JPH0995939A - Longitudinal joint burying construction method for steel pipe pile - Google Patents

Longitudinal joint burying construction method for steel pipe pile

Info

Publication number
JPH0995939A
JPH0995939A JP27665595A JP27665595A JPH0995939A JP H0995939 A JPH0995939 A JP H0995939A JP 27665595 A JP27665595 A JP 27665595A JP 27665595 A JP27665595 A JP 27665595A JP H0995939 A JPH0995939 A JP H0995939A
Authority
JP
Japan
Prior art keywords
steel pipe
pile
piles
ground
pipe piles
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP27665595A
Other languages
Japanese (ja)
Inventor
Kiyoshi Shioda
喜義 潮田
Hiroshi Kiritani
浩 桐谷
Tomoharu Hirose
智治 廣瀬
Yoichi Yokoyama
陽一 横山
Hiroyuki Eguchi
宏幸 江口
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Nitto Kogyo Co Ltd
Kubota Corp
Original Assignee
Nitto Kogyo Co Ltd
Kubota Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Nitto Kogyo Co Ltd, Kubota Corp filed Critical Nitto Kogyo Co Ltd
Priority to JP27665595A priority Critical patent/JPH0995939A/en
Publication of JPH0995939A publication Critical patent/JPH0995939A/en
Pending legal-status Critical Current

Links

Landscapes

  • Piles And Underground Anchors (AREA)
  • Placing Or Removing Of Piles Or Sheet Piles, Or Accessories Thereof (AREA)

Abstract

PROBLEM TO BE SOLVED: To improve the executing ability and economic ability of the longitudinal joint underground installation of a steel pipe pile. SOLUTION: Several pieces of regular sized steel pipe piles 3a, 3b are laterally joined on the ground and formed as a lower pile, and inserted in an underground hole 1, and a key reinforcement 5 is set on a bearing base 8 and supported with its head slightly protruded above the ground. Next the upper pile 3c of the regular sized steel pipe pile is suspended up and lowered on a lower pile, and they are mutually weldedly joined for ending longitudinal joint. After all longitudinally joined piles 3a, 3b, 3c are slightly suspended up to remove the key reinforcement 5, the piles 3a, 3b, 3c are lowered and inserted in the underground hole 1.

Description

【発明の詳細な説明】Detailed Description of the Invention

【0001】[0001]

【産業上の利用分野】本発明は、通常の鋼管杭や縦方向
に継手部材を有する鋼管杭の縦継ぎによる埋設工法に関
するものである。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a method for burying ordinary steel pipe piles or steel pipe piles having joint members in the longitudinal direction by vertical connection.

【0002】[0002]

【従来の技術】鋼管杭は、製造や運搬の都合により定尺
に製造されているが、それより長い鋼管杭を必要とする
場合は、通常、現場に搬入された鋼管杭の複数本を地上
で継ぎ合せて必要な長さのものに形成し、それを埋設す
るようにしている。この鋼管杭の継ぎ合せは、従来、鋼
管杭を地上に倒伏した状態で、溶接により横継ぎして必
要な長さのものに形成する。そして、これをクレーンに
より吊り上げ、吊り下して埋設施工を行っている。
2. Description of the Related Art Steel pipe piles are manufactured to a fixed length for the convenience of manufacturing and transportation. However, when steel pipe piles longer than that are required, it is normal to use multiple steel pipe piles that have been delivered to the site. They are spliced together to form the required length and embedded. Conventionally, the steel pipe piles are joined to each other by welding in a state in which the steel pipe piles are laid down on the ground and formed into a required length. Then, this is lifted by a crane and suspended to carry out burial construction.

【0003】[0003]

【発明が解決しようとする課題】上記のように、鋼管杭
の継ぎ合せを要する深度の大きな杭の施工では、鋼管杭
を地上で横継ぎにするために、それに応じた長大な敷地
を必要とする。多くの工事現場では、2本の鋼管杭を継
げる程度の広さの敷地を確保できるのがようやくであ
り、それ以上の継ぎ合せは殆どできないのが実情であ
る。したがって、工事用として大きな敷地のとれない市
街地などでは、深度の大きな杭の埋設が行えないといっ
た状況である。
As described above, in the construction of piles with a large depth that require the joining of steel pipe piles, in order to laterally join the steel pipe piles on the ground, a correspondingly large site is required. To do. At many construction sites, it is only possible to secure a site large enough to connect two steel pipe piles, and it is the actual situation that no more joints can be made. Therefore, it is not possible to bury piles with a large depth in urban areas where a large site is not available for construction.

