JPH1114008A - Bed temperature controlling method and device at the time of warming bed material storage tank of pressurized fluidized bed boiler - Google Patents

Bed temperature controlling method and device at the time of warming bed material storage tank of pressurized fluidized bed boiler

Info

Publication number
JPH1114008A
JPH1114008A JP17025397A JP17025397A JPH1114008A JP H1114008 A JPH1114008 A JP H1114008A JP 17025397 A JP17025397 A JP 17025397A JP 17025397 A JP17025397 A JP 17025397A JP H1114008 A JPH1114008 A JP H1114008A
Authority
JP
Japan
Prior art keywords
bed
bed material
temperature
output
storage tank
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP17025397A
Other languages
Japanese (ja)
Other versions
JP3826498B2 (en
Inventor
Masashi Ichihara
昌志 市原
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
IHI Corp
Original Assignee
IHI Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by IHI Corp filed Critical IHI Corp
Priority to JP17025397A priority Critical patent/JP3826498B2/en
Publication of JPH1114008A publication Critical patent/JPH1114008A/en
Application granted granted Critical
Publication of JP3826498B2 publication Critical patent/JP3826498B2/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Landscapes

  • Fluidized-Bed Combustion And Resonant Combustion (AREA)

Abstract

PROBLEM TO BE SOLVED: To provide a bed temperature controlling method and device at the time of warming a bed material storage tank of a pressurized fluidized bed boiler which can prevent lowering of the bed temperature in the body of the pressurized fluidized bed boiler at the time of warming a bed material in the bed material storage tank. SOLUTION: At the time of warming a bed material B in a bed material storage tank 4, in response to the temperature difference 65a between the bed temperature 63a in a body 3 of a fluidized bed boiler and the bed material temperature 64a at the lower portion of the bed material storage tank 4, a close time t" outputted from a function generator 66 is inputted to an ON delay timer 54 of a pulse generator 41 so as to change the injection speed of the bed material B into the body 3 of the fluidized bed boiler from the bed material storage tank 4, while in response to the above-mentioned temperature difference 65a, a fuel bias 70 outputted from the function generator 69 is outputted to an adder 75 so as to change the supply amount of fuel 9 thus controlling the bed temperature 63a at a given value while preventing lowering of the temperature.

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【発明の属する技術分野】本発明は、加圧流動層ボイラ
のベッド材貯蔵タンクウォーミング時における層温度制
御方法及び装置に関するものである。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a method and an apparatus for controlling bed temperature during warming of a bed material storage tank of a pressurized fluidized bed boiler.

【0002】[0002]

【従来の技術】図4は従来の加圧流動層ボイラの一例を
示したものであり、加圧流動層ボイラ1は、圧力容器2
内に、流動層ボイラ本体3とベッド材貯蔵タンク4を備
えており、流動層ボイラ本体3内の下部には下側の空気
取入口5から取り入れた圧力容器2内の加圧空気6を上
側に向けて吹き出す散気管或いは散気板からなる散気装
置7が配設されていると共に、該散気装置7の上側には
燃焼灰、石灰石、砂等からなるベッド材Bが装入されて
おり、前記散気装置7から吹き出される加圧空気6によ
り、流動層10が形成される燃料ポンプ等の燃料供給装
置8によって外部から供給される石炭スラリー、重油等
の燃料9が、ベッド材Bと共に混合して流動燃焼するこ
とにより、低NOx燃焼及び炉内脱硫が可能である。
2. Description of the Related Art FIG. 4 shows an example of a conventional pressurized fluidized-bed boiler.
A fluidized-bed boiler main body 3 and a bed material storage tank 4 are provided inside the fluidized-bed boiler main body 3. A diffuser 7 composed of an air diffuser or a diffuser plate is provided, and a bed material B made of combustion ash, limestone, sand, or the like is inserted above the diffuser 7. The fuel 9 such as coal slurry and heavy oil supplied from the outside by a fuel supply device 8 such as a fuel pump in which a fluidized bed 10 is formed by pressurized air 6 blown out from the air diffuser 7 is used as a bed material. By mixing with B and performing fluid combustion, low NOx combustion and in-furnace desulfurization are possible.

【0003】前記流動層ボイラ本体3内の流動層10が
形成される位置には伝熱管11が曲折して配設されてお
り、給水ポンプ等の給水供給装置12からの給水13が
前記伝熱管11を通る際にベッド材Bとの接触によって
加熱されて蒸気14となり、該蒸気14は加圧流動層ボ
イラ1の外部に設けられた蒸気タービン15に導かれ
て、該蒸気タービン15を駆動することにより同軸の発
電機16を駆動して電力を発生させている。
A heat transfer tube 11 is provided at a position where the fluidized bed 10 is formed in the fluidized bed boiler main body 3, and a water supply 13 from a water supply device 12 such as a water supply pump is supplied to the heat transfer tube 11. When passing through the bed 11, it is heated by contact with the bed material B to become steam 14, and the steam 14 is guided to a steam turbine 15 provided outside the pressurized fluidized-bed boiler 1 to drive the steam turbine 15. Thus, the coaxial generator 16 is driven to generate electric power.

【0004】又、流動層ボイラ本体3内で燃焼を行った
後の燃焼ガス17は、ガスタービン18に導かれて該ガ
スタービン18を駆動すると共に、同軸の空気圧縮機1
9を駆動し、更に余剰の動力で発電機20を駆動するよ
うになっており、前記空気圧縮機19により所定圧力に
圧縮された加圧空気6が前記圧力容器2内に供給される
ようになっている。
[0004] Combustion gas 17 after combustion in the fluidized bed boiler main body 3 is guided to a gas turbine 18 to drive the gas turbine 18 and, at the same time, coaxial air compressor 1.
9 to drive the generator 20 with surplus power so that the pressurized air 6 compressed to a predetermined pressure by the air compressor 19 is supplied into the pressure vessel 2. Has become.

【0005】前記流動層ボイラ本体3の下部に一端が接
続されたベッド材取出管21の他端が前記ベッド材貯蔵
タンク4の上部に接続されており、又、ベッド材貯蔵タ
ンク4の上部にはベッド材抜出排気管22が接続されて
圧力容器2の外部に導かれていて、該圧力容器2の外部
に導かれたベッド材抜出排気管22途中にはベッド材抜
出弁23が設けられており、該ベッド材抜出弁23を開
いて前記ベッド材貯蔵タンク4内を排気することによ
り、圧力差を利用して流動層ボイラ本体3内のベッド材
Bをベッド材取出管21を介してベッド材貯蔵タンク4
に取り出せるようになっている。
[0005] The other end of the bed material take-out pipe 21 having one end connected to the lower portion of the fluidized bed boiler main body 3 is connected to the upper portion of the bed material storage tank 4. Is connected to a bed material extraction exhaust pipe 22 and guided to the outside of the pressure vessel 2. A bed material extraction valve 23 is provided in the middle of the bed material extraction exhaust pipe 22 guided to the outside of the pressure vessel 2. The bed material extraction valve 23 is opened to exhaust the inside of the bed material storage tank 4, so that the bed material B in the fluidized bed boiler main body 3 is removed by utilizing the pressure difference. Bed material storage tank 4 through
Can be taken out.

【0006】更に、前記流動層ボイラ本体3の下部に
は、圧力容器2内の加圧空気6をベッド材注入弁24を
介して吹き込むようにしたベッド材吹込管26が接続さ
れると共に、前記ベッド材貯蔵タンク4の下部に上端が
接続された吸引管28の下端が、前記ベッド材吹込管2
6における流動層ボイラ本体3とベッド材注入弁24と
の間にLバルブ27を介して接続されており、前記ベッ
ド材注入弁24を開けてベッド材吹込管26から圧力容
器2内の加圧空気6をLバルブ27へ吹き込むことによ
り、ベッド材貯蔵タンク4内のベッド材Bを吸引管28
を介して流動層ボイラ本体3に吹き込めるようになって
いる。
Further, a bed material blowing pipe 26 for blowing the pressurized air 6 in the pressure vessel 2 through a bed material injection valve 24 is connected to a lower portion of the fluidized bed boiler main body 3. The lower end of the suction pipe 28 whose upper end is connected to the lower part of the bed material storage tank 4 is connected to the bed material blowing pipe 2.
6 is connected via an L valve 27 between the fluidized bed boiler main body 3 and the bed material injection valve 24, and opens the bed material injection valve 24 to pressurize the pressure vessel 2 from the bed material blowing pipe 26. By blowing the air 6 into the L valve 27, the bed material B in the bed material storage tank 4 is sucked into the suction pipe 28.
Through the fluidized-bed boiler main body 3.

【0007】図4中、29はベッド材Bの注入、抜出を
行って流動層ボイラ本体3内のベッド材Bのレベルを制
御するレベル制御装置であり、該レベル制御装置29に
は、集中指令室等から加圧流動層ボイラ1に発せられる
負荷指令34に基づいて関数発生器40から出力される
レベル制御指令39が入力されており、該レベル制御指
令39は、図5に示すように、負荷指令34の増減に対
し略比例して増減されるようになっている。
In FIG. 4, reference numeral 29 denotes a level control device for controlling the level of the bed material B in the fluidized-bed boiler main body 3 by injecting and extracting the bed material B. A level control command 39 output from the function generator 40 based on a load command 34 issued to the pressurized fluidized bed boiler 1 from a command room or the like is input, and as shown in FIG. The load command 34 is increased or decreased substantially in proportion to the increase or decrease.

