JP2004116059A - Method of building corrugated steel plate web bridge - Google Patents
Method of building corrugated steel plate web bridge Download PDFInfo
- Publication number
- JP2004116059A JP2004116059A JP2002278838A JP2002278838A JP2004116059A JP 2004116059 A JP2004116059 A JP 2004116059A JP 2002278838 A JP2002278838 A JP 2002278838A JP 2002278838 A JP2002278838 A JP 2002278838A JP 2004116059 A JP2004116059 A JP 2004116059A
- Authority
- JP
- Japan
- Prior art keywords
- corrugated steel
- slab
- precast
- construction
- block
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Images
Abstract
Description
【0001】
【発明の属する技術分野】
本願発明は、波形鋼板ウェブ橋を張出し施工により所定長のブロック毎に架設する方法に関するものである。
【0002】
【従来の技術】
波形鋼板ウェブ橋は、上床版と下床版とこれらを連結する複数の波形鋼板とで箱形断面を形成するようにして橋軸方向に延びる構成となっているが、この波形鋼板ウェブ橋の架設は、一般に、張出し施工により所定長のブロック毎に行われるようになっている。
【0003】
その際、波形鋼板を利用した架設方法も採用されている(例えば「非特許文献1」参照)。この架設方法においては、上床版未施工の先頭ブロックを構成する複数の波形鋼板に、下床版施工用の吊り支保工を吊り下げた状態で、先頭ブロックの次のブロックを構成する複数の波形鋼板を先行架設した後、これら先行架設された波形鋼板に吊り支保工を移動させ、この状態で、次のブロックを構成する下床版の施工と先頭ブロックを構成する上床版の施工とを行うようになっている。
【0004】
【非特許文献1】
「プレストレストコンクリート」、社団法人プレストレストコンクリート技術協会、平成14年1月31日、第44巻、第1号、p.55
−57
【発明が解決しようとする課題】
このように上床版と下床版とを別ブロックで並行して施工することにより施工効率を高めることができるが、これら上床版および下床版の施工自体は、型枠を用いた現場打ち施工で行われている。
【0005】
その際、下床版の施工に関しては、吊り支保工の利用により、ある程度効率良く行うことが可能であるが、上床版の施工に関しては、次のような問題がある。
【0006】
すなわち、上床版の箱形断面部分については、下床版から支保工を立てて施工が行われており、また、上床版の張出床版部分については、すでに施工済みの張出床版部分から架設用の梁を張り出して施工が行われている。したがって、これらの点においてまだ施工が面倒なものとなっており、工費削減および工期短縮を図る上で不十分である、という問題がある。
【0007】
本願発明は、このような事情に鑑みてなされたものであって、波形鋼板を利用した波形鋼板ウェブ橋の架設方法において、下床版の施工のみならず上床版の施工に関しても施工の簡素化を図ることができる波形鋼板ウェブ橋の架設方法を提供することを目的とするものである。
【0008】
【課題を解決するための手段】
本願発明は、上床版の施工を所定のプレキャストリブおよびプレキャスト板を用いて行うことにより、上記目的達成を図るようにしたものである。
【0009】
すなわち、本願発明に係る波形鋼板ウェブ橋の架設方法は、
上床版と下床版とこれらを連結する複数の波形鋼板とで箱形断面を形成するようにして橋軸方向に延びる波形鋼板ウェブ橋を、張出し施工により所定長のブロック毎に架設する方法において、
上床版未施工の先頭ブロックを構成する複数の波形鋼板に、下床版施工用の吊り支保工を吊り下げた状態で、上記先頭ブロックの次のブロックを構成する複数の波形鋼板を先行架設した後、これら先行架設された波形鋼板に上記吊り支保工を移動させ、この状態で、上記次のブロックを構成する下床版の施工と上記先頭ブロックを構成する上床版の施工とを行うように構成されており、
上記上床版の施工が、複数のプレキャストリブを橋軸方向に所定間隔をおいて上記複数の波形鋼板の上端部間に架け渡すとともに、これらプレキャストリブの上に複数のプレキャスト板を敷設した後、これらプレキャストリブおよびプレキャスト板を型枠として上床版コンクリートを打設することにより行われるように構成されている、ことを特徴とするものである。
【0010】
上記「プレキャストリブ」は、複数の波形鋼板の上端部間に架け渡すことができるように構成されたものであれば、その具体的な形状や設置本数等については特に限定されるものではない。
