JPH11286318A - Work carrying and processing method and its device - Google Patents

Work carrying and processing method and its device

Info

Publication number
JPH11286318A
JPH11286318A JP10105820A JP10582098A JPH11286318A JP H11286318 A JPH11286318 A JP H11286318A JP 10105820 A JP10105820 A JP 10105820A JP 10582098 A JP10582098 A JP 10582098A JP H11286318 A JPH11286318 A JP H11286318A
Authority
JP
Japan
Prior art keywords
work
positioning
processing
transfer
moved
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP10105820A
Other languages
Japanese (ja)
Inventor
Kazutoshi Hattori
和敏 服部
Koji Takahashi
浩二 高橋
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Ibiden Co Ltd
Original Assignee
Ibiden Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Ibiden Co Ltd filed Critical Ibiden Co Ltd
Priority to JP10105820A priority Critical patent/JPH11286318A/en
Publication of JPH11286318A publication Critical patent/JPH11286318A/en
Pending legal-status Critical Current

Links

Landscapes

  • Control Of Conveyors (AREA)
  • Electric Connection Of Electric Components To Printed Circuits (AREA)
  • Supply And Installment Of Electrical Components (AREA)

Abstract

PROBLEM TO BE SOLVED: To perform carrying a work and processing the work in parallel, and thereby shorten time required by these operations. SOLUTION: A positioning step positioning a work 7 over a first table 2 is made in a positioning part. Next, the work 7 is moved while being rested over the first table 2 so as to allow a processing step to be made, at this point, a second table 3 is moved to the aforesaid positioning part so as to allow a positioning step positioning the work 7 over the second table 3 to be made. Next, the work 7 having been processed, is moved while being left over the first table 2 so as to allow a discharging step to be made at a discharge part, and at this point, the work 7 having been positioned is moved while being left over the second table 3 so as to allow the processing step to be made. From now on, the respective steps for positioning, processing and discharging shall be performed in parallel.

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【技術分野】本発明は,例えばプリント基板等のワーク
に対して検査等の処理を行う場合に,処理部へのワーク
の搬入,ワークへの処理,及び処理後のワークの搬出を
併行して行う,ワーク搬送処理方法及びそれに用いる処
理装置に関する。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to, for example, carrying out a work to a processing unit, a work to a work, and a work after processing, when performing a processing such as an inspection on a work such as a printed circuit board. The present invention relates to a work transfer processing method and a processing apparatus used for the method.

【0002】[0002]

【従来技術】従来,被処理物であるワーク,例えばプリ
ント基板に対して検査を行う場合には,次のような方法
でプリント基板の検査を行っている。前工程を終えたプ
リント基板を,検査を行う処理部までコンベアによって
移動する。次いで,該処理部において,検査装置に対す
る向き,角度,位置のズレをなくすために,プリント基
板を保持する等の方法で位置決めを行う。そして,上記
プリント基板に対して処理工程としての検査を行う。検
査後においては,上記保持状態にあるプリント基板の位
置決めを解除する。次いで,検査を終えたプリント基板
を上記処理部から後工程へコンベアによって移動する。
2. Description of the Related Art Conventionally, when inspecting a work to be processed, for example, a printed board, the printed board is inspected by the following method. The printed circuit board that has completed the previous process is moved by a conveyor to a processing unit for inspection. Next, in the processing section, positioning is performed by a method such as holding a printed circuit board in order to eliminate deviations in the direction, angle, and position with respect to the inspection device. Then, the printed board is inspected as a processing step. After the inspection, the positioning of the printed circuit board in the holding state is released. Next, the printed circuit board having undergone the inspection is moved from the processing section to a post-process by a conveyor.

【0003】[0003]

【解決しようとする課題】しかしながら,上記従来のワ
ーク搬送処理方法においては,次の問題がある。即ち,
プリント基板の位置決め,解除が,処理部において行わ
れているので,処理部においてプリント基板の検査だけ
を行うことができない。そのため,処理部において位置
決め,解除を待つことになる。また,これに伴ってコン
ベヤの搬送速度が規制されてしまう。それ故,この一連
のプリント基板の搬送,及び検査に要する時間を短縮す
ることは,非常に困難である。
However, the conventional work transfer processing method has the following problems. That is,
Since the positioning and release of the printed circuit board are performed in the processing section, it is not possible to perform only the inspection of the printed circuit board in the processing section. Therefore, the processing unit waits for positioning and release. In addition, the conveying speed of the conveyor is restricted accordingly. Therefore, it is very difficult to shorten the time required for transporting and inspecting a series of printed circuit boards.

【0004】本発明は,かかる従来の問題点に鑑みてな
されたもので,ワークの搬送とワークへの処理とを併行
して行い,ワークの搬送,及び処理に要する時間を短縮
することができる,ワーク搬送処理方法,及び装置を提
供しようとするものである。
The present invention has been made in view of such a conventional problem, and conveys a workpiece and processes the workpiece in parallel, thereby shortening the time required for transporting and processing the workpiece. , A work transfer processing method, and an apparatus.

【0005】[0005]

【課題の解決手段】請求項1の発明は,位置決め部にお
いて第1テーブル上にワークを載置すると共に位置決め
する位置決めステップを行い,次いで,上記ワークを上
記第1テーブル上に載せたまま移動させ,処理部に停止
させて処理ステップを行い,この処理ステップを行って
いる間に第2テーブルを上記位置決め部へ移動させると
共に,該第2テーブル上にワークを載置,位置決めする
位置決めステップを行い,上記第1テーブル上のワーク
に処理ステップを行った後に該ワークを上記第1テーブ
ル上に載せたまま移動させ,排出部において上記ワーク
の位置決めを解除すると共に,上記ワークを排出する排
出ステップを行い,この間に上記第2テーブル上の位置
決め済みのワークを上記第2テーブル上に載せたまま移
動させ,上記処理部において上記処理ステップを行い,
以下,順次,上記位置決めステップ,処理ステップ,及
び排出ステップを併行して行うことを特徴とするワーク
搬送処理方法にある。
According to a first aspect of the present invention, a positioning section performs a positioning step of placing and positioning a work on a first table in a positioning section, and then moving the work while placing the work on the first table. , Causing the processing unit to stop and perform a processing step. While performing the processing step, move the second table to the positioning unit and perform a positioning step of mounting and positioning a work on the second table. After performing the processing step on the work on the first table, the work is moved while being placed on the first table, and the discharging section releases the positioning of the work and discharges the work. In the meantime, the positioned work on the second table is moved while being placed on the second table, Perform the above processing steps in,
Hereinafter, there is provided a workpiece transfer processing method characterized by sequentially performing the positioning step, the processing step, and the discharging step in parallel.

