JPH11166285A - Forms for placing concrete - Google Patents

Forms for placing concrete

Info

Publication number
JPH11166285A
JPH11166285A JP35204197A JP35204197A JPH11166285A JP H11166285 A JPH11166285 A JP H11166285A JP 35204197 A JP35204197 A JP 35204197A JP 35204197 A JP35204197 A JP 35204197A JP H11166285 A JPH11166285 A JP H11166285A
Authority
JP
Japan
Prior art keywords
concrete
base
formwork
slab
reinforcing
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP35204197A
Other languages
Japanese (ja)
Inventor
Toshio Suzuki
敏夫 鈴木
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Taisei Corp
Original Assignee
Taisei Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Taisei Corp filed Critical Taisei Corp
Priority to JP35204197A priority Critical patent/JPH11166285A/en
Publication of JPH11166285A publication Critical patent/JPH11166285A/en
Pending legal-status Critical Current

Links

Landscapes

  • Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)

Abstract

PROBLEM TO BE SOLVED: To provide forms for placing concrete to simplify an arrangement work for support when a piping, a duct, or other apparatus are suspended for arrangement, and to prevent an arrangement place and variation thereof from limitation. SOLUTION: Forms for placing concrete comprise a base 11 formed of a steel; and a number of reinforcing members 12 welded on a concrete placing surface 11a of the base 11 at intervals in the direction of the surface and buried in placed concrete C. A number of through-holes 12a filled with the concrete C are formed in the reinforcing member 12 along the concrete placing surface 11a of the base 11.

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【発明の属する技術分野】本発明は、コンクリート造り
のスラブや壁等のコンクリート打設時に用いられる型枠
に関するものである。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a formwork used for placing concrete such as concrete slabs and walls.

【0002】[0002]

【従来の技術】従来、コンクリート造りのスラブや壁等
の施工方法、たとえば、コンクリートスラブの施工方法
として、木製型枠あるいは合板型枠を、下階に立設した
多数の支保工によって支持しつつ上記型枠を床面全面に
亘って設置し、この型枠上面に配筋を施した後にコンク
リートを所定厚さに打設し、このコンクリートの養生固
化後において、上記型枠を支保工とともに除去してコン
クリートスラブを構築する方法が知られている。そし
て、上記支保工は、打設されるコンクリートの重量によ
って上記型枠が撓むことを防止して、構築されるコンク
リートスラブ中のコンクリートと配筋された鉄筋との位
置関係のずれを抑制し、また、構築されるコンクリート
スラブの平滑度を確保するようにしている。
2. Description of the Related Art Conventionally, as a method of constructing concrete slabs and walls, for example, as a method of constructing concrete slabs, a wooden formwork or a plywood formwork is supported by a large number of erections standing on the lower floor. The above-mentioned formwork is installed over the entire floor surface, concrete is laid to a predetermined thickness after reinforcing the upper surface of the formwork, and after curing and solidification of the concrete, the formwork is removed together with the support. A method of constructing a concrete slab is known. And the shoring works to prevent the formwork from being bent by the weight of the concrete to be cast, and to suppress the displacement of the positional relationship between the concrete in the concrete slab to be constructed and the reinforcing bars arranged. Also, the smoothness of the concrete slab to be constructed is ensured.

【0003】ところで、このような木製型枠や合板型枠
を用いたコンクリートスラブの施工方法においては、施
工時に型枠を支持する多数の支保工を必要とすることか
ら、施工中のコンクリートスラブの下方が上記支保工に
よって占有されてしまい、施工中のコンクリートスラブ
の下方の階へ機器を搬入することができず、したがっ
て、上記コンクリートスラブの施工作業とその下方階に
おける諸作業とを並行して行なうことができないことか
ら、工期の長期化を招いているといった不具合がある。
In the method of constructing a concrete slab using such a wooden formwork or a plywood formwork, a large number of supports for supporting the formwork are required at the time of construction. The lower part is occupied by the above-mentioned support, and it is impossible to carry equipment to the floor below the concrete slab under construction.Therefore, the construction work of the concrete slab and various works on the lower floor are performed in parallel. Since it cannot be performed, there is a problem that the construction period is lengthened.

【0004】また、上記コンクリートスラブの下方に、
配管や空調用のダクトあるいはその他の機器を吊設する
場合には、その設置位置に対応して上記機器を取り付け
るためのサポートや固定金具を、コンクリートの打設時
に予め設置しておくか、あるいはこれらのサポートや固
定金具を固定するための埋込金物を、上記機器の設置位
置に対応させて予め埋設しておく必要がある。しかしな
がら、上記の従来のコンクリートスラブの施工方法にあ
っては、例えば設計変更等によって機器の設置位置が変
わったり、あるいは設置する機器の重量が変化した場合
には、上記サポートや固定金具あるいは埋込金物等の設
置位置および大きさ、スパン等もそれに応じてずらさな
ければならない。この際に、コンクリート打設前および
配筋施工前において、その移動および取り替えは容易に
行なうことができるものの、鉄筋を配筋した後にあって
は、この鉄筋を取り除いた後でなければ上記サポートや
固定金具あるいは埋込金物の移動を行なうことができ
ず、さらにコンクリート打設後においては、上記設置位
置のコンクリートを捌って上記サポートや固定金具ある
いは埋込金物を設置しなければならないために、その作
業が煩雑になるという問題点がある。特に、後者のコン
クリート打設後における機器の設置位置の変更に対して
は、大掛かりな作業となる。
Further, below the concrete slab,
If pipes or air conditioning ducts or other equipment are to be suspended, support or fixtures for mounting the above equipment in accordance with the installation position should be installed beforehand when casting concrete, or It is necessary to previously embed the metal fittings for fixing these supports and the fixing fittings in correspondence with the installation positions of the devices. However, in the above-mentioned conventional concrete slab construction method, when the installation position of the equipment is changed due to, for example, a design change, or the weight of the equipment to be installed is changed, the above-described support, fixing bracket, or embedding is required. The installation position and size of hardware and the like, the span, etc. must be shifted accordingly. At this time, it is easy to move and replace the concrete before placing concrete and before arranging the reinforcing bars, but after arranging the reinforcing bars, the above-mentioned support and It is not possible to move the fixing bracket or embedded metal, and after concrete casting, since the concrete at the installation position must be handled and the support, fixing metal or embedded metal must be installed, There is a problem that the work becomes complicated. In particular, it is a large-scale operation to change the installation position of the equipment after the concrete is poured.

