JPS62292B2 - - Google Patents

Info

Publication number
JPS62292B2
JPS62292B2 JP57018910A JP1891082A JPS62292B2 JP S62292 B2 JPS62292 B2 JP S62292B2 JP 57018910 A JP57018910 A JP 57018910A JP 1891082 A JP1891082 A JP 1891082A JP S62292 B2 JPS62292 B2 JP S62292B2
Authority
JP
Japan
Prior art keywords
wall
concrete
formwork
underwater
steel
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired
Application number
JP57018910A
Other languages
Japanese (ja)
Other versions
JPS58138814A (en
Inventor
Chikao Kato
Tametoshi Ueda
Shinsuke Sakai
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
JFE Steel Corp
Original Assignee
Kawasaki Steel Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Kawasaki Steel Corp filed Critical Kawasaki Steel Corp
Priority to JP57018910A priority Critical patent/JPS58138814A/en
Publication of JPS58138814A publication Critical patent/JPS58138814A/en
Publication of JPS62292B2 publication Critical patent/JPS62292B2/ja
Granted legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B17/00Artificial islands mounted on piles or like supports, e.g. platforms on raisable legs or offshore constructions; Construction methods therefor

Landscapes

  • Engineering & Computer Science (AREA)
  • General Engineering & Computer Science (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Revetment (AREA)

Description

【発明の詳細な説明】 この発明は水中構造物の施工方法に関するもの
で、とくに予め陸上施工した構造物の一部を型枠
代りに使い水中打設コンクリートと一体化させる
ことにより水中構造物を構築する方法について提
案する。
[Detailed Description of the Invention] This invention relates to a method for constructing an underwater structure, and in particular, the underwater structure is constructed by using a part of the structure previously constructed on land as a formwork and integrating it with concrete poured underwater. Suggestions on how to build.

従来、水中コンクリート構造物の施工方法には
位置決めの鋼管杭にブラケツトを介して一対の鋼
製型枠を取付け、その型枠間に中詰コンクリート
を打設し、その後該型枠を埋め殺しにするか徹去
して水中構造物を構築していた。しかしながら、
上記従来施工方法の場合、主としてパネル状の
鋼製型枠を列設する方法であるため、型枠の支
持・補強が難しく作業時間がかかる。とりわけ構
造物の外側型枠については、美観上の問題から据
付精度が要求され作業時間は短縮できない。さら
にこの構造物が浮遊物等の衝突から鋼管杭を保護
することを主目的にするものであるため、前記型
枠も水面近傍に列設する作業が含まれることから
やはり浮遊物に対する考慮が必要となり、風や波
浪に対して弱く不安定である。中詰コンクリー
トの打設後、型枠の徹去回収が困難であり、未回
収の場合環境上好ましくない等の欠点があつた。
Conventionally, the construction method for underwater concrete structures involves attaching a pair of steel formwork to the positioning steel pipe piles via brackets, pouring filling concrete between the formworks, and then filling the formworks in place. Instead, they removed it completely and built an underwater structure. however,
In the case of the conventional construction method described above, since panel-shaped steel formwork is mainly installed in rows, supporting and reinforcing the formwork is difficult and takes time. In particular, for the external formwork of structures, installation accuracy is required due to aesthetic issues, and the work time cannot be shortened. Furthermore, since the main purpose of this structure is to protect the steel pipe piles from collisions with floating objects, consideration must be given to floating objects as the formwork also involves arranging them in rows near the water surface. Therefore, it is weak and unstable against wind and waves. After pouring the filling concrete, it is difficult to remove and recover the formwork, and if it is not recovered, it is environmentally unfavorable.