【0006】本発明において最も注目すべきことは,複
数のテーブルが,位置決め,処理,排出という一連のス
テップを行うと共に,一方のテーブルが処理ステップを
行う間,他方のテーブルは位置決めステップ,又は排出
ステップを行うことである。
It is most remarkable in the present invention that a plurality of tables perform a series of steps of positioning, processing and discharging, and one table performs a processing step while the other table performs a positioning step or discharging. Is to do the steps.

【0007】上記ワークとしては,例えば,プリント基
板,リードフレーム等がある。また,上記処理ステップ
において上記ワークに対して行う処理としては,例え
ば,ワークの検査,ワークへの部品の実装,ワークへの
マーキング等がある。
[0007] Examples of the work include a printed circuit board and a lead frame. Examples of the processing performed on the work in the processing step include inspection of the work, mounting of components on the work, and marking on the work.

【0008】次に,本発明の作用効果につき説明する。
本発明のワーク搬送処理装置においては,上記ワークに
対して行う処理は上記処理部において行う。一方,上記
第1,第2テーブル上へのワークの位置決めは上記位置
決め部において行い,上記ワークの位置決めの解除は上
記排出部において行う。即ち,上記処理部においては上
記処理ステップのみを行うことができる。
Next, the function and effect of the present invention will be described.
In the work transfer processing apparatus of the present invention, the processing performed on the work is performed in the processing unit. On the other hand, the positioning of the work on the first and second tables is performed in the positioning section, and the release of the positioning of the work is performed in the discharge section. That is, the processing section can perform only the processing steps.

【0009】そのため,上記処理ステップを行う間に,
上記位置決めステップ又は排出ステップを併行して行う
ことができ,上記位置決めステップから排出ステップま
での間に要する時間を短縮することができる。また,こ
れに伴って上記位置決め部までのワークの搬入速度,及
び上記排出部からのワークの搬出速度を上げることがで
きる。それ故,上記ワークの搬送,及び処理に要する時
間を短縮することができる。
Therefore, while performing the above processing steps,
The positioning step or the discharging step can be performed simultaneously, and the time required from the positioning step to the discharging step can be reduced. Accordingly, the speed at which the work is carried into the positioning section and the speed at which the work is carried out from the discharge section can be increased. Therefore, the time required for transporting and processing the work can be reduced.

【0010】次に,請求項2の発明のように,上記処理
ステップは,複数種類行うことが好ましい。この場合に
は,例えば上記検査,実装等の複数の処理ステップを連
続して行うことができる。そのため,各処理ステップの
間に,上記排出ステップ,位置決めステップを行う必要
がない。それ故,上記ワークへの処理を迅速に行うこと
ができる。
Next, it is preferable that a plurality of types of the above-mentioned processing steps are performed. In this case, for example, a plurality of processing steps such as the above-described inspection and mounting can be continuously performed. Therefore, there is no need to perform the discharging step and the positioning step between each processing step. Therefore, the processing for the work can be performed quickly.

【0011】次に,請求項3の発明は,複数のワーク搬
送機を設け,該ワーク搬送機によりワークを位置決めス
テップ,処理ステップ,排出ステップにそれぞれ連続し
て搬送し,上記各ステップを行うワーク搬送処理装置で
あって,上記ワーク搬送機は,それぞれワークを載置す
ると共に位置決めするテーブルと,該テーブルを昇降さ
せる昇降機と,上記テーブル及び昇降機を水平方向に移
動させる移動装置と,該移動装置に接続したサーボ機構
とを有することを特徴とするワーク搬送処理装置にあ
る。
Next, a third aspect of the present invention is to provide a plurality of work transporters, and the workpiece transporter successively transports a work to a positioning step, a processing step, and a discharge step, and performs the above steps. A transfer processing device, wherein the work transfer device includes a table on which a work is placed and positioned, a lifting device for moving the table up and down, a moving device for moving the table and the lifting device in a horizontal direction, and the moving device. And a servo mechanism connected to the workpiece transfer processing device.

【0012】本発明において最も注目すべきことは,ワ
ーク搬送機は昇降機と移動装置とを有すると共に,ワー
ク搬送処理装置には上記ワーク搬送機を複数設けること
である。
What is most notable in the present invention is that the work transfer device has an elevator and a moving device, and the work transfer processing device is provided with a plurality of the work transfer devices.

【0013】上記ワーク搬送処理装置は,複数の上記ワ
ーク搬送機に対して,ローダー,処理装置,アンローダ
ーを一組有している。そして,上記位置決め部には位置
決めステップを行う上記ローダーを,上記処理部には処
理ステップを行う上記処理装置を,上記排出部には排出
ステップを行う上記アンローダーを配設してある。
The work transfer processing device has a set of a loader, a processing device, and an unloader for a plurality of the work transfer devices. The positioning section is provided with the loader for performing the positioning step, the processing section is provided with the processing device for performing the processing step, and the discharging section is provided with the unloader for performing the discharging step.

【0014】次に,本発明の作用効果につき説明する。
上記複数のワーク搬送機のうち,1台目のワーク搬送機
の動作について説明する。まず,上記位置決めステップ
において,上記ワーク搬送機の昇降機がテーブルを上昇
させる。そして,該テーブル上に,上記ローダーによっ
てワークを載置,位置決めする。そして,上記ワーク搬
送機の移動装置が,上記テーブルと昇降機とを上記処理
部まで水平移動させる。上記テーブルの停止位置は,上
記サーボ機構によって自動制御される。これは,上記位
置決めステップに限らず,全てのステップにおいて行わ
れる。
Next, the operation and effect of the present invention will be described.
The operation of the first work transfer device of the plurality of work transfer devices will be described. First, in the positioning step, the elevator of the work transfer machine raises the table. Then, the work is placed and positioned on the table by the loader. Then, the moving device of the work transfer device horizontally moves the table and the elevator to the processing section. The stop position of the table is automatically controlled by the servo mechanism. This is performed not only in the positioning step but also in all steps.

【0015】次いで,上記処理ステップにおいて,上記
テーブル上に位置決めされたワークに対して,上記処理
装置によって処理が行われる。そして,上記ワーク搬送
機の移動装置が,上記テーブルを上記排出部まで水平移
動させる。
Next, in the processing step, the work positioned on the table is processed by the processing device. Then, the moving device of the work carrier horizontally moves the table to the discharge section.

【0016】次いで,上記排出ステップにおいて,上記
処理後のワークは,位置決めが解除されて,上記アンロ
ーダーによって排出される。そして,上記ワーク搬送機
の移動装置が,上記ワークを排出されたテーブルを上記
ローダーまで水平移動させる。
Next, in the discharging step, the workpiece after the processing is released from the positioning and discharged by the unloader. Then, the moving device of the work transporter horizontally moves the table from which the work has been discharged to the loader.