【0005】このような不具合に対処すべく従来におい
ては、たとえば、図8〜図12に示すようなスラブの施
工方法が提案されている。
Conventionally, in order to cope with such a problem, there has been proposed a slab construction method as shown in FIGS.

【0006】これらの図に示すコンクリートスラブの施
工方法は、断面が波形の鋼板からなるデッキプレート1
を、構造物の梁間に掛け渡すようにして設置することに
より型枠を形成し、このデッキプレート1の所定位置
に、アンカーボルト2が突設された埋込金物3を設置し
て溶接等により固定するとともに、この埋込金物3とデ
ッキプレート1との間に、これらの隙間にコンクリート
が侵入することを防止するための詰め物4を設置し(図
8参照)、ついで、図9に示すように、上記デッキプレ
ート1の上方に鉄筋Tを配筋した後に、図10に示すよ
うにデッキプレート1の上面にコンクリートCを打設
し、このコンクリートCを養生固化させてコンクリート
スラブSを構築するものであり、上記デッキプレート1
は、構築されたコンクリートスラブSの構成部材として
残される。このような施工方法により、型枠となるデッ
キプレート1の耐力が大きいことにより、このデッキプ
レート1の撓みが抑制され、その分、下階との間に設け
られる支保工の数が減少し、あるいは不要となる結果、
下階の作業領域が拡大されることにより、下階でのある
程度の作業を、上方のコンクリートスラブSの施工作業
と並行して行なうことが可能となる。
The concrete slab construction method shown in these figures is based on a deck plate 1 made of a corrugated steel sheet.
Is formed so as to be bridged between the beams of the structure to form a formwork. At a predetermined position of the deck plate 1, an embedded metal member 3 having an anchor bolt 2 protruded is installed and welded or the like. At the same time, a padding 4 for preventing concrete from entering these gaps is installed between the embedded metal member 3 and the deck plate 1 (see FIG. 8). Then, as shown in FIG. Then, after arranging a reinforcing bar T above the deck plate 1, concrete C is poured on the upper surface of the deck plate 1 as shown in FIG. 10, and the concrete C is cured and solidified to form a concrete slab S. The above deck plate 1
Is left as a constituent member of the constructed concrete slab S. According to such a construction method, since the strength of the deck plate 1 serving as a formwork is large, the bending of the deck plate 1 is suppressed, and accordingly, the number of supports provided between the deck floor and the lower floor is reduced, Or the unnecessary result,
By expanding the work area on the lower floor, it is possible to perform some work on the lower floor in parallel with the construction work on the concrete slab S above.

【0007】そして、配管やダクト等の機器を吊り下げ
るには、図11に示すように、デッキプレート1の上記
詰め物4が設置された部分を、コンクリートスラブSの
下方からの作業によって切断除去することにより、上記
アンカーボルト2によって上記コンクリートCと一体化
された埋込金物3を下方へ露出させ、次いでこの埋込金
物3に、図12に示すように、サポート5を溶接等によ
って固定し、これらの吊り金物5を利用して諸機器を前
記コンクリートCから吊り下げるようにしている。この
ように、上記機器を吊り下げる際に、コンクリートCと
一体化された埋込金物3を介して行なうようにしたの
は、上記デッキプレート1とコンクリートCとの接続強
度が小さく、上記デッキプレート1に直接機器を吊り下
げると、その重量によっては、デッキプレート1がコン
クリートCから剥離して撓んでしまうことが想定される
からである。
In order to suspend equipment such as pipes and ducts, the portion of the deck plate 1 where the padding 4 is installed is cut and removed by working from below the concrete slab S as shown in FIG. Thereby, the embedded metal 3 integrated with the concrete C is exposed downward by the anchor bolt 2, and then, as shown in FIG. 12, the support 5 is fixed to the embedded metal 3 by welding or the like. Various devices are hung from the concrete C using these hanging hardware 5. As described above, when the above-mentioned equipment is suspended, it is performed through the embedded hardware 3 integrated with the concrete C because the connection strength between the deck plate 1 and the concrete C is small, This is because if the device is directly suspended from the concrete C, the deck plate 1 is likely to peel off from the concrete C and bend depending on its weight.

