JPH10220197A JP9294103A JP29410397A JPH10220197A JP H10220197 A JPH10220197 A JP H10220197A JP 9294103 A JP9294103 A JP 9294103A JP 29410397 A JP29410397 A JP 29410397A JP H10220197 A JPH10220197 A JP H10220197A
Authority
JP
Japan
Prior art keywords
drill
hole
head
plug
series
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP9294103A
Other languages
Japanese (ja)
Inventor
Gerhard Sauer
ゲルハルト・ザウアー
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Publication of JPH10220197A publication Critical patent/JPH10220197A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D20/00Setting anchoring-bolts
    • E21D20/02Setting anchoring-bolts with provisions for grouting
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D21/00Anchoring-bolts for roof, floor in galleries or longwall working, or shaft-lining protection
    • E21D21/0026Anchoring-bolts for roof, floor in galleries or longwall working, or shaft-lining protection characterised by constructional features of the bolts
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D21/00Anchoring-bolts for roof, floor in galleries or longwall working, or shaft-lining protection
    • E21D21/0026Anchoring-bolts for roof, floor in galleries or longwall working, or shaft-lining protection characterised by constructional features of the bolts
    • E21D21/0053Anchoring-bolts in the form of lost drilling rods

Abstract

PROBLEM TO BE SOLVED: To hold anchors, etc., surely at accurate places in a press-in of a curable substance by a method wherein a series of hollow drill pipes, piles or anchors into a drilled pit formed to a stratum with a clearance, the curable substance having specific viscosity is injected into the drilled pit, the drill pipe is removed and the anchors, etc., are left. SOLUTION: When a bedrock, on which the structure is fixed, is drilled by a drill head 1, the drill head 1, to which a drill plug 4 is installed, is connected to a series of drill pipes 9, and anchors 19 are inserted into the drill pipes 9. A curable substance having viscosity of 1500-5000cP is injected into the drill pipes at high pressure through a pushing head after the completion of drilling works. The drill pipes 9 and the drill head 1 are extracted simultaneously from a drilled pit at that time. The anchors 19 are pulled out from the insides of the drill pipes 9 by the pressure and high viscosity of the injected substance, and buried into the injected substance under the state, in which the anchors 19 are held at approximately central places, and left in the drilled pit, and the curable substance is cured rapidly.

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【発明の属する技術分野】本発明は、不安定な地質学的
構造物、所定の範囲でのみしか安定していない構造物、
非結合性または僅かしか結合性のない構造物を固定する
方法に関する。
The present invention relates to unstable geological structures, structures that are only stable in certain areas,
The present invention relates to a method of fixing a non-bonded structure or a structure having only a weak bond.

【0002】[0002]

【従来の技術】従来から、たとえば、トンネル工事の際
には、まず地層にドリル孔を形成し、このドリル孔に一
連の中空のドリル管、および杭またはアンカーを隙間を
持って挿入し、この後に硬化物をこのドリル孔内に注入
し、これと同時に上記の一連のドリル管を取り除き、上
記の杭またはアンカーをこのドリル孔内に残す。
2. Description of the Related Art Conventionally, for example, in tunnel construction, a drill hole is first formed in a stratum, and a series of hollow drill pipes and piles or anchors are inserted into the drill hole with a gap. The cured product is later injected into the drill hole, at the same time the series of drill tubes is removed, leaving the pile or anchor in the drill hole.

【0003】このような方法は、たとえばオーストリア
特許出願 AT 392 517B に開示されてい
る。このような方法では、ドリルの穿孔と同時にこのド
リル管とともに杭またはアンカーが挿入され、この杭ま
たはアンカーの先端部はこのドリル管のドリルヘッドに
捩り方向に剛的に保持される。このため、これら杭また
はアンカーのヘッドは、それらに形成されドリルヘッド
の先端部に対向した肩部によって保持される。
[0003] Such a method is disclosed, for example, in the Austrian patent application AT 392 517B. In such a method, a pile or anchor is inserted with the drill tube simultaneously with the drilling of the drill, and the tip of the pile or anchor is rigidly held in the drill head of the drill tube in a torsional direction. To this end, the heads of these piles or anchors are held by shoulders formed on them and facing the tip of the drill head.