【0011】
上記「プレキャスト板」は、該プレキャスト板をプレキャストリブの上に敷設することにより、上床版コンクリートを打設するための型枠を形成することができるものであれば、その具体的な形状や敷設枚数等については特に限定されるものではない。
【0012】
【発明の作用効果】
上記構成に示すように、本願発明に係る波形鋼板ウェブ橋の架設方法は、上床版未施工の先頭ブロックを構成する複数の波形鋼板に、下床版施工用の吊り支保工を吊り下げた状態で、先頭ブロックの次のブロックを構成する複数の波形鋼板を先行架設した後、これら先行架設された波形鋼板に吊り支保工を移動させ、この状態で、次のブロックを構成する下床版の施工と先頭ブロックを構成する上床版の施工とを行うようになっているので、上床版と下床版とを別ブロックで並行して施工することができ、これにより施工効率を高めることができる。また、吊り支保工の利用により、下床版の施工をある程度効率良く行うことができる。
【0013】
特に本願発明においては、上床版の施工が、複数のプレキャストリブを橋軸方向に所定間隔をおいて複数の波形鋼板の上端部間に架け渡すとともに、これらプレキャストリブの上に複数のプレキャスト板を敷設した後、これらプレキャストリブおよびプレキャスト板を型枠として上床版コンクリートを打設することにより行われるようになっているので、従来のように下床版から支保工を立てるとともに施工済みの張出床版部分から架設用の梁を張り出して上床版の施工を行うのに比して、上床版の施工を容易に行うことができる。
【0014】
このように本願発明によれば、波形鋼板を利用した波形鋼板ウェブ橋の架設方法において、下床版の施工のみならず上床版の施工に関しても施工の簡素化を図ることができる。そしてこれにより、一層の工費削減および工期短縮を図ることができる。
【0015】
上記構成において、複数の波形鋼板を、橋軸直交方向に所定間隔をおいて3箇所以上に設けるとともに、各プレキャストリブを、複数の波形鋼板のうち互い隣接する波形鋼板相互間に架け渡すようにすれば、上床版の幅員が大きい場合においても、各プレキャストリブの重量が過大にならないようにすることができ、これにより上床版の施工容易化を維持することができる。
【0016】
【発明の実施の形態】
以下、図面を用いて、本願発明の実施の形態について説明する。
【0017】
図1は、本願発明の一実施形態に係る架設方法の適用対象となる波形鋼板ウェブ橋10を架設途中の状態で示す斜視図である。
【0018】
図示のように、この波形鋼板ウェブ橋10は、上床版12と下床版14とこれらを連結する左右1対の波形鋼板16とで箱形断面を形成するようにして橋軸方向に延びている。各波形鋼板16は、波形鋼板本体16Aと、その上下両端部に接合された上端フランジ部16Bおよび下端フランジ部16Cとからなっている。そして、この波形鋼板ウェブ橋10は、張出し施工により所定長のブロック毎に架設されるようになっている。
【0019】
同図は、先頭ブロックB(n)の手前側のブロックB(n−1)の架設が完了した時点における波形鋼板ウェブ橋10を示すものであり、この時点では、先頭ブロックB(n)は、下床版14および両波形鋼板16については施工が完了した状態となっているが、上床版12については施工がまだ行われていない状態となっている。
【0020】
図2は、波形鋼板ウェブ橋10の架設工程を示す斜視図である。また、図3および4は、この架設工程を示す側面図および橋軸直交断面図である。なお、図4は、先頭ブロックB(n)における橋軸直交断面図である。また、図3および4における(a)〜(d)の各工程は、図2の(a)〜(d)の各工程に対応したものとなっている。
【0021】
波形鋼板ウェブ橋10の架設は、次のようにして行われるようになっている。
【0022】
まず、図1に示すように、上床版未施工の先頭ブロックB(n)を構成する1対の波形鋼板16に、簡易型枠102が取り付けられた下床版施工用の吊り支保工100を吊り下げた状態で、図2(a)に示すように、先頭ブロック(n)の次のブロックB(n+1)を構成する1対の波形鋼板16を先行架設する。これら各波形鋼板16の先行架設は、クレーン等を用いて行う。
【0023】
次に、図2(b)に示すように、先行架設された1対の波形鋼板16に吊り支保工100を移動させ、これを次のブロックB(n+1)の位置に据え付ける。
そして、先頭ブロックB(n)の上床版12を構成する複数のプレキャストリブ22を、橋軸方向に所定間隔をおいて両波形鋼板16の上端部間に架け渡して橋軸直交方向に延びるように配置する。
【0024】
この配置が完了したら、図2(c)に示すように、これらプレキャストリブ22の上に複数のプレキャスト板24を敷設し、これらプレキャスト板24の上に鉄筋および上床版横締め鋼材を配置する。また、これと並行して、次のブロックB(n+1)の簡易型枠102上において、下床版14の鉄筋組立てを行う。
【0025】
