JPH09165758A - Pile structure joined with floor slab connected to resin foam and application method of the pile - Google Patents

Pile structure joined with floor slab connected to resin foam and application method of the pile

Info

Publication number
JPH09165758A
JPH09165758A JP35172495A JP35172495A JPH09165758A JP H09165758 A JPH09165758 A JP H09165758A JP 35172495 A JP35172495 A JP 35172495A JP 35172495 A JP35172495 A JP 35172495A JP H09165758 A JPH09165758 A JP H09165758A
Authority
JP
Japan
Prior art keywords
pile
floor slab
piles
ground
foamed resin
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP35172495A
Other languages
Japanese (ja)
Other versions
JP3155456B2 (en
Inventor
Takuzo Nakamura
拓造 中村
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Nakamura Bussan Co Ltd
Original Assignee
Nakamura Bussan Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Nakamura Bussan Co Ltd filed Critical Nakamura Bussan Co Ltd
Priority to JP35172495A priority Critical patent/JP3155456B2/en
Publication of JPH09165758A publication Critical patent/JPH09165758A/en
Application granted granted Critical
Publication of JP3155456B2 publication Critical patent/JP3155456B2/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Landscapes

  • Foundations (AREA)

Abstract

PROBLEM TO BE SOLVED: To dispense with the curing temporary work for piling and reduce the required number of piles, by using a light replacing material in a piling method for a soft ground. SOLUTION: Paving sand 8 and geogrit or civilwork sheet 7 are laid on the ground excavated in advance and a leveling bed is placed and a light replacing material 5 like polystyrene blocks is laid thereon, and further, reinforcements 2 are arranged thereon and concrete is placed to form a floor slab 1. A piling machine is moved on the floor slab 1 to drive piles 3 from a piling space 4 secured in advance on the floor slab 1 and concrete is charged in the floor slab 1. The decreased value of the subsidence stress resulting from the light replacing material 5 is added in the calculation of the supporting force of the pile 3. Accordingly, the material 5 dispenses with the curing temporary work for the piling machine and the required number of piles is reduced.

Description

【発明の詳細な説明】Detailed Description of the Invention

【0001】「産業上の利用分野」この発明は、軟弱地
盤における、対策工法の一つである杭工法において、発
泡樹脂材に接続する床版と接合する杭構造、及び杭使用
工法に関するものである。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a pile construction method which is one of the countermeasure construction methods in soft ground and is joined to a floor slab connected to a foamed resin material, and a construction method using piles. is there.

【0002】「従前の技術」従来、軟弱地盤における杭
工法は、構造物の沈下増加応力が軟弱地盤の反力を上回
る為に、杭の支持力で沈下対策を行って来ている。ま
た、杭打設方法は、杭打設機材の重量が、軟弱地盤の地
盤反力を上回るために、様々な地盤改良工法を行ったあ
とでなければ、作業ができなかったり、杭打設のため
の、養生仮設工事が必要となり、費用と期間が、多く費
やされて来た、また、杭の支持力を計算する場合、発泡
樹脂材で軽減される沈下増加応力軽減量は、計算されて
いなかったものである。
[Prior Art] Conventionally, in the pile construction method on soft ground, since the increasing stress of subsidence of a structure exceeds the reaction force of the soft ground, the pile supporting force has been used as a countermeasure against subsidence. In addition, the pile driving method is such that the weight of the pile driving equipment exceeds the ground reaction force of the soft ground, so the work cannot be performed or the pile driving can be performed only after performing various ground improvement methods. In order to calculate the bearing capacity of the pile, the amount of settlement increase stress that is reduced by the foamed resin material is calculated. I didn't.

【0003】「発明が解決しようとする課題」従来の杭
工法は、上記の通り、軟弱地盤においては地盤改良等、
打設のための養生仮設工事が必要であり、工事が面倒
で、しかも 時間が掛かる、また、発泡樹脂材で沈下増
加応力を軽減する事によって杭の本数も少なくなり、そ
の分工事費が安くなり工事期間も短くなるという利点が
ある、本発明は、上記従来の杭工法の問題点を解決する
とともに、軟弱地盤における、建物、道路、水路、地下
構造物等、種々の基礎の用途にきょうすることが可能
な、杭構造、及び杭工法を提供するものである。
[Problems to be Solved by the Invention] As described above, the conventional pile construction method is as follows.
Curing temporary work for placing is required, which is troublesome and time consuming, and the number of piles is reduced by reducing the increase in sinking stress with the foamed resin material, which reduces the construction cost accordingly. The present invention has an advantage that the construction period is shortened, and the present invention solves the problems of the above-mentioned conventional pile construction method, and is applicable to various foundations such as buildings, roads, waterways, and underground structures in soft ground. It is possible to provide a pile structure and a pile construction method.

