JP3029797B2 - Building horizontal restoration method and steel pipe pile joint - Google Patents
Building horizontal restoration method and steel pipe pile jointInfo
- Publication number
- JP3029797B2 JP3029797B2 JP8103505A JP10350596A JP3029797B2 JP 3029797 B2 JP3029797 B2 JP 3029797B2 JP 8103505 A JP8103505 A JP 8103505A JP 10350596 A JP10350596 A JP 10350596A JP 3029797 B2 JP3029797 B2 JP 3029797B2
- Authority
- JP
- Japan
- Prior art keywords
- pile
- foundation
- jack
- press
- screw
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Landscapes
- Piles And Underground Anchors (AREA)
Description
【0001】[0001]
【発明の属する技術分野】この発明は、住宅や中低層の
建物において、地盤沈下等によって基礎が不等沈下した
場合に、建物を水平に修復する建物水平修復工法、並び
にこれに用いる鋼管杭継手、単位杭、および反力取り治
具に関する。BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a horizontal restoration method for a house or a middle-to-low-rise building, in which the foundation is horizontally restored when the foundation is unequally settled due to land subsidence, etc. , Unit pile, and reaction force removal jig.
【0002】[0002]
【従来の技術】従来、住宅等の建物において、地震に伴
う地盤の沈下,液状化や、地盤の土質等によって基礎が
不等沈下した場合、建物を水平に修復する工法として、
土台ジャッキアップ工法と、アンダーピーニング工法と
が一般に採用されている。土台ジャッキアップ工法は、
比較的簡単な作業で済むが、沈下の程度が低い場合にし
か採用できず、また地盤が安定していることが必要であ
る。そのため、沈下程度が大きい場合や、地盤が不安定
な場合は、アンダーピーニング工法が採用される。アン
ダーピーニング工法は、図10に示すように、基礎50
の下面に達する穴51を、地盤52に基礎50の近傍か
ら掘削し、油圧ジャッキ53を基礎50の下面に配置し
て基礎50を反力に鋼管杭54を圧入する方法である。2. Description of the Related Art Conventionally, in a building such as a house, when the foundation is unevenly settled due to the subsidence and liquefaction of the ground due to an earthquake, or the soil of the ground, etc., as a method of repairing the building horizontally,
The base jack-up method and the underpeening method are generally adopted. The foundation jack-up method is
Although relatively simple work is required, it can be adopted only when the degree of settlement is low, and the ground must be stable. Therefore, when the degree of settlement is large or the ground is unstable, the underpeening method is adopted. As shown in FIG.
A hole 51 reaching the lower surface of the base 50 is excavated from the vicinity of the foundation 50 in the ground 52, a hydraulic jack 53 is arranged on the lower surface of the foundation 50, and the steel pipe pile 54 is pressed into the base 50 as a reaction force.
【0003】[0003]
【発明が解決しようとする課題】しかし、基礎50の直
下に杭54を配置するため、必要長さとなるまで、短い
単位杭を何本も継いで行く必要があり、作業効率が悪
い。また、その単位杭間の継手には溶接継手が用いられ
ているが、作業スペースを確保するために基礎50の下
方に穴51を大きく掘らなくてはならず、しかも十分な
溶接姿勢を取ることが難しく、溶接品質の安定について
も問題が残る。前記のように穴51を大きく掘削するこ
とが必要なことから、掘削に手間がかかり、重機の使用
が必要となるうえ、狭小地等では土の搬出入にも手間が
かかる。また、大きく掘った穴51内を基礎50の下ま
で作業者55が入って作業を行うことが必要となるた
め、安全性にも問題がある。土が崩れ易いような場合
は、土留め等が必要となって一層手間がかかる。なお、
単位杭の継手部の品質安定化のため、ねじ継手とするこ
とも考えられるが、鋼管からなる単位杭にねじ溝を切る
と、その部分の肉厚が薄くなって強度が低下するため、
杭全体を厚肉にする必要があり、コスト高になる。However, since the piles 54 are arranged directly below the foundation 50, it is necessary to connect a number of short unit piles until the required length is reached, and the working efficiency is poor. In addition, a welded joint is used as a joint between the unit piles. However, in order to secure a working space, a large hole 51 must be dug below the foundation 50, and a sufficient welding posture must be taken. Is difficult, and there is still a problem with the stability of welding quality. Since it is necessary to excavate the large hole 51 as described above, it takes time and effort to excavate, and heavy machinery is required. In addition, it takes time and effort to carry in and out the soil on a small land. Further, since it is necessary for the worker 55 to enter the hole 51 largely dug to the bottom of the base 50 to perform the work, there is a problem in safety. In the case where the soil is likely to collapse, earth retaining and the like are required, which further increases the work. In addition,
To stabilize the quality of the joint part of the unit pile, a threaded joint may be considered.However, if a thread groove is cut into a unit pile made of steel pipe, the thickness of that part will be reduced and the strength will decrease.
It is necessary to make the whole pile thick, which increases the cost.
【0004】この発明は、上記の課題を解消するもので
あり、掘削量が少なくて済み、また単位杭を長くするこ
とができて効率が良く、作業も安全に行える建物水平修
復工法を提供することを目的とする。この発明の他の目
的は、単位杭の継手部の品質の安定が図れる建物水平修
復工法、鋼管杭継手、および単位杭を提供することであ
る。この発明のさらに他の目的は、この発明の工法に効
果的に使用できる反力取り治具を提供することである。SUMMARY OF THE INVENTION The present invention solves the above-mentioned problems, and provides a method for rehabilitating a horizontal building, which requires a small amount of excavation, can lengthen unit piles, is efficient, and can perform work safely. The purpose is to: Another object of the present invention is to provide a horizontal restoration method for a building, a steel pipe pile joint, and a unit pile capable of stabilizing the quality of the joint portion of the unit pile. Still another object of the present invention is to provide a reaction force removing jig which can be effectively used in the method of the present invention.
【0005】[0005]
【課題を解決するための手段】この発明の建物水平修復
工法は、建物の基礎の立ち上がり部の側面に反力取り治
具を取付け、この反力取り治具で支えられるジャッキに
より、前記基礎の近傍の地盤に杭を圧入する工法であ
る。前記杭は複数本の単位杭を継いだものとしても良
い。その場合、下方の単位杭を地盤にある程度圧入した
後、上方の単位杭を下方の単位杭に継ぎ、この継がれた
杭を再度ジャッキで圧入する。この工法によると、杭は
基礎の直下ではなく近傍に打ち込むため、基礎が打ち込
みの邪魔とならない。そのため、単位杭の長さを長くす
ることができ、必要長の杭打ちを行うにつき、効率的に
作業が行える。単位杭に分けずに、1本の連続した杭を
用いることも可能となる。また、基礎の立ち上がり部の
側面に反力取り治具を取付け、杭の圧入の反力を得るた
め、地盤を大きく掘削する必要がない。そのため、掘削
に手間がかからず、狭小地等で問題となる土の搬出入も
少なくて済む。また、土留めも不要で、安全に作業が行
える。これらのため、重機も不要で、杭を建物の内部側
に配置する場合にも、掘削作業等のために建物の床面を
除去する範囲が小さくて済み、床下での作業とすること
もできる。この工法において、基礎が立ち上がり部より
も広がったベース部を有する場合に、前記ベース部の一
部に「はつり部」を設け、このはつり部に、地盤に圧入
する杭を配置しても良い。このようにはつり部を設ける
ことで、杭を基礎芯に近づけて配置することができ、杭
に偏心荷重が作用するすることが緩和されて、堅固な構
造とできる。単位杭は、例えば鋼管杭とし、端部に単位
杭間の接合用のねじ部を有するものとする。このよう
に、ねじ部による機械継手とすることにより、溶接継手
に比べて継手の品質が安定する。また、単位杭を溶接継
手で接合する場合も、基礎の横での作業となるため、作
業スペースが得易く、十分な溶接姿勢がとれて、継手の
品質が安定する。In the horizontal restoration method of a building according to the present invention, a reaction force removing jig is attached to a side surface of a rising portion of a foundation of a building, and a jack supported by the reaction force removing device is used to fix the foundation. This is a method of pressing a pile into the nearby ground. The pile may be formed by connecting a plurality of unit piles. In this case, after the lower unit pile is pressed into the ground to some extent, the upper unit pile is connected to the lower unit pile, and the connected pile is pressed again with the jack. According to this method, the pile is driven into the vicinity instead of directly below the foundation, so that the foundation does not hinder the driving. Therefore, the length of the unit pile can be lengthened, and the work can be efficiently performed when the pile of the required length is driven. It is also possible to use one continuous pile without dividing it into unit piles. In addition, it is not necessary to excavate the ground greatly because a reaction force removing jig is attached to the side surface of the rising portion of the foundation to obtain the reaction force of press-fitting the pile. For this reason, excavation does not require much work, and there is little need to carry in and out soil, which is a problem in narrow land. In addition, it does not require earth retaining, making it possible to work safely. For these reasons, no heavy equipment is required, and even when arranging the piles inside the building, the area for removing the floor of the building for excavation work or the like can be small, and work can be performed under the floor. . In this method, when the foundation has a base portion that is wider than the rising portion, a “hanging portion” may be provided on a part of the base portion, and a pile that is pressed into the ground may be disposed on the hanging portion. By providing the hanging portion in this manner, the pile can be arranged close to the foundation core, and the eccentric load acting on the pile is reduced, and a solid structure can be obtained. The unit pile is, for example, a steel pipe pile and has a threaded portion at the end for joining between the unit piles. Thus, the quality of the joint is stabilized as compared with the welded joint by using the mechanical joint by the threaded portion. Also, when unit piles are joined by welding joints, work is performed beside the foundation, so that a work space is easily obtained, a sufficient welding posture is obtained, and the quality of the joints is stabilized.