【0008】[0008]

【発明が解決しようとする課題】ところで、このような
デッキプレート1を用いたコンクリートスラブSの施工
方法にあっても、配管やダクト等の機器を吊り下げるた
めの埋込金物3や、その下方へのコンクリートCの侵入
を阻止するための詰め物4を必要とし、またこの埋込金
物3を露出させるためには、この埋込金物3の取り付け
位置の確認作業と上記デッキプレート1の切断除去作業
を必要とし、さらにこの埋込金物3を露出させた後に、
この埋込金物3にサポート5を溶接しなければならず、
かつこれらの諸作業が上向き作業となるために、きわめ
て煩雑な作業となるといった問題点を有している。
By the way, even in the method of constructing a concrete slab S using such a deck plate 1, an embedded metal 3 for suspending equipment such as pipes and ducts, and an embedded metal 3 below. In order to prevent the intrusion of the concrete C into the padding 4, and to expose the embedded metal 3, it is necessary to confirm the mounting position of the embedded metal 3 and to cut and remove the deck plate 1. And after exposing this embedded metal part 3,
The support 5 must be welded to this embedded metal part 3,
In addition, since these operations are upward operations, there is a problem that the operations are extremely complicated.

【0009】また、上記機器の設置位置が変更された場
合においては、上記埋込金物3が上記デッキプレート1
に取り付けられた後であると、不用になった埋込金物3
を残したままで、変更位置に新たな埋込金物3を設置し
なければならないため、不用になった埋込金物3が無駄
になる。一方、コンクリートCを打設した後において、
改装等によって上記機器の設置位置を変更する必要が生
じた場合等には、その変更位置において上記デッキプレ
ート1を切断除去した後に、コンクリートCを捌って埋
込金物3を取り付ける必要があり、この場合においても
設置位置の変更作業が煩雑である。
Further, when the installation position of the equipment is changed, the embedded metal member 3 is attached to the deck plate 1.
After being attached to the, the embedded metal fittings 3
Since the new embedded hardware 3 must be installed at the changed position while keeping the, the unnecessary embedded hardware 3 is wasted. On the other hand, after placing concrete C,
When it is necessary to change the installation position of the device due to remodeling or the like, it is necessary to cut and remove the deck plate 1 at the changed position, then handle the concrete C and mount the embedded metal member 3, Also in this case, the operation of changing the installation position is complicated.

【0010】本発明は、このような従来のコンクリート
打設用型枠の有する課題を有効に解決すべくなされたも
ので、配管やダクトあるいはその他の機器の吊り下げ設
置する際に、サポート等の設置作業が簡便であり、か
つ、その設置場所およびその変更が制約されることのな
いコンクリート打設用型枠を提供することを目的とする
ものである。
SUMMARY OF THE INVENTION The present invention has been made to effectively solve the problems of the conventional concrete casting formwork, and has a structure such as a support for hanging a pipe, a duct or other equipment. An object of the present invention is to provide a concrete casting formwork in which installation work is simple and the installation place and its change are not restricted.

【0011】[0011]

【課題を解決するための手段】請求項1に記載のコンク
リート打設用型枠は、コンクリート打設後は、当該コン
クリートと一体化されて構造体の一部を構成する型枠で
あって、鋼板からなる基体と、この基体のコンクリート
打設面にその面方向に間隔をおいて溶接されるととも
に、打設されたコンクリート中に埋め込まれる多数の補
強部材とを備え、これらの補強部材に、上記基体のコン
クリート打設面に沿い、かつ、上記コンクリートが充満
させられる多数の貫通孔を形成してなることを特徴とす
るものである。そして、請求項2に記載の発明は、請求
項1に記載の上記補強部材に形成された貫通孔に鉄筋を
挿通してなることを特徴とするものである。
According to a first aspect of the present invention, there is provided a concrete casting formwork which is integrated with the concrete to form a part of a structure after the concrete is casted. A base made of a steel plate, and a large number of reinforcing members that are welded to the concrete casting surface of the base at intervals in the plane direction and are embedded in the cast concrete, and these reinforcing members include: A plurality of through holes are formed along the concrete casting surface of the base and filled with the concrete. The invention according to a second aspect is characterized in that a reinforcing bar is inserted through a through hole formed in the reinforcing member according to the first aspect.

【0012】また、請求項3に記載の発明は、請求項1
または請求項2に記載の上記基体や補強部材の寸法およ
び上記補強部材の設置数を、これらの基体および補強部
材によって構成される型枠が、打設されるコンクリート
の重量によって撓むことがなく、吊り下げられる機器、
配管重量に耐えられるとともに、竣工後の耐荷重の変動
に対しても対応可能な耐力に設定してなることを特徴と
するものである。
Further, the invention described in claim 3 is the first invention.
Alternatively, the dimensions of the base and the reinforcing member and the number of the reinforcing members according to claim 2 are reduced, and the formwork constituted by the base and the reinforcing member is not bent by the weight of the concrete to be cast. Equipment to be suspended,
It is characterized in that it is set to withstand the weight of the pipe and to withstand the fluctuation of the withstand load after completion.

【0013】請求項1〜請求項3のいずれかに記載の発
明によれば、基体のコンクリート打設面に一体に溶接さ
れた多数の補強部材を、打設されるコンクリート中に埋
設することにより、これらの補強部材を介して上記基体
とコンクリートとを一体化し、この結果上記基体とコン
クリートとの連結強度を、基体のほぼ全面に亘って強化
することができる。そして、上記のように基体とコンク
リートとの連結強度が基体のほぼ全面に亘って強化され
ていることにより、配管やダクトといった諸機器を基体
に取り付ける際に、基体のほぼ全面において、上記諸機
器の取り付けに対する強度を確保することができ、これ
によって上記諸機器の取り付け位置に対する制限が緩和
されるとともに、取り付け位置の変更に対しても容易に
対応することができる。
According to the present invention, a large number of reinforcing members integrally welded to the concrete casting surface of the base are buried in the concrete to be cast. The base and the concrete are integrated through these reinforcing members, and as a result, the connection strength between the base and the concrete can be strengthened over almost the entire surface of the base. And, as described above, since the connection strength between the base and the concrete is strengthened over almost the entire surface of the base, when attaching various devices such as pipes and ducts to the base, the above-described devices are almost completely covered with the base. Thus, the strength with respect to the mounting of the above-mentioned devices can be secured, whereby the restrictions on the mounting positions of the above-described devices can be relaxed, and changes in the mounting positions can be easily handled.

