JPH0941389A - Execution method of temporary cofferdam - Google Patents

Execution method of temporary cofferdam

Info

Publication number
JPH0941389A
JPH0941389A JP19203695A JP19203695A JPH0941389A JP H0941389 A JPH0941389 A JP H0941389A JP 19203695 A JP19203695 A JP 19203695A JP 19203695 A JP19203695 A JP 19203695A JP H0941389 A JPH0941389 A JP H0941389A
Authority
JP
Japan
Prior art keywords
temporary
block
water
dam
pedestal concrete
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP19203695A
Other languages
Japanese (ja)
Other versions
JP3599431B2 (en
Inventor
Fumio Hashimoto
文男 橋本
Iwao Murayama
盤 村山
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Toa Corp
Original Assignee
Toa Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Toa Corp filed Critical Toa Corp
Priority to JP19203695A priority Critical patent/JP3599431B2/en
Publication of JPH0941389A publication Critical patent/JPH0941389A/en
Application granted granted Critical
Publication of JP3599431B2 publication Critical patent/JP3599431B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Landscapes

  • Barrages (AREA)

Abstract

PROBLEM TO BE SOLVED: To provide the safe economical execution method of a temporary cofferdam by installing and executing the temporary cofferdam in a short period at any time regardless of the water level of a dam, etc. SOLUTION: Pedestal concrete 2 is placed on the foundation ground 5 of a dam upstream section, and each block 1 of a temporary cofferdam having double steel shell structure consisting of partition walls 11, in which opposed surfaces to the wall surface of the dam upstream form recessed sections 4, and having bottom slabs 12 in the blocks 1 in lowermost sections is bottomed on the pedestal concrete 2 while being successively joined. Water in the recessed sections 4 is drained, and the partition walls 11 are removed.

Description

【発明の詳細な説明】Detailed Description of the Invention

【0001】[0001]

【発明の属する技術分野】本発明は、既設のダム堤体の
下部に設けられた取水口などを後から増設する場合や、
沈埋トンネルの立坑の補修等を行なう場合等水中構造物
に接して仮締切を施工する際に有効な仮締切の施工方法
に関するものである。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to the case where a water intake provided at the bottom of an existing dam body is added later,
The present invention relates to a temporary deadline construction method effective when a temporary deadline is constructed in contact with an underwater structure, such as when repairing a shaft of a submerged tunnel.

【0002】[0002]

【従来技術】従来、既設のダム堤体の下部に設けられた
取水口などを増設する場合には、冬季の渇水時の低水位
期間を利用してダム堤体の上流面の地盤上に門型構造な
どの仮締切構造物を据え付けた後、取水口の増設などの
作業を行なっている。このため仮締切の施工時期が限定
され、仮締切を施工するのに数回の冬季の低水位期間が
必要となるためそれだけ施工工期が長くなり、工事費が
かさむという問題があった。また、沈埋トンネルの立坑
の補修の場合にも、仮締切を施工するのに、ほとんど潜
水夫による水中作業となるため、安全性及び経済性の面
でも問題があった。
2. Description of the Related Art Conventionally, when adding an intake, etc. provided at the bottom of an existing dam levee, the gate is located on the ground on the upstream side of the dam levee by using the low water level period during the winter drought. After installing a temporary deadline structure such as a mold structure, work such as adding an intake is performed. For this reason, the construction period of the temporary deadline is limited, and several low-water periods in winter are required to construct the temporary deadline, so that the construction period becomes longer and the construction cost becomes higher. Further, even in the case of repairing the shaft of the submerged tunnel, there is also a problem in terms of safety and economy since the construction of the temporary deadline requires almost all underwater work by the diver.

【0003】[0003]

【発明が解決しようとする課題】本発明は、前記従来の
問題点を解決するためになされたものであり、短期間に
水中構造物に接して仮締切構造物の据え付けを行なうこ
とができる安全で経済的な仮締切の施工方法を提供する
ことを目的としている。
SUMMARY OF THE INVENTION The present invention has been made to solve the above-mentioned problems of the prior art, and is a safety system capable of contacting an underwater structure in a short period of time to install a temporary shut-off structure. The purpose is to provide an economical and temporary construction method for temporary deadlines.

