CN108203934A - Based on the whole segment lifting erection crane of the traversing cable-stayed bridge composite beam of unbalance loading - Google Patents

Based on the whole segment lifting erection crane of the traversing cable-stayed bridge composite beam of unbalance loading Download PDF

Info

Publication number
CN108203934A
CN108203934A CN201810106112.3A CN201810106112A CN108203934A CN 108203934 A CN108203934 A CN 108203934A CN 201810106112 A CN201810106112 A CN 201810106112A CN 108203934 A CN108203934 A CN 108203934A
Authority
CN
China
Prior art keywords
section
longeron
tower area
assembled
bridge floor
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201810106112.3A
Other languages
Chinese (zh)
Inventor
纪登贵
朱晓明
郭欣
孙鹏
谢福勇
纵坤
肖伟
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
CCCC SHB First Engineering Co Ltd
Original Assignee
CCCC SHB First Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by CCCC SHB First Engineering Co Ltd filed Critical CCCC SHB First Engineering Co Ltd
Priority to CN201810106112.3A priority Critical patent/CN108203934A/en
Publication of CN108203934A publication Critical patent/CN108203934A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges
    • E01D21/10Cantilevered erection
    • E01D21/105Balanced cantilevered erection
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges
    • E01D21/08Methods or apparatus specially adapted for erecting or assembling bridges by rotational movement of the bridge or bridge sections

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Bridges Or Land Bridges (AREA)

Abstract

本发明公开了一种基于偏载横移的斜拉桥叠合梁整节段吊装桥面吊机,它包括塔区、塔区已拼装梁段桥面、整节段桥面吊机和节段梁,塔区已拼装梁段桥面设置有运梁车和桥面胎架;整节段桥面吊机包括横梁、天车、纵梁、前支腿和后支腿;塔区已拼装梁段桥面的桥面上还设置有第一斜拉索支座,第一斜拉索支座通过第一斜拉索与塔区顶部连接;节段梁包括节段梁横梁、节段梁纵梁和第二斜拉索支架;节段梁纵梁有两根,两根节段梁纵梁之间设置有三根节段梁横梁;所述第二斜拉索支架位于节段梁纵梁中部;本发明即保证了施工的安全和质量,又能提高了施工的效率,降低施工成本。

The invention discloses a bridge deck crane for hoisting and erecting the entire section of a composite girder of a cable-stayed bridge based on eccentric load lateral movement. Segmental girders and tower areas have been assembled. The beam section bridge deck is equipped with beam transport vehicles and bridge deck tire frames; the entire segment bridge deck crane includes beams, crown blocks, longitudinal beams, front outriggers and rear outriggers; the tower area has been assembled The bridge deck of the beam section bridge is also provided with a first stay cable support, which is connected to the top of the tower area through the first stay cable; the section beam includes a section beam beam, a section beam Longitudinal beams and second stay cable supports; there are two section beam longitudinal beams, and three section beam cross beams are arranged between the two section beam longitudinal beams; the second stay cable support is located on the section beam longitudinal beam Middle part; the present invention not only ensures the safety and quality of construction, but also improves the efficiency of construction and reduces construction cost.

Description

基于偏载横移的斜拉桥叠合梁整节段吊装桥面吊机Deck crane for whole segment hoisting of composite girder of cable-stayed bridge based on eccentric load lateral movement

技术领域technical field

本发明涉及一种桥面吊机,更具体地说是它一种基于偏载横移的斜拉桥叠合梁整节段吊装桥面吊机。The invention relates to a bridge deck crane, more specifically, it is a bridge deck crane for hoisting the entire segment of a composite girder of a cable-stayed bridge based on eccentric load lateral movement.

背景技术Background technique

传统斜拉桥叠合梁安装工艺为如下两种:The traditional cable-stayed bridge composite girder installation process is as follows:

一、全回转桥面吊机,该吊机适用于叠合梁钢梁散件安装工艺,安装步骤如下:1. The full-slewing bridge deck crane is suitable for the installation process of composite beam steel beam parts. The installation steps are as follows:

步骤1将钢梁构件运输至主塔提升站工作区域;Step 1: Transport the steel girder components to the working area of the main tower hoisting station;

步骤2利用提升站提升构件至桥面运梁设备上,转运至回转吊机作业范围;Step 2 Use the lifting station to lift the components to the bridge deck beam transportation equipment, and transfer them to the operating range of the slewing crane;

步骤3利用回转吊机依次安装叠合梁边主梁、横梁、小纵梁;Step 3 Use the slewing crane to install the main girder, cross girder and small longitudinal girder on the side of the composite girder in sequence;

步骤4初张斜拉索,安装桥面板,二次张拉斜拉索;Step 4 initially tensions the stay cables, installs the bridge deck, and secondly tensions the stay cables;

步骤5回转吊机前移、就位、锚固,开始下一梁段安装。Step 5 The slewing crane is moved forward, positioned, anchored, and the installation of the next beam section begins.