そして、図2(d)に示すように、先頭ブロックB(n)において、プレキャストリブ22およびプレキャスト板24を型枠として上床版コンクリート26を打設するとともに、次のブロックB(n+1)において下床版コンクリート28を打設し、その養生を図る。その後、先頭ブロックB(n)において、上床版横締め鋼材30にプレストレスを導入して上床版コンクリート26の横締め緊張を行うとともに、外ケーブルの挿入および緊張を行う。
【0026】
以上の工程により先頭ブロックB(n)の架設が完了したら、同様の工程により次のブロックB(n+1)の架設を行い、以後同様にして張出し施工による架設を行う。
【0027】
以上詳述したように、本実施形態に係る波形鋼板ウェブ橋10の架設方法は、上床版未施工の先頭ブロックB(n)を構成する1対の波形鋼板16に、下床版施工用の吊り支保工100を吊り下げた状態で、先頭ブロックB(n)の次のブロックB(n+1)を構成する1対の波形鋼板16を先行架設した後、これら先行架設された波形鋼板16に吊り支保工100を移動させ、この状態で、次のブロックB(n+1)を構成する下床版14の施工と先頭ブロックB(n)を構成する上床版12の施工とを行うようになっているので、上床版12と下床版14とを別ブロックで並行して施工することができ、これにより施工効率を高めることができる。また、吊り支保工100の利用により、下床版12の施工をある程度効率良く行うことができる。
【0028】
特に本実施形態においては、上床版12の施工が、複数のプレキャストリブ22を橋軸方向に所定間隔をおいて1対の波形鋼板16の上端部間に架け渡すとともに、これらプレキャストリブ22の上に複数のプレキャスト板24を敷設した後、これらプレキャストリブ22およびプレキャスト板24を型枠として上床版コンクリート26を打設することにより行われるようになっているので、従来のように下床版から支保工を立てるとともに施工済みの張出床版部分から架設用の梁を張り出して上床版の施工を行うのに比して、上床版12の施工を容易に行うことができる。
【0029】
このように本実施形態によれば、下床版14の施工のみならず上床版12の施工に関しても施工の簡素化を図ることができ、これにより一層の工費削減および工期短縮を図ることができる。
【0030】
上記実施形態においては、波形鋼板16を下床版14の橋軸直交方向両側部に1対設ける場合について説明したが、波形鋼板16を3箇所以上に設けるようにした場合においても、上記実施形態と同様の架設方法を採用することにより上記実施形態と同様の作用効果を得ることができる。
【0031】
図5は、上記実施形態の変形例を示す、図2と同様の図である。
【0032】
本変形例の架設対象となる波形鋼板ウェブ橋50は、上記実施形態の波形鋼板ウェブ橋10に比して、上床版12の幅員が大きいものとなっている。
【0033】
本変形例の架設方法も上記実施形態の架設方法と基本的に同様であるが、本変形例においては、波形鋼板16を下床版14の橋軸直交方向両側部および橋軸直交方向中央部の3箇所に設けるようになっている。また、本変形例においては、上記実施形態のプレキャストリブ22をその長手方向に関して2等分したようなプレキャストリブ22Aを用い、これら各プレキャストリブ22Aを橋軸直交方向両側部に位置する各波形鋼板16と橋軸直交方向中央部に位置する波形鋼板16との間に架け渡すようになっている。
【0034】
このような架設方法を採用することにより、波形鋼板ウェブ橋50のように、その上床版12の幅員が大きい場合においても、各プレキャストリブ22Aの重量が過大にならないようにすることができ、これにより上床版12の施工容易化を維持することができる。
【0035】
なお、波形鋼板16が橋軸直交方向に所定間隔をおいて4箇所以上に設けられる場合においても、上記実施形態のプレキャストリブ22をその長手方向に関して複数のプレキャストリブに分割し、これら分割された各プレキャストリブを互い隣接する波形鋼板相互間に架け渡すようにすれば、上記変形例と同様の作用効果を得ることができる。
【図面の簡単な説明】
【図1】本願発明の一実施形態に係る架設方法の適用対象となる波形鋼板ウェブ橋を、架設途中の状態で示す斜視図
【図2】上記波形鋼板ウェブ橋の架設工程を示す斜視図
【図3】上記架設工程を示す側面図
【図4】上記架設工程を示す橋軸直交断面図
【図5】上記実施形態の変形例を示す、図2と同様の図
【符号の説明】
10、50 波形鋼板ウェブ橋
12 上床版
14 下床版
16 波形鋼板
16A 波形鋼板本体
16B 上端フランジ部
16C 下端フランジ部
22、22A プレキャストリブ
24 プレキャスト板
26 上床版コンクリート
28 下床版コンクリート
30 上床版横締め鋼材
100 吊り支保工
102 簡易型枠
B(n−1) 手前側のブロック
B(n) 先頭ブロック
B(n+1) 次のブロック[0001]
TECHNICAL FIELD OF THE INVENTION
The present invention relates to a method of erection of a corrugated steel web bridge for each block of a predetermined length by overhanging construction.