【0004】[0004]

【課題を解決するための手段】上記の目的を達成するた
め、本発明の仮締切の施工方法は、水中構造物に隣接し
た基礎地盤上に台座コンクリートを打設の後、その水面
上に浮設した作業足場用浮桟橋とクレーンとを使用し
て、水中構造物壁面への対向面が凹状部を形成する隔壁
を有し、さらに凹状部の周縁支承部に水密用シール材を
配置し、かつ最下部に底版を有する二重鋼殻構造の仮締
切構造物を複数のブロックに分割し、下部から上部に各
ブロックを順次接合しながら注水により沈設して台座コ
ンクリート上に着底させ、仮締切構造物の上記凹状部内
の水を排水して水中構造物に圧着させ、仮締切構造物の
下端部の周囲に台座コンクリートを打設した後、隔壁を
撤去することを特徴とするものであり、また仮締切構造
物のブロックの沈設時に、各ブロックの隔壁の二重鋼殻
構造内にバラスト材を中詰めすることを特徴としてい
る。
In order to achieve the above-mentioned object, the construction method of the temporary cut-off of the present invention is to place a pedestal concrete on the foundation ground adjacent to an underwater structure and then float it on the water surface. Using the floating pier for work scaffolding and the crane, the surface facing the underwater structure has a partition wall that forms a concave portion, and further arranges a watertight sealing material in the peripheral bearing portion of the concave portion, In addition, the temporary shut-off structure with a double steel shell structure having a bottom slab at the bottom is divided into multiple blocks, and while each block is sequentially joined from the lower part to the upper part, it is submerged by water injection and settles on the pedestal concrete, It is characterized in that after draining the water in the concave portion of the cutoff structure and crimping it to the underwater structure, after placing the pedestal concrete around the lower end of the temporary cutoff structure, the bulkhead is removed. , Also the block of the temporary shut-off structure is sunk To is characterized in that the middle packed ballast material double steel shell structure of each block partition wall.

【0005】[0005]

【発明の実施の形態】以下図面を参照して本発明の仮締
切の施工方法を用いてダム堤体に接して仮締切構造物を
据え付ける手順の一実施例を説明するが、図1はその仮
締切構造物1を台座コンクリート2上に着座した状態を
示す斜視図であり、この仮締切構造物1は、複数のブロ
ック1A、1B、1Cからなり、図2以降に示すダム堤
体3の上流壁面への対向面が凹状部4を形成する隔壁1
1を有し、しかも最下部のブロック1Aに底版12を有
する二重鋼殻構造から構成され、最下部のブロック1A
の上に次々と各ブロック1B、1Cを溶接・ボルト・ク
リップ・クサビなどで接合するものである。
BEST MODE FOR CARRYING OUT THE INVENTION An embodiment of a procedure for installing a temporary cutoff structure in contact with a dam levee using the temporary cutoff construction method of the present invention will be described below with reference to the drawings. FIG. 3 is a perspective view showing a state where the temporary cut-off structure 1 is seated on the pedestal concrete 2, and the temporary cut-off structure 1 is composed of a plurality of blocks 1A, 1B, 1C, and is shown in FIG. The partition wall 1 whose surface facing the upstream wall surface forms the concave portion 4
1 and the bottom block 1A is composed of a double steel shell structure having a bottom plate 12 on the bottom block 1A.
The blocks 1B and 1C are joined to each other one after another by welding, bolts, clips, wedges, or the like.

