JP2936130B2 - Construction method of steel frame concrete structure - Google Patents

Construction method of steel frame concrete structure

Info

Publication number
JP2936130B2
JP2936130B2 JP31864393A JP31864393A JP2936130B2 JP 2936130 B2 JP2936130 B2 JP 2936130B2 JP 31864393 A JP31864393 A JP 31864393A JP 31864393 A JP31864393 A JP 31864393A JP 2936130 B2 JP2936130 B2 JP 2936130B2
Authority
JP
Japan
Prior art keywords
concrete
concrete structure
slab
steel girder
internal steel
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
JP31864393A
Other languages
Japanese (ja)
Other versions
JPH07173831A (en
Inventor
理 清宮
吉村  正
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
UNYUSHO KOWAN GIJUTSU KENKYUSHOCHO
Mitsui Zosen KK
Original Assignee
UNYUSHO KOWAN GIJUTSU KENKYUSHOCHO
Mitsui Zosen KK
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by UNYUSHO KOWAN GIJUTSU KENKYUSHOCHO, Mitsui Zosen KK filed Critical UNYUSHO KOWAN GIJUTSU KENKYUSHOCHO
Priority to JP31864393A priority Critical patent/JP2936130B2/en
Publication of JPH07173831A publication Critical patent/JPH07173831A/en
Application granted granted Critical
Publication of JP2936130B2 publication Critical patent/JP2936130B2/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Landscapes

  • Bulkheads Adapted To Foundation Construction (AREA)
  • Revetment (AREA)

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【産業上の利用分野】本発明はコンクリート構造物の建
造方法、より詳しくは、比較的高深度水域の防波堤、岸
壁、浮桟橋、浮体空港など海洋港湾構造物に利用される
コンクリート構造物の建設方法に関するものである。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a method for constructing a concrete structure, and more particularly, to the construction of a concrete structure used for a marine harbor structure such as a breakwater, a quay, a floating pier, a floating airport in a relatively deep water area. It is about the method.

【0002】[0002]

【従来の技術】従来、沿岸域において用いられる護岸
壁、消波堤や防波堤等の構造物としてはコンクリート構
造物が用いられている。そしてこのコンクリート構造物
は現地での工期短縮や作業環境等の問題から他の地域で
の浮揚建造物として建造され、これを現地に曳航沈設さ
れることが多い。
2. Description of the Related Art Conventionally, concrete structures have been used as structures such as seawalls, breakwaters and breakwaters used in coastal areas. This concrete structure is often constructed as a floating structure in other areas due to problems such as shortened construction period and work environment at the site, and is often towed to the site.

【0003】即ち、このコンクリート構造物は内部に骨
組材としての内部鋼桁を有する函体として構成され、そ
の底版や側壁等に鉄筋が配置され、コンクリートが打設
されて建造されている。そしてこのコンクリート打設は
通常底版から始められ順次側壁の上部に向かって行なわ
れている。
[0003] That is, this concrete structure is constructed as a box having an internal steel girder as a framing material inside, a reinforcing bar is arranged on the bottom slab and side walls, and concrete is cast and built. This concrete casting is usually started from the bottom slab and is performed sequentially toward the upper part of the side wall.

【0004】[0004]

【発明が解決しようとする課題】ところで前記従来のコ
ンクリート構造物の建造方法には本質的な問題がある。
即ち、内部鋼桁の周囲に打設される側壁にあってはコン
クリート養生の関係から1回の打設高さはせいぜい3〜
4mに制限されるため、それ以上の高さ、例えば15〜
20m程度のコンクリート構造物を建造する場合にあっ
ては鉄筋の配設、コンクリートの打設及びコンクリート
の養生の工程を繰返す必要がある。しかもこのコンクリ
ート養生には1〜2週間もの期間を必要とし、この工程
を繰返すことになるために建造工期が長くなることとな
る。このことは例えばドック内等で建造する場合のドッ
クの使用効率を著しく低下させることとなる。
However, the conventional method for constructing a concrete structure has an essential problem.
That is, in the side wall to be cast around the internal steel girder, the height of one cast is at most 3 to 4 due to the concrete curing.
Because it is limited to 4 m, the height more than that, for example, 15 to
In the case of constructing a concrete structure of about 20 m, it is necessary to repeat the steps of arranging reinforcing bars, placing concrete, and curing concrete. In addition, this concrete curing requires a period of one to two weeks, and since this process is repeated, the construction period is prolonged. This significantly reduces the use efficiency of the dock when building it inside the dock, for example.

