JPH10331107A - Method for constructing stone pavement and stone block unit - Google Patents

Method for constructing stone pavement and stone block unit

Info

Publication number
JPH10331107A
JPH10331107A JP15589697A JP15589697A JPH10331107A JP H10331107 A JPH10331107 A JP H10331107A JP 15589697 A JP15589697 A JP 15589697A JP 15589697 A JP15589697 A JP 15589697A JP H10331107 A JPH10331107 A JP H10331107A
Authority
JP
Japan
Prior art keywords
stone
asphalt
joint
stone block
blocks
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP15589697A
Other languages
Japanese (ja)
Inventor
Hidemitsu Kakudou
秀光 角銅
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shinko Kozai Co Ltd
Original Assignee
Shinko Kozai Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shinko Kozai Co Ltd filed Critical Shinko Kozai Co Ltd
Priority to JP15589697A priority Critical patent/JPH10331107A/en
Publication of JPH10331107A publication Critical patent/JPH10331107A/en
Pending legal-status Critical Current

Links

Abstract

PROBLEM TO BE SOLVED: To establish a method for constructing a stone pavement which can heighten the protection force for stones and with which stone surfaces are not likely contaminated with asphalt. SOLUTION: A plurality of stone blocks 1 are laid on a base roadbed 10 previously adjusted, and an asphalt attachment preventive layer 15 is formed on the surfaces of the stone blocks. A molten asphalt 20 is poured into each joint so that the blocks 1 are adhered to the base roadbed 10, and an asphalt mixture material 27 is put into the joint and subjected to a rolling process, and the asphalt attachment preventive layer 15 is removed so that the contaminant on the block surface is removed as a cleaning process.

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【発明の属する技術分野】本発明は、コンクリート製の
石ブロックや自然石を布設する石舗装の施工方法に関
し、特に車道の様に大きな荷重に耐えられる石舗装の施
工方法に関するものである。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a method for constructing a stone pavement for laying a concrete stone block or natural stone, and more particularly to a method for constructing a stone pavement capable of withstanding a large load such as a roadway.

【0002】[0002]

【従来の技術】舗装には、アスファルト舗装、コンクリ
ート舗装の他に石の舗装がある。アスファルト舗装は、
摩耗し易く、しかも熱に弱いなど耐久性が不充分なの
で、ある程度の年数を経ると、掘り起こしてから再度舗
装する必要があり、景観も良好であるとは言い難い。ま
た、コンクリート舗装は、アスファルト舗装よりも耐久
性に優れるが、熱膨張に対する手段が必要であるし、ま
た、景観が良好であるとは言い難い。この点、石の舗装
は景観が良好であることから、近年は我が国においても
見直されており、歩道ばかりでなく車道にも用いられて
いる。
2. Description of the Related Art Pavement includes stone pavement in addition to asphalt pavement and concrete pavement. Asphalt pavement
Since it is easily worn and has insufficient durability such as being weak to heat, after a certain number of years, it is necessary to dig up and repave it, and it is hard to say that the landscape is good. Concrete pavement is more durable than asphalt pavement, but requires means for thermal expansion, and it is hard to say that the landscape is good. In this regard, stone pavement has been reviewed in Japan in recent years because it has a good landscape, and is used not only on sidewalks but also on roadways.

【0003】ところが、この石の舗装、特に車道に用い
た場合には、目地の破損、それに伴う石の角欠け、ガタ
ツキ、割れ、石の飛散などの問題が発生している。この
様な石舗装の破損の多くは、目地材にモルタルを使用し
た場合に顕著である。
However, when this stone is used on a pavement, particularly on a road, problems such as breakage of joints, chipping of the corner of the stone, rattling, cracking, and scattering of the stone occur. Most of such damage to the stone pavement is remarkable when mortar is used as a joint material.

【0004】すなわち、目地材にモルタルを使用する
と、石が移動しにくく安定している、石の角欠けを
防ぎ易い、目地材が流出しにくい、砂目地に比較して
耐久性に優れている、などの利点があるがその反面、
モルタルが固まるまでの養生期間が長くなり、施工後直
ちに交通開放ができない、剛体である石と硬化して剛
体となったモルタル目地との接合なので弾性がなく、荷
重を受けた際にクラックが生じ易く、一旦クラックが入
ると、目地が外れ易く、その補修も困難である、補修
時の石の抜き入れが難しく、石の再利用が難しい、温
度変化に対応する膨張目地が必要となる、などの欠点が
ある。このため、車道など荷重が大きな部分の舗装に石
舗装は適さない、と言われていた。
[0004] That is, when mortar is used as the joint material, the stone is difficult to move and is stable, the stone is easily prevented from being chipped, the joint material is hard to flow out, and the durability is superior to the sand joint. There are advantages such as, but on the other hand,
The curing period until the mortar hardens becomes longer and traffic cannot be opened immediately after construction.Since it is a joint between a hard stone and a hardened and hardened mortar joint, there is no elasticity and cracks occur when a load is received. Easy, once cracked, joints are easy to come off and repair is also difficult, stones are difficult to pull in during repair, stones are difficult to reuse, expansion joints corresponding to temperature changes are required, etc. There are disadvantages. For this reason, it has been said that stone pavement is not suitable for pavement where the load is large, such as a roadway.

【0005】モルタル目地に対して、目地材にアスファ
ルトを使用した場合、次の様な利点を有する。 柔軟性があり、輪荷重に追随するために破損しにく
い、温度変化に対応する膨張目地が不要であり、施
工後、短時間で目地が安定する点などがある。
[0005] The use of asphalt as a joint material for mortar joints has the following advantages. It has flexibility, does not easily break to follow the wheel load, does not require an expansion joint corresponding to a temperature change, and has a point that the joint is stabilized in a short time after construction.

【0006】[0006]

【発明が解決しようとする課題】しかしながら、アスフ
ァルトを目地材として使用すると、柔軟性はあるが石
を押し戻す程までの弾性や支持力はないので、石に対す
る保護力はモルタル目地に劣る、施工中にアスファル
トが石の表面に付着すると除去が困難であるため、体裁
が悪くなり易い、高温時に目地材が流出することがあ
る、などの欠点がある。
However, when asphalt is used as a joint material, it has flexibility but no elasticity or supporting force enough to push back the stone, so that the protective force against the stone is inferior to that of the mortar joint. When asphalt adheres to the surface of the stone, it is difficult to remove the asphalt, so that the appearance is easily deteriorated, and joint materials may flow out at high temperatures.