【0014】また、多数の補強部材によって上記基体の
剛性を高めて、コンクリート打設時における基体の撓み
を抑制し、これによって、基体を支持するための支保工
等の支持部材を不用にして、このコンクリート打設面と
反対側の面側における作業領域を十分に確保することが
でき、上記コンクリート打設作業と、その他方の面側に
おける諸作業とを並行して行なうことができる。
Further, the rigidity of the base is increased by a large number of reinforcing members to suppress the deflection of the base at the time of placing concrete, thereby eliminating the need for a support member such as a shoring for supporting the base. A sufficient working area on the side opposite to the concrete placing surface can be ensured, and the concrete placing operation and various operations on the other side can be performed in parallel.

【0015】ここで、請求項3に記載の発明のように、
基体や補強部材の寸法および上記補強部材の設置数を、
これらの基体および補強部材によって構成される型枠
が、打設されるコンクリートの重量によって撓むことが
なく、吊り下げられる機器、配管重量に耐えられるとと
もに、竣工後の耐荷重の変動に対しても対応可能な耐力
となるように設定することにより、コンクリート打設時
における基体の撓みを一層確実に防止することができる
のみならず、さらに吊り下げられる機器、配管重量に耐
えられるとともに、竣工後の耐荷重の変動に対しても対
応可能であるために、特に、大スパンのスラブ構築へも
容易に対応することができる。
Here, as in the invention according to claim 3,
The dimensions of the base and the reinforcing members and the number of the reinforcing members installed,
The formwork composed of these bases and reinforcing members does not bend due to the weight of the concrete to be cast, can withstand the weight of suspended equipment and piping, and withstand fluctuations in load capacity after completion. Not only can prevent the deflection of the base during concrete casting, but also can withstand the suspended equipment and the weight of the piping, and Since it is possible to cope with the fluctuation of the withstand load, it is possible to easily cope particularly with the construction of a slab having a large span.

【0016】[0016]

【発明の実施の形態】(第1の実施形態)図1〜図3は
本発明のコンクリート打設用型枠の第1の実施形態を示
すもので、建築物のスラブを構築する際に適用したもの
である。図1において符号10は本実施形態に係わるコ
ンクリート打設用型枠(以下、型枠と略称する)を示
し、この型枠10は、平鋼からなる基体11と、この基
体11の上面で、後述するコンクリートCが打設される
面(以下、コンクリート打設面11aと称す)に、この
コンクリート打設面11aに所定間隔をおいて平行に設
置されるとともに、上記基体11に溶接によって一体に
取り付けられた多数の補強部材12とを備えており、こ
れらの各補強部材12は、本実施形態においては、長尺
な平鋼によって形成され、その幅方向の一辺において上
記基体11に溶接されることにより、この基体11に対
して直交するように一体に立設されている。
DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS (First Embodiment) FIGS. 1 to 3 show a first embodiment of a concrete casting formwork according to the present invention, which is applied when building a slab of a building. It was done. In FIG. 1, reference numeral 10 denotes a concrete casting formwork (hereinafter abbreviated as a formwork) according to the present embodiment. The formwork 10 includes a base 11 made of flat steel and an upper surface of the base 11, A concrete C, which will be described later, is placed on a surface (hereinafter, referred to as a concrete placing surface 11a) parallel to the concrete placing surface 11a at a predetermined interval, and integrally with the base 11 by welding. In the present embodiment, each of the reinforcing members 12 is formed of a long flat steel, and is welded to the base 11 at one side in the width direction thereof. Thus, the base 11 is integrally provided so as to be orthogonal to the base 11.

【0017】また、上記各補強部材12は、その厚さ方
向に沿った貫通孔12aが、長さ方向に所定の間隔をお
いて多数形成されており、隣接する補強部材12に形成
された各貫通孔12aは、相互に同軸となるように形成
されているとともに、上記コンクリートCが打設された
際に、このコンクリートCが上記各貫通孔12a内に充
満されるようになされている。
Each of the reinforcing members 12 has a large number of through-holes 12a formed in the thickness direction thereof at predetermined intervals in the length direction. The through holes 12a are formed so as to be coaxial with each other, and when the concrete C is cast, the concrete C fills each of the through holes 12a.

【0018】このように構成された本実施形態に係わる
型枠10を用いてスラブ(S)を構築するには、まず、
上記基体11を、建築物の梁間に掛け渡すように設置し
た後に、図2に示すように、この基体11の補強部材1
2上にスラブ筋13を配筋し、ついで、上記基体11の
上部に、図3に示すように、コンクリートCを打設し、
このコンクリートCを養生固化させることによってスラ
ブSが構築される。
In order to construct a slab (S) using the formwork 10 according to the present embodiment configured as described above, first,
After the base 11 is installed so as to span between the beams of the building, as shown in FIG.
2, slab bars 13 are arranged thereon, and then concrete C is cast on the upper part of the base 11 as shown in FIG.
The slab S is constructed by curing and solidifying the concrete C.