【0006】このように圧入した杭の建物水平修復への
利用は、大別して、例えば次の2種類の方法で行える。
第1の方法は、杭の圧入完了後、この杭の支持力を基礎
に伝える基礎受部材を前記杭に取付け、基礎の天端面に
コンクリートを打ち継ぐ方法である。基礎受部材は、杭
に溶接されて基礎の下面を受けるブラケットであっても
良く、また基礎の立ち上がり部等に取付けられるもので
あっても良い。このように、天端面にコンクリートを打
ち継いで基礎を嵩上げする場合、基礎を持ち上げること
を要しないので、ジャッキも杭の圧入に必要な程度の加
圧力のもので済み、杭の本数や打ち込み深さも基礎補強
に必要な程度で足り、簡単な工事で済む。そのため、基
礎の不等沈下が生じた建物を、杭で基礎補強して非常に
簡単に水平修復できる。第2の方法は、圧入された杭で
反力を得て、圧入過程、または圧入後、または圧入過程
および圧入後の両方の過程で、建物の基礎をジャッキで
上昇させる方法である。この場合、基礎の複数箇所を同
時にジャッキで上昇させることが必要である。前記杭は
基礎芯から外れて配置されるため、偏心荷重が杭に作用
することになってジャッキによる持ち上げは難しいが、
不等沈下した基礎の状態や、地盤の状況等によっては、
このような基礎のジャッキアップによっても建物の水平
修復が可能である。[0006] The use of the press-fitted piles for horizontal restoration of a building can be roughly divided into, for example, the following two methods.
A first method is a method in which after the press-fitting of the pile is completed, a foundation receiving member for transmitting the supporting force of the pile to the foundation is attached to the pile, and concrete is connected to the top end face of the foundation. The foundation receiving member may be a bracket that is welded to the pile to receive the lower surface of the foundation, or may be a member that is attached to a rising portion of the foundation. In this way, when raising the foundation by joining concrete to the top end face, it is not necessary to lift the foundation, so the jack only needs to have the pressing force necessary for press-fitting the pile, and the number of piles and the driving depth Also, it is enough to reinforce the foundation, and simple construction is enough. Therefore, a building in which uneven settlement of the foundation has occurred can be very easily rehabilitated horizontally by reinforcing the foundation with piles. The second method is a method in which a reaction force is obtained by a press-fitted pile, and the foundation of the building is jacked up during the press-fitting process, or after the press-fitting, or during both the press-fitting process and the press-fitting process. In this case, it is necessary to jack up several places of the foundation at the same time. Since the pile is displaced from the foundation core, an eccentric load acts on the pile and it is difficult to lift with a jack,
Depending on the condition of the sunk foundation, the condition of the ground, etc.
Horizontal restoration of a building is possible by jacking up such a foundation.
【0007】この発明の鋼管杭継手は、雌ねじ側継手部
材と雄ねじ側継手部材とでなる。雌ねじ側継手部材は、
内径面に雌ねじが形成された鋼管製のねじ筒と、このね
じ筒に一部が内嵌して固定されて前記ねじ筒の基端から
突出した短筒状の裏当て金とからなる。雄ねじ側継手部
材は、外径面に雄ねじが形成された鋼管製のねじ筒と、
このねじ筒に一部が内嵌して固定されて前記ねじ筒の基
端から突出した短筒状の裏当て金とからなる。これら雌
ねじ側継手部材および雄ねじ側継手部材は、各々鋼管製
の単位杭本体の端部に前記裏当て金を嵌入して前記ねじ
筒と単位杭本体との間を溶接する。また、この発明の単
位杭は、鋼管製の単位杭本体の両端に雌ねじ側継手部材
と雄ねじ側継手部材とを設けたものであって、次の構成
とする。前記雌ねじ側継手部材は、内径面に雌ねじが形
成された鋼管製のねじ筒と、このねじ筒に一部が内嵌し
て固定されて前記ねじ筒の基端から突出した短筒状の裏
当て金とからなる。前記雄ねじ側継手部材は、外径面に
雄ねじが形成された鋼管製のねじ筒と、このねじ筒に一
部が内嵌して固定されて前記ねじ筒の基端から突出した
短筒状の裏当て金とからなる。前記雌ねじ側継手部材お
よび雄ねじ側継手部材のねじ筒は前記単位杭本体よりも
管壁の肉厚が厚いものとする。これら雌ねじ側継手部材
および雄ねじ側継手部材は、各々前記単位杭本体の端部
に前記裏当て金を挿入してねじ筒と単位杭本体との間を
溶接する。この構成の鋼管杭継手や単位杭の場合、鋼管
からなる単位杭本体と別体の雌ねじ側継手部材および雄
ねじ側継手部材を用いるため、単位杭本体の管壁をねじ
溝の形成のために厚くすることが不要で、杭として必要
な厚みとすれば良く、単位杭を安価なものにできる。ま
た、各継手部材に構造用鋼管等の堅固な材質のものを使
用することも可能で、堅固な継手となる。各継手部材は
短い部材であるため、取扱が簡単で、ねじ溝の形成や裏
当て金の溶接等が簡単に行える。このように、予めねじ
溝を設けた雌ねじ側継手部材および雄ねじ側継手部材を
一対の部品として準備しておくことで、ねじ式継手を有
する単位杭を簡単に製造することができる。[0007] The steel pipe pile joint of the present invention comprises a female screw side joint member and a male screw side joint member. The female screw side joint member is
It comprises a screw tube made of steel pipe with an internal thread formed on the inner diameter surface, and a short tube-shaped backing metal partly fitted and fixed in the screw tube and protruding from the base end of the screw tube. The external thread side joint member is a steel pipe screw cylinder having an external thread formed on the outer diameter surface,
A short cylindrical backing metal partly fitted into and fixed to the screw cylinder and protruding from the base end of the screw cylinder. Each of the female screw side joint member and the male screw side joint member fits the backing metal into an end of a steel pipe unit pile main body and welds the screw cylinder to the unit pile main body. Further, the unit pile according to the present invention has a female thread side joint member and a male thread side joint member provided at both ends of a steel pipe unit pile main body, and has the following configuration. The female screw-side joint member includes a screw pipe made of a steel pipe having an internal thread formed on an inner diameter surface thereof, and a short cylindrical back which is partially fitted and fixed to the screw pipe and protrudes from a base end of the screw pipe. It consists of a deposit. The male screw-side joint member is a steel pipe screw cylinder having an external thread formed on an outer diameter surface, and a short cylindrical shape partly fitted and fixed to the screw cylinder and protruding from a base end of the screw cylinder. It consists of backing money. The screw cylinders of the female screw side joint member and the male screw side joint member have a pipe wall thicker than the unit pile main body. In each of the female screw side joint member and the male screw side joint member, the backing metal is inserted into the end of the unit pile main body to weld between the screw cylinder and the unit pile main body. In the case of a steel pipe pile joint or unit pile of this configuration, since the female thread side joint member and the male screw side joint member which are separate from the unit pile body made of steel pipe are used, the pipe wall of the unit pile body is thickened to form a thread groove. It is not necessary to perform the operation, and it is sufficient that the pile has the necessary thickness, and the unit pile can be made inexpensive. Further, it is also possible to use a solid material such as a structural steel pipe for each joint member, and a solid joint is obtained. Since each joint member is a short member, it is easy to handle and can easily form a thread groove, weld a backing metal, and the like. In this way, by preparing the female screw side joint member and the male screw side joint member provided with the thread grooves in advance as a pair of components, a unit pile having a screw type joint can be easily manufactured.