其优点:工艺成熟,设备通用性强;Its advantages: mature technology, strong versatility of equipment;

其缺点:施工高空作业多、质量、安全管控难度大,经济效益差。Its disadvantages: many high-altitude operations in construction, difficult quality and safety control, and poor economic benefits.

二、缆索吊机,该吊机适用于叠合梁钢梁整节段安装工艺,安装步骤如下:2. Cable crane, which is suitable for the installation process of the entire segment of the composite beam steel beam. The installation steps are as follows:

步骤1将钢梁构件运输至主塔起升设备工作区域;Step 1: Transport the steel beam components to the working area of the main tower hoisting equipment;

步骤2利用起升设备提升并在桥面范围拼装钢梁构件为节段梁;Step 2: use hoisting equipment to lift and assemble the steel girder components in the bridge deck range as segmental girders;

步骤3利用缆索吊依次吊运、安装节段梁;Step 3: Use cable cranes to lift and install segmental beams in sequence;

优点:工艺相对成熟,设备可部分通用。Advantages: The process is relatively mature, and the equipment can be used in part.

缺点:临时设备组装工作量大,成本高,经济效益差。Disadvantages: The assembly of temporary equipment is heavy, the cost is high, and the economic benefit is poor.

如何在以上成熟工艺基础上进行突破,能即保证安全、质量,又能提高施工效率,降低施工成本,是目前需要研究、探索、解决的重要课题,也是本发明的意义所在。How to make a breakthrough on the basis of the above-mentioned mature technology, which can not only ensure safety and quality, but also improve construction efficiency and reduce construction cost, is an important subject that needs to be studied, explored and solved at present, and it is also the significance of the present invention.

发明内容Contents of the invention

本发明的目的是为了克服上述背景技术的不足之处,而提供一种基于偏载横移的斜拉桥叠合梁整节段吊装桥面吊机。The object of the present invention is to overcome the disadvantages of the above-mentioned background technology, and provide a bridge deck crane for hoisting the whole segment of the composite girder of a cable-stayed bridge based on eccentric load lateral movement.

为了实现上述目的,本发明的技术方案为:基于偏载横移的斜拉桥叠合梁整节段吊装桥面吊机,其特征在于:包括塔区、塔区已拼装梁段桥面、整节段桥面吊机和节段梁,所述塔区已拼装梁段桥面位于塔区下部,塔区已拼装梁段桥面的桥面上设置有运梁车和起升设备拼装节段梁时临时设置的桥面胎架,塔区已拼装梁段桥面两端的端部均设置有第一纵梁螺栓;所述整节段桥面吊机安装于塔区已拼装梁段桥面两端上方,整节段桥面吊机包括横梁、天车、纵梁、前支腿和后支腿;所述天车安装于横梁上;所述纵梁位于横梁两端,横梁通过驱动轮结构安装于纵梁上;所述前支腿的一端与纵梁的中部连接,另一端固定在塔区已拼装梁段桥面上;所述后支腿的一端与纵梁靠近塔区的一端连接,另一端固定在纵梁靠近塔区下方的塔区已拼装梁段桥面上;所述塔区已拼装梁段桥面的桥面上还设置有第一斜拉索支座,第一斜拉索支座位于前支腿和后支腿之间,第一斜拉索支座通过第一斜拉索与塔区顶部连接;In order to achieve the above object, the technical solution of the present invention is: a bridge deck crane for hoisting the entire segment of the composite girder of a cable-stayed bridge based on eccentric load lateral movement, which is characterized in that it includes the tower area, the bridge deck of the assembled beam section in the tower area, The entire section of the bridge deck crane and the segmental beam, the bridge deck of the assembled beam section in the tower area is located at the lower part of the tower area, and the bridge deck of the assembled beam section in the tower area is equipped with a beam transport vehicle and a hoisting equipment assembly section The bridge deck tire frame temporarily installed during the section of the beam, and the ends of the bridge deck of the assembled beam section in the tower area are equipped with first longitudinal beam bolts; the whole section deck crane is installed on the assembled beam section bridge Above both ends of the deck, the entire section of the bridge deck crane includes a beam, a crane, a longitudinal beam, a front leg and a rear leg; the crane is installed on the beam; the longitudinal beam is located at both ends of the beam, and the beam is driven by The wheel structure is installed on the longitudinal beam; one end of the front outrigger is connected to the middle of the longitudinal beam, and the other end is fixed on the bridge deck of the assembled beam section in the tower area; one end of the rear outrigger is connected to the side of the longitudinal beam near the tower area One end is connected, and the other end is fixed on the bridge deck of the assembled beam section in the tower area where the longitudinal girder is close to the bottom of the tower area; the deck of the assembled beam section bridge deck in the tower area is also provided with a first stay cable support, and A stay cable support is located between the front outrigger and the rear outrigger, and the first stay cable support is connected to the top of the tower area through the first stay cable;