【0006】なお、本実施例では、仮締切構造物1を、
1A、1B、1Cの3つのブロックに分割しているが、
分割する数は3に限らず、仮締切構造物1の大きさに応
じて決定すればよい。次に、この仮締切構造物1をダム
堤体3に接して据え付ける手順につき説明すると、ダム
堤体3上流部に基礎地盤5を形成するため、図4に示す
ごとく、ダム堤体3の頂部に作業構台6を設置し、トラ
ッククレーン7の附属の密閉式グラブバケット等により
台座コンクリート2の基礎部分の沈木や塵芥等を撤去
し、台座コンクリート2施工のための測量を行う。
In this embodiment, the temporary shutoff structure 1 is
Although it is divided into 3 blocks, 1A, 1B, and 1C,
The number of divisions is not limited to 3, and may be determined according to the size of the temporary cutoff structure 1. Next, the procedure for installing the temporary cutoff structure 1 in contact with the dam dam body 3 will be described. Since the foundation ground 5 is formed in the upstream portion of the dam dam body 3, as shown in FIG. The work gantry 6 is installed in the yard, the shrubs and dust of the foundation of the pedestal concrete 2 are removed by the enclosed grab bucket attached to the truck crane 7, and surveying for the pedestal concrete 2 is performed.

【0007】その後、図5に示すように潜水夫8により
台座コンクリート2の基礎部となる基礎地盤5の清掃及
び型枠設置を行ない、コンクリートポンプ9により水中
不分離性コンクリートを打設し、所定の天端高さの台座
コンクリート2を完成する。次に、図6及びその平面図
である図7に示すごとく、打設した台座コンクリート2
の水面上に作業足場用の浮桟橋20を浮設し、アンカー
21を用いてダム3の壁面に係留し、さらに仮締切沈設
用ガイド22(図12に示す)を潜水夫8により、アン
カーボルト(図12の42)でダム面に固定する。
Thereafter, as shown in FIG. 5, the diver 8 cleans the foundation ground 5 which is the foundation of the pedestal concrete 2 and installs the formwork. Complete the pedestal concrete 2 at the ceiling height. Next, as shown in FIG. 6 and FIG. 7 which is a plan view thereof, the placed pedestal concrete 2
The floating pier 20 for work scaffolding is floated on the surface of the water, and is anchored to the wall surface of the dam 3 by using the anchor 21, and the temporary cutoff and settling guide 22 (shown in FIG. 12) is attached by the diver 8 to the anchor bolt. (42 in FIG. 12) is fixed to the dam surface.

【0008】そこで、図1のごとく複数に分割された二
重鋼殻構造の仮締切構造物1のブロックの最下部のブロ
ック1Aを、浮桟橋20及びクローラクレーン7を使用
して、所定の位置に浮かせた後、最下部のブロック1A
内に注水パイプ23で注水して次のブロック1Bを載せ
て溶接作業が行える高さまで最下部のブロック1Aを沈
設し、次のブロック1Bを載せて溶接・ボルト・クリッ
プ・クサビなどにより接合して、最終的には最下部のブ
ロック1Aの底版12が台座コンクリート2上に着底す
るまでブロックの沈設と接合作業を図8に示すように行
なうが、図8の仮締切構造物1内への注水を図2に示し
ている。
Therefore, as shown in FIG. 1, the lowermost block 1A of the block of the temporary shut-off structure 1 having a double steel shell structure is divided into a predetermined position by using the floating pier 20 and the crawler crane 7. Block 1A at the bottom after floating
Water is poured by the water injection pipe 23 and the next block 1B is placed, and the bottom block 1A is sunk to a height at which welding work can be performed, and the next block 1B is placed and joined by welding, bolts, clips, wedges, etc. Finally, until the bottom slab 12 of the bottom block 1A reaches the bottom of the pedestal concrete 2, the blocks are laid and joined as shown in FIG. 8. Water injection is shown in FIG.

【0009】なお、上記仮締切構造物1の沈設時におい
て、各ブロック1A、1B、1Cの隔壁11の二重鋼殻
構造内には、各ブロックの前壁との重量バランスを保つ
ために、各ブロックごとに前もってバラスト30を中詰
めしておくことが望ましい。なお、バラスト30として
は、砕石、砂、袋詰の砂、コンクリートブロック等固体
状のものがバランス上好ましい。
In order to maintain the weight balance with the front wall of each block in the double steel shell structure of the partition wall 11 of each block 1A, 1B, 1C when the temporary shut-off structure 1 is sunk, It is desirable to fill the ballast 30 in advance for each block. In addition, as the ballast 30, solid things such as crushed stone, sand, bagged sand, and concrete blocks are preferable in terms of balance.

