JPH10254529A - Plant supervisory and controlling device - Google Patents

Plant supervisory and controlling device

Info

Publication number
JPH10254529A
JPH10254529A JP6902697A JP6902697A JPH10254529A JP H10254529 A JPH10254529 A JP H10254529A JP 6902697 A JP6902697 A JP 6902697A JP 6902697 A JP6902697 A JP 6902697A JP H10254529 A JPH10254529 A JP H10254529A
Authority
JP
Japan
Prior art keywords
time
plant
schedule
information file
data setting
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP6902697A
Other languages
Japanese (ja)
Inventor
Kazuto Kaneko
年登 金子
Kiyomitsu Baba
清光 馬場
Masatoshi Hayashi
雅利 林
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Toshiba Corp
Original Assignee
Toshiba Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Toshiba Corp filed Critical Toshiba Corp
Priority to JP6902697A priority Critical patent/JPH10254529A/en
Publication of JPH10254529A publication Critical patent/JPH10254529A/en
Pending legal-status Critical Current

Links

Abstract

PROBLEM TO BE SOLVED: To efficiently operate a plant by making difference between the operation schedule of the plant and an actual operation result small. SOLUTION: A time measurement means S7 measures the operation time of respective operation items, sets it to a time measurement information file T4, calculates average time with average operation time until a previous time for all the operation items for which the time is measured by updating request informing and sets it to the time measurement information file T4 as the new average operation time. In a schedule calculation means S2, a present plant state is judged by process data, the average operation time of the respective operation items until the plant operation of the previous time set inside the time measurement information file T4 is calculated and the operation schedule of the plant whose base point is the informed operation completion request time is calculated and set to a schedule data setting file T2.

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【発明の属する技術分野】本発明は、プラントの運転計
画の計算を行うと共に、その計算結果に基づきプラント
の自動化運転のための制御及び監視を行うプラント監視
制御装置に関する。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a plant monitoring and control device which calculates a plant operation plan and performs control and monitoring for automatic operation of the plant based on the calculation result.

【0002】[0002]

【従来の技術】小規模や中規模の火力発電等のプラント
は、日負荷対応などのために日々起動及び停止の運転を
行う場合が多く、このような場合には、プラント監視制
御装置の運転計画計算機能(スケジュール計算機能)等
により事前にプラントの運転計画を立て、その計画に基
づいてプラントの自動化運転を行っている。
2. Description of the Related Art Plants such as small-scale or medium-scale thermal power plants often start and stop daily to cope with daily loads. A plant operation plan is prepared in advance by a plan calculation function (schedule calculation function) and the like, and the plant is automatically operated based on the plan.

【0003】図19は、従来の発電プラントに適用した
一例を示すプラント監視制御装置の構成図である。
FIG. 19 is a block diagram of a plant monitoring and control device showing an example applied to a conventional power plant.

【0004】図19において、プラント監視制御装置P
2は、プロセス入力手段S1とスケジュール計算手段S
2と実績収集手段S3と自動化運転手段S4とプロセス
表示手段S5と対話入力手段S6とからなり、さらに、
プロセスデータ設定ファイルT1とスケジュールデータ
設定ファイルT2と運転実績データ設定ファイルT3と
を有して、CRT表示装置C1とタッチスクリーン装置
C2とキー入力装置C3とを接続している。
In FIG. 19, a plant monitoring and control device P
2 is a process input means S1 and a schedule calculation means S
2, an operation collecting means S3, an automated driving means S4, a process display means S5, and a dialog input means S6.
It has a process data setting file T1, a schedule data setting file T2, and an operation result data setting file T3, and connects the CRT display device C1, the touch screen device C2, and the key input device C3.

【0005】まず、プロセス入力手段S1は、発電プラ
ントP1から各種プロセスデータを周期的に入力してプ
ロセスデータ設定ファイルT1に設定する。
First, the process input means S1 periodically inputs various process data from the power plant P1 and sets the process data in the process data setting file T1.

【0006】運転員は、CRT表示装置C1の対話画面
から運転計画の計算要求(スケジュール計算要求)を行
い、対話入力手段S6はスケジュール計算手段S2へ運
転完了要求時刻と共に計算要求を通知する。
The operator makes a calculation request (schedule calculation request) for the operation plan from the dialog screen of the CRT display device C1, and the dialog input means S6 notifies the schedule calculation means S2 of the calculation request together with the operation completion request time.

【0007】スケジュール計算手段S2では、プロセス
データ設定ファイルT1のプロセスデータより現在のプ
ラント状態を判断して、通知された運転完了要求時刻を
基点として発電プラントP2の運転計画を計算し、スケ
ジュールデータ設定ファイルT2に設定する。
The schedule calculation means S2 determines the current plant state from the process data in the process data setting file T1, calculates the operation plan of the power plant P2 based on the notified operation completion request time, and sets the schedule data. Set in file T2.

【0008】プロセス表示手段S5では、スケジュール
データ設定ファイルT2の各運転予定時刻などの運転計
画データをCRT表示装置C1へ表示する。
The process display means S5 displays operation plan data such as each scheduled operation time of the schedule data setting file T2 on the CRT display device C1.

【0009】自動化運転手段S4では、プロセスデータ
設定ファイルT1のプロセスデータとスケジュールデー
タ設定ファイルT2の制御パラメータとにより、プラン
トへ制御信号を出力して発電プラントP1の自動化運転
を行う。
The automated operation means S4 outputs a control signal to the plant based on the process data in the process data setting file T1 and the control parameters in the schedule data setting file T2 to perform the automatic operation of the power plant P1.

【0010】実績収集手段S3では、プラント運転の進
行に伴って周期的にプロセスデータ設定ファイルT1の
プロセスデータより、各運転計画の実績時刻の検出とタ
ービン回転数や発電機出力などのデータを収集して運転
実績データ設定ファイルT3へ設定する。
The performance collecting means S3 periodically detects the performance time of each operation plan and collects data such as turbine speed and generator output from the process data in the process data setting file T1 as the plant operation proceeds. To the operation result data setting file T3.

【0011】プロセス表示手段S5では、運転実績デー
タ設定ファイルT3の各運転実績時刻やタービン回転数
/発電機出力などの曲線表示データなどを、図20に示
すように、CRT表示装置C1の運転実績表示画面に周
期的に表示更新する。図20に示す運転実績表示画面5
0は、上段に実績グラフを表示する実績表示グラフ画面
50aがあり、下段に項目毎に予定と実績を数値等で表
示する項目表示部50bがある。
As shown in FIG. 20, the process display means S5 displays the operation result time and the curve display data such as the turbine speed / generator output of the operation result data setting file T3 as shown in FIG. The display is updated periodically on the display screen. Operation result display screen 5 shown in FIG.
0, there is a result display graph screen 50a for displaying the result graph in the upper part, and there is an item display part 50b for displaying the plan and result for each item in numerical values or the like in the lower part.

【0012】このような発電プラントにおいては、運転
計画と実際の運転実績との差異を小さくして運転効率を
向上することが望まれている。
In such a power plant, it is desired to improve the operation efficiency by reducing the difference between the operation plan and the actual operation results.

【0013】[0013]

【発明が解決しようとする課題】しかしながら、従来の
プラント監視制御装置では、以下の問題があった。
However, the conventional plant monitoring and control device has the following problems.

【0014】従来のプラント監視制御装置における運転
計画の計算(スケジュール計算)では、運転員の操作に
おける個人的時間差や長年のプラント運転におけるプラ
ント特性の変化などが考慮されていないため、運転計画
通りに運転することが極めて困難であった。
In the calculation of the operation plan (schedule calculation) in the conventional plant monitoring and control device, since the personal time difference in the operation of the operator and the change in the plant characteristics in the long-term operation of the plant are not taken into account, the operation plan is calculated. Driving was extremely difficult.

【0015】また、夏場と冬場とでプラントの運転時間
が異なるように、季節などの気温差によるプラント特性
の違いなどが考慮されていないため、運転計画通りに運
転することが極めて困難であった。
In addition, it is extremely difficult to operate the plant according to the operation plan, because differences in plant characteristics due to temperature differences such as seasons are not taken into consideration so that the plant operating hours are different between summer and winter. .

【0016】また、プラントの自動化運転において、運
転員はCRT表示装置C1などへの自動化運転メッセー
ジ表示やプロセス表示などによって運転の監視を行って
おり、自動化運転においても進行確認などの運転員によ
る運転操作を必要としている。この場合に、運転員はプ
ラントの自動化運転を常時監視していてその時々で必要
な運転操作を行わなければならず、余裕を持った運転監
視及び運転操作を行うことができなかった。
In the automatic operation of the plant, the operator monitors the operation by displaying an automatic operation message or a process display on the CRT display C1 or the like. Need operation. In this case, the operator constantly monitors the automated operation of the plant, and must perform necessary operation operations at each time, so that the operation monitoring and operation operation cannot be performed with sufficient margin.

【0017】また、従来のプラント監視制御装置の運転
計画では、図20のように、起動運転においては、起動
操作開始/点火/通気/併入/起動操作完了の大まかな
5項目の予定時刻と実績時刻の情報を提供するだけであ
る。従って、運転完了時にどの運転項目の要因により運
転計画通りに運転できなかったかを分析することが困難
であった。そのため、分析結果を次回のプラント運転に
活かすことができず、運転計画通りに運転することが困
難であった。
In the operation plan of the conventional plant monitoring and control apparatus, as shown in FIG. 20, in the start-up operation, there are roughly five scheduled times of start-up operation start / ignition / ventilation / joining / start-up operation completion. It only provides the actual time information. Therefore, it has been difficult to analyze which operation item caused the operation to fail according to the operation plan when the operation was completed. Therefore, the analysis results cannot be utilized for the next plant operation, and it has been difficult to operate according to the operation plan.

【0018】また、タービン過速率などのタービンの制
御パラメータ値は、プラント建設時にタービンの予定寿
命年数とタービンの起動/停止の予定回数などを考慮
し、その中でプラントを効率よく起動(最短時間で起
動)できるような限界値を算出しており、運転計画時は
この制御パラメータ値を用いて計算している。
The turbine control parameters, such as the turbine overspeed, take into account the expected life of the turbine at the time of plant construction and the expected number of times of starting / stopping of the turbine. Is calculated using the control parameter values during operation planning.

【0019】近年では、従来通りプラントを最短時間で
起動する必要性と共に、設備投資の縮小化に伴ってプラ
ント建設時の予定寿命年数以上にタービン寿命を延命す
るようなプラント運転を望まれる場合も少なくないが、
従来のプラント監視制御装置の運転計画では、タービン
の寿命の延命化を考慮した自動化のプラント運転ができ
なかった。
In recent years, in addition to the need to start the plant in the shortest time as in the past, there is also a case where it is desired to operate the plant such that the life of the turbine is extended beyond the expected life at the time of construction of the plant with the reduction in capital investment. Not a few,
In the operation plan of the conventional plant monitoring and control device, an automatic plant operation in consideration of extending the life of the turbine cannot be performed.

【0020】本発明は第1目的として、プラントの運転
計画と実際の運転実績との差異を小さくすることによ
り、効率的なプラント運転すること、第2目的として、
運転員が余裕を持ったプラントの運転及び監視するこ
と、第3目的として、設備の寿命の延命化を考慮したプ
ラント運転計画と自動化運転をすることを可能とするプ
ラント監視制御装置を提供することを目的とする。
A first object of the present invention is to efficiently operate a plant by reducing a difference between an operation plan of a plant and an actual operation result.
A third object of the present invention is to provide a plant monitoring and control device that enables an operator to operate and monitor a plant having a margin and, as a third object, to perform a plant operation plan and an automated operation in consideration of extending the life of equipment. With the goal.

【0021】[0021]

【課題を解決するための手段】請求項1の発明は、プラ
ントから各種情報を入力してプラントの運転計画の計算
を実行して得られる運転計画に従ってプラントを自動化
運転するための監視と制御をするプラント監視制御装置
において、各運転項目について運転時間の計測を実行
し、計測した各運転時間に基づき各運転項目について平
均運転時間を算出して時間計測情報ファイルへ保存する
時間計測手段と、時間計測情報ファイルに保存される各
運転項目の平均運転時間に基づきプラントの運転計画を
計算するスケジュール計算手段とを設けるようにしたも
のである。この手段によれば、各運転項目について計測
された各運転時間に基づき各運転項目の平均運転時間が
算出され、これに基づき新たな運転計画が計算される。
これにより、得られる運転計画がプラントの状況に応じ
たものとなり、運転計画通りに実際のプラントの運転が
できる。従って、従来のように運転員の個人差やプラン
トの特性による実情に沿わない運転計画によって実際の
運転がされ運転計画通りに終了しないという不都合が解
消できる。
The invention according to claim 1 performs monitoring and control for automatically operating a plant in accordance with an operation plan obtained by inputting various information from a plant and calculating a plant operation plan. A time monitoring means for measuring an operation time for each operation item, calculating an average operation time for each operation item based on the measured operation time, and storing the average operation time in a time measurement information file; A schedule calculating means for calculating a plant operation plan based on the average operation time of each operation item stored in the measurement information file is provided. According to this means, the average operation time of each operation item is calculated based on each operation time measured for each operation item, and a new operation plan is calculated based on the average operation time.
As a result, the obtained operation plan is in accordance with the condition of the plant, and the actual operation of the plant can be performed according to the operation plan. Therefore, the inconvenience that the actual operation is performed by the operation plan that does not conform to the actual situation due to the individual differences of the operators and the characteristics of the plant as in the related art and the operation is not completed according to the operation plan can be solved.