【0007】そして、石に対する保護力を向上させるた
めに、アスファルトに代えてアスファルト合材を目地材
として使用することが考えられるとしても、狭くて深い
目地内に確実に充填することは困難である。また、アス
ファルト合材を単に転圧したのでは石の表面にアスファ
ルト合材が付着してしまい、付着したアスファルトは簡
単に除去できないので、実用に供することができない。
[0007] Even if it is conceivable to use an asphalt mixture instead of asphalt as a joint material in order to improve the protection against stones, it is difficult to reliably fill a narrow and deep joint. . Further, if the asphalt mixture is simply rolled, the asphalt mixture adheres to the surface of the stone, and the attached asphalt cannot be easily removed, so that it cannot be put to practical use.

【0008】また、石舗装を施工する場合、石を規則的
に並べるには多大な労力と熟練した技術が必要になると
ともに、目地材を充填する手間も掛かる。さらには、石
を一個ずつ布設すると、車輪が載っている石に荷重が集
中してしまい、周りの石に荷重を分散することができな
い。このため、車輪が通る部分に轍ができ易く、また、
轍の目地が他の部分よりも損傷し易いという問題があ
る。
In addition, when laying stone paving, arranging stones regularly requires a great deal of labor and skilled techniques, and also takes time to fill joint materials. Furthermore, when the stones are laid one by one, the load concentrates on the stone on which the wheels are mounted, and the load cannot be distributed to the surrounding stones. For this reason, it is easy to form a rut in the part where the wheel passes,
There is a problem that the joint of the rut is more easily damaged than other parts.

【0009】そこで本発明の目的は、適度な弾性で石に
対する保護力を従来のアスファルト目地よりも高めるこ
とができ、しかも石の表面がアスファルトで汚れ難い石
舗装の施工方法を提供するとともに、石舗装に適した石
ブロックユニットを提供しようとするものである。
Accordingly, an object of the present invention is to provide a method of constructing a stone pavement in which the protection against stones can be enhanced with moderate elasticity as compared with the conventional asphalt joint, and the stone surface is hardly stained with asphalt. It is intended to provide a stone block unit suitable for pavement.

【0010】[0010]

【課題を解決するための手段】本発明は上記目的を達成
するために提案されたもので、請求項1に記載の施工方
法の発明は、予め調整した基礎路盤上に複数の石ブロッ
クを布設する石ブロック布設工程と、石ブロックの表面
に、アスファルト付着防止剤を塗布してアスファルト付
着防止層を形成する付着防止層形成工程と、布設した石
ブロック間の目地部内に溶融アスファルトを流し込んで
石ブロックを基礎路盤に接着する接着工程と、アスファ
ルトと骨材とを混練したアスファルト合材を上記目地部
内に投入してから転圧するアスファルト合材充填工程
と、石ブロック上の余剰アスファルト合材を排除すると
ともに、アスファルト付着防止層を除去して石ブロック
の表面の汚れを除去する清浄工程と、を含むことを特徴
とする石舗装の施工方法である。
Means for Solving the Problems The present invention has been proposed to achieve the above object, and the invention of the construction method according to claim 1 lays a plurality of stone blocks on a pre-adjusted foundation roadbed. Stone block laying step, an anti-adhesion layer forming step of applying an asphalt anti-adhesion agent to the surface of the stone block to form an asphalt adhesion prevention layer, and pouring the molten asphalt into the joint between the laid stone blocks. Adhesion process for adhering the block to the foundation roadbed, asphalt mixture filling process where the asphalt mixture obtained by kneading the asphalt and the aggregate is put into the joints and rolling is performed, and excess asphalt mixture on the stone blocks is eliminated. And a cleaning process for removing dirt on the surface of the stone block by removing the asphalt adhesion preventing layer. It is the law.

【0011】請求項2に記載の施工方法の発明は、目地
部内に流し込んだ溶融アスファルトが硬化する前に、ア
スファルト合材を目地部内に投入して転圧することを特
徴とする請求項1に記載の石舗装の施工方法である。
In the construction method according to the second aspect of the present invention, before the molten asphalt poured into the joint is hardened, the asphalt mixture is charged into the joint and compacted. The construction method of the stone pavement.

【0012】請求項3に記載の施工方法の発明は、前記
石ブロック布設工程において、複数の石ブロックをジョ
イント部材で目地となる隙間を空けた状態で互いに接合
して予めユニット化しておき、このユニット化した状態
で石ブロックを布設することを特徴とする石舗装の施工
方法である。
In the construction method according to a third aspect of the present invention, in the stone block laying step, a plurality of stone blocks are joined to each other in a state where a joint member is provided with a gap serving as a joint, and are unitized in advance. A stone pavement construction method characterized by laying a stone block in a unitized state.

【0013】請求項4に記載の施工方法の発明は、石灰
水を石ブロックの表面に塗布して乾燥することによりア
スファルト付着防止層を形成し、清浄工程では石ブロッ
クの表面を水洗することによりアスファルト付着防止層
と共に汚れを除去することを特徴とする石舗装の施工方
法である。
According to a fourth aspect of the present invention, an asphalt adhesion preventing layer is formed by applying lime water to the surface of a stone block and drying the same, and in the cleaning step, the surface of the stone block is washed with water. It is a construction method of a stone pavement characterized by removing dirt together with an asphalt adhesion preventing layer.

【0014】請求項5に記載の発明は、複数の石ブロッ
クをジョイント部材で目地となる隙間を空けた状態で相
互に接合してユニット化し、各石ブロックの表面に、水
溶性のアスファルト付着防止層を形成したことを特徴と
する石ブロックユニットである。
According to a fifth aspect of the present invention, a plurality of stone blocks are joined to each other in a state in which a joint member has a gap therebetween to form a unit, and water-soluble asphalt is prevented from adhering to the surface of each stone block. It is a stone block unit characterized by forming a layer.

【0015】請求項6に記載の発明は、前記アスファル
ト付着防止層が、石灰水を塗布して乾燥させた層である
ことを特徴とする石ブロックユニットである。
According to a sixth aspect of the present invention, there is provided the stone block unit, wherein the asphalt adhesion preventing layer is a layer obtained by applying lime water and drying.

【0016】[0016]

【発明の実施の形態】以下、本発明の実施の形態を図面
に基づいて説明する。図1は舗装に使用する石ブロック
1を複数個接続してユニット化した石ブロックユニット
2の平面図、図2はこの石ブロックユニット2の側面図
である。
Embodiments of the present invention will be described below with reference to the drawings. FIG. 1 is a plan view of a stone block unit 2 formed by connecting a plurality of stone blocks 1 used for pavement, and FIG. 2 is a side view of the stone block unit 2.