【0019】このようにして構築されたスラブSにあっ
ては、上記基体11が、そのコンクリート打設面11a
に多数の補強部材12が一体に取り付けられてその剛性
が高められていることにより、打設されるコンクリート
Cの重量を支持できる剛性を確保することができ、この
結果上記基体11の撓みを抑制することができる。した
がって、コンクリートCの打設時において、上記基体1
1の下方に支保工等の支持部材を設置する必要がなくな
り、スラブSの下階に十分な作業領域を確保することが
でき、上記コンクリートCの打設作業と並行して、下階
の諸作業を行なうことができる。この結果、支保工等の
各種資材の使用量を軽減することができるとともに、工
期の短縮化を図ることができる。
In the slab S constructed in this manner, the base 11 is provided on the concrete casting surface 11a.
Since a large number of reinforcing members 12 are integrally attached to each other to increase the rigidity, the rigidity capable of supporting the weight of the concrete C to be cast can be secured, and as a result, the bending of the base 11 is suppressed. can do. Therefore, at the time of placing concrete C,
1, there is no need to install a support member such as a shoring, etc., so that a sufficient work area can be secured on the lower floor of the slab S. Can work. As a result, it is possible to reduce the amount of use of various materials such as support and the like, and to shorten the construction period.

【0020】一方、打設したコンクリートCの固化後に
おいては、このコンクリートCが上記補強部材12の多
数の貫通孔12a内に充満されて、これらの補強部材1
2とコンクリートCとが機械的に結合され、この結果、
上記基体11が上記多数の補強部材12を介して上記コ
ンクリートCと機械的に一体化され、このコンクリート
Cの接着力と相俟って、基体11がコンクリートCへ強
固に接合される。ここで、上記補強部材12が上記基体
11の面方向に所定間隔をおいて全面に亘って取り付け
られていることにより、上記基体11とコンクリートC
とが、基体11のほぼ全面に亘って強固に接合される。
On the other hand, after the cast concrete C is solidified, the concrete C fills the many through holes 12a of the reinforcing member 12, and the reinforcing members 1
2 and concrete C are mechanically connected, and as a result,
The base 11 is mechanically integrated with the concrete C via the plurality of reinforcing members 12, and the base 11 is firmly joined to the concrete C in combination with the adhesive force of the concrete C. Here, since the reinforcing member 12 is attached over the entire surface at a predetermined interval in the surface direction of the base 11, the base 11 and the concrete C
Are firmly joined over almost the entire surface of the base 11.

【0021】そして、スラブSの下方に、配管やダクト
あるいはその他の機器を吊設する必要が生じた場合に
は、これらの機器の設置位置に対応した上記基体11の
下面に、図3に示すように、サポート14を直接溶接等
によって垂設し、これらのサポート14に機器を取り付
けることによって行なうことができる。
When it becomes necessary to suspend pipes, ducts or other equipment below the slab S, the lower surface of the base 11 corresponding to the installation positions of these equipment is shown in FIG. In this manner, the support 14 can be provided by hanging the support 14 directly by welding or the like, and attaching a device to the support 14.

【0022】ここで、上記基体11は、多数の補強部材
12を介して、そのほぼ全面に亘ってコンクリートCに
強固に接合されていることから、設置される機器の重量
に対して、基体11のほぼ全面に亘って支持強度を確保
することができ、この結果、上記機器の設置位置を、基
体11の任意の位置に設定することができる。したがっ
て、スラブSの施工後において、上記機器の設置位置を
設定することも可能であり、また、機器の設置位置を変
更する必要が生じた場合においても、その変更位置が制
限されるようなことがなく、自由な変更が可能である。
Here, the base 11 is firmly joined to the concrete C over substantially the entire surface thereof through a large number of reinforcing members 12, so that the base 11 has a small weight relative to the weight of the installed equipment. Can be secured over almost the entire surface of the base 11, and as a result, the installation position of the device can be set at an arbitrary position on the base 11. Therefore, after the slab S is installed, it is possible to set the installation position of the above-mentioned equipment, and when the installation position of the equipment needs to be changed, the change position is limited. There is no change and free change is possible.

【0023】(第2の実施形態)図4および図5は本発
明の第2の実施形態を示すもので、上記スラブ筋13を
設置する際において、下層のスラブ筋13を、上記各補
強部材12に形成されている貫通孔12aに挿通するよ
うにした点に特徴があり、このような構成とすることに
より、配筋の先組みに対応することができ、かつ打設さ
れるコンクリートCと上記補強部材12とが上記スラブ
筋13を介して機械的に結合し、これによって、上記基
体11とコンクリートCとの接合強度をさらに高めるこ
とができるとともに、スラブSの下方に設置される諸機
器の支持強度を高めて、その設置位置の設定や変更の自
由度をさらに高めることができる。
(Second Embodiment) FIGS. 4 and 5 show a second embodiment of the present invention. When the slab streaks 13 are installed, the lower slab streaks 13 are connected to the reinforcing members. It is characterized in that it is inserted into the through-hole 12a formed in the concrete 12, and by adopting such a configuration, it is possible to cope with the pre-assembly of the reinforcing bars, and to cope with the concrete C to be poured. The reinforcing member 12 is mechanically connected to the reinforcing member 12 via the slab bar 13, whereby the joining strength between the base 11 and the concrete C can be further increased, and various devices installed below the slab S , And the degree of freedom in setting and changing the installation position can be further increased.