【0004】そして、このドリル孔が所定の深さに達し
た後に、上記のドリル管の内面とアンカーまたは杭の間
の隙間に洗浄剤が供給され、このドリル管の内面とアン
カーまたは杭の間に粘性硬化物が圧入され、これと同時
にこのドリル管が引き抜かれ、これによってこのコンク
リートエマルジョンが確実に圧入される。この場合に、
上記のようなアンカーまたは杭が押し上げられることが
ある。
After the drill hole reaches a predetermined depth, a cleaning agent is supplied to a gap between the inner surface of the drill tube and the anchor or the pile, and a gap is provided between the inner surface of the drill tube and the anchor or the pile. The viscous cured product is pressed into the drill tube, and at the same time the drill tube is withdrawn, thereby ensuring that the concrete emulsion is pressed. In this case,
Anchors or stakes such as those described above may be pushed up.

【0005】[0005]

【発明が解決しようとする課題】本発明の目的は、上述
したような方法における不具合を解消し、上記の硬化物
の圧入の際にアンカーまたは杭を正確な位置に確実に保
持するものである。
SUMMARY OF THE INVENTION An object of the present invention is to solve the above-mentioned problems in the method and to surely hold an anchor or a pile at an accurate position during the press-fitting of the above-mentioned cured product. .

【0006】[0006]

【課題を解決するための手段】このような目的を達成す
るために、本発明の方法は請求の範囲第1項に記載しさ
れているように、不安定な構造物、所定の範囲でのみし
か安定していない構造物、非結合性または僅かしか結合
性のない地質学的な構造物を固定する方法であって、特
に、トンネル工事の際に、まず地層にドリル孔を形成
し、このドリル孔に一連の中空のドリル管、および杭ま
たはアンカーを隙間を持って挿入し、この後に硬化物を
このドリル孔内に注入し、これと同時に上記の一連のド
リル管を取り除き、上記の杭またはアンカーをこのドリ
ル孔内に残すトンネル工事の際において、上記の硬化物
はその粘度が1,500ないし5,000cPのものを
注入することを特徴とするものである。
In order to achieve such an object, the method according to the invention is based on the fact that, as defined in claim 1, unstable structures, only in certain areas. A method of fixing a geological structure that is only stable, non-bonded or only slightly bonded, especially in tunnel construction, where drill holes are first formed in the formation, A series of hollow drill tubes and piles or anchors are inserted into the drill holes with a gap, after which the hardened material is injected into the drill holes, at the same time the above series of drill tubes are removed and the pile Alternatively, at the time of tunnel construction in which an anchor is left in the drill hole, the cured product having a viscosity of 1,500 to 5,000 cP is injected.

【0007】このような手段によれば、高粘性物が存在
することにより、アンカーまたは杭が保持され、ドリル
管を軸方向に移動させる際にも、このアンカーまたは杭
がドリル孔の最深の部分に残される。またこれと同時
に、この高粘性物はこれらのアンカーや杭の径方向に偏
位に対して高い抵抗を示し、これによってこれらアンカ
ーや杭の位置精度が極めて向上する。このように高粘性
物によりアンカーの安定性が高くなるので、張り綱ケー
ブルを使用することも可能となる。
According to such a means, the anchor or the pile is held by the presence of the highly viscous material, and even when the drill pipe is moved in the axial direction, the anchor or the pile is moved to the deepest portion of the drill hole. Will be left. At the same time, the high-viscosity material exhibits high resistance to radial displacement of these anchors and piles, thereby greatly improving the positional accuracy of these anchors and piles. Since the stability of the anchor is increased by the high-viscosity material, it is also possible to use a tether cable.

【0008】この圧入される高粘性物としては、アンカ
ーモルタル、合成樹脂材料、またはペースト状の膨脹性
物質が使用される。
As the high-viscosity material to be injected, an anchor mortar, a synthetic resin material, or a paste-like expandable substance is used.