【0022】請求項2の発明は、周期毎にプラントから
各種プロセスデータを入力して、プロセスデータ設定フ
ァイルに設定するプロセス入力手段と、プラント運転の
進行に伴ってプロセスデータ設定ファイルのプロセスデ
ータより各運転項目の実績時刻の検出と必要な機器デー
タを収集して運転実績データ設定ファイルへ設定する実
績収集手段と、プロセスデータ設定ファイルから現在の
プロセスデータを入力して時間計測情報ファイルに記憶
される各運転項目の計測開始/終了条件に基づいて判定
を行い、計測開始条件成立から計測終了条件成立までの
各運転項目の運転時間を計測して、各運転項目毎に計測
した今回の運転時間と計測開始時刻及び計測終了時刻と
を時間計測情報ファイルへ保存すると共に、時間計測し
た全運転項目について、前回までの平均運転時間に今回
の実績を加えて、平均運転時間を算出して新たな平均運
転時間として時間計測情報ファイルへ保存する時間計測
手段と、プロセスデータ設定ファイルのプロセスデータ
より現在のプラント状態を判断し、時間計測情報ファイ
ル内に設定されている前回のプラント運転までの各運転
項目の平均運転時間を参照して、プラントの運転計画デ
ータを作成し、スケジュールデータ設定ファイルに設定
するスケジュール計算手段と、プロセスデータ設定ファ
イルのプロセスデータとスケジュールデータ設定ファイ
ルに保存される制御パラメータとにより、プラントへの
制御信号を出力してプラントの自動化運転を行う自動化
運転手段とを設けるようにしたものである。この手段に
よれば、各運転項目について前回までの平均運転時間に
加え、今回の運転実績を加味して新たな平均運転時間が
算出される。運転完了要求時刻が指定されると、各運転
項目の新たな平均運転時間を用いて運転完了要求時刻に
運転が完了するように運転計画が計算される。これによ
り、実情に沿った的確な運転計画によって実際の運転が
されるので、運転完了時刻が予定より延びたり、早まっ
たりする不都合が生じない。
According to a second aspect of the present invention, there is provided a process input means for inputting various process data from a plant for each cycle and setting the process data in a process data setting file, and a process data input file for setting the process data in the process data setting file as the plant operation proceeds. A result collection unit that detects the actual time of each operation item and collects the necessary device data and sets it in the operation result data setting file, and inputs the current process data from the process data setting file and stores it in the time measurement information file Judgment is made based on the measurement start / end conditions of each operation item, and the operation time of each operation item from the satisfaction of the measurement start condition to the satisfaction of the measurement end condition is measured, and the current operation time measured for each operation item And the measurement start time and measurement end time in the time measurement information file, and Time measurement means for calculating the average operation time by adding the current result to the previous average operation time and saving it as a new average operation time in the time measurement information file; and Judgment of the plant status of the plant, referring to the average operation time of each operation item until the last plant operation set in the time measurement information file, create plant operation plan data, and set it in the schedule data setting file Schedule calculation means, and an automatic operation means for outputting a control signal to the plant and performing an automatic operation of the plant by the process data of the process data setting file and the control parameters stored in the schedule data setting file. It was done. According to this means, a new average operation time is calculated for each operation item in consideration of the current operation results in addition to the average operation time up to the last time. When the operation completion request time is specified, the operation plan is calculated so that the operation is completed at the operation completion request time using the new average operation time of each operation item. As a result, the actual operation is performed according to an accurate operation plan according to the actual situation, so that there is no inconvenience that the operation completion time is extended or earlier than expected.

【0023】請求項3の発明は、請求項1または請求項
2記載のプラント監視制御装置において、スケージュー
ル計算手段で作成したあるいは運転実績データである運
転のスケジュールを表す複数の運転パターンのデータを
保存する運転パターン情報ファイルに要求により取出さ
れた前記時間計測情報ファイルからのデータを新たな1
つの運転パターンとして設定する運転パターン登録手段
を備えて、状況に応じて蓄積した運転パターンによって
運転計画を計算するようにしたものである。この手段に
よれば、複数の運転パターンから状況に応じて選択した
適切な運転パターンによって運転計画が計算される。こ
れにより、実際の運転と運転計画とに差異がなく、効率
的な運転ができる。
According to a third aspect of the present invention, in the plant monitoring and control apparatus according to the first or second aspect, data of a plurality of operation patterns representing the operation schedule created by the schedule calculating means or as operation result data is stored. The data from the time measurement information file extracted by the request in the saved operation pattern information file is added to a new one.
There is provided an operation pattern registration means for setting as one operation pattern, and the operation plan is calculated based on the operation patterns accumulated according to the situation. According to this means, the operation plan is calculated based on an appropriate operation pattern selected from a plurality of operation patterns according to the situation. Thus, there is no difference between the actual operation and the operation plan, and efficient operation can be performed.

【0024】請求項4の発明は、請求項1または請求項
2記載のプラント監視制御装置において、各運転項目毎
に運転予定時刻とガイダンス表示条件とを含む必要なガ
イダンス情報を保存する予定ガイダンス情報ファイル
と、時間計測情報ファイルから各運転項目の平均時間を
取込み各運転予定時刻を算出して予定ガイダンス情報フ
ァイルへ保存すると共に、所定のガイダンス表示条件の
成立を判定し、ガイダンス表示条件が成立すると、事前
に予定ガイダンス情報を外部へ表示出力する予定ガイダ
ンス表示手段とを設けるようにしたものである。この手
段によれば、各運転項目の運転予定時刻の直前にガイダ
ンス情報が外部へ表示出力される。これにより、運転員
は、次の運転項目を事前に知り、余裕をもって作業をす
ることができ、運転員の作業負担が大幅に軽減される。
According to a fourth aspect of the present invention, in the plant monitoring and control apparatus according to the first or second aspect, scheduled guidance information for storing necessary guidance information including a scheduled operation time and guidance display conditions for each operation item. The average time of each operation item is taken from the file and the time measurement information file, the respective scheduled operation times are calculated and saved in the scheduled guidance information file, and it is determined whether a predetermined guidance display condition is satisfied. And a scheduled guidance display means for displaying and outputting scheduled guidance information to the outside in advance. According to this means, the guidance information is externally displayed and output immediately before the scheduled operation time of each operation item. As a result, the operator can know the next operation item in advance and work with a margin, and the operation burden on the operator is greatly reduced.

【0025】請求項5の発明は、請求項1または請求項
2記載のプラント監視制御装置において、過去の実績の
平均運転時間を参照して作成された運転計画の各運転項
目の運転予定時刻と今回の運転実績の運転時刻を表示あ
るいは印字させる運転計画印字表示手段を設けるように
したものである。この手段によれば、必要な各種運転計
画や運転実績が印字され、運転員へ提供されるので、印
字された情報を保存して前回と今回との比較が容易にで
き、次回の運転に活用することができる。
According to a fifth aspect of the present invention, there is provided the plant monitoring and control apparatus according to the first or second aspect, wherein the scheduled operation time of each operation item of the operation plan created with reference to the average operation time of the past performance. An operation plan print display means for displaying or printing the operation time of the current operation result is provided. According to this means, necessary various operation plans and operation results are printed and provided to the operator, so that the printed information can be stored and compared with the previous operation and the current operation, and utilized for the next operation. can do.

【0026】請求項6の発明は、請求項1または請求項
2記載のプラント監視制御装置において、運転計画に応
じた複数の運転モードを設定するスケジュール選択デー
タ設定ファイルを備え、スケジュール計算手段により計
算された運転計画に応じてスケジュール選択データ設定
ファイルから運転モードを選択して運転員へ知らせるよ
うにしたものである。この手段によれば、運転項目に複
数の運転モードがある場合に、運転計画に応じて適切な
運転モードが選択されて運転がされる。これにより、プ
ラントの設備の寿命等を考慮したプラントの運転ができ
る。
According to a sixth aspect of the present invention, there is provided the plant monitoring and control apparatus according to the first or second aspect, further comprising a schedule selection data setting file for setting a plurality of operation modes in accordance with the operation plan, and calculating by the schedule calculation means. The operation mode is selected from the schedule selection data setting file in accordance with the operation plan, and the operation mode is notified to the operator. According to this means, when there are a plurality of operation modes in the operation item, an appropriate operation mode is selected according to the operation plan and operation is performed. As a result, the plant can be operated in consideration of the life of the plant equipment and the like.

【0027】[0027]

【発明の実施の形態】以下、本発明の実施の形態につい
て図面を参照して説明する。
Embodiments of the present invention will be described below with reference to the drawings.

【0028】図1は、本発明の第1実施の形態を示すプ
ラント監視制御装置の構成図であって、従来技術を示す
図19と同一符号は同一部分または相当部分を示し、プ
ラント監視制御装置P2Aは、プロセス入力手段S1と
スケジュール計算手段S2と実績収集手段S3と自動化
運転手段S4とプロセス表示手段S5と対話入力手段S
6とに、新たに時間計測手段S7を設けると共に、プロ
セスデータ設定ファイルT1とスケジュールデータ設定
ファイルT2と運転実績データ設定ファイルT3とに、
新たに時間計測情報ファイルT4を設け、そして、CR
T表示装置C1とタッチスクリーン装置C2とキー入力
装置C3とを接続している。
FIG. 1 is a block diagram of a plant monitoring and control apparatus according to a first embodiment of the present invention. The same reference numerals as those in FIG. P2A includes a process input unit S1, a schedule calculation unit S2, a result collection unit S3, an automated operation unit S4, a process display unit S5, and a dialogue input unit S
6, a new time measuring means S7 is provided, and a process data setting file T1, a schedule data setting file T2, and an operation result data setting file T3 are
A new time measurement information file T4 is provided, and CR
The T display device C1, the touch screen device C2, and the key input device C3 are connected.

【0029】ここで、プロセス入力手段S1は、一定周
期毎にプラントP1から各種プロセスデータを入力し
て、プロセスデータ設定ファイルT1に設定する。対話
入力手段S6は、タッチスクリーン装置C2やキー入力
装置C3を介して対話画面にて運転員からの運転計画の
計算要求を受け、スケジュール計算手段S2へ運転完了
要求時刻を通知すると共に、表示画面にてプラント運転
終了時などに運転員からの時間計測情報ファイルT4の
更新要求を受け、時間計測手段S7へ通知する。
Here, the process input means S1 inputs various process data from the plant P1 at regular intervals and sets them in the process data setting file T1. The dialogue input means S6 receives an operation plan calculation request from the operator on the dialogue screen via the touch screen device C2 or the key input device C3, notifies the schedule calculation means S2 of the operation completion request time, and displays the display screen. Receives an update request of the time measurement information file T4 from the operator at the end of plant operation, and notifies the time measurement means S7.

【0030】スケジュール計算手段S2は、プロセスデ
ータ設定ファイルT1のプロセスデータに基づき現在の
プラント状態を判断し、時間計測情報ファイルT4内に
設定されている前回のプラント運転までの各運転項目の
平均運転時間を参照して、通知された運転完了要求時刻
を基点としたプラントの運転計画を計算し、スケジュー
ルデータ設定ファイルT2に設定する。
The schedule calculation means S2 determines the current plant state based on the process data in the process data setting file T1, and calculates the average operation of each operation item up to the last plant operation set in the time measurement information file T4. With reference to the time, an operation plan of the plant is calculated based on the notified operation completion request time, and is set in the schedule data setting file T2.

【0031】自動化運転手段S4は、プロセスデータ設
定ファイルT1のプロセスデータとスケジュールデータ
設定ファイルT2の制御パラメータとにより、発電プラ
ントP1へ制御信号を出力してプラントの自動化運転を
行う。
The automatic operation means S4 outputs a control signal to the power generation plant P1 based on the process data in the process data setting file T1 and the control parameters in the schedule data setting file T2, and performs an automatic operation of the plant.

【0032】実績収集手段S3は、プラント運転の進行
に伴って周期的にプロセスデータ設定ファイルT1のプ
ロセスデータより各運転計画の実績時刻の検出とタービ
ン回転数や発電機出力などのデータを収集して運転実績
データ設定ファイルT3へ設定する。
The result collection means S3 periodically detects the actual time of each operation plan and collects data such as turbine speed and generator output from the process data in the process data setting file T1 as the plant operation proceeds. To the operation result data setting file T3.

【0033】プロセス表示手段S5は、運転実績データ
設定ファイルT3に保存される各運転実績時刻やタービ
ン回転数及び発電機出力などの曲線表示データを画面形
式にてCRT表示装置C1へ表示して周期的に更新す
る。
The process display means S5 displays on the CRT display device C1 the curve display data such as each operation result time, turbine speed, and generator output stored in the operation result data setting file T3 in the form of a screen, and displays the cycle. Update.

【0034】時間計測手段S7は、自動化運転手段S4
によるプラント運転の進行に伴って周期的に、プロセス
データ設定ファイルT1の現在のプロセスデータを入力
して時間計測情報ファイルT4内の各運転項目の時間計
測開始/終了条件の判定を行うことにより、開始条件成
立から終了条件成立までの各運転項目の運転時間を計測
して、その運転時間と運転項目の開始時刻及び終了時刻
とを時間計測情報ファイルT4へ設定する。また、対話
入力手段S6からの時間計測情報ファイルT4の更新要
求通知により時間計測した全運転項目について、前回ま
での平均運転時間との平均時間を算出し、新たな平均運
転時間として時間計測情報ファイルT4へ設定する。
The time measuring means S7 includes an automated driving means S4
By periodically inputting the current process data of the process data setting file T1 and determining the time measurement start / end conditions of each operation item in the time measurement information file T4 as the plant operation proceeds, The operation time of each operation item from the start condition establishment to the end condition establishment is measured, and the operation time and the start time and end time of the operation item are set in the time measurement information file T4. Further, for all the operation items whose time has been measured in response to the update request notification of the time measurement information file T4 from the dialogue input means S6, the average time with the average operation time up to the previous time is calculated, and the time measurement information file is set as a new average operation time. Set to T4.

【0035】以上の構成により、図2に示す対話画面5
1上にて運転員より運転計画の計算要求が行われると、
対話入力手段S6によって、運転員からの運転計画の計
算要求が受けられ、スケジュール計算手段S2へ運転完
了要求時刻が通知される。すなわち、図2に示す対話画
面51は、運転実績グラフ表示画面51aと項目表示部
51bと運転完了要求時刻表示画面51c等があり、こ
の画面で、計算要求51dが実行される。
With the above configuration, the interactive screen 5 shown in FIG.
When a request for calculation of the operation plan is made by the operator on
A request for calculation of an operation plan is received from the operator by the dialogue input means S6, and the operation completion request time is notified to the schedule calculation means S2. That is, the interactive screen 51 shown in FIG. 2 includes an operation result graph display screen 51a, an item display section 51b, an operation completion request time display screen 51c, and the like, and a calculation request 51d is executed on this screen.