【0005】特に、最近このコンクリート構造物の高さ
が15〜30mにも達する大型のものが要求されてお
り、そのため建造工期を短縮できるコンクリート構造物
の建造方法の開発がこの業界において望まれている。
In particular, recently, there is a demand for a large-sized concrete structure having a height of 15 to 30 m. Therefore, it is desired in the industry to develop a method of constructing a concrete structure capable of shortening the construction period. I have.

【0006】[0006]

【課題を解決するための手段】本発明は前記従来技術の
問題点を解消するためになされたものであって、 部鋼
桁の表面に、縦方向に1回でコンクリートを打設できる
高さよりも長いコ ンクリート壁を有するコンクリート構
造物の建設方法であって、複数の内部鋼 桁を製作すると
共に、前記コンクリート構造物の高さに相当する長さを
有する 複数枚の長いプレストコンクリート版を、水平状
態で製作する工程と、架台上 に底版配筋を敷設し、底版
コンクリートを打設する工程と、前記底版配筋上に 前記
内部鋼桁を所定の間隔をおいて植立する工程と、前記内
部鋼桁を支持部材 としてその表面に、前記水平状態で製
作されたプレストコンクリート版を立て て配置する工程
と、前記各プレストコンクリート版の鉄筋を前記内部鋼
桁に連 結する工程と、更に前記内部鋼桁に固定されたプ
レストコンクリート版の間に コンクリートを打設して、
このプレストコンクリート版を一体的に形成する工 程と
からなる鋼骨組コンクリート構造物の建設方法を提供す
るものである。
SUMMARY OF THE INVENTION The present invention was made to solve the problems of the prior art, internal steel
Concrete can be poured on the girder surface once in the vertical direction
Concrete structure with a long concrete wall than the height
A method of constructing a structure, where multiple internal steel girders are made
In both cases, the length corresponding to the height of the concrete structure is
Hold multiple long prestressed concrete slabs in a horizontal
Manufacturing process, and laying the bottom plate reinforcement on the gantry,
A step of pouring the concrete, the said bottom plate on Reinforcement
Erecting the internal steel girders at predetermined intervals;
The steel girder is used as a support member ,
The process of placing and placing the prepared prestressed concrete slab
And the reinforcing steel of each prestressed concrete
A step of concatenating the digits flop which is further fixed to the inner steel girder
Place concrete between the rest concrete plates ,
And the Presto concrete version as engineering be integrally formed
And a method of constructing a steel-framed concrete structure comprising:

【0007】[0007]

【作 用】本発明の鋼骨組コンクリート構造物の建造方
法によれば、コンクリート構造物を構成する側壁は、こ
のコンクリート構造物の高さに相当する長さを持つプ
ストコンクリート版(プレストレストコンクリート版の
略称)とし、このプレストコンクリート版は1回の打設
工程で完成するように、あらかじめ水平状態でプレスト
コンクリート版として別に製作される。そして内部鋼桁
を支持部材としてこれの周囲を覆うようにプレストコン
クリート版が設けられる。
[Operation] According to the method for constructing a steel-framed concrete structure of the present invention, the side wall constituting the concrete structure is formed by the following method.
Flop les having a length corresponding to the height of the concrete structure
Stretched concrete slab (prestressed concrete slab
Abbreviated name), and this prestressed concrete slab is cast once
It is manufactured separately as a prestressed concrete plate in a horizontal state so that it is completed in the process . Then, a prestressed concrete plate is provided so as to cover the periphery of the internal steel girder as a supporting member.