【0008】更に、前記レベル制御装置29には、流動
層ボイラ本体3の流動層10の上層と下層との差圧を検
出する差圧計30からの検出差圧信号31が入力されて
流動層10の層高が検出されるようになっており、検出
した層高が前記レベル制御指令39と一致するように、
ベッド材抜出弁23に開閉制御信号32を出力すると共
に、ベッド材注入弁24に開閉制御信号33をパルス発
生装置41を介して開閉制御信号33’として出力し、
ベッド材抜出弁23及びベッド材注入弁24の開閉を制
御することによりベッド材Bの注入、抜出を行うように
なっている。
Further, a detected differential pressure signal 31 from a differential pressure gauge 30 for detecting a differential pressure between an upper layer and a lower layer of the fluidized bed 10 of the fluidized bed boiler body 3 is input to the level control device 29, Is detected, so that the detected layer height matches the level control command 39,
An open / close control signal 32 is output to the bed material extraction valve 23, and an open / close control signal 33 is output to the bed material injection valve 24 as an open / close control signal 33 'via the pulse generator 41.
The bed material B is injected and withdrawn by controlling the opening and closing of the bed material extraction valve 23 and the bed material injection valve 24.

【0009】前記パルス発生装置41は、前記レベル制
御装置29から出力される開閉制御信号33と後述する
ウォーミング制御装置42から出力されるウォーミング
指令信号43とが入力され、前記開閉制御信号33が
「1」である場合(流動層10の層高を上昇させるため
にベッド材注入弁24を開く場合)或いは前記ウォーミ
ング指令信号43が「1」である場合(ベッド材貯蔵タ
ンク4内のベッド材Bのウォーミングを行うためにベッ
ド材注入弁24を開く場合)に、「1」の論理和信号4
4を出力するOR回路45と、該OR回路45から出力
される論理和信号44とNOT回路46から出力される
否定信号47とが入力され、両信号44,47の論理積
信号48を出力するAND回路49と、該AND回路4
9から出力される論理積信号48が入力され、該論理積
信号48が「0」から「1」に変化した時に、予め設定
した時間t(例えば、5[sec]程度)だけ遅れを生
じさせて「1」に変化する遅延信号50を出力するオン
ディレイタイマ51と、該オンディレイタイマ51から
出力される遅延信号50が入力され、設定器52に設定
された時間t’(例えば、10[sec]程度)だけ遅
れを生じさせて「1」に変化する遅延信号53を前記N
OT回路46へ出力するオンディレイタイマ54と、前
記オンディレイタイマ51から出力される遅延信号50
と前記OR回路45からNOT回路55を経て出力され
る論理和信号44の否定信号56とが入力され、両信号
50,56の論理和信号57が出力されるOR回路58
と、前記AND回路49から出力される論理積信号48
が「0」から「1」に変化した時にセットされ「1」の
信号59を出力する一方、前記OR回路58から出力さ
れる論理和信号57が「0」から「1」に変化した時に
リセットされ「0」の信号59を出力するシングルフリ
ップフロップ60と、該シングルフリップフロップ60
から出力される信号59が「1」の場合にベッド材注入
弁24を開く開閉制御信号33’を出力する一方、前記
シングルフリップフロップ60から出力される信号59
が「0」の場合にNOT回路61によりベッド材注入弁
24を閉じる開閉制御信号33’を出力する開閉回路6
2とを有し、流動層10の層高を上昇させる場合或いは
ベッド材貯蔵タンク4内のベッド材Bのウォーミングを
行う場合には、ベッド材注入弁24を開く開閉制御信号
33’を前記オンディレイタイマ51に設定された時間
tだけパルスとして出力した後、ベッド材注入弁24を
閉じる開閉制御信号33’を前記設定器52に設定され
た時間t’だけパルスとして出力し、ベッド材注入弁2
4の開閉を繰り返し行わせることにより、所定の注入速
度でベッド材貯蔵タンク4内のベッド材Bを流動層ボイ
ラ本体3内に注入するようになっている。
The pulse generator 41 receives an opening / closing control signal 33 output from the level controller 29 and a warming command signal 43 output from a warming controller 42 described later. Is "1" (when the bed material injection valve 24 is opened to raise the bed height of the fluidized bed 10) or when the warming command signal 43 is "1" (in the bed material storage tank 4). When the bed material injection valve 24 is opened to warm the bed material B), the logical sum signal 4 of "1"
4 and an OR signal 44 output from the OR circuit 45 and a NOT signal 47 output from the NOT circuit 46 are input, and an AND signal 48 of both signals 44 and 47 is output. AND circuit 49 and the AND circuit 4
When the logical product signal 48 output from 9 is input and the logical product signal 48 changes from “0” to “1”, a delay occurs by a preset time t (for example, about 5 [sec]). An on-delay timer 51 that outputs a delay signal 50 that changes to “1” and a delay signal 50 that is output from the on-delay timer 51 are input, and a time t ′ (for example, 10 [ sec]), the delay signal 53 that changes to “1” with a delay
An on-delay timer 54 output to the OT circuit 46, and a delay signal 50 output from the on-delay timer 51
And an OR circuit 58 from which the NOT signal 56 of the OR signal 44 output from the OR circuit 45 via the NOT circuit 55 is input, and the OR signal 57 of the two signals 50 and 56 is output.
AND signal 48 output from the AND circuit 49
Is set when "0" changes from "0" to "1" and outputs a signal 59 of "1", while the OR signal 57 output from the OR circuit 58 is reset when the OR signal 57 changes from "0" to "1". A single flip-flop 60 for outputting a signal 59 of “0”;
The signal 59 output from the single flip-flop 60 outputs the open / close control signal 33 'for opening the bed material injection valve 24 when the signal 59 output from the
Circuit 6 that outputs an open / close control signal 33 ′ for closing the bed material injection valve 24 by the NOT circuit 61 when “0” is “0”.
When the bed height of the fluidized bed 10 is increased or when the bed material B in the bed material storage tank 4 is to be warmed, the opening / closing control signal 33 'for opening the bed material injection valve 24 is set as described above. After outputting as a pulse for the time t set in the on-delay timer 51, an opening / closing control signal 33 'for closing the bed material injection valve 24 is output as a pulse for the time t' set in the setting device 52, and the bed material injection is performed. Valve 2
By repeatedly opening and closing the bed 4, the bed material B in the bed material storage tank 4 is injected into the fluidized bed boiler main body 3 at a predetermined injection speed.

【0010】尚、前記ウォーミング制御装置42は、加
圧流動層ボイラ1の起動直後等のように、ベッド材貯蔵
タンク4内のベッド材Bの温度が低く、該ベッド材貯蔵
タンク4内の温度の低いベッド材Bを流動層ボイラ本体
3内に注入して暖める、いわゆるウォーミングを行う必
要がある場合に、ウォーミング指令信号43を出力する
ものである。
Incidentally, the warming control device 42 has a low temperature of the bed material B in the bed material storage tank 4 such as immediately after the start of the pressurized fluidized bed boiler 1 and the like. The warming command signal 43 is output when bed material B having a low temperature is injected into the fluidized bed boiler main body 3 to warm it, that is, when warming needs to be performed.

【0011】又、前記燃料供給装置8には、前記負荷指
令34に基づいて関数発生器36から出力される燃料制
御指令35が入力されていると共に、前記給水供給装置
12にも負荷指令34に基づいて関数発生器38から出
力される給水制御指令37が入力されている。尚、前記
燃料制御指令35は、前記図5のレベル制御指令39と
略同様に、図6に示される如く、負荷指令34の増減に
伴って略比例した関係で増減されるように予め設定され
ており、又、前記給水制御指令37も、前記図5のレベ
ル制御指令39と略同様に、図7に示される如く、負荷
指令34の増減に伴って略比例した関係で増減されるよ
うに予め設定されている。
Further, a fuel control command 35 output from a function generator 36 based on the load command 34 is input to the fuel supply device 8, and the water supply device 12 also receives the load command 34 The water supply control command 37 output from the function generator 38 based on this is input. The fuel control command 35 is set in advance so as to increase and decrease in a substantially proportional relationship with the increase and decrease of the load command 34, as shown in FIG. 6, in substantially the same manner as the level control command 39 of FIG. The water supply control command 37 is also increased and decreased in a substantially proportional relationship with the increase and decrease of the load command 34, as shown in FIG. 7, similarly to the level control command 39 of FIG. It is set in advance.

【0012】前述の如き従来の加圧流動層ボイラ1にお
ける通常の運転時においては、負荷指令34に基づいた
燃料制御指令35が関数発生器36から燃料供給装置8
に出力されて燃料9の供給量が制御され、且つ負荷指令
34に基づいた給水制御指令37が関数発生器38から
給水供給装置12に出力されて給水13の供給量が制御
されると共に、負荷指令34に基づいたレベル制御指令
39が関数発生器40からレベル制御装置29に出力さ
れて流動層10の層高が制御される。
During normal operation of the conventional pressurized fluidized-bed boiler 1 as described above, a fuel control command 35 based on a load command 34 is transmitted from the function generator 36 to the fuel supply device 8.
And the supply amount of the fuel 9 is controlled, and a water supply control command 37 based on the load command 34 is output from the function generator 38 to the water supply device 12 to control the supply amount of the water 13 and A level control command 39 based on the command 34 is output from the function generator 40 to the level control device 29 to control the bed height of the fluidized bed 10.