【0036】スケジュール計算手段S2では、対話入力
手段S6からの通知により、プロセスデータ設定ファイ
ルT1のプロセスデータより現在のプラント状態を判断
し、時間計測情報ファイルT4内に設定されている前回
のプラント運転までの各運転項目の平均運転時間を参照
して、通知された運転完了要求時刻を基点としたプラン
トの運転計画を計算し、スケジュールデータ設定ファイ
ルT2に設定する。
The schedule calculation means S2 determines the current plant state from the process data in the process data setting file T1 based on the notification from the interactive input means S6, and determines the last plant operation set in the time measurement information file T4. With reference to the average operation time of each operation item up to, the operation plan of the plant based on the notified operation completion request time is calculated and set in the schedule data setting file T2.

【0037】プロセス表示手段S5では、スケジュール
計算手段S2にて設定されたスケジュールデータ設定フ
ァイルT2の運転計画データである各運転予定時刻など
を図2に示す如くの対話画面51にてCRT表示装置C
1へ表示することにより、運転員へ運転計画の計算結果
を提供する。
The process display means S5 displays the respective scheduled operation times, which are the operation plan data of the schedule data setting file T2 set by the schedule calculation means S2, on the CRT display device C on an interactive screen 51 as shown in FIG.
By displaying the result in 1, the calculation result of the operation plan is provided to the operator.

【0038】その後、プラントの自動化運転の進行に伴
い時間計測手段S7は、一定周期毎に、プロセスデータ
設定ファイルT1の現在プロセスデータを入力して時間
計測情報ファイルT4内の各運転項目の時間計測開始/
終了条件の判定を行い、開始条件成立から終了条件成立
までの各運転項目の運転時間を計測して、今回運転時間
と運転項目の開始時刻及び終了時刻とを時間計測情報フ
ァイルT4へ設定する。
Thereafter, with the progress of the automatic operation of the plant, the time measuring means S7 inputs the current process data of the process data setting file T1 at regular intervals and measures the time of each operation item in the time measurement information file T4. start/
The end condition is determined, the operation time of each operation item from the start condition establishment to the end condition establishment is measured, and the current operation time and the start time and end time of the operation item are set in the time measurement information file T4.

【0039】実績収集手段S3は、一定周期毎にプロセ
スデータ設定ファイルT1のプロセスデータより各運転
計画の実績時刻の検出とタービン回転数や発電機出力な
どのデータを収集して運転実績データ設定ファイルT3
へ設定する。
The result collecting means S3 detects the actual time of each operation plan from the process data in the process data setting file T1 and collects data such as the turbine speed and the generator output at regular intervals and collects the operation result data setting file. T3
Set to

【0040】プロセス表示手段S5では、実績収集手段
S3にて設定された運転実績データ設定ファイルT3の
データである各運転実績時刻とタービン回転数や発電機
出力などの曲線表示データを画面形式にてCRT表示装
置C1へ周期的に表示を更新することにより、運転員へ
運転計画と運転実績とを提供する。
The process display means S5 displays, in a screen format, each operation result time, which is data of the operation result data setting file T3 set by the result collection means S3, and curve display data such as turbine speed and generator output. By periodically updating the display on the CRT display device C1, an operation plan and operation results are provided to the operator.

【0041】更に、プラント運転の終了時などに、図4
に示すような表示画面52にて運転員から更新要求52
aが行われた場合、対話入力手段S6は、運転員からの
更新要求を受け、時間計測手段S7へ時間計測情報ファ
イルT4の更新要求を通知する。
Further, at the end of plant operation, for example, FIG.
On the display screen 52 shown in FIG.
When a is performed, the dialogue input unit S6 receives the update request from the operator, and notifies the time measurement unit S7 of the update request for the time measurement information file T4.

【0042】時間計測手段S7では、対話入力手段S6
からの通知により、時間計測した全運転項目について、
前回までの平均運転時間について平均時間を算出し新た
な平均運転時間として時間計測情報ファイルT4へ設定
する。
In the time measuring means S7, the dialog input means S6
From the notification from
The average time is calculated for the average operation time up to the previous time and set as a new average operation time in the time measurement information file T4.

【0043】次に、時間計測手段S7の処理について、
図5を用いて詳細に説明する。
Next, the processing of the time measuring means S7 will be described.
This will be described in detail with reference to FIG.

【0044】まず、時間計測手段S7は、処理S70に
て時間計測処理か、あるいは、対話入力手段S6からの
通知による処理かを判断し、時間計測処理の場合には処
理S71へ移行し、対話入力手段S6からの通知による
処理の場合には処理S78へ処理を移行する。
First, the time measurement means S7 determines whether the processing is time measurement processing in step S70 or processing based on a notification from the dialogue input means S6. In the case of the processing based on the notification from the input means S6, the processing shifts to processing S78.

【0045】次に、処理S71では、プロセスデータ設
定ファイルT1の所定のプロセスデータによりプラント
P1が自動化運転中か否かを判断して、自動化運転中で
ない場合には処理S77へ処理を移す。
Next, in step S71, it is determined whether or not the plant P1 is in an automated operation based on predetermined process data in the process data setting file T1, and if not, the process proceeds to step S77.

【0046】処理S72では、前回も自動化運転中であ
ったか否かを判断し、自動化運転中でなかった場合にの
み図3に示す時間計測情報ファイルT4の全ての運転項
目の計測開始時刻/計測終了時刻及び今回運転時間の設
定時刻をクリアする。
In the process S72, it is determined whether or not the automatic operation was also performed last time. Only when the automatic operation was not performed, the measurement start time / measurement end time of all the operation items in the time measurement information file T4 shown in FIG. Clear the time and the set time of the current operation time.

【0047】図3に示す時間計測情報ファイルT4は、
起動運転情報ポインタT4aと停止運転情報ポインタT
4bとがあり、起動運転情報ポインタT4aに関連する
複数の起動運転項目iからなる起動運転情報T4cと各
起動運転項目iの詳細項目T4dがある。詳細項目T4
dには、「運転項目名称」「計測開始条件」「計測終了
条件」「計測開始時刻」「計測終了時刻」「今回運転時
間」のエリアが設けられている。
The time measurement information file T4 shown in FIG.
Start operation information pointer T4a and stop operation information pointer T
4b, there are start operation information T4c including a plurality of start operation items i related to the start operation information pointer T4a, and detailed items T4d of each start operation item i. Detail item T4
Areas d, “operation item name”, “measurement start condition”, “measurement end condition”, “measurement start time”, “measurement end time”, and “current operation time” are provided.

【0048】次に、処理S73では、現在のプラント自
動化運転状態(起動運転/停止運転)を判断し、その運
転状態用の運転項目iの情報を時間計測情報ファイルT
4より順次取り出す。
Next, in step S73, the current plant automation operation state (start operation / stop operation) is determined, and information on the operation item i for the operation state is stored in the time measurement information file T.
Take out sequentially from 4.

【0049】処理S74では、処理S73で取り出した
運転項目iの計測開始条件をプロセスデータ設定ファイ
ルT1の各種プロセスデータより判断し、条件が成立
し、かつ、計測開始時刻が設定されていない場合にのみ
現在時刻を運転項目iの計測開始時刻として設定する。
In step S74, the measurement start condition of the operation item i extracted in step S73 is determined from the various process data in the process data setting file T1, and if the condition is satisfied and the measurement start time is not set. Only the current time is set as the measurement start time of the operation item i.

【0050】処理S75では、運転項目iの計測開始時
刻が設定されており、かつ、計測終了条件が条件成立
し、計測終了時刻が設定されていない場合にのみ、現在
時刻を運転項目iの計測終了時刻として設定する。更
に、計測終了時刻と計測開始時刻との時間差分を運転項
目iの今回運転時間として設定する。
In the process S75, only when the measurement start time of the operation item i is set and the measurement end condition is satisfied and the measurement end time is not set, the current time is measured by the operation item i. Set as the end time. Further, a time difference between the measurement end time and the measurement start time is set as the current operation time of the operation item i.

【0051】処理S76では、処理S73で判断した運
転状態用の全ての運転項目について処理S73から処理
S75までを終了したか否かを判断し、終了した場合に
は処理S77へ、終了していない場合には全ての運転項
目について終了するまで処理S73へ処理を移す。
In step S76, it is determined whether or not steps S73 to S75 have been completed for all of the operation items for the operation state determined in step S73. In this case, the process proceeds to step S73 until all the operation items are completed.

【0052】処理S77では、一定時間遅延後に処理S
70へ処理を移す。
In step S77, after a predetermined time delay,
The processing moves to 70.

【0053】一方、処理S78では、対話入力手段S6
からの通知により、時間計測情報ファイルT4の全ての
運転項目について検索し、今回運転時間が設定されてい
る運転項目についてのみ、以下の計算の式(1)にて前
回までの平均運転時間と今回運転時間との平均時間を計
算し、新たな平均運転時間として設定した後、処理S7
7へ処理を移す。
On the other hand, in step S78, the dialogue input means S6
From the notification from, all operation items in the time measurement information file T4 are searched, and only the operation items for which the current operation time is set are calculated using the following calculation formula (1) and the average operation time up to the previous time and the current operation time. After calculating the average time with the operation time and setting it as a new average operation time, the process S7
Move the process to 7.

【0054】 Tn={〔To*(N−1)〕+T}/N …(1) Tn:新たな平均運転時間 To:前回までの平均運転時間 T:今回運転時間 N:平均化係数Tn = {[To * (N−1)] + T} / N (1) Tn: new average operation time To: average operation time until last time T: current operation time N: averaging coefficient

【0055】ここで、平均化係数Nは、平均運転時間の
算出にあたり今回運転時間の割合であり、N=4の場
合、1/4(25%)の割合で前回までの平均運転時間
と平均計算することになる。なお、この平均化係数N
は、プラント毎に固定化することも、時間計測情報ファ
イルT4の各運転項目毎にその設定領域を設けて各運転
項目毎に個別の平均化係数Nを持つことも可能である。
Here, the averaging coefficient N is the ratio of the current operation time in calculating the average operation time. When N = 4, the averaging coefficient N is 1/4 (25%) and the average operation time up to the previous operation is the average operation time. Will be calculated. The averaging coefficient N
Can be fixed for each plant, or a setting area can be provided for each operation item in the time measurement information file T4 to have an individual averaging coefficient N for each operation item.

【0056】このように第1実施の形態によれば、プラ
ント運転を繰返すほど運転員の操作における個人的時間
差が平均化され、また、長年のプラント運転におけるプ
ラント特性の変化による運転時間差が吸収されるため、
運転計画通りにプラントを運転することができる。
As described above, according to the first embodiment, as the plant operation is repeated, the personal time difference in the operation of the operator is averaged, and the operation time difference due to the change in the plant characteristics in the long-term plant operation is absorbed. Because
The plant can be operated according to the operation plan.

【0057】図6は、本発明の第2実施の形態を示すプ
ラント監視制御装置の構成図である。
FIG. 6 is a block diagram of a plant monitoring and control apparatus according to a second embodiment of the present invention.

【0058】図6において、従来技術を示す図19と同
一符号は同一部分または相当部分を示し、プラント監視
制御装置P2Bはプロセス入力手段S1とスケジュール
計算手段S2と実績収集手段S3と自動化運転手段S4
とプロセス表示手段S5と対話入力手段S6とに新た
に、時間計測手段S7と運転パターン登録手段S8とを
備え、さらに、プロセスデータ設定ファイルT1とスケ
ジュールデータ設定ファイルT2と運転実績データ設定
ファイルT3とに新たに、時間計測情報ファイルT4と
運転パターン情報ファイルT5とを備え、さらに、CR
T表示装置C1とタッチスクリーン装置C2とキー入力
装置C3とを接続している。
In FIG. 6, the same reference numerals as those in FIG. 19 showing the prior art denote the same or corresponding parts, and the plant monitoring and control device P2B comprises a process input means S1, a schedule calculation means S2, a performance collection means S3, and an automatic operation means S4
, A process display means S5 and an interactive input means S6, a time measuring means S7 and an operation pattern registration means S8 are newly provided, and further, a process data setting file T1, a schedule data setting file T2, an operation result data setting file T3, Newly provided with a time measurement information file T4 and an operation pattern information file T5.
The T display device C1, the touch screen device C2, and the key input device C3 are connected.

【0059】ここで、プロセス入力手段S1は、一定周
期毎にプラントP1から各種プロセスデータを入力し
て、プロセスデータ設定ファイルT1に設定する。対話
入力手段S6は、タッチスクリーン装置C2やキー入力
装置C3を介して対話画面にて運転員からの運転計画の
計算要求を受け、スケジュール計算手段S2へ運転完了
要求時刻を通知すると共に、表示画面にてプラント運転
終了時などに運転員からの時間計測情報ファイルT4の
更新要求を受け、時間計測手段S7へ通知し、対話画面
にて運転員からの運転パターン保存/設定の要求を受
け、運転パターン登録手段S8へ通知する。
Here, the process input means S1 inputs various process data from the plant P1 at regular intervals and sets them in the process data setting file T1. The dialogue input means S6 receives an operation plan calculation request from the operator on the dialogue screen via the touch screen device C2 or the key input device C3, notifies the schedule calculation means S2 of the operation completion request time, and displays the display screen. Receives the update request of the time measurement information file T4 from the operator at the end of the plant operation, notifies the time measurement means S7, receives the operation pattern storage / setting request from the operator on the interactive screen, Notify the pattern registration means S8.

【0060】運転パターン登録手段S8は、対話入力手
段S6からの運転パターン保存/設定の要求通知によ
り、時間計測情報ファイルT4からデータを要求された
パターン番号に対応する運転パターン情報ファイルT5
の領域に保存したり、要求されたパターン番号に対応す
る運転パターン情報ファイルT5のデータを時間計測情
報ファイルT4へ設定したりする。
The operation pattern registration means S8 receives an operation pattern storage / setting request notification from the interactive input means S6, and the operation pattern information file T5 corresponding to the pattern number for which data is requested from the time measurement information file T4.
Of the operation pattern information file T5 corresponding to the requested pattern number is set in the time measurement information file T4.

