JPH0988476A - Method for filling up or backfilling vacant space formed by shield driving work with slurry - Google Patents

Method for filling up or backfilling vacant space formed by shield driving work with slurry

Info

Publication number
JPH0988476A
JPH0988476A JP24197195A JP24197195A JPH0988476A JP H0988476 A JPH0988476 A JP H0988476A JP 24197195 A JP24197195 A JP 24197195A JP 24197195 A JP24197195 A JP 24197195A JP H0988476 A JPH0988476 A JP H0988476A
Authority
JP
Japan
Prior art keywords
shield
mortar
slurry
muddy water
backfilling
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP24197195A
Other languages
Japanese (ja)
Inventor
Masatsugu Iida
正嗣 飯田
Hiroshi Hori
宏 宝利
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Maeda Corp
Original Assignee
Maeda Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Maeda Corp filed Critical Maeda Corp
Priority to JP24197195A priority Critical patent/JPH0988476A/en
Publication of JPH0988476A publication Critical patent/JPH0988476A/en
Pending legal-status Critical Current

Links

Abstract

PROBLEM TO BE SOLVED: To save natural resources by filling up or backfilling the vacant space of a shield reaching wall with mortar prepared by mixing cement in excessive slurry which comes out when slurry is used for shield driving work. SOLUTION: A steel mold 3 is provided between the heading 2 of a main tunnel 1 dug by a shield driving method using slurry and a sheathing 7 so as to surround a communicative port 5. Then a partition wall 6 for shield reaching wall is formed by throwing mortar prepared by mixing a prescribed amount of cement in the excessive slurry of a shield machine 4 in a hopper and placing the mortar between the heading 2 and the mold 3 through a hose. When the shield machine 4 is driven and collides with the heading 2 (partition wall 6) thereafter, the driving work is terminated. Therefore, the slurry can be recycled and the amount of industrial waste can be reduced.

Description

【発明の詳細な説明】Detailed Description of the Invention

【0001】[0001]

【発明の属する技術分野】本発明は、泥水シールド工法
等によるシールド工事における余剰泥水等の泥水を使用
したモルタルによる空隙充填・埋め戻し工法に関するも
のである。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a method for filling and backfilling voids with mortar using mud such as excess mud in shield construction by a mud shield construction method or the like.

【0002】[0002]

【従来の技術】トンネル施工法の一つとしてシールド工
法があり、そのうち密閉型機械シールドに分類されるも
のとして、泥水や泥土により切羽を抑えながら掘進でき
る泥水(泥水加圧)シールド工法や土圧系(削土加圧
式、加水式、加泥式(泥土加圧、泥漿、高濃度沈水)を
含む)シールド工法がある。
2. Description of the Related Art There is a shield construction method as one of tunnel construction methods, and among them, it is classified as a closed type mechanical shield. A mud water (mud pressure) shield construction method and earth pressure that can be dug while suppressing the face with mud or mud There is a shield construction method (including soil pressurization type, water addition type, mud addition type (including mud pressure, sludge, high concentration submersion)).

【0003】そして、シールド到達工における隔壁等の
狭隘部への空隙充填や適宜の埋め戻しに際して従来は、
一般的なモルタルを使用したり、コンクリートまたはソ
イルコンクリートを使用して行っていた。なお、例え
ば、泥水シールド工事における余剰泥水について従来
は、脱水等して産業廃棄物として処理していた。
[0003] In the shield reaching process, when filling voids in a narrow portion such as a partition wall or appropriately backfilling, conventionally,
It was done using standard mortar or concrete or soil concrete. Note that, for example, surplus mud water in the mud shield work has conventionally been dehydrated and treated as industrial waste.

