JP2802612B2 - Underwater formwork method - Google Patents

Underwater formwork method

Info

Publication number
JP2802612B2
JP2802612B2 JP8158092A JP15809296A JP2802612B2 JP 2802612 B2 JP2802612 B2 JP 2802612B2 JP 8158092 A JP8158092 A JP 8158092A JP 15809296 A JP15809296 A JP 15809296A JP 2802612 B2 JP2802612 B2 JP 2802612B2
Authority
JP
Japan
Prior art keywords
formwork
steel frame
underwater
concrete
columns
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
JP8158092A
Other languages
Japanese (ja)
Other versions
JPH108713A (en
Inventor
富士雄 飯塚
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Nishimatsu Construction Co Ltd
Original Assignee
Nishimatsu Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Nishimatsu Construction Co Ltd filed Critical Nishimatsu Construction Co Ltd
Priority to JP8158092A priority Critical patent/JP2802612B2/en
Publication of JPH108713A publication Critical patent/JPH108713A/en
Application granted granted Critical
Publication of JP2802612B2 publication Critical patent/JP2802612B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Landscapes

  • Revetment (AREA)
  • Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【発明の属する技術分野】本発明は、護岸工事その他の
施工での水中型枠工法に関するものである。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to an underwater formwork method for revetment work and other works.

【0002】[0002]

【従来の技術】水中での現場打ちコンクリート工事で
は、水中に型枠を設置してその中にコンクリートを打設
する。そして、この型枠としては、通常陸上で組むよう
な型枠を水中で組むことになる。
2. Description of the Related Art In the field of cast-in-place concrete underwater, a formwork is installed in water and concrete is poured therein. Then, as this formwork, a formwork that is normally assembled on land is assembled underwater.

【0003】[0003]

【発明が解決しようとする課題】このような水中での型
枠設置は潜水士の作業となるが、型枠を構成する部材点
数が多いと作業工程が複雑化し、また、作業時間も長く
なる。すなわち、水中での現場打ちコンクリート工事に
おいては、使用する水中型枠の形式によって作業の効
率、安全性が大きく左右される。
The installation of a formwork in water is a task of a diver, but if the number of members constituting the formwork is large, the work process becomes complicated and the work time becomes long. . In other words, in underwater cast-in-place concrete work, the efficiency and safety of work are greatly affected by the type of underwater formwork used.

【0004】本発明の目的は前記従来例の不都合を解消
し、水中での型枠組立て作業が容易であるとともに、波
圧、流水圧等の対する型枠の安全性も向上することがで
きる水中型枠工法を提供することにある。
An object of the present invention is to solve the disadvantages of the prior art, to facilitate the assembling work of the formwork in water, and to improve the safety of the formwork against wave pressure, flowing water pressure and the like. An object of the present invention is to provide a formwork method.

【0005】[0005]

【課題を解決するための手段】本発明は前記目的を達成
するため、適宜間隔で並べた支柱となるH形鋼間を横材
と筋違いで連結してなる鋼製フレームを現地の陸上で組
み立て、該鋼製フレームを水中の所定の位置にセット
し、該鋼製フレームを既設構造物にアンカーで繋ぎと
め、プレキャストコンクリート製のせき板をその端部を
前記支柱のフランジ間の溝に沿わせて支柱間に落とし込
んで型枠を形成し、その内側にコンクリートを打設する
ことを要旨とするものである。
SUMMARY OF THE INVENTION In order to achieve the above-mentioned object, the present invention assembles a steel frame in which H-shaped steel beams, which are columns arranged at appropriate intervals, are connected to cross members with a straight line on land on land. The steel frame is set at a predetermined position in the water, the steel frame is anchored to the existing structure with an anchor, and the end of the precast concrete dam is placed along the groove between the flanges of the support. The gist of the present invention is to form a formwork by dropping it between support columns and to cast concrete inside the formwork.

