JPH11148111A - Method for erecting bridge - Google Patents
Method for erecting bridgeInfo
- Publication number
- JPH11148111A JPH11148111A JP31343997A JP31343997A JPH11148111A JP H11148111 A JPH11148111 A JP H11148111A JP 31343997 A JP31343997 A JP 31343997A JP 31343997 A JP31343997 A JP 31343997A JP H11148111 A JPH11148111 A JP H11148111A
- Authority
- JP
- Japan
- Prior art keywords
- erection
- girder
- bridge
- work device
- building
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Landscapes
- Bridges Or Land Bridges (AREA)
Abstract
Description
【0001】[0001]
【発明の属する技術分野】本発明は、橋脚を中心にバラ
ンスを取り、左右交互または同時に橋桁プレキャストセ
グメントを接合してプレストレスを与えながら張り出し
て行く片持ち架設プレキャストセグメント工法による橋
梁の架設方法であり、特に、斜張橋やエクストラドーズ
ド橋のように支間長の長い橋梁における側径間の架設に
有効な橋梁の架設方法に関するものである。BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a method of erection of a bridge by a cantilever erection precast segment method which balances around a pier, and alternately or simultaneously joins precast segments of a bridge girder and projects while applying prestress. In particular, the present invention relates to a bridge erection method that is effective for erection of side spans in a bridge having a long span such as a cable-stayed bridge or an extra-dosed bridge.
【0002】[0002]
【従来の技術】プレキャストセグメント工法の代表的な
架設方法として、橋梁の中心にバランスを取り、左右交
互または同時に橋桁プレキャストセグメントを接合して
プレストレスを与えながら張り出して行く片持ち架設工
法(バランスドカンチレバー工法)があり、例えば架設
作業装置の違いにより次に示すような方式が採用されて
いる。2. Description of the Related Art As a typical erection method of the precast segment method, a cantilever erection method in which a bridge is balanced at the center of a bridge and alternately or simultaneously joined to a bridge girder precast segment to protrude while giving prestress (balanced method). There is a cantilever method, for example, and the following method is adopted depending on the difference of the erection work device.
【0003】(1) エレクションノーズ方式(特願平6−
274792号等) 通常の張出し架設においては、橋桁断面力、経済性等の
観点から、支間中央で閉合する方法が一般的であり、図
9(a) に示すようなエレクションノーズ(移動架設作業
車)50を用い、橋脚上から2台のエレクションノーズ
で左右のバランスを取りながら主桁を施工している。図
の右側における側径間においては、別途揚重機51を用
意し、端ピアから支間中央付近まで支保工52等の別の
設備を使って架設している。支保工が設置できない場合
には、ピロン柱(仮設柱)を立ててケーブルで引張支持
している。(1) Election nose method (Japanese Patent Application No.
In the normal overhanging construction, a method of closing at the center of the span is generally used from the viewpoint of the bridge girder cross-section force, economy, etc., and an erection nose (moving construction work vehicle) as shown in FIG. ) 50, the main girder is being constructed while balancing the left and right with two election nose from the pier. In the side span on the right side of the drawing, a separate lifting machine 51 is prepared and installed from the end pier to the vicinity of the center of the span using another facility such as a shoring 52. When a shoring cannot be installed, a pillar column (temporary column) is erected and supported by a cable.
【0004】(2) エレクションガーダー方式(特願平6
−284923号等) 本方式は、側径間架設等において、橋桁プレキャストセ
グメントを現地に直接運搬が不可能な場合等に採用さ
れ、通常、図9(b) に示すように、エレクションガーダ
ー60を他径間の既設橋桁等を利用して押し出し架設す
る。(2) Election girder system (Japanese Patent Application Hei 6
This method is used when it is not possible to directly transport the bridge girder precast segment to the site in the case of side span erection, etc. Usually, as shown in FIG. 9 (b), the erection girder 60 is used. It is extruded and erected using the existing bridge girder of another span.
【0005】[0005]
【発明が解決しようとする課題】エレクションノーズ方
式を、本発明が対象とする斜長橋等の側径間に適用した
場合、順張出し不可能区間(支保工、ピロン柱等を用い
た逆張出し区間)において移動式クレーンあるいは船上
クレーンを使用して橋桁プレキャストセグメントを吊り
上げて接合しなければならず、コストがかかり、迅速な
施工を行うことができない。When the erection nose method is applied to the side span of a sloped bridge or the like to which the present invention is applied, a section in which extension is impossible (a section in which a pier, a pillar, etc. In (1), a bridge girder precast segment must be lifted and joined using a mobile crane or a shipboard crane, which is costly and cannot be performed quickly.