【0013】前記流動層10の層高の制御において、層
高を上昇させるためにベッド材注入弁24を開く場合に
は、レベル制御装置29から出力される開閉制御信号3
3が「1」としてパルス発生装置41のOR回路45へ
入力され、該OR回路45から出力される論理和信号4
4が「1」になると共に、NOT回路46から出力され
る否定信号47も「1」であるため、AND回路49か
ら出力される論理積信号48が「0」から「1」とな
り、シングルフリップフロップ60がセットされ、該シ
ングルフリップフロップ60から「1」の信号59が開
閉回路62へ出力され、該開閉回路62からベッド材注
入弁24を開く開閉制御信号33’が出力され、ベッド
材注入弁24が開かれる。
In controlling the bed height of the fluidized bed 10, when the bed material injection valve 24 is opened in order to raise the bed height, the opening / closing control signal 3 output from the level controller 29 is used.
3 is input to the OR circuit 45 of the pulse generator 41 as “1”, and the OR signal 4 output from the OR circuit 45
4 changes to “1” and the NOT signal 47 output from the NOT circuit 46 also changes to “1”, and the AND signal 48 output from the AND circuit 49 changes from “0” to “1”. The flip-flop 60 is set, a signal 59 of “1” is output from the single flip-flop 60 to the opening / closing circuit 62, and an opening / closing control signal 33 ′ for opening the bed material injection valve 24 is output from the opening / closing circuit 62. Valve 24 is opened.

【0014】前記AND回路49から出力される論理積
信号48が「0」から「1」に変化した後、オンディレ
イタイマ51に予め設定された時間t(例えば、5[s
ec]程度)が経過すると、該オンディレイタイマ51
から出力される遅延信号50が「0」から「1」とな
り、OR回路58から出力される論理和信号57が
「0」から「1」となって前記シングルフリップフロッ
プ60がリセットされ、該シングルフリップフロップ6
0から「0」の信号59が開閉回路62へ出力され、該
開閉回路62からベッド材注入弁24を閉じる開閉制御
信号33’が出力され、ベッド材注入弁24が閉じられ
る。
After the AND signal 48 output from the AND circuit 49 changes from "0" to "1", the ON delay timer 51 sets a predetermined time t (for example, 5 [s]).
ec]), the on-delay timer 51
, The OR signal 57 output from the OR circuit 58 changes from “0” to “1”, the single flip-flop 60 is reset, and the single flip-flop 60 is reset. Flip-flop 6
A signal 59 from 0 to "0" is output to the opening / closing circuit 62, and an opening / closing control signal 33 'for closing the bed material injection valve 24 is output from the opening / closing circuit 62, and the bed material injection valve 24 is closed.

【0015】前記オンディレイタイマ51から出力され
る遅延信号50が「0」から「1」に変化した後、設定
器52に予め設定された時間t’(例えば、10[se
c]程度)が経過すると、オンディレイタイマ54から
出力される遅延信号53が「0」から「1」となり、N
OT回路46から出力される否定信号47が「1」から
「0」となるため、前記AND回路49から出力される
論理積信号48が「1」から「0」となり、前記オンデ
ィレイタイマ51から出力される遅延信号50が「1」
から「0」となり、これにより、オンディレイタイマ5
4から出力される遅延信号53が「1」から「0」とな
り、NOT回路46から出力される否定信号47が
「0」から「1」となり、前記AND回路49から出力
される論理積信号48が「0」から「1」になる一方、
NOT回路55から出力される否定信号56は論理和信
号44が「1」である限り「0」のままであるため、O
R回路58に対して入力される遅延信号50と否定信号
56とが共に「0」となって、該OR回路58から出力
される論理和信号57が「1」から「0」となり、前記
リセットされていたシングルフリップフロップ60が再
びセットされ、該シングルフリップフロップ60から
「1」の信号59が開閉回路62へ出力され、該開閉回
路62からベッド材注入弁24を開く開閉制御信号3
3’が出力され、ベッド材注入弁24が再び開かれる。
After the delay signal 50 output from the on-delay timer 51 changes from "0" to "1", a predetermined time t '(for example, 10 [sec]) is set in the setting unit 52.
c)), the delay signal 53 output from the on-delay timer 54 changes from “0” to “1”, and N
Since the negation signal 47 output from the OT circuit 46 changes from “1” to “0”, the AND signal 48 output from the AND circuit 49 changes from “1” to “0”. The output delay signal 50 is "1"
From “0” to “0”.
4 changes from “1” to “0”, the NOT signal 47 output from the NOT circuit 46 changes from “0” to “1”, and the AND signal 48 output from the AND circuit 49 Changes from “0” to “1”,
The negation signal 56 output from the NOT circuit 55 remains "0" as long as the OR signal 44 is "1".
The delay signal 50 and the negation signal 56 input to the R circuit 58 both become "0", and the OR signal 57 output from the OR circuit 58 changes from "1" to "0", thereby resetting the reset signal. The set single flip-flop 60 is set again, and a signal 59 of “1” is output from the single flip-flop 60 to the opening / closing circuit 62, and the opening / closing control signal 3 for opening the bed material injection valve 24 from the opening / closing circuit 62.
3 'is output, and the bed material injection valve 24 is opened again.

【0016】以下、前述と同様の作動、即ち、ベッド材
注入弁24がオンディレイタイマ51に設定された時間
tだけ開いた後、設定器52に設定された時間t’だけ
閉じ、再び開くという、作動が繰り返し行われ、所定の
注入速度でベッド材貯蔵タンク4内のベッド材Bが流動
層ボイラ本体3内に注入され、流動層10の層高が上昇
される。
Hereinafter, the same operation as described above is performed. That is, after the bed material injection valve 24 is opened for a time t set in the on-delay timer 51, the bed material injection valve 24 is closed for a time t 'set in the setter 52 and then opened again. The operation is repeatedly performed, and the bed material B in the bed material storage tank 4 is injected into the fluidized bed boiler main body 3 at a predetermined injection speed, and the bed height of the fluidized bed 10 is raised.

【0017】一方、加圧流動層ボイラ1の起動直後等に
おいて、ベッド材貯蔵タンク4内のベッド材Bの温度が
低く、該ベッド材貯蔵タンク4内の温度の低いベッド材
Bを流動層ボイラ本体3内に注入して暖める、いわゆる
ウォーミングを行う必要がある場合に、ウォーミング制
御装置42からウォーミング指令信号43が出力される
と、前述の流動層10の層高を上昇させる場合と同様
に、ベッド材注入弁24がオンディレイタイマ51に設
定された時間tだけ開いた後、設定器52に設定された
時間t’だけ閉じ、再び開くという、作動が繰り返し行
われ、所定の注入速度でベッド材貯蔵タンク4内のベッ
ド材Bが流動層ボイラ本体3内に注入される。尚、ウォ
ーミングのためにベッド材貯蔵タンク4内のベッド材B
が流動層ボイラ本体3内に注入され、流動層10の層高
が負荷指令34に基づいたレベル制御指令39の層高よ
り高くなった分については、レベル制御装置29からベ
ッド材抜出弁23を開く開閉制御信号32が出力され、
注入された分のベッド材Bが流動層ボイラ本体3から抜
き出され、流動層10の層高は設定値に保持される。
On the other hand, immediately after the pressurized fluidized bed boiler 1 is started, the temperature of the bed material B in the bed material storage tank 4 is low, and the bed material B in the bed material storage tank 4 having a low temperature is transferred to the fluidized bed boiler. When it is necessary to perform warming by injecting into the main body 3, so-called warming is performed, and when the warming command signal 43 is output from the warming control device 42, the bed height of the fluidized bed 10 is increased. Similarly, after the bed material injection valve 24 opens for the time t set in the on-delay timer 51, closes and opens again for the time t 'set in the setting device 52, the operation is repeatedly performed, and the predetermined injection is performed. The bed material B in the bed material storage tank 4 is injected into the fluidized bed boiler main body 3 at a speed. The bed material B in the bed material storage tank 4 is used for warming.
Is injected into the fluidized-bed boiler main body 3, and when the bed height of the fluidized bed 10 is higher than the bed height of the level control command 39 based on the load command 34, the bed material extraction valve 23 from the level controller 29. Open / close control signal 32 is output,
The injected bed material B is extracted from the fluidized-bed boiler main body 3, and the bed height of the fluidized bed 10 is maintained at a set value.