【0006】本発明によれば、型枠のせき板とバタ材で
ある鋼製フレームとを分離した構造とし、それぞれを陸
上で製作した後、個別に建込むことになる。その結果、
型枠設置のためのセパレータの取付けなど水中作業が必
要となる段階ではせき板は挿入されていないので、潜水
士の作業空間に余裕があり、作業性がよい。また、せき
板による作業空間が閉塞されることもないので、安全性
が高い。
According to the present invention, the damping plate of the formwork and the steel frame, which is a fluttering material, are separated from each other, and they are separately built after being manufactured on land. as a result,
At the stage where underwater work is required, such as installation of a separator for installation of a formwork, since the dam is not inserted, the work space for the diver has ample room and good workability. In addition, since the working space is not blocked by the weir board, the safety is high.

【0007】また、せき板の挿入は型枠組立の最終工程
でよいため、型枠に作用する波圧等の影響を最小限に抑
えることができる。
Further, since the insertion of the weir plate may be performed in the final step of assembling the formwork, the influence of wave pressure or the like acting on the formwork can be minimized.

【0008】[0008]

【発明の実施の形態】以下、図面について本発明の実施
の形態を説明する。図1は本発明の水中型枠工法の1実
施形態を示す縦断側面図、図2は要部の拡大縦断側面
図、図3は要部の拡大平面図である。
Embodiments of the present invention will be described below with reference to the drawings. 1 is a vertical sectional side view showing one embodiment of the underwater formwork method of the present invention, FIG. 2 is an enlarged vertical sectional side view of a main part, and FIG. 3 is an enlarged plan view of a main part.

【0009】図中1は図4にも示すようにH形鋼による
支柱2を適宜間隔(2〜3m)で並べた鋼製フレーム
で、H形鋼4を上端の横材として、アングル材3を中央
の横材および筋違いとして、チャンネル材5を下端の横
材として配設した。図中6はボルト穴である。
In FIG. 1, reference numeral 1 denotes a steel frame in which columns 2 made of H-shaped steel are arranged at appropriate intervals (2 to 3 m) as shown in FIG. Was set as a center horizontal member and a straight line, and the channel member 5 was provided as a lower horizontal member. 6 is a bolt hole in the figure.

【0010】この鋼製フレーム1を現地の陸上で組み立
て、これを水中の所定位置にセットし、既設構造物7に
アンカー14で繋ぎとめる。このアンカー14は、セパ
レターとしての鋼棒9と平板やアングル材などの結合金
物16とボルト・ナット11、ナット12で構成し、既
設構造物7にはケミカルアンカー13で固定する。
The steel frame 1 is assembled on the land on the site, set at a predetermined position in the water, and connected to the existing structure 7 with the anchor 14. The anchor 14 is composed of a steel rod 9 as a separator, a coupling hardware 16 such as a flat plate or an angle material, and bolts / nuts 11 and nuts 12, and is fixed to the existing structure 7 with a chemical anchor 13.

【0011】そして工場で製作したプレキャストコンク
リート製のせき板8をその端部を前記鋼製フレーム1の
支柱2のフランジ2a間の溝に沿わせて支柱2間に落と
し込み、図3に示すようにフランジ2aとの隙間をキャ
ンバー15で固定する。
Then, a precast concrete weir plate 8 manufactured at the factory is dropped between the columns 2 along the groove between the flanges 2a of the columns 2 of the steel frame 1 as shown in FIG. The gap with the flange 2a is fixed with the camber 15.

【0012】せき板8は図5に示すように一体化用の鉄
筋10を突出してなるが、この鉄筋10はせき板8の挿
入時は折り曲げて表面に沿わせ、落とし込み後に伸ばし
て突出させる。また、せき板8は上下に数段積み重ね
る。
As shown in FIG. 5, the weir plate 8 is formed by projecting a reinforcing bar 10 for integration. When the weir plate 8 is inserted, the reinforcing bar 10 is bent to conform to the surface, and is extended and projected after dropping. Further, the weir plates 8 are stacked one above the other.