【0004】また、継ぎ合せて長大となった杭を吊り上
げるには、それに相応した大型クレーンを設置しなけれ
ばならず、多額の経費を要するばかりでなく、作業上の
危険度も著しく増大することになる。そのため、継ぎ合
せを要する鋼管杭の埋設施工に対する改善が要望されて
いた。
Further, in order to hoist piles that have become long by joining them, a large-sized crane corresponding to them must be installed, which not only requires a large amount of cost, but also significantly increases the risk of work. become. Therefore, there has been a demand for improvement in the burial construction of steel pipe piles that require seaming.

【0005】本発明は、上記の事情にかんがみなされた
もので、鋼管杭を埋設孔に挿入する過程において、すな
わち、先に埋設孔に挿入された下杭に対して、これに縦
継ぎする上杭を吊り降して接合、溶接するようにするよ
うにし、また、継手部材を有する鋼管杭の場合には、継
手部材相互の位置合せが正確、容易にできる方法を講じ
ることにより、深度の大な鋼管杭の埋設施工を、長大な
敷地や大型のクレーンを要さず、安全、容易、確実に能
率よく行えるようにしようとするものである。
The present invention has been made in view of the above circumstances, and in the process of inserting the steel pipe pile into the burial hole, that is, to vertically connect the lower pile previously inserted into the burial hole. The piles should be suspended for joining and welding, and in the case of steel pipe piles that have joint members, the method for accurately and easily aligning the joint members with each other should be adopted to increase the depth. It is intended to bury underground steel pipe piles safely, easily, and reliably and efficiently without the need for a long site or large crane.

【0006】[0006]

【課題を解決するための手段】上記の目的を達成するた
めの本発明の構成について、実施例に対応する図面を参
照して説明すると、請求項1の工法は、複数本の鋼管杭
を地上で横継ぎして下杭3a,3bを形成し、この下杭
3a,3bを埋設孔1に挿入して、その頭部を地上に突
出した状態で支持し、この下杭3b上に鋼管杭1本ない
し2本を横継ぎした上杭3cを吊り降して縦継ぎを行っ
た後、縦継ぎされた継手部材を有する鋼管杭3a,3
b,3c全体を埋設孔に挿入することを特徴とするもの
である。
The structure of the present invention for achieving the above object will be described with reference to the drawings corresponding to the embodiments. In the construction method of claim 1, a plurality of steel pipe piles are grounded. To form lower piles 3a and 3b, insert the lower piles 3a and 3b into the embedding hole 1, and support the head with the head protruding above the ground. Steel pipe piles 3a, 3 having joint members that are vertically spliced after suspending an upper pile 3c that horizontally splices one or two pipes and performing longitudinal splicing
It is characterized in that the whole b, 3c is inserted into the buried hole.

【0007】また、請求項2の工法は、継手部材4,4
を有する鋼管杭の複数本を地上で縦継ぎして下杭3a,
3bを形成し、この下杭3a,3bを埋設孔1に挿入し
て、その頭部を地上に突出した状態で支持し、他方、こ
の下杭3bとこれに縦継ぎする上杭3aの接合端部に位
置合せ用の突起体10,10を設け、下杭3bの突起体10,
10に嵌合してガイド治具11を立設した後、下杭3b上に
鋼管杭1本ないし2本を横継ぎした上杭3cを吊り降し
て、その突起体10,10をガイド治具11に係合して下杭3
cに接合させ、縦継ぎを行った後、縦継ぎされた継手部
材を有する鋼管杭3a,3b,3c全体を埋設孔1に挿
入することを特徴とするものである。
Further, the construction method of claim 2 is such that the joint members 4, 4 are
A plurality of steel pipe piles having a
3b is formed, and the lower piles 3a and 3b are inserted into the burial hole 1 to support the head in a state of protruding above the ground, while joining the lower pile 3b and the upper pile 3a vertically connected to the lower pile 3b. Protrusions 10, 10 for alignment are provided at the ends of the protrusions 10 of the lower pile 3b.
After the guide jig 11 is fitted to the lower pile 3 and the guide jig 11 is erected, the upper pile 3c obtained by horizontally connecting one or two steel pipe piles is suspended on the lower pile 3b, and the projecting bodies 10 and 10 are guided and fixed. Lower stake 3 engaging with tool 11
The steel pipe piles 3a, 3b, 3c having joint members which are vertically connected to each other are inserted into the embedding hole 1 after being joined to c and vertically connected.

