JPH09128440A - Production planning method and system using it - Google Patents

Production planning method and system using it

Info

Publication number
JPH09128440A
JPH09128440A JP28130395A JP28130395A JPH09128440A JP H09128440 A JPH09128440 A JP H09128440A JP 28130395 A JP28130395 A JP 28130395A JP 28130395 A JP28130395 A JP 28130395A JP H09128440 A JPH09128440 A JP H09128440A
Authority
JP
Japan
Prior art keywords
production
item
shop
amount
completion
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP28130395A
Other languages
Japanese (ja)
Inventor
Tetsuji Segawa
哲司 瀬川
Hideaki Matoba
秀彰 的場
Mitsuhiro Enomoto
充博 榎本
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hitachi Ltd
Original Assignee
Hitachi Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hitachi Ltd filed Critical Hitachi Ltd
Priority to JP28130395A priority Critical patent/JPH09128440A/en
Publication of JPH09128440A publication Critical patent/JPH09128440A/en
Pending legal-status Critical Current

Links

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02PCLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
    • Y02P90/00Enabling technologies with a potential contribution to greenhouse gas [GHG] emissions mitigation
    • Y02P90/02Total factory control, e.g. smart factories, flexible manufacturing systems [FMS] or integrated manufacturing systems [IMS]
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02PCLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
    • Y02P90/00Enabling technologies with a potential contribution to greenhouse gas [GHG] emissions mitigation
    • Y02P90/30Computing systems specially adapted for manufacturing

Landscapes

  • Multi-Process Working Machines And Systems (AREA)
  • General Factory Administration (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

PROBLEM TO BE SOLVED: To support the intention dicision of a person in charge of production schedule at the time of adjusting a schedule by analyzing a production schedule including a problem so as to narrow down the contents of adjustment for extracting the point of the problem and improving the schedule. SOLUTION: This system consists of an MPU controller 2, a read time calculation device 1, an MRP developing device 8, a countermeasure planing device 101, a data input/output device 12, a data storage device 11, etc. The system supports the intension decision at the time of deciding various kinds of countermeasures to the production schedule by presenting the adjusting plan for the production schedule by a production schedule preparing function, an inventory management function, an operation load situation analyzing function, an assignment situation analyzing function, and a countermeasure plan presenting function, etc. When an execution disabled situation is generated in the production schedle based on a given production schedule, the system analyzes the situation to narrow the contents of the schedule adjustment for grasping a problem generating situation and solving the problem to present the schedule adjusting plan to support the person in charge of the planning to prepare an executable production schedule.

Description

【発明の詳細な説明】Detailed Description of the Invention

【0001】[0001]

【発明の属する技術分野】本発明は、製造システムを対
象に生産計画を生成する生産計画システムに関し、生成
された生産計画に問題が存在し実行不可能な場合に、問
題解決のための対策案を提示することにより、計画調整
作業の支援を行うことができる生産計画システムに関す
るものである。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a production planning system for producing a production plan for a manufacturing system, and if the produced production plan has a problem and cannot be executed, a measure for solving the problem. The present invention relates to a production planning system that can support planning adjustment work by presenting.

【0002】[0002]

【従来の技術】従来の、生産計画に関する技術として
は、特開平2−311250号公報記載の、問題が発生
している生産計画の調整を支援する技術が知られてい
る。
2. Description of the Related Art As a conventional technique relating to a production plan, there is known a technique described in Japanese Patent Application Laid-Open No. 2-311250 that supports adjustment of a production plan in which a problem has occurred.

【0003】本発明による生産計画の立案方式や、その
他の方式を用いて立案した生産計画が問題を含み、実行
不可能なものである場合には、生産計画に対して生産量
の変更や完成品目ロットの工完日をずらす等の調整を施
し、実行可能な計画にする必要がある。但し、生産計画
の立案結果のみを判断材料として計画立案者が対策を行
う場合には、どの完成品目ロットに対して、どのような
調整を行えば実行可能となり、かつ計画立案者が満足で
きる計画になるかを即座に知ることは困難である。そこ
で、現状では多くの試行錯誤を行うことにより調整内容
を決定している。このような状況においては、計画立案
者が考える計画調整の方針に沿った、効果的な調整内容
を教示できるしくみを提供することが出来れば、計画調
整時間を大幅に削減することが可能なだけではなく、よ
り適正な計画を立案することが可能となる。
If the production plan planning method according to the present invention or a production plan prepared using another method is problematic and infeasible, the production quantity is changed or completed with respect to the production plan. It is necessary to make adjustments such as shifting the completion date of the item lot to make the plan feasible. However, if the planner takes measures based only on the results of the production planning, it will be feasible to make adjustments for which finished item lot, and the planner will be satisfied. It is difficult to know immediately what to do. Therefore, at present, the adjustment contents are decided by performing many trials and errors. In such a situation, if it is possible to provide a mechanism that can teach effective adjustment content according to the plan adjustment policy considered by the planner, it is possible to significantly reduce the plan adjustment time. Instead, it becomes possible to make a more appropriate plan.

【0004】[0004]

【発明が解決しようとする課題】特開平2−31125
0号公報記載の技術によれば、問題のある生産計画に対
して、計画立案者の決定した計画変更内容について、各
工程の日程計画が変化する状況を確認することはできる
が、問題発生の原因究明や、計画を改善するための調整
内容の決定等については支援を行わないので、計画立案
者自身が、作成された生産計画について検討し調整内容
を決定するという作業を行わなければならない。そのた
め、計画立案者が決定した変更内容次第では、新たな問
題が発生する可能性もあり、最終的に実行可能な生産計
画を作成するためには、多くの時間を要している。
DISCLOSURE OF THE INVENTION Problems to be Solved by the Invention
According to the technology described in Japanese Patent Publication No. 0, it is possible to confirm the situation in which the schedule plan of each process changes with respect to the plan change content decided by the planner for a production plan having a problem, but Since no support is provided for investigating the cause and deciding the adjustment contents for improving the plan, the planner himself has to perform the work of considering the produced production plan and deciding the adjustment contents. Therefore, new problems may occur depending on the changes decided by the planner, and it takes a lot of time to finally create a viable production plan.

【0005】そこで、本発明では問題を含む生産計画
の、各工程における生産能力に対する作業負荷状況及
び、各品目に関する在庫量の生産計画への引当状況を解
析することにより、問題点の抽出や計画を改善するため
の調整内容の絞り込み等を行い、計画調整の際の計画立
案者の意思決定を支援することを目的とする。
Therefore, in the present invention, by analyzing the work load situation of the production plan including the problem with respect to the production capacity in each process and the allocation situation of the stock amount of each item to the production plan, the problem point is extracted and the plan is planned. The purpose is to support the decision making of planners in the case of plan adjustments by narrowing down the details of adjustments for improvement.

【0006】[0006]

【課題を解決するための手段】前記目的を達成するため
に、本発明は、ユーザの要求する完成品目の完成日、数
量等を示した完成スケジュールに対して、前記完成品目
を構成する品目の製造工程を少なくとも1つのショップ
として取り扱い、かつ前記ショップにおける前記品目の
製造可能な期間を算出して前記完成品目を完成するまで
の生産スケジュールを決定する生産計画システムにおい
て、前記ショップが備える作業能力量と、前記作業能力
量と前記ショップに与えられる作業負荷量とから導かれ
る前記ショップの余剰能力量とを管理する手段と、前記
完成スケジュールに規定される完成日を満足する生産ス
ケジュールを作成できない場合、前記ショップの余剰能
力量から前記品目に必要な作業量を確保できる期日を判
断する手段と、前記各ショップについて判断された期日
に基づいて前記完成品目の生産可能日を算出する手段と
を備えるものである。
In order to achieve the above object, the present invention relates to a completion schedule indicating the completion date, quantity, etc. of a completed item requested by a user, and In a production planning system, which handles a manufacturing process as at least one shop and determines a production period until the finished item is completed by calculating a manufacturable period of the item in the shop, the work capacity provided in the shop And a means for managing the surplus capacity of the shop derived from the work capacity and the work load given to the shop, and when a production schedule that satisfies the completion date specified in the completion schedule cannot be created. , A means for determining a deadline for securing the work amount necessary for the item from the surplus capacity of the shop, and Those comprising means for calculating a producible date of the completion item on the basis of the date determined for each shop.

【0007】より具体的には、ユーザの要求する完成品
目の完成日、数量等を示した完成スケジュールに対し
て、前記完成品目を構成する品目の製造工程を少なくと
も1つのショップとして取り扱い、かつ前記ショップに
おける前記品目の製造可能な期間を算出して前記完成品
目を完成するまでの生産スケジュールを決定する生産計
画システムにおいて、完成スケジュールによる各完成品
目の完成日に遅延が発生しないように、製造品目の完成
日を基準に各品目の作業着手日を設定する生産計画作成
手段と、取り扱う各品目の現在庫量及び将来の入庫予定
量を管理する在庫量管理手段と、前記生産計画作成手段
により作成された生産計画を対象として、品目毎には日
別所要量と在庫量及び入庫予定量の関係を、ショップ毎
には日別作業量と能力との関係を解析し、当該品目の不
足時期/量、余剰時期/量や、当該ショップの過負荷時
期/量、余裕時期/量を算出する生産計画状況解析手段
と、生産計画に問題が存在する場合に、選択した完成品
目ロットに対して、生産計画状況解析手段により得られ
る特徴量を基に、生産可能日を立案する対策立案手段
と、対策立案手段により得られた結果を表示することに
よりユーザがその対策を実施するかどうかの意思決定を
行うことが可能な対策案提示手段とを有するものであ
る。
More specifically, with respect to the completion schedule indicating the completion date, quantity, etc. of the completed item requested by the user, the manufacturing process of the items constituting the completed item is handled as at least one shop, and In a production planning system that calculates the period during which the item can be manufactured in the shop and determines the production schedule until the completed item is completed, the manufactured item is manufactured so that there is no delay in the completion date of each completed item due to the completed schedule. Production plan creation means for setting the work start date of each item based on the completion date of the item, inventory quantity management means for managing the current storage amount and future planned storage amount of each item handled, and the production plan creation means For each production item, the relationship between the daily requirement amount, the inventory amount and the planned storage amount for each item, and the daily work amount and There is a problem with the production plan situation analysis means that analyzes the relationship with the above and calculates the shortage / amount and surplus time / amount of the item, and the overload time / amount and margin time / amount of the shop, and the production plan. In this case, for the selected finished product lot, the measure planning means for formulating the production available date and the result obtained by the measure planning means are displayed based on the feature amount obtained by the production plan status analysis means. According to the present invention, the user has a measure proposal presenting means capable of making a decision as to whether or not to implement the measure.

【0008】従来、計画立案者が膨大な量のデータを対
象として、自由度の大きな調整内容から満足できる調整
内容を決定するため、様々な調整の試行錯誤など検討に
多くの時間を費やしていたが、本発明に係る生産計画シ
ステムによれば、問題を含む計画について、計画の対象
となる品目又は、ショップの計画状況を解析することに
より、短時間で実行可能な計画を作成するための調整案
を提示することができるため、計画立案者は生産計画の
作成に費やされる時間を削減することができ、かつ計画
立案者の評価尺度に沿った生産計画を得ることが可能と
なる。つまり各ショップにおける余剰能力量を解析する
ことで、完成スケジュールに変更が生じた場合等におい
て調整案を提示することを可能としている。
Conventionally, a planner spends a lot of time on trial and error of various adjustments in order to decide a satisfactory adjustment content from a large amount of adjustment content for a huge amount of data. However, according to the production planning system of the present invention, with respect to a plan including a problem, an adjustment is made to create a plan that can be executed in a short time by analyzing a plan condition of an item to be planned or a shop. Since the plan can be presented, the planner can reduce the time spent for producing the production plan, and can obtain the production plan according to the evaluation measure of the planner. In other words, by analyzing the surplus capacity of each shop, it is possible to present an adjustment plan when the completion schedule changes.

【0009】[0009]

【発明の実施の形態】以下、本発明に係る生産計画シス
テムの一実施例について説明する。
BEST MODE FOR CARRYING OUT THE INVENTION An embodiment of the production planning system according to the present invention will be described below.

【0010】図1に、本実施例に係る生産計画システム
の構成を示す。
FIG. 1 shows the configuration of a production planning system according to this embodiment.

【0011】図中、1000は生産計画システム、11
00は受注処理システム、1200は製造システム、1
300は見込生産計画システムである。
In the figure, 1000 is a production planning system, 11
00 is an order processing system, 1200 is a manufacturing system, 1
300 is a make-to-stock production planning system.

【0012】見込生産計画システム1300を用い、計
画立案者は、将来の受注を予測した見込量に基づいて、
製品の完成スケジュールを作成する。製品の完成スケジ
ュールは、製品名と製品の個数と完成日の組毎に注番を
付した生産要求情報のまとまりとして作成される。作成
された製品の完成スケジュールは、生産計画システム1
000に渡される。
[0012] Using the make-to-stock production planning system 1300, the planner, based on the make-to-stock quantity predicted for future orders,
Create a product completion schedule. The product completion schedule is created as a set of production request information with a note number for each set of product name, number of products, and completion date. Completion schedule of the created products, production planning system 1
Passed to 000.

【0013】生産計画システム1000は、製品の完成
スケジュールに基づいて、製造システム1200におけ
る製品の生産スケジュールを作成する。
The production planning system 1000 creates a product production schedule in the manufacturing system 1200 based on the product completion schedule.

【0014】受注処理システム1100は、顧客からの
受注を処理し、受注個数と要求納期を指定する受注情報
を生産計画システム1000に渡す。また、生産計画シ
ステム1000より、生産スケジュールに基づいた請負
納期の回答を得る。
The order processing system 1100 processes an order from a customer and passes order information that specifies the number of orders and a requested delivery date to the production planning system 1000. Further, the production planning system 1000 obtains an answer of the contract delivery date based on the production schedule.

【0015】製造システム1200は、生産計画システ
ム1000により作成した生産計画に従い、実際に製品
を製造するシステムである。
The manufacturing system 1200 is a system for actually manufacturing a product according to the production plan created by the production planning system 1000.