【0008】この発明の反力取り治具は、基礎の立ち上
がり部の側面に取付けられる基礎側部材と、杭圧入用の
ジャッキの受け部を上部に有するジャッキ側部材とを有
し、前記基礎側部材に対してジャッキ側部材を上下に取
付位置変更可能に取付ける結合機構を設けたものであ
る。この治具によれば、この発明の水平修復工法で杭を
圧入するにつき、ジャッキで杭をある程度圧入した後、
反力取り治具のジャッキ側部材の取付位置を下方に変更
し、前記ジャッキによる圧入を再度行うことができる。
このように、反力取り治具のジャッキ側部材の位置を可
変とすることで、ジャッキのストロークが短くても、長
い単位杭を圧入することができる。[0008] The reaction force removing jig of the present invention includes a foundation member attached to a side surface of a rising portion of a foundation, and a jack member having a receiving portion of a jack for press-fitting a pile at an upper portion. A connecting mechanism is provided for mounting the jack-side member up and down so that the mounting position can be changed with respect to the member. According to this jig, when the pile is pressed in by the horizontal restoration method of the present invention, after the jack is pressed into the pile to some extent,
The mounting position of the jack member on the reaction force removing jig can be changed downward, and press-fitting by the jack can be performed again.
Thus, by making the position of the jack-side member of the reaction force removing jig variable, a long unit pile can be press-fitted even if the stroke of the jack is short.
【0009】[0009]
【発明の実施の形態】この発明の一実施形態を図面と共
に説明する。この建物水平修復工法は、建物1の基礎2
の立ち上がり部2aの側面に反力取り治具3を取付け、
この反力取り治具3で支えられるジャッキ4により、基
礎2の近傍の地盤5に杭6を圧入する方法である。基礎
2の天端面には土台(図示せず)を介して外壁7が設置
されている。この実施形態では、建物1は住宅であり、
基礎2は図8に平面図で一部を示す建物外周の布基礎で
ある。この布基礎2における沈下側の辺の複数箇所に、
前記反力取り治具3を取付け、杭6を打つ。なお、同図
の内部基礎となる独立基礎2Aや内部布基礎2Bにも、
外周の布基礎2と同様にこの発明を適用できる。また、
基礎2に対して、反力取り治具3は、この例では建物1
の内側に取付けているが、図9の例のように建物外側の
面に取付けても良い。An embodiment of the present invention will be described with reference to the drawings. This horizontal restoration method of building is based on the foundation 2 of building 1.
The reaction force removal jig 3 is attached to the side of the rising portion 2a of
In this method, the pile 6 is pressed into the ground 5 near the foundation 2 by the jack 4 supported by the reaction force removing jig 3. An outer wall 7 is installed on a top end surface of the foundation 2 via a base (not shown). In this embodiment, building 1 is a house,
The foundation 2 is a cloth foundation around the building, a part of which is shown in a plan view in FIG. At a plurality of locations on the settling side of the cloth foundation 2,
The reaction force removal jig 3 is attached, and the pile 6 is hit. In addition, in the independent foundation 2A and the internal cloth foundation 2B which are the internal foundations in FIG.
The present invention can be applied similarly to the outer fabric base 2. Also,
The reaction force removing jig 3 is, in this example, the building 1 with respect to the foundation 2.
However, it may be mounted on the outer surface of the building as in the example of FIG.
【0010】図1に示すように、反力取り治具3は、各
々鋼製とした基礎側部材8とジャッキ側部材9とでな
る。基礎側部材8は、基礎2a内に埋まるアンカー11
により、上下複数箇所で基礎2の側面に取付けられる。
アンカー11は、硬化性の薬剤等のケミカル式のもので
あっても、貫通ボルト、または打ち込み式のものであっ
ても良く、基礎側部材8の板状部の取付孔21に挿通さ
れる。ジャッキ側部材9は、側面形状が逆L字状に形成
され、その上片部がジャッキ4の受け部9aとなる。ジ
ャッキ4は油圧ジャッキからなり、ボルト・ナットで受
け部9aの下面に下向きに取付けられる。前記基礎側部
材8とジャッキ側部材9とは、結合機構10により、相
互に上下に位置を変更して取付可能とされる。As shown in FIG. 1, the reaction force removing jig 3 includes a base member 8 and a jack member 9 each made of steel. The foundation side member 8 includes an anchor 11 embedded in the foundation 2a.
Thereby, it is attached to the side surface of the foundation 2 at a plurality of upper and lower locations.
The anchor 11 may be a chemical type such as a hardening agent, a through bolt, or a driving type, and is inserted into the mounting hole 21 of the plate-shaped portion of the base member 8. The side surface of the jack-side member 9 is formed in an inverted L-shape, and an upper piece thereof serves as a receiving portion 9 a of the jack 4. The jack 4 is composed of a hydraulic jack, and is attached downward to the lower surface of the receiving portion 9a with bolts and nuts. The base-side member 8 and the jack-side member 9 can be attached to each other by vertically changing their positions by a coupling mechanism 10.
【0011】結合機構10は、基礎側部材8に設けられ
てジャッキ側部材9を上下にスライド自在に支持する左
右一対のガイド部8aと、基礎側部材8に上下に並べて
設けられてボルト12を差し替え可能なボルト挿通孔1
3とで構成される。ボルト12は、ジャッキ側部材9に
貫通させたものであり、上下の複数箇所に配置される。
なお、結合機構10は、同図の構成のものに限らず、基
礎側部材8に対してジャッキ側部材9を上下に取付位置
変更可能とし、その各変更位置で両者8,9を堅固に固
定状態とできるものであれば良い。The coupling mechanism 10 includes a pair of left and right guide portions 8a provided on the base member 8 for supporting the jack member 9 so as to be slidable up and down. Replaceable bolt insertion hole 1
And 3. The bolts 12 penetrate the jack-side member 9 and are arranged at a plurality of upper and lower locations.
The coupling mechanism 10 is not limited to the one shown in the drawing, but can change the mounting position of the jack-side member 9 with respect to the base-side member 8 up and down, and firmly fixes the two 8, 9 at each changed position. Anything that can be in a state is acceptable.
【0012】杭6は、鋼管杭からなるものであって、複
数本の単位杭6aを鋼管杭継手14で継いだものとして
ある。図5に示すように、鋼管杭継手14は、雌ねじ側
継手部材15と雄ねじ側継手部材16とでなる。雌ねじ
側継手部材15は、内径面に雌ねじが形成された鋼管製
のねじ筒15aと、このねじ筒15aに一部が内嵌して
ねじ筒15aの基端から突出した短筒状の裏当て金15
bとからなる。雄ねじ側継手部材16は、外径面に雄ね
じが形成された鋼管製のねじ筒16aと、このねじ筒1
6aに一部が内嵌してねじ筒16aの基端から突出した
短筒状の裏当て金16bとからなる。各ねじ筒15a,
16aには構造用鋼管(STK)を使用し、各裏当て金
15b,16bは、局部的な隅肉溶接17により周方向
の複数箇所(例えば4箇所)で各ねじ筒15a,16a
に溶接してある。各ねじ溝は、例えば矩形ねじとしてあ
る。また、各ねじ筒15a,16aの基端側の端面18
は溶接用の開先の形成のため、内径側が細くなる45°
程度の勾配を持つテーパ面としてある。The pile 6 is made of a steel pipe pile, and a plurality of unit piles 6 a are connected by a steel pipe pile joint 14. As shown in FIG. 5, the steel pipe pile joint 14 includes a female screw side joint member 15 and a male screw side joint member 16. The female screw side joint member 15 is a steel pipe screw cylinder 15a having an internal thread formed on the inner diameter surface, and a short cylindrical backing part partially fitted into the screw cylinder 15a and protruding from the base end of the screw cylinder 15a. Money 15
b. The male screw side joint member 16 includes a steel pipe screw cylinder 16 a having an external thread formed on an outer diameter surface, and a screw cylinder 1.