【0004】[0004]

【発明が解決しようとする課題】以上のように従来は、
シールド到達工における隔壁等の狭隘部への空隙充填や
適宜の埋め戻しに際して、モルタルやコンクリートを使
用して行う一方で、泥水シールド工事における余剰泥水
を産業廃棄物として処理している無駄があった。
As described above, the prior art is as follows.
While using mortar and concrete to fill the voids and appropriately backfill narrow spaces such as bulkheads in the shield arrival work, there was a waste of treating excess mud in the mud shield construction as industrial waste. .

【0005】そこで、本発明の目的は、泥水シールド工
法等によるシールド工事で出る余剰泥水等の泥水を有効
に利用してモルタルを作って、例えば、シールド到達工
における隔壁等の狭隘部への空隙充填や適宜の埋め戻し
を行うことにより、資源の節約と共に、泥水処理による
産業廃棄物の減量化に寄与できるようにしたシールド工
事における泥水使用の空隙充填・埋め戻し工法を提供す
ることにある。
Therefore, an object of the present invention is to effectively use muddy water such as surplus muddy water produced by a shield construction method such as a muddy water shield construction method to make mortar, and for example, to make a gap to a narrow portion such as a partition wall in shield reaching work. It is an object of the present invention to provide a void filling / backfilling method for use in muddy water in shield construction, which can contribute to resource saving as well as reduction of industrial waste by muddy water treatment by performing filling and appropriate backfilling.

【0006】[0006]

【課題を解決するための手段】以上の課題を解決すべく
本発明は、泥水シールド工法等によるシールド工事で出
る余剰泥水等の泥水を使用し、その泥水にセメントを、
例えば、図3に示すような配合により混合して、7日強
度3〜15kgf/cm2程度の必要強度に対応したモ
ルタルを作り、その泥水使用のモルタルを使用して、例
えば、シールド到達工における隔壁等の狭隘部への空隙
充填や埋め戻しを行うようにした、シールド工事におけ
る泥水使用の空隙充填・埋め戻し工法を特徴としてい
る。
Means for Solving the Problems In order to solve the above problems, the present invention uses muddy water such as surplus muddy water produced by a shield construction by a muddy water shield construction method, and cements the muddy water.
For example, a mortar corresponding to a required strength of 7 to 15 days strength of 3 to 15 kgf / cm 2 is prepared by mixing with a composition as shown in FIG. It features a void filling and backfilling method using muddy water in shield work, which is designed to fill and backfill narrow spaces such as partition walls.

【0007】このように、シールド工事で出る泥水を使
用してセメントを混合したモルタルによりシールド到達
工における隔壁等の狭隘部への空隙充填や埋め戻しを行
うことで、余剰泥水等の泥水を有効に再利用して、高強
度を必要としない狭隘部への空隙充填や埋め戻しが行
え、その結果、資源の節約と共に、泥水処理による産業
廃棄物の減量化に寄与できるものとなる。
[0007] In this way, by filling the voids and backfilling the narrow spaces such as partition walls in the shield reaching work with the mortar mixed with cement using the muddy water produced in the shield construction, the muddy water such as surplus muddy water is effectively used. It can be reused for filling of voids and backfilling in narrow spaces that do not require high strength. As a result, resources can be saved and industrial waste can be reduced by muddy water treatment.

【0008】[0008]

【発明の実施の形態】以下に、本発明に係るシールド工
事における泥水使用の空隙充填・埋め戻し工法の実施の
形態例を図1から図3に基づいて説明する。
BEST MODE FOR CARRYING OUT THE INVENTION An embodiment of the void filling / backfilling method using muddy water in a shield work according to the present invention will be described below with reference to FIGS. 1 to 3.