【0004】「課題を解決するための手段」ここで、こ
のような従前の欠点を改良するために、所定の厚さ、
並びに必要な面積に配置した発泡樹脂材に接続する床版
と、、杭が接合することを特徴とする杭構造 や、前
記の杭構造の接合方法において、床版と杭とがコンクリ
ートを用いて接合、又は床版の下部と杭の頭部に、緩衝
材を介して接合することを特徴とする杭構造や、接合
方法に於いて、杭の頭部と緩衝材の間に盤を介して接合
することを特徴とする杭構造や所定の厚さ並びに必要
な面積に施工した発泡樹脂材に接続する床版からなる盤
に、杭打設機材が載り、床版に予め設けた、杭打設のた
めの空間から杭を打設し、床版と杭を接合することを特
徴とする、杭の使用工法や、軟弱地盤において、杭打
設機材の重量によって、盤が沈下しない量の発泡樹脂材
を地盤に設置する、発泡材の算出方法は、杭打ち作業を
する床版面積にたいする地盤が沈下しない地盤反力を求
め、次に杭打設機材の沈下増加応力が、地盤反力を上回
らないか計算する、地盤反力を上回る場合は、地盤を掘
削し土を発泡樹脂材で、置き換え沈下しない沈下増加応
力軽減必要量を算出する、この様な計算にもとずいて作
られた床版上において、杭を打設することを特徴とする
杭の使用方法や、杭の支持力計算において、発泡樹脂
材並びに床版によって、地盤に対する沈下増加応力の軽
減量を杭の支持力に加算することを、特徴とする杭の使
用工法を提供しようとするものである。本発明にかかる
発泡樹脂材に接続する床版と接合する杭構造、及びその
使用工法は、以下の実施形態から明らかになるであろ
う。
"Means for Solving the Problems" Here, in order to improve such a conventional defect, a predetermined thickness,
In addition, in the pile structure characterized by the fact that the pile is joined to the floor slab connected to the foamed resin material arranged in the necessary area, and in the above-mentioned method of joining the pile structure, the floor slab and the pile are made of concrete. Joining, or a pile structure characterized by joining to the bottom of the floor slab and the head of the pile via a cushioning material, and in the joining method, a board is interposed between the head of the pile and the cushioning material. Pile driving equipment is placed on a board consisting of a pile structure characterized by joining and a floor slab connected to a foamed resin material constructed in a predetermined thickness and required area. Pile is driven from the space for installation, and the floor slab and the pile are joined, and the amount of foam that does not sink due to the weight of pile driving equipment in the method of using the pile and the soft ground. The method of calculating the foam material, which installs the resin material on the ground, is based on the area of the floor slab where the pile work is performed. Calculate the ground reaction force that does not cause subsidence, and then calculate whether the increase stress of subsidence of the pile driving equipment exceeds the ground reaction force.If the ground reaction force exceeds the ground reaction force, excavate the ground with foamed resin material, Calculation of the amount of stress required to reduce the amount of subsidence that does not cause replacement settlement. A method of using piles characterized by placing piles on floor slabs made on the basis of such calculations and bearing capacity of piles. In the calculation, an attempt is made to provide a method of using a pile, which is characterized in that the reduction amount of the increased settlement stress to the ground is added to the pile supporting force by the foamed resin material and the floor slab. The pile structure joined to the floor slab connected to the foamed resin material according to the present invention and the method of using the same will be apparent from the following embodiments.

【0005】「発明の実施の形態」以下、この発明の実
施例を表−1の工法の手順で、図−1全体の斜視図、図
−2盤の断面図、にもとずいて説明する。
BEST MODE FOR CARRYING OUT THE INVENTION Hereinafter, an embodiment of the present invention will be described with reference to the procedure of the construction method shown in Table 1 based on the perspective view of the whole of FIG. 1 and the sectional view of the FIG. .