所述节段梁包括节段梁横梁、节段梁纵梁和第二斜拉索支架;所述节段梁纵梁有两根,两根节段梁纵梁之间设置有三根节段梁横梁;所述第二斜拉索支架位于节段梁纵梁中部;所述节段梁有拼装工位、喂梁工位和回转工位;The segmental beam includes a segmental beam crossbeam, a segmental beam longitudinal beam and a second stay cable support; there are two segmental beam longitudinal beams, and three segmental beams are arranged between the two segmental beam longitudinal beams Crossbeam; the second stay cable bracket is located in the middle of the longitudinal beam of the segmental beam; the segmental beam has an assembly station, a beam feeding station and a rotary station;

在拼装工位时通过起升设备在桥面胎架上将节段梁横梁和节段梁纵梁拼装为节段梁;At the assembly station, the segmental beam beam and the segmental beam longitudinal beam are assembled into a segmental beam on the bridge deck tire frame by lifting equipment;

在喂梁工位时节段梁位于运梁车上,运梁车将节段梁运至整节段桥面吊机的工作范围;In the beam feeding station, the segment beam is located on the beam transport vehicle, and the beam transport vehicle transports the segment beam to the working range of the bridge deck crane of the entire segment;

在回转工位时节段梁位于塔区已拼装梁段桥面端部的上方,节段梁通过整节段桥面吊机回转90°。At the rotary station, the segmental beam is located above the end of the bridge deck of the assembled beam section in the tower area, and the segmental beam is rotated 90° by the whole segmental deck crane.

在上述技术方案中,所述整节段桥面吊机在回转工位时,先偏载横移,再将节段梁回转90°。In the above technical solution, when the whole segment bridge deck crane is at the rotary station, it first moves sideways with an unbalanced load, and then rotates the segment beam by 90°.

在上述技术方案中,所述节段梁纵梁一端设置有第一落梁,另一端设置有第二纵梁螺栓;所述节段梁纵梁完成回转后节段梁纵梁设置有第一落梁的一端靠近已拼装梁段桥面。In the above technical solution, one end of the section beam longitudinal beam is provided with a first drop beam, and the other end is provided with a second longitudinal beam bolt; after the section beam longitudinal beam completes the rotation, the section beam longitudinal beam is provided with a first One end of the drop beam is close to the bridge deck of the assembled beam section.

与现有技术相比,本发明的有益效果如下:Compared with the prior art, the beneficial effects of the present invention are as follows:

1)本发明费用为全回转桥面吊机散件拼装的70%,功效为全回转桥面吊机散件拼装的200%;费用为缆索吊机拼装的60%,功效为全回转桥面吊机散件拼装的150%。1) The cost of the present invention is 70% of the assembly of the parts of the full-turn bridge deck crane, and the effect is 200% of the assembly of the parts of the full-turn bridge deck crane; the cost is 60% of the assembly of the cable crane, and the effect is the full-turn bridge deck 150% of the assembled parts of the crane.

2)本发明可以与智能行走系统,安全自动监控系统,液压系统充分结合,符合智能化、电气化,自动化等技术发展潮流。2) The present invention can be fully combined with an intelligent walking system, a safety automatic monitoring system, and a hydraulic system, and conforms to the technological development trend of intelligence, electrification, and automation.

3)本发明可兼顾考虑不同梁段重量,不同桥幅宽度,做到峡谷山区400~800米跨度同类型桥梁架设,极大提高通用性。3) The present invention can take into account different beam section weights and different bridge widths, so that the same type of bridges with a span of 400-800 meters in canyon and mountainous areas can be erected, which greatly improves the versatility.

附图说明Description of drawings

图1为本发明整节段桥面吊机2拼装完成的正视图。Fig. 1 is the front view of the whole section bridge deck crane 2 assembled in the present invention.

图2为图1的右视图。Fig. 2 is the right side view of Fig. 1 .

图3为图1的俯视图。FIG. 3 is a top view of FIG. 1 .

图4为本发明节段梁4拼装完成的正视图。Fig. 4 is a front view of the assembled segmental beam 4 of the present invention.

图5为图4的右视图。Fig. 5 is a right side view of Fig. 4 .

图6为图4的俯视图。FIG. 6 is a top view of FIG. 4 .

图7为本发明整节段桥面吊机2起吊节段梁4的正视图。Fig. 7 is a front view of the entire section deck crane 2 lifting the section beam 4 according to the present invention.

图8为图7的右视图。Fig. 8 is a right side view of Fig. 7 .

图9为图7的俯视图。FIG. 9 is a top view of FIG. 7 .

图10为本发明节段梁4位于回转工位的正视图。Fig. 10 is a front view of the segmental beam 4 of the present invention at the rotary station.

图11为图10的右视图。Fig. 11 is a right side view of Fig. 10 .