【0006】また、エレクションガーダー方式でも、エ
レクションガーダーを一括架設できない場合には、組立
て・押出しスペースが必要となることと、各橋脚を支点
に橋桁を渡す構造であるため、エレクションガーダーの
桁長が最低でも支間長分必要になり、斜張橋のように支
間長が長い場合、通常の方法で押出しするのは不可能と
なる。そのため、エレクションガーダーの押出し可能な
スパンまでは、エレクションノーズ等の他の設備により
架設を行う必要があり、コストがかかり、迅速な施工を
行えない等の問題がある。In the case of the erection girder system, if the erection girder cannot be installed at one time, a space for assembling and pushing is required, and the bridge girder is passed around each pier as a fulcrum. At least the length of the span is required, and if the span is long, such as a cable-stayed bridge, it will not be possible to extrude in the usual way. For this reason, it is necessary to install the erection girder up to the span where the erection girder can be extruded by using other equipment such as an erection nose, which is costly and cannot be performed quickly.
【0007】本発明は、このような問題点を解消すべく
なされたもので、その目的は、斜張橋等のように支間長
が長い場合にも、一つの架設作業装置だけで片持ち架設
プレキャストセグメント工法による架設が可能となり、
コストの低減および施工の迅速化を図ることのできる橋
梁の架設方法を提供することにある。SUMMARY OF THE INVENTION The present invention has been made to solve such a problem, and an object of the present invention is to provide a single cantilever installation device using only one installation work device even when a span length is long, such as a cable-stayed bridge. Construction by the precast segment method is possible,
An object of the present invention is to provide a bridge erection method that can reduce costs and speed up construction.
【0008】[0008]
【課題を解決するための手段】上記目的を達成するた
め、本発明においては、工場またはヤードで製作された
橋桁プレキャストセグメントを接合してプレストレスを
与えながら橋脚を起点として張り出して行く片持ち架設
プレキャストセグメント工法による橋梁の架設方法にお
いて、架設ガーダーと脚フレームとセグメント吊上げ装
置からエレクションノーズ方式の架設作業装置を構成
し、この架設作業装置により前記橋脚から所定の位置ま
での架設を行い、次いで、前記移動架設作業装置の架設
ガーダーにガーダーを追加接続してエレクションガーダ
ー方式の架設作業装置を構成し、この架設作業装置によ
り残りの部分の架設を行う。In order to achieve the above object, according to the present invention, a cantilever erection that extends from a pier as a starting point while applying prestress by joining a bridge girder precast segment manufactured in a factory or a yard. In the method of erection of a bridge by the precast segment method, an erection nose type erection work device is configured from an erection girder, a leg frame, and a segment lifting device, and the erection work device performs erection from the pier to a predetermined position. A girder is additionally connected to the erection girder of the movable erection work device to form an erection girder type erection work device, and the remaining portion is erected by the erection work device.
【0009】また、エレクションノーズ方式の架設作業
装置をエレクションガーダー方式の架設作業装置に変え
る場合には、架設ガーダーに設置されたセグメント吊上
げ装置を用いてガーダーを吊上げて前記架設ガーダーに
追加接続する。追加接続するガーダーは単位長さのガー
ダーとし、このガーダーを吊上げて架設ガーダーに添わ
せ、片側の角部同士をピンで連結した後、180°回転
させて架設ガーダーの後方に接続し、この作業を順次繰
り返すことによりエレンクションガーダーを構成するの
が好ましい。Further, when the erection nose type erection work device is changed to an erection girder type erection work device, the girder is lifted using a segment lifting device installed on the erection girder and is additionally connected to the erection girder. The girder to be additionally connected is a girder of unit length, lift this girder and attach it to the erection girder, connect the corners on one side with pins, rotate it 180 ° and connect it to the back of the erection girder, Are preferably repeated to form an election girder.
【0010】以上のような構成において、順張出し可能
区間は、エレクションノーズ方式の架設作業装置で架設
が行われ、順張出し不可能区間(支保工、ピロン柱等を
用いた逆張出し区間)の手前で、前記エレクションノー
ズ方式の架設作業装置に架設ガーダーを追加接続して送
り出し、エレクションガーダー方式の架設作業装置で順
張出し不可能区間の架設が行われる。これにより、斜張
橋等のように支間長が長い場合にも、一つの架設作業装
置だけで片持ち架設プレキャストセグメント工法による
架設が可能となり、コストの低減および施工の迅速化を
図ることができる。In the above construction, the stretchable section is erected by an erection nose type erection work device, and is located just before the section where extension is not possible (reverse extension section using a pier, a pillar pillar, etc.). Then, an installation girder is additionally connected to the erection nose type erection work device and sent out, and the erection girder type erection work device is erected in a section where extension is impossible. As a result, even when the span length is long, such as a cable-stayed bridge, erection can be performed by the cantilever erection precast segment method with only one erection work device, and cost can be reduced and construction can be speeded up. .
