JPH11193631A - Execution work plan system - Google Patents

Execution work plan system

Info

Publication number
JPH11193631A
JPH11193631A JP36907597A JP36907597A JPH11193631A JP H11193631 A JPH11193631 A JP H11193631A JP 36907597 A JP36907597 A JP 36907597A JP 36907597 A JP36907597 A JP 36907597A JP H11193631 A JPH11193631 A JP H11193631A
Authority
JP
Japan
Prior art keywords
work
time
unit
construction
specified
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP36907597A
Other languages
Japanese (ja)
Inventor
康史 ▲吉▼村
Yasushi Yoshimura
Fumio Hatori
文雄 羽鳥
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hitachi Plant Technologies Ltd
Original Assignee
Hitachi Plant Technologies Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hitachi Plant Technologies Ltd filed Critical Hitachi Plant Technologies Ltd
Priority to JP36907597A priority Critical patent/JPH11193631A/en
Publication of JPH11193631A publication Critical patent/JPH11193631A/en
Pending legal-status Critical Current

Links

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02PCLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
    • Y02P90/00Enabling technologies with a potential contribution to greenhouse gas [GHG] emissions mitigation
    • Y02P90/30Computing systems specially adapted for manufacturing

Abstract

PROBLEM TO BE SOLVED: To provide an execution work plan system through which the work plan of execution work can be accurately carried out. SOLUTION: A computing section 14 reads out a work time variation parameter housed in a data base 16 to compute each element motion time (step 120). Each element motion time is combined to compute a unit motion time (step 130). A unit motion combination is set from the composition of an element work (step 140) to compute an element work time (step 150). The element work combination of a plurality of workers is set up from the formation of unit work, the standard number of workers, a worker combination pattern, standard number of work groups, and the combination pattern of work groups (step 160) to compute a unit work time (step 170). A unit work combination is set up (step 180), and a plurality of unit work time is combined to compute a concluded work time (step 190).

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【発明の属する技術分野】本発明は施工作業計画システ
ムに係り、特に配管、空調機据付、ビル建設等の施工作
業計画時に使用される施工作業計画システムに関する。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a construction work planning system and, more particularly, to a construction work planning system used for construction work planning such as piping, air conditioner installation, and building construction.

【0002】[0002]

【従来の技術】施工作業は複数のまとまり作業から構成
され、各まとまり作業は複数の単位作業から構成され、
各単位作業は複数の作業員で構成される作業班によって
行われる。前記各単位作業は複数の要素作業から構成さ
れ、各要素作業は前記各作業員によって行われる。前記
各要素作業は複数の単位動作から構成され、各単位動作
は複数の要素動作から構成される。
2. Description of the Related Art Construction work is composed of a plurality of collective works, and each collective work is composed of a plurality of unit works.
Each unit work is performed by a work group composed of a plurality of workers. Each unit work is composed of a plurality of element works, and each element work is performed by each worker. Each element operation is composed of a plurality of unit operations, and each unit operation is composed of a plurality of element operations.

【0003】従来の施工作業計画システムでは、まとま
り作業や単位作業レベルにおいて作業の開始時間や終了
時間、必要作業人員を入力し、それらを基にまとまり作
業、単位作業レベルの工程長を演算し、作業員の山積み
を行っていた。
[0003] In the conventional construction work planning system, the start time and end time of work at the collective work and the unit work level and the required worker are input, and the collective work and the process length at the unit work level are calculated based on these. The workers were piled up.

【0004】[0004]

【発明が解決しようとする課題】しかしながら、作業の
開始時間や終了時間は、作業対象や作業環境や作業員及
び作業班の組合せによって変化する。そのため、開始時
間や終了時間が特定できないと、前記工程長を演算する
ことができなかった。また、作業員各々の作業時間から
積み上げた作業の生産性(例えば、工数/t、工数/
m)の演算を行うことができなかった。
However, the start time and the end time of the work vary depending on the work target, the work environment, and the combination of the worker and the work group. Therefore, the process length could not be calculated unless the start time and end time could be specified. Further, the productivity of the work accumulated from the work time of each worker (for example, man-hour / t, man-hour /
m) could not be performed.