【0009】先ず、図1は本発明を適用した一例として
のシールド到達工における隔壁を示す正面図で、図2は
そのシールド到達工における隔壁の断面形状を示す縦断
側面図であり、図中、1は本抗、2は奥壁部、3はスチ
ール型枠、4はシールド機、5は連通口、6は隔壁、7
は土留めである。本抗1は、図示しない泥水シールド工
事用のシールド機により既に掘削されてセグメントによ
り覆工されたもので、図示のように、この本抗1の奥壁
部2には、予めシールド到達工に備えて土留め7との間
に形成する隔壁用のスチール型枠3が設けられており、
本抗1と奥壁部2を挟んだ反対側からは、泥水シールド
工事用のシールド機4が掘進して来る。
First, FIG. 1 is a front view showing a partition wall in a shield reaching process as an example to which the present invention is applied, and FIG. 2 is a longitudinal side view showing a sectional shape of the partition wall in the shield reaching process. 1 is a main wall, 2 is a back wall part, 3 is a steel form, 4 is a shield machine, 5 is a communication port, 6 is a partition wall, 7
Is earth retaining. The main shaft 1 is already excavated by a shield machine for muddy water shield construction not shown and lined with segments. As shown in the drawing, the back wall portion 2 of the main shaft 1 is previously shielded. The steel form 3 for the partition wall provided between the earth retaining member 7 and the earth retaining member 7 is provided.
A shield machine 4 for mud shield construction digs in from the opposite side of the main wall 1 and the back wall 2.

【0010】なお、スチール型枠3は、シールド到達工
により奥壁部2に形成される連通口5に対応してその周
囲を囲む形状をなしていて、鉄骨により本抗1内に支持
されている。また、奥壁部2の連通口5が形成される部
分は、空隙部となっている。
The steel form 3 has a shape surrounding the periphery of the communication port 5 formed in the back wall portion 2 by the shield reaching work, and is supported by the steel frame in the main shaft 1. There is. Further, the portion of the inner wall portion 2 where the communication port 5 is formed is a void portion.

【0011】そして、シールド機4の掘進が進んで、奥
壁部2には、本抗1側から見てスチール型枠3の裏側に
連通口5が開口して形成されることになる。そのシール
ド到達工に備えて、この実施の形態例においては、本抗
1を掘進した際の泥水シールド工事用のシールド機4に
使用された泥水の余剰泥水を使用し、その余剰泥水にセ
メントを混合することによりモルタルを作り、その泥水
使用のモルタルを使用してスチール型枠3と奥壁部2と
の間の空隙を埋めて、隔壁6を形成する。
Then, as the shield machine 4 advances, a communication port 5 is formed in the back wall portion 2 on the back side of the steel form 3 as viewed from the main resistance 1 side. In preparation for the shield arrival work, in this embodiment, the excess muddy water used in the shield machine 4 for the muddy water shield construction when the main tunnel 1 is dug is used, and cement is applied to the excess muddy water. The mortar is made by mixing, and the mortar using muddy water is used to fill the gap between the steel form 3 and the back wall portion 2 to form the partition wall 6.

【0012】即ち、本抗1の側において、具体的には、
図示しないミキサーを用いて、余剰泥水に所定量のセメ
ントを混合してモルタルを作り、その余剰泥水使用のモ
ルタルを図示しないホッパーに投入して、同じく図示し
ないホースを介して、奥壁部2とスチール型枠3との間
に前記余剰泥水使用のモルタルを打設する。その後、打
設したモルタルの乾燥固化により来るシールド到達工に
備えた隔壁6が形成される。
That is, on the side of the main anti-stress 1, specifically,
Using a mixer (not shown), a predetermined amount of cement is mixed with excess mud to make mortar, and the mortar using excess mud is put into a hopper (not shown), and a back wall 2 and The mortar using the excess mud is placed between the steel form 3 and the mortar. After that, the partition wall 6 is formed in preparation for the shield reaching work which is brought about by the drying and solidification of the cast mortar.