图12为图10俯视图。FIG. 12 is a top view of FIG. 10 .

图13为图12中A处的放大图。FIG. 13 is an enlarged view at A in FIG. 12 .

图14为图12中B处的放大图。FIG. 14 is an enlarged view at B in FIG. 12 .

图15为本发明第一落梁4c与第一纵梁螺栓1c连接时的正视图。Fig. 15 is a front view of the connection between the first drop beam 4c and the first longitudinal beam bolt 1c according to the present invention.

图16为图15的右视图。Fig. 16 is a right side view of Fig. 15 .

图17为图15的俯视图。FIG. 17 is a top view of FIG. 15 .

图中,1-塔区已拼装梁段桥面,1a-运梁车,1b-桥面胎架,1c-第一纵梁螺栓,1d-第一斜拉索支座,1d1-第一斜拉索,2-整节段桥面吊机,2a-横梁,2b-天车,2c-纵梁,2d-前支腿,2e-后支腿,3-塔区,4-节段梁,4a-节段梁横梁,4b-节段梁纵梁,4c-第一落梁,4d-第二纵梁螺栓,4e-第二斜拉索支架。In the figure, 1-the bridge deck of the assembled girder section in the tower area, 1a-beam transport vehicle, 1b-the bridge deck tire frame, 1c-the first longitudinal beam bolt, 1d-the first stay cable support, 1d1-the first inclined Stay cable, 2- entire section deck crane, 2a-beam, 2b-crown, 2c-longitudinal beam, 2d-front outrigger, 2e-rear outrigger, 3-tower area, 4-segment beam, 4a-segmental beam crossbeam, 4b-segmental beam longitudinal beam, 4c-first drop beam, 4d-second longitudinal beam bolt, 4e-second stay cable support.

具体实施方式Detailed ways

下面结合附图详细说明本发明的实施情况,但它们并不构成对本发明的限定,仅作举例而已。同时通过说明使本发明的优点将变得更加清楚和容易理解。The implementation of the present invention will be described in detail below in conjunction with the accompanying drawings, but they do not constitute a limitation to the present invention, and are only examples. At the same time, the advantages of the present invention will become clearer and easier to understand through the description.

参阅附图可知:基于偏载横移的斜拉桥叠合梁整节段吊装桥面吊机,包括塔区3、塔区已拼装梁段桥面1、整节段桥面吊机2和节段梁4,所述塔区已拼装梁段桥面1位于塔区3下部,塔区已拼装梁段桥面1的桥面上设置有运梁车1a和起升设备拼装节段梁4时临时设置的桥面胎架1b,塔区已拼装梁段桥面1两端的端部均设置有第一纵梁螺栓1c;所述整节段桥面吊机2安装于塔区已拼装梁段桥面1两端上方,整节段桥面吊机2包括横梁2a、天车2b、纵梁2c、前支腿2d和后支腿2e;所述天车2b安装于横梁2a上;所述纵梁2c位于横梁2a两端,横梁2a通过驱动轮结构安装于纵梁2c上;所述前支腿2d的一端与纵梁2c的中部连接,另一端与固定在塔区已拼装梁段桥面1上;所述后支腿2e的一端与纵梁2c靠近塔区3的一端连接,另一端固定在纵梁2c靠近塔区3下方的塔区已拼装梁段桥面1上;所述塔区已拼装梁段桥面1的桥面上还设置有第一斜拉索支座1d,第一斜拉索支座1d位于前支腿2d和后支腿2e之间,第一斜拉索支座1d通过第一斜拉索1d1与塔区3顶部连接;Referring to the accompanying drawings, it can be seen that the bridge deck crane for hoisting the whole segment of the composite beam of the cable-stayed bridge based on the eccentric load lateral movement includes the tower area 3, the bridge deck of the assembled beam section in the tower area 1, the entire segment deck crane 2 and Segmental beam 4, the assembled beam section bridge deck 1 in the tower area is located at the lower part of the tower area 3, and the bridge deck of the assembled beam section bridge deck 1 in the tower area is provided with a beam transport vehicle 1a and a hoisting equipment assembled segmental beam 4 The bridge deck tire frame 1b temporarily installed, the ends of the two ends of the assembled beam section bridge deck 1 in the tower area are provided with the first longitudinal beam bolts 1c; Above the two ends of the section bridge deck 1, the whole section bridge deck crane 2 includes a beam 2a, a crane 2b, a longitudinal beam 2c, a front outrigger 2d and a rear outrigger 2e; the crane 2b is installed on the beam 2a; The longitudinal beam 2c is located at both ends of the beam 2a, and the beam 2a is installed on the longitudinal beam 2c through the driving wheel structure; one end of the front leg 2d is connected to the middle of the longitudinal beam 2c, and the other end is connected to the assembled beam section fixed in the tower area. On the bridge deck 1; one end of the rear outrigger 2e is connected to the end of the longitudinal beam 2c near the tower area 3, and the other end is fixed on the assembled beam section bridge deck 1 of the longitudinal beam 2c near the tower area below the tower area 3; The first cable-stayed support 1d is also arranged on the bridge deck 1 of the assembled beam section in the tower area, and the first cable-stayed support 1d is located between the front outrigger 2d and the rear outrigger 2e. The cable support 1d is connected to the top of the tower area 3 through the first cable 1d1;