【0011】[0011]
【発明の実施の形態】以下、本発明を図示する実施の形
態に基づいて説明する。これは斜張橋等の側径間の架設
に適用した例である。図1は、本発明の順張出し可能区
間でエレクションノーズ方式とした架設作業装置の一例
を示し、図2は、本発明の順張出し不可能区間でエレク
ションガーダー方式とした架設作業装置の一例を示した
ものである。図3〜図7は、本発明の架設方法の一例を
工程順に示したものである。図8は、本発明における架
設ガーダーの追加接続方法の一例を工程順に示したもの
である。DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS The present invention will be described below based on an embodiment shown in the drawings. This is an example in which the present invention is applied to erection of side spans such as a cable-stayed bridge. FIG. 1 shows an example of an erection work device of an erection nose type in a stretchable section of the present invention, and FIG. 2 shows an example of an erection girder method of an erection girder method in a stretchable non-extendable section of the present invention. It is a thing. 3 to 7 show an example of the erection method of the present invention in the order of steps. FIG. 8 shows an example of a method for additionally connecting an installation girder according to the present invention in the order of steps.
【0012】本発明において使用する架設作業装置1
は、図1に示すように、主として、単位長さの架設ガー
ダー2と、橋軸方向に一対の脚フレーム3と、橋桁プレ
キャストセグメントAの吊上げ装置4と、一対の作業足
場5などから構成されている。An installation work device 1 used in the present invention.
As shown in FIG. 1, it mainly comprises an installation girder 2 of unit length, a pair of leg frames 3 in the bridge axis direction, a lifting device 4 for the bridge girder precast segment A, a pair of work scaffolds 5, and the like. ing.
【0013】そして、架設当初の順張出し可能区間にお
いては、例えば単位長さのガーダーを2本接続してエレ
クションノーズ方式の架設作業装置1Aとし、順張出し
不可能区間においては、この架設作業装置1Aの架設ガ
ーダー2に単位長さのガーダーを順次追加接続して図2
に示すようなエレクションガーダー方式の架設作業装置
1Bとする。In the stretchable section at the beginning of the installation, for example, two girder units of unit length are connected to form an erection nose type erection work apparatus 1A. In the section where extension is impossible, the erection work apparatus 1A is used. The girder 2 of unit length is sequentially connected to the erection girder 2 of FIG.
An erection girder type erection work device 1B as shown in FIG.
【0014】架設ガーダー2は、橋軸直交方向に一対の
トラス桁2aを連結して構成され、各トラス桁2aの下
部に橋軸方向に一対の脚フレーム3がそれぞれ配設され
る。The erection girder 2 is constructed by connecting a pair of truss girders 2a in a direction orthogonal to the bridge axis, and a pair of leg frames 3 are respectively arranged below the truss girders 2a in the bridge axis direction.
【0015】脚フレーム3は、既に架設された橋桁の上
に設置された軌条桁6の上に移動自在に設置され、油圧
シリンダ等からなる移動装置7により移動する。脚フレ
ーム3の上部と架設ガーダー2とは、ロック・アンロッ
ク装置8により固定・固定解除可能とされている。従っ
て、脚フレーム3と架設ガーダー2を固定した状態で移
動装置7を作動させれば、エレクションノーズ方式の架
設作業装置1Aを移動させることができ、またエレクシ
ョンガーダー方式を行うに際して、脚フレーム3と架設
ガーダー2の固定を解除した状態で、移動装置7で脚フ
レーム3を盛替え移動させ、次いで脚フレーム3と架設
ガーダー2を固定した状態で移動装置7で架設ガーダー
2を前方に移動させ、これを繰り返すことで架設ガーダ
ー2を送り出すことができる。The leg frame 3 is movably installed on a rail girder 6 installed on a bridge girder that has already been erected, and is moved by a moving device 7 composed of a hydraulic cylinder or the like. The upper part of the leg frame 3 and the erection girder 2 can be fixed / unlocked by a lock / unlock device 8. Therefore, if the moving device 7 is operated in a state where the leg frame 3 and the erection girder 2 are fixed, the erection work device 1A of the erection nose type can be moved. In a state where the fixing of the erection girder 2 is released, the leg frame 3 is rearranged and moved by the moving device 7, and then the erection girder 2 is moved forward by the moving device 7 while the leg frame 3 and the erection girder 2 are fixed. By repeating this, the construction girder 2 can be sent out.