【0024】なお、上記の実施形態において示した各構
成部材の諸形状や寸法等は種々変更可能である。例え
ば、上記実施形態においては、スラブSの構築に適用し
た例について示したが、壁の構築への適用も可能であ
り、また上記基体11や補強部材12の寸法や上記補強
部材12の設置数を、上記打設されるコンクリートCの
総重量および吊り下げる機器や配管の重量等を勘案し
て、このコンクリートCによって上記型枠10が撓むこ
とがなく、かつ吊り下げられる機器、配管重量に耐えら
れるとともに、竣工後の耐荷重の変動に対しても対応可
能な剛性が得られるように設定することにより、より長
いスパンのスラブSを支保工無しに構築することが可能
となる。
It should be noted that various shapes, dimensions, and the like of each component shown in the above embodiment can be variously changed. For example, in the above embodiment, an example in which the present invention is applied to the construction of the slab S has been described. However, the present invention is also applicable to the construction of a wall, and the dimensions of the base 11 and the reinforcing members 12 and the number of the reinforcing members 12 to be installed. In consideration of the total weight of the concrete C to be cast and the weight of the equipment and pipes to be hung, the concrete C does not bend the formwork 10 and the weight of the equipment and pipe to be hung. By setting so as to be able to withstand and obtain rigidity that can cope with fluctuations in load resistance after completion, a slab S having a longer span can be constructed without support.

【0025】また、上記の平板状の補強部材12に代え
て、図7の(a)〜(c)に示すように、断面形状がL
型、V型、あるいは、台形型の補強部材15・16・1
7とし、これらの補強部材15・16・17に、上記基
体11の面方向に沿った貫通孔15a・16a・17a
を形成しておくことも可能である。このような構成とす
ることにより、コンクリートCと基体11との、相互に
離間する方向への相対移動に際して、上記補強部材15
〜17とコンクリートCとの係合力を大きくして、上記
コンクリートCと基体11との接合強度を高めることが
できる。
In place of the flat reinforcing member 12, the cross-sectional shape is L, as shown in FIGS.
, V-shaped, or trapezoidal reinforcing member 15.16.1.
7, and through holes 15a, 16a, 17a extending in the surface direction of the base 11 are formed in the reinforcing members 15, 16, 17 respectively.
Can be formed in advance. With such a configuration, when the concrete C and the base 11 move relative to each other in a direction away from each other, the reinforcing member 15
17 to the concrete C, the joint strength between the concrete C and the base 11 can be increased.

【0026】さらに、上記基体11を平板状の鋼板によ
って形成した例について示したが、これに代えて、基体
11を波形鋼板によって形成することも可能であり、ま
た、上記平板状の補強部材12を格子状に組み上げるこ
とも可能であり、これによって、基体11自体あるいは
形成される型枠全体の剛性を一層高めることができる。
また、補強部材12に穿孔する貫通孔12aについて
も、スラブ筋13を挿通さない箇所については、例えば
千鳥状等にするなど自由な位置に穿設することが可能で
ある。
Further, although an example has been shown in which the base 11 is formed of a flat steel plate, the base 11 may be formed of a corrugated steel plate instead. Can be assembled in a lattice shape, whereby the rigidity of the base 11 itself or the entire formwork formed can be further increased.
Also, the through holes 12a formed in the reinforcing member 12 can be formed at any position where the slab streaks 13 are not inserted, such as in a staggered shape.

【0027】[0027]

【発明の効果】以上説明したように、請求項1〜請求項
3のいずれかに記載の発明によれば、基体のコンクリー
ト打設面に一体に取り付けた多数の補強部材によって上
記基体の剛性を高め、打設されるコンクリートの重量を
支持できる剛性を確保することができ、上記基体の撓み
を抑制することができ、コンクリートの打設時におい
て、上記基体を支持する支保工等の支持部材不用にし
て、基体の、コンクリート打設面と反対側に十分な作業
領域を確保することができ、これによって、上記コンク
リートの打設作業と並行して、他面側の諸作業を行なう
ことができ、資材の使用量を軽減することができるとと
もに、工期の短縮化を図ることができる。
As described above, according to any one of the first to third aspects of the present invention, the rigidity of the base is increased by a large number of reinforcing members integrally attached to the concrete casting surface of the base. The rigidity that can increase the weight of the concrete to be cast can be ensured, the deflection of the base can be suppressed, and a support member such as a shoring for supporting the base is not required when the concrete is poured. As a result, a sufficient working area can be secured on the side of the base opposite to the concrete casting surface, whereby various operations on the other surface can be performed in parallel with the concrete placing operation. In addition, the amount of materials used can be reduced, and the construction period can be shortened.