【0017】石ブロックユニット2は、適宜な形状に形
成した複数の石ブロック1…をジョイント部材3により
互いに接合して構成する。また、施工後の美観を向上さ
せるとともに、目地材の充填が均一に行ない得るよう
に、各石ブロック1の位置、平面形状及び石ブロック
1,1間の隙間Dがそれぞれの石ブロックユニット2に
おいて同じになるように予め規定した形状、位置および
所定寸法に規格化してある。
The stone block unit 2 is formed by joining a plurality of stone blocks 1... Formed in an appropriate shape to each other with a joint member 3. In addition, the position of each stone block 1, the planar shape, and the gap D between the stone blocks 1, 1 are adjusted in each stone block unit 2 so that the aesthetic appearance after the construction is improved and the joint material can be uniformly filled. The shape, position and predetermined dimensions are standardized so as to be the same.

【0018】各石ブロック1は、砂とセメント及び若干
の水並びに必要に応じて配合する結合剤等を型枠に充填
して加圧することにより締め固め、直ちに脱型する所謂
即脱工法によって形成したコンクリートブロックであ
る。また、石ブロック1の表面(上面)には、景観を向
上するために自然石を模して、適宜な色彩或は模様を有
する着色層(図示せず)を形成する。この着色層は、型
枠の内側に予め着色液を塗布しておき、充填したコンク
リートの粒子に上記着色顔料を浸透させて、表面部分に
着色する所謂浸透着色工法を利用する。なお、型枠には
実際の石から型取りした或は石を模した適宜な凹凸を設
けて、脱型した石ブロック1の表面に上記浸透着色と相
俟って天然石の有する地肌が形成されるようにすること
が望ましい。
Each of the stone blocks 1 is formed by a so-called quick demolding method in which sand, cement, a little water, a binder to be blended as required, and the like are filled in a mold, compacted by pressing, and immediately removed from the mold. Concrete block. On the surface (upper surface) of the stone block 1, a colored layer (not shown) having an appropriate color or pattern is formed by imitating natural stone in order to improve the scenery. This coloring layer employs a so-called permeation coloring method in which a coloring liquid is applied in advance to the inside of a mold, and the coloring pigment is penetrated into the filled concrete particles to color the surface portion. In addition, the mold is provided with appropriate irregularities imitated from a real stone or imitating a stone, and the ground of natural stone is formed on the surface of the demolded stone block 1 in combination with the above-described permeation coloring. It is desirable to do so.

【0019】石ブロックユニット2は、上記のような石
ブロック1…を、ジョイント部材3によって複数個それ
ぞれ隙間Dを空けた状態で集合させて形成するものであ
る。ジョイント部材3は、石ブロック1を接続すること
ができればどのような構成でもよいが、本実施形態で
は、図3に示すように、細い金属線を束ねた直径約6mm
のワイヤーを所定の長さに切断するとともに、両端部に
拡径した抜け止め部4を形成してある。また、ジョイン
ト部材3は、可撓性を有するワイヤー製に限らず、両端
部分に抜け止め部4を形成した金属製、あるいはプラス
チック製のピン状でもよい。
The stone block unit 2 is formed by assembling a plurality of the above-described stone blocks 1... With a gap D therebetween. The joint member 3 may have any configuration as long as it can connect the stone block 1, but in the present embodiment, as shown in FIG. 3, a diameter of about 6 mm in which thin metal wires are bundled.
The wire is cut to a predetermined length, and a retaining portion 4 having an enlarged diameter is formed at both ends. The joint member 3 is not limited to a flexible wire, but may be a metal or plastic pin having stopper portions 4 formed at both ends.

【0020】この様なジョイント部材3により石ブロッ
ク1を接続するには、型枠内に仕切壁を設けて石ブロッ
ク1を成形するための凹部を適宜な形状で形成し、この
仕切壁の所望個所に、ジョイント部材3を装着する小さ
な凹状切欠部を形成しておき、この切欠部内にジョイン
ト部材3をセットした状態で石ブロック1を成型する。
なお、仕切壁が目地となる隙間Dを形成する部材として
機能するので、仕切壁を横切る状態でジョイント部材3
をセットすると、このジョイント部材3が石ブロック1
間の隙間Dを横断して隣り合う石ブロック1,1を接合
することになる。
In order to connect the stone block 1 with the joint member 3 as described above, a partition wall is provided in a mold, and a concave portion for forming the stone block 1 is formed in an appropriate shape. A small concave notch for mounting the joint member 3 is formed at each location, and the stone block 1 is molded with the joint member 3 set in this notch.
Since the partition wall functions as a member forming the gap D serving as a joint, the joint member 3 is moved across the partition wall.
When this is set, this joint member 3
The stone blocks 1 and 1 adjacent to each other across the gap D between them will be joined.

【0021】石ブロックユニット2は、順次布設した際
に、隣りの石ブロックユニット2との隙間D′が石ブロ
ック1の隙間Dと同じになるように、外周形状は、隣り
の石ブロックユニット2と組み合せられるように相補形
状とする。即ち、凸部と凹部とが組み合わさって両者の
間隔が一定の寸法D′を保てる形状とする。また、この
石ブロックユニット2は、作業者が手で運べる大きさ、
重さになるように、出来上り寸法が例えば900mm×
600mm程度に設定し、車道用であれば厚さ100m
m程度に設定することが望ましい。そして、上記仕切壁
の位置が各石ブロック1の隙間D、即ち目地となるの
で、この仕切壁の厚み(隙間D)は、例えば車道用であ
れば20mm程度とする。なお、厚さは、用途(荷重)
に応じて適宜調整することができ、また、目地となる隙
間Dも同様である。
When the stone block units 2 are sequentially laid, the outer peripheral shape of the stone block units 2 is set so that the gap D 'between the adjacent stone block units 2 is the same as the gap D between the stone blocks 1. And a complementary shape to be combined. In other words, the shape is such that the convex portion and the concave portion are combined so that the distance between the two can maintain a constant dimension D '. The stone block unit 2 is large enough to be carried by a worker,
The finished dimensions are, for example, 900 mm x
Set to about 600mm, 100m thick for roadway
It is desirable to set it to about m. And since the position of the said partition wall becomes clearance D of each stone block 1, ie, a joint, the thickness (gap D) of this partition wall is about 20 mm, for example, for roadways. The thickness depends on the application (load)
Can be adjusted as appropriate, and the gap D serving as a joint is also the same.

【0022】この様にして成形した石ブロックユニット
2は、型により成型してあるので、いずれにおいても全
体の外周形状、各石ブロック1の形状及び位置、隙間D
の寸法および位置がすべて統一された、即ち規格化され
たものとして出来上がる。
Since the stone block unit 2 molded in this manner is molded by a mold, the entire outer peripheral shape, the shape and position of each stone block 1, and the gap D
Are all unified, that is, standardized.

