is placed between the outer walls and the other form. CONSTITUTION:An outer concrete wall 3 previously cast on the land is supported under water through the brackets 12 and 12' of steel pipe piles 2, and then an inner form 4 to construct an inner wall is set concentrically with the outer wall 3. Then, filling concrete 5 is placed between the outer wall 3 and the inner form 4 through a tremie tube 14. In case where the height is short for the underwater foundation, the filling concrete 5 is further placed after additionally constructing and setting the concrete outer wall 3 and the inner form 4, and cement mortar is injected into both joints for joint treatment.

Description

【発明の詳細な説明】 この発明は水中槽m物の施工方法に関するもので、とく
に予め陸ヒ施工した構造物の一部を型枠代りに使い水中
打設コンクリートと一体化びせることにより水中構造物
を構築する77−法について提案する。
Detailed Description of the Invention The present invention relates to a method for constructing underwater tanks, and in particular, by using a part of a structure previously constructed on land as a formwork and integrating it with concrete poured underwater. We propose a 77-method for constructing structures.

従来、水中コンクリート構造物の施工方法には位1w決
めの真管杭にブラケットを介して一対の鋼製型枠を取付
け、その型枠間に中詰コンクリートを打設し、その接顔
型枠を埋め殺しにするが撤去して水中構造物を構築して
いた。しかしながら、上記従来施工方法の場合、■主と
してパネル吠の鋼製型枠を列設するH法であるため、型
枠の支持・補強が難しく作業時間がかかる上、とりわけ
海上作業にあっては風や波浪に対して弱く不安定である
。■中詰コンクリートの打設後、型枠の撤去回収が困1
ノ並であり、未101収の場合11ヒ好ましくない等の
欠点があった。
Conventionally, the construction method for underwater concrete structures involves attaching a pair of steel formworks via brackets to true pipe piles of 1w, placing filling concrete between the formworks, and constructing the facing formwork. They buried it to death, but removed it and built an underwater structure. However, in the case of the above-mentioned conventional construction method, it is mainly the H method in which panel steel formwork is installed in rows, so supporting and reinforcing the formwork is difficult and takes time, and especially in offshore work, wind It is weak and unstable against waves and waves. ■It is difficult to remove and collect the formwork after pouring the filling concrete.
There were drawbacks such as 11% unfavorable in case of 101% yield.

この発明はト述した嘩来施工tテ法のもつ欠点を免服す
ることを目的とするものであって、水中で。
The purpose of this invention is to overcome the drawbacks of the above-mentioned construction method, and it is possible to do so under water.

のコンクリート構尚物施工に際し、予め構造物壁体の一
部を構成するW1殻状コンクリート外壁な打設成型し、
このフンクリート外壁を仮設用ブラケットを固定した真
管杭に沿って所定の位置に据付け、その後上記コンクリ
ート外壁と池の型枠との間に中詰コンクリートを打設し
て、上記筒殻状コンクリート壁をその一部に含む一体構
造物にすることを構成の特徴とする。以下にその構成の
詳細を説明する。
When constructing a concrete structure, the W1 shell-shaped concrete outer wall that forms part of the structure wall is cast and formed in advance.
This Funkrete outer wall is installed at a predetermined position along the true pipe piles to which the temporary brackets are fixed, and then filling concrete is poured between the concrete outer wall and the pond formwork to form the cylindrical concrete wall. The feature of the structure is that it is an integral structure that includes a part of it. The details of the configuration will be explained below.

図面の第1図は本発明にかかる水中構造物を必要とする
配管橋、道路橋の一般図であり、第2図第8図はその水
中基礎部分の詳細図を示す。図示例の水中構造物は、柱
脚基礎の例で、長円筒形の構造物壁体1を、土質中に打
込んだ複数本の鋼管杭2で所定の位置に支持した構成で
ある。本発明の施工にかかる水中構造物は、施工段階の
順で説明すると、予め外周壁をなすfiIi殻状コンク
リート外壁8と内周壁を構成する型枠4とを用意し、そ
の後中詰コンクリート5を打設する工程によって構築さ
れる。
Figure 1 of the drawings is a general view of a pipe bridge or road bridge that requires the underwater structure according to the present invention, and Figures 2, 8, and 8 show detailed views of the underwater foundation thereof. The illustrated underwater structure is an example of a pillar base, and has a configuration in which an elongated cylindrical structure wall 1 is supported at a predetermined position by a plurality of steel pipe piles 2 driven into soil. To explain the underwater structure according to the present invention in the order of construction steps, the fiIi shell-shaped concrete outer wall 8 forming the outer peripheral wall and the formwork 4 forming the inner peripheral wall are prepared in advance, and then the filling concrete 5 is prepared. Constructed by pouring process.