[0002]
[Prior art]
The corrugated steel sheet web bridge is configured to extend in the bridge axis direction so as to form a box-shaped cross section with the upper deck, the lower deck, and a plurality of corrugated steel sheets connecting them, The erection is generally performed for each block of a predetermined length by overhanging construction.
[0003]
At that time, an erection method using a corrugated steel plate is also adopted (for example, see “Non-Patent
[0004]
[Non-patent document 1]
"Prestressed Concrete", Japan Prestressed Concrete Technology Association, Vol. 44, No. 1, January 31, 2002, p. 55
−57
[Problems to be solved by the invention]
The construction efficiency can be improved by constructing the upper slab and the lower slab in parallel in separate blocks as described above, but the construction of the upper slab and the lower slab itself is performed by cast-in-place using a formwork. It is done in.
[0005]
At that time, the construction of the lower slab can be performed to some extent efficiently by using the suspension support, but the construction of the upper slab has the following problems.
[0006]
In other words, for the box-shaped cross section of the upper slab, the support is erected from the lower slab, and the slab of the upper slab is installed. Construction work is being carried out by projecting beams for erection from. Therefore, the construction is still troublesome in these points, and there is a problem that it is insufficient to reduce the construction cost and the construction period.
[0007]
The present invention has been made in view of such circumstances, and in a method of erection of a corrugated steel sheet web bridge using corrugated steel sheets, simplification of construction not only for the construction of the lower slab but also for the construction of the upper slab. It is an object of the present invention to provide a method of erection of a corrugated steel sheet web bridge capable of achieving the following.
[0008]
[Means for Solving the Problems]
The invention of the present application is intended to achieve the above object by performing the construction of the upper floor slab using predetermined precast ribs and precast plates.
[0009]
That is, the method of erection of the corrugated steel web bridge according to the present invention is as follows.
In a method of erection of a corrugated steel sheet web bridge extending in the bridge axis direction so as to form a box-shaped cross section with an upper slab, a lower slab, and a plurality of corrugated steel sheets connecting them, by overhanging construction for each block of a predetermined length. ,
A plurality of corrugated steel sheets constituting the block next to the above-mentioned top block were erected in advance in a state in which the suspension support for the lower deck slab was suspended on the plurality of corrugated steel sheets constituting the top block without the upper slab. After that, the suspension support is moved to these pre-installed corrugated steel plates, and in this state, the construction of the lower slab constituting the next block and the construction of the upper slab constituting the top block are performed. Is composed of
The construction of the upper floor slab, while extending a plurality of precast ribs at predetermined intervals in the bridge axis direction between upper ends of the plurality of corrugated steel plates, and laying a plurality of precast plates on these precast ribs, The precast ribs and the precast plates are used as a formwork, and the upper floor slab concrete is cast to be formed.
[0010]
The specific shape and number of the “precast ribs” are not particularly limited as long as the “precast ribs” are configured so as to be able to be bridged between upper end portions of a plurality of corrugated steel plates.
[0011]
The above-mentioned "precast board" is a concrete form or laying as long as it can form a formwork for placing concrete on the upper slab by laying the precast board on the precast ribs. The number of sheets and the like are not particularly limited.