【0013】従って、本抗1と奥壁部2(隔壁6)を挟
んだ反対側から泥水シールド工事用のシールド機4が掘
進して来て、土留め7および奥壁部2(隔壁6)に突き
当たって、本抗1側から見てスチール型枠3の裏側に連
通口5が開口すると、シールド機4の掘進が終了する。
その後、隔壁部6およびスチール型枠3を撤去すること
で、本抗1側から見て連通口5が開口した状態となる。
Therefore, the shield machine 4 for mud shield work is dug from the opposite side of the main body 1 and the back wall portion 2 (the partition wall 6), and the earth retaining 7 and the back wall portion 2 (the partition wall 6). When the communication port 5 is opened on the back side of the steel form 3 as seen from the main resistance 1 side, the excavation of the shield machine 4 is completed.
After that, the partition 6 and the steel form 3 are removed, so that the communication port 5 is opened when viewed from the main tunnel 1 side.

【0014】ここで、前述した空隙充填用のモルタルを
作るための泥水とセメントの配合については、種々の試
験配合を繰り返した結果、図3の図表に示したような<
余剰泥水を使用したモルタル強度試験結果>を得ること
ができた。
Here, as for the mixture of muddy water and cement for making the above-mentioned mortar for filling voids, as a result of repeating various test formulations, as shown in the chart of FIG.
The mortar strength test result> using surplus mud was obtained.

【0015】つまり、図3の図表<余剰泥水を使用した
モルタル強度試験結果>において、先ず、データNo.
1は、モルタル1m3当り、セメント80kgで泥水9
75lの配合の場合であり、7日強度としては、3.
4kgf/cm2、3.2kgf/cm2、3.8k
gf/cm2を得た。従って、7日強度の平均は、3.
4kgf/cm2である。
That is, in the chart <Results of mortar strength test using surplus mud> in the chart of FIG.
1 is 80 kg of cement per 1 m 3 of mortar and muddy water 9
In the case of 75 liters, the 7-day strength is 3.
4 kgf / cm 2 , 3.2 kgf / cm 2 , 3.8k
gf / cm 2 was obtained. Therefore, the average of 7-day intensity is 3.
It is 4 kgf / cm 2 .

【0016】また、図3の図表<余剰泥水を使用したモ
ルタル強度試験結果>において、次の、データNo.2
は、モルタル1m3当り、セメント120kgで泥水9
62lの配合の場合であり、7日強度としては、6.
5kgf/cm2、6.1kgf/cm2、6.0k
gf/cm2を得た。従って、7日強度の平均は、6.
2kgf/cm2である。
In addition, in the chart of FIG. 3 <results of mortar strength test using excess mud>, the following data No. Two
Is 9 kg of muddy water with 120 kg of cement per 1 m 3 of mortar.
In the case of the 62 l formulation, the 7-day strength was 6.
5 kgf / cm 2 , 6.1 kgf / cm 2 , 6.0 k
gf / cm 2 was obtained. Therefore, the average of 7-day intensity is 6.
It is 2 kgf / cm 2 .

【0017】さらに、図3の図表<余剰泥水を使用した
モルタル強度試験結果>において、次のデータNo.3
は、モルタル1m3当り、セメント160kgで泥水9
52lの配合の場合であり、7日強度としては、9.
2kgf/cm2、8.8kgf/cm2、8.7k
gf/cm2を得た。従って、7日強度の平均は、8.
9kgf/cm2である。
Further, in the chart <Results of mortar strength test using excess mud> shown in FIG. 3
Is muddy water with 160 kg of cement per 1 m 3 of mortar.
In the case of the composition of 52 l, the 7-day strength was 9.
2kgf / cm 2, 8.8kgf / cm 2, 8.7k
gf / cm 2 was obtained. Therefore, the average of 7-day intensity is 8.
It is 9 kgf / cm 2 .