【0005】作業に使用されるクレーン等の施工装置や
溶接機等の道工具に関しては、施工計画当初において計
画したピーク量に併せて各作業に分配していた。そのた
め、使用量の時間推移や稼働率に応じて各作業班に有効
に分配することができず、作業の効率をあげることがで
きなかった。本発明は、このような事情に鑑みてなされ
たもので、施工作業の作業計画を正確に行うことができ
る施工作業計画システムを提供することを目的とする。
[0005] Construction tools such as cranes and tool tools such as welding machines used for the work have been distributed to each work in accordance with the peak amount planned at the beginning of the construction plan. For this reason, it has not been possible to effectively distribute the usage to the respective working groups in accordance with the time transition and the operating rate of the used amount, and it has not been possible to increase the efficiency of the work. The present invention has been made in view of such circumstances, and has as its object to provide a construction work planning system that can accurately perform a work plan for construction work.

【0006】[0006]

【課題を解決する為の手段】本発明は上記課題を解決す
るために、単位作業が特定されると、該単位作業に対し
て階層構造をなす要素作業、単位動作及び要素動作を特
定する手段と、前記特定された要素動作に要する第1の
時間を求める手段と、前記特定された単位動作に要する
第2の時間を、該単位動作に属する要素動作の前記求め
た第1の時間に基づいて求める手段と、前記特定された
要素作業に要する第3の時間を、該要素作業に属する単
位動作の組合せパターンと前記求めた第2の時間とに基
づいて求める手段と、前記特定された単位作業に要する
第4の時間を、該単位作業に属する要素作業の組合せパ
ターンと前記求めた第3の時間とに基づいて求める手段
と、を備えたことを特徴とする。
According to the present invention, in order to solve the above-mentioned problems, when a unit work is specified, means for specifying the element work, the unit operation and the element operation forming a hierarchical structure with respect to the unit work are specified. Means for determining a first time required for the specified element operation, and a second time required for the specified unit operation based on the determined first time of the element operation belonging to the unit operation. Means for obtaining the third time required for the specified element work based on the combination pattern of the unit actions belonging to the element work and the obtained second time; and Means for obtaining a fourth time required for the work based on the combination pattern of the element works belonging to the unit work and the obtained third time.

【0007】本発明によれば、単位作業が特定される
と、該単位作業に対して階層構造をなす要素作業、単位
動作及び要素動作を特定し、特定された要素動作に要す
る第1の時間を求める。第1の時間が求められると、特
定された単位動作に要する第2の時間を前記求めた第1
の時間に基づいて求める。第2の時間が求められると、
特定された要素作業に要する第3の時間を、該要素作業
に属する単位動作の組合せパターンと前記求めた第2の
時間とに基づいて求める。第3の時間が求められると、
特定された単位作業に要する第4の時間を、該単位作業
に属する要素作業の組合せパターンと前記求めた第3の
時間とに基づいて求める。このように、要素動作に要す
る第1の時間を求め、単位動作に要する第2の時間、要
素作業に要する第3の時間、単位作業に要する第4の時
間の順に求めることによって、要素動作から単位作業ま
での施工作業の作業計画を正確に行うことができる。
According to the present invention, when a unit work is specified, the element work, the unit operation, and the element operation that form a hierarchical structure with respect to the unit work are specified, and the first time required for the specified element operation is specified. Ask for. When the first time is determined, the second time required for the specified unit operation is determined by the determined first time.
Calculate based on time. When the second time is required,
A third time required for the specified element work is obtained based on the combination pattern of the unit actions belonging to the element work and the obtained second time. When a third time is required,
A fourth time required for the specified unit work is obtained based on the combination pattern of the element works belonging to the unit work and the obtained third time. As described above, the first time required for the element operation is obtained, and the second time required for the unit operation, the third time required for the element work, and the fourth time required for the unit operation are obtained in this order, so that the element operation is calculated. The work plan of the construction work up to the unit work can be accurately performed.