【0061】スケジュール計算手段S2は、プロセスデ
ータ設定ファイルT1のプロセスデータより現在のプラ
ント状態を判断し、時間計測情報ファイルT4内に設定
されている前回のプラント運転までの各運転項目の平均
運転時間を参照して、通知された運転完了要求時刻を基
点としたプラントの運転計画を計算し、スケジュールデ
ータ設定ファイルT2に設定する。
The schedule calculation means S2 determines the current plant state from the process data in the process data setting file T1, and calculates the average operation time of each operation item until the last plant operation set in the time measurement information file T4. , A plant operation plan is calculated based on the notified operation completion request time, and is set in the schedule data setting file T2.

【0062】プロセス表示手段S5は、スケジュールデ
ータ設定ファイルT2の運転計画データである各運転予
定時刻などを画面形式にてCRT表示装置C1へ表示す
る。
The process display means S5 displays the scheduled operation time, which is the operation plan data of the schedule data setting file T2, on the CRT display device C1 in a screen format.

【0063】自動化運転手段S4は、プロセスデータ設
定ファイルT1のプロセスデータとスケジュールデータ
設定ファイルT2の制御パラメータとにより、プラント
への制御信号を出力してプラントの自動化運転を行う。
The automatic operation means S4 outputs a control signal to the plant based on the process data of the process data setting file T1 and the control parameters of the schedule data setting file T2, and performs the automatic operation of the plant.

【0064】実績収集手段S3は、プラント運転の進行
に伴って周期的にプロセスデータ設定ファイルT1のプ
ロセスデータより各運転計画の実績時刻の検出とタービ
ン回転数や発電機出力などのデータを収集して運転実績
データ設定ファイルT3へ設定する。
The result collection means S3 periodically detects the actual time of each operation plan and collects data such as turbine speed and generator output from the process data in the process data setting file T1 as the plant operation proceeds. To the operation result data setting file T3.

【0065】また、プロセス表示手段S5は、運転実績
データ設定ファイルT3に保存された各運転実績時刻と
タービン回転数や発電機出力などの曲線表示データを画
面形式にてCRT表示装置C1へ表示して周期的に更新
する。
Further, the process display means S5 displays each operation result time and curve display data such as turbine speed and generator output stored in the operation result data setting file T3 on the CRT display device C1 in a screen format. Update periodically.

【0066】時間計測手段S7は、自動化運転手段S4
によるプラント運転の進行に伴って周期的に、プロセス
データ設定ファイルT1の現在プロセスデータを入力し
て時間計測情報ファイルT4内の各運転項目の時間計測
開始/終了条件の判定を行うことにより、開始条件成立
から終了条件成立までの各運転項目の運転時間を計測し
て、その運転時間と運転項目の開始時刻及び終了時刻と
を時間計測情報ファイルT4へ設定する。また、対話入
力手段S6からの時間計測情報ファイルT4の更新要求
通知により時間計測した全運転項目について、前回まで
の平均運転時間との平均時間を算出し新たな平均運転時
間として時間計測情報ファイルT4へ設定する。
The time measuring means S7 includes an automatic driving means S4
By periodically inputting the current process data of the process data setting file T1 and determining the time measurement start / end conditions of each operation item in the time measurement information file T4 as the plant operation progresses. The operation time of each operation item from when the condition is satisfied to when the end condition is satisfied is measured, and the operation time and the start time and end time of the operation item are set in the time measurement information file T4. Further, for all the operation items whose time has been measured by the update request notification of the time measurement information file T4 from the interactive input means S6, the average time with the average operation time up to the previous time is calculated, and the time measurement information file T4 is calculated as a new average operation time. Set to

【0067】以上の構成により、運転員が対話入力手段
S6を介して運転パターンの保存/設定要求を行った場
合、対話入力手段S6は、運転終了時などに、タッチス
クリーン装置C2やキー入力装置C3を介して図7に示
す対話画面53を表示する。
With the above configuration, when the operator makes a request to save / set an operation pattern via the dialogue input means S6, the dialogue input means S6 is activated by the touch screen device C2 or the key input device at the end of operation or the like. The interactive screen 53 shown in FIG. 7 is displayed via C3.

【0068】この図7に示す対話画面53には、運転パ
ターン一覧表示エリア53aと指定された運転パターン
No.(××)エリア53bと運転パターン名称エリア
53cと保存要求エリア53dと設定要求エリア53e
が設けられている。
The interactive screen 53 shown in FIG. 7 includes an operation pattern list display area 53a and a designated operation pattern No. (Xx) area 53b, operation pattern name area 53c, storage request area 53d, and setting request area 53e
Is provided.

【0069】この対話画面53で、運転員からの運転パ
ターン保存要求を受け、要求された運転パターン番号と
運転パターン名称と共に運転パターン保存要求を運転パ
ターン登録手段S8へ通知する。
On this dialogue screen 53, an operation pattern storage request is received from the operator, and an operation pattern storage request is notified to the operation pattern registration means S8 together with the requested operation pattern number and operation pattern name.

【0070】運転パターン登録手段S8は、対話入力手
段S6からの運転パターン保存要求の通知により、時間
計測情報ファイルT4のデータと通知された運転パター
ン名称を通知された運転パターン番号に対応する図8に
示す運転パターン情報ファイルT5へ保存する。
The operation pattern registering means S8 responds to the operation pattern storage request from the interactive input means S6, and the data of the time measurement information file T4 and the notified operation pattern name correspond to the notified operation pattern number in FIG. In the operation pattern information file T5 shown in FIG.

【0071】図8に示す運転パターン情報ファイルT5
は運転パターンNo.1〜No.nのエリアT5aがあ
り、各運転パターンiについて運転パターン番号エリア
T5bと運転パターンデータエリアT5cが設けられて
いる。
The operation pattern information file T5 shown in FIG.
Is the operation pattern No. 1 to No. There are n areas T5a, and an operation pattern number area T5b and an operation pattern data area T5c are provided for each operation pattern i.

【0072】また、対話入力手段S6は、運転計画時等
に、タッチスクリーン装置C2やキー入力装置C3を介
して、図7に示す対話画面53にて運転員からの運転パ
ターン設定要求を受け、要求された運転パターン番号と
共に運転パターン設定要求を運転パターン登録手段S8
へ通知する。
Further, the dialogue input means S6 receives a driving pattern setting request from the driver on the dialogue screen 53 shown in FIG. 7 via the touch screen device C2 or the key input device C3 at the time of driving planning or the like. An operation pattern setting request is sent together with the requested operation pattern number to the operation pattern registration means S8.
Notify to

【0073】運転パターン登録手段S8は、対話入力手
段S6からの運転パターン設定要求の通知により、運転
パターン情報ファイルT5より通知された運転パターン
番号に対応する運転パターンデータを取出し、時間計測
情報ファイルT4へ設定する。その後、対話入力手段S
6は、対話画面にて運転員からの運転計画の計算要求を
受け、スケジュール計算手段S2へ運転完了要求時刻を
通知する。
The operation pattern registration means S8 extracts the operation pattern data corresponding to the operation pattern number notified from the operation pattern information file T5 by the notification of the operation pattern setting request from the interactive input means S6, and obtains the time measurement information file T4. Set to Then, the interactive input means S
6 receives the operation plan calculation request from the operator on the dialogue screen and notifies the schedule calculation means S2 of the operation completion request time.

【0074】スケジュール計算手段S2は、プロセスデ
ータ設定ファイルT1のプロセスデータより現在のプラ
ント状態を判断し、運転パターン登録手段S8にて設定
された時間計測情報ファイルT4より各運転項目の平均
運転時間を取出して、対話入力手段S6より通知された
運転完了要求時刻を基点としたプラントの運転計画を計
算し、スケジュールデータ設定ファイルT2に設定す
る。
The schedule calculation means S2 determines the current plant state from the process data in the process data setting file T1, and calculates the average operation time of each operation item from the time measurement information file T4 set by the operation pattern registration means S8. Then, the operation plan of the plant is calculated based on the operation completion request time notified from the interactive input means S6, and is set in the schedule data setting file T2.

【0075】プロセス表示手段S5では、スケジュール
計算手段S2にて設定されたスケジュールデータ設定フ
ァイルT2の運転計画データをCRT表示装置C1へ表
示することにより、運転員へ運転計画の計算結果を提供
する。これにより、予め保存されている各運転パターン
における時間計測情報ファイルT4での運転計画の計算
が可能となる。
The process display means S5 displays the operation plan data of the schedule data setting file T2 set by the schedule calculation means S2 on the CRT display device C1, thereby providing the operator with a calculation result of the operation plan. This makes it possible to calculate an operation plan in the time measurement information file T4 for each operation pattern stored in advance.

【0076】このように第2実施の形態によれば、夏場
/冬場等季節の気温差によるプラント特性の違いがあっ
ても、それぞれの場合の運転パターンに応じた時間計測
情報を保存/設定できるため、より精度の高い運転計画
が計算でき、運転計画通りにプラントを運転することが
できる。
As described above, according to the second embodiment, even if there are differences in plant characteristics due to seasonal temperature differences such as summer / winter, time measurement information can be stored / set according to the operation pattern in each case. Therefore, a more accurate operation plan can be calculated, and the plant can be operated according to the operation plan.

【0077】図9は、本発明の第3実施の形態を示すプ
ラント監視制御装置の構成図である。
FIG. 9 is a block diagram of a plant monitoring and control apparatus according to a third embodiment of the present invention.

【0078】図9において、従来技術を示す図19と同
一符号は同一部分または相当部分を示し、プラント監視
制御装置P2Cはプロセス入力手段S1とスケジュール
計算手段S2と実績収集手段S3と自動化運転手段S4
とプロセス表示手段S5と対話入力手段S6とに、新た
に時間計測手段S7と予定ガイダンス表示手段S9とを
備え、プロセスデータ設定ファイルT1とスケジュール
データ設定ファイルT2と運転実績データ設定ファイル
T3とに、新たに時間計測情報ファイルT4と予定ガイ
ダンス情報ファイルT6とを備え、さらに、CRT表示
装置C1とタッチスクリーン装置C2とキー入力装置C
3と、新たに、チャイム装置C4とを接続している。
In FIG. 9, the same reference numerals as those in FIG. 19 showing the prior art denote the same or corresponding parts, and the plant monitoring and control device P2C comprises a process input means S1, a schedule calculation means S2, a performance collection means S3, and an automatic operation means S4
, A process display means S5, a dialogue input means S6, a time measuring means S7 and a schedule guidance display means S9, and a process data setting file T1, a schedule data setting file T2, and an operation result data setting file T3. A time measurement information file T4 and a schedule guidance information file T6 are newly provided, and a CRT display device C1, a touch screen device C2, and a key input device C are further provided.
3 and a new chime device C4.

【0079】ここで、プロセス入力手段S1は、一定周
期毎にプラントP1から各種プロセスデータを入力し
て、プロセスデータ設定ファイルT1に設定する。対話
入力手段S6は、タッチスクリーン装置C2やキー入力
装置C3を介して対話画面にて運転員からの運転計画の
計算要求を受け、スケジュール計算手段S2へ運転完了
要求時刻を通知する一方、表示画面にてプラント運転終
了時などに運転員からの時間計測情報ファイルT4の内
容の更新要求を受け、時間計測手段S7へ通知する。
Here, the process input means S1 inputs various process data from the plant P1 at regular intervals and sets them in the process data setting file T1. The dialogue input means S6 receives an operation plan calculation request from the operator on the dialogue screen via the touch screen device C2 or the key input device C3, and notifies the schedule calculation means S2 of the operation completion request time, while displaying the display screen. Receives a request for updating the contents of the time measurement information file T4 from the operator at the end of the plant operation or the like, and notifies the time measurement means S7.

【0080】スケジュール計算手段S2は、プロセスデ
ータ設定ファイルT1のプロセスデータより現在のプラ
ント状態を判断し、時間計測情報ファイルT4内に設定
されている前回のプラント運転までの各運転項目の平均
運転時間を参照して、通知された運転完了要求時刻を基
点としたプラントの運転計画を計算し、スケジュールデ
ータ設定ファイルT2に設定する。また、運転計画の計
算終了時に運転開始予定時刻と運転開始項目番号とを予
定ガイダンス表示手段S9へ通知する。
The schedule calculation means S2 determines the current plant state from the process data in the process data setting file T1, and calculates the average operation time of each operation item until the last plant operation set in the time measurement information file T4. , A plant operation plan is calculated based on the notified operation completion request time, and is set in the schedule data setting file T2. At the end of the calculation of the operation plan, the scheduled operation start time and the operation start item number are notified to the schedule guidance display means S9.

【0081】プロセス表示手段S5は、スケジュールデ
ータ設定ファイルT2の運転計画データである各運転予
定時刻などを画面形式にてCRT表示装置C1へ表示す
る。
The process display means S5 displays the scheduled operation times as the operation plan data of the schedule data setting file T2 on the CRT display device C1 in a screen format.

【0082】自動化運転手段S4は、プロセスデータ設
定ファイルT1のプロセスデータとスケジュールデータ
設定ファイルT2の制御パラメータとにより、プラント
へ制御信号を出力してプラントの自動化運転を行う。
The automatic operation means S4 outputs a control signal to the plant based on the process data in the process data setting file T1 and the control parameters in the schedule data setting file T2, and performs the automatic operation of the plant.

【0083】実績収集手段S3は、プラント運転の進行
に伴って周期的にプロセスデータ設定ファイルT1のプ
ロセスデータより各運転計画の実績時刻の検出とタービ
ン回転数や発電機出力などのデータを収集して運転実績
データ設定ファイルT3へ設定する。
The performance collection means S3 periodically detects the performance time of each operation plan and collects data such as turbine speed and generator output from the process data in the process data setting file T1 as the plant operation proceeds. To the operation result data setting file T3.

【0084】また、プロセス表示手段S5は、運転実績
データ設定ファイルT3のデータである各運転実績時刻
とタービン回転数や発電機出力などの曲線表示データを
画面形式にてCRT表示装置C1へ表示して周期的に更
新する。
The process display means S5 displays in the CRT display device C1 in the form of a screen, each operation result time, which is data of the operation result data setting file T3, and curve display data such as turbine speed and generator output. Update periodically.