【0028】一方、打設されるコンクリートを上記補強
部材の多数の貫通孔内に充満させて、これらの補強部材
とコンクリートとの接合強度、すなわち、基体とコンク
リートとの接合強度を基体のほぼ全面に亘って高めるこ
とができ、よってスラブに、配管やダクトあるいはその
他の機器を取り付ける際に、設置される機器の重量に対
して、基体のほぼ全面に亘って支持強度を確保すること
ができ、この結果上記機器の設置位置を基体の任意の位
置に設定することができる。しかも、コンクリートの打
設後において、上記機器の設置位置を設定することも可
能であり、また、機器の設置位置を変更する必要が生じ
た場合においても、その変更位置が制限されることな
く、自由な変更が可能であるとともに、上記機器を設置
する際に、基体を切断するといった作業を必要とせず、
上記基体へ直接溶接するといった簡便な作業で機器の設
置が可能になる。
On the other hand, the concrete to be poured is filled in the many through holes of the reinforcing member, and the bonding strength between the reinforcing member and the concrete, that is, the bonding strength between the base and the concrete, is increased over almost the entire surface of the base. Therefore, when attaching pipes, ducts or other equipment to the slab, the supporting strength can be secured over almost the entire surface of the base body with respect to the weight of the equipment to be installed, As a result, the installation position of the device can be set to an arbitrary position on the base. Moreover, after the concrete is poured, it is also possible to set the installation position of the device, and even when it is necessary to change the installation position of the device, the change position is not limited, Free change is possible, and when installing the above equipment, there is no need to work such as cutting the base,
Equipment can be installed by a simple operation such as direct welding to the base.

【0029】ここで、請求項2に記載の発明のように、
補強部材に形成した貫通孔に、コンクリート中に埋め込
まれる鉄筋の一部を挿通させておくことにより、上記基
体とコンクリートとの接合強度を一層高めて、上記基体
に取り付けられる諸機器の支持強度を高めることができ
るとともに、配筋の先組によりそのユニット化も図るこ
とが可能になり、さらに請求項3に記載の発明のよう
に、基体や補強部材の寸法および上記補強部材の設置数
を、これらの基体および補強部材によって構成される上
記型枠が、打設されるコンクリートの重量によって撓む
ことがなく、かつ吊り下げられる機器、配管重量に耐え
られるとともに、竣工後の耐荷重の変動に対しても対応
可能な耐力となるように設定することにより、より長い
スパンのコンクリート打設を支保工なしに施工すること
ができるといった効果が得られる。
Here, as in the invention according to claim 2,
By inserting a part of the reinforcing bar embedded in the concrete into the through hole formed in the reinforcing member, the joining strength between the base and the concrete is further increased, and the supporting strength of various devices attached to the base is increased. As well as being able to increase, it is also possible to achieve unitization by the pre-assembly of the reinforcing bars, and further, as in the invention according to claim 3, the dimensions of the base and the reinforcing member and the number of the reinforcing members to be installed are reduced. The formwork composed of these bases and reinforcing members does not bend due to the weight of the concrete to be cast, and can withstand the suspended equipment and the weight of the piping. By setting it to be able to handle the strength of concrete, it is possible to cast concrete with a longer span without support. It is obtained.

【図面の簡単な説明】[Brief description of the drawings]

【図1】本発明の第1の実施形態に係わるコンクリート
打設用型枠を示す縦断面図である。
FIG. 1 is a longitudinal sectional view showing a concrete casting formwork according to a first embodiment of the present invention.

【図2】本発明の第1の実施形態に係わるコンクリート
打設用型枠を用いたスラブ構築時の工程図である。
FIG. 2 is a process diagram when a slab is constructed using a concrete casting formwork according to the first embodiment of the present invention.

【図3】本発明の第1の実施形態に係わるコンクリート
打設用型枠を用いて構築したスラブの縦断面図である。
FIG. 3 is a longitudinal sectional view of a slab constructed using the concrete casting formwork according to the first embodiment of the present invention.

【図4】本発明の第2の実施形態に係わるコンクリート
打設用型枠を示す外観斜視図である。
FIG. 4 is an external perspective view showing a concrete casting formwork according to a second embodiment of the present invention.

【図5】本発明の第2の実施形態に係わるコンクリート
打設用型枠を用いたスラブ構築時の工程図である。
FIG. 5 is a process chart at the time of slab construction using a concrete casting formwork according to a second embodiment of the present invention.

【図6】本発明の第2の実施形態に係わるコンクリート
打設用型枠を用いて構築したスラブの縦断面図である。
FIG. 6 is a longitudinal sectional view of a slab constructed using a concrete casting formwork according to a second embodiment of the present invention.

【図7】本発明の変形例を示すもので、(a)〜(c)
は補強部材の縦断面図である。
FIG. 7 shows a modified example of the present invention, in which (a) to (c).
Is a longitudinal sectional view of a reinforcing member.

【図8】従来のコンクリート打設用型枠の一例を示す縦
断面図である。
FIG. 8 is a longitudinal sectional view showing an example of a conventional concrete casting mold.

【図9】図8に示すコンクリート打設用型枠を用いたス
ラブ構築時の工程図である。
9 is a process chart at the time of slab construction using the concrete casting formwork shown in FIG. 8;

【図10】図8に示すコンクリート打設用型枠を用いて
構築したスラブの縦断面図である。
FIG. 10 is a longitudinal sectional view of a slab constructed using the concrete casting formwork shown in FIG. 8;

【図11】図8に示すコンクリート打設用型枠を用いて
構築したスラブに、諸機器を取り付ける際に実施される
基体の処理状態を示す縦断面図である。
FIG. 11 is a vertical cross-sectional view showing a processing state of a base body performed when attaching various devices to a slab constructed using the concrete casting formwork shown in FIG.