【0008】[0008]

【発明の実施の形態】以下添付図面に従って本発明に係
る施工作業計画システムの好ましい実施の形態について
詳説する。図1は、施工作業の階層構造を示す説明図で
ある。施工作業は複数のまとまり作業から構成され、各
まとまり作業は複数の単位作業から構成され、各単位作
業は複数の作業員で構成される作業班によって行われ
る。前記各単位作業は複数の要素作業から構成され、各
要素作業は前記各作業員によって行われる。前記各要素
作業は複数の単位動作から構成され、前記各単位動作は
複数の要素動作から構成される。
DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS Preferred embodiments of a construction work planning system according to the present invention will be described below in detail with reference to the accompanying drawings. FIG. 1 is an explanatory diagram showing the hierarchical structure of the construction work. The construction work is composed of a plurality of collective works, each collective work is composed of a plurality of unit works, and each unit work is performed by a work group composed of a plurality of workers. Each unit work is composed of a plurality of element works, and each element work is performed by each worker. Each element operation is composed of a plurality of unit operations, and each unit operation is composed of a plurality of element operations.

【0009】例えば、図2に示すように、施工作業を構
成するまとまり作業は、サポート据付、大径配管据付、
小径配管据付、…、空調機据付である。サポート据付を
構成する単位作業は、搬入、芯だし、加工、溶接であ
り、大径配管据付を構成する単位作業は、搬入、吊上
げ、仮付け、溶接、検査である。大径配管据付の搬入
は、作業班Aによって行われ、作業班Aは作業員a、
b、cによって構成され、各作業員は各々要素作業を行
う。作業員cの行う単位動作は取付位置へ等であり、取
付位置へを構成する要素動作は、ローリングタワーへ登
り、安全帯を掛ける、ローリングタワーへ降りる、…で
ある。
[0009] For example, as shown in FIG. 2, the collective work constituting the construction work includes support installation, large-diameter pipe installation,
Installation of small diameter pipes, installation of air conditioners. The unit work constituting the support installation is carrying-in, centering, processing, and welding, and the unit work constituting the large-diameter piping installation is carrying-in, lifting, tacking, welding, and inspection. The installation of the large-diameter piping is carried out by the work team A, and the work team A
b, c, each worker performs element work. The unit operation performed by the worker c is, for example, to the mounting position, and the elementary operations constituting the mounting position include climbing to the rolling tower, putting on a safety belt, descending to the rolling tower, and so on.

【0010】図3は施工作業計画システムの構成を示す
ブロック図である。同図に示すように、施工作業計画シ
ステム10は、作業対象の情報等を入力する入力部12
と、入力されたデータを基に演算を行う演算部14と、
演算に使用するデータを格納するデータベース16と、
プリンタ18やディスプレー20に演算結果を出力する
出力部22とから構成される。
FIG. 3 is a block diagram showing the configuration of the construction work planning system. As shown in FIG. 1, the construction work planning system 10 includes an input unit 12 for inputting work target information and the like.
And an operation unit 14 for performing an operation based on the input data;
A database 16 for storing data used for the calculation,
An output unit 22 for outputting the calculation result to the printer 18 and the display 20.

【0011】前記データベース16には、図4に示すよ
うに、前述したまとまり作業から要素動作までの各作業
階層の構成、要素作業と施工装置、単位動作と道工具、
要素作業標準作業員数、単位作業標準作業班数、作業時
間変動パラメータ、作業員組合せパターン、及び作業班
組合せパターンのデータが格納されている。また、前記
演算部14には、対象物名や作業位置や物量や形状等の
作業対象の情報、投入可能作業員数、及びまとまり作業
と単位作業の開始時期が入力される。このとき、作業対
象の情報は、演算部14に入力部12での手動操作で入
力せず、CADのデータベース24から演算部14に自
動的に入力してもよい。
As shown in FIG. 4, the database 16 has a structure of each work hierarchy from the above-mentioned collective work to element operation, element work and construction equipment, unit operation and tool,
Data on the number of elementary work standard workers, the number of unit work standard work groups, work time variation parameters, worker combination patterns, and work group combination patterns are stored. In addition, information of the work target such as the name of the work, the work position, the quantity and the shape, the number of workers that can be input, and the start time of the collective work and the unit work are input to the arithmetic unit 14. At this time, the work target information may be automatically input from the CAD database 24 to the arithmetic unit 14 without being input to the arithmetic unit 14 by the manual operation of the input unit 12.