【0009】原理的には、アンカーまたは杭を用いない
ドリル管によってドリル孔を形成することができる。ド
リル穿孔が終了した後に、洗浄剤が供給される洗浄また
は押圧ヘッドはドリル管から取り外され、このドリル管
内にアンカーまたは杭が挿入される。この後に、この洗
浄または押圧ヘッドはドリル管に再度装着され、硬化物
が圧入され、またこれと同時にこのドリル孔からドリル
管が除去される。各要求に対応して、この作用は、ドリ
ル管の外側端部の引っ張りの荷重、または圧入の際にド
リル管の表面に作用する圧力の下でこの注入物による荷
重によって行われてもよい。
In principle, the drill hole can be formed by a drill tube without anchors or piles. After the drilling has been completed, the cleaning or pressing head supplied with the cleaning agent is removed from the drill tube and the anchor or stake is inserted into the drill tube. Thereafter, the cleaning or pressing head is reattached to the drill tube, the hardened material is pressed in, and at the same time the drill tube is removed from the drill hole. Depending on the requirements, this effect may be effected by a pulling load on the outer end of the drill tube or by a load from this implant under pressure acting on the surface of the drill tube during press-fitting.

【0010】また、本発明の別の目的は、本発明の方法
を実施する装置を提供するものである。
Another object of the present invention is to provide an apparatus for performing the method of the present invention.

【0011】従来の装置は、一連のドリル管を備え、こ
のドリル管は軸方向のダクトを備え、またその前端部に
は通孔を有するドリルヘッドが形成され、上記のドリル
ヘッドの自由面端から軸方向の少なくとも一部にわたっ
て、この通孔は非円形の断面形状を有し、この通孔の断
面形状の周囲の少なくとも一部には、上記の一連のドリ
ル管およびアンカーまたは杭の内壁と、上記のドリルヘ
ッドの通孔との間に隙間が形成されているものにおい
て、それらの一端部に設けられたアンカーが先端面にナ
イフエッジを有するヘッドと共に使用される。このアン
カーのヘツドは、ドリル穿孔方向に対して軸方向に支持
される。よって、このアンカーをドリルヘッドに挿入す
る必要がある。しかしながら、このアンカーの長さはド
リル管を保持するクレードルの分岐範囲に対応した最大
長さにしかできず、逆に言えば、クレードルはこのアン
カーの長さと対応したものを使用する必要があるという
不具合が生じる。
The prior art device comprises a series of drill tubes, which are provided with an axial duct and at the front end of which are formed a drill head with a through hole, the free face end of said drill head. Over at least a portion in the axial direction, the through-hole has a non-circular cross-sectional shape, and at least a portion of the perimeter of the cross-sectional shape of the through-hole includes the series of drill pipes and the inner wall of the anchor or pile. In the case where a gap is formed between the drill hole and the through hole of the above-mentioned drill head, an anchor provided at one end thereof is used together with a head having a knife edge on a tip end surface. The head of the anchor is supported axially with respect to the drilling direction. Therefore, it is necessary to insert this anchor into the drill head. However, the length of this anchor can only be the maximum length corresponding to the branch range of the cradle holding the drill tube, conversely, the cradle needs to use the length corresponding to this anchor Failure occurs.

【0012】本発明の目的は、このような不具合を解消
し、上記のような装置において、使用されるクレードル
の分岐範囲を超えた長さを有するアンカーを使用できる
装置を提供するものである。
An object of the present invention is to solve such a problem and to provide an apparatus capable of using an anchor having a length exceeding a branch range of a cradle to be used in the above-mentioned apparatus.

【0013】この目的を達成するために、本発明の装置
は、請求の範囲第2項に示すように、一連のドリル管を
備え、このドリル管は軸方向のダクトを備え、またその
前端部には通孔を有するドリルヘッドが形成され、上記
のドリルヘッドの自由面端から軸方向の少なくとも一部
にわたって、この通孔は非円形の断面形状を有し、この
通孔の断面形状の周囲の少なくとも一部には、上記の一
連のドリル管およびアンカーまたは杭の内壁と、上記の
ドリルヘッドの通孔との間に隙間が形成されているもの
において、上記のドリルヘッドの軸方向の通孔内にはド
リルプラグが保持されており、このドリルプラグはドリ
ル穿孔方向の軸方向に排除されるものであり、またこの
ドリルプラグはナイフエッジを備え、このドリルプラグ
は上記の通孔のドリルヘッドの前面側に連通する部分に
保持されており、またこのドリルプラグは非円形の断面
形状を有していることを特徴とするものである。
[0013] To this end, the device according to the invention comprises a series of drill tubes, comprising an axial duct and a front end thereof, as claimed in claim 2. A drill head having a through hole is formed, and the through hole has a non-circular cross-sectional shape from the free surface end of the drill head to at least a portion in the axial direction. At least in part, a gap is formed between the inner wall of the series of drill pipes and anchors or piles and the through-hole of the drill head, wherein the drill head has an axial passage. A drill plug is held in the hole, which is removed in the axial direction of the drilling direction, and which has a knife edge and which is provided with a hole in the through hole. Front side of the heads or others are held in the portion communicating with, and this drill plug is characterized in that it has a non-circular cross-sectional shape.