6a, a short cylindrical backing metal 16b partially fitted inside and protruding from the base end of the screw cylinder 16a. Each screw cylinder 15a,
Structural steel pipe (STK) is used for 16a, and each backing metal 15b, 16b is screwed to each screw cylinder 15a, 16a at a plurality of locations (for example, four locations) in the circumferential direction by local fillet welding 17.
Welded to. Each screw groove is, for example, a rectangular screw. Further, the end face 18 on the base end side of each of the screw cylinders 15a and 16a.
Is 45 ° whose inner diameter is narrower to form a groove for welding
It has a tapered surface with a slight gradient.
【0013】これら雌ねじ側継手部材15および雄ねじ
側継手部材16は、各々鋼管製の単位杭本体6aaの端
部に裏当て金15b,16bを内嵌させ、ねじ筒15
a,16aの端面と単位杭本体6aaとの間に形成され
る開先で、突き合わせ溶接等の溶接19により接合す
る。この溶接19は、杭打ち作業の前に、単位杭本体6
aaに予め工場等で行っておく。図5(B)のように、
単位杭本体6aaの一端に雌ねじ側継手部材15を、他
端に雄ねじ側継手部材16を各々溶接することで、単位
杭6aが構成される。単位杭本体6aaは、ねじ筒15
a,16aと同じ管径(外径が同じ径)とすることが好
ましいが、単位杭本体6aaの管壁の肉厚t1は、同図
のようにねじ筒15a,16aよりも薄くしても良く、
また図5(C)のように同じ肉厚としても良い。寸法例
を示すと、ねじ筒15a,16aの管径が120〜14
0mm、肉厚が6mmの場合に、単位杭本体6aの管壁の肉
厚を3.2mmまたは4.8mmまたは6mmとしてある。単
位杭本体6aaをねじ筒15a,16aと同じ管径(外
径)として肉厚を薄くした場合、裏当て金15b,16
bは、外径が単位杭本体6aaおよびねじ筒15a,1
6aの内径に略合致するように段差をもつものとする。
この段差は、裏当て金15b,16bとなる鋼管を部分
絞り加工することで得られる。The female screw side joint member 15 and the male screw side joint member 16 are each fitted with a backing metal 15b, 16b at the end of a unit pile main body 6aa made of a steel pipe.
A groove formed between the end faces of the a and 16a and the unit pile main body 6aa is joined by welding 19 such as butt welding. This welding 19 is carried out before the pile driving operation.
aa is performed in a factory or the like in advance. As shown in FIG.
The unit pile 6a is formed by welding the female screw side joint member 15 to one end of the unit pile main body 6aa and the male screw side joint member 16 to the other end. The unit pile body 6aa is a screw cylinder 15
Although it is preferable that the pipe diameter is the same as the pipe diameters a and 16a (the outer diameter is the same), even if the wall thickness t1 of the pipe wall of the unit pile main body 6aa is thinner than the screw cylinders 15a and 16a as shown in FIG. well,
The thickness may be the same as shown in FIG. If the dimension example is shown, the pipe | tube diameter of the screw cylinder 15a, 16a is 120-14.
When the thickness is 0 mm and the wall thickness is 6 mm, the wall thickness of the pipe wall of the unit pile main body 6a is set to 3.2 mm, 4.8 mm, or 6 mm. When the unit pile main body 6aa is made thinner with the same pipe diameter (outer diameter) as the screw cylinders 15a and 16a,
b is an outer diameter of the unit pile main body 6aa and the screw cylinders 15a, 1b.
It is assumed that there is a step so as to substantially match the inner diameter of 6a.
This step is obtained by partially drawing a steel pipe to be the backing metal 15b, 16b.
【0014】次に、この建物水平修復工法の手順を図2
および図3と共に説明する。図2(A)に示す基礎2が
沈下部分である場合、基礎2の屋内側または屋外側にお
ける近傍部分の地盤5を若干掘り(同図(B))、その
側面に反力取り治具3をアンカー11で取付ける。ジャ
ッキ4は反力取り治具3のジャッキ側部材9に取付けて
おき、ジャッキ側部材9は、基礎側部材8に対する最も
上方位置に取付ける。この状態で、ジャッキ4の下方に
杭6の単位杭6aを配置する。このとき、地盤5が同図
(B)のように掘削してあると、その分、長い単位杭6
aが使用できる。なお、地盤5は必ずしも掘削しなくて
も良く、また掘削する場合も、杭6の周囲だけで良い。
また、この掘削穴22は、後に基礎2の下にブラケット
形式の基礎受部材23(図3)を配置する場合は、その
配置が可能な程度の大きさとしておく。このように準備
した後、ジャッキ4で単位杭6aを地盤5に圧入する
(D)。圧入の反力は、反力取り治具3を介して基礎2
で得られる。ジャッキ4を例えばストローク端まで伸長
させた後、図2(E)のようにジャッキ4を短縮させて
ジャッキ側部材9の基礎側部材8に対する取付位置を下
方に変更し、再度ジャッキ4を伸長させて単位杭6aを
圧入する。このようなジャッキ4による圧入と、ジャッ
キ側部材9の取付位置変更とを繰り返す。Next, the procedure of this building horizontal restoration method is shown in FIG.
And FIG. In the case where the foundation 2 shown in FIG. 2A is a subsidence portion, the ground 5 near the indoor or outdoor side of the foundation 2 is slightly dug (FIG. 2B), and a reaction force removing jig 3 is provided on the side surface. Is attached with the anchor 11. The jack 4 is attached to the jack-side member 9 of the reaction force removing jig 3, and the jack-side member 9 is attached to the uppermost position with respect to the base-side member 8. In this state, the unit pile 6a of the pile 6 is arranged below the jack 4. At this time, if the ground 5 is excavated as shown in FIG.
a can be used. In addition, the ground 5 does not necessarily need to be excavated, and when excavating, only the periphery of the pile 6 is sufficient.
In the case where a bracket-type foundation receiving member 23 (FIG. 3) is to be arranged below the foundation 2 later, the excavation hole 22 has a size that allows the arrangement. After such preparation, the unit pile 6a is pressed into the ground 5 with the jack 4 (D). The reaction force of the press-fitting is applied to the foundation 2 via the reaction force removal jig 3.
Is obtained. After extending the jack 4 to the stroke end, for example, as shown in FIG. 2E, the jack 4 is shortened to change the mounting position of the jack side member 9 to the base side member 8 downward, and the jack 4 is extended again. Press the unit pile 6a. The press-fitting by the jack 4 and the change of the mounting position of the jack-side member 9 are repeated.
【0015】単位杭6aが地盤5にある程度圧入される
と(F)、ジャッキ側部材9の基礎側部材8に対する取
付位置を上端位置に戻し(G)、圧入状態の単位杭6a
に次の単位杭6aを、その鋼管杭継手14のねじ込みに
よって継ぐ。このとき、ジャッキ4の下面と上側の単位
杭6aとの間に高さの余裕があれば、ジャッキ側部材9
を基礎側部材8に対して取り外してしまうことなく、上
方へスライドさせて再度ねじ締めを行うことで上側単位
杭6aのねじ込みが行える。When the unit pile 6a is pressed into the ground 5 to some extent (F), the mounting position of the jack-side member 9 to the foundation-side member 8 is returned to the upper end position (G), and the unit pile 6a in the press-fitted state is returned.