【0012】演算部14は入力されたデータを基に、必
要作業員数、まとまり作業と単位作業の終了時期、稼働
率、原単位、作業時間、施工設備、及び道工具稼働率を
演算して出力部22に出力する。次に、施工作業計画シ
ステムの作用について説明する。図5は作業計画の手順
を示すフローチャートである。まず、演算部14は入力
された作業対象の情報からまとまり作業を特定する(ス
テップ100)。まとまり作業を特定したら、演算部1
4はまとまり作業構成データベース30から各まとまり
作業を構成する単位作業、要素作業、単位動作、要素動
作を特定する(ステップ110)。単位作業から要素動
作までの構成は、図6に示すようなデータとして構築さ
れる。図6上で網かけされた項目は、予め入力されてい
るデータである。
The calculation unit 14 calculates and outputs the required number of workers, the end time of the group work and the unit work, the operation rate, the basic unit, the work time, the construction equipment, and the tool operation rate based on the input data. Output to the unit 22. Next, the operation of the construction work planning system will be described. FIG. 5 is a flowchart showing the procedure of the work plan. First, the calculation unit 14 specifies a grouped work from the input information of the work target (Step 100). After specifying the united work, the operation unit 1
4 specifies the unit work, the element work, the unit operation, and the element operation constituting each collective work from the collective work configuration database 30 (step 110). The configuration from the unit work to the element operation is constructed as data as shown in FIG. Items shaded in FIG. 6 are data that have been input in advance.

【0013】まとまり作業から要素動作まで特定した
ら、演算部14はデータベース16内に格納された作業
時間変動パラメータを読み出し、各要素動作時間を算出
する(ステップ120)。例えば、「はしごで登る」と
いう要素動作に要する時間は、足場段数、チェーンブロ
ックを持って登る等の作業時間変動要因に基づいて、既
知の方法によって算出される。要素動作時間を算出した
ら、各要素動作時間を組み合わせて単位動作時間を算出
する(ステップ130)。
After specifying from the collective operation to the element operation, the operation unit 14 reads the operation time variation parameter stored in the database 16 and calculates each element operation time (step 120). For example, the time required for the element operation of “climbing with a ladder” is calculated by a known method based on the number of working steps and the factors of work time fluctuation such as climbing with a chain block. After calculating the element operation time, the unit operation time is calculated by combining the element operation times (Step 130).

【0014】単位動作時間が算出されたら、要素作業の
構成から単位動作組合せを設定し(ステップ140)、
単位動作時間を組み合わせて要素作業時間を算出する
(ステップ150)。要素作業時間が算出されたら、単
位作業の構成と標準作業員数とデータベースに格納され
た作業員組合せパターンから作業班毎(図2上では作業
班Aのみ)に複数作業員の要素作業タイムチャート40
を作成し、単位作業の構成と標準作業班数とデータベー
スに格納された作業班組合せパターンから複数作業員の
要素作業組合せを設定する(ステップ160)。要素作
業組合せが設定されたら、演算部14は、作成された要
素作業タイムチャート40と要素作業組合せから単位作
業時間を算出する(ステップ170)。
After the unit operation time is calculated, a unit operation combination is set from the configuration of the element work (step 140).
The element operation time is calculated by combining the unit operation times (step 150). When the element work time is calculated, the element work time chart 40 of a plurality of workers for each work group (only the work group A in FIG. 2) from the unit work configuration, the standard number of workers, and the worker combination pattern stored in the database.
Is created, and an element work combination of a plurality of workers is set from the unit work configuration, the standard work group number, and the work group combination pattern stored in the database (step 160). When the element work combination is set, the calculation unit 14 calculates a unit work time from the created element work time chart 40 and the element work combination (Step 170).

【0015】単位作業時間が算出されたら、演算部14
はまとまり作業の構成から単位作業組合せを設定し(ス
テップ180)、演算部14に入力された各単位作業の
開始時間と各単位作業時間に基づいてまとまり作業時間
を算出する(ステップ190)。通常、まとまり作業時
間は単位作業時間を単純に組み合わせて算出されるの
で、単位作業時間まで算出できれば十分とする。
When the unit working time is calculated, the operation unit 14
A unit work combination is set from the configuration of the united work (step 180), and a united work time is calculated based on the start time of each unit work and each unit work time input to the arithmetic unit 14 (step 190). Usually, the united work time is calculated by simply combining the unit work times, so it is sufficient if the unit work time can be calculated.