【0023】次に、上記した石ブロックユニット2を使
用して舗装する施工方法について説明する。まず、舗装
する路面には予め基礎路盤10を形成し、この基礎路盤
10上に石ブロックユニット2を所定の間隔D′(=
D)を空けて順次布設する。
Next, a method of paving using the above-described stone block unit 2 will be described. First, a foundation roadbed 10 is formed in advance on a pavement road surface, and a stone block unit 2 is placed on the foundation roadbed 10 at a predetermined interval D ′ (=
D) is vacated and laid sequentially.

【0024】基礎路盤10は、例えば図4に示すよう
に、最下部分から順に、厚さ約250mmの切り込み砕
石層11を、その上に厚さ約40mmの粗粒アスファル
トコンクリート層12を、その上に厚さ約60mmの半
撓み性舗装13を、その上に厚さ約30mmの砂層14
を形成して構成する。なお、この基礎路盤10は、従来
の基礎路盤と同様であり、歩道や車道などの用途、ま
た、車道であれば通行車両の数量等の条件に応じて適宜
設計変更することができる。
As shown in FIG. 4, for example, as shown in FIG. 4, the foundation roadbed 10 has a cut crushed stone layer 11 having a thickness of about 250 mm and a coarse asphalt concrete layer 12 having a thickness of about 40 mm. A semi-flexible pavement 13 having a thickness of about 60 mm is provided thereon, and a sand layer 14 having a thickness of about 30 mm is provided thereon.
Is formed. The foundation roadbed 10 is the same as the conventional foundation roadbed, and its design can be appropriately changed according to the use such as a sidewalk or a road, or the number of passing vehicles in a road.

【0025】基礎路盤10ができたならば、この基礎路
盤10上に石ブロックユニット2を所定の間隔で順次布
設する(石ブロック布設工程)。
When the foundation roadbed 10 is formed, the stone block units 2 are sequentially laid at predetermined intervals on the foundation roadbed 10 (stone block laying step).

【0026】石ブロックユニット2の布設が終了したな
らば、各石ブロック1の表面(上面)に、アスファルト
付着防止剤を塗布してから乾燥してアスファルト付着防
止層15を形成する(付着防止層形成工程)。このアス
ファルト付着防止剤は、後述するアスファルト合材が石
ブロック1の表面に載っても付着することがなく、容易
に剥離・除去できるようにするためのものである。した
がって、アスファルト付着防止機能を備えていればどの
ような成分でもよい。例えば、本実施形態では現場で石
ブロック1を布設した後に石灰水を塗布してから乾燥す
ることにより形成する。しかしながら、石ブロック布設
工程の前に、例えば工場や現場で各石ブロック1の表面
に予め形成しておいてもよい。なお、アスファルト付着
防止層15を工場で予め形成する場合、搬送途中での割
れや剥離を防止するために、水溶性のバインダーを少量
混合することが望ましい。この様に、アスファルト付着
防止層15を石ブロック1の表面に予め成形しておく
と、施工現場で塗布したり乾燥する時間を省略すること
ができるので、作業能率を高めることができる。
When the installation of the stone block units 2 is completed, an asphalt adhesion preventing agent is applied to the surface (upper surface) of each stone block 1 and dried to form an asphalt adhesion preventing layer 15 (adhesion preventing layer). Forming step). This asphalt adhesion preventive agent is for preventing the asphalt mixture described later from adhering to the surface of the stone block 1 even when placed on the surface of the stone block 1 so that it can be easily peeled and removed. Therefore, any component may be used as long as it has an asphalt adhesion preventing function. For example, in this embodiment, the stone block 1 is formed on site by applying lime water after drying, and then drying. However, before the stone block laying step, for example, the stone blocks 1 may be formed on the surface of each stone block 1 in a factory or on site. When the asphalt adhesion preventing layer 15 is formed in a factory in advance, it is desirable to mix a small amount of a water-soluble binder in order to prevent cracking and peeling during transportation. In this way, if the asphalt adhesion preventing layer 15 is formed on the surface of the stone block 1 in advance, the time for application and drying at the construction site can be omitted, so that work efficiency can be improved.

【0027】塗布した石灰水が乾燥してアスファルト付
着防止層15が形成されたならば、石ブロック1の間隙
D(即ち、目地部)内に溶融アスファルト20を注入
し、この溶融アスファルト20により各石ブロック1を
基礎路盤10に接着する(接着工程)。溶融アスファル
ト20は、アスファルトを含有して接着剤として機能す
る液剤であり、例えば加熱溶融したストレートアスファ
ルト、アスファルト乳剤などである。
When the applied lime water has dried and the asphalt adhesion preventing layer 15 has been formed, the molten asphalt 20 is poured into the gap D (ie, joint) of the stone block 1 and each of the molten asphalts 20 is used. The stone block 1 is bonded to the foundation roadbed 10 (bonding step). The molten asphalt 20 is a liquid material that contains asphalt and functions as an adhesive, and is, for example, straight asphalt or asphalt emulsion that is heated and melted.

【0028】この様な溶融アスファルト20を目地部内
に注入するには、図5に示すように、注入装置21を使
用する。この注入装置21は、下端に小さな出口22を
有する溶融アスファルト貯留部23と、この貯留部23
の下部に設けた車輪24と、貯留部23から上方に延び
たハンドル25とを備えている。したがって、このハン
ドル25を操作しながら、溶融アスファルト貯留部23
の出口22を目地部(間隙D)上に位置するようにしな
がら走行させると、出口22から流下した溶融アスファ
ルト20を目地部D内に容易に注入することができる。
また、溶融アスファルト20は流動性があるので、注入
装置21を停止したまま注入しても、溶融アスファルト
20が目地部D内をその延在方向に沿って流れる。な
お、目地部D内には、約10mm程の深さになるだけの量
を注入することが望ましい。
In order to inject such molten asphalt 20 into the joint, an injecting device 21 is used as shown in FIG. The injection device 21 includes a molten asphalt storage section 23 having a small outlet 22 at the lower end,
And a handle 25 extending upward from the storage part 23. Therefore, while operating the handle 25, the molten asphalt storage section 23 is operated.
The molten asphalt 20 that has flowed down from the outlet 22 can be easily injected into the joint D when the vehicle travels while the outlet 22 is positioned above the joint (gap D).
Further, since the molten asphalt 20 has fluidity, even if the molten asphalt 20 is injected with the injection device 21 stopped, the molten asphalt 20 flows in the joint portion D along the extending direction. In addition, it is desirable to inject into the joint portion D an amount sufficient to have a depth of about 10 mm.