【0010】また、各ブロックはクローラクレーン7に
より浮桟橋20内側に吊り降ろされて下部から上部に順
次接合されるが、底版12を有する二重鋼殻構造による
浮力を利用し、内部に注水することにより沈設が安全に
行われる。次に、仮締切構造物1の沈設終了後、図9の
状態で仮締切全体をウインチによりダム堤体3側に引き
込み、図3に示すごとく、ダム堤体3の上流壁面と仮締
切の隔壁11との間に挟まれた凹状部4内の水を注水ポ
ンプ31を用いて排水することにより、図3に示す外圧
Pと内圧との差により仮締切のブロック1はダム堤体3
面に固定される。
Each block is hung inside the floating pier 20 by the crawler crane 7 and joined in sequence from the lower part to the upper part. The buoyancy of the double steel shell structure having the bottom slab 12 is utilized to inject water into the inside. By doing so, the deposit can be performed safely. Next, after the temporary shut-off structure 1 has been sunk, the entire temporary shut-off is pulled by the winch toward the dam embankment 3 side in the state of FIG. 9, and as shown in FIG. By draining the water in the concave portion 4 sandwiched between 11 and 11, using the water injection pump 31, the block 1 of the temporary cutoff is dam dam body 3 due to the difference between the external pressure P and the internal pressure shown in FIG.
Fixed to the surface.

【0011】上記仮締切構造物1の沈設時に、ダム堤体
3の上流壁面と、それに接合する仮締切の隔壁11の外
側の凹状部4の周縁支承部14との接合部には、図12
に示すような水密用シール材40として、例えばこの実
施例ではゴムガスケットを介設しており、このゴムガス
ケットは水圧に対して所要な伸縮量を保つような諸元を
持たせている。
When the temporary shut-off structure 1 is sunk, the upstream wall surface of the dam levee body 3 is joined to the peripheral wall bearing portion 14 of the concave portion 4 on the outer side of the partition wall 11 of the temporary shut-off, which is joined to the upstream wall surface of the dam cut-off wall 3, as shown in FIG.
As the watertight sealing material 40 as shown in FIG. 3, for example, a rubber gasket is provided in this embodiment, and the rubber gasket has specifications for maintaining a required expansion / contraction amount against water pressure.

【0012】上記の仮締切構造物1の沈設後に台座コン
クリート2上の仮締切の周囲に図1に24で示す平面形
状がコの字型の残りの台座コンクリートを打設して、仮
締切構造物1の底版12に揚圧力が作用するのを防止す
る。なお、図12に示すこの実施例では、上記周縁支承
部14のゴムガスケットの周囲に、二次止水用の単泡ス
ポンジ41を挿設し、さらにこの周縁支承部14はダム
3側にアンカーボルト42で固定するようになってい
る。
After the temporary cut-off structure 1 is sunk, the remaining pedestal concrete having a U-shaped planar shape shown by 24 in FIG. 1 is placed around the temporary cut-off on the pedestal concrete 2 to form the temporary cut-off structure. The lifting pressure is prevented from acting on the bottom plate 12 of the article 1. In this embodiment shown in FIG. 12, a single-foam sponge 41 for secondary water stop is inserted around the rubber gasket of the peripheral edge support portion 14, and the peripheral edge support portion 14 is anchored to the dam 3 side. It is designed to be fixed with bolts 42.

【0013】仮締切構造物1をダム堤体3に接合後、速
やかに隔壁11を搬出可能な分割片に切断し、クローラ
クレーン17により撤去し、図10に示すごとく、仮締
切構造物1内に足場を設け、アンカーボルト50により
ダム面に仮締切構造物を固定し、ダム堤体3内の水位の
低下時の転倒防止対策とする。次に、仮締切内に階段5
1やエレベータなどを設置し、ダム堤体3の取水口60
や止水ゲート取付・スクリーン設置などの施工を行う。
After the temporary shut-off structure 1 is joined to the dam bank 3, the partition wall 11 is quickly cut into split pieces that can be carried out, and the crawler crane 17 removes the temporary shut-off structure 1, as shown in FIG. A temporary scaffolding structure is fixed to the dam surface with anchor bolts 50 to prevent falling when the water level in the dam body 3 falls. Next, stairs 5 within the temporary deadline
1 and elevator etc. are installed, and the water intake 60 of dam dam body 3
Construction such as installing a water stop gate and installing a screen.