【0016】なお、これに限らず、脚フレーム3の上部
と架設ガーダー2との間に、電動ローラー、スライドジ
ャッキ等の送り装置を配設することもできるし、この送
り装置を脚フレーム3に装備せずに外部に設置すること
もできる。The present invention is not limited to this. A feeder such as an electric roller or a slide jack may be provided between the upper part of the leg frame 3 and the bridge girder 2. It can be installed outside without any equipment.
【0017】吊上げ装置4は、図1に示すように、橋軸
直交方向のクレーン桁4aと、2台のクラブトロリ4b
からなる橋形クレーンであり、クレーン桁4aが走行装
置9により架設ガーダー2の各トラス桁2aのレール上
を橋軸方向に走行する。クラブトロリ4bは、油圧ジャ
ッキなどの横行装置10によりクレーン桁4a上を橋軸
直交方向に横行可能とされ、橋桁プレキャストセグメン
トAの種々の幅に対応でき、かつ後述するように単位長
さの架設ガーダー2の追加接続を装置上で簡単に行える
ようにされている。なお、作業足場5は架設ガーダー2
の先端側に移動可能に垂設されている。As shown in FIG. 1, the lifting device 4 includes a crane girder 4a in a direction orthogonal to the bridge axis and two club trolleys 4b.
The crane girder 4a travels on the rail of each truss girder 2a of the erection girder 2 in the bridge axis direction by the traveling device 9. The club trolley 4b can be traversed on the crane girder 4a in a direction orthogonal to the bridge axis by a traversing device 10 such as a hydraulic jack, and can cope with various widths of the bridge girder precast segment A, and has a unit length as described later. Additional connections of the girder 2 can be made easily on the device. In addition, the work scaffold 5 is the construction girder 2
Is movably suspended at the distal end side of the camera.
【0018】以上のような構成の架設作業装置を使用し
て次のような手順で架設を行う(図3〜図7参照)。な
お、図において左側が本発明による架設方法であり、右
側は従来のエレクションノーズによる方法を示してい
る。Using the erection work apparatus having the above-described configuration, erection is performed in the following procedure (see FIGS. 3 to 7). In the drawings, the left side shows the method of erection according to the present invention, and the right side shows the conventional method using an erection nose.
【0019】(1) 橋脚Bの頭部のセグメント(または場
所打ち施工)および張出し部分の数セグメントを地上よ
り移動式クレーンにより架設する。橋桁プレキャストセ
グメントAは、架設地点まで、仮設道路等を用いてトレ
ーラーや他の搬送機により、あるいは運搬船により運搬
される。(1) The segment of the head of the pier B (or the cast-in-place construction) and several segments of the overhang portion are erected from the ground by a mobile crane. The bridge girder precast segment A is transported to a erection point using a temporary road or the like by a trailer or another transporter, or by a transport ship.
【0020】(2) 仮設作業装置の設置場所が確保された
段階で、地上の移動式クレーンまたは船上クレーンを用
いて軌条桁6、仮設ガーダー2、脚フレーム3、吊上げ
装置4、作業足場5等を橋桁上に設置して組立て、図3
(a) に示すように、エレクションノーズ方式の仮設作業
装置1Aを構成する。(2) When the installation place of the temporary work device is secured, the rail girder 6, the temporary girder 2, the leg frame 3, the lifting device 4, the work scaffold 5, etc., using a mobile crane or a shipboard crane on the ground. Is installed on the bridge girder and assembled, Fig. 3
As shown in (a), an erection nose type temporary work device 1A is configured.
【0021】(3) 支持架台11を撤去し、図3(b) に示
すように、軌条桁6を盛替え、脚フレーム3の移動装置
7で架設ガーダー2を前進させる。図3(c) に示すよう
に、先端側へ移動させた吊上げ装置4により例えばNo.
13の橋桁プレキャストセグメントAを吊上げて接合す
る。鋼棒の挿入、接合、緊張作業を作業足場5を利用し
て行う。この作業を複数回繰り返してエレクションノー
ズ方式の仮設作業装置1Aによる架設作業を終了する。(3) The support gantry 11 is removed, the rail girder 6 is replaced as shown in FIG. 3B, and the erection girder 2 is advanced by the moving device 7 for the leg frame 3. As shown in FIG. 3 (c), for example, No.
13 bridge girder precast segments A are lifted and joined. The work of inserting, joining, and tensioning the steel bars is performed using the work scaffold 5. This work is repeated a plurality of times, and the erection work by the erection nose temporary work device 1A is completed.