【0008】従って、コンクリート版の打設高さによる
制限がなくなり、コンクリート養生期間の短縮と内部鋼
桁等の製作配置とその工期を同時期とすることができ、
大幅な工期短縮を計ることができる。
Accordingly, there is no limitation due to the height of the concrete slab, so that the concrete curing period can be shortened, the production arrangement of the internal steel girders, etc., and the construction period can be made at the same time.
The construction period can be significantly reduced.

【0009】[0009]

【実 施 例】以下、図1ないし図8に基づき本発明に
よる鋼骨組コンクリート構造物の建造方法の一実施例を
説明する。図1は埋立地1の護岸用に配置された鋼骨組
コンクリート構造物2の一部を破断して示す斜視図であ
って、この鋼骨組コンクリート構造物2は海底3に布設
された基礎捨石4上に配置されており、その構造は内部
鋼桁5の周囲に鉄筋を有するコンクリート側壁6及び図
示しない底版と上部に上部工7が設けられている。な
お、必要に応じて隔壁8が設けられている。
DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS An embodiment of a method of constructing a steel-framed concrete structure according to the present invention will be described below with reference to FIGS. FIG. 1 is a perspective view showing a part of a steel-framed concrete structure 2 disposed for revetment of a landfill 1 in a cutaway view. The steel-framed concrete structure 2 is a foundation rubble 4 laid on a seabed 3. The structure is provided with a concrete side wall 6 having a reinforcing bar around an internal steel girder 5, a bottom slab (not shown), and a superstructure 7 at an upper portion. In addition, the partition 8 is provided as needed.

【0010】そしてこの鋼骨組コンクリート構造物2は
ドライドック等により建造され、この据付現地、即ち埋
立地等に曳航されて沈設されるものである。このコンク
リート構造物2を建造する工程は、図2に示すようにド
ック内あるいはコンクリート構造物2を進水させること
ができる地盤13上に設けた架台9上に底版配筋10を
行なう。そしてこの底版配筋10に図3に示す如く底版
コンクリート11が打設されて底版が完成するものであ
る。
The steel-framed concrete structure 2 is constructed by a dry dock or the like, and is towed and laid down at the installation site, that is, a landfill. In the step of constructing the concrete structure 2, as shown in FIG. 2, the bottom slab arrangement 10 is performed in a dock or on a gantry 9 provided on a ground 13 on which the concrete structure 2 can be launched. Then, the bottom slab concrete 11 is poured into the bottom slab arrangement 10 as shown in FIG. 3 to complete the bottom slab.

【0011】本発明は、従来技術のようにコンクリート
を高さ方向に短く打設してこれを 養生するという打設と
養生を数回繰り返しながら、所定の高さのコンクリート
版(コンクリート壁)とする逐次的な打設方法を採用す
るのではなく、建造物 壁面の高さに合わせて高さ方向
に分割された、長いプレストコンクリート版を、水平に
した状態で1回の打設で製作し、これをクレーンを使用
して内部鋼桁5の周囲に貼り付けるように組立てること
を特徴とするものである。
According to the present invention, there is provided a method in which concrete is poured short in the height direction and cured as in the prior art.
Adopt a sequential placement method to make a concrete slab (concrete wall) of a predetermined height while repeating curing several times .
Instead, a long prestressed concrete slab divided in the height direction according to the height of the wall of the building is produced in a single casting in a horizontal state, and this is made using a crane. It is characterized in that it is assembled so as to be attached around the internal steel girder 5.