【0014】一方、取水口60などの工事が終了した後
には、図11に示すごとく足場70を設置し、仮締切構
造物1の固定用のアンカーボルト50を撤去し、次に仮
締切構造物1内に注水を行い、各ブロックごとにクロー
ラクレーン17で吊り上げ可能な大きさに潜水夫8によ
り分割し、仮締切構造物1を撤去することになるなお、
上記実施例は、ダム堤体への適用について述べたが本発
明は、沈埋トンネルの立坑の補修、防波堤の補修等水中
構造物に接して仮締切を施工する際に適用できる。
On the other hand, after the construction of the water intake 60 and the like is completed, the scaffold 70 is installed as shown in FIG. 11, the anchor bolts 50 for fixing the temporary shut-off structure 1 are removed, and then the temporary shut-off structure. Water will be poured into 1, and each block will be divided by the diver 8 into a size that can be lifted by the crawler crane 17, and the temporary deadline structure 1 will be removed.
Although the above-described embodiment has been described as applied to a dam levee, the present invention can be applied to a temporary cutoff in contact with an underwater structure such as repair of a shaft of a submerged tunnel or repair of a breakwater.

【0015】[0015]

【発明の効果】以上に説明したように、本発明の仮締切
の施工方法によれば、仮締切構造物をトラッククレーン
などで吊り降ろし可能な最下部に底版を有する二重鋼殻
構造の複数のブロックに分割し、浮力を利用しながら順
次注水することにより、下部から上部に接合の都度沈設
させているので、潜水夫による作業が従来に比べて大幅
に削減されることになり、安全性の向上がはかれると共
に、施工の無人化及びプレハブ化がはかれて作業コスト
を低減することができる。
As described above, according to the method for constructing a temporary shutoff of the present invention, a plurality of double steel shell structures having a bottom slab at the bottom can be suspended by a truck crane or the like. Since it is divided into blocks and sequentially poured with water using buoyancy, it is submerged from the bottom to the top each time it is joined, so the work by the diver will be greatly reduced compared to the past, and safety The work cost can be reduced because the construction work is unmanned and prefabricated.

【0016】また、本発明では仮締切構造物の壁面への
対向面に凹状部を形成し、仮締切構造物の沈設完了後
に、その凹状部の水を排水することで、内外水圧差によ
りダム面に仮締切を確実に固定でき、さらに、仮締切構
造物の沈設時に各ブロックの隔壁内に砕石を中詰めして
おくことにより、各ブロックの重量バランスが良好に保
たれ、安全確実な仮締切の施工が行われうることにな
る。
Further, according to the present invention, a concave portion is formed on the surface of the temporary shutoff structure facing the wall surface, and after the temporary shutoff structure is completely sunk, the water in the concave portion is drained, whereby the water pressure difference between the inside and the outside causes the dam. The temporary cutoff can be securely fixed to the surface, and by crushing stones inside the bulkhead of each block when the temporary cutoff structure is sunk, the weight balance of each block can be maintained well and The deadline can be constructed.

【図面の簡単な説明】[Brief description of drawings]

【図1】本発明の仮締切の施工方法に適用される仮締切
構造物の一実施例に係る斜視図である。
FIG. 1 is a perspective view of an example of a temporary deadline structure applied to a temporary deadline construction method of the present invention.

【図2】図1の仮締切構造物の各ブロックを、ダム堤体
上流面の台座コンクリート上にブロック内への注水によ
り沈設する状態の説明図である。
FIG. 2 is an explanatory diagram showing a state in which each block of the temporary shut-off structure of FIG. 1 is submerged on the pedestal concrete on the upstream surface of the dam body by pouring water into the block.