【0016】さて、生産計画システム1000は、見込
生産計画システム1300により作成された製品の完成
スケジュールや、受注処理システム1100から渡され
る受注情報や生産スケジュールや製造システム1200
についての情報等を記憶するデータ記憶装置11と、計
画立案者との間のユーザインターフェイスを提供するデ
ータ入出力装置12とを有している。
The production planning system 1000 has a product completion schedule created by the make-to-stock production planning system 1300, order information and production schedules passed from the order processing system 1100, and a manufacturing system 1200.
Has a data storage device 11 for storing information and the like, and a data input / output device 12 for providing a user interface with a planner.

【0017】また、MRP制御装置2、MRP展開装置
8、リードタイム計算装置1、作業量計算装置3、作業
量解析装置27、生産計画実行判定装置101を有して
いる。
Further, it has an MRP control device 2, an MRP expansion device 8, a lead time calculation device 1, a work amount calculation device 3, a work amount analysis device 27, and a production plan execution judgment device 101.

【0018】また、問題点解析装置7、生産能力調整装
置4、完成日調整装置5、代替ショップ調整装置6、作
業着手順序調整装置33、生産量調整装置40、計画削
除装置104を有している。
Further, it has a problem analysis device 7, a production capacity adjustment device 4, a completion date adjustment device 5, an alternative shop adjustment device 6, a work start sequence adjustment device 33, a production amount adjustment device 40, and a plan deletion device 104. There is.

【0019】ここで、本実施例においては、製造システ
ム1200を次のようにモデル化する。
Here, in this embodiment, the manufacturing system 1200 is modeled as follows.

【0020】まず、各ショップをグループ化しそれぞれ
をショップグループと呼ぶことにする。各ショップグル
ープは、作業を相互に代替することが可能であり、かつ
担当する製造過程に相互の前後関係がないショップの集
合であり、例えば、組立作業を行うショップのショップ
グループ、塗装作業を行うショップのショップグルー
プ、加工作業を行うショップのショップグループ等が考
えられる。
First, each shop is grouped and each shop is called a shop group. Each shop group is a set of shops that are capable of substituting for each other's work and do not have a context in the manufacturing process that they are in charge of. For example, a shop group of shops that perform assembly work and a painting work A shop group of shops, a shop group of shops that perform processing work, and the like can be considered.

【0021】次に、各ショップグループをトポロジカル
ソートの手法により並べる。つまり、製品各々につい
て、製造過程の進行する順番に対象となるショップを並
べ、並んだ各ショップに対応させ、各ショップが属する
ショップグループの番号を並べた場合に、必ず、より小
さい番号が、より大きい番号より前になるように各ショ
ップグループに番号を付ける。これにより、いかなる製
品の生産においても、より前の製造過程を担当するショ
ップが属するショップグループの番号は、より後の製造
過程を担当するショップが属するショップグループの番
号より小さいことになる。そこで、より小さい番号のシ
ョップグループを上流のショップグループと呼び、より
大きい番号のショップグループを下流のショップグルー
プと呼ぶことにする。
Next, the shop groups are arranged by the method of topological sorting. In other words, for each product, when the target shops are arranged in the order in which the manufacturing process progresses, and the corresponding shops are arranged, and the number of the shop group to which each shop belongs is arranged, the smaller number is always better. Number each shop group so that it precedes the higher numbers. As a result, in producing any product, the number of the shop group to which the shop in charge of the earlier manufacturing process belongs is smaller than the number of the shop group to which the shop in charge of the later manufacturing process belongs. Therefore, the smaller-numbered shop group is called an upstream shop group, and the higher-numbered shop group is called a downstream shop group.

【0022】なお、各ショップで製造された結果物を品
目といい、各品目と当該品目を製造するショップとの関
係は、予め製造システムに関する情報としてデータ記憶
装置11に設定されているものとして説明する。また、
本実施例では、材料等、外部より調達する必要のある品
目の調達を行うシステムもショップとして取り扱う。本
実施例では、このショップを調達ショップと呼ぶ。調達
ショップは、当該品目に関して、所要量より在庫量を減
じた正味所要量を外部に発注し、調達するシステムであ
る。
The products produced in each shop are referred to as items, and the relationship between each item and the shop that manufactures the item is explained as being set in advance in the data storage device 11 as information about the manufacturing system. To do. Also,
In this embodiment, a system for procuring items such as materials that need to be procured from outside is also handled as a shop. In this embodiment, this shop is called a procurement shop. The procurement shop is a system for ordering and procuring the net requirement amount, which is obtained by subtracting the inventory amount from the requirement amount, for the item concerned.

【0023】また、製造システム1200は、各品目の
在庫量をも管理しており、現時点での在庫情報を生産計
画システム1000のデータ記憶装置11に送る。そし
て、各ショップで製造された品目/量及び、調達ショッ
プで調達された品目/量は、在庫情報に追加される。
The manufacturing system 1200 also manages the inventory quantity of each item, and sends the current inventory information to the data storage device 11 of the production planning system 1000. Then, the item / quantity manufactured in each shop and the item / quantity procured in the procurement shop are added to the inventory information.

【0024】以下、本実施例に関わる生産計画システム
1000の動作について説明する。
The operation of the production planning system 1000 according to this embodiment will be described below.

【0025】本実施例に関わる生産計画システム100
0は、まず、見込生産計画システム1300が作成した
製品の完成スケジュールに基づいた生産計画を作成す
る。
The production planning system 100 according to this embodiment
0 first creates a production plan based on the product completion schedule created by the expected production planning system 1300.

【0026】図2に、本実施例に関わる生産計画システ
ムの生産計画作成の処理手順を示す。
FIG. 2 shows a processing procedure for producing a production plan of the production planning system according to this embodiment.

【0027】まず、見込生産計画システム1300から
受け取った製品の完成スケジュールをデータ記憶装置1
1に記憶した後に、データ入出力装置12よりMRP実
行指示18を受けると、MRP制御装置2はMRP展開
装置8にMRP展開指示30を送り、完成スケジュール
中の各注番に対応する生産要求情報中の製品(完成品
目)名と、完成品目の総所要量と完成日を、データ記憶
装置11より読みだす(201)。
First, the data storage device 1 stores the product completion schedule received from the expected production planning system 1300.
When the MRP execution instruction 18 is received from the data input / output device 12 after it is stored in 1, the MRP control device 2 sends the MRP expansion instruction 30 to the MRP expansion device 8 and the production request information corresponding to each order number in the completion schedule. The name of the product (completed item), the total required amount of the completed item, and the completion date are read from the data storage device 11 (201).

【0028】次に、MRP制御装置2は、MRP展開装
置8の動作を制御し、最下流のショップグループに属す
る各ショップについて(202)、順次、当該ショップ
で製造する各品目毎に、総所要量より、データ記憶装置
11に記憶されている在庫量を減じ、実際に当該ショッ
プで製造する必要のある数量を求め、当該ショップで製
造する各品目の正味所要量とする(203、204)。
次に、ショップ毎に求めた各品目の正味所要量と、それ
ぞれの完成日を作業量計算装置3に渡す。また、この
際、注番毎の所要量も求めておく。
Next, the MRP control device 2 controls the operation of the MRP expansion device 8 so that for each shop belonging to the most downstream shop group (202), the total required for each item manufactured in the shop in sequence. The inventory quantity stored in the data storage device 11 is subtracted from the quantity to determine the quantity that actually needs to be manufactured in the shop, and set as the net required quantity of each item manufactured in the shop (203, 204).
Next, the net required amount of each item obtained for each shop and the completion date of each item are passed to the work amount calculation device 3. At this time, the required amount for each order number is also obtained.

【0029】作業量計算装置3は、ショップ毎に完成作
業量26を計算し(208)、リードタイム計算装置1
に渡す。ここで完成作業量とは、各日毎に、当該日を完
成日としている全ての品目を製造するために必要な当該
ショップの作業量を求めたものである。
The work amount calculating device 3 calculates the completed work amount 26 for each shop (208), and the lead time calculating device 1
Pass to. Here, the completion work amount is the amount of work of the shop required for manufacturing all the items having the completion date as the completion date for each day.

【0030】一方、リードタイム計算装置1では、ショ
ップ毎に求めた完成作業量26と、予め設定されている
各ショップの生産能力13をもとに、各品目のリードタ
イム14を求める(207、208、209)。リード
タイムの計算方法については、後に詳細に述べる。
On the other hand, in the lead time calculation apparatus 1, the lead time 14 of each item is obtained based on the completed work amount 26 obtained for each shop and the preset production capacity 13 of each shop (207, 208, 209). The method of calculating the lead time will be described in detail later.

【0031】次に、MRP展開装置8では、各品目を順
次、展開対象品目とし、リードタイム計算装置1で求め
た展開対象品目のリードタイム14を完成日から減じる
ことにより、展開対象品目の製造着手日を決定し、展開
対象品目を製造するために必要な品目(子品目)を求
め、決定した展開対象品目の製造着手日の前日を子品目
の完成日とする。また、求めた各子品目毎に総所要量に
ついての所要量展開処理を行い、展開対象品目を製造す
るために必要な各子品目の数量を求める(210〜21
3)。
Next, in the MRP expanding device 8, each item is sequentially made an expanding target item, and the lead time 14 of the expanding target item obtained by the lead time calculating device 1 is subtracted from the completion date to manufacture the expanding target item. The start date is determined, the items (sub-items) necessary for manufacturing the development target item are obtained, and the day before the start of manufacturing of the determined development target item is set as the completion date of the sub-item. In addition, the required amount expansion process for the total required amount is performed for each obtained child item, and the number of each child item required to manufacture the item to be developed is obtained (210 to 21).
3).

【0032】以上により、最下流のショップグループに
ついての生産計画が完了するので、次に、MRP制御装
置2は、順次、上流に遡り、各ショップグループについ
て、図2符号203以降の処理を繰り返す(214、2
15)。ただし、調達ショップについては、単純に、そ
の品目の調達に要する期間をリードタイム(調達リード
タイム)とし、調達リードタイムより求まる着手日を、
その品目を発注する日とする。
As described above, the production plan for the most downstream shop group is completed. Next, the MRP control device 2 sequentially traces upstream, and repeats the processing after the reference numeral 203 in FIG. 2 for each shop group ( 214, 2
15). However, for the procurement shop, simply set the lead time (procurement lead time) to the period required to procure the item, and set the start date obtained from the procurement lead time to
It is the date when the item is ordered.

【0033】本実施例に係る生産計画システムは、この
ように生産計画の生成(MRPリジェネレーション)を
行う。
The production planning system according to the present embodiment thus carries out the production planning (MRP regeneration).

【0034】次に、リードタイム計算装置1が行うリー
ドタイム計算について説明する。前述のように、リード
タイム計算装置1は、各ショップの負荷を考慮して各工
程でのリードタイムを予測する。
Next, the lead time calculation performed by the lead time calculation device 1 will be described. As described above, the lead time calculation device 1 predicts the lead time in each process in consideration of the load of each shop.

【0035】ところで、各ショップが製造過程において
固定の作業を担当するフローショップにおいては、ライ
ン固有のタクトタイムを有し、最適な生産速度及び1個
当たりのリードタイムが存在する。
By the way, in a flow shop in which each shop is in charge of fixed work in the manufacturing process, there is a tact time unique to the line, and there is an optimum production speed and a lead time per piece.

【0036】また、各ショップが投入されたジョブの作
業を担当するジョブショップにおいては、平均のリード
タイムがショップ内仕掛りにほぼ比例して増大するのに
対して、生産速度は、仕掛りが増えてもあるレベルで飽
和して増加しなくなることが、待ち行列理論等を利用し
た過去の研究により良く知られている。この事実は、最
適な仕掛りレベル、生産速度が存在し、ジョブを投入し
ても、品目1個当たりのリードタイムが増大するばかり
で生産速度がほとんど増えなくなる点が存在することを
示している。
Further, in a job shop in which each shop is in charge of the work of a job, the average lead time increases almost in proportion to the in-shop work in process, while the production speed It is well known from past studies using queuing theory that it saturates and stops increasing at a certain level even if it increases. This fact indicates that there is an optimal work-in-progress level and production speed, and even if a job is input, the lead time per item only increases and the production speed hardly increases. .

【0037】従って、この最適な生産速度を保てるよう
な生産計画を生成するようにリードタイムを求める必要
がある。
Therefore, it is necessary to obtain the lead time so as to generate a production plan that can maintain this optimum production speed.

【0038】そこで、本実施例では、次のようにしてリ
ードタイムを図3に示す方法で予測する。ただし、各シ
ョップにおける最適な生産速度におけるサイクルタイム
(投入間隔=品目1個の算出間隔)と、各品目1個当た
りのリードタイムがショップ毎に分かっているものとす
る。
Therefore, in this embodiment, the lead time is predicted by the method shown in FIG. 3 as follows. However, it is assumed that the cycle time (input interval = calculation interval for one item) and the lead time for each item at the optimum production speed in each shop are known for each shop.

【0039】前述のように、まず、作業量計算装置3で
対象ショップの各日の完成作業量を求める。完成作業量
とは、当該日を完成日とする品目の作業量の総計であ
り、図3に示すように、品目の個数と当該品目を1個製
造するのに要する標準時間STの積を、当該日を完成日
とする全品目について総和したものとなる。なお、この
際には、当該日を完成日とする品目を用いる注番毎の、
対象ショップにおける作業量も求めておく。
As described above, first, the work amount calculation device 3 determines the completed work amount of each day of the target shop. The completion work amount is the total work amount of the items whose completion date is the relevant day, and as shown in FIG. 3, the product of the number of items and the standard time ST required to manufacture one of the items is It will be the sum of all items with that date as the completion date. At this time, for each order number that uses items whose completion date is
Also find the amount of work at the target shop.