【0006】調査段階として,(1)地質調査を行い、
地盤の長期許容支持力を求める、次に、(2)構造物の
計画沈下増加応力を求め、(3)必要とする、長期許容
支持力を求め、対策工法を検討する。
At the survey stage, (1) geological survey is conducted,
Obtain the long-term allowable bearing capacity of the ground, then (2) obtain the planned subsidence stress of the structure, and (3) obtain the required long-term acceptable bearing capacity, and examine the countermeasure construction method.

【0007】設計について、説明する、(4)杭から得
られる支持力と軽量置き換え材による沈下増加応力軽減
量を、構造物の構造計算から、杭と発泡樹脂材の使用数
量を計算する、(5)は、盤の割り付け図である、
(4)で求められた数量から、杭の数量、軽量置き換え
材の厚さ面積を求め、盤の割り付け図を作成する。
The design will be explained. (4) Calculate the bearing capacity obtained from piles and the amount of stress reduction due to subsidence due to the lightweight replacement material, and the quantity of piles and foamed resin material used from the structural calculation of the structure. 5) is a layout diagram of the board,
From the quantity obtained in (4), find the quantity of piles and the thickness area of the lightweight replacement material, and create a board allocation diagram.

【0008】計算例について、説明する、調査、設計条
件から、A)構造物の沈下増加応力3.0tf/m
B)地盤の長期許容支持力1.0tf/m C)杭の
長期許容支持力0.8tf/m D)土と置き換えた
発泡ポリスチレンブロックによる沈下増加応力減少量
2.055tf/m E)床版の沈下増加応力0.2
5tf/m F)杭打設機材の沈下増加応力0.8t
f/m安全率Fs=1.2とすれば、 A×Fs〈(B+C+D−E) 3.6tf/m〈3.830tf/m従って構造物
の沈下増加応力による沈下は無い。次に、杭打設機材が
盤に載り、杭打設作業をする場合の沈下に対する計算
は、 F×Fs〈B+D−E 0.96tf/m〈2.805tf/m従って沈下
は無い、
From the investigation and design conditions, which will be described with respect to calculation examples, A) an increase in the settlement of the structure of 3.0 tf / m 2
B) Long-term allowable bearing capacity of ground 1.0 tf / m 2 C) Long-term allowable bearing capacity of pile 0.8 tf / m 2 D) Increase in settlement due to expanded polystyrene block replacing soil 2.055 tf / m 2 E ) Floor slab sinking stress 0.2
5tf / m 2 F) Increase in sinking stress of pile driving equipment 0.8t
If f / m 2 safety factor Fs = 1.2, A × Fs <(B + C + D−E) 3.6 tf / m 2 <3.830 tf / m 2 Therefore, there is no subsidence due to the increase in subsidence of the structure. Next, when the pile driving equipment is mounted on the panel and the pile driving work is performed, the calculation for the settlement is F × Fs <B + DE 0.96tf / m 2 <2.805tf / m 2 Therefore, there is no settlement.