【0012】従って、底版コンクリート11の周囲ない
しは別の箇所において各種のプレストコンクリート版が
製作され、あるいは製作されたものが搬入される。図3
はこの1例を示すもので、側壁コンクリート版6a、端
壁コンクリート版6b等が水平状態で一体的に製作され
る。内部鋼桁5は図4にその一部を示すように周囲にフ
ランジ部5aを有し、その表面の中央部にはスタッド1
6が突設されている。また、図5に示すように各コンク
リート版6a、6bの側方に鉄筋17が突出して設けら
れている。
Therefore, various prestressed concrete slabs are produced around the bottom slab concrete 11 or at another place, or the produced slabs are carried in. FIG.
Shows an example of this, in which a side wall concrete plate 6a, an end wall concrete plate 6b and the like are integrally manufactured in a horizontal state. The internal steel girder 5 has a flange portion 5a around its periphery as shown in FIG.
6 are protrudingly provided. Further, as shown in FIG. 5, a reinforcing bar 17 is provided to protrude to the side of each of the concrete plates 6a and 6b.

【0013】このように各プレストコンクリート版が水
平においた状態で製作されると、図3に示すように、底
版コンクリート11の上方中央部に内部鋼桁5が所定の
間隔(a)で配置され、継材によってこれらの内部鋼桁
5同士が連結されて枠状の構造物が形成される。この間
隔(a)は側壁コンクリート版6aの幅(b)より僅か
に大きな幅に形成されている。
When each prestressed concrete slab is manufactured in a horizontal state as described above, the internal steel girders 5 are arranged at a predetermined interval (a) in the upper central portion of the bottom slab concrete 11, as shown in FIG. The internal steel girders 5 are connected to each other by the joining material to form a frame-shaped structure. This space (a) is formed to have a width slightly larger than the width (b) of the side wall concrete slab 6a.

【0014】なお、水平方向に置いた状態でコンクリー
トを打設して製作するプレストコンクリート版は、従来
技術であれば複数回に分けて打設しなければできない部
材に適用することを意味し、小規模なプレストコンクリ
ート版であれば従来技術を採用して製作することは許容
されるものである。次に図6及び図7に示すように底版
コンクリート11上に植立された内部鋼桁5を内部構造
部材としてこれの表面を覆うように側壁コンクリート版
6a、端壁コンクリート版6bが次々に内部鋼桁5のフ
ランジ部5a上に配置され、鉄筋コンクリートあるいは
プレストコンクリートによるプレキヤストコンクリート
版の大組立がなされ、常法により図7〜図10に示すよ
うにシース16連結、PC鋼線17の挿入、プレストレ
スの導入等の組立工程が行なわれる。
The prestressed concrete slab, which is produced by casting concrete while placed horizontally, means that it can be applied to members which cannot be cast in a plurality of times in the prior art. It is acceptable to manufacture a small-scale prestressed concrete plate by employing the conventional technology. Next, as shown in FIG. 6 and FIG. 7, the internal steel girders 5 planted on the bottom slab concrete 11 are used as internal structural members, and the side wall concrete slabs 6a and the end wall concrete slabs 6b are successively provided so as to cover the surfaces thereof. It is arranged on the flange portion 5a of the steel girder 5, and large-scale assembly of a precast concrete slab made of reinforced concrete or prestressed concrete is performed. As shown in FIG. 7 to FIG. An assembling process such as introduction of prestress is performed.

【0015】次に、側壁コンクリート版6a、端壁コン
クリート版6bの間を連結して一体構造にするために打
継ぎのコンクリート18(図7)の打設が行なわれ、P
C緊張力がPC鋼線17に与えられ、コンクリート構造
物2が完成する。前記工程によって大型の鋼骨組コンク
リート構造物2がドック内等で完成されたわけである
が、この場合ドック内に注水することによってこのコン
クリート構造物2を浮上させて設置場所に曳航して図1
示す捨石4上に沈設し、その後の工事を行なって埋立護
岸工事が完成するのである。
Next, in order to connect the side wall concrete slab 6a and the end wall concrete slab 6b to form an integrated structure, a joint concrete 18 (FIG. 7) is cast.
C tension is applied to the PC steel wire 17, and the concrete structure 2 is completed. The large steel frame concrete structure 2 was completed in the dock or the like by the above-described process. In this case, the concrete structure 2 was floated by pouring water into the dock and towed to the installation place.
It is laid on the rubble 4 shown below, and the subsequent work is performed to complete the reclamation work.