【0016】要素動作時間からまとまり作業時間まで算
出されたら、物量データベース32から据付対象物量と
作業人員とを演算部14に入力する(ステップ20
0)。演算部14は入力されたデータを基に、工数/t
(効率、生産性)、作業期間、稼働率を演算する(ステ
ップ210)。工数/tは前記物量データベースの据付
対象物量と工数とから演算する。作業期間は、入力され
たまとまり作業と単位作業との開始時期から作業の各階
層について図2に示すような作業期間のタイムチャート
を作成して演算する。
When the total operation time is calculated from the element operation time, the amount of the object to be installed and the number of workers are input from the physical quantity database 32 to the calculation unit 14 (step 20).
0). The arithmetic unit 14 calculates man-hours / t based on the input data.
(Efficiency, productivity), work period, and operation rate are calculated (step 210). The man-hour / t is calculated from the amount of the object to be installed and the man-hour in the physical quantity database. The work period is calculated by creating a time chart of the work period as shown in FIG. 2 for each hierarchy of the work from the input start time of the collective work and the unit work.

【0017】次に、稼働率の演算方法について説明す
る。図7は複数の作業員a〜dの作業時間を示すタイム
チャートである。作業員の稼働率は、各作業員a〜dが
作業を行っている時間を作業が行われている時間Tで除
算して算出される。また、複数の作業員の稼働率は、
(1) 式で算出される。
Next, a method of calculating the operation rate will be described. FIG. 7 is a time chart showing the working hours of the workers a to d. The operating rate of the worker is calculated by dividing the time during which each of the workers a to d is performing the work by the time T during which the worker is performing the work. Also, the operating rate of multiple workers is
It is calculated by equation (1).

【0018】[0018]

【数1】 稼働率=ΣWi /I・T …(1) Iは作業員数、iは各作業員のナンバーを表し、Wi
作業員iが作業を行う時間を表す。また、図8は装置1
〜4の使用される時間を示すタイムチャートである。各
装置1〜4の稼働率は、装置の使用されている時間を作
業が行われている時間Tで除算して算出される。
[Number 1] operating rate = ΣW i / I · T ... (1) I can work force, i represents the number of each worker, W i represents the time to perform the work worker i. FIG. 8 shows the device 1
It is a time chart which shows the use time of No.-. The operation rate of each of the devices 1 to 4 is calculated by dividing the time during which the device is used by the time T during which work is performed.

【0019】図9は道工具1〜4の使用される時間を示
すタイムチャートである。各道工具1〜4の稼働率は、
道工具の使用されている時間を作業が行われている時間
Tで除算して算出される。図10に示すように、作業場
所が複数のエリア1、2、3、…、nに区分された場合
には、各エリア毎に図5に示した手順で演算を行い、各
作業エリアの演算結果を評価項目によって評価する。評
価項目は、要素作業レベルでの装置稼働率と道工具稼働
率と作業員稼働率と、まとまり作業と単位作業レベルで
の装置山積みと道工具山積みと作業員山積みとである。
これによって、各エリアに投入する作業員数や装置や道
工具を調整することができる。
FIG. 9 is a time chart showing the use time of the road tools 1-4. The operating rate of each road tool 1-4 is
It is calculated by dividing the time during which the tool is used by the time T during which work is performed. As shown in FIG. 10, when the work place is divided into a plurality of areas 1, 2, 3,..., N, the calculation is performed for each area according to the procedure shown in FIG. The results are evaluated according to the evaluation items. The evaluation items are the equipment operation rate, the tool operation rate, and the worker operation rate at the element work level, and the apparatus stack, the tool stack, and the worker stack at the collective work and the unit work level.
This makes it possible to adjust the number of workers, devices and tools to be put into each area.

【0020】[0020]

【発明の効果】以上説明したように、本発明の施工作業
計画システムによれば、要素動作に要する第1の時間を
求め、単位動作に要する第2の時間を第1の時間に基づ
いて求め、要素作業に要する第3の時間を要素作業に属
する単位動作の組合せパターンと第2の時間とに基づい
て求め、単位作業に要する第4の時間を該単位作業に属
する要素作業の組合せパターンと第3の時間とに基づい
て求めることによって、要素動作から単位作業までの施
工作業の作業計画を正確に行うことができる。
As described above, according to the construction work planning system of the present invention, the first time required for the element operation is obtained, and the second time required for the unit operation is obtained based on the first time. The third time required for the elementary work is determined based on the combination pattern of the unit operations belonging to the elementary work and the second time, and the fourth time required for the unitary work is determined based on the combination pattern of the elementary works belonging to the unit work. By calculating based on the third time, the work plan of the construction work from the element operation to the unit work can be accurately performed.