【0029】目地部D内に溶融アスファルト20を注入
すると、この溶融アスファルト20は、次第に基礎路盤
10内に浸透するので、各石ブロック1を基礎路盤10
に接着することができる。
When the molten asphalt 20 is injected into the joint portion D, the molten asphalt 20 gradually penetrates into the foundation roadbed 10, so that each of the stone blocks 1 is
Can be adhered to.

【0030】次に、アスファルトと骨材26…を混練し
たアスファルト合材27を目地部D内に投入してから転
圧する(アスファルト合材充填工程)。目地部D内に投
入するアスファルト合材27は、従来通り加熱状態で施
工するものでも、或は近年開発され常温で施工できるよ
うにしたもの(アスファルト常温合材)でもよい。そし
て、本実施形態では目地部の幅が20mmなので、骨材2
6…の粒径が5mm以下のものを使用することが好まし
い。また、目地部D内に投入するアスファルト合材27
の量は、図4(b)に示すように、石ブロック1の表面
から少し盛り上がる程度であることが望ましい。
Next, the asphalt mixture 27 obtained by kneading the asphalt and the aggregates 26 is charged into the joint portion D, and is then compacted (asphalt mixture filling step). The asphalt mixture 27 to be charged into the joint portion D may be one that is constructed in a heated state as before, or one that has been developed recently and can be constructed at room temperature (asphalt room temperature mixture). In this embodiment, since the width of the joint is 20 mm, the aggregate 2
It is preferable to use particles having a particle diameter of 6 mm or less. The asphalt mixture 27 to be charged into the joint D
It is desirable that the amount is slightly raised from the surface of the stone block 1 as shown in FIG.

【0031】この様にして、少し盛り上がる程度まで投
入したならば、このアスファルト合材27を、ブロック
コンパクターやローラーなどの転圧装置(図示せず)を
使用して転圧する。目地部に沿ってアスファルト合材2
7を転圧すると、アスファルト合材27自体が締め固め
られることは勿論のこと、目地部内の隅々までアスファ
ルト合材27が充填され、これにより目地部内の底部に
溜っていた溶融アスファルト20がアスファルト合材2
7の小さな隙間に浸透して行き渡る。したがって、先に
注入した溶融アスファルト20と目地部D内で締め固め
られたアスファルト合材27と基礎路盤10と石ブロッ
ク1とが強固に一体化される。
When the asphalt mixture 27 is charged to the extent that it rises slightly in this way, the asphalt mixture 27 is rolled using a rolling device (not shown) such as a block compactor or a roller. Asphalt mixture 2 along the joint
7, the asphalt mixture 27 itself is compacted, as well as the asphalt mixture 27 is filled into every corner of the joint, so that the molten asphalt 20 accumulated at the bottom in the joint is asphalt. Mix 2
7 penetrates the small gaps and spreads. Therefore, the molten asphalt 20 previously injected, the asphalt mixture 27 compacted in the joint portion D, the foundation roadbed 10, and the stone block 1 are firmly integrated.

【0032】前記した転圧作業中、目地部Dから盛り上
がったアスファルト合材27が転圧により石ブロック1
の表面上に余剰アスファルト合材27としてこぼれ散っ
たりするが、この石ブロック1の表面にはアスファルト
付着防止層15が形成されているので、アスファルト合
材27が直接石ブロック1の表面に付着することがな
い。また、石ブロック1の表面にこぼれ散った余剰アス
ファルト合材が転圧装置によって押圧されても、アスフ
ァルト付着防止層15による保護により石ブロック1の
表面が大きく傷付くことも防止できる。
During the above-mentioned compaction work, the asphalt mixture 27 raised from the joint portion D is pressed by the stone block 1
Surplus asphalt mixture 27 spills on the surface of the stone block 1, but since the asphalt adhesion preventing layer 15 is formed on the surface of the stone block 1, the asphalt mixture 27 directly adheres to the surface of the stone block 1. Nothing. Further, even if the surplus asphalt mixture spilled on the surface of the stone block 1 is pressed by the rolling device, the surface of the stone block 1 can be prevented from being greatly damaged by the protection by the asphalt adhesion preventing layer 15.

【0033】そして、転圧作業が終了したならば、図4
(c)に示すように、石ブロック1上の余剰アスファル
ト合材を排除するとともに、アスファルト付着防止層1
5を除去して石ブロック1の表面の汚れを除去する(清
浄工程)。
When the compaction operation is completed, FIG.
As shown in (c), the excess asphalt mixture on the stone block 1 is eliminated, and the asphalt adhesion preventing layer 1 is removed.
5 is removed to remove dirt on the surface of the stone block 1 (cleaning step).

【0034】前述したように、石ブロック1の表面には
石灰水の塗布・乾燥によるアスファルト付着防止層15
が形成してあり、この付着防止層15が水溶性なので、
石ブロック1の表面を水洗いすると、この付着防止層1
5が水に溶けて流れてしまい、これにより付着防止層1
5上に付着していたアスファルト合材27や溶融アスフ
ァルト20の滴などの汚れも簡単に洗い流されてしま
う。したがって、水洗いという極めて簡単な作業により
汚れを確実に除去することができる。このため、狭い目
地部D内に溶融アスファルト20を注入したり、アスフ
ァルト合材27を投入して転圧しても、石ブロック1の
表面に黒いアスファルトの汚れを残すことがなく、体裁
を損ねることはない。
As described above, the surface of the stone block 1 is coated with lime water and dried to prevent the asphalt adhesion preventing layer 15 from being applied.
Is formed, and since the adhesion preventing layer 15 is water-soluble,
When the surface of the stone block 1 is washed with water, the adhesion preventing layer 1
5 dissolves in water and flows, thereby preventing the adhesion preventing layer 1
Dirt such as the asphalt mixture 27 and the droplets of the molten asphalt 20 adhered on the surface 5 are easily washed away. Therefore, dirt can be reliably removed by a very simple operation of washing with water. For this reason, even if the molten asphalt 20 is injected into the narrow joint portion D or the asphalt mixture 27 is charged and compacted, black asphalt dirt is not left on the surface of the stone block 1 and the appearance is impaired. There is no.

【0035】なお、アスファルト付着防止層15を水洗
いにより除去する場合には、ブラシを使用しながら洗浄
すると、石ブロック1の表面に凹凸があっても確実に洗
い流すことができるし、アスファルト合材27なども掃
く様にして容易に除去できるので、作業効率がよい。ま
た、アスファルト合材27の転圧作業が終了したなら
ば、目地鏝で目地部を押し付けながら仕上げることが望
ましい。
When the asphalt-adhesion preventing layer 15 is removed by washing with water, if the surface of the stone block 1 is uneven by washing with a brush, the asphalt mixture 27 can be reliably washed away. Can be easily removed by sweeping, so that the working efficiency is good. When the work of compacting the asphalt mixture 27 is completed, it is desirable to finish the joint while pressing the joint with a joint trowel.