【0040】次に、作業量分布と投入時期を求める。こ
こでは、作業量計算装置3で求めた各ショップにおける
完成作業量26を、未来から過去の方向へ順次前倒しし
ながら作業量分布を決めていく。例えば、n日に完成す
る品目群Aの作業量分布は、次のようにして決める。ま
ず、完成時刻(=品目群の最後の1個の産出時刻)を完
成日の終わりと一致するように設定する。次に、最初の
1個の産出時刻から最後の1個の産出時刻の間の幅を、
当該日の正規化完成作業量×標準サイクルタイムとして
求め、最初の1個の産出時刻を決定する。さらに、当該
品目1個当たりのリードタイムを減じた時刻が、最初の
1個の投入時刻、すなわち品目群Aの着手時刻となる。
ただし、品目群Bのように、次の日に完成する品目群の
最初の1個の産出時刻が、自身の完成日より前となった
場合には、品目群Bの完成時刻をこれと一致させるよう
に設定する。
Next, the work amount distribution and the input time are calculated. Here, the work amount distribution is determined by sequentially advancing the completed work amount 26 in each shop obtained by the work amount calculation device 3 from the future to the past. For example, the work load distribution of the item group A completed on the nth day is determined as follows. First, the completion time (= the production time of the last one in the item group) is set to coincide with the end of the completion date. Next, the width from the first production time to the last production time,
The normalization completion work amount on that day is calculated as the standard cycle time, and the production time of the first one is determined. Further, the time obtained by subtracting the lead time for each item becomes the time of introduction of the first item, that is, the start time of the item group A.
However, like the item group B, when the first production time of the item group that will be completed on the next day is before the completion date of its own, the completion time of the item group B will match this. Set to allow.

【0041】ここで、正規化完成作業量とは、前記完成
作業量を標準ST(当該ショップで製造される品目のS
Tの、製造数量比による加重平均値をとったもの)で割
って正規化したものである。また、標準サイクルタイム
とは、当該ショップで製造される品目のサイクルタイム
の製造数量比による加重平均値をとったものである。1
個当たりの標準リードタイムとしては、当該ショップで
製造される品目の1個当たりのリードタイムの、製造数
量比による加重平均値をとったものである。
Here, the normalized completed work amount is the standard work amount (S of the items manufactured in the shop).
It is normalized by dividing the weighted average value of T by the manufacturing quantity ratio). Further, the standard cycle time is a weighted average value of cycle times of items manufactured in the shop according to the manufacturing quantity ratio. 1
The standard lead time per piece is the weighted average value of the lead time per piece of the item manufactured in the shop, which is based on the manufacturing quantity ratio.

【0042】次に、着手時刻と完成時刻との間隔をリー
ドタイムとする。当該完成日以降に完成する品目の作業
が、当該完成日より前にずれ込んでいる場合には、その
分だけリードタイムが増大することとなる。
Next, the interval between the start time and the completion time is set as the lead time. If the work of the item completed after the completion date is delayed before the completion date, the lead time is increased accordingly.

【0043】ところで、本実施例では、後述するように
生産計画の調整を行う際、ショップの能力を、日毎に異
なった値に設定することにより行う場合がある。そこ
で、この場合の動作について説明する。
By the way, in the present embodiment, when the production plan is adjusted as will be described later, the capacity of the shop may be set to a different value for each day. Therefore, the operation in this case will be described.

【0044】例えば、能力がα倍になったときには、標
準サイクルタイムと標準リードタイムが1/αとなるの
で、図3の幅と傾きを1/α倍すれば良い。しかし、こ
のようにすると、図4左に示すように、能力の変わり目
では計算が複雑になる。そこで、本実施例では、図4右
のようにする。つまり、能力がα倍になったということ
は、時間軸がα倍に伸びたと考え、この伸縮した時間軸
上で、図3と同様に幅と傾きを設定し、リードタイムを
計算する。
For example, since the standard cycle time and the standard lead time become 1 / α when the capacity becomes α times, the width and inclination in FIG. 3 may be multiplied by 1 / α. However, in this case, the calculation becomes complicated at the turning point of the ability, as shown on the left side of FIG. Therefore, in this embodiment, the configuration shown on the right side of FIG. 4 is adopted. That is, the fact that the ability is increased by α means that the time axis is extended by α times, and the lead time is calculated by setting the width and the inclination on this expanded / contracted time axis as in FIG. 3.

【0045】以上のようにして、リードタイム計算装置
1は、ショップ毎に当該ショップの総合的な作業量を考
慮して、各工程のリードタイムを設定する。
As described above, the lead time calculation apparatus 1 sets the lead time of each process in consideration of the total work amount of the shop for each shop.

【0046】なお、以上のように、リードタイムの予測
を行うためには、予測用パラメータが必要である。ここ
で、予測用パラメータは、ST、サイクルタイム及び、
1個当たりのリードタイムである。これらは、製造シス
テム1200についての情報として、データ記憶装置1
1に、予め記憶しておく。但し、製造システムから生産
実績の情報を得、これを基に正確な予測用パラメータを
計算し、リードタイム計算装置1に与えるようにしても
良い。
As described above, in order to predict the lead time, the parameters for prediction are necessary. Here, the prediction parameters are ST, cycle time, and
It is the lead time per piece. These are used as information about the manufacturing system 1200 and are included in the data storage device 1.
1 is stored in advance. However, the production performance information may be obtained from the manufacturing system, an accurate prediction parameter may be calculated based on the production performance information, and may be provided to the lead time calculation device 1.

【0047】また、リードタイム計算装置1は、パター
ン変換モデル、例えば、ニューラルネットワークを用い
て実現することもできる。ニューラルネットワークは、
入力データと出力データとの間のパターン変換能力及
び、パターン学習能力を有するため、リードタイム計算
装置1、作業量計算装置3に関して、例えば、以下に示
すようなデータを用いて、各々のニューラルネットワー
クを学習させておくことにより、新たな入力に対してリ
ードタイムをパターン変換により算出することが可能と
なる。
The lead time calculation device 1 can also be realized by using a pattern conversion model, for example, a neural network. Neural networks are
Since each of the lead time calculation device 1 and the work amount calculation device 3 has the pattern conversion ability between the input data and the output data and the pattern learning ability, for example, the following data is used for each neural network. It is possible to calculate the lead time for a new input by pattern conversion by learning.

【0048】 入力:各ショップの能力、完成作業量 出力:リードタイム なお、ニューラルネットワークの理論については、ルメ
ルハルト ディー・イー、マクラレンド ジェー・エル
アンド ザ ピーディーピー リサーチグループ、1
986、パラレル ディストリビューティッド プロセ
シング:エムアイティー プレス (Remelhart D. E.,
Maclelland J. L. and The PDP Research group, 198
6, Parallel Destributed Processing : MIT Press)に
詳述されている。
Input: Ability of each shop, completed work output: Lead time In addition, regarding the theory of neural networks, Rumelhardt DEE, McLarend JL and the PDP Research Group, 1
986, Parallel Distributed Processing: MI Press (Remelhart DE,
Maclelland JL and The PDP Research group, 198
6, Parallel Destributed Processing: MIT Press).

【0049】ニューラルネットワークをリードタイム計
算装置1として使用する時も、予測用パラメータが必要
である。予測用パラメータは、ニューラルネットワーク
の細胞間の結合強度値の組である。これらは、製造シス
テムから得られた生産実績データを基にニューラルネッ
トワークの学習を行うようにする。
Even when the neural network is used as the lead time calculation apparatus 1, a prediction parameter is necessary. The prediction parameter is a set of coupling strength values between cells of the neural network. These perform learning of the neural network based on the production performance data obtained from the manufacturing system.

【0050】さて、このようにして、見込生産計画シス
テム1300が作成した製品の完成スケジュールに従っ
た、注番毎の生産/調達計画が、ショップ毎に生産計画
システム1000により作成され、データ記憶装置11
に記憶される。いま、この時点で、生産/調達計画は、
製品の完成スケジュールを満足できるように、すなわ
ち、現在より以前に品目の着手日または、発注日が設定
されることなく作成できたものとする。
In this way, a production / procurement plan for each order number is created by the production planning system 1000 for each shop according to the product completion schedule created by the expected production planning system 1300, and the data storage device is used. 11
Is stored. At this point, the production / procurement plan is
It is assumed that the product can be created so that the completion schedule of the product can be satisfied, that is, the start date or order date of the item is not set before the present time.

【0051】この後、見込生産計画システム1300で
将来の受注量を予測し、作成した製品の完成スケジュー
ルの生産量を越える受注または、品目の完成が予定され
ている時期よりも早い時期に顧客の要求があった場合に
は、受注処理システム1100から、追加生産が必要な
製品名と要求個数と要求納期を指定する受注情報が生産
計画システム1000のデータ記憶装置11に送られ
る。すると、生産計画システムでは、上記受注情報が示
す受注内容を満足する製品名と生産量と完成日を指示す
る生産要求情報を作成し、これに新たな注番を付して製
品の完成スケジュールに加え、MRP展開装置8に生産
計画の再生成を指示する。
After that, the future production quantity is predicted by the forecast production planning system 1300, and the customer's order is received earlier than the time when the production quantity exceeds the production quantity on the completion schedule of the created product or the completion of the item is scheduled. When a request is made, the order processing system 1100 sends order information that specifies a product name, a required quantity, and a requested delivery date for which additional production is required, to the data storage device 11 of the production planning system 1000. Then, the production planning system creates the production request information that indicates the product name, the production amount, and the completion date that satisfy the order contents indicated by the above order information, and adds a new order number to the product completion schedule. In addition, the MRP expansion device 8 is instructed to regenerate the production plan.

【0052】生産計画の再生成を指示されたMRP展開
装置8、作業量計算装置3、リードタイム計算装置1
は、現在の在庫量をデータ記憶装置11より読みだし、
前述したように注番毎の生産/調達計画を、ショップ毎
に作成し、データ記憶装置11に記憶するが、この際、
作業量解析装置27と、生産計画判定装置101は、作
業量の面から、この新たな製品の完成スケジュールを満
足する実行可能な生産計画が立案されたか否か、立案さ
れなかった場合には、顧客からの要求に引き当てられて
いる全ての注番の生産要求を満足する実行可能な生産計
画が立案可能か否かを判定する。また、MRP展開装置
8と生産計画判定装置101は、外部より調達する品目
についての在庫量の面から、この新たな製品の完成スケ
ジュールを満足する実行可能な生産計画が立案されたか
否か、立案されなかった場合には、顧客からの要求に引
き当てられている全ての注番の生産要求を満足する実行
可能な生産計画が立案可能か否かを判定する。
MRP expansion device 8, work amount calculation device 3, lead time calculation device 1 instructed to regenerate the production plan
Reads the current stock amount from the data storage device 11,
As described above, the production / procurement plan for each order number is created for each shop and stored in the data storage device 11. At this time,
From the viewpoint of the amount of work, the work amount analysis device 27 and the production plan determination device 101 determine whether or not an executable production plan that satisfies the completion schedule of this new product is drawn up. It is determined whether or not a workable production plan that satisfies the production demands of all the order numbers allocated to the demands from customers can be drafted. In addition, the MRP expansion device 8 and the production plan determination device 101 make a plan from the viewpoint of the inventory quantity of the items to be procured from the outside, whether or not a feasible production plan satisfying the completion schedule of this new product is made. If not, it is determined whether or not a viable production plan that satisfies all the production demands of the order numbers allocated to the demand from the customer can be drafted.

【0053】ここで、作業量及び在庫量の両面で新たな
製品の完成スケジュールを満足する実行可能な生産計画
が立案された場合には、さらなる生産計画の調整作業は
不必要であるが、実行可能な生産計画が立案できなかっ
た場合には、対策を行う必要がある。そこで以下、実行
可能な生産計画が立案できなかった場合に、新たな製品
の生産をいつならば行うことができるか、また新たな製
品の完成スケジュールを満足させるために、顧客からの
要求に引き当てられていないいくつかの注番の完成スケ
ジュールを後倒しする場合に、それぞれの注番の生産時
期をいつに設定すべきかをユーザに提示する対策立案支
援機能について述べる。
If a feasible production plan satisfying the completion schedule of a new product is made in terms of both the work amount and the inventory amount, further work for adjusting the production plan is unnecessary, but is not necessary. If it is not possible to formulate a possible production plan, it is necessary to take measures. Therefore, in the following, when a viable production plan could not be drawn up, when new products could be produced, and in order to satisfy the completion schedule of new products, the requirements from customers were allocated. This paper describes a countermeasure planning support function that presents to the user when to set the production time of each order in case of delaying the completion schedule of some orders that have not been done.

【0054】処理は、以下に示す手順に従い行われる。
始めにリードタイム計算装置1の出力結果に基づいて、
作業量解析装置27において各生産工程の作業負荷状況
について解析を行う。ここでは、生産工程毎にその作業
負荷状況から、生産能力に対して作業負荷が過剰になっ
ている期間と、作業負荷が生産能力に満たず能力的な余
裕が存在する期間及びその量を明らかにする。
The processing is performed according to the procedure shown below.
First, based on the output result of the lead time calculation device 1,
The work load analyzer 27 analyzes the work load situation of each production process. Here, from the work load situation for each production process, the period when the work load is excessive with respect to the production capacity, the period when the work load does not reach the production capacity and there is a capacity margin, and the amount thereof are clarified. To

【0055】次に所要量展開の際、MRP展開装置8に
おいて各品目の日別所要量に対する現在庫/入庫予定量
の引当状況について解析を行う。ここでは、品目毎にそ
の引当状況から、使用可能量に対して所要量が過剰にな
っている期間と、所要量が使用可能量未満であり、余剰
在庫が存在する期間及びその量を明らかにする。
Next, when developing the required amount, the MRP developing device 8 analyzes the allocation status of the current stock / planned stock quantity for the daily required quantity of each item. Here, from the allocation status of each item, the period when the required amount is excessive with respect to the available amount, the period when the required amount is less than the available amount, and the excess inventory exists and its amount are clarified. To do.

【0056】以上により、生産能力及び品目に関する余
剰量/期間を明確にした後、デ−タ記憶装置11から今
生産時期を設定しようとしている注番の構成品目及びそ
の生産工程に関する情報を引き出し、対策立案装置10
0において、当該注番に対して生産可能な時期を設定す
る。設定された当該注番に関する情報は、デ−タ入出力
装置12によりユーザに提示され、ユーザの意思決定
後、MRP制御装置2にその決定内容に従ったMRP実
行指示が送られることになる。
As described above, after clarifying the production capacity and the surplus amount / period relating to the item, the information concerning the constituent item of the order number for which the production time is now set and the production process thereof are retrieved from the data storage device 11, Countermeasure planning device 10
In 0, the time when production is possible is set for the order number. The information regarding the set order number is presented to the user by the data input / output device 12, and after the user makes a decision, the MRP execution instruction according to the decision content is sent to the MRP control device 2.