【図面の簡単な説明】[Brief description of the drawings]

【図1】施工作業の階層構造を示す説明図FIG. 1 is an explanatory diagram showing a hierarchical structure of construction work.

【図2】まとまり作業から単位動作までのタイムチャー
トと単位動作を構成する要素動作を示す説明図
FIG. 2 is a time chart from a collective operation to a unit operation and an explanatory diagram showing element operations constituting the unit operation;

【図3】施工作業計画システムの構成を示すブロック図FIG. 3 is a block diagram showing a configuration of a construction work planning system.

【図4】演算部に入力されるデータと出力されるデータ
を示す説明図
FIG. 4 is an explanatory diagram showing data input to and output data from an arithmetic unit;

【図5】施工作業計画システムの演算手順を示すフロー
チャート
FIG. 5 is a flowchart showing a calculation procedure of the construction work planning system.

【図6】単位作業から単位動作までのデータ構成を示す
説明図
FIG. 6 is an explanatory diagram showing a data configuration from a unit operation to a unit operation.

【図7】複数作業員の作業を行っている時間を示すタイ
ムチャート
FIG. 7 is a time chart showing the time during which a plurality of workers are working.

【図8】複数装置の使用されている時間を示すタイムチ
ャート
FIG. 8 is a time chart showing the time during which a plurality of devices are used.

【図9】複数道工具の使用されている時間を示すタイム
チャート
FIG. 9 is a time chart showing the time during which a multi-path tool is used.

【図10】複数のエリアに投入する作業員や装置や道工
具を調整する方法を示す説明図
FIG. 10 is an explanatory diagram showing a method of adjusting workers, devices, and tools to be put into a plurality of areas.

【符号の説明】[Explanation of symbols]

10…施工作業計画システム 12…入力部 14…演算部 16…データベース 22…出力部 DESCRIPTION OF SYMBOLS 10 ... Construction work planning system 12 ... Input part 14 ... Calculation part 16 ... Database 22 ... Output part

Claims (5)

【特許請求の範囲】[Claims] 【請求項1】 単位作業が特定されると、該単位作業に
対して階層構造をなす要素作業、単位動作及び要素動作
を特定する手段と、 前記特定された要素動作に要する第1の時間を求める手
段と、 前記特定された単位動作に要する第2の時間を、該単位
動作に属する要素動作の前記求めた第1の時間に基づい
て求める手段と、 前記特定された要素作業に要する第3の時間を、該要素
作業に属する単位動作の組合せパターンと前記求めた第
2の時間とに基づいて求める手段と、 前記特定された単位作業に要する第4の時間を、該単位
作業に属する要素作業の組合せパターンと前記求めた第
3の時間とに基づいて求める手段と、 を備えたことを特徴とする施工作業計画システム。
When a unit work is specified, means for specifying an element work, a unit operation, and an element operation that form a hierarchical structure with respect to the unit work, and a first time required for the specified element operation, Means for obtaining, a means for obtaining the second time required for the specified unit operation based on the obtained first time of the element operation belonging to the unit operation, and a third time required for the specified element operation Means for determining the time of the unit work based on the combination pattern of the unit operations belonging to the element work and the obtained second time; and determining the fourth time required for the specified unit work by the element belonging to the unit work. Means for obtaining based on the combination pattern of the work and the obtained third time, a construction work planning system.
【請求項2】 ある特定されたまとまり作業に要する第
5の時間を、該まとまり作業に属する単位作業について
入力された開始時期と、各単位作業毎に求めた前記第4
の時間とに基づいて求める手段を有することを特徴とす
る請求項1の施工作業計画システム。
2. The method according to claim 1, wherein the fifth time required for the specified group work is a start time input for the unit work belonging to the group work, and the fourth time obtained for each unit work.
2. The construction work planning system according to claim 1, further comprising means for obtaining the time based on the time.
【請求項3】 前記第1の時間を求める手段は、作業対
象の情報の入力により特定した作業時間変動パラメータ
から各要素動作に要する前記第1の時間を求めることを
特徴とする請求項1の施工作業計画システム。
3. The apparatus according to claim 1, wherein said means for obtaining the first time obtains the first time required for each element operation from a work time variation parameter specified by inputting information on a work target. Construction work planning system.
【請求項4】 前記求めた要素作業に要する第3の時間
と、該要素作業に属する単位動作を行う作業員の作業時
間に相当する前記求めた第2の時間とに基づいて、作業
員の稼働率を算出する手段を有することを特徴とする請
求項1の施工作業計画システム。
4. Based on the obtained third time required for the element work and the obtained second time corresponding to the work time of the worker performing the unit operation belonging to the element work, 2. The construction work planning system according to claim 1, further comprising means for calculating an operation rate.
【請求項5】 施工装置に関連付けられた要素作業の前
記求めた第3の時間に基づいて該施工装置の稼働率を求
める手段と、道工具に関連付けられた単位動作の前記求
めた第2の時間に基づいて該道工具の稼働率を求める手
段とを有することを特徴とする請求項1の施工作業計画
システム。
5. A means for determining an operation rate of the construction device based on the determined third time of the element work associated with the construction device, and the determined second operation of the unit operation associated with the tool. 2. A construction work planning system according to claim 1, further comprising means for calculating an operation rate of said tool based on time.
JP36907597A 1997-12-26 1997-12-26 Execution work plan system Pending JPH11193631A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP36907597A JPH11193631A (en) 1997-12-26 1997-12-26 Execution work plan system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP36907597A JPH11193631A (en) 1997-12-26 1997-12-26 Execution work plan system