前記型枠4としては、鋼製のものとコンクリート製のも
のを使うが、前者の場合従来法と同じように後で撤去す
る必要があるのに対し、後者の場合前記コンクリート外
壁8と同じように構造物壁体lの一部として中詰コンク
リート5打設時に一体化させる。要するGこ、本発明施
工方法の特徴の1つは、構造物の内・外壁を構成する部
分を予め陸上で成型して、これを従来の型枠の代りに使
いながら、同時に構造物の一部として中詰コンクリート
5賭共に一体化させる点にある。
As the formwork 4, one made of steel and one made of concrete are used, but in the case of the former it is necessary to remove it later as in the conventional method, whereas in the case of the latter it is necessary to remove it later as in the case of the concrete outer wall 8. It is integrated as part of the structure wall 1 when the filling concrete 5 is placed. One of the features of the construction method of the present invention is that the parts that make up the inner and outer walls of the structure are formed in advance on land, and this is used in place of conventional formwork, while at the same time forming part of the structure. The main point is that all five types of filling concrete are integrated as a part.

なお、図示する6、6’、6’はいずれも埋設する鉄筋
、7は鋼管杭から突設した補強用鉄筋である。その配筋
の詳細を第4図に示す。第4図に示す8は内−外壁8,
4と中詰フンクリート5の一体結合を強化する強化鉄筋
で、それぞれの壁体中に埋設した支持板9から中詰コン
クリート打設空間に向けて突設した形に固定しである。
In addition, 6, 6', and 6' shown in the figure are all reinforcing bars to be buried, and 7 is a reinforcing reinforcing bar protruding from the steel pipe pile. The details of the reinforcement arrangement are shown in Fig. 4. 8 shown in FIG. 4 is an inner-outer wall 8,
4 and the filling concrete concrete 5 are reinforced reinforcing bars, which are fixed in a form protruding from support plates 9 buried in each wall toward the filling concrete placement space.

第5図は本発明施工方法の各段階を示すもので、まず予
め陸上にて構造物の外壁を構成するコンクリート外壁8
を製作する。同時に水中の据付は位置には、鋼管杭2を
打込み、その鋼管杭2には上記コンクリート外1居8を
水中の所定の位置に支持するためのブラケット12 、
12’を固定しておく。  ′ブラケット12.12’
の固定位置は水中になるので、作業の便を考え該ブラケ
ットからダミーバー12 a 、 12’aを突設、シ
てこれを杭に沿って水面上に持ち来し、その水面上に位
置する上部を溶接固定してブラケット位置を決める。こ
うして用意されたw4管杭2に、クレーン船10および
台船11により前記コンクリート外壁3をブラケット1
2.12’を介して水中に支持する。その後、内壁を構
成するためのコンクリート製または鋼製の内型枠4を外
壁8と同心に設置aする。コンクリート外嗜3ならびに
型枠4支持の模様については、その詳細を第6図、第7
図に示す。
FIG. 5 shows each stage of the construction method of the present invention. First, the concrete outer wall 8 that constitutes the outer wall of the structure on land
Manufacture. At the same time, a steel pipe pile 2 is driven into the position for underwater installation, and the steel pipe pile 2 has a bracket 12 for supporting the above-mentioned concrete exterior 1 8 at a predetermined position underwater.
Fix 12'. 'Bracket 12.12'
Since the fixing position is underwater, for convenience of work, dummy bars 12a and 12'a are protruded from the bracket, and the dummy bars 12a and 12'a are brought above the water surface along the stakes, and the upper part located above the water surface is Fix by welding and decide the bracket position. The concrete outer wall 3 is attached to the W4 pipe pile 2 prepared in this way by a crane ship 10 and a barge 11 with a bracket 1.
2. Support in water via 12'. Thereafter, an inner formwork 4 made of concrete or steel for forming the inner wall is installed a concentrically with the outer wall 8. The details of the concrete exterior 3 and formwork 4 support patterns are shown in Figures 6 and 7.
As shown in the figure.

上記の段階を終えると、フンクリート外1118と内型
枠4との間にトレミー管14を使って中詰コンクリート
5を打設する。この打設に際しては、中詰コンクリート
が流出しないように、第8図。
After completing the above steps, filling concrete 5 is placed between the outside concrete 1118 and the inner formwork 4 using the tremie pipe 14. When pouring, be careful not to spill out the filling concrete as shown in Figure 8.

第9図に示すような盛土18を施工しておく。An embankment 18 as shown in FIG. 9 is constructed in advance.