【0057】まず、作業量解析装置27において行われ
る工程毎の生産能力に対する作業負荷状況の解析方法に
ついて説明する。
First, a method of analyzing the work load status with respect to the production capacity of each process performed by the work amount analyzing apparatus 27 will be described.

【0058】いま工完日の変更を行う注番を構成する一
つの品目が製造される工程について、日々の生産能力に
対する作業負荷量が図5に示されるような状況であると
する。このときリードタイム計算装置1では、図3を用
いて説明した方法により生産計画期間の最終日から現在
に向けて、日々の生産能力に対する過負荷が順次前倒し
される。その結果、現在日に過負荷が存在する場合に
は、現在日から将来に向けて順に日別の過負荷の前倒し
量をチェックする。その時、将来で最も早く過負荷の前
倒し量が0となる日(本例では現在+2日)までの期間
内では、生産能力よりも作業負荷の方が過剰になってい
る。しかし、図中の過負荷発生境界日以降では、能力的
に余裕のある状態である可能性がある。そこで、過負荷
発生境界日から将来に向けて、余剰能力を後倒しし、将
来の過負荷に対して引き当てる処理を行う。これによ
り、計画対象期間の最終日の余剰能力の後倒し量がプラ
スの場合には、余剰能力が存在することが分かり、計画
対象期間内での余剰能力の存在有無をチェックすること
が可能である。図5の余剰能力の後倒し量を示したグラ
フでは、現在+3日〜+5日の期間に存在する余剰能力
がn−3日とn−2日の過負荷に引き当てられることに
より、現在+3日〜n−2日の期間では、aだけの余剰
能力が、n−1日からn日の期間では、bだけの余剰能
力が存在している。つまり、余剰能力aは、過負荷発生
境界日以降において確保できる余剰能力の後倒し量であ
り、同様にbは(n−1)日以降において確保できる後
倒し量である。従って、工完日を変更する注番の対象工
程での作業負荷xが例えばa<x≦bであるならば、n
−1日が最も早い生産可能日ということになる。また、
図中の期間別余剰能力量よりも大きな作業負荷である注
番については、生産計画対象期間内では、受け入れるこ
とができず、次回の生産計画に組み込む必要が発生す
る。以上、作業量解析装置27により得られた生産工程
に関する情報は、デ−タ記憶装置11に記憶される。
It is assumed that the work load amount with respect to the daily production capacity is as shown in FIG. 5 in the process in which one item constituting the order number for which the work completion date is changed is manufactured. At this time, in the lead time calculation device 1, the overload on the daily production capacity is progressively advanced from the last day of the production planning period to the present by the method described with reference to FIG. As a result, if there is an overload on the current day, the amount of advance of the overload is checked for each day sequentially from the present day to the future. At that time, the work load is more excessive than the production capacity within the period until the earliest amount of advance overload in the future reaches 0 (currently +2 days in this example). However, there is a possibility that there is a margin in capacity after the overload occurrence boundary date in the figure. Therefore, from the boundary date of overload occurrence, the surplus capacity is moved backward and assigned to future overload. Therefore, if the amount of surplus capacity on the last day of the planning period is positive, it is known that there is surplus capacity, and it is possible to check whether there is surplus capacity within the planning period. is there. In the graph showing the amount of surplus capacity pushed backward in FIG. 5, the surplus capacity currently existing in the period of +3 days to +5 days is allocated to the overload of n−3 days and n−2 days, so that it is currently +3 days. There is a surplus capacity of a in the period of up to n-2 days, and a surplus capacity of b in the period of n-1 days to n days. In other words, the surplus capacity a is the postponement amount of the surplus capacity that can be ensured after the overload occurrence boundary date, and similarly, the b is the postponement amount that can be ensured after (n-1) days. Therefore, if the work load x in the target process of the order number for changing the work completion date is, for example, a <x ≦ b, then n
-1 day is the earliest production possible date. Also,
The order number, which is a work load larger than the surplus capacity by period in the figure, cannot be accepted within the production plan target period and needs to be incorporated in the next production plan. As described above, the information about the production process obtained by the work amount analyzing device 27 is stored in the data storage device 11.

【0059】次に、MRP展開装置8において行われる
品目毎の日別所要量に対する現在庫/入庫予定量の引当
状況の解析方法について説明する。
Next, a method of analyzing the allocation status of the current stock / planned stock quantity with respect to the daily required quantity for each item, which is performed in the MRP expanding device 8, will be described.

【0060】いま工完日の変更を行う注番を構成する一
つの品目に関する日々の所要量及び現在庫/入庫予定量
から算出される調達リードタイム期間内の在庫推移が、
図6のようであったとする。本例のように在庫量推移に
マイナスとなる日が存在する場合には、不足が発生する
ことになり、その不足量に対応するだけの使用量を減ら
さなければ、生産計画を実行することはできない。そこ
で、使用量を減らすためにその期間内の注番の生産の取
り止めや工完日の後倒しなどにより対策を行った結果、
将来において余剰が発生する場合が考えられる。それ
は、図6に色付の丸印で示す不足が解消された場合の在
庫量推移より知ることができる。本例では、現在+5日
以降の当該品目の調達リードタイム期間中で、使用され
ない品目量が40個あり、工完日変更する注番に使用す
る当該品目の量が40個以下であれば、現在+5日に調
達可能であることが分かる。もしそれ以上の部品が必要
である場合には、今から部品を手配することにより、調
達リードタイム後の現在+7日に調達可能であることが
分かる。以上、MRP展開装置8により得られた品目の
引当状況に関する情報は、デ−タ記憶装置11に記憶さ
れる。
The inventory transition within the procurement lead time period calculated from the daily required quantity and the current stock / planned stock quantity for one item constituting the order number for which the work completion date is changed,
It is assumed that it is as shown in FIG. If there is a negative day in the inventory change as in this example, a shortage will occur, and if the usage amount corresponding to the shortage is not reduced, the production plan cannot be executed. Can not. Therefore, as a result of taking measures to reduce the usage amount, such as by canceling the production of the order number within that period and delaying the work completion date,
A surplus may occur in the future. This can be known from the inventory quantity transition when the shortage indicated by the colored circles in FIG. 6 is resolved. In this example, if there are 40 unused item quantities in the procurement lead time period of the current item after +5 days and the quantity of the relevant item used for the order number for changing the completion date is 40 or less, It can be seen that it can be procured at +5 days now. If more parts are needed, it can be seen that by arranging parts from now on, it can be procured now +7 days after the procurement lead time. As described above, the information on the allocation status of the item obtained by the MRP developing device 8 is stored in the data storage device 11.

【0061】次に、対策立案装置100において行われ
る当該注番に対する生産可能時期の設定方法について図
7、図21を用いて説明する。ただし、当該注番として
生産される製品は品目1と品目2で構成され、その品目
1は品目3と品目4から構成されるものとする。また、
その内品目4は、調達品目であるものとする。
Next, a method of setting the producible period for the order number performed by the countermeasure planning apparatus 100 will be described with reference to FIGS. 7 and 21. However, the product produced as the order number is composed of item 1 and item 2, and item 1 is composed of item 3 and item 4. Also,
Among them, the item 4 is a procured item.

【0062】まず、初めに完成日設定不可期間を特定す
る。ここで、完成日設定不可期間とは、完成スケジュー
ル変更の対象注番に対して、完成スケジュール上で完成
日を設定しても、必ずいずれかの生産工程で過負荷量が
増加するか、もしくは調達品目の不足量が増加する期間
である。
First, the period in which the completion date cannot be set is specified first. Here, the completion date unsettable period means that even if the completion date is set on the completion schedule for the target order number for which the completion schedule is changed, the overload amount will increase in any production process, or This is the period when the shortage of procured items increases.

【0063】この期間を求めるためには、デ−タ記憶1
1より当該注番の構成品目に関する生産工程及び調達品
目に関する情報を引き出し、各生産工程については製造
可能日を、各調達品目については調達可能日を算出する
(ステップ701)。
In order to obtain this period, data storage 1
Information regarding the production process and the procurement item regarding the component item of the order number is extracted from 1, and the manufacture possible date is calculated for each production process and the procurement possible date is calculated for each procurement item (step 701).

【0064】次に、最下位の品目群に関して、最早完成
日を求める(ステップ702)。ここで、最早完成日と
は、同じ親品目を有する各品目の製造/調達可能日から
求められる品目群全ての製造/調達が可能な最も早い日
と定義する。つまり、最下位の品目群が1品目のみであ
る場合には、その品目の製造/調達可能日が最早完成日
となり、本例のように最下位の品目群が複数の品目から
なる場合には、それらの品目中で最も遅い製造/調達可
能日が最早完成日となる。
Next, the earliest completion date is obtained for the lowest item group (step 702). Here, the earliest completion date is defined as the earliest possible date for manufacturing / procuring all the item groups obtained from the possible manufacturing / procuring dates of each item having the same parent item. That is, when the lowest item group is only one item, the manufacture / procurement date of the item is the earliest completion date, and when the lowest item group is composed of a plurality of items as in this example. , The latest manufacture / procurement date of those items is the earliest completion date.

【0065】次に、一つ上位の品目群に着目(ステップ
703)し、各品目の製造(調達)可能日(au[u;工程レ
ベル(0,1,2,…)]、図21においては[A])と、下位
の品目群の最早完成日の翌日(xb[b;工程レベル(1,2,3,
…)]、図21においては[B])との前後関係を比較す
る(ステップ704から707)。そして、au≦xb(下
位品目群の最早完成日の翌日の方が将来または、同一
日)である場合には、xbを当該品目群の最早完成日と
し、新たにxbにxbの翌日を設定する(ステップ70
9)。また、xb<au(当該品目群の最早完成日の方が将
来)である場合には、auを当該品目群の最早完成日と
し、xbにauの翌日を設定する(ステップ708)。この
処理を最上位品目まで繰り返すことにより(ステップ7
11)、当該注番の仮の生産時期を設定する(ステップ
712)。この際、構成品目中で計画期間中に製造/調
達可能日が存在しない品目がある場合には、計画期間中
での生産は不可能と判定し、デ−タ入出力装置12にそ
の旨を提示する。
Next, paying attention to the next higher item group (step 703), the manufacturing (procurement) possible date of each item (a u [ u ; process level (0, 1, 2, ...)], FIG. [A]) and the day after the earliest completion date of the subordinate item group (x b [ b ; Process level (1,2,3,
]), And [B] in FIG. 21 is compared with the context (steps 704 to 707). Then, if a u ≤ x b (the next day of the earliest completion date of the subordinate item group is in the future or on the same day), then x b is the earliest completion date of the item group, and x x is newly added to x. Set the day after b (step 70)
9). If x b < au (the earliest completion date of the item group is in the future), a u is the earliest completion date of the item group, and x b is set to the day after a u (step 708). By repeating this process up to the top item (step 7
11), the provisional production time of the order number is set (step 712). At this time, if there is an item which does not have a manufacture / procureable date in the planning period among the constituent items, it is determined that the production in the planning period is impossible, and the data input / output device 12 is notified of that fact. Present.

【0066】このようにして、仮の生産時期を設定でき
た場合には、完成スケジュール上の当該注番の完成日を
その日に変更し(ステップ713)、MRP制御装置1
8にMRP実行指示を送る(ステップ714)。これに
より、MRP制御装置18は、リードタイム計画装置1
及びMRP展開装置8にそれぞれ処理開始の指示を出す
が、生産工程に対する作業負荷状況変化において過負荷
量が完成スケジュール変更前に比べ増加したり、調達品
目に対する品目引当状況変化において不足量が完成スケ
ジュール変更前の比べ増加していないかチェックする
(ステップ715)。その際、いずれかの生産工程また
は調達品目に関して増加が認められた場合には(ステッ
プ716)、その時点でMRP制御装置2は、リードタ
イム計画装置1及びMRP展開装置8に処理中止の指示
を出し、完成スケジュール上の当該注番の完成日を翌日
に変更し、再度処理開始の指示を出す(ステップ71
4)。この処理を全ての生産工程/調達品目について、
過負荷量/不足量が増加しない日が見つかるまで、繰り
返すことにより、当該注番の生産可能な時期を設定する
(ステップ717)。ここで、設定された生産可能時期
は、デ−タ記憶装置11に記憶される。
In this way, when the provisional production time can be set, the completion date of the order number on the completion schedule is changed to that day (step 713), and the MRP controller 1
8 to send an MRP execution instruction (step 714). As a result, the MRP control device 18 causes the lead time planning device 1 to
And the MRP expansion device 8 are instructed to start processing, respectively, but when the work load status changes to the production process, the overload amount increases compared to before the completion schedule change, and when the item allocation status change to the procurement item changes, the shortage amount becomes the completion schedule. It is checked whether the number has increased compared to the value before the change (step 715). At this time, if an increase is recognized in any of the production processes or procurement items (step 716), the MRP control device 2 then instructs the lead time planning device 1 and the MRP expansion device 8 to stop the processing. Issue, change the completion date of the order number on the completion schedule to the next day, and issue a processing start instruction again (step 71).
4). This process is applied to all production processes / procured items.
By repeating the process until the day when the overload / deficiency does not increase is found, the production-enabled period of the order number is set (step 717). Here, the set producible period is stored in the data storage device 11.

【0067】ところで、以上説明してきたような生産計
画の生成や、生成された生産計画に問題があるか否かの
確認や、問題がある場合の生産計画の調整は、データ入
出力装置12が提供する物理的なユーザインターフェイ
スを介して行なわれる。
By the way, the data input / output device 12 is responsible for generating the production plan as described above, confirming whether or not there is a problem in the generated production plan, and adjusting the production plan when there is a problem. This is done via the physical user interface provided.

【0068】以下、このようなユーザインターフェイス
の操作に対応させて、生産計画システムの、生成された
生産計画に問題があるか否かの確認や、問題がある場合
の生産計画の調整動作を説明する。
Hereinafter, the operation of the production planning system for confirming whether or not there is a problem in the generated production plan and the operation of adjusting the production plan when there is a problem will be described in correspondence with the operation of such a user interface. To do.