【0016】[0016]

【発明の効果】本発明に係る鋼骨組コンクリート構造物
の建設方法は、内部鋼桁の表面に、 縦方向に1回でコン
クリートを打設できる高さよりも長いコンクリート壁を
するコンクリート構造物の建設方法であって、複数の
内部鋼桁を製作すると共 に、前記コンクリート構造物の
高さに相当する長さを有する複数枚の長いプレ ストコン
クリート版を、水平状態で製作する工程と、架台上に底
版配筋を敷設 し、底版コンクリートを打設する工程と、
前記底版配筋上に前記内部鋼桁を所 定の間隔をおいて植
立する工程と、前記内部鋼桁を支持部材としてその表面
、前記水平状態で製作されたプレストコンクリート版
を立てて配置する工程と 、前記各プレストコンクリート
版の鉄筋を前記内部鋼桁に連結する工程と、更 に前記内
部鋼桁に固定されたプレストコンクリート版の間にコン
クリートを打 設して、このプレストコンクリート版を一
体的に形成する工程とから構成されている。
The method for constructing a steel-framed concrete structure according to the present invention provides a method for constructing a steel frame concrete on the surface of an internal steel girder once in the vertical direction.
A concrete wall longer than the height where cleats can be cast
A construction method Yu to the concrete structure, a plurality of
Co When fabricating the internal steel girder, of the concrete structure
A plurality of long pre Sutokon having a length corresponding to the height
The process of manufacturing the cleat plate in a horizontal state and the bottom
Laying slab arrangements and placing bottom slab concrete;
Planting at intervals of the internal steel girder to Jo Tokoro on the bottom plate on the reinforcement
Erecting, and the surface of the internal steel girder as a support member
The prestressed concrete plate manufactured in the horizontal state
And placing each of the prestressed concrete
A step of connecting the plate of rebar in the internal steel girder, further within said
Between the prestressed concrete slabs
The cleat was pouring, the Presto concrete version of one
And a step of forming physically .

【0017】従って、鋼骨組コンクリート構造物を構成
する側壁のプレストコンクリート版はあらかじめ水平状
態において製作されるために打設高さに制限されること
がなくなり、コンクリート養生期間を短縮できると共
に、このプレストコンクリート版と支持部材を構成する
内部鋼桁等の製作を同時にできるために大幅な工期の短
縮ができる。
Therefore, the prestressed concrete slab of the side wall constituting the steel frame concrete structure is manufactured in advance in a horizontal state, so that the height of the prestressed concrete slab is not limited, and the concrete curing period can be shortened. Since the concrete plate and the internal steel girder constituting the support member can be manufactured at the same time, the construction period can be significantly reduced.

【0018】そしてこのプレストコンクリート版は水平
状態において製作されるためにかなり長尺物を製作する
ことが可能である上に寸法精度が良い上に強度的にも優
れたプレストコンクリート版を製作することが可能であ
り、これを使用した鋼骨組コンクリート構造物は耐久性
に優れたものとすることができる。
Since the prestressed concrete slab is manufactured in a horizontal state, it is possible to manufacture a considerably long object, and to manufacture a prestressed concrete slab having excellent dimensional accuracy and excellent strength. And a steel-framed concrete structure using the same can have excellent durability.

【図面の簡単な説明】[Brief description of the drawings]

【図1】本発明の実施例にかかるコンクリート構造物の
一部破断斜視図である。
FIG. 1 is a partially broken perspective view of a concrete structure according to an embodiment of the present invention.

【図2】底版配筋の工程を示す斜視図である。FIG. 2 is a perspective view showing a step of reinforcing bar arrangement.