【0085】時間計測手段S7は、自動化運転手段S4
によるプラント運転の進行に伴って周期的に、プロセス
データ設定ファイルT1の現在プロセスデータを入力し
て時間計測情報ファイルT4内の各運転項目の時間計測
開始/終了条件の判定を行うことにより、開始条件成立
から終了条件成立までの各運転項目の運転時間を計測し
て、その運転時間と運転項目の開始時刻及び終了時刻と
を時間計測情報ファイルT4へ設定する。また、対話入
力手段S6からの時間計測情報ファイルT4の更新要求
通知により時間計測した全運転項目について、前回まで
の平均運転時間との平均時間を算出し新たな平均運転時
間として時間計測情報ファイルT4へ設定する。
The time measuring means S7 includes an automatic driving means S4
By periodically inputting the current process data of the process data setting file T1 and determining the time measurement start / end conditions of each operation item in the time measurement information file T4 as the plant operation progresses. The operation time of each operation item from when the condition is satisfied to when the end condition is satisfied is measured, and the operation time and the start time and end time of the operation item are set in the time measurement information file T4. Further, for all the operation items whose time has been measured by the update request notification of the time measurement information file T4 from the interactive input means S6, the average time with the average operation time up to the previous time is calculated, and the time measurement information file T4 is calculated as a new average operation time. Set to

【0086】予定ガイダンス表示手段S9は、スケジュ
ール計算手段S2からの運転計画計算終了の通知にて、
時間計測情報ファイルT4より各運転項目の平均運転時
間を取出し、予定ガイダンス情報ファイルT6内の各運
転項目の運転開始予定時刻を算出して設定する。
The schedule guidance display means S9 receives the notification of the end of the operation plan calculation from the schedule calculation means S2,
The average operation time of each operation item is extracted from the time measurement information file T4, and the scheduled operation start time of each operation item in the schedule guidance information file T6 is calculated and set.

【0087】また、プラント運転中には周期的に予定ガ
イダンス情報ファイルT6のガイダンス表示条件と運転
開始予定時刻とを監視して、予定ガイダンスメッセージ
を周期的にCRT表示装置C1へ表示すると共に、チャ
イム装置C4からもチャイム音を出力して運転員へ知ら
せる。
During the operation of the plant, the guidance display conditions and scheduled operation start time of the scheduled guidance information file T6 are periodically monitored, and the scheduled guidance message is periodically displayed on the CRT display device C1 and the chime is displayed. The device C4 also outputs a chime sound to notify the operator.

【0088】以上の構成により、図2に示す如くの対話
画面51にて運転員より運転計画の計算要求が行われた
場合、対話入力手段S6は、運転員からの運転計画の計
算要求を受け、スケジュール計算手段S2へ運転完了要
求時刻を通知する。
With the above configuration, when an operator requests a calculation of an operation plan on the dialogue screen 51 as shown in FIG. 2, the dialogue input means S6 receives a request for calculation of the operation plan from the operator. Then, the operation completion request time is notified to the schedule calculation means S2.

【0089】スケジュール計算手段S2は、対話入力手
段S6からの通知により、プロセスデータ設定ファイル
T1のプロセスデータより現在のプラント状態を判断
し、時間計測情報ファイルT4内に設定されている前回
のプラント運転までの各運転項目の平均運転時間を参照
して、通知された運転完了要求時刻を基点としたプラン
トの運転計画を計算し、スケジュールデータ設定ファイ
ルT2に設定すると共に、予定ガイダンス表示手段S9
へ運転開始予定時刻と運転開始項目番号を通知する。
The schedule calculation means S2 determines the current plant state from the process data in the process data setting file T1 based on the notification from the interactive input means S6, and determines the last plant operation set in the time measurement information file T4. With reference to the average operation time of each operation item up to the above, a plant operation plan based on the notified operation completion request time is calculated, set in the schedule data setting file T2, and the schedule guidance display means S9.
To the scheduled operation start time and the operation start item number.

【0090】予定ガイダンス表示手段S9は、スケジュ
ール計算手段S2からの通知により、通知された運転開
始予定時刻と運転開始項目番号とに基づき時間計測情報
ファイルT4より各運転項目の平均運転時間を取出し、
予定ガイダンス情報ファイルT6内の各運転項目の運転
開始予定時刻を算出して設定する。
The schedule guidance display means S9 takes out the average operation time of each operation item from the time measurement information file T4 based on the notified scheduled operation start time and the operation start item number according to the notification from the schedule calculation means S2.
The scheduled operation start time of each operation item in the schedule guidance information file T6 is calculated and set.

【0091】その後、プラントの自動化運転の進行に伴
い予定ガイダンス表示手段S9は、一定周期毎に、予定
ガイダンス情報ファイルT6のガイダンス表示条件と運
転開始予定時刻とを監視して、ガイダンス表示条件が成
立し、かつ、運転開始予定時刻の5分前である運転項目
の中で一番早い運転開始予定時刻の運転項目について、
予定ガイダンスメッセージと運転開始予定時刻までの残
り時間とを周期的にCRT表示装置C1へ表示すると共
に、運転開始予定時刻の1分前にはチャイム装置C4に
てチャイム音を出力して運転員へ知らせる。
Thereafter, the schedule guidance display means S9 monitors the guidance display condition and the scheduled operation start time of the schedule guidance information file T6 at regular intervals as the automated operation of the plant progresses, and the guidance display condition is satisfied. And the operation item at the earliest scheduled operation start time among the operation items 5 minutes before the scheduled operation start time,
The scheduled guidance message and the remaining time until the scheduled operation start time are periodically displayed on the CRT display device C1, and one minute before the scheduled operation start time, the chime device C4 outputs a chime sound to the operator. Inform.

【0092】次に、予定ガイダンス表示手段S9の処理
について図10を用いて詳細に説明する。
Next, the processing of the schedule guidance display means S9 will be described in detail with reference to FIG.

【0093】まず、予定ガイダンス表示手段S9は、処
理S90にて予定ガイダンス表示処理かスケジュール計
算手段S2からの通知による処理かを判断し、予定ガイ
ダンス表示処理の場合には処理S92へ、スケジュール
計算手段S2からの通知による処理の場合には処理S9
1へ処理を移す。
First, the scheduled guidance display means S9 determines whether the scheduled guidance display processing or the processing based on the notification from the schedule calculation means S2 is performed in step S90, and in the case of the scheduled guidance display processing, proceeds to step S92. In the case of processing by notification from S2, processing S9
Move the process to 1.

【0094】次に、処理S91では、運転項目番号を検
索キーとして時間計測情報ファイルT4の平均運転時間
を検索して、スケジュール計算手段S2より通知された
運転開始予定時刻と運転開始項目番号とに基づき、以下
の式(2)の計算式より全ての運転開始予定時刻を算出
し予定ガイダンス情報ファイルT6へ設定して、処理S
98へ処理を移す。
Next, in step S91, the average operation time of the time measurement information file T4 is searched using the operation item number as a search key, and the average operation time and the operation start item number notified by the schedule calculation means S2 are retrieved. Based on the following formula (2), all scheduled operation start times are calculated and set in the scheduled guidance information file T6, and the process S
Move the process to 98.

【0095】[0095]

【数1】 (Equation 1)

【0096】図11は、予定ガイダンス情報ファイルT
6の構成を示し、ガイダンス情報1〜nの各エリアT6
aに対して詳細データのエリアT6bがあり、詳細デー
タのエリアT6bには、「運転項目番号」「ガイダンス
表示条件」「運転開始予定時刻」「ガイダンスメッセー
ジ」のエリアが設けられている。
FIG. 11 shows the schedule guidance information file T
6 shows the configuration of each area T6 of the guidance information 1 to n.
There is an area T6b for detailed data with respect to a, and the area T6b for detailed data has areas for "operation item number", "guidance display condition", "scheduled start time of operation", and "guidance message".

【0097】処理S92では、ガイダンス表示する情報
を保存する保存領域をクリアし、処理S93へ処理を移
す。処理S93では、予定ガイダンス情報ファイルT6
から各ガイダンス情報を順次取出して処理S94へ処理
を移す。
In step S92, the storage area for storing the information to be displayed for guidance is cleared, and the process proceeds to step S93. In the processing S93, the schedule guidance information file T6
, Each guidance information is sequentially taken out, and the process proceeds to the process S94.

【0098】処理S94では、処理S93で取り出した
ガイダンス情報のガイダンス表示条件の条件判定と、現
在時刻と運転開始予定時刻とから予定5分前かの判定と
を行い、両方共に条件成立の場合には、処理S95へ、
そうでなければ処理S96へ処理を移す。
In step S94, the condition determination of the guidance display condition of the guidance information extracted in step S93 and the determination of whether the current time and the scheduled operation start time are 5 minutes before the scheduled time are performed. Goes to step S95.
Otherwise, the process moves to step S96.

【0099】処理S95では、処理S92でクリアされ
た保存領域の内容をチェックして、まだ予定5分前のガ
イダンス表示項目が検出されていないか、または既に検
出された表示項目よりも今回の表示項目の予定時刻の方
が早い場合には、今回検出した表示項目の運転開始予定
時刻とガイダンスメッセージを予定ガイダンス情報ファ
イルT6へ保存して、処理S96へ移る。
In step S95, the contents of the storage area cleared in step S92 are checked, and the guidance display item 5 minutes before the scheduled time has not been detected yet, or the current display item has been displayed more than the already detected display item. When the scheduled time of the item is earlier, the scheduled operation start time and the guidance message of the display item detected this time are stored in the scheduled guidance information file T6, and the process proceeds to step S96.

【0100】処理S96では、全てのガイダンス情報に
ついて処理S93から処理S95までを終了したか否か
を判断し、終了の場合には、処理S97へ移し、終了し
ていない場合には全てのガイダンス情報について終了す
るまで処理S93へ処理を移す。
In step S96, it is determined whether or not steps S93 to S95 have been completed for all pieces of guidance information. If the steps have been completed, the process proceeds to step S97. Until the process is completed, the process proceeds to the process S93.

【0101】処理S97では、処理S92でクリアされ
た保存領域の内容をチェックしてガイダンス表示項目が
有る場合には、現在時刻と保存された運転開始予定時刻
とから運転開始までの残り時間を算出して、ガイダンス
メッセージと算出した残り時間とをCRT表示装置C1
へガイダンス表示する。
In step S97, the contents of the storage area cleared in step S92 are checked, and if there is a guidance display item, the remaining time until the start of operation is calculated from the current time and the stored scheduled operation start time. Then, the guidance message and the calculated remaining time are displayed on the CRT display device C1.
To the guidance display.

【0102】さらに、残り時間が1分前以内の場合には
チャイム装置C4へチャイム音を出力する。その後、処
理S98へ処理を移す。処理S98では、一定時間遅延
後に処理S90へ再び処理を移す。
If the remaining time is less than one minute before, a chime sound is output to the chime device C4. After that, the processing moves to S98. In the process S98, the process is shifted to the process S90 again after a delay of a predetermined time.

【0103】このように第3実施の形態によれば、事前
に運転項目の内容と予定操作までの時間の情報が運転員
へ通知されると共に、1分前以内にはチャイム音での通
知もするため、余裕を持った運転監視及び運転操作を行
うことができる。
As described above, according to the third embodiment, the contents of the operation items and information on the time until the scheduled operation are notified to the operator in advance, and the chime sound is also notified within one minute before. Therefore, it is possible to perform operation monitoring and operation with a margin.

【0104】図12は、本発明の第4実施の形態を示す
プラント監視制御装置の構成図である。
FIG. 12 is a block diagram of a plant monitoring and control apparatus according to a fourth embodiment of the present invention.

【0105】図12において、従来技術を示す図19と
同一符号は同一部分または相当部分を示し、プラント監
視制御装置P2Dはプロセス入力手段S1とスケジュー
ル計算手段S2と実績収集手段S3と自動化運転手段S
4とプロセス表示手段S5と対話入力手段S6とに、新
たに時間計測手段S7と運転計画印字手段S10とを備
え、さらに、プロセスデータ設定ファイルT1とスケジ
ュールデータ設定ファイルT2と運転実績データ設定フ
ァイルT3に、新たに時間計測情報ファイルT4を備
え、CRT表示装置C1とタッチスクリーン装置C2と
キー入力装置C3とに、新たに印字装置C5とを接続し
ている。
In FIG. 12, the same reference numerals as those in FIG. 19 showing the prior art denote the same or corresponding parts, and the plant monitoring and control device P2D includes process input means S1, schedule calculation means S2, performance collection means S3, and automatic operation means S
4, a process display means S5, and an interactive input means S6, a time measuring means S7 and an operation plan printing means S10 are newly provided, and a process data setting file T1, a schedule data setting file T2, and an operation result data setting file T3 are further provided. A time measurement information file T4 is newly provided, and a printing device C5 is newly connected to the CRT display device C1, the touch screen device C2, and the key input device C3.

【0106】ここで、プロセス入力手段S1は、一定周
期毎にプラントP1から各種プロセスデータを入力し
て、プロセスデータ設定ファイルT1に設定する。対話
入力手段S6は、タッチスクリーン装置C2やキー入力
装置C3を介して対話画面にて運転員からの運転計画の
計算要求を受け、スケジュール計算手段S2へ運転完了
要求時刻を通知する一方、表示画面にてプラント運転終
了時などに運転員からの時間計測情報ファイルT4の内
容の更新要求を受け、時間計測手段S7へ通知し、運転
終了時などに運転員からの印字要求を受け、運転計画印
字手段S10へ印字要求通知を行う。
Here, the process input means S1 inputs various process data from the plant P1 at regular intervals and sets them in the process data setting file T1. The dialogue input means S6 receives an operation plan calculation request from the operator on the dialogue screen via the touch screen device C2 or the key input device C3, and notifies the schedule calculation means S2 of the operation completion request time, while displaying the display screen. Receives an update request of the contents of the time measurement information file T4 from the operator at the end of plant operation, notifies the time measurement means S7, receives a print request from the operator at the end of operation, and prints the operation plan. The print request is notified to the means S10.

【0107】スケジュール計算手段S2は、プロセスデ
ータ設定ファイルT1のプロセスデータにより現在のプ
ラント状態を判断し、時間計測情報ファイルT4内に設
定されている前回のプラント運転までの各運転項目の平
均運転時間を参照して、通知された運転完了要求時刻を
基点としたプラントの運転計画を計算し、スケジュール
データ設定ファイルT2に設定する。また、運転計画の
計算終了時に運転開始予定時刻と運転開始項目番号とを
運転計画印字手段S10へ通知する。
The schedule calculation means S2 determines the current plant state based on the process data in the process data setting file T1, and calculates the average operation time of each operation item until the last plant operation set in the time measurement information file T4. , A plant operation plan is calculated based on the notified operation completion request time, and is set in the schedule data setting file T2. At the end of the calculation of the operation plan, the scheduled operation start time and the operation start item number are notified to the operation plan printing means S10.