【図3】図2の仮締切構造物が台座コンクリート上に着
底した状態の説明図である。
FIG. 3 is an explanatory view showing a state in which the temporary cut-off structure of FIG. 2 is bottomed on the pedestal concrete.

【図4】図1の仮締切構造物の据え付け施工時の基礎地
盤の準備の説明図である。
FIG. 4 is an explanatory diagram of preparation of the foundation ground at the time of installation and construction of the temporary cut-off structure of FIG. 1.

【図5】図4の準備の後、台座コンクリートの打設を示
す説明図である。
FIG. 5 is an explanatory view showing pouring of pedestal concrete after the preparation of FIG.

【図6】図5の後の仮締切施工の準備の説明図である。FIG. 6 is an explanatory diagram of preparation for temporary shutoff construction after FIG. 5;

【図7】図6の要部平面図である。FIG. 7 is a plan view of a main part of FIG. 6;

【図8】図6の後の仮締切構造物のブロックの沈設の説
明図である。
FIG. 8 is an explanatory view of the sunk block of the temporary shutoff structure after FIG. 6;

【図9】図8のブロックの沈設後の内外水圧差により仮
締切構造物をダム堤体側に接合する説明図である。
9 is an explanatory view of joining the temporary shutoff structure to the dam levee side by the difference in internal and external water pressure after the block of FIG. 8 is sunk.

【図10】図9の後の仮締切構造物の隔壁撤去の説明図
である。
10 is an explanatory view of removing the partition wall of the temporary shut-off structure after FIG.

【図11】図10による仮締切施工後の仮締切構造物の
撤去の説明図である。
FIG. 11 is an explanatory diagram of removal of the temporary deadline structure after the temporary deadline construction according to FIG. 10;

【図12】図1の仮締切構造物の周縁支承部要部の拡大
平断面図である。
FIG. 12 is an enlarged plan sectional view of a main part of a peripheral edge support portion of the temporary cut-off structure of FIG.

【符号の説明】[Explanation of symbols]

1 仮締切構造物 2 台座コンク
リート 3 ダム堤体 4 凹状部 5 基礎地盤 11 隔壁 12 底版 14 周縁支承
部 20 浮桟橋 30 バラスト
材 40 水密用シール材
1 Temporary cut-off structure 2 Pedestal concrete 3 Dam embankment 4 Recessed part 5 Foundation ground 11 Partition wall 12 Bottom plate 14 Perimeter support part 20 Floating pier 30 Ballast material 40 Watertight sealing material

Claims (2)

【特許請求の範囲】[Claims] 【請求項1】 水中構造物に隣接した基礎地盤上に台座
コンクリートを打設の後、その水面上に浮設した作業足
場用浮桟橋とクレーンとを使用して、水中構造物壁面へ
の対向面が凹状部を形成する隔壁を有し、さらに凹状部
の周縁支承部に水密用シール材を配置し、かつ最下部に
底版を有する二重鋼殻構造の仮締切構造物を複数のブロ
ックに分割し、下部から上部に各ブロックを順次接合し
ながら注水により沈設して台座コンクリート上に着底さ
せ、仮締切構造物の上記凹状部内の水を排水して水中構
造物に圧着させ、仮締切構造物の下端部の周囲に台座コ
ンクリートを打設した後、隔壁を撤去する仮締切の施工
方法。
1. After placing a pedestal concrete on a foundation ground adjacent to an underwater structure, facing a surface of the underwater structure by using a floating scaffold for work scaffolding and a crane which are floated on the water surface. The surface has a partition wall forming a concave portion, the watertight sealing material is further arranged on the peripheral support of the concave portion, and the temporary shut-off structure of the double steel shell structure having the bottom plate at the bottom is divided into a plurality of blocks. Divide it into blocks by sequentially joining each block from the bottom to the top and pour it on the pedestal concrete by pouring water to the bottom, drain the water in the concave part of the temporary cutoff structure and crimp it to the underwater structure, and make a temporary cutoff. A construction method of a temporary deadline in which the partition wall is removed after placing pedestal concrete around the lower end of the structure.
【請求項2】 仮締切構造物のブロックの沈設時に、各
ブロックの隔壁の二重鋼殻構造内にバラスト材を中詰め
する請求項1記載の仮締切の施工方法。
2. The method for constructing a temporary cutoff according to claim 1, wherein when the block of the temporary cutoff structure is sunk, the ballast material is filled in the double steel shell structure of the partition wall of each block.
JP19203695A 1995-07-27 1995-07-27 Construction method of temporary deadline Expired - Fee Related JP3599431B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP19203695A JP3599431B2 (en) 1995-07-27 1995-07-27 Construction method of temporary deadline