所述节段梁4包括节段梁横梁4a、节段梁纵梁4b和第二斜拉索支架4e;所述节段梁纵梁4b有两根,两根节段梁纵梁4b之间设置有三根节段梁横梁4a;所述第二斜拉索支架4e位于节段梁纵梁4b中部;所述节段梁4有拼装工位、喂梁工位和回转工位(如图4和图6所示);The section beam 4 includes a section beam crossbeam 4a, a section beam longitudinal beam 4b and a second stay cable support 4e; there are two section beam longitudinal beams 4b, and between the two section beam longitudinal beams 4b Three section beam crossbeams 4a are provided; the second stay cable support 4e is positioned at the middle part of the section beam longitudinal beam 4b; the section beam 4 has an assembly station, a beam feeding station and a rotary station (as shown in Fig. and shown in Figure 6);

在拼装工位时通过起升设备在桥面胎架1b上将节段梁横梁4a和节段梁纵梁4b拼装为节段梁4(如图5所示);At the assembling station, the segmental girder crossbeam 4a and the segmental girder longitudinal girder 4b are assembled into a segmental girder 4 (as shown in FIG. 5 ) on the deck tire frame 1b by lifting equipment;

在喂梁工位时节段梁4位于运梁车1a上,运梁车1a将节段梁4运至整节段桥面吊机2的工作范围(如图8所示);When feeding the beam station, the segmental beam 4 is located on the beam transport vehicle 1a, and the beam transport vehicle 1a transports the segmental beam 4 to the working range of the entire segment bridge deck crane 2 (as shown in Figure 8);

在回转工位时节段梁4位于塔区已拼装梁段桥面1端部的上方,节段梁4通过整节段桥面吊机2回转90°(如图10、图11、图12和图13所示)。During the rotary station, the segmental beam 4 is located above the end of the assembled beam section bridge deck 1 in the tower area, and the segmental beam 4 is rotated by 90° through the entire segmental bridge deck crane 2 (as shown in Figures 10, 11, 12 and Figure 13).

所述整节段桥面吊机2在回转工位时,先偏载横移200cm或适当距离,再将节段梁4回转90°(如图12和图13所示)。如果整节段桥面吊机2不偏载横移200cm或适当距离而直接带动节段梁4回转的话,节段梁4在回转时会与前支腿2d产生干扰,无法完成回转(图14所示),此时可以有两种解决方法:When the entire section deck crane 2 is at the rotary station, it first shifts 200cm or an appropriate distance with an unbalanced load, and then rotates the section beam 4 by 90° (as shown in Figures 12 and 13). If the deck crane 2 of the entire segment directly drives the segmental beam 4 to rotate without unbalanced load by 200cm or an appropriate distance, the segmental beam 4 will interfere with the front outrigger 2d during the rotation, and the rotation cannot be completed (as shown in Figure 14 shown), there are two possible solutions:

方法1:增加纵梁2c的长度。Method 1: Increase the length of the stringer 2c.

方法2:整节段桥面吊机2在回转工位时,先偏载横移200cm或适当距离,再将节段梁4回转90°。Method 2: When the deck crane 2 of the entire segment is at the rotary station, firstly move the eccentric load laterally by 200cm or an appropriate distance, and then rotate the segmental girder 4 by 90°.

方法1增加了纵梁2c的长度,纵梁2c长了,纵梁2c弯矩增大大,截面就要做强,重量就增加了;而方法二只需要整节段桥面吊机2偏载横移200cm或适当距离,不增加纵梁2c的重量,提高施工效率,降低施工成本。Method 1 increases the length of the longitudinal girder 2c, the longer the longitudinal girder 2c, the greater the bending moment of the longitudinal girder 2c, the section needs to be stronger, and the weight increases; while the second method only needs the partial load of the deck crane 2 of the entire section Transversely moving 200cm or an appropriate distance does not increase the weight of the longitudinal beam 2c, improves construction efficiency and reduces construction cost.

所述节段梁纵梁4b一端设置有第一落梁4c,另一端设置有第二纵梁螺栓4d;所述节段梁纵梁4b完成回转后节段梁纵梁4b设置有第一落梁4c的一端靠近已拼装梁段桥面1(如图11所示)。One end of the section beam longitudinal beam 4b is provided with a first drop beam 4c, and the other end is provided with a second longitudinal beam bolt 4d; One end of the beam 4c is close to the bridge deck 1 of the assembled beam section (as shown in FIG. 11 ).