【0008】[0008]

【作用】複数本の鋼管杭3a,3bを地上で、横継ぎし
て下杭とされる。まず、この下杭3a,3bが埋設孔1
に挿入され、頭部を地上に突出した状態で、カンザシ筋
5を受台8に載せて支持させる。この下杭に対し、上杭
3cを吊り降して接合し、溶接により結合して縦継ぎが
なされる。それら縦継ぎされた鋼管杭3a、3b、3c
を少し吊り上げてカンザシ筋を除去し、再び吊り降して
全体が埋設孔1に挿入される。
Operation: A plurality of steel pipe piles 3a and 3b are laterally connected on the ground to form a lower pile. First, the lower piles 3a and 3b are the buried holes 1
And the head muscles are projected onto the ground, and the kanzashi muscles 5 are placed on and supported by the pedestal 8. The upper pile 3c is suspended and joined to the lower pile, and the upper pile 3c and the lower pile are joined by welding to form a vertical joint. Steel pipe piles 3a, 3b, 3c vertically connected to each other
Is lifted a little to remove the kanzashi muscle, and then suspended again to insert the whole into the embedding hole 1.

【0009】請求項2の工法においては、上杭3cを下
杭3bに接合する際、下杭3bに立設したガイド治具11
の導入孔13に上杭3cの突起体10が誘導されて係合する
ことにより、両杭3c,3bの周方向の位置合せが容
易、確実に行われる。
According to the construction method of claim 2, when the upper pile 3c is joined to the lower pile 3b, the guide jig 11 provided upright on the lower pile 3b is used.
By guiding and engaging the projection body 10 of the upper pile 3c with the introduction hole 13 of the above, the circumferential alignment of both piles 3c and 3b can be performed easily and reliably.

【0010】[0010]

【実施例】以下、本発明の実施例について、図面を参照
して説明する。図1〜図4は施工の概要を行程順に示し
たものである。
Embodiments of the present invention will be described below with reference to the drawings. 1 to 4 show the outline of construction in order of process.

【0011】鋼管杭の埋設にあたっては、まず地盤に、
鋼管杭より大径の埋設孔1が所定の深さに掘削、形成さ
れ、その中にはソイルセメント2が充填される。埋設す
る鋼管杭3としては、単に鋼管で形成した通常のもの、
或は、図示のように、鋼管の外周面の縦方向に一対の継
手部材4,4を設けたものが使用される。
When burying steel pipe piles, first, in the ground,
A buried hole 1 having a diameter larger than that of a steel pipe pile is excavated and formed to a predetermined depth, and soil cement 2 is filled therein. As the steel pipe pile 3 to be buried, a normal one simply formed of a steel pipe,
Alternatively, as shown in the figure, a steel pipe provided with a pair of joint members 4 and 4 in the longitudinal direction of the outer peripheral surface is used.