【0036】目地部内に注入した溶融アスファルト20
や目地部内に充填した目地材としてのアスファルト合材
27は、モルタル目地材の様な養生を必要としないの
で、清浄工程が終了したならば、即ち施工後直ちに交通
を開放することができる。したがって、交通を遮断する
時間を短縮することができる。
The molten asphalt 20 injected into the joint
Since the asphalt mixture 27 as the joint material filled in the joint portion does not require curing like the mortar joint material, the traffic can be released immediately after the completion of the cleaning process, that is, immediately after the construction. Therefore, the time for blocking traffic can be reduced.

【0037】そして、本実施形態による石舗装は、複数
の石ブロック1をジョイント部材3で接合してユニット
化してあるので、石ブロック1の布設作業の容易化を図
ることができるばかりでなく、布設後は、1つの石ブロ
ック1に掛かった荷重をジョイント部材3を介して分散
させることができる。したがって、石ブロック1を1つ
1つ独立した状態で布設したものに比べて、負荷を軽減
することができ、これにより損傷を減少させ、耐久性を
高めることができる。
In the stone pavement according to the present embodiment, since the plurality of stone blocks 1 are joined together by the joint member 3 to form a unit, not only the work of laying the stone blocks 1 can be facilitated, but also. After laying, the load applied to one stone block 1 can be dispersed via the joint member 3. Therefore, the load can be reduced as compared with the case where the stone blocks 1 are laid one by one independently, whereby the damage can be reduced and the durability can be increased.

【0038】また、目地材に柔軟性があるので石ブロッ
ク1に輪荷重が掛かった場合に石ブロック1が追随する
ことができ破損しにくく、また、温度変化に対応する膨
張目地が不要であり、施工後、短時間で目地が安定する
などのアスファルト目地の利点はそのまま残しつつ、尚
且つ、目地材としてアスファルト合材27を充填したの
で、骨材26…の存在によって、石ブロック1に対する
支持力や保護力を著しく高めることができる。しかも、
モルタル目地材では期待できなかった弾性があるので、
輪荷重に追随した後で元の状態に確実に復元することが
でき、これにより破損し難い。
In addition, since the joint material is flexible, the stone block 1 can follow the stone block 1 when a wheel load is applied thereto, so that the stone block 1 is hard to be damaged, and an expansion joint corresponding to a temperature change is unnecessary. The asphalt joints, such as stabilization of the joints in a short time after construction, are left as they are, and the asphalt mixture 27 is filled as the joint material. Strength and protection can be significantly increased. Moreover,
Since there is elasticity that could not be expected with mortar joint material,
After following the wheel load, it can be surely restored to the original state, thereby hardly being damaged.

【0039】また、目地材としてのアスファルト合材2
7を投入して転圧しても、石ブロック1の表面に汚れを
残さないので、美観に優れた石舗装を簡単に施工するこ
とができる。
Asphalt mixture 2 as joint material
Even if 7 is introduced and compacted, no dirt is left on the surface of the stone block 1, so that a stone pavement excellent in aesthetic appearance can be easily constructed.

【0040】なお、前記実施形態においては、複数の石
ブロック1をジョイント部材3により相互に接合した石
ブロックユニット2を布設する車道用の石舗装として説
明したが、本発明はこれに限定されるものではなく、歩
道用など他の用途でも実施することができる。そして、
布設する石ブロック1は、ジョイント部材で接合しない
単独した状態で布設してもよいし、また、石ブロック1
はコンクリート製に限らず、自然石であってもよい。
In the above-described embodiment, a description has been given of a stone pavement for a road on which a stone block unit 2 in which a plurality of stone blocks 1 are joined to each other by a joint member 3 is laid, but the present invention is not limited thereto. Instead, it can be implemented in other applications such as sidewalks. And
The stone block 1 to be laid may be laid in a single state without being joined by a joint member.
Is not limited to concrete but may be natural stone.

【0041】[0041]

【発明の効果】以上説明したように本発明によれば、以
下の効果を奏する。請求項1の発明では、石ブロックの
表面に、アスファルト付着防止剤を塗布してアスファル
ト付着防止層を形成する付着防止層形成工程を含むの
で、狭い目地部内に溶融アスファルトを注入したり、投
入したアスファルト合材を転圧して、石ブロックの表面
に溶融アスファルトの滴が飛んだり、アスファルト合材
がこぼれても、これらアスファルト材を清浄工程で簡単
に除去することができる。したがって、施工後は、黒く
て目立つアスファルトの汚れが石ブロックの表面に残ら
ない。このため、施工直後からすぐれた景観の石舗装を
提供することができる。
According to the present invention as described above, the following effects can be obtained. According to the first aspect of the present invention, since the method includes the step of forming an asphalt adhesion preventing layer by applying an asphalt adhesion preventing agent to the surface of the stone block, molten asphalt is injected or injected into the narrow joint. Even if the asphalt mixture is compacted and drops of molten asphalt fly or spill on the surface of the stone block, these asphalt materials can be easily removed in the cleaning step. Therefore, after the construction, no noticeable black and asphalt stain remains on the surface of the stone block. For this reason, it is possible to provide a stone pavement with an excellent landscape immediately after the construction.

【0042】また、布設した石ブロック間の目地部内に
溶融アスファルトを流し込んで石ブロックを基礎路盤に
接着する接着工程と、アスファルトと骨材とを混練した
アスファルト合材を目地部内に投入してから転圧するア
スファルト合材充填工程と、を含むので、基礎路盤と石
ブロックと目地材とを、従来のアスファルト目地の場合
に比べて、一層強固に一体化することができる。そし
て、目地材中に骨材を含むので、骨材を含まない従来の
アスファルト目地の場合に比較して、石ブロックに対す
る目地材の支持力や保護力を著しく高めることができ
る。しかも、モルタル目地材では期待できなかった弾性
があるので、石ブロックが輪荷重に追随した後、元の状
態に確実に復元することができる。そして、この様な機
能は、剛体となってしまう従来のモルタル目地では期待
できなかった。この様に、本発明では、剛体である石ブ
ロックを、適度な弾性と支持力を有するアスファルト合
材による目地で保護するため、破損し難くなり、耐久性
の向上を図ることができる。
Further, a bonding step of pouring molten asphalt into the joints between the laid stone blocks and bonding the stone blocks to the foundation roadbed, and charging an asphalt mixture obtained by kneading asphalt and aggregate into the joints. Since the method includes the step of filling the asphalt mixture, which is to be compacted, the foundation roadbed, the stone block, and the joint material can be more firmly integrated than in the case of the conventional asphalt joint. And since an aggregate is contained in a joint material, the supporting force and protection force of the joint material with respect to a stone block can be remarkably improved compared with the case of the conventional asphalt joint which does not contain an aggregate. Moreover, since the mortar joint material has elasticity that could not be expected, it can be reliably restored to the original state after the stone block follows the wheel load. And such a function could not be expected in the conventional mortar joint which becomes a rigid body. As described above, in the present invention, since the stone block which is a rigid body is protected by the joint made of the asphalt mixture having appropriate elasticity and supporting force, the stone block is hardly damaged, and the durability can be improved.