Then, the next unit pile 6a is connected by screwing the steel pipe pile joint 14. At this time, if there is sufficient height between the lower surface of the jack 4 and the upper unit pile 6a, the jack-side member 9
The upper unit pile 6a can be screwed in by sliding upward and screwing again without removing the base unit 8 from the base side member 8.
【0016】このように単位杭6aを継いだ後、ジャッ
キ4で杭6を再度圧入し、ジャッキ4による圧入と、ジ
ャッキ側部材9の取付位置変更とを繰り返す。このよう
にして、単位杭6aを任意本数継いで必要長の杭6を地
盤に圧入する。杭6の圧入が完了すると、反力取り治具
3を基礎2から取り外し、図3(A)のように基礎2の
下面に接する高さで杭6に基礎受部材23を溶接する。
基礎受部材23は、この例では、図4に示すように縦方
向の杭接合材23aと、水平な基礎受材23bと、斜材
23cとで三角形状に溶接枠組みしたブラケット形式の
ものとし、その三角形内には補強板(図示せず)を溶接
してある。杭接合材23aには溝形鋼を外向きに用い、
各種の径の単位杭6aに対応して両フランジで溶接可能
としてある。基礎受材23bおよび斜材23cは、溝形
鋼やH形鋼等の形鋼からなる。なお、図4の例では、基
礎2のベース部2bに、はつり部24を設け、はつり部
24内に杭6を配置することで、杭6を基礎芯に近づけ
ている。After the unit piles 6a are joined in this way, the piles 6 are press-fitted with the jacks 4 again, and the press-fitting by the jacks 4 and the change of the mounting position of the jack-side member 9 are repeated. In this manner, the required number of unit piles 6a are spliced into the ground by connecting an arbitrary number of them. When the press-fitting of the pile 6 is completed, the reaction force removing jig 3 is removed from the foundation 2, and the foundation receiving member 23 is welded to the pile 6 at a height in contact with the lower surface of the foundation 2 as shown in FIG.
In this example, the base receiving member 23 is of a bracket type in which a vertical pile connecting member 23a, a horizontal base receiving member 23b, and a diagonal member 23c are welded in a triangular shape as shown in FIG. A reinforcing plate (not shown) is welded within the triangle. For the pile connection material 23a, channel steel is used outward,
Welding is possible on both flanges corresponding to unit piles 6a of various diameters. The base receiving member 23b and the diagonal member 23c are formed of a section steel such as a channel steel or an H-section steel. In the example of FIG. 4, the hanging portion 24 is provided on the base portion 2 b of the foundation 2, and the pile 6 is disposed in the hanging portion 24, so that the pile 6 is brought closer to the foundation core.
【0017】このように基礎受部材23を杭6に溶接し
た後、基礎2の天端面に打ち継ぎ部2cとなるコンクリ
ートを打ち継いで基礎2の全体の天端面を均一にする。
また、基礎受部材23および杭6の上端付近が埋まるよ
うに、掘削穴22にコンクリート2dを打設する(図3
(B))。この後、基礎2のベース部2bの上方を土砂
で埋め戻す。前記の基礎コンクリートの打ち継ぎに際し
ては、基礎2の沈下部分につき、予め土台ジャッキアッ
プ工法等で建物1の基礎2よりも上方の部分を持ち上げ
ておく。After the foundation receiving member 23 is welded to the pile 6 in this manner, concrete serving as a joint 2c is joined to the top end surface of the foundation 2 to make the entire top end surface of the foundation 2 uniform.
Also, concrete 2d is poured into the excavation hole 22 so that the vicinity of the upper end of the foundation receiving member 23 and the pile 6 is filled (FIG. 3).
(B)). Thereafter, the upper part of the base 2b of the foundation 2 is backfilled with earth and sand. At the time of the jointing of the foundation concrete, a portion above the foundation 2 of the building 1 is previously lifted by the foundation jack-up method or the like for the subsidence portion of the foundation 2.
【0018】このようにして、基礎2の沈下部を杭6で
補強し、土台ジャッキアップ工法で建物1を水平に修復
することができる。なお、前記のジャッキ4による杭6
の圧入に際しては、ある程度圧入した後、ジャッキ4を
短縮状態に戻し、図4(B)に示すように単位杭6aと
ジャッキ4との間にダミー杭25を介在させて圧入を再
度行っても良い。このようにダミー杭24を使用するこ
とで、ジャッキ4のストローク不足を補い、長い単位杭
6aの圧入が可能となる。ダミー杭25は、各種の長さ
のものを準備し、順次取り替えるようにしても良い。こ
れにより、一層長い単位杭6aの圧入が可能となる。ダ
ミー杭25は、下端の外径が段付き軸状となったものと
し、その小径端25aを単位杭6aの上端に嵌入させて
芯ずれを防止する。ダミー杭25を使用する場合、反力
取り治具3は上下スライド式のものとしなくても済む。In this way, the subsidence of the foundation 2 is reinforced by the pile 6, and the building 1 can be horizontally restored by the foundation jack-up method. In addition, the pile 6 by the jack 4 is used.
At the time of press-fitting, the jack 4 may be returned to the shortened state after press-fitting to some extent, and the press-fitting may be performed again with the dummy pile 25 interposed between the unit pile 6a and the jack 4 as shown in FIG. good. By using the dummy piles 24 in this manner, shortage of the stroke of the jack 4 is compensated, and the long unit piles 6a can be press-fitted. The dummy piles 25 may be prepared in various lengths, and may be sequentially replaced. Thereby, press-fitting of the longer unit pile 6a becomes possible. The dummy pile 25 has an outer diameter of a stepped shaft at the lower end, and its small-diameter end 25a is fitted into the upper end of the unit pile 6a to prevent misalignment. When the dummy pile 25 is used, the reaction force removing jig 3 does not have to be a vertical slide type.
【0019】図6は他の実施形態を示す。この例では、
基礎2の近傍部分の地盤を掘削した後、杭6を圧入する
部分につき、図4(A)と共に前述したように、基礎2
の立ち上がり部2aよりも広がったベース2bに、はつ
り部24を形成する(図6(B))。この後、ベース部
2bを受けるブラケット状の基礎受け部材23Aを、基
礎2に取付ける。この基礎受け部材23Aは、基端の杭
接合材23aが基礎受材23bよりも上方に突出したも
のとし、その上方突出部分を基礎2の立ち上がり部2a
およびはつり部24の内面にかけてアンカーで取付ける
(図6(C))。この後、基礎2の立ち上がり部2a
に、反力取り治具3を基礎2の立ち上がり部2aにアン
カーで取付ける。反力取り治具3は、基礎2の立ち上が
り部2aの他に基礎受け部材23Aにもボルト等で取付
けられるものとしても良い。反力取り治具3のその他の
構成は、図1の実施形態と同じ構成のものである。この
ように反力取り治具3を取付けた後、第1の実施形態で
図2(C)〜(H)と共に前述したと同様な方法で、複
数本の単位杭6aの継がれた杭6を所定深さまで地盤5
に圧入する(図6(D),(E))。ただし、杭6は、
はつり部24内に配置する。ジャッキ4による圧入は、
図4(B)と共に前述したようなダミー杭25を用いて
行っても良い。FIG. 6 shows another embodiment. In this example,
After excavating the ground in the vicinity of the foundation 2, as described above with reference to FIG.
The hanging portion 24 is formed on the base 2b which is wider than the rising portion 2a (FIG. 6B). Thereafter, the bracket-shaped base receiving member 23A for receiving the base portion 2b is attached to the base 2. This base receiving member 23A has a base pile joining material 23a protruding above the basic receiving material 23b, and its upward protruding portion is a rising portion 2a of the foundation 2.
And, it attaches to the inner surface of the hanging part 24 with an anchor (FIG. 6C). Thereafter, the rising portion 2a of the foundation 2
Then, the reaction force removing jig 3 is attached to the rising portion 2a of the foundation 2 with an anchor. The reaction force removing jig 3 may be attached to the foundation receiving member 23A in addition to the rising portion 2a of the foundation 2 with a bolt or the like. The other configuration of the reaction force removing jig 3 is the same as that of the embodiment of FIG. After the reaction force removing jig 3 is attached in this manner, the pile 6 connected with the plurality of unit piles 6a is used in the same manner as described above with reference to FIGS. 2C to 2H in the first embodiment. The ground 5 to the specified depth
(FIGS. 6D and 6E). However, the pile 6
It is arranged in the hanging part 24. Press-fitting with jack 4
This may be performed using the dummy pile 25 as described above with reference to FIG.