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP19203695A JP3599431B2 (en) 1995-07-27 1995-07-27 Construction method of temporary deadline

Publications (2)

Publication Number Publication Date
JPH0941389A true JPH0941389A (en) 1997-02-10
JP3599431B2 JP3599431B2 (en) 2004-12-08

Family

ID=16284543

Family Applications (1)

Application Number Title Priority Date Filing Date
JP19203695A Expired - Fee Related JP3599431B2 (en) 1995-07-27 1995-07-27 Construction method of temporary deadline

Country Status (1)

Country Link
JP (1) JP3599431B2 (en)

Cited By (13)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100499072B1 (en) * 2002-11-16 2005-07-05 주식회사 엠디건설 coffering structure with hydraulic pressure or self load and the construction or repairing method using the same
KR100647091B1 (en) * 2005-01-10 2006-11-23 명보산공 주식회사 Method of repairing a constructive material in water and device thereof
JP2007231676A (en) * 2006-03-02 2007-09-13 Shimizu Corp Cut-off device and through-hole forming method
JP2008095330A (en) * 2006-10-10 2008-04-24 Penta Ocean Construction Co Ltd Work caisson for temporary cofferdam
KR100837635B1 (en) * 2007-04-17 2008-06-12 이중우 Sector caisson for maintenance of the large underwater structures
JP2009180018A (en) * 2008-01-31 2009-08-13 Jfe Engineering Corp Method of constructing cofferdam for underwater structure and structure for cofferdam
KR100936161B1 (en) * 2009-07-31 2010-01-12 현대엔지니어링 주식회사 Nature friendly polygon cell type coffering method for harbor, river and dam construction
KR100949239B1 (en) * 2007-07-12 2010-03-24 한국전력공사 Temporary levee protector
JP2013091923A (en) * 2011-10-24 2013-05-16 Chugoku Electric Power Co Inc:The Cofferdam structure and construction method for the same
JP2013124510A (en) * 2011-12-15 2013-06-24 Ohbayashi Corp Construction method for dam body cofferdam structure
WO2014156864A1 (en) * 2013-03-27 2014-10-02 鹿島建設株式会社 Construction method for temporary floating cofferdam
CN110172985A (en) * 2019-06-27 2019-08-27 四川公路桥梁建设集团有限公司 A kind of interlocking pile-double-wall steel combined cofferdam connection structure and construction manipulation process
CN113737780A (en) * 2021-09-01 2021-12-03 中国水利水电第六工程局有限公司 Underwater rock-socketed concrete pile and construction method thereof