【0022】(4) 図4(b) に示すように、例えばNo.1
6の橋桁プレキャストセグメントAの接合が終了する
と、エレクションノーズ方式の仮設作業装置1Aの架設
ガーダー2の後方に単位長さのガーダーを順次追加接続
し、所定の間隔をおいて配設した支持架台11で支持す
る。この追加接続は、後述するように吊上げ装置4で行
う。なお、この追加接続は、これに限らず、地上の移動
式クレーンや船上クレーンにより行ってもよい。(4) As shown in FIG. 4B, for example, No. 1
When the joining of the bridge girder precast segment A of No. 6 is completed, a girder of unit length is sequentially connected to the rear of the erection girder 2 of the temporary working device 1A of the erection nose type, and the support gantry 11 arranged at a predetermined interval is added. Support with. This additional connection is performed by the lifting device 4 as described later. This additional connection is not limited to this, and may be performed by a mobile crane on the ground or a crane on board.
【0023】(5) 図4(c) に示すように、支持架台11
を一部撤去し、残りの支持架台11のジャッキで架設ガ
ーダー2をジャッキアップし、一対の脚フレーム3、3
を後方へ盛替える。(5) As shown in FIG.
Is partially removed, the installation girder 2 is jacked up with the jacks of the remaining support stand 11, and a pair of leg frames 3, 3
Is rearranged.
【0024】(6) 図5、図6に示すように、移動装置7
あるいは別の送り装置を用いて架設ガーダー2を前方へ
送り、一対の脚フレーム3、3の後方への盛替えを順次
繰り返して、架設ガーダー2を前進させる。(6) As shown in FIG. 5 and FIG.
Alternatively, the erection girder 2 is sent forward by using another feeding device, and rearrangement of the pair of leg frames 3 and 3 is sequentially repeated to advance the erection girder 2.
【0025】(7) 図7に示すように、前進させた架設ガ
ーダー2の先端をベント12で支持し、送り出しが完了
する。(7) As shown in FIG. 7, the leading end of the erected girder 2 which has been advanced is supported by the vent 12, and the delivery is completed.
【0026】(8) この状態でエレクションガーダー方式
の架設作業装置1Bが橋脚B側の既設の橋桁と橋脚C間
に掛け渡され、図2に示すように、架設ガーダー2に沿
って吊上げ装置4を前方に移動させ、橋桁プレキャスト
セグメントAを運搬していく。(8) In this state, the erection girder type erection work device 1B is hung between the existing bridge girder on the pier B side and the pier C, and as shown in FIG. Is moved forward to transport the bridge girder precast segment A.
【0027】橋桁プレキャストセグメントAは、橋脚C
側からの逆張出しで接合していき、支点間の中央で閉合
する。The bridge girder precast segment A includes a pier C
Joining by reverse overhang from the side, close at the center between the fulcrums.
【0028】この逆張出し区間では、従来と同様に、図
示のように、ベント12上に立てたピロン柱13からの
斜材14で順次支持していき、あるいは図示しない支保
工で支持する。In this reverse overhang section, as in the conventional case, as shown in the drawing, the support is sequentially supported by a diagonal member 14 from a pillar column 13 erected on a vent 12, or is supported by a support (not shown).
【0029】次に、架設ガーダー2の追加接続は、図8
に示すような方法で行う。即ち、吊上げ装置4を架設ガ
ーダー2の中央部に移動させ、この状態から接続する架
設ガーダー2’の各トラス桁2a’を吊上げ、各クラブ
トロリ4bをそれぞれ内側に横行させ、各トラス桁2
a’を各トラス桁2aに外面に添接させ、隣接する角部
のピンで連結する。次いで、このピンを中心にしてトラ
ス桁2a’をウインチ等の適宜の手段で後方に180°
旋回させ、トラス桁2aの後方にトラス桁2a’を連続
させ、内側の角部同士をピンで連結して一体化する。Next, an additional connection of the erection girder 2 is shown in FIG.
The method is performed as shown in FIG. That is, the lifting device 4 is moved to the center of the erection girder 2, and the truss girders 2a 'of the erection girder 2' to be connected are lifted from this state, and the respective club trolleys 4b are traversed inward.
a 'is attached to the outer surface of each truss girder 2a, and is connected by pins at adjacent corners. Then, the truss girder 2a 'is turned 180 ° rearward around the pin by an appropriate means such as a winch.
Then, the truss girder 2a 'is connected to the back of the truss girder 2a, and the inner corners are connected by a pin to be integrated.