【0069】データ入出力装置12は、例えば、ブラウ
ン管ディスプレイ装置等の表示装置と、キーボード、マ
ウス等の入力装置を有している。
The data input / output device 12 has, for example, a display device such as a cathode ray tube display device and an input device such as a keyboard and a mouse.

【0070】まず、生産計画の生成指示を受け付けるた
めに、データ入出力装置12の表示装置に表示されるグ
ラフィックユーザインターフェイスを示す。
First, a graphic user interface displayed on the display unit of the data input / output unit 12 for receiving a production plan generation instruction is shown.

【0071】図8は、生産計画システムが起動された
時、データ入出力装置12が初めに表示する画面であ
る。
FIG. 8 is a screen initially displayed by the data input / output device 12 when the production planning system is activated.

【0072】コマンドメニューの内、「初期計画」コマ
ンドがマウスでピックされると、データ入出力装置12
は、MRP制御装置2へ、MRP実行を指示する。
When the "initial plan" command in the command menu is picked with the mouse, the data input / output device 12
Instructs the MRP control device 2 to execute MRP.

【0073】この指示により、前述したように生産計画
の生成が行なわれる。なお、受注処理システム1100
より、受け取った新たな受注情報を反映した生産計画の
生成も、「初期計画」コマンドがマウスでピックされる
ことにより行なわれる。
By this instruction, the production plan is generated as described above. The order processing system 1100
Thus, the production plan reflecting the new received order information is also generated by picking the "initial plan" command with the mouse.

【0074】一方、生産計画の生成後に、図8におい
て、コマンドメニューの内「問題解析」コマンド41が
マウスでピックされると、図1の問題点解析指示19が
送られる。問題解析装置7は、この問題点解析指示19
を受けて、データ記憶装置11から、生成された生産計
画を入力する。
On the other hand, after the production plan is generated, when the "problem analysis" command 41 in the command menu in FIG. 8 is picked with the mouse, the problem analysis instruction 19 of FIG. 1 is sent. The problem analysis device 7 uses this problem analysis instruction 19
In response, the generated production plan is input from the data storage device 11.

【0075】問題解析装置7は、生産計画内容をサーチ
して、その最も上流側のショップの着手日が現在日より
前(つまり、現在日より以前に製造を開始していなけれ
ば、製品の完成スケジュールを満足できない品目)とな
る品目の一覧を、注番毎に作成し、その結果20をデー
タ入出力装置12へ出力し、問題点解析結果をデータ入
出力装置12の表示装置に表示する。
The problem analysis device 7 searches the contents of the production plan, and if the start date of the shop on the most upstream side is before the current date (that is, if the production is not started before the current date, the completion of the product is completed). A list of items for which the schedule cannot be satisfied) is created for each order number, the result 20 is output to the data input / output device 12, and the problem analysis result is displayed on the display device of the data input / output device 12.

【0076】また、この際、外部からの調達部品の内、
発注日が現在日より前(つまり、現在日より以前に発注
を行なっていなければ、生産計画を満足できない品目)
となる品目の一覧を作成し、その結果もデータ入出力装
置12へ出力し、表示するようにしてもよい。
At this time, among the parts procured from the outside,
The order date is before the current date (that is, if the order is not placed before the current date, the production plan cannot be satisfied).
It is also possible to create a list of items to be obtained and output the result to the data input / output device 12 for display.

【0077】図9に問題点解析結果の出力画面を示す。FIG. 9 shows an output screen of the problem analysis result.

【0078】図9中の問題区間表示表42は、横軸に半
月単位の期間、縦軸に製品のカテゴリをとってある。
In the problem section display table 42 in FIG. 9, the horizontal axis represents the period of a half month unit, and the vertical axis represents the product category.

【0079】縦横軸で区切られる各マトリクスは、横軸
で表される範囲内に納期がある注番の内、対応する品目
中に製造着手日もしくは外部調達部品の発注日が現在よ
り以前に設定されているものがあって、製品の完成スケ
ジュールを満足できないものがある場合、濃色で表示さ
れる。また、その際、問題発生状況を示すための情報と
して、マトリクス内に含まれる件数、数量、遅れ件数
(最も上流側のショップの着手日が現在日より以前とな
る製品数)、最大遅れ(最も上流側のショップの着手日
から現在日までの日数)等が表示される。
Each matrix delimited by the vertical and horizontal axes has a delivery date within the range represented by the horizontal axis, and the manufacturing start date or the order date of the externally procured parts is set in the corresponding item before the present date. If there are some that are not satisfied with the completion schedule of the product, they are displayed in dark color. At that time, the number of cases, quantity, number of delays (number of products whose start date of the upstream shop is earlier than the current date), maximum delay (most The number of days from the start date of the shop on the upstream side to the current date) is displayed.

【0080】さて、計画立案者は、これらの問題が発生
しているマトリクスの詳細な情報を以下の手順により参
照することができる。
Now, the planner can refer to the detailed information of the matrix where these problems occur by the following procedure.

【0081】詳細情報マトリクスの決定 マウスにより、詳細情報を参照しようとするマトリクス
をピックする。図9は、「期間:3月/上、カテゴリ:
2」のマトリクス部分がピックされていることを示して
いる。
Determination of detailed information matrix A matrix for which detailed information is to be referred is picked up with the mouse. FIG. 9 shows “Period: March / Upper, Category:
It indicates that the matrix portion of "2" is picked.

【0082】在庫不足/着手日遅れ注文一覧の表示 コマンドメニューの内、「注文一覧」メニュー44をピ
ックする。「注文一覧」メニューをピックすることによ
り、詳細情報として、着手遅れ注文一覧表43が表示さ
れる。着手遅れ注文一覧表43には、在庫不足(使用す
る外部調達部品の発注日が現在日より以前である状態)
もしくは、着手遅れ(製造着手日が現在日より以前であ
る状態)を発生している注番、その注番の製品に関して
在庫不足、着手遅れを発生している品目数(関係件
数)、納期および、遅れ/余裕が表示される(遅れ/余
裕の詳細については、後述する。)。
Insufficient stock / Launch start date Display of order list Pick the "order list" menu 44 from the command menu. By picking the "order list" menu, the late-start order list 43 is displayed as detailed information. There is a shortage of stock in the delayed start list 43 (the order date of the externally procured parts used is before the current date)
Or, the order number that is behind the start (the date when the manufacturing start date is before the current date), inventory shortage for the product of that order number, the number of items that are behind the start (number of related cases), delivery date and , Delay / margin is displayed (details of the delay / margin will be described later).

【0083】一方、図9において詳細情報参照マトリク
スを決定後、コマンドメニューの内、「選択」メニュー
45をピックすると、図10に示す注番/日付別問題発
生箇所表示表46が表示される。
On the other hand, when the "select" menu 45 of the command menu is picked after the detailed information reference matrix is determined in FIG. 9, the order number / date problem occurrence point display table 46 shown in FIG. 10 is displayed.

【0084】図10中の注番/日付別問題発生箇所表示
表46は、横軸に日付、縦軸に注番をとってある。
In the note number / date problem occurrence point display table 46 in FIG. 10, the horizontal axis indicates the date and the vertical axis indicates the note number.

【0085】また、表示されている期間は、図9に示し
た「期間:3月/上、カテゴリ:2」に対応している。
The displayed period corresponds to "period: March / upper, category: 2" shown in FIG.

【0086】注番/日付別問題発生箇所表示表46で、
濃色のマトリクス部分が問題発生箇所を示しており、発
生問題状況を示すための情報として、最大遅れと、その
注番の製品に関して着手遅れ、在庫不足を発生している
品目数が表示されている。
In the problem location display table 46 by order number / date,
The dark matrix shows the problem occurrence point.The maximum delay and the number of items for which the order number is delayed or insufficient for the product of the order number are displayed as information for indicating the problem occurrence status. There is.

【0087】ここで、さらに、注番/日付別問題発生箇
所表示表46において、問題が発生しているマトリクス
の詳細情報は、以下の手順により参照することができ
る。
Here, further, in the problem number display table 46 by order number / date, the detailed information of the matrix in which the problem occurs can be referred to by the following procedure.

【0088】詳細情報参照マトリクスの決定 マウスにより、詳細情報を参照しようとするマトリクス
をピックする。図10には、「期間:3/4、注番:1
003」マトリクスがピックされていることを示してい
る。
Determination of Detailed Information Reference Matrix A matrix for which detailed information is to be referred is picked up with the mouse. In Fig. 10, "Period: 3/4, note number: 1
This indicates that the "003" matrix has been picked.

【0089】詳細情報指示 コマンドメニューの内、「詳細」メニュー48をピック
する。「詳細」メニューをピックすることにより、詳細
情報一覧表47が表示される。詳細情報一覧表47に
は、指定された注番の製品名、型式、数量、着手遅れ日
数(製造着手日から現在日までの日数)等が表示され
る。
Detailed Information Instruction Pick the “Details” menu 48 from the command menu. A detailed information list 47 is displayed by picking the “details” menu. The detailed information list 47 displays the product name, model, quantity, start delay days (number of days from the start date of manufacture to the current date) of the specified order number, and the like.

【0090】着手遅れ品目一覧表示 の「詳細」メニュー48の代わりに「品目一覧」メニ
ュー49をピックすることにより、図11に示す着手遅
れ一覧表画面50に、指定された注番の製品に関して着
手遅れを発生している全品目の着手遅れ日数、数量等が
表示される。
By picking the "item list" menu 49 instead of the "details" menu 48 for displaying the item list of delayed start, the start delay list screen 50 shown in FIG. 11 is displayed for the products of the specified order number. Displays the number of days late, the quantity, etc. of all the items that are late.

【0091】さて、以上の問題点解析装置7による問題
点のデータ入出力装置12への表示より、生産計画の問
題点が確認された場合、計画立案者は、生産計画を調整
しなければならない。
When the problem of the production plan is confirmed from the display of the problem on the data input / output device 12 by the problem analysis device 7 described above, the planner must adjust the production plan. .

【0092】生産計画の調整は、図12に示す表示上で
行なうことができる。
The adjustment of the production plan can be performed on the display shown in FIG.

【0093】図12は、問題経路表示部53、生産能力
表示部54、完成日変更メニュー55、代替ショップメ
ニュー56、能力調整メニュー57、MRP実行指示メ
ニュー58、作業着手順序変更メニュー150、生産量
調整メニュー151、計画削除メニュー156、調整実
行メニュー157、対策プロポーザルメニュー93、生
産能力変更開始時点設定ダイアル59、生産能力変更修
了時点設定ダイアル60、生産能力設定ダイアル61等
から構成される。
FIG. 12 shows the problem route display section 53, the production capacity display section 54, the completion date change menu 55, the alternative shop menu 56, the capacity adjustment menu 57, the MRP execution instruction menu 58, the work start order change menu 150, and the production amount. It comprises an adjustment menu 151, a plan deletion menu 156, an adjustment execution menu 157, a countermeasure proposal menu 93, a production capacity change start point setting dial 59, a production capacity change end point setting dial 60, a production capacity setting dial 61 and the like.

【0094】図12の表示は、以下の手順により呼び出
され、この呼び出された表示中の問題経路表示部53
は、問題経路を表示する。経路とは、品目の製造工程を
ショップとリードタイムとの関連で示したものをいう。
問題経路とは、着手遅れを発生している品目の内、対策
品目として選択された品目の経路である。
The display of FIG. 12 is called by the following procedure, and the called problem route display portion 53 is being displayed.
Displays the problem route. The route refers to the manufacturing process of the item in relation to the shop and the lead time.
The problem route is the route of the item selected as the countermeasure item among the items for which the start delay has occurred.

【0095】対策品目の選択 生産計画の調整を行う上において、その対象となる品目
(在庫不足/着手遅れを発生している品目)を選択す
る。例えば、図11の在庫不足/着手遅れ品目一覧表5
0において、「仕切り板」をマウスでピックした後、
「終了」ボタン52をマウスでピックすることにより、
対象となる品目として「仕切り板」が選択される。
Selection of Countermeasure Item In adjusting the production plan, the target item (item in which inventory shortage / starting delay has occurred) is selected. For example, inventory shortage / delayed item list 5 in FIG.
In 0, after picking the "partition plate" with the mouse,
By picking the "End" button 52 with the mouse,
"Partition board" is selected as the target item.

【0096】生産計画調整指示 図9の出力画面のコマンドメニューの内「調整」メニュ
ー51をピックする。
Production plan adjustment instruction Pick the "adjustment" menu 51 in the command menu of the output screen of FIG.

【0097】問題点解析 これにより、データ入出力装置12から問題点解析指示
19が送られる。問題点解析装置7は、この問題点解析
指示19を受けて、データ記憶装置11から生産計画2
1を入力する。
Problem Analysis As a result, the problem analysis instruction 19 is sent from the data input / output device 12. Upon receiving the problem analysis instruction 19, the problem analysis device 7 receives the production plan 2 from the data storage device 11.
Enter 1.

【0098】また、問題点解析装置7は、で選択され
た対策品目を製造するために使用される各ショップとそ
の負荷状況を求め、その結果20をデータ入出力装置1
2へ出力する。
Further, the problem analysis device 7 obtains each shop used to manufacture the countermeasure item selected in and its load status, and outputs the result 20 to the data input / output device 1.
Output to 2.

【0099】問題経路表示 データ入出力装置12は、問題点解析結果20を問題経
路表示部53に所定のフォーマットで表示する。
Problem Route Display The data input / output device 12 displays the problem analysis result 20 on the problem route display unit 53 in a predetermined format.

【0100】なお、この問題経路表示部53の表示フォ
ーマットは、以下のような特徴を持つ。
The display format of the problem route display section 53 has the following features.

【0101】対策品目の経路に関係するショップにつ
いてのみ表示する。
Only the shops related to the route of the countermeasure item are displayed.

【0102】各ショップの各期間の負荷状況(作業量
/生産量)を、その大小に応じて色分け表示する。
The load status (work volume / production volume) of each shop for each period is displayed in different colors according to its size.