この発明は上述した従来施工方法のもつ欠点を
克服することを目的とするものであつて、水中で
のコンクリート構造物施工に際し、予め構造物壁
体の一部を構成する筒殻状コンクリート外壁をそ
の内面側に鉄筋を配設した状態に打設成形し、こ
のコンクリート外壁を、仮設用ブラケツトをダミ
ーバーを介して水面上で固定した鋼管杭に沿つて
所定の位置に据付け、その後上記コンクリート外
壁と相対する構造物壁体内面側の型枠を設置した
後その型枠との間に中詰コンクリートを打設し
て、上記筒殻状コンクリート外壁をその一部に含
む一体構造物にすることを特徴とする。以下にそ
の構成の詳細を説明する。
The purpose of this invention is to overcome the drawbacks of the conventional construction methods described above, and when constructing a concrete structure underwater, it is necessary to prepare a cylindrical concrete outer wall that forms part of the structure wall in advance. The concrete outer wall is cast and formed with reinforcing bars arranged on its inner surface, and this concrete outer wall is installed at a predetermined position along the steel pipe piles fixed above the water surface via a dummy bar, and then the concrete outer wall and the concrete outer wall are installed. After installing the formwork on the inner side of the opposing structure wall, filling concrete is poured between the formwork and forming an integral structure including the cylindrical concrete outer wall as a part thereof. Features. The details of the configuration will be explained below.

図面の第1図は本発明にかかる水中構造物を必
要とする配管橋、道路橋の一般図であり、第2
図、第3図はその水中基礎部分の詳細を示す。図
示例の水中構造物は、柱脚基礎の例で、長市筒形
の構造物壁体1を、土質中に打込んだ複数本の鋼
管杭2で所定の位置に支持した構成である。本発
明の施工にかかる水中構造物は、施工段階の順で
説明すると、予め外周壁をなす筒殻状コンクリー
ト外壁3と内周壁を構成する型枠4とを用意し、
その後中詰コンクリート5を打設する工程によつ
て構築される。
Figure 1 of the drawings is a general diagram of a pipe bridge and road bridge that require underwater structures according to the present invention, and Figure 2 is a general diagram of a pipe bridge and a road bridge that require underwater structures according to the present invention.
Figures 3 and 3 show details of the underwater foundation. The illustrated underwater structure is an example of a pillar base, and has a structure in which a cylindrical structure wall 1 is supported at a predetermined position by a plurality of steel pipe piles 2 driven into the soil. To explain the underwater structure according to the construction of the present invention in the order of construction steps, a cylindrical concrete outer wall 3 forming an outer peripheral wall and a formwork 4 forming an inner peripheral wall are prepared in advance,
After that, it is constructed by a process of pouring filling concrete 5.

前記型枠としては、筒殻状コンクリート内壁、
筒殻状鋼製内壁、あるいはパネル状鋼製型枠が使
用される。なお図示したのは筒殻状のコンクリー
ト内、外壁を使用した例で6,6′はいずれも埋
設する鉄筋である。7は鋼管杭から突設した補強
用鉄筋で予め鋼管杭に溶接しておいてもよく、ま
たコンクリート外壁3の据付後溶接してもよい。
その配筋である。その配筋の詳細を第4図に示
す。第4図に示す8は内・外壁3,4と中詰コン
クリート5の一体結合を強化する強化鉄筋で、そ
れぞれの壁体中に埋設した支持板9から中詰コン
クリート打設空間に向けて突設した形に固定して
ある。型枠として筒殻状鋼製内壁を使用する場合
の配筋は特に図示しないが、コンクリート内壁と
同様に配筋するが、この場合は型枠4に溶接して
取り付ける。
The formwork includes a cylindrical concrete inner wall,
A cylindrical steel inner wall or a panel steel formwork is used. The illustrated example uses a cylindrical shell-shaped concrete interior and an exterior wall, and 6 and 6' are reinforcing bars to be buried. Reference numeral 7 is a reinforcing reinforcing bar protruding from the steel pipe pile, and may be welded to the steel pipe pile in advance, or may be welded after the concrete outer wall 3 is installed.
This is the reinforcement arrangement. The details of the reinforcement arrangement are shown in Fig. 4. Reference numeral 8 shown in Fig. 4 is a reinforcing reinforcing bar that strengthens the integral connection between the inner and outer walls 3, 4 and the filling concrete 5, and extends from the support plate 9 buried in each wall toward the filling concrete placement space. It is fixed in the set shape. Although reinforcement is not particularly shown in the case where a cylindrical steel inner wall is used as a formwork, reinforcement is arranged in the same way as for a concrete inner wall, but in this case, it is attached to the formwork 4 by welding.