【0012】現場へは、工場で製造された定尺(例えば
15m)の鋼管杭3が搬入され、掘削孔1が長大である場
合は、鋼管杭3の2〜4本を継ぎ合せて埋設する。図1
〜図4は、3本の鋼管杭3a,3b,3cを継ぎ合せて
埋設した実施例を示している。この場合、2本の鋼管杭
3a,3bは、地上において倒伏させた状態で端面を接
合し、溶接により、横継ぎ(結合)9して下杭とする。
そして、この下杭3a,3bの上部適所には、カンザシ
筋5の貫通孔6,6が設けられる。また、埋設孔1の上
部は若干広く形成され、孔縁部にはガイドウォール7,
7が、その下方部には杭支持用の受台8,8が設けられ
る。
[0012] To the site, a factory-made standard (for example,
When the steel pipe pile 3 of 15 m) is carried in and the excavation hole 1 is long, 2 to 4 of the steel pipe piles 3 are spliced and buried. FIG.
4 shows an embodiment in which three steel pipe piles 3a, 3b, 3c are joined and buried. In this case, the two steel pipe piles 3a and 3b are joined together at their end faces in a state of being laid down on the ground, and laterally connected (joined) 9 by welding to form a lower pile.
Then, through holes 6 and 6 of the knapweed muscle 5 are provided at appropriate places above the lower piles 3a and 3b. In addition, the upper portion of the buried hole 1 is formed slightly wider, and the guide wall 7,
7, and pedestals 8 for supporting the piles are provided in the lower part thereof.

【0013】2本の鋼管杭よりなる下杭3a,3bは、
図1に示すように、クレーンで吊り上げられ、埋設孔1
内に降下、挿入される。その際、貫通孔6,6にはカン
ザシ筋5が貫挿され、その両端部は鋼管の外方に突出さ
れる。挿入された下杭3a,3bは、図2に示すよう
に、カンザシ筋5がその両端部を受台8,8に載ること
により、その頭端を所要の高さ地上に突出して受台8,
8に吊持される。この突出する高さは、貫通孔6,6の
設けられる高さ位置及び受台8,8の設けられる深さ位
置によって選定される。
The lower piles 3a and 3b composed of two steel pipe piles are
As shown in Fig. 1, the crane is hoisted and the buried hole 1
It is dropped inside and inserted. At that time, the kakuza muscle 5 is inserted through the through holes 6 and 6, and both ends thereof are projected to the outside of the steel pipe. As shown in FIG. 2, the inserted lower piles 3a and 3b have their head ends projecting above the required height on the pedestal 8 by placing both ends of the kanzashi muscle 5 on the pedestals 8 and 8. ,
Suspended at 8. The projecting height is selected depending on the height position where the through holes 6 and 6 are provided and the depth position where the pedestals 8 and 8 are provided.

【0014】ついで、上杭である鋼管杭3Cをクレーン
により吊り上げ、矢印で示すように、上記下杭3a,3
bに位置合せしながら降下させて各端面を接合し、両者
を溶接により結合9して、縦継ぎを行う。それによっ
て、埋設する所定長さの鋼管杭が形成されることにな
る。その後は、図3に示すように、縦継ぎされた鋼管杭
3a,3b,3cを、上記カンザシ筋5が地面より少し
出る高さとなるまでクレーンで吊り上げ、打撃を加える
などしてカンザシ筋5を除去し、図4に示すように、再
び降下させて埋設孔1への挿入を終えるのである。この
挿入後は、ガイドウォール7,7及び受台8,8は撤去
され、それらを設置した広穴は埋め戻される。
Next, the steel pipe pile 3C, which is the upper pile, is lifted by a crane and, as indicated by the arrow, the lower piles 3a, 3
While being aligned with b, it is lowered to join the end faces, and the two are joined by welding 9 to perform a vertical joint. As a result, a steel pipe pile having a predetermined length to be buried is formed. After that, as shown in FIG. 3, the vertically connected steel pipe piles 3a, 3b, 3c are lifted by a crane until the height of the kanzashi streak 5 is slightly above the ground, and the striking force is applied to the kanzashi streak 5. It is removed and, as shown in FIG. 4, it is lowered again to finish the insertion into the buried hole 1. After this insertion, the guide walls 7, 7 and the pedestals 8, 8 are removed, and the wide holes in which they are installed are backfilled.