【0017】そして,上記ワーク搬送機は,上記位置決
めステップから処理ステップへの搬送,処理ステップか
ら排出ステップへの搬送,及び排出ステップから位置決
めステップへの搬送を繰り返し行う。そして,上記ワー
ク搬送機によって搬送されるワークは,上記各ステップ
においてそれぞれの操作を行われる。
Then, the work transfer machine repeatedly performs the transfer from the positioning step to the processing step, the transfer from the processing step to the discharge step, and the transfer from the discharge step to the positioning step. The work carried by the work carrier is subjected to the respective operations in the above steps.

【0018】次に,上記複数のワーク搬送機のうち,他
のワーク搬送機について説明する。他のワーク搬送機に
おける動作も,上記と同様である。しかし,2台目のワ
ーク搬送機は,上記1台目のワーク搬送機にワンステッ
プ遅れて動作を始める。そのため,各ワーク搬送機は互
いに異なるステップを併行して行う。
Next, of the plurality of work transfer machines, another work transfer machine will be described. The operation of the other work transfer devices is the same as described above. However, the second work carrier starts operation one step behind the first work carrier. Therefore, each work transfer machine performs different steps in parallel.

【0019】上記ワーク搬送処理装置によれば,上記の
ごとく,ワークに処理を行うための上記位置決め,処
理,排出の各ステップを併行して行うことができる。そ
のため,タイムロスなく,効率的に上記ワークへ処理を
行うことができる。
According to the work transfer processing apparatus, as described above, the steps of positioning, processing, and discharging for performing processing on a work can be performed in parallel. Therefore, the work can be efficiently processed without any time loss.

【0020】次に,請求項4の発明のように,上記各ワ
ーク搬送機におけるテーブルは,それぞれ位置決め具を
有することが好ましい。この場合には,上記テーブルが
それぞれ位置決め具を有しているため,該テーブルが位
置決め部に搬送された段階で,位置決めを行うことがで
きる。そのため,位置決めステップに要する時間を短縮
し,能率を向上させることができる。
Next, it is preferable that each of the tables in each of the work transfer devices has a positioning tool. In this case, since each of the tables has a positioning tool, positioning can be performed when the table is transported to the positioning unit. Therefore, the time required for the positioning step can be reduced, and the efficiency can be improved.

【0021】次に,請求項5の発明のように,上記各テ
ーブルは,互いに上下方向に位置することができると共
に,独立して水平方向に移動することができ,かつ上記
位置決めステップにおいては基準位置まで上昇可能に設
けてあり,排出ステップにおいては下降可能に設けてあ
ることが好ましい。
Next, as in the fifth aspect of the present invention, each of the tables can be positioned vertically with respect to each other, can be independently moved in the horizontal direction, and can be moved to the reference position in the positioning step. It is preferably provided so as to be able to ascend to the position and to be able to descend in the discharge step.

【0022】この場合には,上記各テーブルは,上記位
置決めステップから処理ステップへの搬送,及び処理ス
テップから排出ステップへの搬送において,順次,各ス
テップへ水平方向に移動する。次いで,排出ステップか
ら位置決めステップへの搬送においては,上記各テーブ
ルは下降した後,上記とは逆方向に水平に移動して,位
置決め部において基準位置まで上昇する。
In this case, the respective tables sequentially move in the horizontal direction to the respective steps in the transfer from the positioning step to the processing step and in the transfer from the processing step to the discharge step. Next, in the transport from the discharge step to the positioning step, the tables are lowered, then horizontally moved in the opposite direction to the above, and are raised to the reference position in the positioning section.

【0023】そのため,上記ワーク搬送機は,上記テー
ブルを循環して搬送することができる。また,そのサイ
クル中に複数の上記テーブルが存在しても,各テーブル
が互いに干渉することなく,スムーズに上記複数のテー
ブルを併行して搬送することができる。
Therefore, the work transfer device can circulate and transfer the table. Further, even if a plurality of the tables exist during the cycle, the tables can be smoothly transferred in parallel without interfering with each other.

【0024】[0024]

【発明の実施の形態】実施形態例 本発明の実施形態例にかかるワーク搬送処理方法,及び
それに用いる装置について,図1〜図8を用いて説明す
る。本例は,被処理物であるワークとしてのプリント基
板に対して,処理ステップにおいてパターン部の欠陥検
査を行った例である。
DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS Embodiments A work transfer processing method according to an embodiment of the present invention and an apparatus used therefor will be described with reference to FIGS. This example is an example in which a pattern portion is inspected for defects in a processing step on a printed circuit board as a work as an object to be processed.

【0025】本例のワーク搬送処理方法について概説す
る。上記ワーク搬送処理方法は,図1,図2に示すごと
く,位置決め部において第1テーブル2上にワーク7を
載置すると共に位置決めする位置決めステップを行う
(第2工程)。次いで,上記ワーク7を上記第1テーブ
ル2上に載せたまま移動させ,処理部に停止させて処理
ステップを行う(第4,第6,第8工程)。該処理ステ
ップは,2種類行う。この処理ステップを行っている間
に,第2テーブル3を上記位置決め部へ移動させると共
に,該第2テーブル3上にワーク7を載置,位置決めす
る位置決めステップを行う(第8工程)。
The work transfer processing method of the present embodiment will be outlined. In the work transfer processing method, as shown in FIGS. 1 and 2, a positioning step is performed in which the work 7 is placed on the first table 2 and positioned in the positioning section (second step). Next, the work 7 is moved while being placed on the first table 2 and stopped by the processing unit to perform processing steps (fourth, sixth, and eighth steps). The processing steps are performed in two types. While performing this processing step, the second table 3 is moved to the positioning section, and a positioning step of mounting and positioning the work 7 on the second table 3 is performed (eighth step).

【0026】次いで,上記第1テーブル2上のワーク7
に処理ステップを行った後に該ワーク7を上記第1テー
ブル2上に載せたまま移動させ,排出部において上記ワ
ーク7の位置決めを解除すると共に,上記ワーク7を排
出する排出ステップを行う(第10工程)。この間に上
記第2テーブル3上の位置決め済みのワーク7を上記第
2テーブル3上に載せたまま移動させ,上記処理部にお
いて上記処理ステップを行う(第10,第12,第14
工程)。以下,順次,上記位置決めステップ,処理ステ
ップ,及び排出ステップを併行して行う。
Next, the work 7 on the first table 2
After the processing step is performed, the work 7 is moved while being placed on the first table 2 to release the positioning of the work 7 in the discharge section, and a discharge step of discharging the work 7 is performed (tenth step). Process). In the meantime, the work 7 positioned on the second table 3 is moved while being placed on the second table 3, and the processing section performs the processing steps (tenth, twelfth, and fourteenth).
Process). Hereinafter, the positioning step, the processing step, and the discharging step are sequentially performed in parallel.