【0108】プロセス表示手段S5は、スケジュールデ
ータ設定ファイルT2の運転計画データである各運転予
定時刻などを画面形式にてCRT表示装置C1へ表示す
る。
The process display means S5 displays the scheduled operation times as the operation plan data of the schedule data setting file T2 on the CRT display device C1 in a screen format.

【0109】自動化運転手段S4は、プロセスデータ設
定ファイルT1のプロセスデータとスケジュールデータ
設定ファイルT2の制御パラメータとにより、プラント
への制御信号を出力してプラントの自動化運転を行う。
The automatic operation means S4 outputs a control signal to the plant based on the process data of the process data setting file T1 and the control parameters of the schedule data setting file T2, and performs the automatic operation of the plant.

【0110】実績収集手段S3は、プラント運転の進行
に伴って周期的にプロセスデータ設定ファイルT1のプ
ロセスデータより各運転計画の実績時刻の検出とタービ
ン回転数や発電機出力などのデータを収集して運転実績
データ設定ファイルT3へ設定する。
The performance collection means S3 periodically detects the performance time of each operation plan and collects data such as the turbine speed and the generator output from the process data in the process data setting file T1 as the plant operation proceeds. To the operation result data setting file T3.

【0111】プロセス表示手段S5は、運転実績データ
設定ファイルT3のデータである各運転実績時刻とター
ビン回転数や発電機出力などの曲線表示データを画面形
式にてCRT表示装置C1へ表示し、周期的に更新す
る。
The process display means S5 displays in the CRT display device C1 the actual operation time and the curve display data such as the turbine speed and the generator output, which are the data of the operation result data setting file T3, in a screen format. Update.

【0112】時間計測手段S7は、自動化運転手段S4
によるプラント運転の進行に伴って周期的に、プロセス
データ設定ファイルT1の現在プロセスデータを入力し
て時間計測情報ファイルT4内の各運転項目の時間計測
開始/終了条件の判定を行うことにより、開始条件成立
から終了条件成立までの各運転項目の運転時間を計測し
て、その運転時間と運転項目の開始時刻及び終了時刻と
を時間計測情報ファイルT4へ設定する。また、対話入
力手段S6からの時間計測情報ファイルT4の更新要求
通知により時間計測した全運転項目について、前回まで
の平均運転時間との平均時間を算出し新たな平均運転時
間として時間計測情報ファイルT4へ設定する。
The time measuring means S7 includes an automated driving means S4
By periodically inputting the current process data of the process data setting file T1 and determining the time measurement start / end conditions of each operation item in the time measurement information file T4 as the plant operation progresses. The operation time of each operation item from when the condition is satisfied to when the end condition is satisfied is measured, and the operation time and the start time and end time of the operation item are set in the time measurement information file T4. Further, for all the operation items whose time has been measured by the update request notification of the time measurement information file T4 from the interactive input means S6, the average time with the average operation time up to the previous time is calculated, and the time measurement information file T4 is calculated as a new average operation time. Set to

【0113】運転計画印字手段S10は、スケジュール
計算手段S2からの運転計画終了通知に対して、時間計
測情報ファイルT4の各運転項目の平均運転時間に基づ
き各運転項目名称・運転開始/終了の予定時刻・運転予
定時刻とを印字装置C5へ印字出力する。また、対話入
力手段S6からの印字要求通知に対して、印字内容と共
に、時間計測情報ファイルT4の各運転開始/終了の実
績時刻・運転実績時間と運転予定時間との時間差を追加
して印字装置C5へ印字出力する。
The operation plan printing means S10 responds to the operation plan end notification from the schedule calculation means S2 based on the average operation time of each operation item in the time measurement information file T4, and each operation item name / operation start / end schedule. The time and scheduled operation time are printed out to the printing device C5. In addition to the print request notification from the interactive input means S6, the printing device adds the actual time of each operation start / end in the time measurement information file T4 and the time difference between the actual operation time and the scheduled operation time together with the print contents. Print out to C5.

【0114】以上の構成により、対話画面にて運転員よ
り運転計画の計算要求が行われた場合、対話入力手段S
6は、運転員からの運転計画の計算要求を受け、スケジ
ュール計算手段S2へ運転完了要求時刻を通知する。
With the above configuration, when the operator requests the operation plan calculation on the dialogue screen, the dialogue input means S
6 receives the operation plan calculation request from the operator and notifies the schedule calculation means S2 of the operation completion request time.

【0115】スケジュール計算手段S2は、対話入力手
段S6からの通知により、プロセスデータ設定ファイル
T1のプロセスデータにより現在のプラント状態を判断
し、時間計測情報ファイルT4内に設定されている前回
のプラント運転までの各運転項目の平均運転時間を参照
して、通知された運転完了要求時刻を基点としたプラン
トの運転計画を計算し、スケジュールデータ設定ファイ
ルT2に設定すると共に、運転計画印字手段S10へ運
転開始予定時刻と運転開始項目番号を通知する。
The schedule calculating means S2 determines the current plant state based on the process data in the process data setting file T1 according to the notification from the interactive input means S6, and determines the last plant operation set in the time measurement information file T4. With reference to the average operation time of each operation item up to, the operation plan of the plant based on the notified operation completion request time is calculated, set in the schedule data setting file T2, and operated to the operation plan printing means S10. Notify the scheduled start time and operation start item number.

【0116】運転計画印字手段S10では、スケジュー
ル計算手段S2からの通知により、通知された運転開始
項目番号より時間計測情報ファイルT4を検索して運転
開始から運転終了までの運転項目名称と平均運転時間を
取出すと共に、取出した各運転項目の運転開始及び終了
の予定時刻を通知された運転開始予定時刻/運転開始項
目番号と取出した各平均運転時間とから算出して、印字
装置C5へ運転項目名称欄及び運転予定欄の項目である
運転項目名称・運転開始予定時刻・運転終了予定時刻・
運転予定時間(平均運転時間)を印字することにより、
運転計画の詳細を運転員へ提供する。
The operation plan printing means S10 searches the time measurement information file T4 based on the notified operation start item number based on the notification from the schedule calculation means S2, and executes the operation item name and the average operation time from the operation start to the operation end. At the same time, the scheduled operation start and end times of the extracted operation items are calculated from the notified operation start time / operation start item number and the average operation times extracted, and the operation item name is sent to the printing device C5. Item, operation start time, operation end time,
By printing the scheduled operation time (average operation time),
Provide details of the operation plan to operators.

【0117】さらに、プラント運転終了時などに、画面
にて運転員から印字要求が行われた場合、次のように作
用する。
Further, when a printing request is made by the operator on the screen at the end of plant operation or the like, the following operation is performed.

【0118】対話入力手段S6は、図13に示す対話画
面54エリアの印字要求54aを指定すると運転員から
の印字要求を受け、運転計画印字手段S10へ印字要求
を通知する。
When the print request 54a in the dialogue screen 54 area shown in FIG. 13 is designated, the dialogue input means S6 receives a print request from the operator and notifies the operation plan printing means S10 of the print request.

【0119】これにより、運転計画印字手段S10で
は、時間計測情報ファイルT4内のそれらの運転開始/
終了の実績時刻と運転実績時間(今回運転時間)を検索
し、運転計画終了時の運転予定時間と運転実績時間(今
回運転時間)との時間差を算出して、図14に示す印字
出力例55のように、運転計画終了時の運転項目名称欄
55a及び運転予定欄55bの情報と共に運転実績欄5
5c及び運転時間差欄55dの内容について印字装置C
5へ印字出力する。この結果、各運転項目毎の運転計画
と運転実績との差異が運転員へ通知される。
As a result, the operation plan printing means S10 starts / stops the operations in the time measurement information file T4.
The actual end time and the actual operation time (current operation time) are searched, and the time difference between the scheduled operation time at the end of the operation plan and the actual operation time (current operation time) is calculated, and a print output example 55 shown in FIG. And the operation result column 5 together with the information in the operation item name column 55a and the operation schedule column 55b at the end of the operation plan.
5c and the contents of the operation time difference column 55d
Print out to 5. As a result, the difference between the operation plan and the operation result for each operation item is notified to the operator.

【0120】このように第4実施の形態によれば、運転
計画にどのような運転項目があるのかが明確になると共
に、運転完了時にはどの運転項目の要因により運転計画
通りに運転できなかったかを分析することが容易とな
り、分析結果を次回のプラント運転に活かすことができ
るため、運転計画通りに運転することが容易となる。
As described above, according to the fourth embodiment, it becomes clear what operation items are included in the operation plan, and when the operation is completed, it is determined which operation item caused the operation to fail according to the operation plan. The analysis becomes easy, and the analysis result can be utilized for the next plant operation, so that the operation can be easily performed according to the operation plan.

【0121】図15は、本発明の第5実施の形態を示す
プラント監視制御装置の構成図である。
FIG. 15 is a block diagram of a plant monitoring and control apparatus according to a fifth embodiment of the present invention.

【0122】図15において、従来例を示す図19と同
一符号は同一符号または相当部分を示し、プラント監視
制御装置P2Eはプロセス入力手段S1とスケジュール
計算手段S2と実績収集手段S3と自動化運転手段S4
とプロセス表示手段S5と対話入力手段S6とに、新た
に時間計測手段S7を備え、プロセスデータ設定ファイ
ルT1とスケジュールデータ設定ファイルT2と運転実
績データ設定ファイルT3とに、新たに時間計測情報フ
ァイルT4とスケジュール選択データ設定ファイルT7
を備え、さらに、CRT表示装置C1とタッチスクリー
ン装置C2とキー入力装置C3とを接続している。
In FIG. 15, the same reference numerals as those in FIG. 19 showing the conventional example denote the same or corresponding parts, and the plant monitoring and control device P2E includes process input means S1, schedule calculation means S2, performance collection means S3, and automatic operation means S4.
, A process display means S5, a dialogue input means S6, and a new time measuring means S7, and a process data setting file T1, a schedule data setting file T2, an operation result data setting file T3, and a new time measurement information file T4. And schedule selection data setting file T7
And a CRT display device C1, a touch screen device C2, and a key input device C3 are connected.

【0123】プロセス入力手段S1は、一定周期毎にプ
ラントP1から各種プロセスデータを入力して、プロセ
スデータ設定ファイルT1に設定する。対話入力手段S
6は、タッチスクリーン装置C2やキー入力装置C3を
介して対話画面にて運転員からの運転計画の計算要求を
受け、スケジュール計算手段S2へ運転完了要求時刻を
通知する。
The process input means S1 inputs various process data from the plant P1 at regular intervals and sets them in the process data setting file T1. Dialogue input means S
6 receives an operation plan calculation request from the operator on the interactive screen via the touch screen device C2 or the key input device C3, and notifies the schedule calculation means S2 of the operation completion request time.

【0124】さらに、運転員からタービンの起動モード
(低速/中速/高速)の選択要求がある場合には、選択
された起動モードと共に、モード選択要求をスケジュー
ル計算手段S2へ通知する一方、表示画面にてプラント
運転終了時などに運転員からの時間計測情報ファイルT
4の更新要求を受け、時間計測手段S7へ通知する。
Further, when there is a request from the operator to select the start mode (low speed / medium speed / high speed) of the turbine, the mode selection request is notified to the schedule calculation means S2 together with the selected start mode, and displayed. Time measurement information file T from the operator at the end of plant operation on the screen
In response to the update request of No. 4, it notifies the time measuring means S7.

【0125】スケジュール計算手段S2は、プロセスデ
ータ設定ファイルT1のプロセスデータにより現在のプ
ラント状態を判断し、時間計測情報ファイルT4内に設
定されている前回のプラント運転までの各運転項目の平
均運転時間を参照して、通知された運転完了要求時刻を
基点としたプラントの運転計画を計算し、スケジュール
データ設定ファイルT2と検出された起動モードに対応
するスケジュール選択データ設定ファイルT7とに設定
する。さらに、この運転計画で検出したタービンの起動
モード(低速モード/中速モード/高速モード)より低
い(低速モード<中速モード<高速モード)の場合での
運転計画も追加計算し、それぞれの起動モードに対応す
るスケジュール選択データ設定ファイルT7に設定す
る。
The schedule calculation means S2 determines the current plant state based on the process data in the process data setting file T1, and calculates the average operation time of each operation item until the last plant operation set in the time measurement information file T4. , A plant operation plan is calculated based on the notified operation completion request time, and is set in the schedule data setting file T2 and the schedule selection data setting file T7 corresponding to the detected start mode. Further, an operation plan in the case of a lower (lower-speed mode / medium-speed mode / high-speed mode) (low-speed mode <medium-speed mode <high-speed mode) than the start-up mode of the turbine (low-speed mode / medium-speed mode / high-speed mode) detected in this operation plan is additionally calculated. It is set in the schedule selection data setting file T7 corresponding to the mode.

【0126】また、対話入力手段S6からのモード選択
要求通知により、通知された起動モードに対応するデー
タをスケジュールデータ設定ファイルT2へ設定する。
In response to the mode selection request notification from the interactive input means S6, data corresponding to the notified start mode is set in the schedule data setting file T2.

【0127】プロセス表示手段S5は、スケジュール選
択データ設定ファイルT7の運転計画データを画面形式
にてCRT表示装置C1へ表示する。
The process display means S5 displays the operation plan data of the schedule selection data setting file T7 in a screen format on the CRT display C1.

【0128】自動化運転手段S4は、プロセスデータ設
定ファイルT1のプロセスデータとスケジュールデータ
設定ファイルT2の制御パラメータとにより、プラント
への制御信号を出力してプラントの自動化運転を行う。
The automatic operation means S4 outputs a control signal to the plant based on the process data in the process data setting file T1 and the control parameters in the schedule data setting file T2, and performs the automatic operation of the plant.

