JPH03287909A JP2088142A JP8814290A JPH03287909A JP H03287909 A JPH03287909 A JP H03287909A JP 2088142 A JP2088142 A JP 2088142A JP 8814290 A JP8814290 A JP 8814290A JP H03287909 A JPH03287909 A JP H03287909A
Authority
JP
Japan
Prior art keywords
backfilling
soil
site
water
excavated
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP2088142A
Other languages
Japanese (ja)
Inventor
Toshiaki Furuya
古谷 俊明
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Taiheiyo Cement Corp
Original Assignee
Onoda Cement Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Onoda Cement Co Ltd filed Critical Onoda Cement Co Ltd
Priority to JP2088142A priority Critical patent/JPH03287909A/en
Publication of JPH03287909A publication Critical patent/JPH03287909A/en
Pending legal-status Critical Current

Links

Landscapes

  • Investigation Of Foundation Soil And Reinforcement Of Foundation Soil By Compacting Or Drainage (AREA)

Abstract

PURPOSE:To prevent the occurrence of subsidence by a method in which excavated soil is mixed with a hardening agent and carried to an embedding site, and the soil is fluidized with water supplied, subjected to vibration and packed into the backfilling site. CONSTITUTION:Excavated soil is mixed with about 5wt% hardening agent such as cement and carried along to a backfilling site. The soil is supplied with about 10% or more water while packing into the backfilling site and fluidized by a vibrator to pack it into the site. The backfilling work can thus be completely attained to prevent the occurrence of subsidence of the ground.

Description

【発明の詳細な説明】 [産業上の利用分野] この発明は水道管や下水管およびガス管等の埋設や補修
または構築物の建設工事における掘削箇所の埋戻し充填
工法に関するものである。
[Detailed Description of the Invention] [Industrial Application Field] The present invention relates to a method for burying or repairing water pipes, sewer pipes, gas pipes, etc., or backfilling excavated areas during construction work of structures.

[従来の技術] 一般に、上下水道管やガス管等の埋設および補修或は構
築物の建設工事等における掘削箇所の埋戻しは掘削残土
で行うのが望ましいが、残土が不適当な場合には別途に
良質の土砂を用いるか、或は掘削残土に固化材等を配合
した改良土を使用してこれを十分に突き固めて行うのが
多く、且つ一般的である。
[Prior Art] Generally, it is desirable to backfill excavated areas during burying and repair of water and sewage pipes, gas pipes, etc. or construction of structures using excavated soil, but if the remaining soil is inappropriate, separate It is common practice to use good quality earth and sand, or to use improved soil made by adding a hardening agent to the excavated soil, and to thoroughly compact the soil.

[発明が解決しようとする問題点コ 併し乍ら、実際には、この様な建設土木工事において特
に管渠回り等は十分な突き固めが困難で、弛る詰めとな
ったり、空洞が残存し勝ちである。
[Despite the problems that the invention seeks to solve, in reality, in such construction and civil engineering work, it is difficult to sufficiently ram the pipes, especially around pipes, and the ramming tends to be loose and cavities remain.] be.

このために、後日地盤沈下や陥没の原因と成る等の問題
が有る。
For this reason, there are problems such as causing ground subsidence and cave-ins at a later date.

この様な問題を解決するために、例えば特開平1−31
2118号公報に記載される様に、掘削残土に固化材と
水とを混合してスラリー状の流動化した流動性処理土を
用いる方法も試みられているが、この様な工法において
は処理土の混合撹拌を施工現場に設けた現場プラントや
、若しくは生コンクリートプラント等によって行うため
にプラントヤードの確保等、狭隘な現場では著しく困難
であり、また生コンクリートプラントの切換えやコンク
リートミキサー車の洗浄等が繁雑であり、コスト高に付
く等の問題点が見られる。。
In order to solve such problems, for example, Japanese Patent Application Laid-Open No. 1-31
As described in Publication No. 2118, a method has also been attempted in which the excavated soil is mixed with a solidifying agent and water to create a slurry of fluidized treated soil. Mixing and agitation is carried out by an on-site plant installed at the construction site or a ready-mixed concrete plant, so it is extremely difficult to secure a plant yard on a narrow site. However, there are problems such as the process is complicated and the cost is high. .

従って、この発明は、掘削残土の埋戻し現場において、
簡便な方法で流動性埋戻し材を得ることを目的とするも
ので、掘削残土に固化材を配合する工程と水等を混合し
て流動性を付与する工程とを分離して、埋戻し現場にお
ける埋戻し作業の過程において水の注水と振動掛けとに
よって処理上の混練と流動化を行うことをポイントとす
るものである。
Therefore, this invention can be used at backfilling sites with excavated soil.
The purpose of this method is to obtain a fluid backfill material using a simple method, and the process of adding a solidifying material to excavated soil and the process of adding fluidity by mixing water etc. are separated, and the process of adding fluidity to the excavated soil is separated. The key point of this method is to perform mixing and fluidization through water injection and vibration during the backfilling process.