【0027】次に,上記ワーク搬送処理方法に用いる装
置について概説する。ワーク搬送処理装置1は,図3〜
図7に示すごとく,4台のワーク搬送機12,13を設
け,該ワーク搬送機12,13によりワーク7を位置決
めステップ,処理ステップ,排出ステップにそれぞれ連
続して搬送し,上記各ステップを行う。上記ワーク搬送
機12は,図5〜図7に示すごとく,ワーク7を載置す
ると共に位置決めする第1テーブル2と,該第1テーブ
ル2を昇降させる昇降機21と,上記第1テーブル2及
び昇降機21を水平方向に移動させる移動装置22と,
該移動装置22に接続したサーボ機構23とを有する。
同様に,上記ワーク搬送機13は,第2テーブル3,昇
降機31,移動装置32,及びサーボ機構33を有す
る。
Next, an apparatus used in the above-described work transfer processing method will be outlined. The workpiece transfer processing device 1 is shown in FIGS.
As shown in FIG. 7, four work transfer machines 12 and 13 are provided, and the work 7 is transferred by the work transfer machines 12 and 13 successively to the positioning step, the processing step, and the discharge step, and the above steps are performed. . As shown in FIGS. 5 to 7, the work transfer device 12 includes a first table 2 on which the work 7 is placed and positioned, a lift 21 for lifting and lowering the first table 2, a first table 2 and a lift A moving device 22 for moving the device 21 in the horizontal direction;
And a servo mechanism 23 connected to the moving device 22.
Similarly, the work carrier 13 has a second table 3, a lift 31, a moving device 32, and a servo mechanism 33.

【0028】以下,順を追って詳説する。上記ワーク搬
送処理装置1においては,図3に示すごとく,上記ワー
ク搬送機12,13が一対となって構成されており,こ
れらが並行に2系列設けられている。上記ワーク搬送機
12,13は,互いのテーブルを対向して配設されてい
るため,左右対称の構造である。
The details will be described below step by step. As shown in FIG. 3, the work transfer processing apparatus 1 is configured such that the work transfer machines 12 and 13 are configured as a pair, and these are provided in two lines in parallel. The work transfer machines 12 and 13 have a symmetrical structure because the tables are arranged to face each other.

【0029】上記ワーク搬送機12における第1テーブ
ル2は,図4に示すごとく,ワーク7(図8)を2枚載
置する板状体であり,各ワーク7の対角に設けた2個所
の位置決め穴70に対応する位置に,該位置決め穴70
の穴径より細い直径のピン状の位置決め具27を有して
いる。また,上記第1テーブル2は,上記各ワーク7を
載置する位置に,複数の空気噴出口(図示略)を有して
いる。同様に,上記ワーク搬送機13における第2テー
ブル3も,位置決め具37,空気噴出口を有している。
As shown in FIG. 4, the first table 2 of the work transfer device 12 is a plate-like body on which two works 7 (FIG. 8) are placed. At the position corresponding to the positioning hole 70, the positioning hole 70
And a pin-shaped positioning tool 27 having a diameter smaller than the diameter of the hole. The first table 2 has a plurality of air outlets (not shown) at positions where the respective works 7 are placed. Similarly, the second table 3 in the work transfer machine 13 also has a positioning tool 37 and an air outlet.

【0030】また,上記第1テーブル2と第2テーブル
3とは,図6,図7に示すごとく,互いに上下方向に位
置することができると共に,独立して水平方向に移動す
ることができ,かつ上記位置決めステップにおいては基
準位置H(図4,図5)まで上昇可能に設けてあり,排
出ステップにおいては下降可能に設けてある。また,上
記第1テーブル2と上記第2テーブル3とは同じ軌跡を
移動する。そのため,上記ワーク搬送機12の位置決め
部と,上記ワーク搬送機13の位置決め部とは,同じ場
所に位置する。これは,処理部,排出部についても同様
である。
As shown in FIGS. 6 and 7, the first table 2 and the second table 3 can be vertically positioned with respect to each other, and can be independently moved in the horizontal direction. Further, in the positioning step, it is provided so as to be able to ascend to a reference position H (FIGS. 4 and 5), and in the discharging step, it is provided so as to be able to descend. Further, the first table 2 and the second table 3 move along the same trajectory. Therefore, the positioning portion of the work transfer device 12 and the positioning portion of the work transfer device 13 are located at the same position. This is the same for the processing unit and the discharge unit.

【0031】次に,上記ワーク搬送機12における昇降
機21,移動装置22,サーボ機構23について説明す
る。上記昇降機21は,図5に示すごとく,走行柱21
3と,該走行柱213の側面にスライド可能に配設され
た走行機214と,該走行機214を上昇させるための
シリンダ(図示略)とからなる。上記走行機214は,
上記第1テーブル2の側面側に固定されている。
Next, the elevator 21, the moving device 22, and the servo mechanism 23 in the work transfer device 12 will be described. The elevator 21 is, as shown in FIG.
3, a traveling machine 214 slidably disposed on the side surface of the traveling column 213, and a cylinder (not shown) for raising the traveling machine 214. The traveling machine 214
The first table 2 is fixed to the side surface.

【0032】また,上記移動装置22は,図6,図7に
示すごとく,水平方向に配設されたレール225と,該
レール225と並行して配設されたボールネジ226と
からなる。上記レール225上には上記昇降機21をス
ライド可能に配設してある。また,上記ボールネジ22
6の雌ネジ部(図示略)には上記昇降機21が固定され
ている。また,上記サーボ機構23は,制御対象である
上記ボールネジ226に接続され,これを駆動するサー
ボモータ237,及び位置検出部(図示略)とからな
る。
As shown in FIGS. 6 and 7, the moving device 22 includes a rail 225 provided in the horizontal direction and a ball screw 226 provided in parallel with the rail 225. The elevator 21 is slidably disposed on the rail 225. In addition, the ball screw 22
The elevator 21 is fixed to a female screw portion 6 (not shown) of the elevator. The servo mechanism 23 is connected to the ball screw 226 to be controlled, and includes a servomotor 237 for driving the ball screw 226 and a position detection unit (not shown).

【0033】一方,上記ワーク搬送機13においても,
上記と同様に,昇降機31は,走行柱313と走行機3
14とシリンダ(図示略)とからなり,第1テーブル
2,第2テーブル3とを挟んだ状態で,上記ワーク搬送
機12の昇降機21とは反対側に配設されている。ま
た,移動装置32は,レール325とボールネジ326
とからなり,上記ワーク搬送機12の移動装置22と並
行して配設されている。また,サーボ機構33は,サー
ボモータ337,位置検出部(図示略)とからなる。
On the other hand, in the work transfer machine 13 as well,
Similarly to the above, the elevator 31 includes the traveling column 313 and the traveling machine 3.
14 and a cylinder (not shown). The first and second tables 2 and 3 are disposed on the opposite side of the work transporter 12 from the elevator 21 while sandwiching the first table 2 and the second table 3 therebetween. The moving device 32 includes a rail 325 and a ball screw 326.
And is arranged in parallel with the moving device 22 of the work carrier 12. The servo mechanism 33 includes a servomotor 337 and a position detection unit (not shown).