[0012]
Operation and Effect of the Invention
As shown in the above configuration, the method of erection of the corrugated steel sheet web bridge according to the invention of the present application is a method in which a plurality of corrugated steel sheets constituting the top block without the upper slab are suspended with the suspension support for the lower slab. Then, after a plurality of corrugated steel plates constituting the block next to the first block are erected in advance, the suspension supports are moved to these erected corrugated steel plates, and in this state, the lower floor slab constituting the next block is formed. Since the construction and the construction of the top floor slab constituting the top block are performed, the upper slab and the lower slab can be constructed in parallel in separate blocks, thereby increasing construction efficiency. . In addition, the use of the suspension shoring enables the construction of the lower slab to be performed to some extent efficiently.
[0013]
In particular, in the present invention, the construction of the upper floor slab, the plurality of precast ribs are bridged between the upper ends of the plurality of corrugated steel plates at predetermined intervals in the bridge axis direction, and a plurality of precast plates are placed on these precast ribs. After laying, these precast ribs and precast plates are used as the formwork to cast concrete on the upper floor slab. The construction of the upper slab can be performed more easily than the construction of the upper slab by projecting a beam for erection from the slab portion.
[0014]
As described above, according to the invention of the present application, in the method of erection of the corrugated steel sheet web bridge using the corrugated steel sheet, not only the construction of the lower floor slab but also the construction of the upper floor slab can be simplified. Thus, it is possible to further reduce the construction cost and the construction period.
[0015]
In the above configuration, a plurality of corrugated steel sheets are provided at three or more locations at predetermined intervals in a direction orthogonal to the bridge axis, and each precast rib is bridged between adjacent corrugated steel sheets among the plurality of corrugated steel sheets. Then, even when the width of the upper slab is large, it is possible to prevent the weight of each precast rib from becoming excessive, thereby maintaining the ease of construction of the upper slab.
[0016]
BEST MODE FOR CARRYING OUT THE INVENTION
Hereinafter, embodiments of the present invention will be described with reference to the drawings.
[0017]
FIG. 1 is a perspective view showing a state in which a corrugated
[0018]
As shown in the figure, the corrugated
[0019]
This figure shows the corrugated
[0020]
FIG. 2 is a perspective view showing a process of erection of the corrugated steel
[0021]
The erection of the corrugated
[0022]
First, as shown in FIG. 1, a
[0023]
Next, as shown in FIG. 2B, the
Then, the plurality of
[0024]
When this arrangement is completed, as shown in FIG. 2 (c), a plurality of
[0025]
Then, as shown in FIG. 2 (d), in the head block B (n), the upper
[0026]
When the erection of the first block B (n) is completed by the above steps, the erection of the next block B (n + 1) is performed by the same steps, and thereafter the erection by overhanging is performed in the same manner.
[0027]
As described in detail above, the method of erection of the corrugated steel
[0028]
In particular, in the present embodiment, the construction of the
[0029]
As described above, according to the present embodiment, not only the construction of the
[0030]
In the above embodiment, the case where a pair of
[0031]
FIG. 5 is a view similar to FIG. 2 and shows a modification of the above embodiment.
[0032]
The corrugated steel
[0033]
Although the erection method of this modification is basically the same as the erection method of the above embodiment, in this modification, the
[0034]
By adopting such an erection method, even when the width of the
[0035]
In addition, even when the
[Brief description of the drawings]
FIG. 1 is a perspective view showing a corrugated steel sheet web bridge to which a method of erection according to an embodiment of the present invention is applied, in a state of being erected. FIG. 2 is a perspective view showing a erection step of the corrugated steel sheet web bridge. FIG. 3 is a side view showing the erection step. FIG. 4 is a cross-sectional view orthogonal to the bridge axis showing the erection step. FIG. 5 is a view similar to FIG. 2 showing a modification of the embodiment.