【0014】この目的は、ドリルヘッドの通孔の先端側
開口を略閉塞することにより達成され、またこのドリル
ヘッドはアンカーを挿入せずに完全に使用される。これ
により、最初にドリル孔が形成され、この後にドリル管
内にアンカーが挿入される。これにより、しばしば問題
となっていたドリル管内に挿入されるアンカーの遊びが
解消される。さらに、クレードルの分岐長さに対応して
アンカーの長さが制限されるという問題も解消される。
This object is achieved by substantially closing the distal opening of the through hole of the drill head, and the drill head can be used completely without inserting an anchor. This initially forms the drill hole, after which the anchor is inserted into the drill tube. This eliminates the often problematic play of the anchor inserted into the drill tube. Further, the problem that the length of the anchor is limited corresponding to the branch length of the cradle is also solved.

【0015】このアンカーおよびドリルプラグは、注入
物の押圧により、このドリル管からドリル穿孔方向の軸
方向に押し出される。
[0015] The anchor and the drill plug are pushed out of the drill tube in the axial direction of the drilling direction by pressing the injection material.

【0016】また、請求の範囲第3項に記載された装置
は、上記のドリルプラグを極めて簡単に固定できる特徴
がある。また、自重でドリルヘッドから落下することも
なく、鉛直下方に穿孔する場合でも容易に実施すること
ができる。
The device described in claim 3 is characterized in that the above-mentioned drill plug can be fixed very easily. In addition, even when drilling vertically downward without dropping from the drill head by its own weight, it can be easily implemented.

【0017】また、請求の範囲第4項に記載された装置
は、最も簡単な構造を提供するものである。
The device described in claim 4 provides the simplest structure.

【0018】[0018]

【発明の実施の形態】図1、2および3には、ドリルヘ
ッド1を示し、このドリルヘッドの先端面にはカーバイ
ド製のドリルピン2が設けられ、また、このドリルヘッ
ド1の軸方向に通孔3が形成されている。この通孔3
は、非円形の断面形状を有し、またこのドリルヘッドの
先端側に向かって拡径している。
1, 2, and 3 show a drill head 1 having a drill pin 2 made of carbide at a tip end surface thereof and having a drill pin 2 extending in the axial direction of the drill head 1. A hole 3 is formed. This through hole 3
Has a non-circular cross-sectional shape and expands in diameter toward the distal end of the drill head.

【0019】また、図3に示すように、この通孔3は略
十字状の断面形状をなしている。またこの通孔3はドリ
ルヘッド1の先端側に向けて拡径しており、この通孔に
はドリルプラグ4が保持されており、このドリルプラグ
の先端面にはナイフエッジ5が形成されている。このド
リルプラグ4はドリル穿孔方向に対して軸方向に支持さ
れており、この円錐形の通孔3により保持されている。
As shown in FIG. 3, the through hole 3 has a substantially cross-sectional shape. The diameter of the through hole 3 is increased toward the distal end of the drill head 1. A drill plug 4 is held in the through hole, and a knife edge 5 is formed on the distal end surface of the drill plug. I have. The drill plug 4 is supported in the axial direction with respect to the drilling direction, and is held by the conical through hole 3.

【0020】また、このドリルプラグ4には横方向の孔
6が形成されており、この孔を貫通して略U字状のスプ
リング7が設けられている。このスプリングの両脚部
は、上記の通孔3内に形成されたポケット状の延長部8
内に嵌合しており、これによって上記のドリルプラグが
摩擦によりこの通孔3の壁部に保持されている。そし
て、このドリルプラグ4は、ドリル穿孔方向の軸方向に
排除可能である。
The drill plug 4 has a horizontal hole 6 formed therein, and a substantially U-shaped spring 7 is provided through the hole. Both legs of the spring are formed with pocket-like extensions 8 formed in the through holes 3.
The drill plug is held in the wall of the through hole 3 by friction. The drill plug 4 can be removed in the axial direction of the drilling direction.