【0034】次に,上記ワーク搬送処理装置1は,図3
に示すごとく,上記2台のワーク搬送機12,13に対
して,ローダー15,処理装置16,17,アンローダ
ー18を一組有している。そして,上記位置決め部には
位置決めステップを行う上記ローダー15を,上記処理
部には処理ステップを行う上記処理装置16,17を,
上記排出部には排出ステップを行う上記アンローダー1
8を配設してある。
Next, the above-described work transfer processing apparatus 1
As shown in FIG. 1, a set of a loader 15, processing devices 16, 17 and an unloader 18 is provided for the two work transporters 12, 13. The loader 15 for performing the positioning step is provided in the positioning section, the processing devices 16 and 17 for performing the processing step are provided in the processing section,
The unloader 1 performs a discharging step in the discharging section.
8 is arranged.

【0035】上記ローダー15は,図3,図4に示すご
とく,2系列設けられた上記一対のワーク搬送機12,
13に対して,各系列の位置決め部の間を水平方向に移
動し,各位置決め部の上方において上下方向に移動する
ように構成されている。また,上記ローダー15は,ワ
ーク7を搬入するための搬入コンベヤ151を有してい
る。また,上記ローダー15には,上記第1テーブル
2,第2テーブル3の空気噴出口(図示略)に対応する
位置に,空気吸引口150(図4)を設けている。
As shown in FIGS. 3 and 4, the loader 15 is provided with two pairs of the work transfer machines 12,
As compared with 13, the positioning unit is configured to move in the horizontal direction between the positioning units of each series, and to move in the vertical direction above each positioning unit. The loader 15 has a carry-in conveyor 151 for carrying the work 7. Further, the loader 15 is provided with an air suction port 150 (FIG. 4) at a position corresponding to an air ejection port (not shown) of the first table 2 and the second table 3.

【0036】また,上記処理装置16,17は,図3,
図5〜図7に示すごとく,各系列において,上記ワーク
搬送機12とワーク搬送機13の間に配設されている。
上記処理装置16は,ワーク7であるプリント基板のパ
ターン部75(図8)において,高さ方向に生じた凸凹
(欠陥)を検出するカメラであり,上記処理装置17
は,水平方向に生じた凸凹を検出するカメラである。
The processing units 16 and 17 are the same as those shown in FIG.
As shown in FIG. 5 to FIG. 7, in each system, the work carrier 12 is disposed between the work carrier 12 and the work carrier 13.
The processing device 16 is a camera that detects irregularities (defects) generated in the height direction in the pattern portion 75 (FIG. 8) of the printed circuit board serving as the work 7.
Is a camera that detects unevenness generated in the horizontal direction.

【0037】また,上記アンローダー18は,図3に示
すごとく,2系列設けられた上記一対のワーク搬送機1
2,13に対して,各系列の排出部の間を水平方向に移
動し,各排出部の上方において上下方向に移動するよう
に構成されている。また,上記アンローダー18は,ワ
ーク7を搬出するための搬出コンベヤ181を有してい
る。該搬出コンベヤ181の上方には,不良品のワーク
79の払い出し装置19が配設されている。また,上記
アンローダー15,払い出し装置19にも,上記ローダ
ー15と同様に,空気吸引口を設けている。
As shown in FIG. 3, the unloader 18 is provided with two pairs of the work transfer machines 1 provided in two lines.
With respect to 2 and 13, it is configured to move in the horizontal direction between the discharge units of each series and to move in the vertical direction above each discharge unit. The unloader 18 has an unloading conveyor 181 for unloading the work 7. Above the unloading conveyor 181, there is provided a device 19 for unloading a defective work 79. The unloader 15 and the payout device 19 are also provided with an air suction port, similarly to the loader 15.

【0038】なお,図8には,上記ワーク7であるプリ
ント基板のボンディングパット面を示している。また,
符号75はパターン部,符号76はチップ搭載部であ
る。
FIG. 8 shows the bonding pad surface of the printed circuit board as the work 7. Also,
Reference numeral 75 denotes a pattern portion, and reference numeral 76 denotes a chip mounting portion.

【0039】次に,本例の作用効果につき説明する。上
記2台のワーク搬送機12,13のうち,1台目のワー
ク搬送機12の動作について説明する。まず,上記位置
決めステップにおいて,上記昇降機21がシリンダを用
いて第1テーブル2を基準位置H(図4,図5)まで上
昇させる(図2の第14工程参照)。この間,上記ロー
ダー15は,図3に示すごとく,上記搬入コンベヤ15
1によって搬入されたワーク7を,上記空気吸引口15
0によって吸着したまま,上記第1テーブル2上まで水
平移動する(図1の第1工程)。
Next, the operation and effect of this embodiment will be described. The operation of the first work transfer device 12 of the two work transfer devices 12 and 13 will be described. First, in the positioning step, the elevator 21 raises the first table 2 to a reference position H (FIGS. 4 and 5) using a cylinder (see a fourteenth step in FIG. 2). During this time, as shown in FIG.
1 is transferred to the air suction port 15
While being sucked by 0, it is horizontally moved to above the first table 2 (first step in FIG. 1).

【0040】そして,上記ローダー15は,図4(A)
に示すごとく,上記第1テーブル2上に位置する。次い
で,上記ローダー15は,図4(B)に示すごとく,上
記第1テーブル2上まで下降して,空気吸引口150か
ら空気を吸引することを停止してワーク7の吸着を解除
する。これにより,自重によってワーク7が上記第1テ
ーブル2上に載置される。このとき,上記ワーク7は,
その位置決め穴70が上記第1テーブル2の位置決め具
27に対して挿通された状態となって,図4(C)に示
すごとく,上記第1テーブル上に位置決めされている
(図1の第2工程)。
Then, the loader 15 shown in FIG.
As shown in FIG. Next, as shown in FIG. 4B, the loader 15 descends to the first table 2 and stops sucking air from the air suction port 150 to release the suction of the work 7. As a result, the work 7 is placed on the first table 2 by its own weight. At this time, the work 7
The positioning hole 70 is inserted into the positioning tool 27 of the first table 2 and positioned on the first table as shown in FIG. 4C (the second table in FIG. 1). Process).

【0041】そして,図6,図7に示すごとく,上記サ
ーボモーター237を駆動させることにより,上記移動
装置22であるボールネジ226が,上記第1テーブル
2上の先頭側のワーク7だけを,上記上記処理装置16
の下方に位置するように,上記第1テーブル2を上記処
理装置16の下方へ水平移動させる(図1の第3工
程)。上記第1テーブル2の停止位置は,上記サーボ機
構23によって自動制御される。これは,上記位置決め
ステップに限らず,全てのステップにおいて行われる。
As shown in FIGS. 6 and 7, by driving the servo motor 237, the ball screw 226 as the moving device 22 moves only the work 7 on the first side on the first table 2 to the above-mentioned position. The processing device 16
The first table 2 is horizontally moved below the processing device 16 so as to be located below (the third step in FIG. 1). The stop position of the first table 2 is automatically controlled by the servo mechanism 23. This is performed not only in the positioning step but also in all steps.