Cited By (14)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100499072B1 (en) * 2002-11-16 2005-07-05 주식회사 엠디건설 coffering structure with hydraulic pressure or self load and the construction or repairing method using the same
KR100647091B1 (en) * 2005-01-10 2006-11-23 명보산공 주식회사 Method of repairing a constructive material in water and device thereof
JP2007231676A (en) * 2006-03-02 2007-09-13 Shimizu Corp Cut-off device and through-hole forming method
JP2008095330A (en) * 2006-10-10 2008-04-24 Penta Ocean Construction Co Ltd Work caisson for temporary cofferdam
KR100837635B1 (en) * 2007-04-17 2008-06-12 이중우 Sector caisson for maintenance of the large underwater structures
KR100949239B1 (en) * 2007-07-12 2010-03-24 한국전력공사 Temporary levee protector
JP2009180018A (en) * 2008-01-31 2009-08-13 Jfe Engineering Corp Method of constructing cofferdam for underwater structure and structure for cofferdam
KR100936161B1 (en) * 2009-07-31 2010-01-12 현대엔지니어링 주식회사 Nature friendly polygon cell type coffering method for harbor, river and dam construction
JP2013091923A (en) * 2011-10-24 2013-05-16 Chugoku Electric Power Co Inc:The Cofferdam structure and construction method for the same
JP2013124510A (en) * 2011-12-15 2013-06-24 Ohbayashi Corp Construction method for dam body cofferdam structure
WO2014156864A1 (en) * 2013-03-27 2014-10-02 鹿島建設株式会社 Construction method for temporary floating cofferdam
JP2014190073A (en) * 2013-03-27 2014-10-06 Kyushu Regional Development Bureau Ministry Of Land Infrastructure & Transport Construction method for temporary floating cofferdam
CN110172985A (en) * 2019-06-27 2019-08-27 四川公路桥梁建设集团有限公司 A kind of interlocking pile-double-wall steel combined cofferdam connection structure and construction manipulation process
CN113737780A (en) * 2021-09-01 2021-12-03 中国水利水电第六工程局有限公司 Underwater rock-socketed concrete pile and construction method thereof

Also Published As

Publication number Publication date
JP3599431B2 (en) 2004-12-08

Similar Documents

Publication Publication Date Title
US4073148A (en) Precast element for the construction of trenched structures and the process related thereto
JP3599431B2 (en) Construction method of temporary deadline
KR20070090733A (en) Waterproof open caisson assembly and concrete foundation construction method using the same
CN109648696A (en) Side slope precast lattice beam of reinforcing bar connection and preparation method thereof and construction method
Rasmussen Concrete immersed tunnels—Forty years of experience
JP4206165B2 (en) Temporary deadline construction method
CN111676900B (en) Slope type seawall and construction method thereof
JP2000290936A (en) Method and caisson for constructing bridge pier footing
JP2681503B2 (en) Steel sink and its installation method
CN211172070U (en) Assembled type suspended wall retaining wall structure of reinforced concrete member
JPS6310243B2 (en)
JP2004162426A (en) Foundation cell, cell foundation structure, and construction method for cell foundation structure
JP2949341B1 (en) Underwater girder construction method
CN113684849B (en) Steel sheet pile cofferdam supporting and anti-collision conversion structure and construction method
JP7467291B2 (en) Method for constructing a concrete structure
JPH0219252B2 (en)
JP2581602B2 (en) Waste treatment method
JP4250945B2 (en) Cell foundation structure and cell foundation construction method
JPH08120657A (en) Cereation of artificial water-surface ground
Duddeck et al. Design criteria for immersed tube tunnels: Experience from the autobahn tunnel under the river Ems
CN118065298A (en) Ship lock berthing section ship-leaning and flow-isolating structure and construction method thereof
JPH0258631A (en) Execution of caisson
JPH01169397A (en) Building foundation structure of nuclear power generation plant
JPS61155514A (en) Placement work of mass concrete
CN110042796A (en) A kind of New-Type Wharf construction method suitable for batholith

Legal Events

Date Code Title Description
TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20040907

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20040914

R150 Certificate of patent (=grant) or registration of utility model

Free format text: JAPANESE INTERMEDIATE CODE: R150

FPAY Renewal fee payment (prs date is renewal date of database)

Free format text: PAYMENT UNTIL: 20100924

Year of fee payment: 6

FPAY Renewal fee payment (prs date is renewal date of database)

Free format text: PAYMENT UNTIL: 20100924

Year of fee payment: 6

FPAY Renewal fee payment (prs date is renewal date of database)

Free format text: PAYMENT UNTIL: 20110924

Year of fee payment: 7

FPAY Renewal fee payment (prs date is renewal date of database)

Free format text: PAYMENT UNTIL: 20110924

Year of fee payment: 7

FPAY Renewal fee payment (prs date is renewal date of database)

Free format text: PAYMENT UNTIL: 20120924

Year of fee payment: 8

FPAY Renewal fee payment (prs date is renewal date of database)

Free format text: PAYMENT UNTIL: 20130924

Year of fee payment: 9

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

LAPS Cancellation because of no payment of annual fees