【0020】杭6の圧入が完了すると、図6(F)のよ
うに反力取り治具3を基礎2から取り外し、基礎受け部
材23Aは基礎2に残しておく。ついで、図6(G)の
ように、この残された基礎受け部材23Aを、適宜のス
ペーサ兼用の連結材33を介して杭6に溶接等で接合す
る。この基礎受け部材23Aと基礎2の下部と杭6の上
端を接合した部分は、コンクリート2dを打設してその
内に埋め込む。コンクリート2dの打設後、地盤5の掘
削穴22を埋め戻す。このようにして杭6による基礎2
の補強が完了する。この後、前記と同様に建物1の基礎
2よりも上方の部分を持ち上げて水平修復する。このよ
うに、基礎2のベース部2bにはつり部24を設けてそ
の中に杭6を配置し、後ではつり部24を含めて杭6お
よび基礎受け部材23Aの周辺をコンクリート2dで埋
め込むことにより、杭6と基礎芯の距離が短くて、堅固
で作業効率の良い基礎補強が行える。When the press-fitting of the pile 6 is completed, the reaction force removing jig 3 is removed from the foundation 2 as shown in FIG. 6 (F), and the foundation receiving member 23A is left on the foundation 2. Next, as shown in FIG. 6 (G), the remaining base receiving member 23A is joined to the pile 6 by welding or the like via an appropriate spacer 33 serving as a connecting member. A portion where the foundation receiving member 23A, the lower portion of the foundation 2 and the upper end of the pile 6 are joined is cast with concrete 2d and embedded therein. After placing the concrete 2d, the excavation hole 22 of the ground 5 is backfilled. In this way, the foundation 2 with the pile 6
Is completed. Thereafter, the portion above the foundation 2 of the building 1 is lifted and horizontally restored as described above. As described above, the suspension portion 24 is provided in the base portion 2b of the foundation 2 and the pile 6 is disposed therein. Thereafter, the periphery of the pile 6 and the foundation receiving member 23A including the suspension portion 24 are embedded with concrete 2d. Since the distance between the pile 6 and the foundation core is short, the foundation can be reinforced firmly and with high working efficiency.
【0021】図7はさらに他の実施形態を示す。この例
は、図3,図4の例のようなブラケット形式の基礎受部
材23を用いる代わりに、図7(A)または図7(B)
のように、基礎2の立ち上がり部2aに基礎受部材23
A,23Bを取付けて基礎2と杭6とを連結する場合の
杭圧入過程を示す。この圧入過程は、地盤5の掘削穴2
2を、基礎2のベース部2bが露出する程度の浅いもの
とする他は、図2の実施形態と同じである。圧入の完了
後、基礎2に取付けてあった反力取り治具3の全体を取
り外し、図7(A)のように、基礎受部材23Aを基礎
2の立ち上がり部2aにアンカー26で取付け、この部
材23Aに杭6を溶接やその他の方法で接合する。ま
た、反力取り治具3の全体を取り外す代わりに、図7
(B)のように基礎側部材8を残し、ジャッキ側部材9
(図1)に代えて基礎受部材23Bを取付けても良い。
この基礎受部材23Bに杭6を接合する。このように基
礎2の立ち上がり部2に杭6を基礎受部材23A,23
Bで連結する場合、地盤5の掘削量が一層少なくて済
む。FIG. 7 shows still another embodiment. In this example, instead of using the bracket type base receiving member 23 as in the examples of FIGS. 3 and 4, FIG. 7A or FIG.
As shown in FIG.
7 shows a pile press-in process when connecting the foundation 2 and the pile 6 by attaching A and 23B. This press-fitting process is performed in the excavation hole 2
2 is the same as the embodiment of FIG. 2 except that the base 2 is shallow enough to expose the base 2b of the base 2. After the press-fitting is completed, the entire reaction force removing jig 3 attached to the foundation 2 is removed, and as shown in FIG. 7 (A), the foundation receiving member 23A is attached to the rising portion 2a of the foundation 2 with the anchor 26. The pile 6 is joined to the member 23A by welding or other methods. In addition, instead of removing the entire reaction force removing jig 3, FIG.
(B), leaving the base side member 8 and the jack side member 9
A base receiving member 23B may be attached instead of (FIG. 1).
The pile 6 is joined to the foundation receiving member 23B. Thus, the pile 6 is attached to the rising portion 2 of the foundation 2 by the foundation receiving members 23A, 23A.
In the case of connection at B, the excavation amount of the ground 5 can be further reduced.
【0022】また、前記各実施形態では基礎2を持ち上
げずに、後に基礎2をコンクリートの打ち継ぎで嵩上げ
するようにしたが、基礎2の沈下の程度や地盤5の状況
等によっては、杭6の圧入に伴い、基礎2が持ち上が
る。この場合、建物1の水平が修復されるまで基礎4が
持ち上がると、杭6の圧入を終了し、前記各例のように
杭6と基礎2とを基礎受部材23,23A,23Bで連
結する。あるいは、杭6の圧入完了後に、杭6で支持力
を得て、基礎2をジャッキ4や他のジャッキで持ち上げ
るようにしても良い。この場合、土台ジャッキアップは
不要となるが、基礎2が十分に持ち上がらない場合は、
土台ジャッキアップ等による建物1の水平修復と杭6の
圧入による水平修復とを併用する。Further, in each of the above embodiments, the foundation 2 is raised later by splicing concrete without lifting the foundation 2, but depending on the degree of settlement of the foundation 2 and the condition of the ground 5, the pile 6 , The foundation 2 is lifted. In this case, when the foundation 4 is lifted until the level of the building 1 is restored, the press-fitting of the pile 6 is finished, and the pile 6 and the foundation 2 are connected by the foundation receiving members 23, 23A, 23B as in each of the above examples. . Alternatively, after the press-fit of the pile 6 is completed, the support force may be obtained by the pile 6 and the foundation 2 may be lifted by the jack 4 or another jack. In this case, the foundation jack-up is not required, but if the foundation 2 cannot be lifted sufficiently,
Horizontal restoration of the building 1 by jacking up the foundation and horizontal restoration by press-fitting the pile 6 are used together.
【0023】なお、前記実施形態では杭6を鋼管杭とし
たが、杭6にH形鋼や溝形鋼等の形鋼を用いても良い。In the above embodiment, the pile 6 is a steel pipe pile, but the pile 6 may be made of a section steel such as an H-section steel or a channel steel.
【0024】[0024]
【発明の効果】この発明の建物水平修復工法によれば、
地盤を大きく掘る必要がなく、狭小地でも土の搬出が少
なくて済み、土留めの必要も無くて、安全に作業が行え
る。しかも、掘削等のための重機の使用が不要で、建物
内側に杭打ちを行う場合にも、床を除去する範囲が最小
で済む。また、単位杭を長くできて必要長の杭打ちを効
率的に行える。基礎のベース部にはつり部を形成し、そ
の中に杭を配置した場合は、杭と基礎芯を近づけること
ができて、杭による一層堅固な支持が行える。また、こ
の発明の鋼管杭継手および単位杭によると、単位杭を継
ぐときの継手の品質が安定する。また、単位杭本体の厚
みを、ねじ溝の形成のために厚くすることが不要で、材
料コストが安くて済む。この発明の反力取り治具によれ
ば、この発明方法の実施に際し、ジャッキのストローク
が短くても長い単位杭の圧入が行え、効率的な杭打ちが
行える。According to the horizontal restoration method of a building according to the present invention,
There is no need to excavate the ground greatly, and there is little need to carry out the soil even on narrow land, and there is no need for earth retaining, and work can be performed safely. Moreover, it is not necessary to use heavy equipment for excavation and the like, and even when pile driving is performed inside the building, the area for removing the floor can be minimized. In addition, the unit pile can be lengthened, and the required length of pile can be driven efficiently. When a hanging portion is formed in the base portion of the foundation and the pile is disposed therein, the pile and the foundation core can be brought closer to each other, and the pile can be more firmly supported. Further, according to the steel pipe pile joint and the unit pile of the present invention, the quality of the joint when the unit pile is joined is stabilized. Further, it is not necessary to increase the thickness of the unit pile main body for forming the thread groove, and the material cost can be reduced. ADVANTAGE OF THE INVENTION According to the reaction force removal jig of this invention, when implementing this invention method, even if the stroke of a jack is short, a long unit pile can be press-fitted and efficient pile driving can be performed.