【0021】上記のドリルヘッド1はドリル管9に通常
の方法で螺装されており、このドリル管は複数の部品を
接続した一連のものである。
The drill head 1 is screwed in a conventional manner on a drill tube 9 which is a series of connected parts.

【0022】この一連のドリル管9の駆動側の端部に
は、押圧ヘッド10が接続されており、この押圧ヘッド
には注入物を供給する供給手段11が設けられている。
この押圧ヘッド10には、通常の手段で上記の供給手段
11とともにスリーブ12が設けられている。このスリ
ーブ12の内周面には、上記の供給手段11の部分に周
方向の溝13が形成され、またこのスリーブはヘッド1
4を囲んでおり、このヘッドは上記の一連のドリル管9
に対して一体的に回転するように剛的に接続されてい
る。このヘッド14には、中央のめくら孔15が形成さ
れ、このめくら孔はドリル管9の内側に連通しており、
また横方向の孔16を介して上記のスリーブ12の環状
の溝13に連通している。このスリーブ12は、このヘ
ッド14に対して、パッキング17等の手段により、シ
ール性が維持されている。
A pressing head 10 is connected to an end of the series of drill pipes 9 on the driving side, and the pressing head is provided with supply means 11 for supplying an injectate.
The pressing head 10 is provided with a sleeve 12 together with the supply means 11 by a usual means. On the inner peripheral surface of the sleeve 12, a circumferential groove 13 is formed in the part of the supply means 11 described above.
4 and this head is connected to the series of drill tubes 9 described above.
Are rigidly connected to each other so as to rotate integrally. A central blind hole 15 is formed in the head 14, and the blind hole communicates with the inside of the drill tube 9.
In addition, the sleeve 12 communicates with the annular groove 13 of the sleeve 12 through a horizontal hole 16. The sealing performance of the sleeve 12 is maintained with respect to the head 14 by means such as a packing 17.

【0023】また、上記のヘッド14のめくら孔18に
は、ドリルハンマー(図示せず)が装着され、このヘッ
ド14を作動させる。
A drill hammer (not shown) is mounted in the blind hole 18 of the head 14, and the head 14 is operated.

【0024】図1ないし図5に示す状態は、アンカー1
9が一連のドリル管9内にすでに挿入されている状態で
あり、このアンカーには、好ましくは螺旋形のリブ20
が形成されている。また、図4に特に明瞭に示されるよ
うに、この一連のドリル管9の内面と上記のアンカー1
9との間には隙間21が形成されている。この隙間は、
ドリル穿孔の際に洗浄剤を供給するために使用され、こ
の洗浄剤は前記の押圧ヘッド10と同様の構成の洗浄ヘ
ッドを介してこの一連のドリル管9内に供給される。
The state shown in FIG. 1 to FIG.
9 having already been inserted into the series of drill tubes 9, the anchors having preferably helical ribs 20.
Are formed. Also, as shown particularly clearly in FIG. 4, the inner surface of this series of drill pipes 9 and the above-mentioned anchor 1
A gap 21 is formed between the gap 9 and the gap 9. This gap is
It is used for supplying a cleaning agent during drilling, and the cleaning agent is supplied into the series of drill pipes 9 through a cleaning head having the same configuration as the pressing head 10 described above.

【0025】本発明によってこのアンカーを施工する場
合には、構造物を固定する岩盤にドリルヘッド1により
穿孔がなされ、この際に、このドリルヘッドには上記の
ドリルプラグ4が装着され、このドリルヘッドは一連の
ドリル管9に接続される。また、この一連のドリル管9
内にはアンカー19が挿入されるが、これは必ずしも必
要なものではない。
When this anchor is installed according to the present invention, a rock head for fixing a structure is perforated by a drill head 1, and at this time, the drill plug 4 is attached to the drill head, and the drill plug is attached to the drill head. The head is connected to a series of drill tubes 9. Also, this series of drill pipes 9
An anchor 19 is inserted therein, but this is not necessary.