【0009】施工について、説明する、(6)は、地盤
基面工である、予め掘削した地盤にたいし、レベリン
グ層を施工する、レベリング層は、一般には、敷砂し
調整するが、床が乱れる場合は、敷砂とジオグリッ
ト又は土木シートを敷いてレベリング層を施工する。
(7)は、置き換え材設置工である、軽量置き換え材
の材質は、発泡ポリスチレンブロックが好ましいが、必
要な強度が有れば、他の発泡樹脂でも、発泡樹脂とコン
クリートを混合した、発泡樹脂材でも良い、(8)は、
床版工である、床版は、(7)の上に、床版補強の為
鉄筋を配筋し、杭スペースを確保して、コンクリー
トを打設する、(9)は、杭工である、杭は、地盤掘
削の前に打設しても、床版が出来上がってから打設し
ても良い、但し、杭打設の為の養生仮設工事が必要な場
合は、床版を利用すれば、養生仮設工事の費用と工期が
省かれ経済的である、床版を利用する場合の説明をす
る、杭打設機材は床版上を移動して、床版に予め確保し
た杭スペースから、杭を打設する、▲10▼杭の頭
部の位置は、床版の下でも、中間でも、上の面でも良い
が、振動、地震による振動を考慮すれば、床版下の部分
が良い、(10)は、杭頭部と床版接合工である、床
版の杭スペースに、鉄筋で床版を補強して、▲11
▼コンクリート充填接合する、図−2は、床版の下で接
合する場合、▲10▼杭頭部に▲12▼定磐、緩衝材
を介して床版と接合する、▲12▼定盤は、▲10▼
杭頭部の面積より、大きくし、床版から緩衝材を介
して▲10▼杭頭部に伝達する荷重を分散して緩衝材
を保護する為に用いる、緩衝材の材質は、ゴムであっ
ても発泡樹脂材、例えば発泡ポリプロピレンでも、杭の
支持力を上回る圧縮強度が有れば良い、例えば、杭の支
持力1本当たり、50トンとした場合、▲12▼定磐と
緩衝材の面積を1mとしたら緩衝材の圧縮強度
は、5Kg/cmに安全率20%を加算した6Kgf
/cmが必要である、この構造は、地震にたいする免
振構造にもなる。この発明は、このような発泡樹脂材に
接続する床版と接合する杭構造、及び杭の使用工法によ
る、構造物の沈下対策並びに土圧軽減工法を提供するも
のである。
The construction will be explained. (6) is a ground foundation work, in which a leveling layer is applied to the previously excavated ground. The leveling layer is generally laid with sand, and the floor is adjusted. If it is disturbed, lay sand and geogrid or civil engineering sheets and apply a leveling layer.
(7) is a replacement material installation work. The material of the lightweight replacement material is preferably a foam polystyrene block, but if the required strength is satisfied, other foam resins may be mixed with foam resin and concrete foam resin. Material (8) is
The floor slab, which is a floor slab, arranges reinforcing bars for reinforcing the floor slab on (7), secures a pile space, and places concrete. (9) is a pile slab. The piles may be placed before ground excavation or after the floor slab is completed. However, if curing temporary construction for pile placement is necessary, use the floor slab. For example, the cost and construction period for temporary curing work will be saved, and it will be economical. We will explain the case of using a floor slab. The pile head may be placed under the floor slab, in the middle, or on the upper surface, but if the vibration and the vibration due to an earthquake are taken into consideration, the part under the floor slab may be placed. Good (10) is the joint between the pile head and the floor slab. In the pile space of the floor slab, the floor slab is reinforced with reinforcing bars.
▼ Concrete filling joining, Fig. 2 shows when joining under the floor slab, ▲ 10 ▼ Pile heads ▲ 12 ▼ fixed lantern, joining with floor slab via cushioning material, ▲ 12 ▼ surface plate , ▲ 10 ▼
The cushioning material is rubber that is larger than the area of the pile head and is used to protect the cushioning material by distributing the load transmitted from the floor slab to the pile head through the cushioning material (10). However, even a foamed resin material, such as foamed polypropylene, should have a compressive strength that exceeds the bearing capacity of the pile. For example, if the bearing capacity of a pile is 50 tons, (12) If the area is set to 1 m 2 , the compressive strength of the cushioning material is 6 Kgf obtained by adding 20% of safety factor to 5 Kg / cm 2.
This structure, which requires / cm 2, is also an isolation structure against earthquakes. The present invention provides a pile structure joined to a floor slab connected to such a foamed resin material, and a construction settlement countermeasure and a soil pressure reducing construction method by a construction method using the pile.

【0010】「発明の効果」この発明に係る発泡樹脂材
に接続する床版と接合する杭構造、及び杭使用工法は、
杭と軽量軽量置き換え材を使用するため、構造物の沈下
対策、土圧軽減が非常に簡単に出来、発泡樹脂材にたい
する水による浮力にも安全施工出来る、また、杭の仮設
工事が無いので工事期間が短くて済み、従来工法より経
済的にも安価に提供出来るという効果をも有するもので
ある。
[Advantages of the Invention] The pile structure joined to the floor slab connected to the foamed resin material and the method of using the pile according to the present invention are
Since piles and lightweight replacement materials are used, it is very easy to take measures against subsidence of structures and reduce earth pressure, and it is possible to safely construct buoyancy due to water against foamed resin materials. Also, there is no temporary construction work for piles. It also has the effect that the period is short and it can be provided economically and cheaply as compared with the conventional method.