【0129】実績収集手段S3は、プラント運転の進行
に伴って周期的にプロセスデータ設定ファイルT1のプ
ロセスデータより各運転計画の実績時刻の検出とタービ
ン回転数や発電機出力などのデータを収集して運転実績
データ設定ファイルT3へ設定する。
The performance collecting means S3 periodically detects the performance time of each operation plan and collects data such as turbine speed and generator output from the process data in the process data setting file T1 as the plant operation proceeds. To the operation result data setting file T3.

【0130】また、プロセス表示手段S5は、スケジュ
ールデータ設定ファイルT2の運転計画データと運転実
績データ設定ファイルT3のデータである各運転実績時
刻とタービン回転数や発電機出力などの曲線表示データ
とを画面形式にてCRT表示装置C1へ表示し、周期的
に更新する。
The process display means S5 displays the operation plan data in the schedule data setting file T2 and the actual operation times, which are the data in the operation result data setting file T3, and the curve display data such as the turbine speed and the generator output. The information is displayed on the CRT display device C1 in a screen format, and is periodically updated.

【0131】時間計測手段S7は、自動化運転手段S4
によるプラント運転の進行に伴って周期的に、プロセス
データ設定ファイルT1から現在のプロセスデータを入
力して時間計測情報ファイルT4内の各運転項目の時間
計測開始/終了条件の判定を行うことにより、開始条件
成立から終了条件成立までの各運転項目の運転時間を計
測して、その運転時間と運転項目の開始時刻及び終了時
刻とを時間計測情報ファイルT4へ設定する。
The time measuring means S7 is composed of an automated driving means S4
By periodically inputting the current process data from the process data setting file T1 and determining the time measurement start / end conditions of each operation item in the time measurement information file T4 as the plant operation proceeds, The operation time of each operation item from the start condition establishment to the end condition establishment is measured, and the operation time and the start time and end time of the operation item are set in the time measurement information file T4.

【0132】また、対話入力手段S6からの時間計測情
報ファイルT4の更新要求通知により時間計測した全運
転項目について、前回までの平均運転時間との平均時間
を算出し新たな平均運転時間として時間計測情報ファイ
ルT4へ設定する。
Further, for all the operation items whose time has been measured by the update request notification of the time measurement information file T4 from the interactive input means S6, the average time with the average operation time up to the previous time is calculated, and the time measurement is performed as a new average operation time. Set in the information file T4.

【0133】以上の構成により、図18に示す対話画面
56により運転員より運転計画の計算要求が行われた場
合、対話入力手段S6は、運転員からの運転計画の計算
要求を受け、スケジュール計算手段S2へ運転完了要求
時刻を通知する。
With the above configuration, when the operator requests the calculation of the operation plan on the dialogue screen 56 shown in FIG. 18, the dialogue input means S6 receives the request of the operation plan calculation from the operator and receives the schedule calculation. The operation completion request time is notified to the means S2.

【0134】スケジュール計算手段S2は、対話入力手
段S6からの通知により、プロセスデータ設定ファイル
T1のプロセスデータにより現在のプラント状態を判断
し、時間計測情報ファイルT4内に設定されている前回
のプラント運転までの各運転項目の平均運転時間を参照
して、通知された運転完了要求時刻を基点としたプラン
トの運転計画を計算し、スケジュールデータ設定ファイ
ルT2と検出された起動モードに対応するスケジュール
選択データ設定ファイルT7とに設定する。
The schedule calculating means S2 determines the current plant state based on the process data in the process data setting file T1 according to the notification from the interactive input means S6, and determines the last plant operation set in the time measurement information file T4. With reference to the average operation time of each operation item up to, a plant operation plan based on the notified operation completion request time is calculated, and the schedule selection data corresponding to the schedule data setting file T2 and the detected start mode is calculated. Set in the setting file T7.

【0135】図17は、スケジュール選択データ設定フ
ァイルT7の構成を示し、スケジュール選択データ設定
ファイルT7は、低速モード情報と中速モード情報と高
速モード情報の各エリアT7aがあり、例えば、低速モ
ード情報内に詳細情報エリアT7bがあり、例えば、制
御パラメータのエリアにはタービン昇速率のエリアT7
cとタービンヒートソーク時間のエリアT7dとが設け
られている。
FIG. 17 shows the structure of the schedule selection data setting file T7. The schedule selection data setting file T7 has low-speed mode information, medium-speed mode information, and high-speed mode information areas T7a. There is a detailed information area T7b inside the area.
c and a turbine heat soak time area T7d.

【0136】次に、この運転計画で検出した運転モード
であるタービンの起動モード(低速モード/中速モード
/高速モード)より低い起動モード(低速モード<中速
モード<高速モード)の場合での運転計画も追加計算
し、それぞれの起動モードに対応するスケジュール選択
データ設定ファイルT7に設定する。
Next, in the case of a start mode (low-speed mode <medium-speed mode <high-speed mode) lower than the turbine start mode (low-speed mode / medium-speed mode / high-speed mode) which is the operation mode detected in this operation plan. The operation plan is additionally calculated and set in the schedule selection data setting file T7 corresponding to each start mode.

【0137】プロセス表示手段S5では、CRT表示装
置C1へスケジュール計算手段S2にて設定されたスケ
ジュール選択データ設定ファイルT7の各起動モードの
運転計画データに対応する起動モードの欄に表示する。
ここで、図18の対話画面56にはスケジュールデータ
設定ファイルT2に設定されている運転計画データのみ
を表示する。その後、運転員から図18の予定欄以外の
起動モードが選択要求された場合、対話入力手段S6
は、図18の「低速モード選択」56a「中速モード選
択」56b「高速モード選択」56cのいずれかの起動
モード(低速/中速/高速)の選択要求を受け、選択さ
れた起動モードと共に、モード選択要求をスケジュール
データ設定ファイルT2へ通知する。
In the process display means S5, a display is made on the CRT display device C1 in the start mode column corresponding to the operation plan data of each start mode in the schedule selection data setting file T7 set by the schedule calculation means S2.
Here, only the operation plan data set in the schedule data setting file T2 is displayed on the interactive screen 56 of FIG. Thereafter, when the operator requests the start mode other than the schedule column in FIG. 18 to be selected, the interactive input means S6
Receives a request to select one of the start modes (low speed / medium speed / high speed) of “select low speed mode” 56a “select medium speed mode” 56b “select high speed mode” 56c in FIG. , A mode selection request is notified to the schedule data setting file T2.

【0138】スケジュール計算手段S2では、対話入力
手段S6からのモード選択要求通知により、通知された
起動モードに対応するスケジュール選択データ設定ファ
イルT7内の情報領域の運転計画データをスケジュール
データ設定ファイルT2へ設定する。
In the schedule calculation means S2, according to the mode selection request notification from the interactive input means S6, the operation plan data in the information area in the schedule selection data setting file T7 corresponding to the notified start mode is transferred to the schedule data setting file T2. Set.

【0139】このとき、図4のような運転実績表示画面
の予定欄にはプロセス表示手段S5により、運転員が選
択してスケジュールデータ設定ファイルT2に設定され
た運転計画データが表示される。また、以後のプラント
運転は、自動化運転手段S4にて、運転員が選択してス
ケジュールデータ設定ファイルT2に設定された運転計
画データに基づき自動化運転が行われる。
At this time, the operation plan data set by the operator and set in the schedule data setting file T2 is displayed in the schedule column of the operation result display screen as shown in FIG. 4 by the process display means S5. Further, in the subsequent plant operation, the automated operation is performed by the automated operation means S4 based on the operation plan data selected by the operator and set in the schedule data setting file T2.

【0140】次に、スケジュール計算手段S2の処理に
ついて、図16を用いて詳細に説明する。
Next, the processing of the schedule calculation means S2 will be described in detail with reference to FIG.

【0141】まず、スケジュール計算手段S2は、処理
S20にて対話入力手段S6からの通知内容を判断し
て、運転計画計算要求であれば処理S21へ、起動モー
ドの選択要求であれば処理S24へ処理を移す。処理S
21では、まず、スケジュール選択データ設定ファイル
T7を全てクリアする。また、プロセスデータ設定ファ
イルT1のプロセスデータより現在のプラント状態(起
動モードなど)を判断し、時間計測情報ファイルT4内
に設定されている前回のプラント運転における各運転項
目の平均運転時間を参照して、通知された運転完了要求
時刻としたプラントの運転計画を計算し、スケジュール
データ設定ファイルT2と検出された起動モードに対応
するスケジュール選択データ設定ファイルT7とに設定
して、処理S22へ移る。
First, in step S20, the schedule calculating means S2 determines the contents of the notification from the interactive input means S6. If the request is an operation plan calculation request, the process proceeds to step S21. If the request is a start mode selection request, the process proceeds to step S24. Transfer processing. Processing S
At 21, all schedule selection data setting files T7 are cleared. Further, the current plant state (eg, start mode) is determined from the process data in the process data setting file T1, and the average operation time of each operation item in the previous plant operation set in the time measurement information file T4 is referred to. Then, the operation plan of the plant at the notified operation completion request time is calculated, set in the schedule data setting file T2 and the schedule selection data setting file T7 corresponding to the detected start mode, and the process proceeds to step S22.

【0142】処理S23では、スケジュール計算手段S
2で検出した起動モードが高速モード以上であれば中速
モードでの運転計画の計算処理を行い、その結果を中速
モードのスケジュール選択データ設定ファイルT7へ設
定して、処理を終了する。
At step S23, the schedule calculation means S
If the startup mode detected in Step 2 is higher than the high-speed mode, calculation processing of the operation plan in the medium-speed mode is performed, the result is set in the schedule selection data setting file T7 in the medium-speed mode, and the processing is terminated.

【0143】処理S24では、対話入力手段S6より通
知された起動モードに対応するスケジュール選択データ
設定ファイルT7の運転計画データを取り出してスケジ
ュールデータ設定ファイルT2に設定して、処理を終了
する。
In the process S24, the operation plan data of the schedule selection data setting file T7 corresponding to the start mode notified from the interactive input means S6 is taken out, set in the schedule data setting file T2, and the process is terminated.

【0144】このように第5実施の形態によれば、いく
つかの運転モードによる運転計画を運転員へ提供し、運
転員の判断により選択できるため、タービン等の設備の
寿命の延命を考慮した自動のプラント運転も可能とな
る。
As described above, according to the fifth embodiment, the operation plan in several operation modes is provided to the operator, and the operation plan can be selected according to the judgment of the operator. Therefore, the life extension of the equipment such as the turbine is considered. Automatic plant operation is also possible.

【0145】[0145]

【発明の効果】以上説明したように請求項1の発明によ
れば、各運転項目について計測された各運転時間に基づ
き各運転項目の平均運転時間を算出し、これに基づき新
たな運転計画を計算するので、得られる運転計画がプラ
ントの状況に応じたものとなり、運転計画通りに実際の
プラントの運転ができる。従って、従来のように運転員
の個人差やプラントの特性による実情に沿わない運転計
画によって実際の運転がされ運転計画通りに終了しない
という不都合が解消でき、効率的な運転ができる。
As described above, according to the first aspect of the present invention, an average operation time of each operation item is calculated based on each operation time measured for each operation item, and a new operation plan is created based on the average operation time. Since the calculation is performed, the obtained operation plan is in accordance with the condition of the plant, and the actual operation of the plant can be performed according to the operation plan. Therefore, it is possible to eliminate the inconvenience that the actual operation is not performed according to the operation plan that does not conform to the actual situation due to the individual differences of the operators or the characteristics of the plant and that the operation is not completed according to the operation plan.

【0146】また、請求項2の発明によれば、各運転項
目について前回までの平均運転時間に加え、今回の運転
実績を加味して新たな平均運転時間を算出し、各運転項
目の新たな平均運転時間を用いて指定された運転完了要
求時刻に運転が完了するように運転計画を計算するの
で、実情に沿った的確な運転計画によって実際の運転が
でき、運転完了時刻が予定より延びたり、早まったりす
る不都合が生じない。
According to the second aspect of the present invention, a new average operation time is calculated for each operation item in consideration of the current operation results in addition to the average operation time up to the previous operation, and a new average operation time for each operation item is calculated. Since the operation plan is calculated so that the operation is completed at the specified operation completion request time using the average operation time, the actual operation can be performed according to the accurate operation plan according to the actual situation, and the operation completion time may be longer than expected Inconvenience of hastening does not occur.

【0147】また、請求項3の発明によれば、複数の運
転パターンから状況に応じて選択した適切な運転パター
ンによって運転計画を計算するので、実際の運転と運転
計画とに差異がなく、効率的な運転ができる。
According to the third aspect of the present invention, since the operation plan is calculated based on a plurality of operation patterns and an appropriate operation pattern selected according to the situation, there is no difference between the actual operation and the operation plan, and the efficiency is improved. Driving is possible.

【0148】また、請求項4の発明によれば、各運転項
目の運転予定時刻の直前にガイダンス情報を外部へ知ら
せるので、運転員は、次の運転項目を事前に知り、余裕
をもって作業をすることができ、運転員の作業負担を大
幅に軽減することができる。
According to the fourth aspect of the present invention, since the guidance information is notified to the outside immediately before the scheduled operation time of each operation item, the operator knows the next operation item in advance and works with a margin. As a result, the workload of the operator can be greatly reduced.

【0149】また、請求項5の発明によれば、必要な各
種運転計画や運転実績を印字して、運転員へ提供するの
で、印字された情報を保存して前回と今回との比較が容
易にでき、次回の運転に活用することができる。
Further, according to the fifth aspect of the present invention, necessary various operation plans and operation results are printed and provided to the operator, so that the printed information is saved so that the previous time and the current time can be easily compared. It can be used for the next driving.

【0150】また、請求項6の発明によれば、運転項目
に複数の運転モードがある場合に、運転計画に応じて適
切な運転モードを選択して運転をするので、プラントの
設備の寿命等を考慮したプラントの運転ができる。
According to the invention of claim 6, when there are a plurality of operation modes in the operation item, the operation is performed by selecting an appropriate operation mode according to the operation plan, so that the life of the equipment of the plant or the like can be improved. The plant can be operated in consideration of the above.

【図面の簡単な説明】[Brief description of the drawings]

【図1】本発明の第1実施の形態を示すプラント監視制
御装置の構成図である。
FIG. 1 is a configuration diagram of a plant monitoring and control device according to a first embodiment of the present invention.