[内題点を解決するための手段] 上述の目的を達成するために、この発明に依れば、建設
工事における掘削埋戻し工事に際して、掘削残土に予め
固化材を配合して混合し、この処理した処理土を埋戻し
現場へ運搬し、埋戻しつ1処理土に注水すると共に振動
を掛けて流動化して、埋戻し箇所の完全な充填を行うよ
うにしたことを特徴としている。
[Means for Solving the Internal Problems] In order to achieve the above-mentioned object, according to the present invention, during excavation and backfilling work in construction work, a solidification material is mixed in advance with the excavated soil, and this treatment is carried out. The treated soil is transported to the backfilling site, water is poured into the treated soil, and the treated soil is fluidized by vibration, thereby completely filling the backfilling area.

[作  用] 従って、この発明は上述の手段に依って、建設工事にお
ける掘削埋戻し工事に際して、掘削残土を用いて流動性
処理土として再使用するには掘削残土に予め固化材の配
合と水等の添加が必要工程となり、特に固化材の配合に
はタンク等の設備が大型となるので、この工程を埋戻し
現場から離して埋戻し現場近くの空地等で集中的に行う
ようにする。掘削残土の含水比が大きくて軟弱であって
も、多くの場合、固化材としてセメントを重量比で約5
%程添加して十分に混合することで埋戻し土として使用
可能となる。こうして処理した処理土を現場に運搬して
、埋戻し乍ら処理土に約10%以下の少Iの水を用いて
注水して、これにバイブレータによって振動を掛けて流
動化して埋戻し箇所の埋戻しが行われる。この様に、流
動化することによって処理土の突き固めが不用となり、
管周りも十分充填される。また、この様な埋戻しにおけ
る注水と振動掛けは、作業者が施工中の処理土の性状を
見ながら加減することが可能であり、必要最小限の水量
に調節することが容易であり、特に流動化を例えば管回
り等の充填不足となり易い箇所のみに最小限とすること
が可能であり、極めて実用的である。
[Function] Accordingly, the present invention uses the above-mentioned means to mix the excavated soil with a solidifying agent and water in advance in order to reuse the excavated soil as fluid treated soil during excavation and backfilling work in construction work. Addition of such substances is a necessary step, and in particular, the mixing of solidifying materials requires large equipment such as tanks. Therefore, this step should be carried out away from the backfilling site and concentrated in a vacant lot near the backfilling site. Even if the excavated soil has a high moisture content and is soft, in many cases cement is used as a solidification agent by weight of about 5%.
By adding approximately 50% and mixing thoroughly, it can be used as backfill soil. The treated soil treated in this way is transported to the site, and while being backfilled, water is poured into the treated soil using water with a low I content of about 10% or less, and the water is vibrated with a vibrator to make it fluid and fill the backfilling area. Backfilling is performed. In this way, fluidization eliminates the need for compacting the treated soil,
The area around the pipe is also filled sufficiently. In addition, the water injection and vibration application in such backfilling can be adjusted by the worker while observing the properties of the treated soil during construction, and it is easy to adjust the amount of water to the minimum necessary, especially when It is possible to minimize fluidization only in areas where filling is likely to be insufficient, such as around pipes, which is extremely practical.

[実 施 例コ この様なこの発明の埋戻し充填工法の実際の例を下水管
の埋設現場の例に就いて説明すると、本現場の土性は湿
mWi度γt=1.68g/c1、含水比w=73.5
%、砂分32%、シルト分51%、粘土骨17%の粒度
構成であった1本現場の掘削によって発生した掘削残土
を現場から50離れた空地に野積みした。下水管設置が
完了した時点で、上述の野積みした残土に固化材として
セメントを重量比で約5%添加してバックホウで十分混
合した後に、ダンプトラックで埋戻し現場に搬入してダ
ンプしつ)埋戻した。
[Example] An actual example of the backfilling method of the present invention will be explained using an example of a site where a sewer pipe is buried. Water content ratio w=73.5
%, sand content of 32%, silt content of 51%, and clay bone of 17%.The excavated soil generated from the excavation of one site was piled up in the open at a vacant lot 50 meters away from the site. When the sewer pipe installation is completed, approximately 5% by weight of cement is added as a solidifying agent to the above-mentioned open piled surplus soil, thoroughly mixed with a backhoe, and then transported to the backfilling site using a dump truck and dumped. ) Backfilled.