なお鋼製内が使用できる理由は、構造物内面で
は鋼材の腐食に対する外観上の考慮が不要である
こと、およびコンクリート外壁3に守られている
から浮遊物等の衝突による破損、変形を考慮する
必要がなく、従つて軽量化が図れることから使い
捨てが可能になるためである。
The reason why a steel interior can be used is that there is no need to consider the appearance of steel corrosion on the inside of the structure, and since it is protected by the concrete exterior wall 3, consideration should be given to damage and deformation caused by collisions with floating objects, etc. This is because there is no need for it, and the weight can be reduced, making it disposable.

さらに内面に予め陸上で一体的に組立てたパネ
ル状鋼製型枠を用いる場合は、コンクリート外壁
3に突設した鉄筋8をこの型枠の近くまで伸ばし
ておけば若干の現場配筋で済み大した作業の阻害
要因とはならない。この型枠の利点は、後述する
ように、幾つかのブロツクに分けて構造物に必要
な高さを確保する際や同一形状の構造物を構築す
る場合に、順次取外して再利用できるので経済的
である。
Furthermore, if a panel-shaped steel formwork that has been pre-assembled on land is used for the inner surface, the reinforcing bars 8 protruding from the concrete outer wall 3 can be extended close to this formwork, and only a few on-site reinforcements are required. It will not be an impediment to the work done. The advantage of this formwork, as will be explained later, is that it is economical because it can be removed one by one and reused when dividing it into several blocks to ensure the required height for the structure or when constructing structures of the same shape. It is true.

要するに本発明工法の特徴の一つは、構造物の
内、外壁を構成する部分を予め陸上で作成してお
き、これを従来の型枠の代りに使いながら同時に
構造物の一部として中詰コンクリート5と共に一
体化させる点と、予め陸上で作成したコンクリー
ト外壁を利用して同様に陸上で一体的に組立てた
パネル状鋼製型枠等を内側枠に用いることにより
構造物の内外型枠の現場組立作業を省略するとと
もに極力配筋のための作業をも少くした点にあ
る。
In short, one of the features of the construction method of the present invention is that the parts that make up the inner and outer walls of the structure are prepared on land in advance, and while this can be used in place of conventional formwork, it can also be used as part of the structure. By integrating it with concrete 5, and by using a panel-shaped steel formwork, etc., which was also assembled integrally on land using the concrete outer wall previously created on land, for the inner frame, the inner and outer formwork of the structure can be In addition to omitting on-site assembly work, the work for reinforcing reinforcement is also minimized.