【図2】本発明の第1実施の形態を示す対話画面例であ
る。
FIG. 2 is an example of an interactive screen showing the first embodiment of the present invention.

【図3】本発明の第1実施の形態を示す時間計測情報フ
ァイルの構成図である。
FIG. 3 is a configuration diagram of a time measurement information file according to the first embodiment of the present invention.

【図4】本発明の第1実施の形態を示す実績表示画面例
である。
FIG. 4 is an example of a performance display screen showing the first embodiment of the present invention.

【図5】本発明の第1実施の形態を示す時間計測手段の
処理の流れ図である。
FIG. 5 is a flowchart of a process of a time measuring unit according to the first embodiment of the present invention.

【図6】本発明の第2実施の形態を示すプラント監視制
御装置の構成図である。
FIG. 6 is a configuration diagram of a plant monitoring and control device according to a second embodiment of the present invention.

【図7】本発明の第2実施の形態を示す対話画面例であ
る。
FIG. 7 is an example of an interactive screen showing a second embodiment of the present invention.

【図8】本発明の第2実施の形態を示す運転パターン情
報ファイルの構成図である。
FIG. 8 is a configuration diagram of an operation pattern information file showing a second embodiment of the present invention.

【図9】本発明の第3実施の形態を示すプラント監視制
御装置の構成図である。
FIG. 9 is a configuration diagram of a plant monitoring and control device according to a third embodiment of the present invention.

【図10】本発明の第3実施の形態を示す予定ガイダン
ス表示手段の処理の流れ図である。
FIG. 10 is a flowchart of a process performed by a scheduled guidance display unit according to the third embodiment of the present invention.

【図11】本発明の第3実施の形態を示す予定ガイダン
ス情報ファイルの構成図である。
FIG. 11 is a configuration diagram of a schedule guidance information file according to a third embodiment of the present invention.

【図12】本発明の第4実施の形態を示すプラント監視
制御装置の構成図である。
FIG. 12 is a configuration diagram of a plant monitoring and control device according to a fourth embodiment of the present invention.

【図13】本発明の第4実施の形態を示す実績表示画面
例である。
FIG. 13 is a result display screen example showing the fourth embodiment of the present invention.

【図14】本発明の第4実施の形態を示す運転計画印字
例である。
FIG. 14 is an example of operation plan printing showing the fourth embodiment of the present invention.

【図15】本発明の第5実施の形態を示すプラント監視
制御装置の構成図である。
FIG. 15 is a configuration diagram of a plant monitoring and control device according to a fifth embodiment of the present invention.

【図16】本発明の第5実施の形態を示すスケジュール
計算手段の処理の流れ図である。
FIG. 16 is a flowchart of a process of a schedule calculating means according to the fifth embodiment of the present invention.

【図17】本発明の第5実施の形態を示すスケジュール
選択データ設定ファイルの構成図である。
FIG. 17 is a configuration diagram of a schedule selection data setting file according to a fifth embodiment of the present invention.

【図18】本発明の第5実施の形態を示す対話画面例で
ある。
FIG. 18 is an example of a dialogue screen showing a fifth embodiment of the present invention.

【図19】従来のプラント監視制御装置の構成図であ
る。
FIG. 19 is a configuration diagram of a conventional plant monitoring and control device.

【図20】従来のプラント監視制御装置での実績表示画
面例である。
FIG. 20 is an example of a result display screen in a conventional plant monitoring and control device.

【符号の説明】[Explanation of symbols]

P2 プラント監視制御装置 C1 CRT表示装置 C2 タッチスクリーン装置 C3 キー入力装置 C4 チャイム装置 C5 印字装置 S1 プロセス入力手段 S2 スケジュール計算手段 S3 実績収集手段 S4 自動化運転手段 S5 プロセス表示手段 S6 対話入力手段 S7 時間計測手段 S8 運転パターン登録手段 S9 予定ガイダンス表示手段 S10 運転計画印字手段 T1 プロセスデータ設定ファイル T2 スケジュールデータ設定ファイル T3 運転実績データ設定ファイル T4 時間計測情報ファイル T5 運転パターン情報ファイル T6 予定ガイダンス情報ファイル T7 スケジュール選択データ設定ファイル P2 Plant monitoring and control device C1 CRT display device C2 Touch screen device C3 Key input device C4 Chime device C5 Printing device S1 Process input means S2 Schedule calculation means S3 Result collection means S4 Automated operation means S5 Process display means S6 Interactive input means S7 Time measurement Means S8 Operation pattern registration means S9 Schedule guidance display means S10 Operation plan printing means T1 Process data setting file T2 Schedule data setting file T3 Operation result data setting file T4 Time measurement information file T5 Operation pattern information file T6 Schedule guidance information file T7 Schedule selection Data setting file

Claims (6)

【特許請求の範囲】[Claims] 【請求項1】 プラントから各種情報を入力してプラン
トの運転計画の計算を実行して得られる運転計画に従っ
てプラントを自動化運転するための監視と制御をするプ
ラント監視制御装置において、 各運転項目について運転時間の計測を実行し、計測した
各運転時間に基づき各運転項目について平均運転時間を
算出して時間計測情報ファイルへ保存する時間計測手段
と、 前記時間計測情報ファイルに保存される前記各運転項目
の平均運転時間に基づきプラントの運転計画を計算する
スケジュール計算手段とを備えることを特徴とするプラ
ント監視制御装置。
1. A plant monitoring and control device for monitoring and controlling an automatic operation of a plant according to an operation plan obtained by inputting various information from the plant and calculating a plant operation plan. Time measurement means for measuring the operation time, calculating an average operation time for each operation item based on the measured operation time, and storing the average operation time in a time measurement information file; and each of the operations stored in the time measurement information file A plant monitoring and control device, comprising: schedule calculation means for calculating a plant operation plan based on an average operation time of an item.
【請求項2】 周期毎にプラントから各種プロセスデー
タを入力して、プロセスデータ設定ファイルに設定する
プロセス入力手段と、 プラント運転の進行に伴って前記プロセスデータ設定フ
ァイルのプロセスデータより各運転項目の実績時刻の検
出と必要な機器データを収集して運転実績データ設定フ
ァイルへ設定する実績収集手段と、 前記プロセスデータ設定ファイルから現在のプロセスデ
ータを入力して時間計測情報ファイルに記憶される各運
転項目の計測開始/終了条件に基づいて判定を行い、計
測開始条件成立から計測終了条件成立までの各運転項目
の運転時間を計測して、各運転項目毎に計測した今回の
運転時間と計測開始時刻及び計測終了時刻とを前記時間
計測情報ファイルへ保存すると共に、時間計測した全運
転項目について、前回までの平均運転時間に今回の実績
を加えて、平均運転時間を算出して新たな平均運転時間
として前記時間計測情報ファイルへ保存する時間計測手
段と、 前記プロセスデータ設定ファイルのプロセスデータより
現在のプラント状態を判断し、前記時間計測情報ファイ
ル内に設定されている前回のプラント運転までの各運転
項目の平均運転時間を参照して、プラントの運転計画デ
ータを作成し、スケジュールデータ設定ファイルに設定
するスケジュール計算手段と、 前記プロセスデータ設定ファイルのプロセスデータと前
記スケジュールデータ設定ファイルに保存される制御パ
ラメータとにより、プラントへの制御信号を出力してプ
ラントの自動化運転を行う自動化運転手段とを備えるこ
とを特徴とするプラント監視制御装置。
2. Process input means for inputting various process data from a plant for each cycle and setting the process data in a process data setting file; and A result collection means for detecting the actual time and collecting necessary device data and setting the result in an operation result data setting file, and each operation stored in a time measurement information file by inputting current process data from the process data setting file Judgment is made based on the measurement start / end conditions of the items, the operation time of each operation item from the measurement start condition satisfaction to the measurement end condition satisfaction is measured, and the current operation time measured for each operation item and the measurement start The time and the measurement end time are stored in the time measurement information file, and all the operation items for which the time was measured are stored. A time measurement unit that calculates the average operation time by adding the present operation result to the average operation time up to the previous time and saves the average operation time as a new average operation time in the time measurement information file. Judgment of the plant state of, referring to the average operation time of each operation item up to the last plant operation set in the time measurement information file, to create plant operation plan data, schedule data setting file Schedule calculation means to be set, and automatic operation means for outputting a control signal to the plant and performing an automatic operation of the plant by using the process data of the process data setting file and the control parameters stored in the schedule data setting file. A plant monitoring and control device, comprising:
【請求項3】 スケージュール計算手段で作成したある
いは運転実績データである運転のスケジュールを表す複
数の運転パターンのデータを保存する運転パターン情報
ファイルに要求により取出された前記時間計測情報ファ
イルからのデータを新たな1つの運転パターンとして設
定する運転パターン登録手段を備えて、状況に応じて蓄
積した運転パターンによって前記運転計画を計算するこ
とを特徴とする請求項1または請求項2記載のプラント
監視制御装置。
3. The data from the time measurement information file generated by the schedule calculation means or taken out by a request to an operation pattern information file for storing data of a plurality of operation patterns representing operation schedules as operation result data. 3. The plant monitoring control according to claim 1, further comprising an operation pattern registration unit that sets the operation plan as a new operation pattern, and calculates the operation plan based on the operation pattern accumulated according to the situation. apparatus.
【請求項4】 各運転項目毎に運転予定時刻とガイダン
ス表示条件とを含む必要なガイダンス情報を保存する予
定ガイダンス情報ファイルと、 前記時間計測情報ファイルから各運転項目の平均時間を
取込み各運転予定時刻を算出して前記予定ガイダンス情
報ファイルへ保存すると共に、所定のガイダンス表示条
件の成立を判定し、ガイダンス表示条件が成立すると、
事前に予定ガイダンス情報を外部へ表示出力する予定ガ
イダンス表示手段とを備えることを特徴とする請求項1
または請求項2記載のプラント監視制御装置。
4. A schedule guidance information file for storing necessary guidance information including a scheduled operation time and guidance display conditions for each operation item, and an average time of each operation item from the time measurement information file. The time is calculated and stored in the scheduled guidance information file, and it is determined whether a predetermined guidance display condition is satisfied.
2. A schedule guidance display means for displaying and outputting schedule guidance information to the outside in advance.
Or the plant monitoring and control device according to claim 2.
【請求項5】 過去の実績の平均運転時間を参照して作
成された運転計画の各運転項目の運転予定時刻と今回の
運転実績の運転時刻を表示あるいは印字させる運転計画
印字表示手段を備えることを特徴とする請求項1または
請求項2記載のプラント監視制御装置。
5. An operation plan printing display means for displaying or printing the scheduled operation time of each operation item of the operation plan created with reference to the average operation time of the past results and the operation time of the current operation results. The plant monitoring and control device according to claim 1 or 2, wherein:
【請求項6】 運転計画に応じた複数の運転モードを設
定するスケジュール選択データ設定ファイルを備え、ス
ケジュール計算手段により計算された運転計画に応じて
前記スケジュール選択データ設定ファイルから運転モー
ドを選択して運転員へ知らせることを特徴とする請求項
1または請求項2記載のプラント監視制御装置。
6. A schedule selection data setting file for setting a plurality of operation modes according to an operation plan, wherein an operation mode is selected from the schedule selection data setting file according to the operation plan calculated by schedule calculation means. 3. The plant monitoring and control device according to claim 1, wherein the operator is notified.
JP6902697A 1997-03-07 1997-03-07 Plant supervisory and controlling device Pending JPH10254529A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP6902697A JPH10254529A (en) 1997-03-07 1997-03-07 Plant supervisory and controlling device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP6902697A JPH10254529A (en) 1997-03-07 1997-03-07 Plant supervisory and controlling device

Publications (1)

Publication Number Publication Date
JPH10254529A true JPH10254529A (en) 1998-09-25

Family

ID=13390671

Family Applications (1)

Application Number Title Priority Date Filing Date
JP6902697A Pending JPH10254529A (en) 1997-03-07 1997-03-07 Plant supervisory and controlling device

Country Status (1)

Country Link
JP (1) JPH10254529A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2003070286A (en) * 2001-08-22 2003-03-07 Keyence Corp Motor driver having character information display
JP2006518894A (en) * 2003-02-26 2006-08-17 エンベディッド・テクノロジーズ・コーポレイション・プロプライエタリー・リミテッド Process control system and method for configuring a process control system
JP2008293207A (en) * 2007-05-23 2008-12-04 Yanmar Co Ltd System, method, and program for managing inventory and ordering of maintenance part

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2003070286A (en) * 2001-08-22 2003-03-07 Keyence Corp Motor driver having character information display
JP2006518894A (en) * 2003-02-26 2006-08-17 エンベディッド・テクノロジーズ・コーポレイション・プロプライエタリー・リミテッド Process control system and method for configuring a process control system
JP2008293207A (en) * 2007-05-23 2008-12-04 Yanmar Co Ltd System, method, and program for managing inventory and ordering of maintenance part

Similar Documents

Publication Publication Date Title
JP2008021296A (en) Test planning support apparatus and test planning support program
JPH09259181A (en) Work flow managing system
JP2001195483A (en) Device and method for supporting project risk management, and storage medium with program stored thereon
JPH10254529A (en) Plant supervisory and controlling device
JP3938221B2 (en) Process information management system
JP2000039904A (en) Project management system
JP2018136823A (en) Work support system, work support method, and program
JP2003332187A (en) Maintenance method and system for manufacturing semiconductor
JP5764081B2 (en) Plant monitoring and control system
JPH0625991B2 (en) Process planning support device
JP2009043188A (en) Operation management support system, and program
JP2004310210A (en) Work support system
JP2006099558A (en) Production navigation system and navigation terminal
JP2002324088A (en) Support apparatus for design of structure
JPH03218527A (en) Plan-type inference device
JPH0922433A (en) Dynamic plan management device and method
JPH07200981A (en) Reliability evaluating method for plant and update evaluating method therefor
JP3358641B2 (en) Information processing system and information processing method
JP2002342118A (en) System for evaluating software test process and method for evaluating test process
JP4196495B2 (en) Work status information overview device
JPH08166487A (en) Operation planning device
JPH0916069A (en) Creating method for process design and device thereof
JP4040735B2 (en) Work man-hour estimation device
JPH0573107A (en) System and method for planning production
JPH07296062A (en) Method for supporting decision of staff arrangement