【0103】各ショップの各期間の負荷状況の表示の
上に重ねて、対策対象品目の経路を示す。図中の太線枠
で示したのが問題経路であり、順次ショップ8、7、
3、2、1により当該品目が製造されることを示してい
る。また、1つの太枠矩形は、1つのショップにおける
日程を示し、その横軸方向が、その工程のリードタイム
を示す。
The route of the countermeasure target item is shown on the display of the load status of each shop for each period. The problem route is indicated by the bold frame in the figure, and the shops 8, 7 and
3, 2, 1 indicates that the item is manufactured. In addition, one thick frame rectangle indicates the schedule in one shop, and the horizontal axis direction indicates the lead time of the process.

【0104】問題経路表示53を、このように構成する
ことにより、生産計画者は、問題経路が理解しやすくな
ると同時に、作業量の面でも、込み具合の大きな所から
対策を打つというような意志決定を容易に行うことが可
能となる。
By constructing the problem route display 53 in this way, the production planner can easily understand the problem route, and at the same time, in terms of the amount of work, he / she will take a countermeasure from a place with a large degree of complexity. It will be possible to make a decision easily.

【0105】さて、この状態で、「対策プロポーザル」
メニュー93がピックされると、データ記憶装置11
に、対策品目を用いる注番について、最終判定として、
受注に引き当てられていない注番の生産スケジュールを
変更することにより、立案可能な旨が記憶されている場
合には、図19に示すような領域95に、その旨表示す
る。また、この際、この注番について、データ記憶装置
11にスケジュール変更対象注番として記憶されている
注番についての情報も、合わせて表示するようにしても
良い。また、作業量、在庫量の面のいずれが問題である
かを合わせて表示するようにする。
By the way, in this state, "measure proposal"
When the menu 93 is picked up, the data storage device 11
For the order number using countermeasure items, as the final judgment,
When the fact that a plan can be planned is stored by changing the production schedule of the order number that is not assigned to the order, the fact is displayed in the area 95 as shown in FIG. Further, at this time, for this order number, information about the order number stored in the data storage device 11 as the schedule change target order number may be displayed together. In addition, whether the amount of work or the amount of inventory is a problem is displayed together.

【0106】この際、表示されている注番に対して、生
産を取り止めたり生産量を減らしたりするのではなく、
生産時期を将来にずらすことにより問題の解決を図るこ
とが即座に意思決定できる場合には、領域95の「完成
日変更案提示」をピックすることにより、当該注番に対
する対策立案指示が対策立案装置100に送られ、MR
P制御装置18にその旨の指示が送られる。その結果得
られた当該注番の完成時期は、デ−タ記憶装置11に記
憶され、図20に示すように、表示される。
At this time, instead of stopping the production or reducing the production amount for the displayed order number,
When it is possible to immediately make a decision to solve the problem by shifting the production time to the future, by picking the “completion of change plan of completion date” in the area 95, the measure planning instruction for the order number will be taken. MR sent to device 100
An instruction to that effect is sent to the P control device 18. The completion time of the order number obtained as a result is stored in the data storage device 11 and displayed as shown in FIG.

【0107】また、最終判定として、注番に対応する生
産要求を満足する生産計画が立案不可能な場合がある旨
が、記憶されている場合には、その旨を表示するように
する。
Further, as a final judgment, if it is stored that the production plan satisfying the production request corresponding to the order number cannot be drafted, that fact is displayed.

【0108】また、この場合も、作業量、在庫量の面の
いずれが問題であるかを合わせて表示するようにする。
Also in this case, which of the work amount and the stock amount is the problem is also displayed.

【0109】なお、前述したMRP展開装置8、作業量
解析装置27、生産計画実行判定装置101により行わ
れる作業量、在庫量の面からの生産計画の判定は、生産
計画の生成の際に行わずに、この対策プロポーザルメニ
ュー93がピックされた際に、データ記憶装置11に記
憶された詳細な生産計画に基づいて行うようにしても良
い。
The determination of the production plan in terms of the amount of work and the amount of inventory performed by the MRP expansion device 8, the work amount analysis device 27, and the production plan execution determination device 101 described above is performed when the production plan is generated. Alternatively, when the countermeasure proposal menu 93 is picked up, it may be performed based on the detailed production plan stored in the data storage device 11.

【0110】これにより、生産計画立案者は、対策品目
についての対策の指針を得ることができたので、この指
針に基づいて対策を決定し、生産計画の調整を行う。
As a result, the production planner was able to obtain the guideline for the countermeasure for the countermeasure item, so the countermeasure is determined based on this guideline and the production plan is adjusted.

【0111】さて、生産計画の調整は、完成日変更メニ
ュー55、代替ショップメニュー56、能力調整メニュ
ー57、MRP実行指示メニュー58、作業着手順序変
更メニュー150、生産量調整メニュー151、計画削
除メニュー156を用いて行う。
Now, in the adjustment of the production plan, the completion date change menu 55, the alternative shop menu 56, the capacity adjustment menu 57, the MRP execution instruction menu 58, the work start order change menu 150, the production amount adjustment menu 151, the plan deletion menu 156. Using.

【0112】まず、生産計画立案者が対策として、ショ
ップの能力の変更を行うことを決定した場合には、以下
の手順により、生産計画の調整を行う。
First, when the production planner decides to change the capacity of the shop as a countermeasure, the production plan is adjusted by the following procedure.

【0113】生産能力変更ショップの選択 問題経路表示部53の中の問題経路中で、生産能力を変
更しようとするショップをマウスでピックした後に、能
力調整メニュー57をピックする。例えば、図12のs
hop3の太線で囲まれた部分をマウスでピックする。
Selection of production capacity change shop In the problem route in the problem route display portion 53, after picking the shop whose production capacity is to be changed with the mouse, the capability adjustment menu 57 is selected. For example, s in FIG.
Pick the part surrounded by the thick line of hop3 with the mouse.

【0114】生産能力表示部54の表示 これに従い、データ入出力装置12は、図12に示すよ
うに上記で選択された工程の負荷状況、生産能力を生
産能力表示部54に示すフォーマットで表示する。生産
能力表示部54は、負荷状況62、生産能力線63、生
産能力変更開始点64、生産能力変更開終了点65、生
産能力変更対象区間枠66から構成される。
Display on production capacity display section 54 Accordingly, the data input / output device 12 displays the load status and the production capacity of the process selected above in the format shown on the production capacity display section 54 as shown in FIG. . The production capacity display unit 54 includes a load status 62, a production capacity line 63, a production capacity change start point 64, a production capacity change open / close point 65, and a production capacity change target section frame 66.

【0115】生産能力変更開始/終了点の設定 生産能力変更開始時点設定ダイアル59、生産能力変更
終了時点設定ダイアル60をマウスでピックすることに
より生産能力変更開始点64、生産能力変更終了点65
を左右に移動する。マウスでのピックにおいては、例え
ば2ボタン式のマウスの場合は、マウスの左ボタンをピ
ックした場合は生産能力変更開始/終了点を左へ、右ボ
タンをピックした場合は右へ移動する。
Setting of production capacity change start / end point Production capacity change start point setting dial 59 and production capacity change end point setting dial 60 are picked up with a mouse to start production capacity change start point 64 and production capacity change end point 65.
To move left and right. In picking with a mouse, for example, in the case of a two-button mouse, when the left mouse button is picked, the production capacity change start / end point is moved to the left, and when the right button is picked, it is moved to the right.

【0116】生産能力変更 生産能力設定ダイアル61をマウスでピックすることに
より、生産能力変更開始点64と生産能力変更終了点6
5の間の区間の生産能力を変更する。マウスでのピック
においては、例えば2ボタン式のマウスの場合は、マウ
スの左ボタンをピックした場合は生産能力線63を下
(生産能力減少)へ、右ボタンをピックした場合は上
(生産能力増加)へ移動する。
Production capacity change By picking the production capacity setting dial 61 with the mouse, the production capacity change start point 64 and the production capacity change end point 6
Change the production capacity of the section between 5. In the case of picking with a mouse, for example, in the case of a two-button type mouse, if the left mouse button is picked, the production capacity line 63 is moved downward (production capacity is reduced), and if the right button is picked, production capacity is increased (production capacity is reduced). Increase).

【0117】リードタイム変更/MRP計算実行 この後、調整実行メニュー157がピックされたら、デ
ータ入出力装置12は、の生産能力変更結果に基づき
生産能力調整指示15を生産能力調整装置4へ出す。生
産能力調整装置4は、生産能力調整結果とMRP実行指
示22をMRP制御装置2へ送る。MRP実行装置2
は、生産能力調整結果に基づき、MRP展開装置8と協
調して、選択されたショップを含む問題経路により製造
される注番についての生産計画のみを生成しなおす。す
なわち、これ以外の注番に関する生産計画を前提条件と
して生産計画のみを計算しなおし、生産計画を修正す
る。修正された生産計画は、データ記憶装置11に記憶
される。但し、生産能力調整結果を踏まえて、全ての注
番の生産計画を生成しなおすようにしても良い。なお、
この生産計画の修正もしくは生成の際には、MRP展開
装置8、作業量解析装置27、生産計画実行判定装置1
01は、再度、前述した作業量、在庫量の面からの判定
を行い、データ記憶装置11の判定の内容を更新する。
After that, when the adjustment execution menu 157 is picked up, the data input / output device 12 issues a production capacity adjustment instruction 15 to the production capacity adjustment device 4 based on the production capacity change result. The production capacity adjustment device 4 sends the production capacity adjustment result and the MRP execution instruction 22 to the MRP control device 2. MRP execution device 2
On the basis of the production capacity adjustment result, in cooperation with the MRP expansion device 8, regenerates only the production plan for the order number manufactured by the problem route including the selected shop. That is, only the production plan is recalculated on the basis of the production plans related to the other order numbers, and the production plan is corrected. The corrected production plan is stored in the data storage device 11. However, the production plans for all the order numbers may be regenerated based on the production capacity adjustment result. In addition,
When correcting or generating this production plan, the MRP expansion device 8, the work amount analysis device 27, the production plan execution determination device 1
01 again makes a determination from the aspects of the work amount and the stock amount described above, and updates the determination content of the data storage device 11.

【0118】問題経路表示部変更 データ入出力装置12は、データ記憶装置11からMR
P実行結果21を入力し、対策対象品目に関係する生産
期間を修正表示する。
Change the problem route display section. The data input / output device 12 changes the data storage device 11 from the MR.
The P execution result 21 is input, and the production period relating to the countermeasure target item is corrected and displayed.

【0119】〜により、生産計画者は、簡単な操作
で生産能力を変更できると同時に、生産能力の変更が生
産計画にどのような影響を及ぼすかをオンラインで確認
することが可能になる。
With the above, the production planner can change the production capacity by a simple operation, and at the same time, can confirm online how the change in the production capacity affects the production plan.

【0120】ところで、図12の生産能力表示部54の
表示は、図13のように構成しても良い。図12との違
いは、リードタイム表示部90と能力増加ボタン91及
び能力減少ボタン92を設けたことである。この場合、
上記の操作が異なるのでこれについて説明する。
By the way, the display of the production capacity display section 54 of FIG. 12 may be configured as shown in FIG. The difference from FIG. 12 is that a lead time display section 90, a capacity increase button 91, and a capacity decrease button 92 are provided. in this case,
Since the above operation is different, this will be described.

【0121】’生産能力変更開始/終了点の設定 負荷状況62の棒グラフをマウスの左ボタンでピックす
ることによりその日付に生産能力変更開始点64を、マ
ウスの右ボタンでピックすることによりその日付に生産
能力変更終了点65を設定する。
[Setting of production capacity change start / end point] By picking the bar graph of the load status 62 with the left mouse button, the production capacity change start point 64 is picked on that date and with the right mouse button the date is selected. The production capacity change end point 65 is set to.

【0122】’生産能力変更 能力増加ボタン91及び能力減少ボタン92をマウスで
ピックすることにより、生産能力変更開始点64と生産
能力変更終了点65の間の区間の生産能力を変更する。
[Production Capacity Change] The production capacity in the section between the production capacity change start point 64 and the production capacity change end point 65 is changed by picking the capacity increase button 91 and the capacity decrease button 92 with the mouse.

【0123】次に、生産計画立案者が対策として、完成
日の変更を行うことを決定した場合には、以下の手順に
より、生産計画の調整を行う。
Next, when the production planner decides to change the completion date as a countermeasure, the production plan is adjusted by the following procedure.

【0124】図14に製品完成日変更用画面を示す。図
14の表示画面は、図12の完成日変更モード切り替え
メニュー55をマウスでピックすることにより呼び出さ
れる。
FIG. 14 shows a screen for changing the product completion date. The display screen of FIG. 14 is called by picking the completion date change mode switching menu 55 of FIG. 12 with the mouse.

【0125】さて、この製品完成日変更用画面におい
て、遅れ/余裕表示部68は、注番表示75、余裕表示
76、遅れ表示78及び、遅れ/余裕棒グラフ79によ
り構成される。
On the product completion date change screen, the delay / margin display section 68 is composed of a note number display 75, a margin display 76, a delay display 78, and a delay / margin bar graph 79.

【0126】遅れ/余裕棒グラフ79において、「現
在」と「着手」の間の黒色の部分が着手遅れ日数を、
「完成」と「納期」の間の白色の部分が、余裕日数を表
している。
In the delay / margin bar graph 79, the black portion between “current” and “start” indicates the number of days behind start,
The white part between "completion" and "delivery date" represents the number of spare days.

【0127】ここで、「納期」は顧客に回答した期日で
あり、「完成」は生産計画上の製品完成予定日である。
前述したように、生産計画を作成する場合、顧客納期に
ある程度の余裕をもたせて製品完成予定日を設定するの
が一般的である。
Here, the "delivery date" is the date when the customer answers, and the "completion" is the scheduled date of product completion in the production plan.
As described above, when a production plan is created, it is common to set a scheduled product completion date with a certain amount of customer delivery time.

【0128】従って、今着手遅れを発生している製品に
対しては、この完成予定日を納期に近付けることによ
り、着手遅れを解消できる可能性がある。
Therefore, for a product which has a delay in starting work, there is a possibility that the delay in starting work can be resolved by bringing this scheduled completion date closer to the delivery date.

【0129】製品完成日の変更は、以下の手順により実
行される。
The change of the product completion date is executed by the following procedure.