【0018】[0018]

【発明が解決しようとする課題】しかしながら、前述の
如く、ウォーミングが行われる際のベッド材貯蔵タンク
4から流動層ボイラ本体3へのベッド材Bの注入速度
は、流動層ボイラ本体3内の層温度とベッド材貯蔵タン
ク4内下部のベッド材Bの温度には関係なく常に一定に
設定されているため、特に前記流動層ボイラ本体3内の
層温度とベッド材貯蔵タンク4内下部のベッド材Bの温
度との温度差が大きい時には、流動層ボイラ本体3内の
層温度が低下してしまうという欠点を有していた。
However, as described above, the rate of injection of the bed material B from the bed material storage tank 4 to the fluidized-bed boiler body 3 during warming is controlled by the flow rate in the fluidized-bed boiler body 3. Since the bed temperature is always set to be constant regardless of the bed temperature and the temperature of the bed material B in the lower part of the bed material storage tank 4, the bed temperature in the fluidized bed boiler body 3 and the bed in the lower part of the bed material storage tank 4 When the temperature difference from the temperature of the material B is large, there is a disadvantage that the bed temperature in the fluidized-bed boiler main body 3 decreases.

【0019】尚、図示していないが、ウォーミングの際
には、ベッド材注入弁24の開動作と連動する形で、関
数発生器36から燃料供給装置8へ出力される燃料制御
指令35にバイアスが掛けられるようになっているが、
これも、前記ベッド材Bの注入速度と同様、流動層ボイ
ラ本体3内の層温度とベッド材貯蔵タンク4内下部のベ
ッド材Bの温度には関係なく常に一定であり、しかも、
ベッド材注入弁24が開いている間(オンディレイタイ
マ51に設定された時間t)のみしかバイアスが掛から
ないため、燃料供給装置8がバイアス指令に追従せず、
流動層ボイラ本体3内の層温度の低下は避けられないの
が現状であった。
Although not shown, during warming, a fuel control command 35 output from the function generator 36 to the fuel supply device 8 is interlocked with the opening operation of the bed material injection valve 24. Although bias is applied,
This is also constant, regardless of the bed temperature in the fluidized-bed boiler body 3 and the temperature of the bed material B in the lower part of the bed material storage tank 4, similarly to the injection speed of the bed material B.
Since the bias is applied only while the bed material injection valve 24 is open (time t set in the on-delay timer 51), the fuel supply device 8 does not follow the bias command,
At present, it is inevitable that the bed temperature in the fluidized-bed boiler body 3 decreases.

【0020】本発明は、斯かる実情に鑑み、ベッド材貯
蔵タンク内のベッド材のウォーミングを行った際に、流
動層ボイラ本体内の層温度の低下を防止し得る加圧流動
層ボイラのベッド材貯蔵タンクウォーミング時における
層温度制御方法及び装置を提供しようとするものであ
る。
In view of such circumstances, the present invention provides a pressurized fluidized-bed boiler which can prevent a decrease in bed temperature in a fluidized-bed boiler body when a bed material in a bed material storage tank is warmed. It is an object of the present invention to provide a method and an apparatus for controlling a bed temperature during warming of a bed material storage tank.

【0021】[0021]

【課題を解決するための手段】本発明は、ベッド材貯蔵
タンク4内のベッド材Bのウォーミングを行う際、流動
層ボイラ本体3内の層温度63aとベッド材貯蔵タンク
4内下部のベッド材温度64aとの温度差65aを検出
し、該温度差65aに応じてベッド材貯蔵タンク4から
流動層ボイラ本体3へのベッド材Bの注入速度を変化さ
せると共に、前記温度差65aに応じて流動層ボイラ本
体3への燃料9供給量を変化させ、流動層ボイラ本体3
内の層温度63aを所要値に制御することを特徴とする
加圧流動層ボイラのベッド材貯蔵タンクウォーミング時
における層温度制御方法にかかるものである。
According to the present invention, when the bed material B in the bed material storage tank 4 is warmed, the bed temperature 63a in the fluidized-bed boiler body 3 and the bed in the lower part of the bed material storage tank 4 are controlled. The temperature difference 65a from the bed temperature 64a is detected, and the injection speed of the bed material B from the bed material storage tank 4 to the fluidized-bed boiler main body 3 is changed according to the temperature difference 65a. The supply amount of fuel 9 to the fluidized-bed boiler main body 3 is changed, and the fluidized-bed boiler main body 3 is changed.
The present invention relates to a method for controlling the bed temperature during warming of a bed material storage tank of a pressurized fluidized-bed boiler, wherein the bed temperature 63a is controlled to a required value.

【0022】又、本発明は、流動層ボイラ本体3内の層
温度63aを検出する層温度検出器63と、ベッド材貯
蔵タンク4内下部のベッド材温度64aを検出するベッ
ド材温度検出器64と、前記層温度検出器63で検出さ
れた層温度63aとベッド材温度検出器64で検出され
たベッド材温度64aとの差を求め、温度差65aを出
力する減算器65と、該減算器65から出力される温度
差65aに基づきウォーミング時のベッド材注入弁24
の開閉における閉時間t”を求めて出力する関数発生器
66と、レベル制御装置29からのベッド材注入弁24
の開閉制御信号33と、ウォーミング制御装置42から
のウォーミング指令信号43とが入力され、ウォーミン
グ時には、予め設定された時間tだけベッド材注入弁2
4を開いた後、前記関数発生器66から出力される閉時
間t”だけベッド材注入弁24を閉じ、これを繰り返す
開閉制御信号33’をベッド材注入弁24へ出力するパ
ルス発生装置41と、前記減算器65から出力される温
度差65aに基づきウォーミング時の燃料バイアス70
を求めて出力する関数発生器69と、ウォーミング時に
は、負荷指令34に基づいて燃料供給装置8へ出力され
る燃料制御指令35に対し、前記関数発生器69から出
力される燃料バイアス70を加算する加算器75とを備
えたことを特徴とする加圧流動層ボイラのベッド材貯蔵
タンクウォーミング時における層温度制御装置にかかる
ものである。
The present invention also provides a bed temperature detector 63 for detecting a bed temperature 63a in the fluidized bed boiler main body 3, and a bed material temperature detector 64 for detecting a bed material temperature 64a in the lower part of the bed material storage tank 4. And a subtracter 65 that calculates a difference between the bed temperature 63a detected by the bed temperature detector 63 and the bed material temperature 64a detected by the bed material temperature detector 64, and outputs a temperature difference 65a. The bed material injection valve 24 during warming based on the temperature difference 65a output from the
A function generator 66 for obtaining and outputting a closing time t ″ in opening and closing of the bed, and a bed material injection valve 24 from the level controller 29.
And a warming command signal 43 from the warming control device 42 are inputted. During warming, the bed material injection valve 2 is set for a preset time t.
4, the bed material injection valve 24 is closed for the closing time t ″ output from the function generator 66, and a pulse generator 41 that outputs to the bed material injection valve 24 an open / close control signal 33 ′ that repeats this operation. The fuel bias 70 during warming based on the temperature difference 65a output from the subtractor 65.
A fuel bias 70 output from the function generator 69 is added to a function generator 69 for calculating and outputting the fuel control command 35 output to the fuel supply device 8 based on the load command 34 during warming. The pressurized fluidized-bed boiler according to the present invention relates to a bed temperature control device during warming of a bed material storage tank in a pressurized fluidized-bed boiler.

【0023】上記手段によれば、以下のような作用が得
られる。
According to the above means, the following effects can be obtained.

【0024】本発明の加圧流動層ボイラのベッド材貯蔵
タンクウォーミング時における層温度制御方法において
は、ベッド材貯蔵タンク4内のベッド材Bのウォーミン
グを行う際、流動層ボイラ本体3内の層温度63aとベ
ッド材貯蔵タンク4内下部のベッド材温度64aとの温
度差65aを検出し、該温度差65aに応じてベッド材
貯蔵タンク4から流動層ボイラ本体3へのベッド材Bの
注入速度を変化させると共に、前記温度差65aに応じ
て流動層ボイラ本体3への燃料9供給量を変化させる
と、流動層ボイラ本体3内の層温度63aが所要値に制
御され、流動層ボイラ本体3内の層温度63aの低下を
抑制できる。
In the bed temperature control method for warming the bed material storage tank of the pressurized fluidized bed boiler of the present invention, when the bed material B in the bed material storage tank 4 is warmed, Of the bed material B from the bed material storage tank 4 to the fluidized-bed boiler main body 3 according to the temperature difference 65a between the bed temperature 63a of the bed material storage tank 4 and the bed material temperature 64a in the lower part of the bed material storage tank 4. When the injection rate is changed and the supply amount of the fuel 9 to the fluidized-bed boiler main body 3 is changed according to the temperature difference 65a, the bed temperature 63a in the fluidized-bed boiler main body 3 is controlled to a required value, and the fluidized-bed boiler is controlled. The lowering of the layer temperature 63a in the main body 3 can be suppressed.