第5図は本発明施工方法の各段階を示すもの
で、まず予め陸上にて構造物の外壁を構成するコ
ンクリート外壁3を製作する。同時に水中の据付
け位置には、鋼管杭2を打込み、その鋼管杭2に
は上記コンクリート外壁3を水中の所定の位置に
支持するためのブラケツト12,12′を固定し
ておく。ブラケツト12,12′の固定位置は水
中になるので、作業の便を考えて該ブラケツトか
らダミーバー12a,12′aを突設してこれを
杭に沿つて水面上に持ち来し、その水面上に位置
する上部を溶接固定してブラケツト位置を決め
る。こうして用意された鋼管杭2に、クレーン船
10および台船11により前記コンクリート外壁
3をブラケツト12,12′を介して水中に支持
する。その後、内壁を構成するためのコンクリー
ト製または鋼製の内型枠4を外壁3と同心に設置
する。コンクリート外壁3ならびに型枠4支持の
模様については、その詳細を第6図,第7図に示
す。
FIG. 5 shows each stage of the construction method of the present invention. First, the concrete outer wall 3 constituting the outer wall of the structure is manufactured on land in advance. At the same time, a steel pipe pile 2 is driven into the underwater installation position, and brackets 12, 12' for supporting the concrete outer wall 3 at a predetermined position underwater are fixed to the steel pipe pile 2. Since the fixed positions of the brackets 12, 12' are underwater, for convenience of work, dummy bars 12a, 12'a are provided protruding from the brackets and brought above the water surface along the stakes. Weld and fix the upper part located at , and determine the bracket position. The concrete outer wall 3 is supported underwater on the thus prepared steel pipe pile 2 by means of a crane ship 10 and a barge 11 via brackets 12 and 12'. Thereafter, an inner formwork 4 made of concrete or steel for forming the inner wall is installed concentrically with the outer wall 3. The details of the concrete outer wall 3 and the support pattern of the formwork 4 are shown in FIGS. 6 and 7.

上記の段階を終えると、コンクリート外壁3と
内型枠4との間にトレミー管14を使つて中詰コ
ンクリート5を打設する。この打設に際しては、
中詰コンクリートが流出しないように、第8図,
第9図に示すような盛土13を施工しておく。
After completing the above steps, filling concrete 5 is placed between the concrete outer wall 3 and the inner formwork 4 using the tremie pipe 14. During this pouring,
To prevent the filling concrete from flowing out,
An embankment 13 as shown in FIG. 9 is constructed in advance.

その後、水中基礎としての必要な高さを得るた
め、幾つかのブロツクに分けて施工する必要があ
るときには、第5図のニ,ホで示すように前述し
た同様な工程の繰返しによつて前記コンクリート
外壁3と内型枠4との間に中詰コンクリート5を
打設し、両接合部にモルタル注入によつて目地処
理し、必要な高さのものに重ね合せて完成させ
る。
After that, if it is necessary to construct the foundation in several blocks in order to obtain the required height for the underwater foundation, repeat the above-mentioned steps as shown in Fig. 5 (d) and (e). Filling concrete 5 is placed between the concrete outer wall 3 and the inner formwork 4, joint treatment is performed by pouring mortar into both joints, and the concrete is overlaid to the required height to complete the work.

実施例 水島製鉄所で発生するCガス,Nガスを高梁川
を挾む対岸の工場に送給する高梁川横断パイプラ
イン敷設工事における配管橋柱脚基礎の施工に当
り本発明の効果を確認するために試験的に本発明
法を適用した例を説明する。第10図のイ,ロは
該基礎の詳細図であり、長さ7.8m×巾4.3m×高
さ9.4mの長円形柱脚である。柱脚壁の厚さ80cm
の内、15cmのコンクリート外壁を高さ4.5mの2
ブロツクに分けて事前に陸上製作したものを使つ
た。さらに構造物の内側型枠として、4ブロツク
に分割作成したパネル状鋼製型枠を陸上でボルト
により1体的に組立てたものを使用した。この実
施例の結果、工事期間が従来のものに比べると約
10日短縮でき、その作業も頗る順調であつた。
Example: The effect of the present invention was confirmed in the construction of a piping bridge column pedestal foundation in the construction of a pipeline across the Takahashi River, which will transport C gas and N gas generated at the Mizushima Steel Works to a factory on the opposite bank of the Takahashi River. An example in which the method of the present invention was applied on a trial basis will be explained below. Figures 10A and 10B are detailed views of the foundation, which has an oval column base of 7.8m in length, 4.3m in width, and 9.4m in height. Pillar base wall thickness 80cm
Of these, the 15cm concrete outer wall is 4.5m high.
I used blocks that had been made in advance on land. Furthermore, as the inner formwork for the structure, we used a panel-shaped steel formwork that was divided into four blocks and assembled into one piece on land using bolts. As a result of this example, the construction period is approximately
The time was saved by 10 days, and the work went very smoothly.