【0026】上記のドリル穿孔の際には、この一連のド
リル管の内部を介して洗浄剤が供給される。この洗浄剤
の供給は、前述の押圧ヘッド10と同様な構造の洗浄ヘ
ッド等の手段を介しておこなわれる。
At the time of the above drilling, a cleaning agent is supplied through the inside of the series of drill pipes. The supply of the cleaning agent is performed through a means such as a cleaning head having the same structure as the pressing head 10 described above.

【0027】このドリル穿孔作業が終了した後に、上記
の洗浄ヘッドが取り外され、その後にこのドリル管9内
に上記のアンカー19または杭が挿入される。この後
に、上記の押圧ヘッド10を介して、粘度が1,500
ないし5,000cPの注入物が高圧でドリル管の内部
に注入され、この注入物は上記のドリルヘッド1の通孔
3を介して先端面まで注入される。この際に、このドリ
ル管9およびドリルヘッドがドリル孔から同時に引き抜
かれる。この場合に、この注入物の圧力のみならず、こ
のドリル管9に引っ張り荷重を追加して作用させてもよ
い。
After the drilling operation is completed, the cleaning head is removed, and then the anchor 19 or the pile is inserted into the drill tube 9. After this, the viscosity is 1,500 via the pressing head 10 described above.
5,000 cP of injection material is injected at high pressure into the inside of the drill tube, and this injection material is injected through the through hole 3 of the drill head 1 to the tip surface. At this time, the drill tube 9 and the drill head are simultaneously pulled out of the drill hole. In this case, not only the pressure of the injected material but also a tensile load may be applied to the drill tube 9.

【0028】この注入物の圧力およびその高い粘性によ
り、上記のアンカー19がこのドリル管9内から引き抜
かれ、この注入物に埋設されてこのドリル孔内に残留さ
れ、迅速に硬化する。また、この注入物は、上記の押圧
ヘッド10からこのドリル管9の中心部に注入されるの
で、この注入物によりこのアンカー19が略中心位置に
保持される。
Due to the pressure of the injection and its high viscosity, the anchor 19 is withdrawn from the drill tube 9 and buried in the injection and remains in the drill hole and hardens rapidly. Further, since the injection material is injected from the pressing head 10 into the center of the drill tube 9, the anchor 19 is held at a substantially central position by the injection material.

【0029】上記のようにしてこの注入物が迅速に硬化
した後には、この構造物は岩盤に確実に固定される。
After the injection has cured rapidly as described above, the structure is securely fixed to the bedrock.

【0030】[0030]

【発明の効果】上述の如く本発明によれば、岩盤等にア
ンカー等の構造物を正確かつ確実に固定することができ
る。
As described above, according to the present invention, a structure such as an anchor can be accurately and reliably fixed to a bedrock or the like.

【図面の簡単な説明】[Brief description of the drawings]

【図1】アンカーが挿入された状態のドリルヘッドの部
分の概略的な縦断面図。
FIG. 1 is a schematic longitudinal sectional view of a portion of a drill head with an anchor inserted.

【図2】図1に対して90°回動した方向からの概略的
な縦断面図。
FIG. 2 is a schematic longitudinal sectional view from a direction rotated by 90 ° with respect to FIG. 1;

【図3】ドリルプラグを挿入した状態のドリルヘッドの
正面図。
FIG. 3 is a front view of the drill head with a drill plug inserted.

【図4】図1のIV−IV線に沿う断面図。FIG. 4 is a sectional view taken along the line IV-IV in FIG. 1;

【図5】ドリル管に装着された押圧ヘッドの縦断面図。FIG. 5 is a longitudinal sectional view of a pressing head mounted on a drill tube.