【0025】又、本発明の加圧流動層ボイラのベッド材
貯蔵タンクウォーミング時における層温度制御装置にお
いては、ベッド材貯蔵タンク4内のベッド材Bのウォー
ミングを行う際、層温度検出器63によって流動層ボイ
ラ本体3内の層温度63aが検出されると共に、ベッド
材温度検出器64によってベッド材貯蔵タンク4内下部
のベッド材温度64aが検出され、前記層温度検出器6
3で検出された層温度63aとベッド材温度検出器64
で検出されたベッド材温度64aとの差が減算器65に
おいて求められ、温度差65aが出力され、該減算器6
5から出力される温度差65aに基づき関数発生器66
においてウォーミング時のベッド材注入弁24の開閉に
おける閉時間t”が求められて出力され、パルス発生装
置41からベッド材注入弁24へ、予め設定された時間
tだけベッド材注入弁24を開いた後、前記関数発生器
66から出力される閉時間t”だけベッド材注入弁24
を閉じ、これを繰り返す開閉制御信号33’が出力さ
れ、ベッド材注入弁24が時間tだけ開いた後、前記温
度差65aに基づく閉時間t”だけ閉じ、再び開くとい
う、作動が繰り返し行われ、温度差65aに対応した所
望の注入速度でベッド材貯蔵タンク4内のベッド材Bが
流動層ボイラ本体3内に注入され、同時に、前記減算器
65から出力される温度差65aに基づき関数発生器6
9においてウォーミング時の燃料バイアス70が求めら
れて出力され、負荷指令34に基づいて燃料供給装置8
へ出力される燃料制御指令35に対し、前記関数発生器
69から出力される燃料バイアス70が加算器75にお
いて加算され、温度差65aに応じて燃料9の供給量が
増加される。
In the bed temperature control apparatus for warming the bed material storage tank of the pressurized fluidized bed boiler according to the present invention, when the bed material B in the bed material storage tank 4 is warmed, the bed temperature detector is used. The bed temperature 63a in the fluidized-bed boiler main body 3 is detected by 63, and the bed material temperature 64a in the lower part of the bed material storage tank 4 is detected by the bed material temperature detector 64.
Bed temperature 63a and bed material temperature detector 64 detected at 3
The difference from the bed material temperature 64a detected by the subtractor 65 is obtained in the subtractor 65, and the temperature difference 65a is output.
5, a function generator 66 based on the temperature difference 65a output from
The closing time t ″ for opening and closing the bed material injection valve 24 during warming is determined and output, and the bed material injection valve 24 is opened from the pulse generator 41 to the bed material injection valve 24 for a preset time t. After that, the bed material injection valve 24 is closed for the closing time t ″ output from the function generator 66.
An opening / closing control signal 33 'that repeats this operation is output, and after the bed material injection valve 24 is opened for a time t, the operation is repeated for a closing time t "based on the temperature difference 65a and then opened again. The bed material B in the bed material storage tank 4 is injected into the fluidized bed boiler main body 3 at a desired injection speed corresponding to the temperature difference 65a, and at the same time, a function is generated based on the temperature difference 65a output from the subtractor 65. Vessel 6
9, a fuel bias 70 at the time of warming is obtained and output, and based on the load command 34, the fuel supply device 8
The fuel bias 70 output from the function generator 69 is added to the fuel control command 35 output to the control unit 35 by the adder 75, and the supply amount of the fuel 9 is increased according to the temperature difference 65a.

【0026】この結果、前記温度差65aが小さけれ
ば、ベッド材注入弁24の開閉における閉時間t”が短
く、ベッド材貯蔵タンク4から流動層ボイラ本体3への
ベッド材Bの注入速度は速くなる一方、燃料制御指令3
5に加算される燃料バイアス70は小さく、燃料9の増
加分は少ないが、前記温度差65aが大きければ、ベッ
ド材注入弁24の開閉における閉時間t”が長く、ベッ
ド材貯蔵タンク4から流動層ボイラ本体3へのベッド材
Bの注入速度は遅くなる一方、燃料制御指令35に加算
される燃料バイアス70は大きく、燃料9の増加分は多
くなるため、流動層ボイラ本体3内の層温度63aの低
下が抑制される。
As a result, if the temperature difference 65a is small, the closing time t ″ of opening and closing the bed material injection valve 24 is short, and the speed of pouring the bed material B from the bed material storage tank 4 into the fluidized bed boiler main body 3 is high. On the other hand, the fuel control command 3
5, the fuel bias 70 is small, and the increase of the fuel 9 is small. However, if the temperature difference 65a is large, the closing time t ″ in opening and closing the bed material injection valve 24 is long, and the flow from the bed material storage tank 4 is increased. While the injection speed of the bed material B into the bed boiler main body 3 is slowed down, the fuel bias 70 added to the fuel control command 35 is large, and the increase of the fuel 9 is increased, so that the bed temperature in the fluidized bed boiler main body 3 is increased. 63a is suppressed.

【0027】[0027]

【発明の実施の形態】以下、本発明の実施の形態を図示
例と共に説明する。
Embodiments of the present invention will be described below with reference to the drawings.

【0028】図1〜図3は本発明を実施する形態の一例
であって、図中、図4〜図7と同一の符号を付した部分
は同一物を表わしており、図1中、63は流動層ボイラ
本体3内の層温度63aを検出する層温度検出器、64
はベッド材貯蔵タンク4内下部のベッド材温度64aを
検出するベッド材温度検出器、65は前記層温度検出器
63で検出された層温度63aとベッド材温度検出器6
4で検出されたベッド材温度64aとの差を求め、温度
差65aを出力する減算器、66は前記減算器65から
出力される温度差65aに基づきウォーミング時のベッ
ド材注入弁24の開閉における閉時間t”を求めて出力
する関数発生器、67はレベル制御装置29からベッド
材注入弁24を開く開閉制御信号33が出力された時に
は設定器52に設定された時間t’を設定信号68とし
てパルス発生装置41のオンディレイタイマ54へ出力
する(b→c側へ切り換えられる)一方、前記レベル制
御装置29からベッド材注入弁24を開く開閉制御信号
33が出力されていないウォーミング時には前記関数発
生器66から出力される閉時間t”を設定信号68とし
てパルス発生装置41のオンディレイタイマ54へ出力
する(a→c側へ切り換えられる)切換リレー、69は
前記減算器65から出力される温度差65aに基づきウ
ォーミング時の燃料バイアス70を求めて出力する関数
発生器、71は非ウォーミング時の燃料バイアスとして
零の設定信号72が設定された設定器、73はレベル制
御装置29からベッド材注入弁24を開く開閉制御信号
33が出力された時には設定器71に設定された設定信
号72を設定信号74として出力する(b→c側へ切り
換えられる)一方、前記レベル制御装置29からベッド
材注入弁24を開く開閉制御信号33が出力されていな
いウォーミング時には前記関数発生器69から出力され
る燃料バイアス70を設定信号74として出力する(a
→c側へ切り換えられる)切換リレー、75は負荷指令
34に基づいて燃料供給装置8へ出力される燃料制御指
令35に対し、前記切換リレー73から出力される設定
信号74を加算する加算器であり、ベッド材貯蔵タンク
4内のベッド材Bのウォーミングを行う際には、流動層
ボイラ本体3内の層温度63aとベッド材貯蔵タンク4
内下部のベッド材温度64aとの温度差65aに応じ
て、関数発生器66から出力される閉時間t”を切換リ
レー67を介して設定信号68としてパルス発生装置4
1のオンディレイタイマ54へ入力し、ベッド材貯蔵タ
ンク4から流動層ボイラ本体3へのベッド材Bの注入速
度を変化させると共に、前記温度差65aに応じて、関
数発生器69から出力される燃料バイアス70を切換リ
レー73を介して設定信号74として加算器75へ出力
し、流動層ボイラ本体3への燃料9の供給量を変化さ
せ、流動層ボイラ本体3内の層温度63aを所要値に制
御してその低下を防止するよう構成したものである。
FIGS. 1 to 3 show an example of an embodiment of the present invention. In the drawings, portions denoted by the same reference numerals as those in FIGS. 4 to 7 represent the same components. A bed temperature detector 64 for detecting a bed temperature 63a in the fluidized bed boiler main body 3;
Reference numeral 65 denotes a bed material temperature detector for detecting a bed material temperature 64a in the lower portion of the bed material storage tank 4. Reference numeral 65 denotes a bed temperature 63a detected by the bed temperature detector 63 and a bed material temperature detector 6.
The subtracter 66 calculates the difference from the bed material temperature 64a detected in step 4, and outputs a temperature difference 65a. The opening / closing of the bed material injection valve 24 during warming is performed based on the temperature difference 65a output from the subtractor 65. Is a function generator that calculates and outputs the closing time t ″ in the above. When the opening / closing control signal 33 for opening the bed material injection valve 24 is output from the level control device 29, the function generator 67 sets the time t ′ set in the setting device 52 to the setting signal. At the time of warming, when the opening / closing control signal 33 for opening the bed material injection valve 24 is not output from the level control device 29 while being output to the on-delay timer 54 of the pulse generation device 41 (switched from b to c side) as 68. The closing time t ″ output from the function generator 66 is output as a setting signal 68 to the on-delay timer 54 of the pulse generator 41 (switching to the a → c side). The switching relay 69 is a function generator that calculates and outputs the fuel bias 70 at the time of warming based on the temperature difference 65a output from the subtractor 65, and 71 is a zero as the fuel bias at the time of non-warming. The setting device 73 to which the setting signal 72 has been set, 73 outputs the setting signal 72 set in the setting device 71 as the setting signal 74 when the opening / closing control signal 33 for opening the bed material injection valve 24 is output from the level control device 29. On the other hand, the fuel bias 70 output from the function generator 69 is set at the time of warming in which the open / close control signal 33 for opening the bed material injection valve 24 is not output from the level control device 29. Output as signal 74 (a
A switching relay 75 is an adder for adding a setting signal 74 output from the switching relay 73 to a fuel control command 35 output to the fuel supply device 8 based on the load command 34. When warming the bed material B in the bed material storage tank 4, the bed temperature 63a in the fluidized bed boiler main body 3 and the bed material storage tank 4
In response to the temperature difference 65a between the inner and lower bed material temperatures 64a, the closing time t ″ output from the function generator 66 is set as a setting signal 68 via the switching relay 67 as the pulse generator 4.
1 to the on-delay timer 54 to change the injection speed of the bed material B from the bed material storage tank 4 to the fluidized-bed boiler body 3 and output from the function generator 69 according to the temperature difference 65a. The fuel bias 70 is output to the adder 75 as a setting signal 74 via the switching relay 73 to change the supply amount of the fuel 9 to the fluidized-bed boiler main body 3, and the bed temperature 63a in the fluidized-bed boiler main body 3 is set to a required value. In order to prevent the decrease.