本发明施工基于偏载横移的斜拉桥叠合梁整节段吊装桥面吊机的工艺,包含如下步骤:The construction of the present invention is based on the process of hoisting the bridge deck crane for the entire segment of the composite girder of the cable-stayed bridge based on the lateral movement of the partial load, including the following steps:

步骤1:将塔区已拼装梁段桥面1作为拼装平台,通过起升设备依次拼装前支腿2d、后支腿2e、纵梁2c、横梁2a和天车2b(如图2所示);Step 1: Use the bridge deck 1 of the assembled beam section in the tower area as the assembly platform, and assemble the front outrigger 2d, the rear outrigger 2e, the longitudinal beam 2c, the beam 2a and the crane 2b in sequence through the hoisting equipment (as shown in Figure 2) ;

步骤2:在桥面胎架1b上通过起升设备将节段梁横梁4a、节段梁纵梁4b和第二斜拉索支架4e拼装为节段梁4(如图4和图5所示);Step 2: Assemble the segmental girder beam 4a, the segmental girder longitudinal girder 4b and the second stay cable support 4e into a segmental girder 4 on the bridge deck tire frame 1b (as shown in Fig. 4 and Fig. 5 );

步骤3:将节段梁4固定与运梁车1a上(如图5所示);Step 3: Fix the segmental beam 4 on the beam transport vehicle 1a (as shown in Figure 5);

步骤4:通过运梁车1a将节段梁4运至整节段桥面吊机2的工作范围(如图8所示);Step 4: Transport the segmental girder 4 to the working range of the entire segmental deck crane 2 by the beam transporter 1a (as shown in FIG. 8 );

步骤5:整节段桥面吊机2起吊节段梁4,吊点为节段梁横梁4a的中横梁中心处(如图8和图9所示);Step 5: The segmental girder 4 is hoisted by the deck crane 2 of the entire segment, and the lifting point is the center of the mid-beam of the segmental girder beam 4a (as shown in Figures 8 and 9);

步骤6:整节段桥面吊机2带动节段梁4纵移至回转工位(如图10所示);Step 6: The whole section bridge deck crane 2 drives the section beam 4 to move longitudinally to the rotary station (as shown in Figure 10);

步骤7:整节段桥面吊机2偏载横移200cm或适当距离后节段梁4回转90°,回转完成后整节段桥面吊机2回正(如图10、图11、图12和图13所示);Step 7: The deck crane 2 of the whole section moves laterally with 200cm or an appropriate distance, and then the beam 4 of the section turns 90°. 12 and Figure 13);

步骤8:节段梁4下落,第一落梁4c与第一纵梁螺栓1c连接,完成架设(如图15、图16和图17所示);Step 8: The segmental beam 4 falls, and the first falling beam 4c is connected with the first longitudinal beam bolt 1c to complete the erection (as shown in Figure 15, Figure 16 and Figure 17);

步骤9:初张与第二斜拉索支架4e配套的第二斜拉索,安装桥面板,二次张拉第二斜拉索;Step 9: Initially stretch the second stay cable matched with the second stay cable support 4e, install the bridge deck, and secondly stretch the second stay cable;

步骤10:整节段桥面吊机2前移、就位、锚固,重复步骤1至步骤9,开始下一梁段安装,直至工作完成。Step 10: The bridge deck crane 2 of the entire section moves forward, puts in place, and anchors, and repeats steps 1 to 9 to start the installation of the next beam section until the work is completed.

实际使用中,位于塔区已拼装梁段桥面1两端上方的整节段桥面吊机2可以交叉工作。In actual use, the entire segment deck cranes 2 located above both ends of the assembled beam section deck 1 in the tower area can work crosswise.

其它未说明的部分均属于现有技术。Other unspecified parts belong to the prior art.

Claims (3)