【符号の説明】[Explanation of symbols]

1 ドリルヘッド 3 通孔 4 ドリルプラグ 5 ナイフエッジ 7 スプリング 9 ドリル管 19 アンカー DESCRIPTION OF SYMBOLS 1 Drill head 3 Through hole 4 Drill plug 5 Knife edge 7 Spring 9 Drill tube 19 Anchor

Claims (4)

【特許請求の範囲】[Claims] 【請求項1】 不安定な構造物、所定の範囲でのみしか
安定していない構造物、非結合性または僅かしか結合性
のない地質学的な構造物を固定する方法であって、特
に、トンネル工事の際に、まず地層にドリル孔を形成
し、このドリル孔に一連の中空のドリル管、および杭ま
たはアンカーを隙間を持って挿入し、この後に硬化物を
このドリル孔内に注入し、これと同時に上記の一連のド
リル管を取り除き、上記の杭またはアンカーをこのドリ
ル孔内に残すトンネル工事の際において、 上記の硬化物はその粘度が1,500ないし5,000
cPのものを注入することを特徴とする地質学的な構造
物の固定方法。
1. A method for fixing an unstable structure, a structure that is only stable within a predetermined range, a geological structure that is non-bonded or only slightly bonded, During tunnel construction, a drill hole is first formed in the formation, a series of hollow drill pipes and piles or anchors are inserted into the drill hole with a gap, and then the hardened material is injected into the drill hole. At the same time, at the time of tunnel construction in which the series of drill pipes is removed and the pile or anchor is left in the drill hole, the cured product has a viscosity of 1,500 to 5,000.
A method for fixing a geological structure, comprising injecting cP.
【請求項2】 請求の範囲第1項に記載した方法を実施
する装置であって、一連のドリル管(9)を備え、この
ドリル管は軸方向のダクトを備え、またその前端部には
通孔(3)を有するドリルヘッドが形成され、上記のド
リルヘッド(1)の自由面端から軸方向の少なくとも一
部にわたって、この通孔は非円形の断面形状を有し、こ
の通孔の断面形状の周囲の少なくとも一部には、上記の
一連のドリル管(9)およびアンカー(19)または杭
の内壁と、上記のドリルヘッド(1)の通孔(3)との
間に隙間が形成されているものにおいて、 上記のドリルヘッド(1)の軸方向の通孔(3)内には
ドリルプラグ(4)が保持されており、このドリルプラ
グはドリル穿孔方向の軸方向に排除されるものであり、
またこのドリルプラグはナイフエッジ(5)を備え、こ
のドリルプラグは上記の通孔(3)のドリルヘッド
(1)の前面側に連通する部分に保持されており、また
このドリルプラグは非円形の断面形状を有していること
を特徴とする装置。
2. Apparatus for carrying out the method according to claim 1, comprising a series of drill tubes (9), said drill tubes comprising an axial duct and having at its front end a front end. A drill head having a through-hole (3) is formed, which has a non-circular cross-sectional shape from at least a part of the axial direction from the free surface end of the drill head (1). At least part of the circumference of the cross-sectional shape has a gap between the series of drill pipes (9) and the inner wall of the anchor (19) or the pile and the through hole (3) of the drill head (1). In what is formed, a drill plug (4) is held in an axial bore (3) of the drill head (1), which drill plug is removed in the axial direction of the drilling direction. And
The drill plug also has a knife edge (5), which is held in a part of the through hole (3) communicating with the front side of the drill head (1), and the drill plug is non-circular. An apparatus having a cross-sectional shape of:
【請求項3】 前記のドリルプラグ(4)は、少なくと
も1個のスプリング(7)により前記のドリルヘッド
(1)に摩擦保持されており、このスプリング(7)は
このドリルヘッド(1)の通孔(3)の内壁に保持され
ていることを特徴とする請求の範囲第2項の装置。
3. The drill plug (4) is frictionally held on the drill head (1) by at least one spring (7), the spring (7) being connected to the drill head (1). 3. The device according to claim 2, wherein the device is held on the inner wall of the through hole.
【請求項4】 前記のスプリングは略V字状に屈曲され
たものであり、前記のドリルプラグ(4)の横方向孔
(6)内に挿入されており、またこのスプリングの2つ
の脚部の先端部は前記のドリルヘッド(1)の通孔
(3)の内壁に保持されていることを特徴とする請求の
範囲第2項または第3項の装置。
4. The spring is bent in a substantially V-shape, is inserted into a lateral hole (6) of the drill plug (4), and has two legs of the spring. 4. The device according to claim 2, wherein the tip of the drill head is held on the inner wall of the through hole (3) of the drill head (1).
JP9294103A 1996-11-13 1997-10-27 Method and equipment for fixing geological structure Pending JPH10220197A (en)

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
AT198996 1996-11-13
AT1989/96 1996-11-13

Publications (1)