【図12】図8に示すコンクリート打設用型枠を用いて
構築したスラブに、諸機器を取り付ける際に実施される
基体の処理状態を示す縦断面図である。
FIG. 12 is a longitudinal sectional view showing a processing state of a base body performed when attaching various devices to a slab constructed using the concrete casting formwork shown in FIG. 8;

【符号の説明】[Explanation of symbols]

10 (コンクリート打設用)型枠 11 基体 11a コンクリート打設面 12・15・16・17 補強部材 12a・15a・16a・17a 貫通孔 13 スラブ筋(鉄筋) 14 サポート Reference Signs List 10 Formwork (for concrete casting) 11 Base 11a Concrete casting surface 12, 15, 16, 17 Reinforcement member 12a, 15a, 16a, 17a Through hole 13 Slab bar (rebar) 14 Support

Claims (3)

【特許請求の範囲】[Claims] 【請求項1】 コンクリート打設後は当該コンクリート
と一体化されて構造体の一部を構成する型枠であって、
鋼板からなる基体と、この基体のコンクリート打設面に
その面方向に間隔をおいて溶接されるとともに、打設さ
れたコンクリート中に埋め込まれる多数の補強部材とを
備え、これらの補強部材に、上記基体のコンクリート打
設面に沿い、かつ上記コンクリートが充満させられる多
数の貫通孔を形成してなることを特徴とするコンクリー
ト打設用型枠。
1. A formwork that is integrated with the concrete after casting and forms a part of the structure,
A base made of a steel plate, and a large number of reinforcing members that are welded to the concrete casting surface of the base at intervals in the plane direction and are embedded in the cast concrete, and these reinforcing members include: A concrete casting formwork comprising a plurality of through holes formed along the concrete casting surface of the base and filled with the concrete.
【請求項2】 上記補強部材に形成された貫通孔に鉄筋
を挿通してなることを特徴とする請求項1に記載のコン
クリート打設用型枠。
2. The concrete casting formwork according to claim 1, wherein a reinforcing bar is inserted through a through hole formed in the reinforcing member.
【請求項3】 上記基体や補強部材の寸法および上記補
強部材の設置数を、これらの基体および補強部材によっ
て構成される上記型枠が、打設されるコンクリートの重
量によって撓むことがなく、吊り下げられる機器、配管
重量に耐えられるとともに、竣工後の耐荷重の変動に対
しても対応可能な耐力に設定してなることを特徴とする
請求項1または請求項2に記載のコンクリート打設用型
枠。
3. The dimensions of the base and the reinforcing member and the number of the reinforcing members installed are such that the formwork constituted by the base and the reinforcing member does not bend due to the weight of the concrete to be cast. 3. The concrete casting according to claim 1 or 2, wherein the concrete pouring is set so as to be able to withstand the suspended equipment and the weight of the pipe and to cope with fluctuations in the withstand load after completion. Formwork.
JP35204197A 1997-12-05 1997-12-05 Forms for placing concrete Pending JPH11166285A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP35204197A JPH11166285A (en) 1997-12-05 1997-12-05 Forms for placing concrete

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP35204197A JPH11166285A (en) 1997-12-05 1997-12-05 Forms for placing concrete

Publications (1)

Publication Number Publication Date
JPH11166285A true JPH11166285A (en) 1999-06-22

Family

ID=18421384

Family Applications (1)

Application Number Title Priority Date Filing Date
JP35204197A Pending JPH11166285A (en) 1997-12-05 1997-12-05 Forms for placing concrete

Country Status (1)

Country Link
JP (1) JPH11166285A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2015161081A (en) * 2014-02-26 2015-09-07 ドーエイ外装有限会社 Joint plate for floor
JP2020084547A (en) * 2018-11-22 2020-06-04 株式会社ハナミズキ・ブリッジ・プランニング Steel floor slab pavement structure

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2015161081A (en) * 2014-02-26 2015-09-07 ドーエイ外装有限会社 Joint plate for floor
JP2020084547A (en) * 2018-11-22 2020-06-04 株式会社ハナミズキ・ブリッジ・プランニング Steel floor slab pavement structure

Similar Documents

Publication Publication Date Title
KR101849940B1 (en) Bracket structure and construction method there of
JP6691007B2 (en) Formwork unit and basic insulation method
JP2014190116A (en) Construction method of concrete slab
JPH11166285A (en) Forms for placing concrete
JP2754369B2 (en) Rebar unit for void slab of building structure
JP2004116059A (en) Method of building corrugated steel plate web bridge
JP2714763B2 (en) Construction method of reinforced concrete structure
JP3004242B2 (en) Building material for vibration control, vibration control structure and construction method
JP2002047796A (en) Sleeve fixture and method for forming through hole
KR100743729B1 (en) Reinforcing apparatus for head of steel pipe pile
JP2000248739A (en) Sleeve fixture
JP3059428B1 (en) Embedding method of form member and anchor member used therefor
JP7269807B2 (en) Rooftop facility foundation structure and its construction method
JP3849234B2 (en) Reinforced concrete underground outer wall construction method
JP2004003168A (en) Fixing metal fitting of concrete form
JP2938386B2 (en) Construction method of formwork for residential foundation
JP2002303043A (en) Method for fixing sleeve for pipe arrangement, and sleeve fixture
JP2000320035A (en) Form-cum-thermal insulating material, method for constructing concrete skeleton having the form-cum- heat insulating material, and structure provided with the concrete skeleton
JPH10299002A (en) Form fixing structure for precast reinforced concrete footing
JP2024090740A (en) Anchor mounting method
JPH10204897A (en) Joining method of precast-concrete foundation block
JP2000257078A (en) Construction method of mat foundation to use pc foundation beam member and pc support frame for pc foundation beam member
JPH0874381A (en) Reinforcement unit and construction method of reinforced concrete-made building using the same
JP2007332728A (en) Earthquake-resisting wall setting structure
JP3487934B2 (en) Trench for laying piping and method of construction