【0018】そして、図3の図表<余剰泥水を使用した
モルタル強度試験結果>において、最後のデータNo.
4は、モルタル1m3当り、セメント180kgで泥水
943lの配合の場合であり、7日強度としては、1
1.3kgf/cm2、11.8kgf/cm2、1
1.6kgf/cm2を得た。従って、7日強度の平均
は、11.5kgf/cm2である。
Then, in the chart <Results of mortar strength test using surplus mud> of the last data No.
No. 4 is a case of mixing 180 kg of cement and 943 l of muddy water per 1 m 3 of mortar.
1.3 kgf / cm 2 , 11.8 kgf / cm 2 , 1
1.6 kgf / cm 2 was obtained. Therefore, the average of 7-day strength is 11.5 kgf / cm 2 .

【0019】以上の図3の図表<余剰泥水を使用したモ
ルタル強度試験結果>に基づいて、さほど高強度を必要
としない隔壁部分等の空隙充填や埋め戻しに際し、その
必要強度に対応した配合を選定して使用するものとす
る。
Based on the above chart <results of mortar strength test using surplus mud>, when filling or backfilling voids such as partition walls which does not require so high strength, a composition corresponding to the required strength is used. It shall be selected and used.

【0020】なお、以上の実施の形態例においては、泥
水シールド工事での余剰泥水を使用したモルタルによる
シールド到達工における隔壁の空隙充填としたが、本発
明はこれに限定されるものではなく、他の土圧系(削土
加圧式、加水式、加泥式(泥土加圧、泥漿、高濃度沈
水)を含む)シールド工事等で出る泥水(泥土も含む)
を使用したモルタルによる適宜箇所への空隙充填や埋め
戻しを行ってもよい。
In the above-mentioned embodiments, the gap filling of the partition walls in the shield reaching work by the mortar using the excess mud in the mud shield construction is carried out, but the present invention is not limited to this. Mud water (including mud) produced by other earth pressure systems (including earth cutting pressure type, water addition type, mud addition type (mud pressure, sludge, highly concentrated submersion)) shield work, etc.
The voids may be filled or backfilled in appropriate places with mortar using.

【0021】[0021]

【発明の効果】以上のように、本発明に係るシールド工
事における泥水使用の空隙充填・埋め戻し工法によれ
ば、シールド工事で出る泥水を使用してセメントを混合
したモルタルによりシールド到達工における隔壁等の狭
隘部への空隙充填や埋め戻しを行うため、余剰泥水等の
泥水を有効に再利用して、高強度を必要としない狭隘部
への空隙充填や埋め戻しを施工性良く行うことができ
る。従って、資源を節約することができると共に、泥水
処理による産業廃棄物の減量化にも寄与することができ
る。
As described above, according to the void filling and backfilling method using muddy water in the shield work according to the present invention, the partition wall in the shield reaching work is prepared by using the mortar mixed with the cement using the muddy water produced in the shield work. It is possible to effectively reuse the muddy water such as surplus muddy water to fill the voids in the narrow space and to backfill it in the narrow space that does not require high strength. it can. Therefore, it is possible to save resources and also contribute to reduction of the amount of industrial waste due to muddy water treatment.

【図面の簡単な説明】[Brief description of drawings]

【図1】本発明を適用した一例としてのシールド到達工
における隔壁を示す正面図である。
FIG. 1 is a front view showing a partition wall in a shield reaching process as an example to which the present invention is applied.

【図2】図1のシールド到達工における隔壁の断面形状
を示す縦断側面図である。
FIG. 2 is a vertical sectional side view showing a sectional shape of a partition wall in the shield reaching process of FIG.

【図3】本発明による余剰泥水を使用したモルタル強度
試験結果を示す図表である。
FIG. 3 is a table showing the results of mortar strength test using excess mud water according to the present invention.