1. based on the whole segment lifting erection crane of the traversing cable-stayed bridge composite beam of unbalance loading, it is characterised in that:Including tower area (3), tower Area assembled beam section bridge floor (1), whole segment erection crane (2) and beam sections (4), tower area assembly beam section bridge floor (1) position Yu Taqu (3) lower part, tower area are provided with beam car (1a) and erecting equipment assembly segment on the bridge floor of assembled beam section bridge floor (1) The bridge floor moulding bed (1b) set temporarily during beam (4), the end at tower area assembled beam section bridge floor (1) both ends are both provided with the first longeron Bolt (1c);The whole segment erection crane (2) is installed on tower area assembled beam section bridge floor (1) both ends top, whole segment bridge floor Loop wheel machine (2) includes crossbeam (2a), overhead traveling crane (2b), longeron (2c), front leg strut (2d) and rear support leg (2e);Overhead traveling crane (2b) installation In on crossbeam (2a);The longeron (2c) is installed on longeron positioned at crossbeam (2a) both ends, crossbeam (2a) by driving wheel structure On (2c);One end of the front leg strut (2d) is connect with the middle part of longeron (2c), and the other end is fixed on tower area assembled beam section bridge On face (1);One end of the rear support leg (2e) is connect with longeron (2c) close to the one end in tower area (3), and the other end is fixed on longeron The tower area of (2c) below tower area (3) is on assembled beam section bridge floor (1);The bridge floor of the tower area assembled beam section bridge floor (1) On be additionally provided with the first suspension cable bearing (1d), the first suspension cable bearing (1d) positioned at front leg strut (2d) and rear support leg (2e) it Between, the first suspension cable bearing (1d) at the top of the first suspension cable (1d1) and tower area (3) by connecting;
The beam sections (4) include beam sections crossbeam (4a), beam sections longeron (4b) and the second suspension cable stent (4e);The section Section beam longeron (4b) has two, and three beam sections crossbeams (4a) are provided between two beam sections longerons (4b);Described second tiltedly Cable support (4e) is in the middle part of beam sections longeron (4b);The beam sections (4) have assembled station, feeding beam station and revolution work Position;
In assembled station by erecting equipment on bridge floor moulding bed (1b) by beam sections crossbeam (4a) and beam sections longeron (4b) It is assemblied into beam sections (4);
In feeding beam station, for beam sections (4) on beam car (1a), beam sections (4) are transported to whole segment bridge floor by beam car (1a) The working range of loop wheel machine (2);
When turning round station, beam sections (4) are positioned at the top of tower area assembled beam section bridge floor (1) end, and beam sections (4) are by whole Segment erection crane (2) turns round 90 °.
2. the whole segment lifting erection crane of the cable-stayed bridge composite beam traversing based on unbalance loading according to claim 1, feature It is:For the whole segment erection crane (2) when turning round station, first unbalance loading is traversing, then beam sections (4) are turned round 90 °.
3. the whole segment lifting erection crane of the cable-stayed bridge composite beam traversing based on unbalance loading according to claim 1 or 2, special Sign is:Described beam sections longeron (4b) one end is provided with first and falls beam (4c), and the other end is provided with the second longeron bolt (4d); Beam sections longeron (4b) is provided with the first close assembly in one end for falling beam (4c) after the beam sections longeron (4b) completes revolution Beam section bridge floor (1).
CN201810106112.3A 2018-02-02 2018-02-02 Based on the whole segment lifting erection crane of the traversing cable-stayed bridge composite beam of unbalance loading Pending CN108203934A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810106112.3A CN108203934A (en) 2018-02-02 2018-02-02 Based on the whole segment lifting erection crane of the traversing cable-stayed bridge composite beam of unbalance loading

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810106112.3A CN108203934A (en) 2018-02-02 2018-02-02 Based on the whole segment lifting erection crane of the traversing cable-stayed bridge composite beam of unbalance loading

Publications (1)

Publication Number Publication Date
CN108203934A true CN108203934A (en) 2018-06-26

Family

ID=62605457

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810106112.3A Pending CN108203934A (en) 2018-02-02 2018-02-02 Based on the whole segment lifting erection crane of the traversing cable-stayed bridge composite beam of unbalance loading

Country Status (1)

Country Link
CN (1) CN108203934A (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108842632A (en) * 2018-08-02 2018-11-20 中交第四公路工程局有限公司 A kind of cable-stayed bridge girder steel and floorings combined hanging equipment and hanging method
CN114232487A (en) * 2021-12-15 2022-03-25 中交路桥建设有限公司 Construction system for erecting main beam of large-span cable-stayed bridge
CN115490148A (en) * 2022-10-12 2022-12-20 中交第二航务工程局有限公司 A bridge deck crane for intelligent erection and auxiliary cable adjustment of cable-stayed bridges and its construction method
CN115772851A (en) * 2022-11-17 2023-03-10 中交第三公路工程局有限公司 Construction method for feeding beams behind large-volume steel box girder of cable-stayed bridge in narrow terrain
CN115961549A (en) * 2022-12-02 2023-04-14 中铁广州工程局集团有限公司 Rear-feeding beam type erection construction method for large-tonnage whole-section steel beam of cable-stayed bridge

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH11148111A (en) * 1997-11-14 1999-06-02 Kajima Corp Bridge construction method
KR20060002650A (en) * 2004-07-03 2006-01-09 휘선건설(주) Precast Segment Bridge Construction Method Using Lifting Traveler
CN103981815A (en) * 2014-06-04 2014-08-13 贵州路桥集团有限公司 Cable-stayed door type wheeltrack proceeding cantilever crane
CN205024596U (en) * 2015-09-11 2016-02-10 中交路桥华东工程有限公司 Foldable rocking arm bridge deck crane
CN106192762A (en) * 2016-08-16 2016-12-07 山东省路桥集团有限公司 Steel box girder construction trestle fortune beam, beam body plane swivel, free cantilever erection construction method
CN106884384A (en) * 2017-03-01 2017-06-23 贵州桥梁建设集团有限责任公司 A kind of mountain area steel-concrete composite beam cable-stayed bridge erection crane method
CN206438420U (en) * 2016-12-02 2017-08-25 腾达建设集团股份有限公司 The assembled equipment of fixed asymmetric bridge girder cantilever