以上説明したように本発明によれば、コンクリ
ート外壁及びコンクリート内壁又は、鋼製内壁が
型枠を兼用するから、水中または水上で型枠を組
立てたり徹去したりする必要がなく、例え内側に
鋼製型枠を使用したとしても現場での組立作業は
必要なく、徹去のみの作業となる。いずれにして
も配筋等の現場作業並びに水中作業を殆んど必要
としないため、施工工事が簡単で工事を短縮する
ことができ、美観の点でも従来に優れる。
As explained above, according to the present invention, since the concrete outer wall and the concrete inner wall or the steel inner wall also serve as formwork, there is no need to assemble or remove the formwork underwater or on the water. Even if steel formwork is used, there is no need for on-site assembly, and only clearing is required. In any case, since there is almost no need for on-site work such as bar arrangement or underwater work, the construction work is simple and can be shortened, and it is superior to conventional methods in terms of aesthetics.

【図面の簡単な説明】[Brief explanation of the drawing]

第1図は柱脚基礎の一般的な例を示す正面図、
第2図のイ,ロおよび第3図のイ,ロは、いずれ
も本発明施工例で採用する水中構造物の切欠き平
面図と切欠き正面図、第4図のイ,ロは、構造物
壁体の部分断面図、第5図は本発明施工方法の各
段階を示す工程図、第6図のイ,ロはブラケツト
によるコンクリート外壁、型枠支持の模様を示す
断面図、第7図はブラケツトの詳細を示す正面
図、第8図および第9図は構造物下に盛土施工し
した状態の断面図、第10図のイ,ロはいずれも
実施例の柱脚の切欠き断面図である。 1……水中構造物壁体、2……鋼管杭、3……
コンクリート外壁、4……型枠(内側壁用)、5
……中詰コンクリート、6,6′,7,8……鉄
筋、9……支持板、10……クレーン船、11…
…台船、12,12′……ブラケツト、12a,
12′a……ブラケツトのダミーバー、13……
盛士、14……トレミー管。
Figure 1 is a front view showing a general example of a column base foundation;
A and B in Fig. 2 and A and B in Fig. 3 are a cutout plan view and a cutout front view of an underwater structure adopted in the construction example of the present invention, and A and B in Fig. 4 are the structure. A partial cross-sectional view of the object wall, Figure 5 is a process diagram showing each step of the construction method of the present invention, Figure 6 A and B are cross-sectional views showing the pattern of concrete outer wall and formwork support by brackets, Figure 7 is a front view showing details of the bracket, Figures 8 and 9 are sectional views of the embankment constructed under the structure, and Figure 10 A and B are cutaway sectional views of the column base of the example. It is. 1... Underwater structure wall, 2... Steel pipe pile, 3...
Concrete external wall, 4...Formwork (for internal wall), 5
...Filled concrete, 6,6',7,8...Reinforcement bar, 9...Support plate, 10...Crane ship, 11...
...Barge, 12, 12'...Bracket, 12a,
12'a... Bracket dummy bar, 13...
Seishi, 14...Tolemy tube.

Claims (1)