【図面の簡単な説明】 [Brief description of the drawings]

【図−1】 全体斜視図FIG. 1 is an overall perspective view

【図−2】 盤断面図[Fig.-2] Board cross section

【符号の説明】[Explanation of symbols]

(1) 地質調査 (2) 構造物の計画沈下応力 (3) 必要とする長期支持力 (4) 杭の支持力と軽量置き換え材増加応力軽減量
を計算する (5) 盤の割り付け図作成 (6) 地盤基面工 (7) 置き換え材設置工 (8) 床版工 (9) 杭打設工 (10) 杭頭部と床版接合工 (11) 床版上の構造物施工 床版 鉄筋 杭 杭スペース 発泡ポリスチレン レベリング層 ジオグリット又は土木シート 敷砂 緩衝材 ▲10▼ 杭頭部 ▲11▼ 充填コンクリート ▲12▲ 定盤
(1) Geological survey (2) Planned settlement stress of structure (3) Required long-term bearing capacity (4) Pile bearing capacity and light weight replacement material increase stress reduction amount calculation (5) Board allocation diagram creation ( 6) Ground foundation work (7) Replacement material installation work (8) Floor slab work (9) Pile driving work (10) Pile head and floor slab joint work (11) Construction of floor slab floor slab Pile Pile space Expanded polystyrene leveling layer Geogrid or civil engineering sheet Soil cushioning material ▲ 10 ▼ Pile head ▲ 11 ▼ Filled concrete ▲ 12 ▲ Surface plate

Claims (6)

【特許請求の範囲】[Claims] 【請求項1】所定の厚さ、並びに必要な面積に配置した
発泡樹脂材に接続する床版と、杭が接合することを特徴
とする杭構造。
1. A pile structure in which a pile is joined to a floor slab connected to a foamed resin material arranged in a predetermined thickness and a required area.
【請求項2】請求項1記載の杭構造の接合方法におい
て、床版と杭とがコンクリートを用いて接合、又は床版
の下部と杭の頭部に、緩衝材を介して接合することを特
徴とする杭構造。
2. The method for joining a pile structure according to claim 1, wherein the floor slab and the pile are joined using concrete, or the lower part of the floor slab and the head of the pile are joined via a cushioning material. Characteristic pile structure.
【請求項3】請求項2記載の接合方法に於いて、杭の頭
部と緩衝材の間に盤を介して、接合することを特徴とす
る杭構造。
3. The pile structure according to claim 2, wherein the head of the pile and the cushioning material are joined via a board.
【請求項4】所定の厚さ並びに必要な面積に施工した発
泡樹脂材に接続する床版からなる盤に、杭打設機材が載
り、床版に予め設けた杭打設のための空間から杭を打設
し、床版と杭を接合することを特徴とする杭の使用工
法。
4. A pile driving equipment is placed on a board made of a floor slab connected to a foamed resin material having a predetermined thickness and a required area, and a space for pile driving is provided in advance on the floor slab. A method of using piles, which comprises placing the piles and joining the slab to the piles.
【請求項5】軟弱地盤において、杭打設機材の重量によ
って、盤が沈下しない量の発泡樹脂材を地盤に設置す
る、発泡材の算出方法は、杭打ち作業する床版面積にた
いする地盤が沈下しない地盤反力を求め、次に杭打設機
材の沈下応力が、地盤反力を上回らないか計算する、地
盤反力を上回る場合は、地盤を掘削し土を発泡樹脂材で
置き換え沈下しない沈下増加応力軽減必要量を算出す
る、この様な計算にもとずいて作られた床版上におい
て、杭を打設することを特徴とする杭の使用工法。
5. In soft ground, the amount of foamed resin material that does not sink due to the weight of pile driving equipment is set on the ground. The method of calculating foam material is as follows: Calculate the ground reaction force, and then calculate whether the settlement stress of the pile driving equipment will exceed the ground reaction force.If it exceeds the ground reaction force, excavate the ground and replace the soil with a foamed resin material. A method of using piles, which comprises placing piles on a floor slab made based on such calculation to calculate the amount of increase in stress reduction requirements.
【請求項6】杭の支持力計算において、発泡樹脂材並び
に床版によって、地盤に対する沈下増加応力の軽減量を
杭の支持力に加算することを特長とする杭の使用工法。
6. A method of using a pile, characterized in that, in the calculation of the pile bearing capacity, a reduction amount of the increased settlement stress to the ground is added to the pile bearing capacity by the foamed resin material and the floor slab.
JP35172495A 1995-12-16 1995-12-16 Pile structure to be joined to floor slab connected to foam resin material, and construction method of pile structure Expired - Lifetime JP3155456B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP35172495A JP3155456B2 (en) 1995-12-16 1995-12-16 Pile structure to be joined to floor slab connected to foam resin material, and construction method of pile structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP35172495A JP3155456B2 (en) 1995-12-16 1995-12-16 Pile structure to be joined to floor slab connected to foam resin material, and construction method of pile structure