【0029】尚、前記関数発生器66には、図2に示す
ような関数が設定されており、該関数は、前記温度差6
5aが約200[℃]以下の場合にはベッド材注入弁2
4の開閉における閉時間t”をおよそ10[sec]程
度とし、前記温度差65aが約200〜800[℃]の
範囲内である場合にはベッド材注入弁24の開閉におけ
る閉時間t”を、およそ10〜25[sec]の間で前
記温度差65aの増減に対し略比例させて増減させ、更
に、前記温度差65aが約800[℃]以上の場合には
ベッド材注入弁24の開閉における閉時間t”をおよそ
25[sec]程度とすることを表わしている。又、前
記関数発生器69には、図3に示すような関数が設定さ
れており、該関数は、前記温度差65aが約200
[℃]以下の場合には燃料バイアス70を零とし、前記
温度差65aが約200以上の場合には燃料バイアス7
0を、前記温度差65aの増減に対し所望のカーブで増
減させることを表わしている。
A function as shown in FIG. 2 is set in the function generator 66.
When 5a is about 200 ° C. or less, the bed material injection valve 2
4 is about 10 [sec], and when the temperature difference 65a is in the range of about 200 to 800 [° C.], the closing time t ″ for opening and closing the bed material injection valve 24 is The temperature difference 65a is increased or decreased substantially in proportion to the increase or decrease of the temperature difference 65a between about 10 to 25 [sec]. Further, when the temperature difference 65a is about 800 [° C.] or more, opening and closing of the bed material injection valve 24 is performed. Is set to about 25 [sec]. A function as shown in FIG. 3 is set in the function generator 69, and the function is based on the temperature difference. 65a is about 200
When the temperature difference is less than 200 ° C., the fuel bias 70 is set to zero.
0 is increased or decreased in a desired curve with respect to the increase or decrease in the temperature difference 65a.

【0030】次に、上記図示例の作動を説明する。Next, the operation of the illustrated example will be described.

【0031】加圧流動層ボイラ1の起動直後等におい
て、ベッド材貯蔵タンク4内のベッド材Bの温度が低
く、該ベッド材貯蔵タンク4内の温度の低いベッド材B
を流動層ボイラ本体3内に注入して暖める、いわゆるウ
ォーミングを行う必要がある場合に、ウォーミング制御
装置42からウォーミング指令信号43が出力される
と、パルス発生装置41のOR回路45から出力される
論理和信号44が「1」になると共に、NOT回路46
から出力される否定信号47も「1」であるため、AN
D回路49から出力される論理積信号48が「0」から
「1」となり、シングルフリップフロップ60がセット
され、該シングルフリップフロップ60から「1」の信
号59が開閉回路62へ出力され、該開閉回路62から
ベッド材注入弁24を開く開閉制御信号33’が出力さ
れ、ベッド材注入弁24が開かれる。
Immediately after the pressurized fluidized-bed boiler 1 is started, for example, the temperature of the bed material B in the bed material storage tank 4 is low, and the bed material B in the bed material storage tank 4 is low in temperature.
When the warming command signal 43 is output from the warming control device 42 when it is necessary to perform warming by injecting into the fluidized bed boiler main body 3, so-called warming, the OR circuit 45 of the pulse generating device 41 When the output OR signal 44 becomes “1”, the NOT circuit 46
Since the negation signal 47 output from is also "1", AN
The AND signal 48 output from the D circuit 49 changes from “0” to “1”, the single flip-flop 60 is set, and a signal 59 of “1” is output from the single flip-flop 60 to the switching circuit 62. An opening / closing control signal 33 'for opening the bed material injection valve 24 is output from the opening / closing circuit 62, and the bed material injection valve 24 is opened.

【0032】前記AND回路49から出力される論理積
信号48が「0」から「1」に変化した後、オンディレ
イタイマ51に予め設定された時間t(例えば、5[s
ec]程度)が経過すると、該オンディレイタイマ51
から出力される遅延信号50が「0」から「1」とな
り、OR回路58から出力される論理和信号57が
「0」から「1」となって前記シングルフリップフロッ
プ60がリセットされ、該シングルフリップフロップ6
0から「0」の信号59が開閉回路62へ出力され、該
開閉回路62からベッド材注入弁24を閉じる開閉制御
信号33’が出力され、ベッド材注入弁24が閉じられ
る。
After the AND signal 48 output from the AND circuit 49 changes from "0" to "1", a time t (for example, 5 [s]
ec]), the on-delay timer 51
, The OR signal 57 output from the OR circuit 58 changes from “0” to “1”, the single flip-flop 60 is reset, and the single flip-flop 60 is reset. Flip-flop 6
A signal 59 from 0 to "0" is output to the opening / closing circuit 62, and an opening / closing control signal 33 'for closing the bed material injection valve 24 is output from the opening / closing circuit 62, and the bed material injection valve 24 is closed.

【0033】ここで、流動層ボイラ本体3内の層温度6
3aは層温度検出器63によって検出されていると共
に、ベッド材貯蔵タンク4内下部のベッド材温度64a
はベッド材温度検出器64によって検出されており、前
記層温度検出器63で検出された層温度63aとベッド
材温度検出器64で検出されたベッド材温度64aとの
温度差65aが減算器65において求められて関数発生
器66と関数発生器69へ出力され、関数発生器66に
おいて前記減算器65から出力される温度差65aに基
づきウォーミング時のベッド材注入弁24の開閉におけ
る閉時間t”が求められ切換リレー67(a→c側へ切
り換えられている)を介して設定信号68としてパルス
発生装置41のオンディレイタイマ54へ入力されてい
る。
Here, the bed temperature 6 in the fluidized bed boiler body 3
3a is detected by the bed temperature detector 63 and the bed material temperature 64a in the lower part of the bed material storage tank 4
Is detected by the bed material temperature detector 64, and the temperature difference 65 a between the bed temperature 63 a detected by the bed temperature detector 63 and the bed material temperature 64 a detected by the bed material temperature detector 64 is subtracted by the subtractor 65. Is output to the function generator 66 and the function generator 69, and based on the temperature difference 65a output from the subtractor 65 in the function generator 66, the closing time t for opening and closing the bed material injection valve 24 during warming. Is input as a setting signal 68 to the on-delay timer 54 of the pulse generator 41 via the switching relay 67 (switched from the side a to the side c).

【0034】このため、前記オンディレイタイマ51か
ら出力される遅延信号50が「0」から「1」に変化し
た後、前記温度差65aに基づく閉時間t”が経過する
と、オンディレイタイマ54から出力される遅延信号5
3が「0」から「1」となり、NOT回路46から出力
される否定信号47が「1」から「0」となるため、前
記AND回路49から出力される論理積信号48が
「1」から「0」となり、前記オンディレイタイマ51
から出力される遅延信号50が「1」から「0」とな
り、これにより、オンディレイタイマ54から出力され
る遅延信号53が「1」から「0」となり、NOT回路
46から出力される否定信号47が「0」から「1」と
なり、前記AND回路49から出力される論理積信号4
8が「0」から「1」になる一方、NOT回路55から
出力される否定信号56は論理和信号44が「1」であ
る限り「0」のままであるため、OR回路58に対して
入力される遅延信号50と否定信号56とが共に「0」
となって、該OR回路58から出力される論理和信号5
7が「1」から「0」となり、前記リセットされていた
シングルフリップフロップ60が再びセットされ、該シ
ングルフリップフロップ60から「1」の信号59が開
閉回路62へ出力され、該開閉回路62からベッド材注
入弁24を開く開閉制御信号33’が出力され、ベッド
材注入弁24が再び開かれる。
Therefore, after the delay signal 50 output from the on-delay timer 51 changes from "0" to "1", when the closing time t "based on the temperature difference 65a elapses, the on-delay timer 54 outputs Output delay signal 5
3 changes from “0” to “1”, and the negation signal 47 output from the NOT circuit 46 changes from “1” to “0”, and the AND signal 48 output from the AND circuit 49 changes from “1” to “1”. "0" and the on-delay timer 51
From the "1" to "0", the delay signal 53 output from the on-delay timer 54 changes from "1" to "0", and the negative signal output from the NOT circuit 46 47 changes from “0” to “1”, and the AND signal 4 output from the AND circuit 49
8 changes from “0” to “1”, while the negation signal 56 output from the NOT circuit 55 remains “0” as long as the OR signal 44 is “1”. Both the input delay signal 50 and negative signal 56 are “0”
And the logical sum signal 5 output from the OR circuit 58
7 changes from “1” to “0”, the single flip-flop 60 that has been reset is set again, and a signal 59 of “1” is output from the single flip-flop 60 to the switching circuit 62. An opening / closing control signal 33 'for opening the bed material injection valve 24 is output, and the bed material injection valve 24 is opened again.