Publication Number Publication Date
JPH10220197A true JPH10220197A (en) 1998-08-18

Family

ID=3525438

Family Applications (1)

Application Number Title Priority Date Filing Date
JP9294103A Pending JPH10220197A (en) 1996-11-13 1997-10-27 Method and equipment for fixing geological structure

Country Status (3)

Country Link
EP (1) EP0843073B1 (en)
JP (1) JPH10220197A (en)
DE (1) DE59706293D1 (en)

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE102010023627B4 (en) * 2010-03-08 2012-07-26 Markus Swoboda self-drilling
CN105089550A (en) * 2014-05-20 2015-11-25 枣庄矿业集团中兴建安工程有限公司 Pulling-type slip grout packer

Family Cites Families (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
FR1369178A (en) * 1963-09-05 1964-08-07 Anchoring method and device applicable to support rods used in mines, and for all other dry seals
BE750586A (en) * 1969-05-30 1970-11-03 Klemm Bohrtech DRILLING MACHINE FOR COVERING GROUNDS, CALLED "WAGON-DRILL" AND METHOD FOR ITS USE
DE2431113A1 (en) * 1974-06-28 1976-01-15 Takechi Komusho Kk Ground anchor for retaining wall support - is inserted by boring tool with expanding cutters and can be removed
US4289427A (en) * 1979-02-07 1981-09-15 Owens-Corning Fiberglas Corporation Process for installing roof bolts
JPS5856594B2 (en) * 1980-10-03 1983-12-15 住友化学工業株式会社 Non-combustible and heat-resistant adhesive for fixing anchor bolts in holes.
US4378180A (en) * 1980-11-05 1983-03-29 Scott James J Yieldable mine roof support fixture
AT392517B (en) * 1988-11-03 1991-04-25 Sauer Gerhard Ing Dr METHOD AND DEVICE FOR SECURING NON OR. Moderately stable, non-cohesive to slightly cohesive geological formations
FI905862A (en) * 1990-11-28 1992-05-29 Tampella Oy Ab BERGBULT.
DE4131457A1 (en) * 1991-09-21 1993-03-25 Basf Ag CARTRIDGE OR CARTRIDGE FOR CHEMICAL FASTENING TECHNOLOGY

Also Published As

Publication number Publication date
DE59706293D1 (en) 2002-03-21
EP0843073B1 (en) 2002-02-06
EP0843073A1 (en) 1998-05-20

Similar Documents

Publication Publication Date Title
US20090052995A1 (en) Arrangement for injecting and affixing a reinforcing or anchoring element in a rock wall
US6575240B1 (en) System and method for driving pipe
KR101481123B1 (en) Extension excavation machine of soft ground and method for reinforcing soft ground using the same
RU2005141565A (en) ANCHOR BOLT
KR20080038276A (en) Method and device for drilling, particularly percussion or rotary percussion drilling, a hole in soil or rock material
JP2009041335A (en) Repair method for existing lining object
KR970001774A (en) Method for creating anchored fasteners without expanding pressure and devices and use therefor for cutting indentation bolts
CN112539075A (en) Preset internal anchor rod structure for tunnel in-situ extension project and supporting method thereof
CN201176593Y (en) Anchor rod for mixing soil-cement
JP2008542594A (en) Method and apparatus for drilling holes in soil or rock material, especially percussion or rotary percussion drilling
HRP20030813A2 (en) Method and device for drilling a hole and for securing an anchorage in a bore hole
JP2015117462A (en) Pinning method
JPH10220197A (en) Method and equipment for fixing geological structure
JP2020033698A (en) Hole-in anchor and construction method thereof
JP3453387B2 (en) Perforation method and casing shoe
JP2002038477A (en) Stabilizing method for slope face
JP2006336387A (en) Anchor device
KR19990026113A (en) Composite anchoring hole for tension recovery type anchor
KR100717252B1 (en) Grouting apparatus and Method of construction work using Earth anchor
JP7339789B2 (en) Anchor and anchor construction method
AU2013101106A4 (en) Thrust Dolly
JP2016176284A (en) Lock bolt and construction method thereof
JP2546733B2 (en) Anchor construction method for consolidation ground
AU2021106794A4 (en) Rock bolt anchor
KR20020038451A (en) construction method for ground anchor and ground anchor