Publications (1)

Publication Number Publication Date
JPH11193631A true JPH11193631A (en) 1999-07-21

Family

ID=18493499

Family Applications (1)

Application Number Title Priority Date Filing Date
JP36907597A Pending JPH11193631A (en) 1997-12-26 1997-12-26 Execution work plan system

Country Status (1)

Country Link
JP (1) JPH11193631A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2003122888A (en) * 2001-10-18 2003-04-25 Tokyo Electron Ltd Staff assigning system and method
US7850071B2 (en) 2005-02-15 2010-12-14 Max Co., Ltd. Portable tool and work management data collection system
US7925359B2 (en) 2005-02-18 2011-04-12 Max Co., Ltd. Air compressor and work management data collection system

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2003122888A (en) * 2001-10-18 2003-04-25 Tokyo Electron Ltd Staff assigning system and method
US7850071B2 (en) 2005-02-15 2010-12-14 Max Co., Ltd. Portable tool and work management data collection system
US7925359B2 (en) 2005-02-18 2011-04-12 Max Co., Ltd. Air compressor and work management data collection system

Similar Documents

Publication Publication Date Title
Heravi et al. Production process improvement of buildings’ prefabricated steel frames using value stream mapping
Mattila et al. Comparison of linear scheduling model and repetitive scheduling method
JP4759580B2 (en) Plant construction simulation data creation method and system
JP2005242531A (en) Installation work management system utilizing 3d-cad
KR20000016851A (en) Production estimate management system
JP2011065626A (en) Apparatus and method for supporting plant construction planning
CN115187039A (en) Construction progress management method and system based on BIM
Dunlop et al. Planning, estimation and productivity in the lean concrete pour
Faza et al. Evaluation of rebar waste rate calculation model utilizing bim function: High rise building case study
JPH11193631A (en) Execution work plan system
JP4896832B2 (en) Process management system and method
JP2019169016A (en) Construction process optimizing system
JP2002355724A (en) Assembly-disassembly process design support device
JPH02130678A (en) Manufacture plan preparing device
Rulkens et al. Batch size optimization of a furnace and pre-clean area by using dynamic simulations
JP2004171484A (en) Automatic preparation device for production line information
JP2004110828A (en) Method and system for generating numerical control tool path on solid model
JP3104535B2 (en) How to determine the work allocation of the robot
Wandt et al. Simulation aided disturbance management in one-of-a-kind production on the assembly site
JP5519575B2 (en) Plant construction process creation support system, plant construction process creation support method and program
Sadeghi et al. A framework for simulating industrial construction processes
JP2007220027A (en) Module evaluation method and device
Cheung et al. Applying virtual reality to improve the construction logistics of high-rise modular integrated construction
Zheng et al. RETRACTED ARTICLE: Exposure Assessment for Roller Compacted Concrete Dam Construction Integrated Real-Time Location Information
KR20170002994A (en) Apparatus of managementing process for pipe