【0030】続いて、接続された架設ガーダー2a’上
に吊上げ装置4を移動させ、前記と同様の手順を繰り返
して所定の長さの架設ガーダー2を得る。次いで、架設
ガーダー2の押出しを行うことになる。Subsequently, the lifting device 4 is moved onto the connected construction girder 2a ', and the same procedure as described above is repeated to obtain the construction girder 2 having a predetermined length. Next, the construction girder 2 is extruded.
【0031】なお、以上の図示例は、斜長橋等について
示したが、これに限らず、その他の支間長の長い橋梁に
も本発明を適用できることはいうまでもない。Although the above-described example shows an oblique bridge and the like, it is needless to say that the present invention can be applied to other bridges having a long span.
【0032】[0032]
【発明の効果】前述のとおり、本発明は、架設ガーダー
と脚フレームとセグメント吊上げ装置からエレクション
ノーズ方式の架設作業装置を構成し、この架設作業装置
により順張出し可能区間の架設を行い、次いで、前記移
動架設作業装置の架設ガーダーにガーダーを追加接続し
てエレクションガーダー方式の架設作業装置を構成し、
この架設作業装置により残りの順張出し不可能区間の架
設を行うようにしたため、斜張橋等のように支間長が長
い場合にも、一つの架設作業装置だけで片持ち架設プレ
キャストセグメント工法による架設が可能となり、コス
トの低減および施工の迅速化を図ることができる。As described above, according to the present invention, an erection nose type erection work device is constructed from an erection girder, a leg frame, and a segment lifting device. Girder is additionally connected to the erection girder of the moving erection work device to constitute an erection girder type erection work device,
Since the remaining section where extension is not possible is installed using this erection work device, even when the span length is long, such as a cable-stayed bridge, only one erection work device can be used for cantilever erection using the precast segment method. It is possible to reduce costs and speed up construction.
【図1】本発明の順張出し可能区間でエレクションノー
ズ方式とした架設作業装置の一例を示す、(a) は平面
図、(b) は側面図、(c) は正面図である。FIG. 1 shows an example of an erection nose type erection work device in a stretchable section of the present invention, in which (a) is a plan view, (b) is a side view, and (c) is a front view.
【図2】本発明の順張出し不可能区間でエレクションガ
ーダー方式とした架設作業装置の一例を示し、(a) は平
面図、(b) は側面図である。FIG. 2 shows an example of an erection girder type erection work apparatus according to the present invention in a section where extension is impossible, in which (a) is a plan view and (b) is a side view.
【図3】本発明の架設方法の一例を工程順(工程1〜
3)に示した側面図である。FIG. 3 shows an example of the erection method of the present invention in the order of steps (steps 1 to 3).
It is the side view shown to 3).
【図4】本発明の架設方法の一例を工程順(工程4〜
6)に示した側面図である。FIG. 4 shows an example of the erection method according to the present invention in the order of steps (steps 4 to 4).
It is a side view shown to 6).
【図5】本発明の架設方法の一例を工程順(工程7〜
9)に示した側面図である。FIG. 5 shows an example of the erection method of the present invention in the order of steps (steps 7 to
It is a side view shown to 9).
【図6】本発明の架設方法の一例を工程順(工程10〜
12)に示した側面図である。FIG. 6 shows an example of the erection method of the present invention in the order of steps (steps 10 to 10).
It is a side view shown to 12).
【図7】本発明の架設方法の一例を工程順(工程13)
に示した側面図である。FIG. 7 shows an example of the erection method of the present invention in the order of steps (step 13).
It is a side view shown in FIG.
【図8】本発明における架設ガーダーの追加接続の一例
を工程順に示した側面図・正面図・平面図である。FIG. 8 is a side view, a front view, and a plan view showing an example of additional connection of an installation girder according to the present invention in the order of steps.
【図9】(a) は従来のエレクションノーズ方式の架設方
法を示す側面図、(b) は従来のエレクションガーダー方
式の架設方法を示す側面図である。9A is a side view showing a conventional erection nose type erection method, and FIG. 9B is a side view showing a conventional erection girder type erection method.