【0015】継手部材4,4を有する鋼管杭3a,3
b,3cどうしの縦継ぎでは、それらの継手部材4,4
どうしの正しい位置合せが必要である。鋼管杭の縦継ぎ
が、上記下杭3a,3bにおけるように、地上で倒伏し
て行う場合には継手部材4,4の位置合せは容易にでき
る。しかし、埋設孔1に挿入された下杭3a,3bに対
し、上杭4Cを吊り下しにより接合させる場合は、杭の
芯合せばかりでなく、周方向の位置合せも要することに
なり、作業が面倒なものとなる。本発明では、このよう
な位置合せもの問題も併せ解決できるようにしている。
次に、その実施例について、図6〜図9も加えて説明す
る。
Steel pipe piles 3a, 3 having joint members 4, 4
In the vertical connection between b and 3c, those joint members 4, 4 are connected.
Correct alignment between them is necessary. When the vertical connection of the steel pipe piles is performed by lying down on the ground as in the lower piles 3a and 3b, the positioning of the joint members 4 and 4 can be easily performed. However, when joining the upper pile 4C to the lower piles 3a and 3b inserted in the burial hole 1 by suspending them, not only the centering of the piles but also the circumferential alignment is required. Would be a hassle. In the present invention, such a problem of alignment is also solved.
Next, the embodiment will be described with reference to FIGS. 6 to 9.

【0016】継手部材4,4を有する鋼管杭では、縦継
ぎにおける溶接の都合上、図5,図6にも示すように、
継手部材4,4は杭の端面より少し内方位置までの長さ
で設けられている。本発明では、下杭中の鋼管杭3bと
上杭3cの各接合端部の外周に、両継手部材4,4の中
間部に位置して、それぞれ位置合せ用の突起体10,10を
固着しておく。この場合、上下の突起体10,10が杭の軸
線方向に対向されるようになる。
In the steel pipe pile having the joint members 4 and 4, as shown in FIG. 5 and FIG.
The joint members 4 and 4 are provided with a length slightly inward from the end surface of the pile. In the present invention, the protrusions 10 and 10 for positioning are fixed to the outer circumferences of the joint ends of the steel pipe pile 3b and the upper pile 3c in the lower pile, which are located in the intermediate portions of the joint members 4 and 4, respectively. I'll do it. In this case, the upper and lower protrusions 10, 10 are opposed to each other in the axial direction of the pile.

【0017】他方、上記突起体10,10と関連してガイド
治具11を用意する。このガイド治具11は図9に示すよう
に、長下に長い板体で形成され、その下部には突起体10
と嵌合孔12が、また上部には、上開きとされた突起体10
の導入溝13が設けられており、導入溝13の下部には調整
ボルト14,14が導入溝13内に進退自在に設けられてい
る。
On the other hand, a guide jig 11 is prepared in association with the projections 10 and 10. As shown in FIG. 9, this guide jig 11 is formed of a long long plate, and a protrusion 10 is formed on the lower part thereof.
And a fitting hole 12, and an upper open projection 10 at the top.
Introducing groove 13 is provided, and adjusting bolts 14, 14 are provided in the lower part of the introducing groove 13 so as to be movable back and forth in the introducing groove 13.

【0018】下杭3a,3bを埋設孔1に挿入して孔内
に吊持し、上杭3cをクレーンで吊り上げ、降下させる
ようにするまでの作業はさきの実施例におけると同様で
ある(図1,図2,図5参照)。この場合、上杭3cを
降下させながら、上杭3cの継手部材4,4の位置が、
下杭の継手部材4,4の位置に大よそ合うようにさせ
る。その際、図6に示すように、下杭3bの突起体10に
ガイド治具11の嵌合孔12を嵌めて、ガイド治具11を突設
する。
The work from inserting the lower piles 3a and 3b into the embedding hole 1 and suspending them in the hole and lifting the upper pile 3c by a crane and lowering it is the same as in the previous embodiment ( (See FIGS. 1, 2 and 5). In this case, while lowering the upper pile 3c, the positions of the joint members 4 and 4 of the upper pile 3c are
The positions of the joint members 4 and 4 of the lower pile are roughly matched. At that time, as shown in FIG. 6, the fitting jig 12 of the guide jig 11 is fitted into the protrusion 10 of the lower pile 3b to project the guide jig 11.