【0042】次いで,上記処理ステップにおいて,図
6,図7に示すごとく,上記処理装置16は,上記先頭
側のワーク7に対して,高さ方向に生じた欠陥検査を行
う。そして,上記移動装置22が,上記と同様に,上記
第1テーブル2を上記処理装置17の下方へ水平移動さ
せる(図1の第4,5工程)。次いで,上記処理装置1
7は,上記先頭側のワーク7に対して,水平方向に生じ
た欠陥検査を行う。また,同時に,上記処理装置16
が,上記第1テーブル2上に位置決めされた後方側のワ
ーク7に対して,高さ方向に生じた欠陥検査を行う。そ
して,上記移動装置22が,上記第1テーブル2を排出
部方向へ水平移動させる(図1の第6,7工程)。
Next, in the above processing steps, as shown in FIGS. 6 and 7, the processing device 16 performs a defect inspection on the work 7 on the head side in a height direction. Then, the moving device 22 horizontally moves the first table 2 below the processing device 17 in the same manner as described above (the fourth and fifth steps in FIG. 1). Next, the processing device 1
7 inspects the work 7 on the head side for a defect generated in the horizontal direction. At the same time, the processing unit 16
Performs a defect inspection on the work 7 on the rear side positioned on the first table 2 in a height direction. Then, the moving device 22 horizontally moves the first table 2 toward the discharge section (steps 6 and 7 in FIG. 1).

【0043】そして,上記処理装置17が,上記後方側
のワーク7に対して,上記と同様に,水平方向に生じた
欠陥検査を行う。そして,上記移動装置22が,上記第
1テーブル2を上記排出部まで水平移動させる(図1の
第8,9工程)。
Then, the processing device 17 performs a defect inspection in the horizontal direction on the work 7 on the rear side in the same manner as described above. Then, the moving device 22 horizontally moves the first table 2 to the discharge section (the eighth and ninth steps in FIG. 1).

【0044】次いで,上記排出ステップにおいて,上記
処理後のワーク7は,上記第1テーブル2の空気噴出口
から空気を噴出されて若干浮き上がり,位置決め具27
から抜け易くなっている。そして,上記アンローダー1
8は,上記第1テーブル2上まで水平移動し,上記第1
テーブル2上まで下降する。そして,空気吸引口から空
気を吸引することによって,上記ワーク7を吸着し,そ
の状態のまま上昇する(図1の第10工程,図2の第1
1工程)。
Next, in the discharging step, the work 7 after the processing is slightly lifted up by being blown out of the air from the air outlet of the first table 2, and the positioning tool 27 is lifted.
It is easy to get out of. And the above unloader 1
8 moves horizontally to the first table 2 and
It descends to the table 2. Then, the work 7 is sucked by sucking air from the air suction port, and the work 7 is raised as it is (the tenth process in FIG. 1 and the first process in FIG. 2).
1 step).

【0045】そして,図3に示すごとく,上記アンロー
ダー18は,搬出コンベヤ181上に上記2種類の欠陥
検査を終了したワーク7を排出する。良品のワーク71
は,そのまま上記搬出コンベヤ181上を搬送される。
一方,不良品のワーク79は,払い出し装置19によっ
て排出され,不良品テーブル195上にストックされ
る。
Then, as shown in FIG. 3, the unloader 18 discharges the workpiece 7 having been subjected to the above two types of defect inspection onto a carry-out conveyor 181. Good work 71
Is transported on the carry-out conveyor 181 as it is.
On the other hand, the defective work 79 is discharged by the payout device 19 and stocked on the defective product table 195.

【0046】一方,上記ワーク7を排出された第1テー
ブル2は,上記移動装置22によって,上記位置決め部
まで水平移動される(図2の第12,13工程)。
On the other hand, the first table 2 from which the work 7 has been discharged is horizontally moved to the positioning portion by the moving device 22 (steps 12 and 13 in FIG. 2).

【0047】そして,上記ワーク搬送機12は,上記位
置決めステップから処理ステップへの搬送,処理ステッ
プから排出ステップへの搬送,及び排出ステップから位
置決めステップへの搬送を繰り返し行う。そして,上記
ワーク搬送機12の第1テーブル2によって搬送される
ワーク7は,上記各ステップにおいてそれぞれの操作を
行われる。
The work transfer device 12 repeats the transfer from the positioning step to the processing step, the transfer from the processing step to the discharge step, and the transfer from the discharge step to the positioning step. The work 7 transferred by the first table 2 of the work transfer device 12 is subjected to each operation in each of the above steps.

【0048】次に,上記2台のワーク搬送機12,13
のうち,他のワーク搬送機13について説明する。上記
ワーク搬送機13における動作も,上記ワーク搬送機1
2の動作と同様である。しかし,2台目のワーク搬送機
13は,上記1台目のワーク搬送機12にワンステッ
プ,即ち6工程分遅れて動作を始める(図1参照)。そ
のため,ワーク搬送機12とワーク搬送機13とは互い
に異なるステップを併行して行う。
Next, the two work transporters 12, 13
Among them, another work transporter 13 will be described. The operation of the work transfer device 13 is also performed by the work transfer device 1.
The operation is the same as that of the second operation. However, the second work carrier 13 starts operation one step behind the first work carrier 12, that is, six steps later (see FIG. 1). Therefore, the work transfer device 12 and the work transfer device 13 perform different steps in parallel.

【0049】即ち,図1の第8工程に示すごとく,上記
ワーク搬送機12の第1テーブル2上のワーク7に欠陥
検査を行っている間,上記ワーク搬送機13の第2テー
ブル3上にワーク7が位置決めされる。また,図1の第
10工程に示すごとく,上記第1テーブル2上のワーク
7が排出されている間,上記第2テーブル3上のワーク
7には欠陥検査を行う。また,図2の第16工程に示す
ごとく,上記第1テーブル2上にワーク7が位置決めさ
れている間,上記第2テーブル3上のワーク7が排出さ
れる。
That is, as shown in the eighth step of FIG. 1, while the work 7 on the first table 2 of the work transfer machine 12 is being inspected for defects, the work 7 is placed on the second table 3 of the work transfer machine 13. The work 7 is positioned. Further, as shown in the tenth step of FIG. 1, while the work 7 on the first table 2 is being discharged, the work 7 on the second table 3 is subjected to a defect inspection. Further, as shown in a sixteenth step of FIG. 2, while the work 7 is positioned on the first table 2, the work 7 on the second table 3 is discharged.