A……橋桁プレキャストセグメント B、C…橋脚 1A…エレクションノーズ方式の架設作業装置 1B…エレクションガーダー方式の架設作業装置 2……架設ガーダー 2a…トラス桁 3……脚フレーム 4……吊上げ装置 4a…クレーン桁 4b…クラブトロリ 5……作業足場 6……軌条桁 7……移動装置 8……ロック・アンロック装置 9……走行装置 10……横行装置 11……支持架台 12……ベント 13……ピロン柱 14……斜材 A: Bridge girder precast segment B, C: Bridge pier 1A: Erection nose type erection work device 1B ... Erection girder type erection work device 2 ... Erecting girder 2a ... Truss girder 3 ... Leg frame 4 ... Lifting device 4a ... Crane girder 4b Club trolley 5 Work scaffold 6 Rail girder 7 Moving device 8 Locking / unlocking device 9 Traveling device 10 Traversing device 11 Support base 12 Vent 13 … Pilon pillar 14… diagonal
───────────────────────────────────────────────────── フロントページの続き (72)発明者 平川 隆一 広島県府中市元町77番地の1 株式会社北 川鉄工所内 (72)発明者 徳永 真作 広島県府中市元町77番地の1 株式会社北 川鉄工所内 ──────────────────────────────────────────────────続 き Continuing on the front page (72) Ryuichi Hirakawa, 77-1, Motomachi, Fuchu-shi, Hiroshima Inside the Kitagawa Iron Works Co., Ltd. (72) Masasaku Tokunaga 77-1, Motomachi, Fuchu-shi, Hiroshima Kitagawa, Inc. Inside the ironworks
Claims (2)
キャストセグメントを接合してプレストレスを与えなが
ら橋脚を起点として張り出して行く片持ち架設プレキャ
ストセグメント工法による橋梁の架設方法において、架
設ガーダーと脚フレームとセグメント吊上げ装置からエ
レクションノーズ方式の架設作業装置を構成し、この架
設作業装置により前記橋脚から所定の位置までの架設を
行い、次いで、前記移動架設作業装置の架設ガーダーに
ガーダーを追加接続してエレクションガーダー方式の架
設作業装置を構成し、この架設作業装置により残りの部
分の架設を行うことを特徴とする橋梁の架設方法。1. A method of erection of a bridge by a cantilever erection precast segment method, in which a bridge girder precast segment manufactured in a factory or a yard is joined and pre-stressed and extended from a pier as a starting point. An erection nose type erection work device is constructed from the segment lifting device, erection is performed from the pier to a predetermined position by this erection operation device, and then a girder is additionally connected to the erection girder of the movable erection work device by erection. A method for erection of a bridge, comprising a girder type erection work device, and erection of the remaining portion by the erection work device.
て、架設ガーダーに設置されたセグメント吊上げ装置を
用いてガーダーを吊上げて前記架設ガーダーに追加接続
することを特徴とする橋梁の架設方法。2. The bridge erection method according to claim 1, wherein the girder is lifted using a segment lifting device installed on the erection girder, and is additionally connected to the erection girder.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP9313439A JP3025227B2 (en) | 1997-11-14 | 1997-11-14 | Bridge construction method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP9313439A JP3025227B2 (en) | 1997-11-14 | 1997-11-14 | Bridge construction method |
Publications (2)
Publication Number | Publication Date |
---|---|
JPH11148111A true JPH11148111A (en) | 1999-06-02 |
JP3025227B2 JP3025227B2 (en) | 2000-03-27 |
Family
ID=18041318
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP9313439A Expired - Fee Related JP3025227B2 (en) | 1997-11-14 | 1997-11-14 | Bridge construction method |
Country Status (1)
Country | Link |
---|---|
JP (1) | JP3025227B2 (en) |
Cited By (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101914898A (en) * | 2010-09-06 | 2010-12-15 | 中铁大桥局集团有限公司 | Guide beam for jacking construction of three truss steel beams |
KR101630312B1 (en) * | 2015-11-17 | 2016-06-24 | 한국도로공사 | Rapid bridge replacement construction method using through bridge girder segment |
CN105970833A (en) * | 2016-07-01 | 2016-09-28 | 北京中铁建北方路桥工程有限公司 | Precast segment span-by-span assembling bridge fabrication machine |
CN108203934A (en) * | 2018-02-02 | 2018-06-26 | 中交二公局第工程有限公司 | Based on the whole segment lifting erection crane of the traversing cable-stayed bridge composite beam of unbalance loading |
KR20190057579A (en) * | 2017-11-20 | 2019-05-29 | 대림산업 주식회사 | Constructing Method of Bridge using Launching Gantry |
CN110284429A (en) * | 2019-04-24 | 2019-09-27 | 中国一冶集团有限公司 | Scalable nose girder and its application method |
CN111188276A (en) * | 2020-01-17 | 2020-05-22 | 中铁电气化局集团有限公司 | Segmental beam sliding and assembling construction method |
CN113914225A (en) * | 2021-10-19 | 2022-01-11 | 安徽省公路桥梁工程有限公司 | Longitudinal sliding vertical lifting construction method for main truss of large-tonnage guyed hanging basket |
Families Citing this family (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102518041B (en) * | 2011-12-09 | 2013-11-06 | 中国建筑第六工程局有限公司 | Construction method of support system for overhead continuous beam form-erecting falsework |