【0130】完成日変更注番の選択 問題経路が複数個表示されている場合、どの注番の製品
を対象に完成日を変更するかを選択する。注番の選択の
ためには、注番変更ダイアル73をマウスでピックす
る。マウスでのピックにおいては、例えば2ボタン式の
マウスの場合は、マウスの左ボタンをピックした場合は
注番を増加し、右ボタンをピックした場合は注番を減少
する。図14においては問題経路が一つしか表示されて
いないので注番1003が完成日変更の対象となる。
Selection of completion date change order number When a plurality of problem routes are displayed, it is selected which order number product is to be changed in completion date. To select a note number, pick the note number change dial 73 with the mouse. In picking with a mouse, for example, in the case of a two-button mouse, when the left button of the mouse is picked, the note number is increased, and when the right button is picked, the note number is decreased. In FIG. 14, since only one problem route is displayed, the order number 1003 is the target for changing the completion date.

【0131】完成日変更 完成日変更ダイアル74をマウスでピックすることによ
り完成日を変更する。例えば、2ボタン式のマウスの場
合は、マウスの左ボタンをピックした場合は完成日を早
く(「完成」表示を左へ動かす)し、右ボタンをピック
した場合は完成日を遅く(「完成」表示を右へ動かす)
する。
Change of Completion Date The completion date is changed by picking the completion date change dial 74 with the mouse. For example, in the case of a two-button mouse, if you pick the left mouse button, the completion date will be earlier (move the "Complete" display to the left), and if you pick the right button, the completion date will be later ("Complete""Move the display to the right)
I do.

【0132】なお、遅れ/余裕棒グラフ79をマウスで
ピックしたまま左右に動かす(ドラッグする)ことによ
って、完成日を変更するようにしても良い。
The completion date may be changed by moving (dragging) the delay / margin bar graph 79 left and right while picking it up with the mouse.

【0133】MRP計算実行 調整実行メニュー157がピックされると、データ入出
力装置12は、の完成日変更結果に基づき完成日調整
指示16を完成日調整装置5へ指令する。完成日調整装
置5は、完成日調整結果とMRP実行指示23をMRP
制御装置2に指令する。MRP制御装置2は、完成日調
整結果に基づきMRP展開装置8と協調して、選択され
たショップを含む問題経路により製造される注番の生産
計画のみを生成しなおす。すなわち、これ以外の注番に
関する生産計画を前提条件として、選択された注番につ
いての生産計画のみを計算しなおし、生産計画を修正す
る。修正された生産計画は、データ記憶装置11へ記憶
される。ただし、完成日調整結果に基づき完成スケジュ
ールを変更し、全ての注番についての生産計画を生成し
なおすようにしても良い。なお、この生産計画の修正も
しくは生成の際には、MRP展開装置8、作業量解析装
置27、生産計画実行判定装置101は、再度、前述し
た作業量、在庫量の面からの判定を行い、データ記憶装
置11の判定の内容を更新する。
MRP Calculation Execution When the adjustment execution menu 157 is picked, the data input / output device 12 issues a completion date adjustment instruction 16 to the completion date adjustment device 5 based on the completion date change result of. The completion date adjustment device 5 displays the completion date adjustment result and the MRP execution instruction 23 in the MRP.
The control device 2 is instructed. The MRP control device 2 cooperates with the MRP development device 8 based on the completion date adjustment result to regenerate only the production plan of the order number manufactured by the problem route including the selected shop. That is, with the production plans for other order numbers as a precondition, only the production plans for the selected order numbers are recalculated and the production plan is revised. The modified production plan is stored in the data storage device 11. However, the completion schedule may be changed based on the completion date adjustment result, and the production plans for all the order numbers may be regenerated. When the production plan is modified or generated, the MRP expansion device 8, the work amount analysis device 27, and the production plan execution determination device 101 again perform the determination in terms of the work amount and the stock amount, The contents of the judgment of the data storage device 11 are updated.

【0134】問題経路/遅れ/余裕表示部変更 データ入出力装置12は、データ記憶装置11から新た
な生産計画を入力し、問題経路/遅れ/余裕表示部を修
正表示する。
Change of problem route / delay / margin display unit The data input / output device 12 inputs a new production plan from the data storage device 11 and corrects and displays the problem route / delay / margin display unit.

【0135】以上〜により、生産計画者は、簡単な
操作で完成日を変更できると同時に、製品完成日の変更
が生産計画にどのような影響を及ぼすかをオンラインで
確認することが可能になる。
As described above, the production planner can change the completion date by a simple operation, and at the same time, can confirm online how the change of the product completion date affects the production plan. .

【0136】次に、生産計画立案者が対策として、ショ
ップの変更を行うことを決定した場合には、以下の手順
により、生産計画の調整を行う。
Next, when the production planner decides to change the shop as a countermeasure, the production plan is adjusted by the following procedure.

【0137】図15に生産ショップ変更用画面を示す。
図15に示す生産ショップ変更用画面は、図12の代替
ショップモード切り替えメニュー56がピックされた場
合に呼びだされる。
FIG. 15 shows a screen for changing the production shop.
The production shop change screen shown in FIG. 15 is called when the alternative shop mode switching menu 56 of FIG. 12 is picked up.

【0138】図中の、代替ショップ表示部81には、問
題経路のうちの任意のショップを選択した際に、そのシ
ョップと同等の作業を実行しうる代替ショップ群と、各
代替ショップにおけるリードタイムおよび、各代替ショ
ップを採用した際の改善日数つまり、リードタイム短縮
日数が表示される。
In the alternative shop display portion 81 in the figure, when an arbitrary shop in the problem route is selected, a group of alternative shops which can execute the same work as that shop and the lead time in each alternative shop. Also, the number of days for improvement when each alternative shop is adopted, that is, the number of days for shortening the lead time is displayed.

【0139】すなわち、問題経路のうちの任意の工程に
代替ショップが存在する場合、代替ショップを採用する
ことにより着手遅れを解消できる可能性がある。
That is, when an alternative shop exists in an arbitrary process in the problem route, there is a possibility that the start delay can be resolved by adopting the alternative shop.

【0140】生産ショップを変更しながらの生産計画調
整は以下の手順により実行される。
The production plan adjustment while changing the production shop is executed by the following procedure.

【0141】生産ショップ変更工程の選択 問題経路表示部80の中で、生産ショップを変更しよう
とするショップをマウスでピックする。例えば、図15
のshop3の太線で囲まれた部分をマウスでピックす
る。代替ショップが存在する場合、代替ショップ表示部
81が表示される。
Selection of production shop change process In the problem route display portion 80, a shop for which the production shop is to be changed is picked with the mouse. For example, FIG.
Pick the part of shop3 surrounded by the thick line with the mouse. When there is an alternative shop, the alternative shop display section 81 is displayed.

【0142】また、問題経路表示部53にも代替ショッ
プが図15に示すようなフォーマットで表示される。
Also, the alternative shop is displayed in the problem route display portion 53 in the format as shown in FIG.

【0143】代替ショップ選択 代替ショップ表示部81の各ショップ名をマウスでピッ
クすることにより代替ショップを選択する。
Alternative shop selection The alternative shop is selected by picking each shop name in the alternative shop display area 81 with the mouse.

【0144】MRP計算実行 調整実行メニュー157がピックされると、データ入出
力装置12が、の代替ショップ選択結果に基づき代替
ショップ調整指示17を代替ショップ調整装置6へ指令
する。代替ショップ調整装置6は、MRP制御装置2へ
代替ショップ調整結果とMRP実行指示24を出力す
る。MRP制御装置2は、代替ショップ調整結果に基づ
き、MRP展開装置と協調して、選択されたショップを
含む問題経路により製造される注番についての生産計画
のみを生成しなおす。すなわち、これ以外の注番に関す
る生産計画を前提条件として対策品目についての生産計
画のみを計算しなおし、生産計画を修正する。修正され
た生産計画は、データ記憶装置11へ記憶される。ただ
し、代替ショップ調整結果を踏まえて、全ての注番の生
産計画を生成しなおすようにしても良い。なお、この生
産計画の修正もしくは、生成の際には、MRP展開装置
8、作業量解析装置27、生産計画実行判定装置101
は、再度、前述した作業量、在庫量の面から判定を行
い、データ記憶装置11の判定の内容を更新する。
MRP Calculation Execution When the adjustment execution menu 157 is picked up, the data input / output device 12 issues an alternative shop adjustment instruction 17 to the alternative shop adjustment device 6 based on the alternative shop selection result. The alternative shop adjustment device 6 outputs the alternative shop adjustment result and the MRP execution instruction 24 to the MRP control device 2. Based on the alternative shop adjustment result, the MRP control device 2 cooperates with the MRP expansion device to regenerate only the production plan for the order number manufactured by the problem route including the selected shop. That is, only the production plans for the countermeasure items are recalculated with the production plans for the other order numbers as a precondition, and the production plans are corrected. The modified production plan is stored in the data storage device 11. However, the production plans for all the order numbers may be regenerated based on the alternative shop adjustment result. When the production plan is modified or generated, the MRP expansion device 8, the work amount analysis device 27, the production plan execution determination device 101.
Performs the determination again from the aspects of the work amount and the inventory amount described above, and updates the determination content of the data storage device 11.

【0145】問題経路表示部変更 データ入出力装置12は、データ記憶装置11からMR
P実行結果21を入力し、代替ショップ採用後の問題経
路を修正表示する。
Change the problem route display section.
The P execution result 21 is input, and the problem route after the alternative shop is adopted is corrected and displayed.

【0146】以上〜により、生産計画者は、簡単な
操作で生産ショップを変更できると同時に、生産ショッ
プの変更が生産計画にどのような影響を及ぼすかをオン
ラインで確認することが可能になる。
As described above, the production planner can change the production shop by a simple operation, and at the same time, can confirm online how the change of the production shop affects the production plan.

【0147】次に、生産計画立案者が対策として作業着
手順序の変更を行うことを決定した場合には、以下の手
順により、生産計画の調整を行う。
Next, when the production planner decides to change the work start order as a countermeasure, the production plan is adjusted by the following procedure.

【0148】図16に作業着手順序変更用画面を示す。
作業着手順序変更用画面は、図12において、作業着手
順序変更メニュー150がピックされた場合に呼びださ
れる。
FIG. 16 shows a screen for changing the work start order.
The work start order change screen is called up when the work start order change menu 150 is picked in FIG.

【0149】図16中の着手順序変更表示部167に
は、問題経路の内の任意のショップを選択した際に、そ
のショップと、そのショップを含む期間内に作業すべき
ショップとに対応する注番の作業着手順序、その注番の
完成日、さらに着手順序の設定を入力する項目が表示さ
れる。
In the start order change display portion 167 in FIG. 16, when an arbitrary shop in the problem route is selected, the note corresponding to that shop and the shop to be worked within the period including the shop are displayed. The items for inputting the work start order of the number, the completion date of the order number, and the setting of the start order are displayed.

【0150】作業着手順序を変更しながらの生産計画調
整は以下の手順により実行される。
The production plan adjustment while changing the work start order is executed by the following procedure.

【0151】作業着手変更注番の選択 問題経路表示部53の中で、作業着手順序を変更しよう
とするショップをマウスでピックする。例えば、図16
のshop3の太線で囲まれた部分をマウスでピックす
る。その結果、着手順序変更表示部167に示すフォ−
マットで、選択されたショップを発生させている注番
と、そのショップを含む期間内に作業すべきショップを
発生させている注番の作業着手順序、その注番の完成
日、さらに着手順序の設定を入力する項目が表示され
る。
Selection of work start change order number In the problem route display portion 53, a shop for which the work start order is to be changed is picked with the mouse. For example, in FIG.
Pick the part of shop3 surrounded by the thick line with the mouse. As a result, the sequence shown in the start order change display section 167 is displayed.
On the mat, the order number of the order that generated the selected shop, the work start order of the order number that generated the shop that should work in the period including the shop, the completion date of the order, and the start order. The items for entering the settings are displayed.

【0152】作業着手順序変更 着手順序変更表示部167に表示される製品の注番群の
中から着手順序を変更する注番に対し変更したい前後の
着手順序を変更順序入力項目へ入力する。例えば、図1
6では着手順序3の注番1005を着手順序2にするた
めに、変更順序入力項目に着手順序2を入力する。
Work start order change The start order before and after the order for which the order is changed among the order numbers of the products displayed in the change order display area 167 is input to the change order input item. For example, FIG.
In step 6, in order to change the order number 1005 of the starting order 3 to the starting order 2, the starting order 2 is input to the change order input item.

【0153】MRP計算実行 データ入出力装置12が、の作業着手順序変更結果に
基づき、作業着手順序調整指示31を作業着手順序調整
装置33へ指令する。作業着手順序調整装置31は、M
RP制御装置2へ作業着手順序調整結果とMRP実行指
示23を指令する。MRP制御装置2は、作業着手順序
調整結果を満足するように、MRP展開装置と協調し
て、作業着手順序が変更された注番についての生産計画
のみを生成しなおす。すなわち、これ以外の注番に関す
る生産計画を前提条件として、対策品目についての生産
計画のみを計算しなおし、生産計画を修正する。修正さ
れた生産計画は、データ記憶装置11へ記憶される。な
お、この生産計画の修正の際には、MRP展開装置8、
作業量解析装置27、生産計画実行判定装置101は、
再度、前述した作業量、在庫量の面からの判定を行い、
データ記憶装置11の判定の内容を更新する。
MRP calculation execution The data input / output device 12 commands the work start order adjustment instruction 31 to the work start order adjustment device 33 based on the result of the work start order change. The work start order adjustment device 31 is M
The RP control device 2 is instructed of the work start order adjustment result and the MRP execution instruction 23. The MRP control device 2 cooperates with the MRP expansion device so as to satisfy the work start order adjustment result, and regenerates only the production plan for the order number in which the work start order is changed. That is, with the production plans for the other order numbers as a precondition, only the production plans for the countermeasure items are recalculated and the production plans are revised. The modified production plan is stored in the data storage device 11. When modifying this production plan, the MRP expansion device 8,
The work amount analysis device 27 and the production plan execution determination device 101 are
Again, judging from the aspects of work volume and inventory volume,
The contents of the judgment of the data storage device 11 are updated.

【0154】問題経路表示部変更 データ入出力装置12は、データ記憶装置11から生成
された新たな生産計画を入力し、問題経路表示部166
を修正表示する。
Change of problem route display unit The data input / output device 12 inputs the new production plan generated from the data storage device 11, and the problem route display unit 166.
Is corrected and displayed.