【0035】以下、前述と同様の作動、即ち、ベッド材
注入弁24がオンディレイタイマ51に設定された時間
tだけ開いた後、前記温度差65aに基づく閉時間t”
だけ閉じ、再び開くという、作動が繰り返し行われ、温
度差65aに対応した所望の注入速度でベッド材貯蔵タ
ンク4内のベッド材Bが流動層ボイラ本体3内に注入さ
れる。
Hereinafter, the same operation as described above, that is, after the bed material injection valve 24 is opened for the time t set in the on-delay timer 51, the closing time t ″ based on the temperature difference 65a
The bed material B in the bed material storage tank 4 is injected into the fluidized bed boiler main body 3 at a desired injection speed corresponding to the temperature difference 65a.

【0036】これと同時に、前記関数発生器69におい
て前記減算器65から出力される温度差65aに基づき
ウォーミング時の燃料バイアス70が求められ切換リレ
ー73(a→c側へ切り換えられている)を介して設定
信号74として加算器75へ入力され、該加算器75に
おいて負荷指令34に基づいて燃料供給装置8へ出力さ
れる燃料制御指令35に対し、前記切換リレー73から
出力される設定信号74、即ち温度差65aに対応した
所望の燃料バイアス70が加算され、温度差65aに応
じて燃料9の供給量が増加される。
At the same time, the function generator 69 obtains the fuel bias 70 at the time of warming based on the temperature difference 65a output from the subtractor 65, and the switching relay 73 (switched from a to c side). A setting signal output from the switching relay 73 in response to a fuel control command 35 output to the fuel supply device 8 based on the load command 34 in the adder 75 as a setting signal 74 74, that is, the desired fuel bias 70 corresponding to the temperature difference 65a is added, and the supply amount of the fuel 9 is increased according to the temperature difference 65a.

【0037】この結果、前記温度差65aが小さけれ
ば、ベッド材注入弁24の開閉における閉時間t”が短
く、ベッド材貯蔵タンク4から流動層ボイラ本体3への
ベッド材Bの注入速度は速くなる一方、燃料制御指令3
5に加算される燃料バイアス70は小さく、燃料9の増
加分は少ないが、前記温度差65aが大きければ、ベッ
ド材注入弁24の開閉における閉時間t”が長く、ベッ
ド材貯蔵タンク4から流動層ボイラ本体3へのベッド材
Bの注入速度は遅くなる一方、燃料制御指令35に加算
される燃料バイアス70は大きく、燃料9の増加分は多
くなるため、流動層ボイラ本体3内の層温度63aの低
下が抑制される。
As a result, if the temperature difference 65a is small, the closing time t ″ of opening and closing the bed material injection valve 24 is short, and the speed of injecting the bed material B from the bed material storage tank 4 to the fluidized bed boiler main body 3 is high. On the other hand, the fuel control command 3
5, the fuel bias 70 is small, and the increase of the fuel 9 is small. However, if the temperature difference 65a is large, the closing time t ″ in opening and closing the bed material injection valve 24 is long, and the flow from the bed material storage tank 4 is increased. While the injection speed of the bed material B into the bed boiler main body 3 is slowed down, the fuel bias 70 added to the fuel control command 35 is large, and the increase of the fuel 9 is increased, so that the bed temperature in the fluidized bed boiler main body 3 is increased. 63a is suppressed.

【0038】尚、加圧流動層ボイラ1の運転時におい
て、流動層10の層高を上昇させるためにベッド材注入
弁24を開く場合に、レベル制御装置29から「1」の
開閉制御信号33が出力されると、前記切換リレー67
がa→c側の状態からb→c側へ切り換えられ、設定器
52に設定された時間t’が設定信号68としてパルス
発生装置41のオンディレイタイマ54へ出力され、従
来の場合と同様、ベッド材注入弁24がオンディレイタ
イマ51に設定された時間tだけ開いた後、設定器52
に設定された時間t’だけ閉じ、再び開くという、作動
が繰り返し行われ、所定の注入速度でベッド材貯蔵タン
ク4内のベッド材Bが流動層ボイラ本体3内に注入さ
れ、流動層10の層高が上昇される一方、前記切換リレ
ー73がa→c側の状態からb→c側へ切り換えられ、
設定器71に設定された零の設定信号72が設定信号7
4として加算器75へ出力され、従来の場合と同様、負
荷指令34に基づいて燃料供給装置8へ出力される燃料
制御指令35により燃料9の供給量が制御される。
During operation of the pressurized fluidized-bed boiler 1, when the bed material injection valve 24 is opened to raise the bed height of the fluidized bed 10, the open / close control signal 33 of “1” is sent from the level controller 29. Is output, the switching relay 67
Is switched from the state of a → c to the side of b → c, and the time t ′ set in the setting unit 52 is output as the setting signal 68 to the on-delay timer 54 of the pulse generator 41, and as in the conventional case, After the bed material injection valve 24 is opened for the time t set in the on-delay timer 51, the setting device 52
The operation of closing and reopening only for the time t ′ set in the above is repeatedly performed, and the bed material B in the bed material storage tank 4 is injected into the fluidized bed boiler main body 3 at a predetermined injection speed, and the fluidized bed 10 While the layer height is raised, the switching relay 73 is switched from the state of a → c to the side of b → c,
The zero setting signal 72 set in the setting device 71 is the setting signal 7
4 is output to the adder 75, and the supply amount of the fuel 9 is controlled by the fuel control command 35 output to the fuel supply device 8 based on the load command 34 as in the conventional case.

【0039】こうして、ベッド材貯蔵タンク4内のベッ
ド材Bのウォーミングを行った際に、流動層ボイラ本体
3内の層温度の低下を防止し得る。
Thus, when the bed material B in the bed material storage tank 4 is warmed, the bed temperature in the fluidized bed boiler main body 3 can be prevented from lowering.

【0040】尚、本発明の加圧流動層ボイラのベッド材
貯蔵タンクウォーミング時における層温度制御方法及び
装置は、上述の図示例にのみ限定されるものではなく、
本発明の要旨を逸脱しない範囲内において種々変更を加
え得ることは勿論である。
The method and apparatus for controlling the bed temperature of the pressurized fluidized-bed boiler of the present invention at the time of warming the bed material storage tank are not limited to the above-described examples.
It goes without saying that various changes can be made without departing from the spirit of the present invention.

【0041】[0041]

【発明の効果】以上、説明したように本発明の加圧流動
層ボイラのベッド材貯蔵タンクウォーミング時における
層温度制御方法及び装置によれば、ベッド材貯蔵タンク
内のベッド材のウォーミングを行った際に、流動層ボイ
ラ本体内の層温度の低下を防止し得るという優れた効果
を奏し得る。
As described above, according to the bed temperature control method and apparatus for the bed material storage tank of the pressurized fluidized bed boiler of the present invention, the bed material in the bed material storage tank is warmed. When performed, an excellent effect of preventing a decrease in the bed temperature in the fluidized bed boiler main body can be achieved.

【図面の簡単な説明】[Brief description of the drawings]

【図1】本発明を実施する形態の一例の概要構成図であ
る。
FIG. 1 is a schematic configuration diagram of an example of an embodiment of the present invention.

【図2】図1に示す関数発生器66に設定された関数を
表わす線図である。
FIG. 2 is a diagram showing functions set in a function generator 66 shown in FIG.

【図3】図1に示す関数発生器69に設定された関数を
表わす線図である。
FIG. 3 is a diagram showing functions set in function generator 69 shown in FIG. 1;

【図4】従来例の概要構成図である。FIG. 4 is a schematic configuration diagram of a conventional example.