【図1】(A)はこの発明の建物水平修復工法の一実施
形態を示す破断側面図、(B)はその反力取り治具の基
礎側部材の拡大正面図、(C)は同基礎側部材の破断平
面図である。1 (A) is a cutaway side view showing an embodiment of a building horizontal restoration method according to the present invention, FIG. 1 (B) is an enlarged front view of a base side member of the reaction force removing jig, and FIG. It is a fracture | rupture top view of a side member.
【図2】同建物水平修復工法の手順の説明図である。FIG. 2 is an explanatory diagram of a procedure of the building horizontal restoration method.
【図3】同建物水平修復工法の図2に続く過程の説明図
である。FIG. 3 is an explanatory diagram of a process following the process of FIG. 2 of the building horizontal restoration method.
【図4】(A)は同建物水平修復工法における基礎受部
材と基礎および杭との関係を示す斜視図、(B)は杭圧
入方法の別の例を示す破断正面図である。FIG. 4A is a perspective view showing a relationship between a foundation receiving member, a foundation, and a pile in the horizontal restoration method of the building, and FIG. 4B is a cutaway front view showing another example of the pile press-fitting method.
【図5】(A)は鋼管杭継手の断面図、(B)は同鋼管
杭継手を溶接した単位杭の縦断面図、(C)は単位杭の
他の例の中間省略縦断面図である。5A is a cross-sectional view of a steel pipe pile joint, FIG. 5B is a vertical cross-sectional view of a unit pile obtained by welding the steel pipe pile joint, and FIG. 5C is an intermediate omitted vertical cross-sectional view of another example of the unit pile. is there.
【図6】この発明の他の実施形態にかかる建物水平修復
工法の手順の説明図である。FIG. 6 is an explanatory diagram of a procedure of a building horizontal restoration method according to another embodiment of the present invention.
【図7】この発明のさらに他の実施形態にかかる建物水
平修復工法の手順の説明図である。FIG. 7 is an explanatory diagram of a procedure of a building horizontal restoration method according to still another embodiment of the present invention.
【図8】基礎の反力取り治具の取付箇所を示す部分平面
図である。FIG. 8 is a partial plan view showing a mounting position of a base reaction force removing jig.
【図9】基礎の反力取り治具の取付箇所の別例を示す部
分平面図である。FIG. 9 is a partial plan view showing another example of a mounting position of a reaction force removing jig on a foundation.
【図10】(A),(B)は各々図7の手順の後工程の
例を示す説明図である。FIGS. 10A and 10B are explanatory diagrams each showing an example of a post-process of the procedure in FIG. 7;
【図11】従来例の断面図である。FIG. 11 is a sectional view of a conventional example.
1…建物、2…基礎、2a…立ち上がり部、3…反力取
り治具、4…ジャッキ、5…地盤、6…杭、6a…単位
杭、6aa…単位杭本体、7…外壁、8…基礎側部材、
9…ジャッキ側部材、10…結合機構、14…鋼管杭継
手、15…雌ねじ側継手部材、16…雄ねじ側継手部
材、15a,16a…ねじ筒、15b,16b…裏当て
金,23,23A…基礎受け部材、24…はつり部DESCRIPTION OF SYMBOLS 1 ... building, 2 ... foundation, 2a ... rising part, 3 ... reaction force removal jig, 4 ... jack, 5 ... ground, 6 ... pile, 6a ... unit pile, 6aa ... unit pile main body, 7 ... outer wall, 8 ... Foundation side members,
9 ... Jack side member, 10 ... Coupling mechanism, 14 ... Steel pipe pile joint, 15 ... Female thread side joint member, 16 ... Male thread side joint member, 15a, 16a ... Screw tube, 15b, 16b ... Back metal, 23, 23A ... Foundation receiving member, 24 ... hanging part
───────────────────────────────────────────────────── フロントページの続き (56)参考文献 特開 昭61−60928(JP,A) 特開 平1−304217(JP,A) 特開 昭48−19011(JP,A) 特開 昭54−79905(JP,A) 特開 平7−102555(JP,A) 実開 昭61−84734(JP,U) (58)調査した分野(Int.Cl.7,DB名) E02D 35/00 - 37/00 E02D 27/34 E02D 27/48 E02D 5/24 ──────────────────────────────────────────────────続 き Continuation of the front page (56) References JP-A-61-60928 (JP, A) JP-A-1-304217 (JP, A) JP-A 48-19011 (JP, A) JP-A 54-19028 79905 (JP, A) JP-A-7-102555 (JP, A) Japanese Utility Model Application Sho 61-84734 (JP, U) (58) Fields investigated (Int. Cl. 7 , DB name) E02D 35 / 00-37 / 00 E02D 27/34 E02D 27/48 E02D 5/24
Claims (10)
取り治具を取付け、この反力取り治具で支えられるジャ
ッキにより、前記基礎の近傍の地盤に杭を圧入する建物
水平修復工法。1. A horizontal restoration method for a building in which a reaction force removing jig is mounted on a side surface of a rising portion of a foundation of a building, and a pile supported by the reaction force removing jig is used to press a pile into the ground near the foundation.
あり、下方の単位杭を地盤にある程度圧入した後、上方
の単位杭を下方の単位杭に継ぎ、この継がれた杭を再度
前記ジャッキで圧入する請求項1記載の建物水平修復工
法。2. The pile is connected with a plurality of unit piles. After the lower unit pile is pressed into the ground to some extent, the upper unit pile is connected to the lower unit pile, and the connected pile is 2. The method according to claim 1, wherein the jack is press-fitted with the jack again.
し、このはつり部内に前記地盤に圧入する杭を配置する
請求項1または請求項2記載の建物水平修復工法。3. The method according to claim 1, wherein a hanging portion is formed in the base portion of the foundation, and a pile pressed into the ground is disposed in the hanging portion.
る基礎側部材と、ジャッキの受け部を有するジャッキ側
部材とを有し、かつこの基礎側部材にジャッキ側部材を
上下に取付位置変更が可能なように取付けたものであ
り、前記ジャッキで前記杭をある程度圧入した後、反力
取り治具のジャッキ側部材の取付位置を下方に変更した
後、前記ジャッキによる圧入を続ける請求項1または請
求項2または請求項3記載の建物水平修復工法。4. The reaction-force removing jig has a base-side member attached to a foundation and a jack-side member having a jack receiving portion, and the jack-side member is vertically attached to the base-side member. The mounting is carried out so as to be changeable, and after the press-fitting of the stake to some extent with the jack, the mounting position of the jack-side member of the reaction force removing jig is changed downward, and then the press-fitting by the jack is continued. The method of claim 1 or claim 2 or claim 3.
位杭間の接合用のねじ部を有するものである請求項2ま
たは請求項3または請求項4記載の建物水平修復工法。5. The method according to claim 2, wherein the unit pile is a steel pipe pile, and has a thread portion at an end for joining the unit piles.
に伝える基礎受部材を杭に取付け、前記基礎の天端面に
コンクリートを打ち継ぐ請求項1ないし請求項5のいず
れかに記載の建物水平修復工法。6. The pile receiving device according to any one of claims 1 to 5, wherein after completion of the press-fitting of the pile, a foundation receiving member for transmitting the supporting force of the pile to the foundation is attached to the pile, and concrete is transferred to the top end surface of the foundation. Building horizontal restoration method.
または圧入後、または圧入過程および圧入後に、建物の
基礎をジャッキで上昇させる請求項1ないし請求項5の
いずれかに記載の建物水平修復工法。7. A reaction force is obtained by the press-fitted pile, and a press-fitting process is performed.