その後、水中基礎としての必要な高さを得るため、幾つ
かのブロックに分けて施工する必要があるときには、第
5図の(ニ) 、 (ホ)で示すように前述した同様な
工程の繰返しによって前記コンクリート外畷3と内型枠
4との闇に中詰コンクIJ −1・5を打設し、固接合
部にモルタル注入によって目地処理し、必要な高さのも
のに重ね合わせて完成させる。
After that, if it is necessary to divide the construction into several blocks in order to obtain the required height for the underwater foundation, repeat the same process described above as shown in (d) and (e) in Figure 5. Filling concrete IJ-1 and 5 were cast in the darkness between the concrete outer wall 3 and inner formwork 4, joints were treated by pouring mortar into the solid joints, and the concrete was overlaid to the required height to complete the work. let

実施例 氷島製鉄所で発生ずるCガス、Nガスを高梁用を挾む対
岸の工場に送給する高梁用横断パイプライン敷設工事に
おける配管橋柱脚基礎の施工に当り本発明の効果を確認
するために試験的に本発明法を適用した例を説明する。
Example: The effectiveness of the present invention was confirmed in the construction of a piping bridge column pedestal foundation in the construction of a cross-pipeline for high beams to send C gas and N gas generated at the Hijima Steel Works to a factory on the opposite bank across the high beams. An example in which the method of the present invention was applied on a trial basis to achieve this will be explained.

第10図の(イ)。Figure 10 (a).

(ロ)は該基礎の詳細図であり、長さ7.8 m X巾
4.3 m X高さ9.4mの長円形柱脚である。柱脚
壁の厚さ80cmの内、15cmのコンクリート外壁を
高さ4.5mの2ブロツクに分けて事前に陸上製作した
ものを使った。この実施の結果、工事期間が従来のもの
に比べると約10日短縮でき、□その作業も頗る順調で
あった。
(B) is a detailed view of the foundation, which has an oval column base measuring 7.8 m long, 4.3 m wide, and 9.4 m high. Of the 80cm thick column pedestal wall, a 15cm concrete outer wall was divided into two 4.5m high blocks that had been fabricated on land in advance. As a result of this implementation, the construction period was shortened by about 10 days compared to the conventional method, and the work went extremely smoothly.

以上説明したように本発明によれば、コンクリート外壁
が型枠を兼用するから型枠を水上で組立てたり撤去した
りするような必要がないので、施工工事が簡単で工期を
短縮することができ、美観の点ても従来に優れる゛。
As explained above, according to the present invention, since the concrete outer wall also serves as the formwork, there is no need to assemble or remove the formwork on the water, so the construction work is simple and the construction period can be shortened. It is also superior to conventional models in terms of aesthetics.

【図面の簡単な説明】[Brief explanation of drawings]

第1図は柱脚基礎の一般的な例を示す【E面図、第2図
の(イ)、(ロ)および第8図の(イ)、(ロ)は、い
ずれも本発明施工例で採用する水中構造物の切欠き平面
図と切欠き正面図、 第4図の(イ)、(ロ)は、構造物壁体の部分断面図、 第5図は本発明施工方法の各段階を示す工程図、第6図
の(イ)、(ロ)はブラケットによるコンクリート外壁
、型枠支持の模様を示す断面図、第7図はブラケットの
詳細を示す正面図、第8図および第9図は構造物下に盛
土施工しした状態の断面図、 第1O図の(イ)、(ロ)はいずれも実施例の柱脚の切
欠き断面図である。 ■・・・水中構造物壁体  2・・・m管杭8・・・コ
ンクリート外壁 4・・・型枠(内側壁用)5・・・申
請コンクリート 6.6’、7.8・・・鉄筋9・・・
支持板      IO・・・クレーン船11・・・台
船      12.12’・・・ブラケット12 a
 、 12’a・・・ブラケットのダミーパー18・・
・盛土      14・・・トレミー管特許出願人 
川崎製鉄株式会社 第4図 (イン 1) 79− 特開昭58−138814(6)
Fig. 1 shows a general example of a column base foundation [E side view, Fig. 2 (a), (b), and Fig. 8 (a), (b) are all examples of construction according to the present invention. Fig. 4 (a) and (b) are partial sectional views of the structure wall, and Fig. 5 shows each stage of the construction method of the present invention. Fig. 6 (a) and (b) are cross-sectional views showing the pattern of the concrete outer wall and formwork support by brackets, Fig. 7 is a front view showing details of the brackets, Figs. 8 and 9 The figure is a sectional view of the embankment constructed under the structure, and Figure 1O (a) and (b) are both cutaway sectional views of the column base of the example. ■...Underwater structure wall 2...m pipe pile 8...Concrete outer wall 4...Formwork (for inner wall) 5...Applicable concrete 6.6', 7.8... Rebar 9...
Support plate IO... Crane ship 11... Barge 12.12'... Bracket 12 a
, 12'a... Bracket dummy par 18...
・Embankment 14... Tremie pipe patent applicant
Kawasaki Steel Co., Ltd. Figure 4 (In 1) 79- JP-A-58-138814 (6)