【特許請求の範囲】 1 水中でのコンクリート構造物施工に際し、予
め構造物壁体の一部を構成する筒殻状コンクリー
ト外壁をその内面側に鉄筋を配設した状態に打設
成形し、このコンクリート外壁を、仮設用ブラケ
ツトをダミーバーを介して水面上で固定した鋼管
杭に沿つて所定の位置に据付け、その後上記コン
クリート外壁と相対する構造物壁体内面側の型枠
を設置した後その型枠との間に中詰コンクリート
を打設して、上記筒殻状コンクリート外壁をその
一部に含む一体構造物にすることを特徴とする水
中構造物の施工方法。 2 上記型枠が、筒殻状のコンクリート壁である
特許請求の範囲1に記載の施工方法。 3 上記型枠が、鋼製枠である特許請求の範囲1
に記載の施工方法。
[Claims] 1. When constructing a concrete structure underwater, a cylindrical concrete outer wall constituting a part of the structure wall is cast in advance with reinforcing bars arranged on its inner surface, and The concrete exterior wall is installed in a predetermined position along the steel pipe pile fixed above the water surface using a temporary bracket via a dummy bar, and then the formwork for the inner surface of the structure wall facing the concrete exterior wall is installed, and then the form is removed. A method for constructing an underwater structure, which comprises placing filling concrete between the structure and the frame to form an integral structure including the cylindrical concrete outer wall as a part thereof. 2. The construction method according to claim 1, wherein the formwork is a cylindrical shell-shaped concrete wall. 3 Claim 1, wherein the formwork is a steel frame
Construction method described in.
JP57018910A 1982-02-10 1982-02-10 Construction of underwater structure Granted JPS58138814A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP57018910A JPS58138814A (en) 1982-02-10 1982-02-10 Construction of underwater structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP57018910A JPS58138814A (en) 1982-02-10 1982-02-10 Construction of underwater structure

Publications (2)

Publication Number Publication Date
JPS58138814A JPS58138814A (en) 1983-08-17
JPS62292B2 true JPS62292B2 (en) 1987-01-07

Family

ID=11984754

Family Applications (1)

Application Number Title Priority Date Filing Date
JP57018910A Granted JPS58138814A (en) 1982-02-10 1982-02-10 Construction of underwater structure

Country Status (1)

Country Link
JP (1) JPS58138814A (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS60203721A (en) * 1984-03-27 1985-10-15 Takenaka Komuten Co Ltd Marine concrete structure

Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS5425727A (en) * 1977-07-28 1979-02-26 Ricoh Co Ltd Image projection method for copying lens

Patent Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS5425727A (en) * 1977-07-28 1979-02-26 Ricoh Co Ltd Image projection method for copying lens

Also Published As

Publication number Publication date
JPS58138814A (en) 1983-08-17

Similar Documents

Publication Publication Date Title
KR101600845B1 (en) The horizontal structural frame and the underground construction methods using it
KR100531385B1 (en) Construction method of underground structure that enables continuous retaining wall using steel wale and diaphragm effect of concrete slab
US4015379A (en) In-ground swimming pool and apparatus and method for constructing same
JP3888174B2 (en) Temporary deadline construction method
JPH09268583A (en) Structural steel embedded half precast concrete member and construction method of underground structure using the same member
JPS62292B2 (en)
JPH11172710A (en) Method for constructing underground part of steel encased reinforced concrete building
JPH10121500A (en) Construction method of outer peripheral beam of basement floor
JPH10168915A (en) Method of ground excavation construction in coffering sheet pile
JPS6137692Y2 (en)
JP2979117B2 (en) Building foundation method
JPS5829922A (en) Constructing method for underground outer wall
JP2733722B2 (en) Construction method of deep foundation pile type retaining wall
JP2949341B1 (en) Underwater girder construction method
JPH08100464A (en) Joint structure and work execution method for structure using it
JP3849234B2 (en) Reinforced concrete underground outer wall construction method
JP2802612B2 (en) Underwater formwork method
JPH06330507A (en) Abutment
JPH03275809A (en) Caisson structure
JPH0565717A (en) Prefabrication work of reinforcing bar for foundation
JPH03253612A (en) Construction of earth retaining of underground structure and construction member used for it
JPS5844802B2 (en) Ganpekino hokiyoukohou
JPH081063B2 (en) Underground continuous wall construction method and underground continuous wall construction formwork
JP2004316133A (en) Temporary coffering method
JPH0748848A (en) Construction method for underground skeleton by inverted construction method