埋戻し土は掘削した溝底部より埋設下水管頂部以上的2
0cmまで注水しつ)、同時に棒状バイブレータを用い
て振動掛けを行った。下水管周辺の土は十分に流動化さ
れて、完全に下水管壁に接触して完全な充填が行われた
ことが確認された。この時、注水した総水量は原土重量
の約8.1%であり、当初に試験室でミキサーで混練し
て作成した流動化した処理土の混練水15%に比して相
当に少ない水量であり、効率的に流動化出来たことが明
確に証明されるものであった。
Backfill soil should be placed from the bottom of the excavated trench to the top of the buried sewer pipe2.
Water was injected to a depth of 0 cm), and at the same time, vibration was applied using a rod-shaped vibrator. It was confirmed that the soil around the sewer pipe had been sufficiently fluidized and was completely in contact with the wall of the sewer pipe, ensuring complete filling. At this time, the total amount of water injected was approximately 8.1% of the weight of the original soil, which was considerably smaller than the 15% mixing water for the fluidized treated soil that was initially mixed in a mixer in the test room. This clearly proves that it was possible to fluidize efficiently.

[発明の効果] 斯様に、この発明に依れば、建設工事における掘削埋戻
し工事に際して、掘削残土に予めセメントの様な固化材
を配合して混合し、この処理した処理土を埋戻し現場へ
運搬し、埋戻しつ藁処理上に僅かな水量の水を注水する
と共に適宜なバイブレータを用いて振動を掛けて流動化
して埋戻し箇所の完全な充填を行うことが出来、少量の
セメントと水とを使用して流動化させ良好な埋戻しが完
全に出来て陥没や地盤沈下の発生の恐れが無く、短期間
に経済性を伴って良好に施工できる等の効果が得られる
[Effect of the invention] According to this invention, when backfilling excavation work in construction work, a solidifying agent such as cement is mixed in advance with excavated soil, and this treated soil is backfilled. It is possible to completely fill the backfill area by transporting it to the site, pouring a small amount of water onto the backfill straw, and applying vibration using an appropriate vibrator to fluidize the backfill. By using water and fluidization, good backfilling can be completely achieved, and there is no fear of cave-ins or ground subsidence, and the construction can be carried out economically and efficiently in a short period of time.

Claims (1)

【特許請求の範囲】[Claims]  建設工事における掘削埋戻し工事に際して、掘削残土
に予め固化材を配合して混合し、この処理した処理土を
埋戻し現場へ運搬し、埋戻しつゝ該処理土に注水すると
共に振動を掛けて流動化して、埋戻し箇所の完全な充填
を行うようにしたことを特徴とする埋戻し充填工法。
When backfilling excavations during construction work, a solidification material is mixed in advance with the excavated soil, the treated soil is transported to the backfilling site, and during backfilling, water is poured into the treated soil and vibration is applied. A backfilling method characterized by fluidizing and completely filling the backfilling area.
JP2088142A 1990-04-04 1990-04-04 Backfilling and packing work Pending JPH03287909A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2088142A JPH03287909A (en) 1990-04-04 1990-04-04 Backfilling and packing work

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2088142A JPH03287909A (en) 1990-04-04 1990-04-04 Backfilling and packing work

Publications (1)

Publication Number Publication Date
JPH03287909A true JPH03287909A (en) 1991-12-18

Family

ID=13934687

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2088142A Pending JPH03287909A (en) 1990-04-04 1990-04-04 Backfilling and packing work

Country Status (1)

Country Link
JP (1) JPH03287909A (en)

Similar Documents

Publication Publication Date Title
CN105887837A (en) On-site ground cemented soil stirring pile construction method
JP3144321B2 (en) Fluidization method
JPH0452327A (en) Stabilized soil and construction method using this soil
JPH03287909A (en) Backfilling and packing work
JPH10227003A (en) Construction of base course
JP2004225453A (en) Construction method of civil engineering structure
JP2000257109A (en) Construction method for fluidized back-filling
JPH11269874A (en) Pile construction method for foundation pile
JP4027572B2 (en) How to use construction soil
JP3660070B2 (en) Construction surplus soil effective utilization method
JP3230147B2 (en) Fluidized soil construction structure and its construction method
JPH05132942A (en) Backfilling material and backfilling method
KR102600771B1 (en) Method of surface solidification construction for soft ground stabilization of soft ground
JP3007940B2 (en) Lightweight ground to be cast on soft ground and construction method thereof
JP2021161860A (en) Buried pile backfill method
JP3341541B2 (en) Backfilling method for buried objects
JP4395212B2 (en) Construction method of underwater cured body
JP2001081806A (en) Fluidization back filling method for construction generated earth
JP3454332B2 (en) Groove backfill method
JP2744578B2 (en) Fluidizing backfill solidifying agent and method of using the same
JPH07100822A (en) Manufacture of hydraulic material
JP3545641B2 (en) Backfill method
JP2849924B2 (en) Crushing method of excess concrete of cast-in-place concrete pile
JP2004353310A (en) Method of improving soil with kneaded material including a large quantity of coal ash
JPH0438311A (en) Constructing method for underwater structure with dredged sludge