10, 50 corrugated steel
Claims (2)
上床版未施工の先頭ブロックを構成する複数の波形鋼板に、下床版施工用の吊り支保工を吊り下げた状態で、上記先頭ブロックの次のブロックを構成する複数の波形鋼板を先行架設した後、これら先行架設された波形鋼板に上記吊り支保工を移動させ、この状態で、上記次のブロックを構成する下床版の施工と上記先頭ブロックを構成する上床版の施工とを行うように構成されており、
上記上床版の施工が、複数のプレキャストリブを橋軸方向に所定間隔をおいて上記複数の波形鋼板の上端部間に架け渡すとともに、これらプレキャストリブの上に複数のプレキャスト板を敷設した後、これらプレキャストリブおよびプレキャスト板を型枠として上床版コンクリートを打設することにより行われるように構成されている、ことを特徴とする波形鋼板ウェブ橋の架設方法。In a method of erection of a corrugated steel sheet web bridge extending in the bridge axis direction so as to form a box-shaped cross section with an upper slab, a lower slab, and a plurality of corrugated steel sheets connecting them, by overhanging construction for each block of a predetermined length. ,
A plurality of corrugated steel sheets constituting the block next to the above-mentioned top block were erected in advance in a state in which the suspension support for the lower deck slab was suspended on the plurality of corrugated steel sheets constituting the top block without the upper slab. After that, the suspension support is moved to these pre-installed corrugated steel plates, and in this state, the construction of the lower slab constituting the next block and the construction of the upper slab constituting the top block are performed. Is composed of
The construction of the upper floor slab, while extending a plurality of precast ribs at predetermined intervals in the bridge axis direction between upper ends of the plurality of corrugated steel plates, and laying a plurality of precast plates on these precast ribs, A method of erection of a web bridge of corrugated steel plates, wherein the method is carried out by placing concrete on the upper floor slab using the precast ribs and the precast plates as a formwork.
上記各プレキャストリブを、上記複数の波形鋼板のうち互い隣接する波形鋼板相互間に架け渡す、ことを特徴とする請求項1記載の波形鋼板ウェブ橋の架設方法。The plurality of corrugated steel sheets are provided at three or more locations at predetermined intervals in a direction orthogonal to the bridge axis,
The method for erection of a web bridge of corrugated steel sheets according to claim 1, wherein each of the precast ribs is bridged between adjacent ones of the plurality of corrugated steel sheets.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2002278838A JP3832651B2 (en) | 2002-09-25 | 2002-09-25 | Corrugated steel web bridge construction method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2002278838A JP3832651B2 (en) | 2002-09-25 | 2002-09-25 | Corrugated steel web bridge construction method |
Publications (2)
Publication Number | Publication Date |
---|---|
JP2004116059A true JP2004116059A (en) | 2004-04-15 |
JP3832651B2 JP3832651B2 (en) | 2006-10-11 |
Family
ID=32274011
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP2002278838A Expired - Lifetime JP3832651B2 (en) | 2002-09-25 | 2002-09-25 | Corrugated steel web bridge construction method |
Country Status (1)
Country | Link |
---|---|
JP (1) | JP3832651B2 (en) |
Cited By (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2008038449A (en) * | 2006-08-04 | 2008-02-21 | Sumitomo Mitsui Construction Co Ltd | Bridge girder constructing method |
JP2009144411A (en) * | 2007-12-13 | 2009-07-02 | Central Nippon Expressway Co Ltd | Moving work vehicle assembling/disassembling omission method for cantilever erection method, and corrugated steel plate for use in the same |
JP2009235835A (en) * | 2008-03-28 | 2009-10-15 | Sumitomo Mitsui Construction Co Ltd | Bridge construction method |
KR101083036B1 (en) | 2007-06-08 | 2011-11-16 | 삼성물산 주식회사 | Construction method for girder of bridge |
CN111321675A (en) * | 2020-04-17 | 2020-06-23 | 侯玉岗 | Precast concrete bridge deck paving method |
CN111395163A (en) * | 2020-04-17 | 2020-07-10 | 侯玉岗 | Precast concrete bridge deck pavement device of short T roof beam of assembled |
-
2002
- 2002-09-25 JP JP2002278838A patent/JP3832651B2/en not_active Expired - Lifetime
Cited By (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2008038449A (en) * | 2006-08-04 | 2008-02-21 | Sumitomo Mitsui Construction Co Ltd | Bridge girder constructing method |
KR101083036B1 (en) | 2007-06-08 | 2011-11-16 | 삼성물산 주식회사 | Construction method for girder of bridge |
JP2009144411A (en) * | 2007-12-13 | 2009-07-02 | Central Nippon Expressway Co Ltd | Moving work vehicle assembling/disassembling omission method for cantilever erection method, and corrugated steel plate for use in the same |
JP2009235835A (en) * | 2008-03-28 | 2009-10-15 | Sumitomo Mitsui Construction Co Ltd | Bridge construction method |
CN111321675A (en) * | 2020-04-17 | 2020-06-23 | 侯玉岗 | Precast concrete bridge deck paving method |