【図3】内部鋼桁を中心としてこれに取付けられるコン
クリート版あるいはコンクリートブロックを示す斜視図
である。
FIG. 3 is a perspective view showing a concrete slab or a concrete block attached to an inner steel girder centered thereon.

【図4】内部鋼桁の一部を拡大して示す斜視図である。FIG. 4 is an enlarged perspective view showing a part of an internal steel girder.

【図5】コンクリート版の縁部を構造を拡大して示す斜
視図である。
FIG. 5 is a perspective view showing an enlarged structure of an edge portion of the concrete slab.

【図6】コンクリート構造物を組立工程の説明図であ
る。
FIG. 6 is an explanatory view of a process of assembling a concrete structure.

【図7】完成したコンクリート構造物を示す斜視図であ
る。
FIG. 7 is a perspective view showing a completed concrete structure.

【図8】図7のA部を示す図である。FIG. 8 is a diagram showing a part A of FIG. 7;

【図9】図7のB部を示す図である。FIG. 9 is a diagram showing a portion B in FIG. 7;

【図10】図7のC部を示す図である。FIG. 10 is a diagram showing a part C in FIG. 7;

【符号の説明】[Explanation of symbols]

1 埋立地 2 鋼骨組コンクリート構造物 4
捨石 5 内部鋼桁 5a フランジ部 6 コンクリート側壁 6a 側壁コンクリート版(プレストコンクリート版) 6b 端壁コンクリート版(プレストコンクリート版) 7 上部工 8 隔壁 9 架台 10 底版配
筋 11 底版コンクリート 13 地盤 14 スタ
ッド 15 鉄筋 16 シース 17 PC鋼線 18 打継ぎのコンクリート
1 landfill 2 steel frame concrete structure 4
Ripped stone 5 Internal steel girder 5a Flange part 6 Concrete side wall 6a Side wall concrete plate (pressed concrete plate) 6b End wall concrete plate (pressed concrete plate) 7 Superstructure 8 Partition wall 9 Stand 10 Bottom plate reinforcement 11 Bottom concrete 13 Ground 14 Stud 15 Reinforcing bar 16 Sheath 17 PC steel wire 18 Concrete joint

フロントページの続き (56)参考文献 特開 昭59−41515(JP,A) 実開 昭50−59812(JP,U) 実公 平5−29237(JP,Y2) (58)調査した分野(Int.Cl.6,DB名) E02D 5/30 E02B 3/06 301 E02D 5/10 Continuation of the front page (56) References JP-A-59-41515 (JP, A) JP-A-50-59812 (JP, U) JP 5-29237 (JP, Y2) (58) Fields investigated (Int) .Cl. 6 , DB name) E02D 5/30 E02B 3/06 301 E02D 5/10

Claims (1)

(57)【特許請求の範囲】(57) [Claims] 【請求項1】 内部鋼桁の表面に、縦方向に1回でコン
クリートを打設で きる高さよりも長いコンクリート壁を
有するコンクリート構造物の建設方法で あって、複数の
内部鋼桁を製作すると共に、前記コンクリート構造物の
高さに 相当する長さを有する複数枚の長いプレストコン
クリート版を、水平状態で製 作する工程と、架台上に底
版配筋を敷設し、底版コンクリートを打設する工程 と、
前記底版配筋上に前記内部鋼桁を所定の間隔をおいて植
立する工程と、前 記内部鋼桁を支持部材としてその表面
に、前記水平状態で製作されたプレスト コンクリート版
を立てて配置する工程と、前記各プレストコンクリート
版の鉄 筋を前記内部鋼桁に連結する工程と、更に前記内
部鋼桁に固定されたプレスト コンクリート版の間にコン
クリートを打設して、このプレストコンクリート版 を一
体的に形成する工程とからなる鋼骨組コンクリート構造
物の建設方法。
(1) A single vertical contact with the surface of an internal steel girder.
The long concrete wall than the height to cut the cleats in the pouring
A construction method of the concrete structure having a plurality of
While manufacturing the internal steel girder,
Several long prestocons with a length equivalent to the height
Bottom cleats plate, a step of manufacturing work in a horizontal state, on to the frame
Laying slab arrangements and placing bottom slab concrete ;
The internal steel girders are planted at predetermined intervals on the bottom slab reinforcement.
A step of standing, the surface pre SL internal steel girder as support members
The prestressed concrete plate manufactured in the horizontal state
And placing each of the prestressed concrete
A step of connecting the reinforcing bars of the plate to the inner steel girder, further in the
Between the prestressed concrete slabs
And Da設the cleat, the Presto concrete version of one
A method for constructing a steel-framed concrete structure comprising the steps of physically forming .
JP31864393A 1993-12-17 1993-12-17 Construction method of steel frame concrete structure Expired - Lifetime JP2936130B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP31864393A JP2936130B2 (en) 1993-12-17 1993-12-17 Construction method of steel frame concrete structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP31864393A JP2936130B2 (en) 1993-12-17 1993-12-17 Construction method of steel frame concrete structure