【0019】そして、さらに上杭3cを降下させれば、
図7に示すように、上杭3cの突起体10は、ガイド治具
11の上開きされた導入溝13に誘導されて係合し、その状
態で上杭3cは下杭3a,3b上に接合、載置されるこ
とになる。この上杭と下杭が接合した際、それらの継手
部材4,4どうしが左右に合致されず若干ずれているこ
とがある。その場合には、ガイド治具11に設けた調整ボ
ルト14,14を進退させて、導入溝13内に係合された突起
体10の位置を横方向に移動させてやれば、上杭3cは突
起体10の移動にしたがって周方向に回動し、継手部材
4,4どうしの正しい位置合せができることになる。
If the upper pile 3c is further lowered,
As shown in FIG. 7, the protrusion 10 of the upper pile 3c is a guide jig.
The upper pile 3c is joined and placed on the lower piles 3a and 3b while being guided and engaged with the introduction groove 13 which is opened upward. When the upper pile and the lower pile are joined, the joint members 4 and 4 may not be aligned left and right, and may be slightly displaced. In that case, if the adjusting bolts 14 provided on the guide jig 11 are moved back and forth to move the position of the protrusion 10 engaged in the introduction groove 13 laterally, the upper pile 3c will be As the protrusion 10 moves, it rotates in the circumferential direction, so that the joint members 4 and 4 can be properly aligned.

【0020】上下両杭3a,3bの位置合せ終了後は、
それらの接合端を溶接して結合9し、その際ガイド治具
11は取り除かれる。また、上下両杭3c,3bの継手部
材4,4間には、継ぎ合せ材15,15(図7,図8参照)
も溶接により取付けられる。以後の行程については、さ
きの実施例の場合と同様である(図3,図4参照)か
ら、その説明は省略する。
After the alignment of the upper and lower piles 3a, 3b is completed,
The joint ends of these are welded and joined together9, and at that time a guide jig is used.
Eleven are removed. In addition, the joint members 15 and 15 are provided between the joint members 4 and 4 of the upper and lower piles 3c and 3b (see FIGS. 7 and 8).
Is also attached by welding. The subsequent steps are the same as in the case of the previous embodiment (see FIGS. 3 and 4), and the description thereof will be omitted.

【0021】[0021]

【発明の効果】以上説明したように、本発明によれば、
定尺の鋼管杭を継ぎ合せて埋設するにあたり、複数本の
杭を横継ぎして埋設孔に挿入、吊持した下杭に対し、鋼
管杭1本ないし2本を横継ぎした上杭を吊り下して縦継
ぎし、その鋼管杭全体を挿入、埋設するようにしたの
で、すべての杭を地上で横継ぎする従来法に比べ、工事
用の敷地が少なくてすむとともに、クレーンの大型化が
さけられ、施工を安全に能率よく行うことができる。ま
た、狭い市街地における長尺の杭の埋設が可能となる。
As described above, according to the present invention,
When burying fixed-size steel pipe piles by splicing together, multiple piles are horizontally spliced and inserted into the burial hole, and suspended from the suspended lower pile, one or two steel pipe piles are spliced horizontally to suspend the upper pile. Since the steel pipe piles are vertically inserted and the entire steel pipe piles are inserted and buried, compared to the conventional method in which all the piles are horizontally spliced on the ground, the construction site can be reduced and the crane can be made larger. The work can be avoided safely and efficiently. In addition, it is possible to bury long piles in a small urban area.

【0022】特に、請求項2の方法では、杭の吊り降し
による縦継ぎにおいて、特に位置合せが困難であった継
手部材を有する鋼管杭を用いた施工でも、継手部材どう
しの位置合せが確実、容易に能率よく行えることにな
り、工期の短縮が図れる。
In particular, according to the method of claim 2, in the vertical connection by suspending the piles, even if the steel pipe pile having the joint member, which is particularly difficult to align, is used for the construction, the alignment of the joint members can be surely performed. , It can be done easily and efficiently, and the construction period can be shortened.