【符号の説明】[Explanation of symbols]

1 本抗 2 奥壁部 3 スチール型枠 4 シールド機 5 連通口 6 隔壁 7 土留め 1 main anti 2 back wall 3 steel form 4 shield machine 5 communication port 6 bulkhead 7 earth retaining

Claims (1)

【特許請求の範囲】[Claims] 【請求項1】 泥水シールド工法等によるシールド工事
で出る余剰泥水等の泥水を使用し、 その泥水にセメントを混合してモルタルを作り、 その泥水使用のモルタルを使用してシールド到達工にお
ける隔壁等の狭隘部への空隙充填や埋め戻しを行うこ
と、を特徴とするシールド工事における泥水使用の空隙
充填・埋め戻し工法。
1. A muddy water such as surplus muddy water produced in a shield construction by a muddy water shield method is used, cement is mixed with the muddy water to make mortar, and the mortar using the muddy water is used to form partition walls in shield reaching work. A method for filling and backfilling voids in mud water in shield construction, characterized by performing void filling and backfilling in narrow spaces.
JP24197195A 1995-09-20 1995-09-20 Method for filling up or backfilling vacant space formed by shield driving work with slurry Pending JPH0988476A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP24197195A JPH0988476A (en) 1995-09-20 1995-09-20 Method for filling up or backfilling vacant space formed by shield driving work with slurry

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP24197195A JPH0988476A (en) 1995-09-20 1995-09-20 Method for filling up or backfilling vacant space formed by shield driving work with slurry

Publications (1)

Publication Number Publication Date
JPH0988476A true JPH0988476A (en) 1997-03-31

Family

ID=17082316

Family Applications (1)

Application Number Title Priority Date Filing Date
JP24197195A Pending JPH0988476A (en) 1995-09-20 1995-09-20 Method for filling up or backfilling vacant space formed by shield driving work with slurry

Country Status (1)

Country Link
JP (1) JPH0988476A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105626088A (en) * 2016-02-02 2016-06-01 中铁十九局集团轨道交通工程有限公司 Well-descending translation method of T-shaped bored tunnel shield tunneling machine

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105626088A (en) * 2016-02-02 2016-06-01 中铁十九局集团轨道交通工程有限公司 Well-descending translation method of T-shaped bored tunnel shield tunneling machine

Similar Documents

Publication Publication Date Title
US4089183A (en) Consolidation construction for improving soft, unstable foundation
JPH0988476A (en) Method for filling up or backfilling vacant space formed by shield driving work with slurry
JPS63233115A (en) Soil reclaiming and filling work
JP2840880B2 (en) Method for producing self-hardening backfill material
JPS63315724A (en) Execution work of cast-in-place concrete pile with high yield strength
JP3639054B2 (en) Backfill injection material
JP2020125648A (en) Columnar improvement method, and soil cement column row wall method using core material pressing-in and vibration pressing-in
JP3660070B2 (en) Construction surplus soil effective utilization method
JP2010012433A (en) Method of treating dug soil containing arsenic
JP2001081806A (en) Fluidization back filling method for construction generated earth
JPH0462221A (en) Back-fill injection work
JPH07100822A (en) Manufacture of hydraulic material
JPS5873694A (en) Method and apparatus for improving discharged soil in soil pressure type shield drilling machine
JPH1113049A (en) Improving method for organic soil ground
JP3454332B2 (en) Groove backfill method
IES940331A2 (en) Method and apparatus for constructing access cavities, including manholes, to underground services
JPH11247175A (en) Soil improvement method
JPH10140155A (en) Flowable refilling material and its production
JPH03287909A (en) Backfilling and packing work
JPS6288999A (en) Method of solidifying and processing radioactive incombustible solid waste
JPH0336313A (en) Crushing method for excessive concrete in cast-in-place concrete pile
JPH01127795A (en) Cast-in-place concrete lining construction method and concrete for lining
JPS6346807B2 (en)
JPH05272168A (en) Underground structure making method and pipe laying method
JPH0216213A (en) Head treatment work of in-situ pile

Legal Events

Date Code Title Description
A977 Report on retrieval

Effective date: 20041227

Free format text: JAPANESE INTERMEDIATE CODE: A971007

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20050111

A02 Decision of refusal

Effective date: 20050517

Free format text: JAPANESE INTERMEDIATE CODE: A02