Publications (2)

Publication Number Publication Date
JPH07173831A JPH07173831A (en) 1995-07-11
JP2936130B2 true JP2936130B2 (en) 1999-08-23

Family

ID=18101431

Family Applications (1)

Application Number Title Priority Date Filing Date
JP31864393A Expired - Lifetime JP2936130B2 (en) 1993-12-17 1993-12-17 Construction method of steel frame concrete structure

Country Status (1)

Country Link
JP (1) JP2936130B2 (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105926532A (en) * 2016-05-25 2016-09-07 中交第航务工程局有限公司 Technology for constructing shoulder pole beam reversely-suspended bottom on abutment

Also Published As

Publication number Publication date
JPH07173831A (en) 1995-07-11

Similar Documents

Publication Publication Date Title
US20160362867A1 (en) Modular construction mold apparatus and method for constructing concrete buildings and structures
US4953280A (en) Method of manufacturing prestressed concrete culverts
US4701075A (en) Reinforced concrete offshore platform
CN110747805B (en) Prefabricated high-pile wharf node structure and construction method
JP2000008329A (en) Construction method of bridge
JP2001348815A (en) Cantilever type installing construction method of bridge
JP2936130B2 (en) Construction method of steel frame concrete structure
JP2005264514A (en) Foundation slab structure of sea berth structure, and its construction method
JPH11241311A (en) Construction method of concrete bridge pier
JP2001207410A (en) Pier structure and its constructing method
JP5356085B2 (en) Temporary strut foundation structure and construction method
JPH09268520A (en) Precast panel for buried frame and construction method of concrete structure using panel
JPH08209653A (en) Form block for civil engineering and construction building, building structure using it, and construction thereof
JPS59150810A (en) Coastal structure with caisson and its construction
JP2755888B2 (en) Abutment
JP2000160530A (en) Prefabricated bank body
JPH0835210A (en) Tower-like structure and construction method thereof
JP2562399B2 (en) breakwater
JP2615344B2 (en) Foundation using expanded polystyrene and its construction method
JPH056602B2 (en)
SU1135852A1 (en) Prefabricated block of ferroconcrete mat of pile foundation and method of constructing pile foundation with ferroconcrete mat of prefabricated blocks
JPH01111923A (en) Construction of concrete foundation
JPH0711620A (en) Construction method of artificial ground
JPS61102911A (en) Steel cell
JP3240373B2 (en) Formwork member and method of constructing concrete structure using the same

Legal Events

Date Code Title Description
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 19990406

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20090611

Year of fee payment: 10

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20090611

Year of fee payment: 10

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20100611

Year of fee payment: 11

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20110611

Year of fee payment: 12

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20130611

Year of fee payment: 14

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20130611

Year of fee payment: 14

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20140611

Year of fee payment: 15

EXPY Cancellation because of completion of term