【図面の簡単な説明】[Brief description of drawings]

【図1】本発明の一実施態を示したもので、下杭の挿入
状態を示す概略図である。
FIG. 1 is a schematic view showing an embodiment of the present invention, showing a state in which a lower pile is inserted.

【図2】同上杭の吊り降し状態を示す概略図である。FIG. 2 is a schematic view showing a suspended state of the pile.

【図3】同カンザシ筋除去の状態を示す概略図である。FIG. 3 is a schematic view showing a state in which the kanzaku muscle is removed.

【図4】同埋設終了の状態を示す概略図である。FIG. 4 is a schematic view showing a state in which the burial is completed.

【図5】図2の要部拡大正断面図である。5 is an enlarged front cross-sectional view of a main part of FIG.

【図6】ガイド治具を立設したところの同側断面図であ
る。
FIG. 6 is a sectional view of the same side where a guide jig is erected.

【図7】上下両杭をガイド治具を用いて接合したところ
の拡大側断面図である。
FIG. 7 is an enlarged side sectional view of the upper and lower piles joined together using a guide jig.

【図8】カンザシ筋の除去状態の拡大正断面図である。FIG. 8 is an enlarged front cross-sectional view showing a state in which the kanzashi muscle is removed.

【図9】ガイド治具の拡大正面図である。FIG. 9 is an enlarged front view of the guide jig.

【符号の説明】[Explanation of symbols]

1 埋設孔 3a,3b 鋼管杭(下杭) 3C 鋼管杭(上杭) 4 継手部材 5 カンザシ筋 7 ガイドウォール 8 受台 9 結合部 10 突起体 11 ガイド治具 12 嵌合孔 13 導入溝 14 調整ボルト 1 Buried hole 3a, 3b Steel pipe pile (lower pile) 3C Steel pipe pile (upper pile) 4 Joint member 5 Kanzashi muscle 7 Guide wall 8 Cradle 9 Joint part 10 Projection body 11 Guide jig 12 Fitting hole 13 Introduction groove 14 Adjustment bolt

───────────────────────────────────────────────────── フロントページの続き (72)発明者 廣瀬 智治 東京都中央区日本橋室町3−1−3 株式 会社クボタ東京本社内 (72)発明者 横山 陽一 東京都中央区日本橋室町3−1−3 株式 会社クボタ東京本社内 (72)発明者 江口 宏幸 千葉県市川市塩浜1−6 株式会社クボタ 市川工場内 ─────────────────────────────────────────────────── ─── Continuation of the front page (72) Inventor Tomoji Hirose 3-1-3 Nihonbashi Muromachi, Chuo-ku, Tokyo Stock company Kubota Tokyo headquarters (72) Inventor Yoichi Yokoyama 3-1-3 Nihonbashi-Muromachi, Chuo-ku, Tokyo Company Kubota Tokyo Head Office (72) Inventor Hiroyuki Eguchi 1-6 Shiohama, Ichikawa, Chiba Kubota Ichikawa factory

Claims (2)