【0013】このようにして鋼製フレーム1とせき板8
で型枠を形成し、既設構造物7との間に水中コンクリー
ト(水中不分離コンクリート)を打設すれば、既設構造
物7の補修・補強が行える。なお、前記鋼製フレーム1
やせき板8の形状寸法は構造物の形状や作業条件に応じ
て、構造計算により決定する。
In this manner, the steel frame 1 and the dam 8
When the underwater concrete (underwater inseparable concrete) is cast between the mold and the existing structure 7, the existing structure 7 can be repaired and reinforced. The steel frame 1
The shape and size of the damping plate 8 are determined by structural calculation according to the shape of the structure and working conditions.

【0014】前記実施形態は既設構造物の補修・補強コ
ンクリートを打設する場合について説明したが、既設構
造物に鋼製フレームをアンカーで繋ぎとめ、プレキャス
トコンクリート製のせき板をその端部を前記支柱のフラ
ンジ間の溝に沿わせて支柱間に落とし込んで型枠を形成
してコンクリートを打設する場合であれば、補修・補強
の場合に限らず適用が可能なものである。
In the above-described embodiment, the case where repair / reinforcement concrete for an existing structure is cast is explained. However, a steel frame is connected to the existing structure with an anchor, and a precast concrete dam is attached to the end of the steel frame. The present invention is applicable not only to the case of repair and reinforcement, but also to the case where concrete is poured by dropping between pillars along the groove between the flanges of the pillars to form a formwork, and is applicable.

【0015】[0015]

【発明の効果】以上述べたように本発明の水中型枠工法
は、水中での型枠組立て作業が容易であるとともに、波
圧、流水圧等の対する型枠の安全性も向上するものであ
る。
As described above, the underwater formwork method of the present invention facilitates the work of assembling the formwork in water and improves the safety of the formwork against wave pressure, flowing water pressure and the like. is there.

【図面の簡単な説明】[Brief description of the drawings]

【図1】本発明の水中型枠工法の1実施形態を示す縦断
側面図である。
FIG. 1 is a vertical sectional side view showing one embodiment of an underwater formwork method of the present invention.

【図2】本発明の水中型枠工法の1実施形態を示す要部
の拡大縦断側面図である。
FIG. 2 is an enlarged longitudinal sectional side view of a main part showing one embodiment of the underwater formwork method of the present invention.

【図3】本発明の水中型枠工法の1実施形態を示す要部
の拡大平面図である。
FIG. 3 is an enlarged plan view of a main part showing one embodiment of the underwater formwork method of the present invention.

【図4】鋼製フレームの正面図である。FIG. 4 is a front view of a steel frame.

【図5】せき板の横断平面図である。FIG. 5 is a cross-sectional plan view of the weir plate.

【符号の説明】[Explanation of symbols]

1…鋼製フレーム 2…支柱 2a…フランジ 3…アングル材 4…H形鋼 5…チャンネル材 6…ボルト穴 7…既成構造物 8…せき板 9…鋼棒 10…鉄筋 11…ボルト・ナット 12…ナット 13…ケミカルアンカー 14…アンカー 15…キャンバー 16…結合金物 DESCRIPTION OF SYMBOLS 1 ... Steel frame 2 ... Prop 2a ... Flange 3 ... Angle material 4 ... H-shaped steel 5 ... Channel material 6 ... Bolt hole 7 ... Prefabricated structure 8 ... Weir board 9 ... Steel rod 10 ... Reinforcing rod 11 ... Bolt / nut 12 ... Nut 13 ... Chemical anchor 14 ... Anchor 15 ... Camber 16 ... Binding hardware

Claims (1)