CN103628411B (en) * | 2013-11-21 | 2015-11-18 | 中交第二航务工程局有限公司 | Attached tower cantilevered bale handle purlin, high-altitude, mountain area crane system |
-
1997
- 1997-11-14 JP JP9313439A patent/JP3025227B2/en not_active Expired - Fee Related
Cited By (9)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101914898A (en) * | 2010-09-06 | 2010-12-15 | 中铁大桥局集团有限公司 | Guide beam for jacking construction of three truss steel beams |
KR101630312B1 (en) * | 2015-11-17 | 2016-06-24 | 한국도로공사 | Rapid bridge replacement construction method using through bridge girder segment |
CN105970833A (en) * | 2016-07-01 | 2016-09-28 | 北京中铁建北方路桥工程有限公司 | Precast segment span-by-span assembling bridge fabrication machine |
CN105970833B (en) * | 2016-07-01 | 2017-11-10 | 中国铁路总公司 | Prefabricated subsection splicing span by span bridge fabrication machine |
KR20190057579A (en) * | 2017-11-20 | 2019-05-29 | 대림산업 주식회사 | Constructing Method of Bridge using Launching Gantry |
CN108203934A (en) * | 2018-02-02 | 2018-06-26 | 中交二公局第工程有限公司 | Based on the whole segment lifting erection crane of the traversing cable-stayed bridge composite beam of unbalance loading |
CN110284429A (en) * | 2019-04-24 | 2019-09-27 | 中国一冶集团有限公司 | Scalable nose girder and its application method |
CN111188276A (en) * | 2020-01-17 | 2020-05-22 | 中铁电气化局集团有限公司 | Segmental beam sliding and assembling construction method |
CN113914225A (en) * | 2021-10-19 | 2022-01-11 | 安徽省公路桥梁工程有限公司 | Longitudinal sliding vertical lifting construction method for main truss of large-tonnage guyed hanging basket |
Also Published As
Publication number | Publication date |
---|---|
JP3025227B2 (en) | 2000-03-27 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
US11634877B2 (en) | Method for removal of temporary support system for road bridge pre-fabricated small box girder-type concealed bent cap, and equipment therefor | |
US5511268A (en) | Construction of large structures by robotic crane placement of modular bridge sections | |
JP7346246B2 (en) | Heavy object moving method using heavy object moving device and heavy object moving device | |
WO1996005375A9 (en) | Construction of large structures by robotic crane placement of modular bridge sections | |
JP2002088718A (en) | Inner form device for concrete box girder bridge and moving method therefor | |
JP3025227B2 (en) | Bridge construction method | |
JP3440422B2 (en) | Bridge construction method and bridge construction device | |
CN111778857B (en) | Process for synchronously erecting upper and lower beams of double-layer overhead bridge of urban public rail | |
JP5184248B2 (en) | Construction method of level crossing | |
JP2006077521A (en) | Bridge constructing apparatus | |
JP2006028881A (en) | Self-propelled pc floor slab erecting machine and pc floor slab erecting method | |
JPH0959932A (en) | Construction method of column head of overhanging erection girder bridge | |
CN112160246A (en) | Method for mounting combined beam | |
JP2001049622A (en) | Bridge erecting apparatus and bridge erecting method | |
CN112610014A (en) | Sliding structure for railway passenger station reconstruction and extension project and construction method thereof | |
JP2768281B2 (en) | Bridge construction method | |
JPS6041165B2 (en) | Equipment for cantilevering bridge structures made of reinforced concrete or prestressed concrete into sections. | |
JP2020186516A (en) | Method of constructing bridge railing | |
JP3471248B2 (en) | Portal crane | |
JPH11269825A (en) | Installation method of bridge girder and lifting equipment | |
JPS60258311A (en) | Construction of high structure | |
JPH07102524A (en) | Method for building concrete cable-stayed bridge and form supporting truck using the same | |
JPH05148817A (en) | Construction of pc bridge | |
JPH10219626A (en) | Movable form timbering device to install bridge and moving execution method thereof | |
JPH11158817A (en) | Balancing erection construction for bridge at height and transferable slinging lifting device therefor |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
A01 | Written decision to grant a patent or to grant a registration (utility model) |
Free format text: JAPANESE INTERMEDIATE CODE: A01 Effective date: 19991221 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20090121 Year of fee payment: 9 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20120121 Year of fee payment: 12 |
|
LAPS | Cancellation because of no payment of annual fees |