【0050】なお,両テーブルの状態は,図2の第20
工程において,図1の第6工程と等しくなる。そのた
め,以後,上記第1テーブル2と第2テーブル3とは,
第7〜第20工程に示す状態を繰り返す。
The states of both tables are the same as those in the 20
In the process, it is equal to the sixth process in FIG. Therefore, hereinafter, the first table 2 and the second table 3
The states shown in the seventh to twentieth steps are repeated.

【0051】上記ワーク搬送処理装置1によれば,上記
のごとく,ワーク7に処理を行うための上記位置決め,
処理,排出の各ステップを上記第1テーブル2,第2テ
ーブル3に併行して行わせることができる。そのため,
タイムロスなく,効率的に上記ワーク7へ処理を行うこ
とができる。
According to the work transfer processing apparatus 1, as described above, the positioning and processing for processing the work 7 can be performed.
Each step of processing and discharging can be performed in parallel with the first table 2 and the second table 3. for that reason,
Processing can be efficiently performed on the work 7 without time loss.

【0052】また,上記第1テーブル2,第2テーブル
3が,図5に示すごとく,それぞれ位置決め具27,3
7を有しているため,両テーブルが位置決め部に搬送さ
れた段階で,ワーク7の位置決めを行うことができる。
そのため,位置決めステップに要する時間を短縮し,能
率を向上させることができる。
Further, as shown in FIG. 5, the first table 2 and the second table 3 respectively have positioning tools 27 and 3 respectively.
Since the table 7 is provided, the work 7 can be positioned when both tables are transported to the positioning section.
Therefore, the time required for the positioning step can be reduced, and the efficiency can be improved.

【0053】また,上記第1テーブル2,第2テーブル
3は,図6に示すごとく,上記位置決めステップから処
理ステップへの搬送,及び処理ステップから排出ステッ
プへの搬送において,順次,各ステップへ水平方向に移
動する。次いで,排出ステップから位置決めステップへ
の搬送においては,上記各テーブルは下降した後,上記
とは逆方向に水平に移動して,位置決め部において基準
位置Hまで上昇する。
Further, as shown in FIG. 6, the first table 2 and the second table 3 are horizontally moved to the respective steps in the transfer from the positioning step to the processing step and the transfer from the processing step to the discharge step. Move in the direction. Next, in the transport from the discharge step to the positioning step, each of the tables is lowered, then moves horizontally in the opposite direction to the above, and rises to the reference position H at the positioning section.

【0054】そのため,上記ワーク搬送機12,13
は,各テーブルを循環して搬送することができる。ま
た,そのサイクル中に2つのテーブルが存在しても,各
テーブルが互いに干渉することはなく,スムーズに上記
2つのテーブルを併行して搬送することができる。
Therefore, the work transfer devices 12 and 13
Can circulate and convey each table. Further, even if two tables exist during the cycle, the two tables do not interfere with each other, and the two tables can be smoothly transported in parallel.

【0055】また,上記ワーク搬送処理装置1は,一対
のワーク搬送機12,13を2系列設けている。そのた
め,一方の系列において,上記ローダー15がワーク搬
送機12にワーク7を位置決めしてから,次にワーク搬
送機13にワーク7を位置決めするまで,4工程分の間
隔がある(図2参照)。そのため,この間に,上記ロー
ダー15は,他方の系列におけるワーク搬送機12,1
3にワーク7を位置決めし,両系列間で交互に位置決め
を行うことができる。また,上記アンローダー18も,
同様にワーク7の排出を行うことができる。
The work transfer processing apparatus 1 is provided with a pair of work transfer machines 12 and 13 in two lines. Therefore, in one system, there is an interval of four processes from the time when the loader 15 positions the work 7 on the work transfer machine 12 to the time when the work 7 is next positioned on the work transfer machine 13 (see FIG. 2). . Therefore, during this time, the loader 15 moves the work transporters 12, 1 in the other system.
The work 7 can be positioned at 3 and the positioning can be performed alternately between the two systems. The unloader 18 also
Similarly, the work 7 can be discharged.

【0056】そのため,ワーク7の位置決め及び排出を
待機する時間を短縮することができるので,搬入コンベ
ヤ151及び搬出コンベヤ181の搬送速度を向上する
ことができる。それ故,より一層能率を向上させること
ができる。
Therefore, the time for waiting for positioning and discharging of the work 7 can be reduced, so that the carrying speed of the carry-in conveyor 151 and the carry-out conveyor 181 can be improved. Therefore, the efficiency can be further improved.

【0057】[0057]

【発明の効果】上述のごとく,本発明によれば,ワーク
の搬送とワークへの処理とを併行して行い,ワークの搬
送,及び処理に要する時間を短縮することができる,ワ
ーク搬送処理方法,及び装置を提供することができる。
As described above, according to the present invention, the work transfer and the processing to the work are performed in parallel, and the work transfer and processing time can be reduced. , And equipment can be provided.

【図面の簡単な説明】[Brief description of the drawings]

【図1】実施形態例にかかる,ワーク搬送処理方法の作
動説明図。
FIG. 1 is a diagram illustrating the operation of a work transfer processing method according to an embodiment.

【図2】図1に続く,ワーク搬送処理方法の作動説明
図。
FIG. 2 is an operation explanatory view of the work transfer processing method, following FIG. 1;

【図3】実施形態例にかかる,ワーク搬送処理装置の平
面図。
FIG. 3 is a plan view of the work transfer processing apparatus according to the embodiment.

【図4】実施形態例にかかる,ワークの位置決め順序を
説明する正面図。
FIG. 4 is a front view illustrating a work positioning sequence according to the embodiment;

【図5】実施形態例にかかる,ワーク搬送機と処理装置
の側面図。
FIG. 5 is a side view of the work transfer device and the processing device according to the embodiment.

【図6】実施形態例にかかる,ワーク搬送機と処理装置
の正面図。
FIG. 6 is a front view of the work transfer device and the processing device according to the embodiment.

【図7】実施形態例にかかる,ワーク搬送機と処理装置
の平面図。
FIG. 7 is a plan view of a work transfer device and a processing device according to the embodiment.

【図8】実施形態例にかかる,ワークの平面図。FIG. 8 is a plan view of a work according to the embodiment.