【図5】図1及び図4に示す関数発生器40に設定され
た関数を表わす線図である。
FIG. 5 is a diagram showing functions set in a function generator 40 shown in FIGS. 1 and 4;

【図6】図1及び図4に示す関数発生器36に設定され
た関数を表わす線図である。
FIG. 6 is a diagram showing a function set in a function generator shown in FIGS. 1 and 4;

【図7】図1及び図4に示す関数発生器38に設定され
た関数を表わす線図である。
FIG. 7 is a diagram showing functions set in a function generator shown in FIGS. 1 and 4;

【符号の説明】[Explanation of symbols]

1 加圧流動層ボイラ 3 流動層ボイラ本体 4 ベッド材貯蔵タンク 8 燃料供給装置 9 燃料 10 流動層 24 ベッド材注入弁 29 レベル制御装置 33 開閉制御信号 33’ 開閉制御信号 34 負荷指令 35 燃料制御指令 41 パルス発生装置 42 ウォーミング制御装置 43 ウォーミング指令信号 51 オンディレイタイマ 54 オンディレイタイマ 63 層温度検出器 63a 層温度 64 ベッド材温度検出器 64a ベッド材温度 65 減算器 65a 温度差 66 関数発生器 69 関数発生器 70 燃料バイアス 75 加算器 B ベッド材 t 時間 t” 閉時間 DESCRIPTION OF SYMBOLS 1 Pressurized fluidized-bed boiler 3 Fluidized-bed boiler main body 4 Bed material storage tank 8 Fuel supply device 9 Fuel 10 Fluidized bed 24 Bed material injection valve 29 Level control device 33 Opening / closing control signal 33 'Opening / closing control signal 34 Load command 35 Fuel control command Reference Signs List 41 pulse generator 42 warming controller 43 warming command signal 51 on-delay timer 54 on-delay timer 63 layer temperature detector 63a layer temperature 64 bed material temperature detector 64a bed material temperature 65 subtractor 65a temperature difference 66 function generator 69 Function generator 70 Fuel bias 75 Adder B Bed material t Time t "Closing time

Claims (2)

【特許請求の範囲】[Claims] 【請求項1】 ベッド材貯蔵タンク(4)内のベッド材
(B)のウォーミングを行う際、流動層ボイラ本体
(3)内の層温度(63a)とベッド材貯蔵タンク
(4)内下部のベッド材温度(64a)との温度差(6
5a)を検出し、該温度差(65a)に応じてベッド材
貯蔵タンク(4)から流動層ボイラ本体(3)へのベッ
ド材(B)の注入速度を変化させると共に、前記温度差
(65a)に応じて流動層ボイラ本体(3)への燃料
(9)供給量を変化させ、流動層ボイラ本体(3)内の
層温度(63a)を所要値に制御することを特徴とする
加圧流動層ボイラのベッド材貯蔵タンクウォーミング時
における層温度制御方法。
When the bed material (B) in the bed material storage tank (4) is warmed, the bed temperature (63a) in the fluidized bed boiler main body (3) and the lower part in the bed material storage tank (4). Temperature difference (6a) from the bed material temperature (64a)
5a) is detected, the injection speed of the bed material (B) from the bed material storage tank (4) to the fluidized bed boiler body (3) is changed according to the temperature difference (65a), and the temperature difference (65a) is detected. ), The amount of fuel (9) supplied to the fluidized-bed boiler body (3) is changed, and the bed temperature (63a) in the fluidized-bed boiler body (3) is controlled to a required value. A bed temperature control method during bed material storage tank warming of a fluidized bed boiler.
【請求項2】 流動層ボイラ本体(3)内の層温度(6
3a)を検出する層温度検出器(63)と、 ベッド材貯蔵タンク(4)内下部のベッド材温度(64
a)を検出するベッド材温度検出器(64)と、 前記層温度検出器(63)で検出された層温度(63
a)とベッド材温度検出器(64)で検出されたベッド
材温度(64a)との差を求め、温度差(65a)を出
力する減算器(65)と、 該減算器(65)から出力される温度差(65a)に基
づきウォーミング時のベッド材注入弁(24)の開閉に
おける閉時間(t”)を求めて出力する関数発生器(6
6)と、 レベル制御装置(29)からのベッド材注入弁(24)
の開閉制御信号(33)と、ウォーミング制御装置(4
2)からのウォーミング指令信号(43)とが入力さ
れ、ウォーミング時には、予め設定された時間(t)だ
けベッド材注入弁(24)を開いた後、前記関数発生器
(66)から出力される閉時間(t”)だけベッド材注
入弁(24)を閉じ、これを繰り返す開閉制御信号(3
3’)をベッド材注入弁(24)へ出力するパルス発生
装置(41)と、 前記減算器(65)から出力される温度差(65a)に
基づきウォーミング時の燃料バイアス(70)を求めて
出力する関数発生器(69)と、 ウォーミング時には、負荷指令(34)に基づいて燃料
供給装置(8)へ出力される燃料制御指令(35)に対
し、前記関数発生器(69)から出力される燃料バイア
ス(70)を加算する加算器(75)とを備えたことを
特徴とする加圧流動層ボイラのベッド材貯蔵タンクウォ
ーミング時における層温度制御装置。
2. The bed temperature (6) in the fluidized bed boiler body (3).
3a) a bed temperature detector (63), and a bed material temperature (64) in the lower part of the bed material storage tank (4).
a) a bed material temperature detector (64) for detecting a), and a bed temperature (63) detected by the bed temperature detector (63).
a) a difference between the bed material temperature (64a) detected by the bed material temperature detector (64) and a subtractor (65) for outputting a temperature difference (65a); and an output from the subtracter (65). A function generator (6) that calculates and outputs a closing time (t ″) for opening and closing the bed material injection valve (24) at the time of warming based on the temperature difference (65a) obtained
6) and the bed material injection valve (24) from the level control device (29)
Open / close control signal (33) and the warming control device (4
The warming command signal (43) from (2) is input. During warming, the bed material injection valve (24) is opened for a preset time (t), and then output from the function generator (66). The bed material injection valve (24) is closed for the closing time (t ″) that is performed, and the opening / closing control signal (3) is repeated.
A fuel bias (70) at the time of warming is obtained based on a pulse generator (41) that outputs 3 ′) to the bed material injection valve (24) and a temperature difference (65a) output from the subtracter (65). A function generator (69) for outputting a fuel control command (35) output to the fuel supply device (8) based on a load command (34) during warming. A bed temperature control device for warming a bed storage tank of a pressurized fluidized-bed boiler, comprising: an adder (75) for adding an output fuel bias (70).
JP17025397A 1997-06-26 1997-06-26 Method and apparatus for controlling bed temperature during warming bed storage tank of pressurized fluidized bed boiler Expired - Lifetime JP3826498B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP17025397A JP3826498B2 (en) 1997-06-26 1997-06-26 Method and apparatus for controlling bed temperature during warming bed storage tank of pressurized fluidized bed boiler

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP17025397A JP3826498B2 (en) 1997-06-26 1997-06-26 Method and apparatus for controlling bed temperature during warming bed storage tank of pressurized fluidized bed boiler

Publications (2)

Publication Number Publication Date
JPH1114008A true JPH1114008A (en) 1999-01-22
JP3826498B2 JP3826498B2 (en) 2006-09-27

Family

ID=15901521

Family Applications (1)

Application Number Title Priority Date Filing Date
JP17025397A Expired - Lifetime JP3826498B2 (en) 1997-06-26 1997-06-26 Method and apparatus for controlling bed temperature during warming bed storage tank of pressurized fluidized bed boiler

Country Status (1)

Country Link
JP (1) JP3826498B2 (en)

Also Published As

Publication number Publication date
JP3826498B2 (en) 2006-09-27

Similar Documents

Publication Publication Date Title
JPH1114008A (en) Bed temperature controlling method and device at the time of warming bed material storage tank of pressurized fluidized bed boiler
JP2002081606A (en) Method for controlling boiler
JP3755242B2 (en) Steam temperature controller for pressurized fluidized bed boiler
JP3794074B2 (en) Steam temperature control method and apparatus in pressurized fluidized bed boiler
JP3837605B2 (en) Pressurized fluidized bed combined power generation system and control method thereof
JP4090047B2 (en) Boiler combustion control method and combustion control apparatus
JPH11325416A (en) Method and device for suppressing decrease of bed temperature with increase in bed height of fluidized bed boiler
JPH1114002A (en) Steam temperature controller for pressurized fluidized bed combustion boiler
JP3928104B2 (en) Pressurized fluidized bed combined power generation system and control method and control apparatus therefor
JP2554492Y2 (en) Control device for pressurized fluidized bed boiler
JP3085792B2 (en) Control device for pressurized fluidized bed boiler
JPH08296802A (en) Control method and apparatus for steam temperature of pressurized fluidized bed boiler
JP2570122Y2 (en) Fluid bed boiler controller
JP2634358B2 (en) Pressurized fluidized bed boiler
JP2005127576A (en) Combustion control unit of boiler
JPH06281109A (en) Bed height control method for pressurized fluidized bed type combustion device and bed height control device
JP2003056808A (en) Fluidized bed height calculating unit
JP3755240B2 (en) Steam temperature controller for pressurized fluidized bed boiler
JP3487032B2 (en) Bed height control method and apparatus for pressurized fluidized bed boiler
JP3680345B2 (en) Steam temperature control method and apparatus for pressurized fluidized bed boiler
JP2000130736A (en) Method and device for controlling pressure of soot blower
JPS5977202A (en) Controller for temperature of steam
JPH04297701A (en) Steam temperature controller for pressurized fluidized bed boiler
JPH07286704A (en) Fluidized-bed temperature controlling method for fluidized-bed burner
JPH0611107A (en) Device for controlling boiler with pressurized fluidized bed

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20040512

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20060526

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20060613

A61 First payment of annual fees (during grant procedure)

Effective date: 20060626

Free format text: JAPANESE INTERMEDIATE CODE: A61

S533 Written request for registration of change of name

Free format text: JAPANESE INTERMEDIATE CODE: R313533

FPAY Renewal fee payment (prs date is renewal date of database)

Free format text: PAYMENT UNTIL: 20090714

Year of fee payment: 3

R350 Written notification of registration of transfer

Free format text: JAPANESE INTERMEDIATE CODE: R350

FPAY Renewal fee payment (prs date is renewal date of database)

Free format text: PAYMENT UNTIL: 20090714

Year of fee payment: 3

FPAY Renewal fee payment (prs date is renewal date of database)

Free format text: PAYMENT UNTIL: 20100714

Year of fee payment: 4