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH11148111A (en) * 1997-11-14 1999-06-02 Kajima Corp Bridge construction method
KR20060002650A (en) * 2004-07-03 2006-01-09 휘선건설(주) Precast Segment Bridge Construction Method Using Lifting Traveler
CN103981815A (en) * 2014-06-04 2014-08-13 贵州路桥集团有限公司 Cable-stayed door type wheeltrack proceeding cantilever crane
CN205024596U (en) * 2015-09-11 2016-02-10 中交路桥华东工程有限公司 Foldable rocking arm bridge deck crane
CN106192762A (en) * 2016-08-16 2016-12-07 山东省路桥集团有限公司 Steel box girder construction trestle fortune beam, beam body plane swivel, free cantilever erection construction method
CN206438420U (en) * 2016-12-02 2017-08-25 腾达建设集团股份有限公司 The assembled equipment of fixed asymmetric bridge girder cantilever
CN106884384A (en) * 2017-03-01 2017-06-23 贵州桥梁建设集团有限责任公司 A kind of mountain area steel-concrete composite beam cable-stayed bridge erection crane method

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108842632A (en) * 2018-08-02 2018-11-20 中交第四公路工程局有限公司 A kind of cable-stayed bridge girder steel and floorings combined hanging equipment and hanging method
CN114232487A (en) * 2021-12-15 2022-03-25 中交路桥建设有限公司 Construction system for erecting main beam of large-span cable-stayed bridge
CN114232487B (en) * 2021-12-15 2024-04-19 中交路桥建设有限公司 Construction system for erecting main girder of large-span cable-stayed bridge
CN115490148A (en) * 2022-10-12 2022-12-20 中交第二航务工程局有限公司 A bridge deck crane for intelligent erection and auxiliary cable adjustment of cable-stayed bridges and its construction method
CN115772851A (en) * 2022-11-17 2023-03-10 中交第三公路工程局有限公司 Construction method for feeding beams behind large-volume steel box girder of cable-stayed bridge in narrow terrain
CN115961549A (en) * 2022-12-02 2023-04-14 中铁广州工程局集团有限公司 Rear-feeding beam type erection construction method for large-tonnage whole-section steel beam of cable-stayed bridge

Similar Documents

Publication Publication Date Title
CN104805773B (en) The Segmental assembling bridge-erecting machine of little curved bridge of constructing
CN108203934A (en) Based on the whole segment lifting erection crane of the traversing cable-stayed bridge composite beam of unbalance loading
CN104195952A (en) Steel box girder erection method applied to steel and concrete hybrid girder cable-stayed bridge
CN105648916B (en) A kind of erection method of Bridge Erector and the Bridge Erector
CN104612718A (en) Supporting trolley for overlapped shield tunnel construction and supporting trolley system
CN101851898A (en) Bridge girder erection machine capable of passing through tunnel and realizing girder erection and bridging process thereof
CN111139743A (en) Method for improving speed of highway beam frame and installation method of gantry crane
CN114525734B (en) Erection method based on steel-concrete composite beam erection system
CN1609342A (en) Down-guiding girder type bridge erecting machine and its beam erecting method
CN101481903B (en) The method of erecting the main truss of the suspension bridge in mountainous area by reversing the cable-span crane
CN110700098A (en) Safe crossing method for double-guide-beam type bridge girder erection machine
CN111335182A (en) Portable single-rail bridge girder erection machine and steel column and steel girder installation method in bridge erecting process
CN114319145A (en) Bridge erecting method using bridge erecting machine
CN114370006A (en) Construction method for transferring girder transport vehicle carrying bridge girder erection machine
CN115182265B (en) Integrated bridge girder erection machine used under working condition of dry spliced segment bent cap and construction method
CN217325000U (en) Middle support bracket system of bridge girder erection machine
CN114476962B (en) A steel-concrete composite beam erection system based on bridge crane
CN108625270A (en) Nose girder gantry crane installs bridge prefabrication box girder construction method
CN102071641B (en) Cement beam packs bridge machine cloth supporting leg type integration of transporting and building Bridge Erector and bridge formation engineering method thereof
CN114277688B (en) Bridge girder erection machine
CN107747280A (en) The Bridge Erector of full span erection steel-pipe concrete truss
CN104929056B (en) The hydraulic drive of a kind of sphere track and control Bridge Erector, bridge formation system and bridging method
CN217536722U (en) Front bracket system of bridge girder erection machine
CN106320181A (en) Construction method for installing precast beam slabs by adopting bridge girder erection machine
CN107285209B (en) A kind of Novel U-shaped erection equipment and its operating method

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20180626