Claims (1)

【特許請求の範囲】 1、 水中でのコンクリート構造物施工に際し、予め構
a物壁体の一部を構成する筒殻状コンクIJ−)外11
iを打設成型し、このコンクリート外壁を仮設用ブラケ
ットを固定17た真管杭に沿って所定の位置に据付け、
その後上記コンクリート外壁と他の型枠との間に中詰コ
ンクリートを打設して、上記筒殻状コンクリート外墜を
その−・部に含む一体構唐物にすることを特徴とする水
中構造物の施工H法。 a 上記の池の型枠が、筒殻状コンクリート壁または鋼
製枠である特許請求の範囲1記載の方法。
[Claims] 1. When constructing a concrete structure underwater, a cylindrical concrete IJ-) outside 11 that forms part of the wall of the structure is prepared in advance.
i was cast and formed, and this concrete outer wall was installed in a predetermined position along the true pipe piles to which temporary brackets were fixed.
An underwater structure characterized in that filling concrete is then placed between the concrete outer wall and another formwork to form an integral structure including the cylindrical shell-shaped concrete outer wall in its part. Construction method H. a. The method according to claim 1, wherein the pond formwork is a cylindrical concrete wall or a steel frame.
JP57018910A 1982-02-10 1982-02-10 Construction of underwater structure Granted JPS58138814A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP57018910A JPS58138814A (en) 1982-02-10 1982-02-10 Construction of underwater structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP57018910A JPS58138814A (en) 1982-02-10 1982-02-10 Construction of underwater structure

Publications (2)

Publication Number Publication Date
JPS58138814A true JPS58138814A (en) 1983-08-17
JPS62292B2 JPS62292B2 (en) 1987-01-07

Family

ID=11984754

Family Applications (1)

Application Number Title Priority Date Filing Date
JP57018910A Granted JPS58138814A (en) 1982-02-10 1982-02-10 Construction of underwater structure

Country Status (1)

Country Link
JP (1) JPS58138814A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS60203721A (en) * 1984-03-27 1985-10-15 Takenaka Komuten Co Ltd Marine concrete structure

Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS5425727A (en) * 1977-07-28 1979-02-26 Ricoh Co Ltd Image projection method for copying lens

Patent Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS5425727A (en) * 1977-07-28 1979-02-26 Ricoh Co Ltd Image projection method for copying lens

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS60203721A (en) * 1984-03-27 1985-10-15 Takenaka Komuten Co Ltd Marine concrete structure

Also Published As

Publication number Publication date
JPS62292B2 (en) 1987-01-07

Similar Documents

Publication Publication Date Title
US4015379A (en) In-ground swimming pool and apparatus and method for constructing same
JPS58138814A (en) Construction of underwater structure
KR101923973B1 (en) Outer wall construction method of underground structure using the reverse t-type steel composite vertical member
JPS5829922A (en) Constructing method for underground outer wall
GB2136287A (en) Swimming pool construction
JPH08100464A (en) Joint structure and work execution method for structure using it
JPH03191116A (en) Construction method of underground beam and underground beam driving form
JPH10299003A (en) Foundation work using precast concrete member
JPS61102911A (en) Steel cell
JP3232487B2 (en) Construction method of column base and column base structure
JP2802612B2 (en) Underwater formwork method
JPS6290445A (en) Block for foundation and its manufacture
JPS61134422A (en) Method of building precast concrete underground continuous wall
JPS63537A (en) Construction work of underground structure
JPH06330507A (en) Abutment
JP2936130B2 (en) Construction method of steel frame concrete structure
JPH0321771A (en) Construction method for footing using sheet mould
JPH0337603B2 (en)
JPS5841118A (en) Sheathing and protecting method for long-sized slope
JPH073781A (en) Method for constructing foundation footing on cast-in-place concrete pile head
JPH0649824A (en) Breakwater
JP3289163B2 (en) How to build underground structures
JPH0441817A (en) Sheathing method
JPH03253612A (en) Construction of earth retaining of underground structure and construction member used for it
JPH03260222A (en) Construction of slope frame and block structure