【特許請求の範囲】[Claims] 【請求項1】 複数本の鋼管杭を地上で横継ぎして下杭
を形成し、この下杭を埋設孔に挿入して、その頭部を地
上に突出した状態で支持し、この下杭上に鋼管杭1本な
いし2本を横継ぎした上杭を吊り降ろして縦継ぎを行っ
た後、縦継ぎされた継手部材を有する鋼管杭全体を埋設
孔に挿入することを特徴とする、鋼管杭の縦継ぎ埋設工
法。
1. A lower pile is formed by horizontally connecting a plurality of steel pipe piles on the ground, and the lower pile is inserted into an embedding hole and supported with the head protruding above the ground. A steel pipe characterized by inserting an entire pile of a steel pipe having a joint member, which is vertically connected, after hanging an upper pile having one or two steel pipe piles horizontally spliced on top of the pile. Vertical pile construction method for piles.
【請求項2】 継手部材を有する鋼管杭の複数本を地上
で横継ぎして下杭を形成し、この下杭を埋設孔に挿入し
て、その頭部を地上に突出した状態で支持し、他方、こ
の下杭とこれに縦継ぎする上杭の接合端部に位置合せ用
の突起体を設け、下杭の突起体に嵌合してガイド治具を
立設した後、下杭上に鋼管杭1本ないし2本を横継ぎし
た上杭を吊り降ろして、その突起体をガイド治具に係入
して下杭に接合させ、縦継ぎを行った後、縦継ぎされた
継手部材を有する鋼管杭全体を埋設孔に挿入することを
特徴とする、鋼管杭の縦継ぎ埋設工法。
2. A plurality of steel pipe piles having joint members are laterally connected on the ground to form a lower pile, and the lower pile is inserted into an embedding hole and supported with the head protruding above the ground. , On the other hand, the lower pile and the upper pile vertically connected to the lower pile are provided with alignment projections, which are fitted to the projections of the lower pile and the guide jig is erected. The upper pile, which is one or two steel pipe piles horizontally spliced, is hung, the protrusions are engaged with the guide jig to be joined to the lower pile, and the vertical splicing is performed. A method of vertically burying steel pipe piles, characterized in that the entire steel pipe pile having the above is inserted into the burying hole.
JP27665595A 1995-09-29 1995-09-29 Longitudinal joint burying construction method for steel pipe pile Pending JPH0995939A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP27665595A JPH0995939A (en) 1995-09-29 1995-09-29 Longitudinal joint burying construction method for steel pipe pile

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP27665595A JPH0995939A (en) 1995-09-29 1995-09-29 Longitudinal joint burying construction method for steel pipe pile

Publications (1)

Publication Number Publication Date
JPH0995939A true JPH0995939A (en) 1997-04-08

Family

ID=17572485

Family Applications (1)

Application Number Title Priority Date Filing Date
JP27665595A Pending JPH0995939A (en) 1995-09-29 1995-09-29 Longitudinal joint burying construction method for steel pipe pile

Country Status (1)

Country Link
JP (1) JPH0995939A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2016108847A (en) * 2014-12-08 2016-06-20 大成建設株式会社 Steel pipe connection structure and formation method thereof

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2016108847A (en) * 2014-12-08 2016-06-20 大成建設株式会社 Steel pipe connection structure and formation method thereof

Similar Documents

Publication Publication Date Title
US4021979A (en) Aligning bracket for underground sectional precast concrete structures and method of assembly
KR102190480B1 (en) Implant pile pressing apparatus in architecture foundation system and a universal implant piling method
JPH0995939A (en) Longitudinal joint burying construction method for steel pipe pile
JP3029797B2 (en) Building horizontal restoration method and steel pipe pile joint
JP4958890B2 (en) A guide jig for alignment and a method of longitudinal joining of piles using them.
JP3031659B2 (en) Longitudinal joint method of steel pipe pile and positioning device used for the method
JP3731975B2 (en) Method and apparatus for positioning a steel pipe column when installing a plug-in type steel pipe column
JPH09100530A (en) Vertical jointing method for steel pipe pile having coupling member
JP3790310B2 (en) Construction method of the building by the prior construction of steel frame
JP2001279666A (en) Steel pipe erection and steel pipe erection/immersion method
JP2513983B2 (en) Installation method of vertical shaft inner wall having vertical shaft facility and vertical shaft inner wall having vertical shaft facility
JP4010492B2 (en) Column beam connection method in jackdown method of steel building
JP2755846B2 (en) Pile core alignment jig
JPH07292858A (en) Structure for connecting pc member
JP2011220009A (en) Erection method of permanent sub-substructural column
JPH0612011B2 (en) Coupling structure of steel pipe piles and rebar cages
JPH04366229A (en) Temporary corresponding standard used for method of reverse driving construction
JP2005098086A (en) Positioning guide fixture, pile installed with it, and method for vertically joining pile using them
JPH08338567A (en) Burying process for gas pipe line
JP2001241188A (en) Construction method for structure and provitional frame base
JPH09143984A (en) Vertical splicing method for steel pipe pile having joint member and guide jig for therefor
JP2023140927A (en) Construction method of underground structure and underground structure
JP2505595Y2 (en) Ground drill drill guide device
JP3126021B2 (en) Casing driver sole plate
JPH09255276A (en) Segment lifting tool