The building horizontal restoration method according to any one of claims 1 to 5, wherein the foundation of the building is raised with a jack after the press-fitting, or during the press-fitting process and after the press-fitting.
でなり、前記雌ねじ側継手部材は、内径面に雌ねじが形
成された鋼管製のねじ筒と、このねじ筒に一部が内嵌し
て固定されて前記ねじ筒の基端から突出した短筒状の裏
当て金とからなり、前記雄ねじ側継手部材は、外径面に
雄ねじが形成された鋼管製のねじ筒と、このねじ筒に一
部が内嵌して固定されて前記ねじ筒の基端から突出した
短筒状の裏当て金とからなり、これら雌ねじ側継手部材
および雄ねじ側継手部材は、各々鋼管製の単位杭本体の
端部に前記裏当て金を嵌入して前記ねじ筒と単位杭本体
との間を溶接するものである鋼管杭継手。8. A female thread side joint member and a male thread side joint member, wherein the female thread side joint member is a steel pipe screw cylinder having an internal thread formed on an inner diameter surface, and a part of the screw cylinder is internally fitted into the screw cylinder. The male screw side joint member comprises a steel pipe screw cylinder having an external thread formed on an outer diameter surface, and a screw cylinder made of a steel pipe having a short cylindrical backing metal protruding from a base end of the screw cylinder. And a short tube-shaped backing metal part of which is fixed inside and protrudes from the base end of the screw tube, and the female screw side joint member and the male screw side joint member are each made of a steel pipe unit pile body. A steel pipe pile joint, wherein the backing metal is fitted into an end of the pipe pile to weld between the screw cylinder and the unit pile body.
手部材と雄ねじ側継手部材とを設け、前記雌ねじ側継手
部材は、内径面に雌ねじが形成された鋼管製のねじ筒
と、このねじ筒に一部が内嵌して固定されて前記ねじ筒
の基端から突出した短筒状の裏当て金とからなり、前記
雄ねじ側継手部材は、外径面に雄ねじが形成された鋼管
製のねじ筒と、このねじ筒に一部が内嵌して固定されて
前記ねじ筒の基端から突出した短筒状の裏当て金とから
なり、前記雌ねじ側継手部材および雄ねじ側継手部材の
ねじ筒は前記単位杭本体よりも管壁の肉厚が厚いものと
し、これら雌ねじ側継手部材および雄ねじ側継手部材
は、各々前記単位杭本体の端部に前記裏当て金を挿入し
てねじ筒と単位杭本体との間を溶接した単位杭。9. A female pipe-side joint member and a male screw-side joint member are provided at both ends of a steel pipe unit pile main body, and the female screw-side joint member includes a steel pipe screw cylinder having an internal thread formed on an inner diameter surface thereof. A steel pipe having a short cylindrical backing metal partly fitted and fixed in the screw cylinder and protruding from the base end of the screw cylinder, wherein the male screw-side joint member has a male screw formed on an outer diameter surface. And a short cylindrical backing metal partly fitted into and fixed to the screw cylinder and protruding from the base end of the screw cylinder, the female screw side joint member and the male screw side joint member The threaded tube has a pipe wall thicker than the unit pile main body, and the female screw side joint member and the male screw side joint member are each inserted with the backing metal at an end of the unit pile main body and screwed. Unit pile welded between the tube and the unit pile body.
れる基礎側部材と、杭圧入用のジャッキの受け部を上部
に有するジャッキ側部材とを有し、前記基礎側部材にジ
ャッキ側部材を上下に取付位置変更可能に取付ける結合
機構を設けた反力取り治具。10. A base-side member attached to a side surface of a rising portion of a foundation, and a jack-side member having a jack receiving portion for press-fitting a pile at an upper portion, wherein the jack-side member is vertically attached to the foundation-side member. A reaction force removal jig equipped with a coupling mechanism that can be mounted so that the mounting position can be changed.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP8103505A JP3029797B2 (en) | 1996-03-29 | 1996-03-29 | Building horizontal restoration method and steel pipe pile joint |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP8103505A JP3029797B2 (en) | 1996-03-29 | 1996-03-29 | Building horizontal restoration method and steel pipe pile joint |
Publications (2)
Publication Number | Publication Date |
---|---|
JPH09264034A JPH09264034A (en) | 1997-10-07 |
JP3029797B2 true JP3029797B2 (en) | 2000-04-04 |
Family
ID=14355845
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP8103505A Expired - Fee Related JP3029797B2 (en) | 1996-03-29 | 1996-03-29 | Building horizontal restoration method and steel pipe pile joint |
Country Status (1)
Country | Link |
---|---|
JP (1) | JP3029797B2 (en) |
Families Citing this family (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR100478689B1 (en) * | 2002-10-15 | 2005-03-24 | 주식회사 한국피엔알건설 | Stability method of Structure |
JP4703233B2 (en) * | 2005-03-30 | 2011-06-15 | 報国エンジニアリング株式会社 | Building foundation reinforcement method and structure |
JP4973621B2 (en) * | 2007-08-03 | 2012-07-11 | 大成ユーレック株式会社 | Method for correcting horizontal height of structure, equipment used in the method, and method for reinforcing bearing capacity of structure |
JP4856737B2 (en) * | 2009-05-27 | 2012-01-18 | 株式会社オーク | Foundation reinforcement method for existing houses |
JP6543476B2 (en) * | 2015-01-30 | 2019-07-10 | アップコン株式会社 | How to correct uneven settlement of cloth foundation |
JP6960115B2 (en) * | 2017-03-30 | 2021-11-05 | 株式会社デュアル・ポイント・システムズ | Building foundation structure and building foundation structure construction method |
CN113338360B (en) * | 2021-06-28 | 2022-09-30 | 关喜才 | Tower type building deviation correcting device |
CN115717436A (en) * | 2022-11-23 | 2023-02-28 | 吴宇翔 | Prefabricated building base fixed knot who builds temporarily constructs |
-
1996
- 1996-03-29 JP JP8103505A patent/JP3029797B2/en not_active Expired - Fee Related
Also Published As
Publication number | Publication date |
---|---|
JPH09264034A (en) | 1997-10-07 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
KR100807810B1 (en) | Structure lifting method by foundation strengthening | |
JP3071402B2 (en) | Lifting method of structure, jack engaging structure and bracket used in the method | |
US6872031B2 (en) | Apparatus and method of supporting a structure with a pier | |
JP3029797B2 (en) | Building horizontal restoration method and steel pipe pile joint | |
US7044686B2 (en) | Apparatus and method for supporting a structure with a pier | |
JP2022078187A (en) | Foundation construction method by pressing-in durable block for repairing foundation | |
KR102190480B1 (en) | Implant pile pressing apparatus in architecture foundation system and a universal implant piling method | |
JP3002126B2 (en) | Temporary receiving method for structures | |
KR102335023B1 (en) | pulling up device for restoration structure | |
CN212656218U (en) | Heavy pile machine load underpinning structure | |
JP4868610B2 (en) | Building subsidence restoration method | |
CN112593584B (en) | Existing building foundation pile extension reinforcing structure and construction method thereof | |
JP3185129B2 (en) | Column-integrated column base fixed foundation structure and its construction method | |
JP2000008398A (en) | Correcting method and correcting device for building having uneven settlement | |
JP2001214465A (en) | Reinforcing structure for underground construction | |
CN111809615A (en) | Heavy pile machine load underpinning structure and construction method thereof | |
JP7392697B2 (en) | Subsidence correction method for steel pipe members and buildings | |
JP2858997B2 (en) | Temporary support column used for reverse driving method | |
JPH0978580A (en) | Foundation pile pressing-in method and pressing-in device | |
JPH10131176A (en) | Reinforcing method of existing pile by force-fit of outer winding steel pipe | |
CN221645814U (en) | Foundation pit upright post underpinning system | |
JP2006132174A (en) | Connector and connecting structure using the same | |
JPH01304217A (en) | Jack method of pile and jack device thereof | |
CN114892711B (en) | Construction method of retaining wall in deep and weak soil stratum and side slope supporting structure | |
JPH11148236A (en) | Erected pipe for forming pile |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20090204 Year of fee payment: 9 |
|
LAPS | Cancellation because of no payment of annual fees |