(57)【特許請求の範囲】(57) [Claims] 【請求項1】 適宜間隔で並べた支柱となるH形鋼間を
横材と筋違いで連結してなる鋼製フレームを現地の陸上
で組み立て、該鋼製フレームを水中の所定の位置にセッ
トし、該鋼製フレームを既設構造物にアンカーで繋ぎと
め、プレキャストコンクリート製のせき板をその端部を
前記支柱のフランジ間の溝に沿わせて支柱間に落とし込
んで型枠を形成し、その内側にコンクリートを打設する
ことを特徴とする水中型枠工法。
1. A steel frame formed by connecting H-shaped steels, which are columns arranged at appropriate intervals, with a cross member and a streak, is assembled on land locally, and the steel frame is set at a predetermined position in water. Anchoring the steel frame to the existing structure with an anchor, dropping a precast concrete weir plate between the columns with the ends thereof along the grooves between the flanges of the columns to form a formwork, An underwater formwork method characterized by placing concrete in the concrete.
JP8158092A 1996-06-19 1996-06-19 Underwater formwork method Expired - Fee Related JP2802612B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP8158092A JP2802612B2 (en) 1996-06-19 1996-06-19 Underwater formwork method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP8158092A JP2802612B2 (en) 1996-06-19 1996-06-19 Underwater formwork method

Publications (2)

Publication Number Publication Date
JPH108713A JPH108713A (en) 1998-01-13
JP2802612B2 true JP2802612B2 (en) 1998-09-24

Family

ID=15664133

Family Applications (1)

Application Number Title Priority Date Filing Date
JP8158092A Expired - Fee Related JP2802612B2 (en) 1996-06-19 1996-06-19 Underwater formwork method

Country Status (1)

Country Link
JP (1) JP2802612B2 (en)

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP4776043B1 (en) * 2010-09-06 2011-09-21 株式会社西田工業 Expansion method for offshore structures
JP6915844B2 (en) * 2017-03-27 2021-08-04 株式会社 南組 Work space formation for wall surface repair and work space formation method for wall surface repair

Family Cites Families (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2836406B2 (en) * 1992-11-06 1998-12-14 株式会社大林組 Construction method of reinforced concrete wall using PC version
JP2852173B2 (en) * 1993-04-21 1999-01-27 ジオスター株式会社 Seawall construction using steel sheet piles

Also Published As

Publication number Publication date
JPH108713A (en) 1998-01-13

Similar Documents

Publication Publication Date Title
RU2375523C1 (en) Formwork for constructing reinforcing covering of construction made from corrugated steel plates
US4192120A (en) Method of constructing reinforced concrete bridges
JP2802612B2 (en) Underwater formwork method
KR20080099061A (en) Psc beam for connection steel width step of psc bridges
KR100324704B1 (en) Formwork method using no prop for the floor concrete of the bridge
JP3466961B2 (en) Reinforcement method for existing load-bearing walls with openings
JP2000234410A (en) Driven form and slab construction method making use thereof
KR100346960B1 (en) An apparatus and method for anchoring steel column to concrete
JP3137448B2 (en) Construction method of concrete main tower
JP2001311247A (en) Construction method for concrete structure
KR100609825B1 (en) Preflexed rigid- frame bridge installed using prestressed upper structure and constructing method thereof
JP3103808B2 (en) Net formwork method for walls and floors
JPH08100464A (en) Joint structure and work execution method for structure using it
JP2000160687A (en) Construction method for composite structure and precast concrete column
JP2000064314A (en) Construction of structural foundation building frame
JP2860501B2 (en) Concrete foundation
JPH08269912A (en) Fastening method of steel bridge pier to footing
JPH0634465Y2 (en) Simple PC panel
JPH05239810A (en) Constructing method for reinforced concrete arch bridge
KR20100057991A (en) Concrete slab mold assembly and method for constructing slab
JPH07292855A (en) Steel encased reinforcing concrete girder
GB1579569A (en) Method of erecting a building
JP2782111B2 (en) Steel framing construction method
JP3232487B2 (en) Construction method of column base and column base structure
SU1135852A1 (en) Prefabricated block of ferroconcrete mat of pile foundation and method of constructing pile foundation with ferroconcrete mat of prefabricated blocks

Legal Events

Date Code Title Description
R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20090717

Year of fee payment: 11

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20100717

Year of fee payment: 12

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20110717

Year of fee payment: 13

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20120717

Year of fee payment: 14

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20130717

Year of fee payment: 15

LAPS Cancellation because of no payment of annual fees