【符号の説明】[Explanation of symbols]

1...ワーク搬送処理装置, 12,13...ワーク搬送機, 15...ローダー, 16,17...処理装置, 18...アンローダー, 2...第1テーブル, 21...昇降機, 22...移動装置, 23...サーボ機構, 27...位置決め具, 3...第2テーブル, 7...ワーク, 1. . . Work transfer processing device, 12, 13. . . Work carrier, 15. . . Loader, 16,17. . . Processing device, 18. . . Unloader, 2. . . First table, 21. . . Elevator, 22. . . Mobile device, 23. . . Servo mechanism, 27. . . Positioning tool, 3. . . 6. second table, . . work,

Claims (5)

【特許請求の範囲】[Claims] 【請求項1】 位置決め部において第1テーブル上にワ
ークを載置すると共に位置決めする位置決めステップを
行い,次いで,上記ワークを上記第1テーブル上に載せ
たまま移動させ,処理部に停止させて処理ステップを行
い,この処理ステップを行っている間に第2テーブルを
上記位置決め部へ移動させると共に,該第2テーブル上
にワークを載置,位置決めする位置決めステップを行
い,上記第1テーブル上のワークに処理ステップを行っ
た後に該ワークを上記第1テーブル上に載せたまま移動
させ,排出部において上記ワークの位置決めを解除する
と共に,上記ワークを排出する排出ステップを行い,こ
の間に上記第2テーブル上の位置決め済みのワークを上
記第2テーブル上に載せたまま移動させ,上記処理部に
おいて上記処理ステップを行い,以下,順次,上記位置
決めステップ,処理ステップ,及び排出ステップを併行
して行うことを特徴とするワーク搬送処理方法。
A positioning step of placing and positioning a work on a first table in a positioning section, moving the work while placing the work on the first table, and stopping the processing section to process the work; Steps are performed, and while this processing step is being performed, the second table is moved to the positioning section, and a positioning step of mounting and positioning the work on the second table is performed. After performing the processing step, the work is moved while being placed on the first table, and the discharging section releases the positioning of the work and performs a discharge step of discharging the work. The above positioned work is moved while being placed on the second table, and the processing section performs the processing step. And carrying out the positioning step, the processing step, and the discharging step in this order in parallel.
【請求項2】 請求項1の発明において,上記処理ステ
ップは,複数種類行うことを特徴とするワーク搬送処理
方法。
2. The method according to claim 1, wherein the processing steps are performed in plural types.
【請求項3】 複数のワーク搬送機を設け,該ワーク搬
送機によりワークを位置決めステップ,処理ステップ,
排出ステップにそれぞれ連続して搬送し,上記各ステッ
プを行うワーク搬送処理装置であって,上記ワーク搬送
機は,それぞれワークを載置すると共に位置決めするテ
ーブルと,該テーブルを昇降させる昇降機と,上記テー
ブル及び昇降機を水平方向に移動させる移動装置と,該
移動装置に接続したサーボ機構とを有することを特徴と
するワーク搬送処理装置。
3. A plurality of work transporters are provided, and the workpiece transporter positions a work, a processing step,
A work transfer processing device that transfers the work successively to the discharge step and performs each of the steps. The work transfer device includes a table for placing and positioning a work, an elevator for moving the table up and down, A work transfer processing device comprising: a moving device for moving a table and an elevator in a horizontal direction; and a servo mechanism connected to the moving device.
【請求項4】 請求項3において,上記各ワーク搬送機
におけるテーブルは,それぞれ位置決め具を有すること
を特徴とするワーク搬送処理装置。
4. The apparatus according to claim 3, wherein each of the tables in each of the work transfer devices has a positioning tool.
【請求項5】 請求項3又は4において,上記各テーブ
ルは,互いに上下方向に位置することができると共に,
独立して水平方向に移動することができ,かつ上記位置
決めステップにおいては基準位置まで上昇可能に設けて
あり,排出ステップにおいては下降可能に設けてあるこ
とを特徴とするワーク搬送処理装置。
5. The apparatus according to claim 3, wherein each of the tables can be positioned vertically with respect to each other.
A workpiece transfer processing device which can be independently moved in a horizontal direction, is provided so as to be able to ascend to a reference position in the positioning step, and is provided so as to be able to descend in a discharging step.
JP10105820A 1998-03-31 1998-03-31 Work carrying and processing method and its device Pending JPH11286318A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP10105820A JPH11286318A (en) 1998-03-31 1998-03-31 Work carrying and processing method and its device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP10105820A JPH11286318A (en) 1998-03-31 1998-03-31 Work carrying and processing method and its device

Publications (1)

Publication Number Publication Date
JPH11286318A true JPH11286318A (en) 1999-10-19

Family

ID=14417717

Family Applications (1)

Application Number Title Priority Date Filing Date
JP10105820A Pending JPH11286318A (en) 1998-03-31 1998-03-31 Work carrying and processing method and its device

Country Status (1)

Country Link
JP (1) JPH11286318A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2009038261A (en) * 2007-08-02 2009-02-19 Hitachi High-Tech Instruments Co Ltd Component mounting apparatus
JP2009253070A (en) * 2008-04-08 2009-10-29 Sony Corp Component mounting device, method of manufacturing mounted component, and conveyor apparatus

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2009038261A (en) * 2007-08-02 2009-02-19 Hitachi High-Tech Instruments Co Ltd Component mounting apparatus
JP2009253070A (en) * 2008-04-08 2009-10-29 Sony Corp Component mounting device, method of manufacturing mounted component, and conveyor apparatus
US8162128B2 (en) 2008-04-08 2012-04-24 Sony Corporation Component mounting apparatus, mounting-component producing method, and conveyor apparatus
US8376129B2 (en) 2008-04-08 2013-02-19 Sony Corporation Component mounting apparatus, mounting-component producing method, and conveyor apparatus

Similar Documents

Publication Publication Date Title
EP1042201B1 (en) Method and apparatus for inverting a tray
JP3560722B2 (en) Substrate transfer method and apparatus
KR100339499B1 (en) Loadding device and method of PCB manufacturing process
JP2003078287A (en) Method and apparatus for conveyance of board in component mounting machine
CN108116888B (en) Automated substrate processing system with dual process equipment
JP4175057B2 (en) Electronic component mounting system
JPH11286318A (en) Work carrying and processing method and its device
JP6326541B1 (en) Substrate dividing apparatus and substrate dividing method
TWI393901B (en) Workpiece handling apparatus
US6688840B2 (en) Transport apparatus and method
KR101863139B1 (en) Substrate cutting apparatus of which scrap collector is installed under unloading area
JP2005017386A (en) Device for inspecting and correcting flat plate work
JP3444187B2 (en) Solder ball mounting method
JP4334291B2 (en) Work transfer device and processing system
KR101828381B1 (en) Substrate cutting apparatus comprising complex transfer tool and method of transferring substrate using the same
JP3898401B2 (en) Parts supply device
TWI599286B (en) Automatic substrate processing system with dual process devices
JP2000174158A (en) Ball mounting apparatus
KR100232699B1 (en) Inspection device of trimming and forming apparatus
JP2003051698A (en) Method and device for mounting electronic component
KR100754764B1 (en) Vacuum suction system to operate by robot arm
JP7062531B2 (en) Component mounting device
TW202203333A (en) Article manufacturing device, article manufacturing method, program, and recording medium
JP3215444B2 (en) Chip mounting method
KR0126333Y1 (en) Semiconductor package transferring device