【0043】請求項2の発明では、目地部内に流し込ん
だ溶融アスファルトが硬化する前に、アスファルト合材
を目地部内に投入して転圧するので、アスファルト合材
を転圧することによって、溶融アスファルトがアスファ
ルト合材に浸透しながら上昇する。したがって、基礎路
盤と石ブロックと目地材とを一層強固に一体化すること
ができる。
According to the second aspect of the present invention, before the molten asphalt poured into the joint is hardened, the asphalt mixture is charged into the joint and rolled. It rises while penetrating the mixture. Therefore, the foundation roadbed, the stone block, and the joint material can be more firmly integrated.

【0044】請求項3の発明によれば、石ブロック布設
工程において、複数の石ブロックをジョイント部材によ
り目地となる隙間を空けた状態で互いに接合して予めユ
ニット化しておき、このユニット化した状態で石ブロッ
クを布設するので、石ブロックを短時間で能率良く布設
することができる。しかも、各石ブロックの配置、目地
の寸法などの精度を確実に高めることが容易である。し
たがって、設計通りの石の配置で景観に優れた石舗装を
容易に施工することができる。また、各石ブロックがジ
ョイント部材で接合されているので、石ブロックの負荷
を分散させることができ、耐久性の向上に寄与する。
According to the third aspect of the present invention, in the stone block laying step, a plurality of stone blocks are joined to each other in a state where a gap serving as a joint is opened by a joint member to form a unit in advance, and this unitized state is obtained. Since the stone block is laid, the stone block can be laid efficiently in a short time. Moreover, it is easy to reliably increase the accuracy of the arrangement of the stone blocks, the dimensions of the joints, and the like. Therefore, the stone pavement excellent in the scenery can be easily constructed with the arrangement of the stones as designed. Moreover, since each stone block is joined by the joint member, the load of the stone block can be dispersed, which contributes to improvement in durability.

【0045】請求項4の発明では、石灰水を石ブロック
の表面に塗布して乾燥することによりアスファルト付着
防止層を形成し、清浄工程では石ブロックの表面を水洗
することによりアスファルト付着防止層と共に汚れを除
去するので、アスファルト付着防止層の形成と除去が極
めて簡単である。また、石灰水を使用すると、入手や取
り扱いが極めて容易であり、特に水洗いで簡単に除去で
きるので清浄工程も簡単である。
According to the fourth aspect of the present invention, the asphalt adhesion preventing layer is formed by applying lime water to the surface of the stone block and drying the same, and in the cleaning step, the surface of the stone block is washed with water to form an asphalt adhesion preventing layer. Since dirt is removed, the formation and removal of the asphalt adhesion preventing layer is extremely simple. In addition, when lime water is used, it is very easy to obtain and handle, and the cleaning step is also simple because it can be easily removed particularly by washing with water.

【0046】請求項5の発明では、複数の石ブロックを
ジョイント部材で目地となる隙間を空けた状態で相互に
接合してユニット化し、各石ブロックの表面に、水溶性
のアスファルト付着防止層を形成した石ブロックユニッ
トなので、布設作業を簡単に能率良く行うことができる
ばかりでなく、1つの石ブロックに掛かる負荷を分散す
ることができるので、損傷し難くなり、耐久性を高める
ことができる。また、水溶性のアスファルト付着防止層
を工場で予め形成できるので、現場における施工が容易
である。さらに、アスファルト付着防止層が水溶性なの
で、水洗いで簡単に除去することができる。
According to the fifth aspect of the present invention, a plurality of stone blocks are joined to each other in a state where a joint member has a gap therebetween to form a unit, and a water-soluble asphalt adhesion preventing layer is provided on the surface of each stone block. With the formed stone block unit, not only can the laying work be performed simply and efficiently, but also the load applied to one stone block can be dispersed, so that the stone block is less likely to be damaged and the durability can be increased. Further, since the water-soluble asphalt adhesion preventing layer can be formed in advance at the factory, construction on site is easy. Furthermore, since the asphalt adhesion preventing layer is water-soluble, it can be easily removed by washing with water.

【0047】請求項6の発明では、アスファルト付着防
止層が、石灰水を塗布して乾燥させた層であるので、簡
単な操作で容易に形成することができ、また、現場で水
洗いすることにより簡単に除去することができる。
According to the sixth aspect of the present invention, since the asphalt adhesion preventing layer is a layer obtained by applying lime water and drying it, it can be easily formed by a simple operation. It can be easily removed.

【図面の簡単な説明】[Brief description of the drawings]

【図1】複数の石ブロックをジョイント部材により接合
した石ブロックユニットの平面図である。
FIG. 1 is a plan view of a stone block unit in which a plurality of stone blocks are joined by a joint member.

【図2】石ブロックユニットの側面図である。FIG. 2 is a side view of the stone block unit.

【図3】ジョイント部材の正面図である。FIG. 3 is a front view of a joint member.

【図4】(a)は目地部内に溶融アスファルトを注入し
た状態における目地部の側面図、(b)は目地部内にア
スファルト合材を投入した状態における目地部の側面
図、(c)は余剰アスファルト合材を除去するとともに
アスファルト付着防止層を洗い流した後における目地部
の側面図である。
4A is a side view of the joint in a state in which molten asphalt is injected into the joint, FIG. 4B is a side view of the joint in a state in which the asphalt mixture is injected into the joint, and FIG. It is a side view of the joint after removing an asphalt mixture and washing away an asphalt adhesion prevention layer.

【図5】注入装置の側面図である。FIG. 5 is a side view of the injection device.