Publications (2)

Publication Number Publication Date
JPH09165758A true JPH09165758A (en) 1997-06-24
JP3155456B2 JP3155456B2 (en) 2001-04-09

Family

ID=18419190

Family Applications (1)

Application Number Title Priority Date Filing Date
JP35172495A Expired - Lifetime JP3155456B2 (en) 1995-12-16 1995-12-16 Pile structure to be joined to floor slab connected to foam resin material, and construction method of pile structure

Country Status (1)

Country Link
JP (1) JP3155456B2 (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US6318031B1 (en) 1998-11-19 2001-11-20 Nakamura Bussan Co., Ltd. Base structure of building and construction method thereof
JP2009084981A (en) * 2007-10-03 2009-04-23 Shimizu Corp Heat insulating curing method of mass concrete

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US6318031B1 (en) 1998-11-19 2001-11-20 Nakamura Bussan Co., Ltd. Base structure of building and construction method thereof
JP2009084981A (en) * 2007-10-03 2009-04-23 Shimizu Corp Heat insulating curing method of mass concrete

Also Published As

Publication number Publication date
JP3155456B2 (en) 2001-04-09

Similar Documents

Publication Publication Date Title
JP3327191B2 (en) Underground structure and its construction method
CN103958780B (en) The method for forming cementing retaining wall
JP2000154550A (en) Vibration control footing structure in building and construction method therefor
JP2005016196A (en) Construction method for embankment on backside of substructure
CN102066669A (en) Elastic construction foundation method
JP2002129584A (en) Foundation structure
JPS62260919A (en) Small pile for reinforcing foundation ground to earthquake
KR20030097084A (en) Construction Method of Reinforced Earth Retaining-Wall for using Anchoring
JPH09165758A (en) Pile structure joined with floor slab connected to resin foam and application method of the pile
Deni et al. Low-Density Cellular Concrete in MSE Structures with Steel Strip Reinforcements—Design and Construction Considerations and Case Histories
JP2004339894A (en) Aseismic reinforcement structure of pile foundation structure
JP3230448B2 (en) Construction method of building foundation on cohesive ground
US4519730A (en) Method for constructing underground structure
KR100819379B1 (en) Concrete construction using hydraulic system and anti-noise non-vibration manufacturing method of concrete construction
KR101973657B1 (en) Inverted Arcuate Structure to prevent Lateral Flow of the Bridge Abutments and Reparing Method using the Same
JP2010090534A (en) Reinforcement structure of paved road
JP4612356B2 (en) How to create a slope
JP4189078B2 (en) Construction method of underground structure in liquefied ground
JP2006037342A (en) Lightweight landfill and construction method therefor
KR102608230B1 (en) Undergroud structure in embankment and construction method thereof
KR102667832B1 (en) Design method of underground exterior wall using PHC retaining wall as permanent exterior wall
JP7314432B1 (en) Foundation structure of building and construction method of foundation structure
JPH07279184A (en) Floating underground beam foundation for building
JP7401362B2 (en) building foundation structure
JP2003049429A (en) Elevated structure and its construction method

Legal Events

Date Code Title Description
R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

FPAY Renewal fee payment (prs date is renewal date of database)

Free format text: PAYMENT UNTIL: 20090202

Year of fee payment: 8

FPAY Renewal fee payment (prs date is renewal date of database)

Free format text: PAYMENT UNTIL: 20100202

Year of fee payment: 9

FPAY Renewal fee payment (prs date is renewal date of database)

Free format text: PAYMENT UNTIL: 20110202

Year of fee payment: 10

FPAY Renewal fee payment (prs date is renewal date of database)

Free format text: PAYMENT UNTIL: 20110202

Year of fee payment: 10

FPAY Renewal fee payment (prs date is renewal date of database)

Free format text: PAYMENT UNTIL: 20120202

Year of fee payment: 11

FPAY Renewal fee payment (prs date is renewal date of database)

Free format text: PAYMENT UNTIL: 20130202

Year of fee payment: 12

FPAY Renewal fee payment (prs date is renewal date of database)

Free format text: PAYMENT UNTIL: 20140202

Year of fee payment: 13

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

EXPY Cancellation because of completion of term