CN111395163A (en) * | 2020-04-17 | 2020-07-10 | 侯玉岗 | Precast concrete bridge deck pavement device of short T roof beam of assembled |
CN111395163B (en) * | 2020-04-17 | 2021-07-13 | 山东晟达新材料有限公司 | Precast concrete bridge deck pavement device of short T roof beam of assembled |
Also Published As
Publication number | Publication date |
---|---|
JP3832651B2 (en) | 2006-10-11 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
JP2019526004A (en) | Precast concrete formwork, floor system, and construction method | |
KR100728106B1 (en) | Cantilever construction structure of slab for bridge and the method thereof | |
JP2005083072A (en) | Joint structure and joint construction method for precast concrete slab | |
JP2014095256A (en) | Ribbed precast concrete plate, and method for separately placing concrete in composite floor slab and beam using the ribbed precast concrete plate | |
JP3701250B2 (en) | Cable stayed bridge and its construction method | |
KR101060566B1 (en) | Continuous method of multi-span PS beam using plate type tension material | |
JP2009030277A (en) | Construction method of composite steel floor slab girder bridge | |
JP2005105766A (en) | Removable support beam | |
JP4073746B2 (en) | Construction method of corrugated steel web bridge | |
JP2004116059A (en) | Method of building corrugated steel plate web bridge | |
JP4226399B2 (en) | How to build a bridge | |
JP2014190116A (en) | Construction method of concrete slab | |
JP5074260B2 (en) | Bridge erection method | |
JP2001200510A (en) | Method for constructing overhangingly erected bridge using corrugated steel plate web | |
JP3682520B2 (en) | PC steel wire anchorage structure in composite bridge girder | |
JP2000038797A (en) | Semi-precast floor slab | |
KR20020063451A (en) | Advanced TEC beam with unsymmetric steel section | |
JPH09221706A (en) | Floor slab for road surface and layout method thereof | |
JP2004232229A (en) | Precast concrete slab | |
JPH10110498A (en) | Half-precast floor slab and construction method of hollow flat slab making use thereof | |
JP2000038798A (en) | Semi-precast floor slab | |
JP2005016157A (en) | Precast concrete plate, slab, and method of constructing the slab | |
JPH03107047A (en) | Constructing method for slab | |
JP2000087313A (en) | Composite floor slab bridge and its erection method | |
JP2004137843A (en) | Join structure of column and beam |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
A621 | Written request for application examination |
Free format text: JAPANESE INTERMEDIATE CODE: A621 Effective date: 20040709 |
|
A977 | Report on retrieval |
Free format text: JAPANESE INTERMEDIATE CODE: A971007 Effective date: 20060622 |
|
TRDD | Decision of grant or rejection written | ||
A01 | Written decision to grant a patent or to grant a registration (utility model) |
Free format text: JAPANESE INTERMEDIATE CODE: A01 Effective date: 20060711 |
|
A61 | First payment of annual fees (during grant procedure) |
Free format text: JAPANESE INTERMEDIATE CODE: A61 Effective date: 20060712 |
|
R150 | Certificate of patent or registration of utility model |
Ref document number: 3832651 Country of ref document: JP Free format text: JAPANESE INTERMEDIATE CODE: R150 Free format text: JAPANESE INTERMEDIATE CODE: R150 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20090728 Year of fee payment: 3 |
|
S111 | Request for change of ownership or part of ownership |
Free format text: JAPANESE INTERMEDIATE CODE: R313114 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20090728 Year of fee payment: 3 |
|
R350 | Written notification of registration of transfer |
Free format text: JAPANESE INTERMEDIATE CODE: R350 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20090728 Year of fee payment: 3 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20120728 Year of fee payment: 6 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20120728 Year of fee payment: 6 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20150728 Year of fee payment: 9 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
S111 | Request for change of ownership or part of ownership |
Free format text: JAPANESE INTERMEDIATE CODE: R313117 |
|
S531 | Written request for registration of change of domicile |
Free format text: JAPANESE INTERMEDIATE CODE: R313531 |
|
R350 | Written notification of registration of transfer |
Free format text: JAPANESE INTERMEDIATE CODE: R350 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
EXPY | Cancellation because of completion of term |