【符号の説明】[Explanation of symbols]

1 石ブロック 2 石ブロックユニット 3 ジョイント部材 4 抜け止め部 10 基礎路盤 11 切り込み砕石層 12 粗粒アスファルト層 13 半撓み舗装 14 砂層 15 アスファルト付着防止層 20 溶融アスファルト 21 注入装置 22 出口 23 溶融アスファルト貯留部 24 車輪 25 ハンドル 26 骨材 27 アスファルト合材 Reference Signs List 1 stone block 2 stone block unit 3 joint member 4 retaining member 10 foundation roadbed 11 cut crushed stone layer 12 coarse asphalt layer 13 semi-flexible pavement 14 sand layer 15 asphalt adhesion preventing layer 20 molten asphalt 21 injection device 22 outlet 23 molten asphalt storage section 24 Wheel 25 Handle 26 Aggregate 27 Asphalt mixture

Claims (6)

【特許請求の範囲】[Claims] 【請求項1】 予め調整した基礎路盤上に複数の石ブロ
ックを布設する石ブロック布設工程と、 石ブロックの表面に、アスファルト付着防止剤を塗布し
てアスファルト付着防止層を形成する付着防止層形成工
程と、 布設した石ブロック間の目地部内に溶融アスファルトを
流し込んで石ブロックを基礎路盤に接着する接着工程
と、 アスファルトと骨材とを混練したアスファルト合材を上
記目地部内に投入してから転圧するアスファルト合材充
填工程と、 石ブロック上の余剰アスファルト合材を排除するととも
に、アスファルト付着防止層を除去して石ブロックの表
面の汚れを除去する清浄工程と、 を含むことを特徴とする石舗装の施工方法。
1. A stone block laying step of laying a plurality of stone blocks on a pre-adjusted foundation roadbed, and forming an anti-adhesion layer by applying an asphalt anti-adhesion agent to the surface of the stone blocks to form an asphalt adhesion prevention layer A bonding step of pouring the molten asphalt into the joints between the laid stone blocks and bonding the stone blocks to the foundation roadbed; and loading the asphalt mixture obtained by kneading the asphalt and the aggregate into the joints and then rolling. A stone characterized by comprising: a step of filling asphalt mixture to be pressed; and a cleaning step of removing excess asphalt mixture on the stone block and removing an asphalt adhesion preventing layer to remove dirt on the surface of the stone block. Construction method of pavement.
【請求項2】 目地部内に流し込んだ溶融アスファルト
が硬化する前に、アスファルト合材を目地部内に投入し
て転圧することを特徴とする請求項1に記載の石舗装の
施工方法。
2. The method for constructing a stone pavement according to claim 1, wherein before the molten asphalt poured into the joint is hardened, the asphalt mixture is charged into the joint and rolled.
【請求項3】 前記石ブロック布設工程は、複数の石ブ
ロックをジョイント部材で目地となる隙間を空けた状態
で互いに接合して予めユニット化しておき、このユニッ
ト化した状態で石ブロックを布設することを特徴とする
請求項1または2に記載の石舗装の施工方法。
3. The stone block laying step comprises joining a plurality of stone blocks together in a state where a joint member has a gap therebetween to form a unit, and laying the stone blocks in this unitized state. The method for constructing a stone pavement according to claim 1 or 2, wherein:
【請求項4】 石灰水を石ブロックの表面に塗布して乾
燥することによりアスファルト付着防止層を形成し、清
浄工程では石ブロックの表面を水洗することによりアス
ファルト付着防止層と共に汚れを除去することを特徴と
する請求項1から3のいずれかに記載の石舗装の施工方
法。
4. An asphalt-adhesion preventing layer is formed by applying lime water to the surface of a stone block and drying it. In a cleaning step, the surface of the stone block is washed with water to remove dirt together with the asphalt-adhesion preventing layer. The method for constructing a stone pavement according to any one of claims 1 to 3, wherein:
【請求項5】 複数の石ブロックをジョイント部材で目
地となる隙間を空けた状態で相互に接合してユニット化
し、各石ブロックの表面に、水溶性のアスファルト付着
防止層を形成したことを特徴とする石ブロックユニッ
ト。
5. A unit in which a plurality of stone blocks are joined to each other with a joint member having a gap therebetween to form joints, and a water-soluble asphalt adhesion preventing layer is formed on the surface of each stone block. And stone block unit.
【請求項6】 前記アスファルト付着防止層は、石灰水
を塗布して乾燥させた層であることを特徴とする請求項
5に記載の石ブロックユニット。
6. The stone block unit according to claim 5, wherein the asphalt adhesion preventing layer is a layer obtained by applying lime water and drying.
JP15589697A 1997-05-29 1997-05-29 Method for constructing stone pavement and stone block unit Pending JPH10331107A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP15589697A JPH10331107A (en) 1997-05-29 1997-05-29 Method for constructing stone pavement and stone block unit

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP15589697A JPH10331107A (en) 1997-05-29 1997-05-29 Method for constructing stone pavement and stone block unit

Publications (1)

Publication Number Publication Date
JPH10331107A true JPH10331107A (en) 1998-12-15

Family

ID=15615884

Family Applications (1)

Application Number Title Priority Date Filing Date
JP15589697A Pending JPH10331107A (en) 1997-05-29 1997-05-29 Method for constructing stone pavement and stone block unit

Country Status (1)

Country Link
JP (1) JPH10331107A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104963257A (en) * 2015-06-15 2015-10-07 中国建筑第八工程局有限公司 Gap filling structure and construction method for stone road surface

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104963257A (en) * 2015-06-15 2015-10-07 中国建筑第八工程局有限公司 Gap filling structure and construction method for stone road surface

Similar Documents

Publication Publication Date Title
US4769191A (en) Monolithic surface ornamentation of pre-cast reinforced concrete wall
US6716482B2 (en) Wear-resistant reinforcing coating
KR100961967B1 (en) Structure of loess paving layer and construction method using thereof
JP2633216B2 (en) Continuously joined snow melting pavement material
KR100869651B1 (en) Road surface repairing method using the rubafalt
CN109468930B (en) Crack repairing method for asphalt pavement after snow
JPH10331107A (en) Method for constructing stone pavement and stone block unit
GB2360959A (en) Profiled structural elements or surfaces
GB2065203A (en) Flexible road surfacing
JPH03260202A (en) Method for repairing pavement with resin concrete
JPH11181712A (en) Boundary block for road and work execution structure of road boundary part
JP3059566B2 (en) Paving method
JP4149592B2 (en) Pavement structure
JPH07119108A (en) Asphalt pavement method
JP6006667B2 (en) Dirt Course Baba Construction Method
JP7239448B2 (en) Pavement method and pavement structure
JPH11280010A (en) Paving method of asphalt pavement road, precast asphalt floor board and manufacture thereof
JP3066640B2 (en) Rationalization method of joint filler for concrete pavement
AU2009100759A4 (en) Resurfacing of Paving
JP2939552B2 (en) Joint structure
JPH0721601Y2 (en) Pavement structure at joints such as roads
JP2002309503A (en) Block pavement and construction method therefor
KR100736918B1 (en) Anti breaking block buffer of block for pavement
KR100616424B1 (en) A paving method having a gravels
JP2622921B2 (en) Paving method and paving material