【0155】以上〜により、納期回答担当者は、簡
単な操作で作業着手順序を変更できると同時に、作業着
手順序の変更が生産計画にどのような影響を及ぼすかを
オンラインで確認することが可能になる。
As described above, the person in charge of delivery can change the work start order with a simple operation, and at the same time, can confirm online how the change of the work start order affects the production plan. become.

【0156】次に、生産計画立案者が対策として生産量
の変更を行うことを決定した場合には、以下の手順によ
り、生産計画の調整を行う。
Next, when the production planner decides to change the production amount as a countermeasure, the production plan is adjusted by the following procedure.

【0157】図17に生産量変更用画面を示す。図17
に生産量変更用画面は、図12の生産量調整メニュー1
51をマウスでピックすることにより呼びだされる。
FIG. 17 shows a screen for changing the production amount. FIG.
The production volume change screen is shown in the production volume adjustment menu 1 in FIG.
Called by picking 51 with the mouse.

【0158】図17中の生産量調整表示部177には、
問題経路の内の任意のショップを選択した際に、そのシ
ョップを発生させた注番、その完成日と生産量、余裕と
遅れが表示される。
The production amount adjustment display section 177 in FIG.
When you select any shop in the problem route, the order number that generated the shop, its completion date and production volume, margin and delay are displayed.

【0159】生産量を変更しながらの生産計画調整は、
以下の手順により実行される。
The production plan adjustment while changing the production amount is as follows.
The procedure is as follows.

【0160】生産量調整ショップの選択 問題経路表示部53の中で、生産量を変更しようとする
ショップをマウスでピックする。例えば、図17のsh
op3の太線で囲まれた部分をマウスでピックする。そ
の結果、生産量変更表示部177に示すフォーマット
で、そのショップを発生させた注番、その完成日と生産
量、余裕と遅れが表示される。
Selection of Production Quantity Adjustment Shop In the problem route display portion 53, the shop whose production quantity is to be changed is picked with the mouse. For example, sh in FIG.
Pick the part surrounded by the thick line in op3 with the mouse. As a result, in the format shown in the production amount change display portion 177, the order number that generated the shop, the completion date and the production amount, the margin and the delay are displayed.

【0161】生産量変更 生産量変更表示部177に表示される製品の注番群の中
から生産量を変更したい注番の生産量変更量項目へ変更
量を入力する。例えば、図17では注番1003の生産
量を15台から10台へ変更するために、変更量入力項
目に変更量10台を入力する。
Change of production amount The change amount is input to the production amount change amount item of the order number of which the production amount is to be changed from the product order number group displayed on the production amount change display portion 177. For example, in FIG. 17, in order to change the production amount of the order number 1003 from 15 to 10, the change amount of 10 is input in the change amount input item.

【0162】MRP計算実行 調整実行メニュー157がピックされると、データ入出
力装置12が、の生産量変更結果に基づき生産量調整
指示34を生産量調整装置40へ指令する。生産量調整
装置40は、MRP制御装置2へ生産量調整結果とMR
P実行指示39を出力する。MRP制御装置2は、生産
量調整結果を満足するように、MRP制御装置2は、生
産量調整結果に基づき、MRP展開装置と協調して、生
産量が変更された注番についての生産計画のみを生成し
なおす。すなわち、これ以外の注番に関する生産計画を
前提条件として、対策品目についての生産計画のみを計
算しなおし、生産計画を修正する。修正された生産計画
は、データ記憶装置11へ記憶される。ただし、生産量
調整結果に基づき完成スケジュールを変更し、全ての注
番について生産計画を生成しなおすようにしても良い。
なお、この生産計画の修正、生成の際には、MRP展開
装置8、作業量解析装置27、生産計画実行判定装置1
01は、前述した作業量、在庫量の面からの判定を、再
度行い、データ記憶装置11に記憶されている判定の内
容を更新する。
MRP Calculation Execution When the adjustment execution menu 157 is picked up, the data input / output device 12 commands the production amount adjustment instruction 34 to the production amount adjustment device 40 based on the production amount change result. The production amount adjusting device 40 sends the production amount adjusting result and the MR to the MRP control device 2.
The P execution instruction 39 is output. Based on the production amount adjustment result, the MRP control device 2 cooperates with the MRP expansion device so that the MRP control device 2 satisfies the production amount adjustment result, and only the production plan for the order number whose production amount has been changed. Is regenerated. That is, with the production plans for the other order numbers as a precondition, only the production plans for the countermeasure items are recalculated and the production plans are revised. The modified production plan is stored in the data storage device 11. However, the completion schedule may be changed based on the production amount adjustment result, and the production plans may be regenerated for all the order numbers.
When the production plan is corrected or generated, the MRP expansion device 8, the work amount analysis device 27, the production plan execution determination device 1
01 again performs the above-described determination in terms of the work amount and the inventory amount, and updates the content of the determination stored in the data storage device 11.

【0163】問題経路表示部変更 データ入出力装置12は、データ記憶装置11からMR
P実行結果21を入力し、問題経路表示部176を修正
表示する。
Change the problem route display section. The data input / output device 12 changes from the data storage device 11 to the MR.
The P execution result 21 is input, and the problem route display unit 176 is corrected and displayed.

【0164】以上〜により、生産計画担当者は、簡
単な操作で生産量を変更できると同時に、生産量の変更
が生産計画にどのような影響を及ぼすかをオンラインで
確認することが可能になる。
As described above, the person in charge of production planning can change the production amount by a simple operation, and at the same time, it is possible to confirm online how the change of the production amount affects the production plan. .

【0165】次に、生産計画立案者が対策として、ある
注番の生産計画の削除を行うことを決定した場合には、
以下の手順により、生産計画の調整を行う。
Next, when the production planner decides to delete the production plan of a certain order number as a countermeasure,
The production plan is adjusted by the following procedure.

【0166】図18に計画削除用画面を示す。図18に
計画削除用画面は、図12の計画削除メニュー156を
マウスでピックすることにより呼びだされる。
FIG. 18 shows the screen for plan deletion. The plan deletion screen in FIG. 18 is called by picking the plan deletion menu 156 in FIG. 12 with the mouse.

【0167】図中の計画削除表示部187には、問題経
路表示部53に表示されている注番に関する完成日と生
産量、余裕と遅れ、顧客引当状況が表示される。
In the plan deletion display portion 187 in the figure, the completion date and the production amount, the margin and the delay, and the customer allocation status regarding the order number displayed in the problem route display portion 53 are displayed.

【0168】計画を削除しながらの生産計画調整は以下
の手順により実行される。
The production plan adjustment while deleting the plan is executed by the following procedure.

【0169】計画削除注番の選択 問題経路が複数個表示されている場合、どの注番の製品
を対象に計画を削除するかを選択する。注番の選択のた
めには、注番変更ダイアル189をマウスでピックす
る。マウスでのピックにおいては、例えば2ボタン式の
マウスの場合は、マウスの左ボタンをピックした場合は
注番を増加し、右ボタンをピックした場合は注番を減少
する。図18においては問題経路が一つしか表示されて
いないので注番1003が計画削除の対象となる。
Selection of Plan Deletion Order Number When a plurality of problem routes are displayed, it is selected which order number product the plan is to be deleted from. To select a note number, pick the note number change dial 189 with the mouse. In picking with a mouse, for example, in the case of a two-button mouse, when the left button of the mouse is picked, the note number is increased, and when the right button is picked, the note number is decreased. In FIG. 18, since only one problem route is displayed, the order number 1003 is the target of plan deletion.

【0170】計画削除 計画削除表示部187に表示される注番に対し計画削除
の実行ボタンをピックする。
Plan deletion The plan deletion execution button is picked for the order number displayed in the plan deletion display area 187.

【0171】MRP計算実行 調整実行メニュー157がピックされると、データ入出
力装置12が、の計画削除結果に基づき計画削除指示
34を計画削除装置103へ指令する。計画削除装置1
03は、MRP制御装置2へ計画削除結果とMRP実行
指示39を出力する。MRP制御装置2は、計画削除結
果に基づき、完成スケジュールから、削除する注番につ
いての生産要求情報を削除し、MRP展開装置8に、新
たな生産計画の生成を指示する。生成された生産計画
は、データ記憶装置11へ記憶される。なお、この生産
計画の生成の際には、MRP展開装置8、作業量解析装
置27、生産計画実行判定装置101は、前述した作業
量、在庫量の面からの判定を、再度行い、データ記憶装
置11に記憶されている判定の内容を更新する。
MRP Calculation Execution When the adjustment execution menu 157 is picked up, the data input / output device 12 issues a plan deletion instruction 34 to the plan deletion device 103 based on the plan deletion result. Plan deletion device 1
03 outputs the plan deletion result and the MRP execution instruction 39 to the MRP control device 2. Based on the plan deletion result, the MRP control device 2 deletes the production request information for the order number to be deleted from the completion schedule, and instructs the MRP expansion device 8 to generate a new production plan. The produced production plan is stored in the data storage device 11. When the production plan is generated, the MRP expansion device 8, the work amount analysis device 27, and the production plan execution determination device 101 again perform the above-described determination in terms of the work amount and the stock amount, and store the data. The contents of the judgment stored in the device 11 are updated.

【0172】問題経路表示部変更 データ入出力装置12は、データ記憶装置11から新た
な生産計画を入力し、問題経路表示部186を修正表示
する。
Change of Problem Route Display Unit The data input / output device 12 inputs a new production plan from the data storage device 11 and corrects and displays the problem route display unit 186.

【0173】以上〜により、生産計画担当者は、簡
単な操作で計画を削除できると同時に、計画の削除が生
産計画にどのような影響を及ぼすかをオンラインで確認
することが可能になる。
As described above, the person in charge of production planning can delete a plan by a simple operation, and at the same time, can confirm online how the deletion of the plan affects the production plan.

【0174】さて、このようにして、問題解析と生産計
画の調整を繰り返し、最終的に問題経路のない生産計画
が立案できたら、生産計画立案者は、生産計画システム
1000と、受注処理システム1100に、受注に引き
当てた注番の完成予定日が、要求納期以前の日であれ
ば、要求納期を請負納期として回答するように指示し、
受注に引き当てた注番の完成予定日が、要求納期以降の
日であれば、これ以降の日を請負納期として回答するよ
うに指示する。
In this way, when the problem analysis and the adjustment of the production plan are repeated in the above manner and finally the production plan without the problem route can be made, the production plan planner makes the production planning system 1000 and the order processing system 1100. If the expected completion date of the order number assigned to the order is before the requested delivery date, instruct to reply the requested delivery date as the contract delivery date,
If the expected completion date of the order number assigned to the order is a day after the requested delivery date, the customer is instructed to reply the date after that as the contract delivery date.

【0175】また、調整された生産計画は、製造システ
ム1200に渡され、実行される。
The adjusted production plan is passed to the manufacturing system 1200 and executed.

【0176】以上のように、本実施例によれば、生産計
画の内、顧客よりの受注に引き当てた生産を、受注に引
き当てられていない生産計画に有せんすることにより、
顧客よりの要求納期を満足させることができるか否か
を、ショップの作業量、在庫量を考慮して判定すること
のできる生産計画システムを提供することができる。
As described above, according to the present embodiment, among the production plans, the production allocated to the customer's order is assigned to the production plan not allocated to the order.
It is possible to provide a production planning system capable of determining whether or not a delivery date required by a customer can be satisfied in consideration of a work amount and an inventory amount of a shop.

【0177】また、さらに、このような生産計画システ
ムにおいて、顧客よりの受注にひきあてた生産を、どの
ように、受注に引き当てられていない生産計画に優先さ
せれば良いかを計画立案者に示唆することができる。
Further, in such a production planning system, the planner should be asked how to prioritize the production that has received the order from the customer over the production plan that has not been assigned to the order. Can be suggested.

【0178】すなわち、見込生産計画で予定した量より
も、受注量が多かった場合には、柔軟に生産計画を、極
力、受注内容を満足するように変更することを支援する
ことができる。
That is, when the order quantity is larger than the quantity planned in the forecast production plan, it is possible to flexibly support the change of the production plan so as to satisfy the order contents as much as possible.

【0179】[0179]

【発明の効果】本発明によれば、所与の生産スケジュー
ルに基づいた生産計画において、実行不可能な状況が発
生している場合に、その状況を解析することにより、問
題発生状況の把握とその問題を解決するための計画調整
内容の絞り込みを行い、計画調整案を提示することによ
り、計画立案者が実行可能な生産計画を作成するための
支援を行うことが出来る。
According to the present invention, in a production plan based on a given production schedule, when an unexecutable situation occurs, the situation is analyzed to grasp the problem occurrence situation. By narrowing down the contents of the plan adjustment for solving the problem and presenting the plan adjustment plan, the planner can support the production of the executable production plan.

【図面の簡単な説明】[Brief description of the drawings]

【図1】生産計画システムの構成を示すブロック図FIG. 1 is a block diagram showing the configuration of a production planning system.

【図2】生産計画生成処理の処理手順を示すフローチャ
ート
FIG. 2 is a flowchart showing a processing procedure of production plan generation processing.

【図3】リードタイム計算の手法を示す図FIG. 3 is a diagram showing a method of lead time calculation.

【図4】生産能力変更時のリードタイム計算の手法を示
す図
FIG. 4 is a diagram showing a method of lead time calculation when the production capacity is changed.

【図5】生産工程に関する生産計画上の作業負荷状況の
解析手法を示す図
FIG. 5 is a diagram showing a method of analyzing a workload situation in a production plan regarding a production process.

【図6】調達品目に関する生産計画上の引当状況の解析
手法を示す図
FIG. 6 is a diagram showing an analysis method of an allocation situation in a production plan regarding procured items.

【図7】完成日変更の対策立案の手法を示す図FIG. 7 is a diagram showing a method for planning measures for changing the completion date.

【図8】グラフィックユーザインターフェイス中の一表
示画面を示す図
FIG. 8 is a diagram showing one display screen in the graphic user interface.

【図9】グラフィックユーザインターフェイス中の一表
示画面を示す図
FIG. 9 is a diagram showing one display screen in the graphic user interface.

【図10】グラフィックユーザインターフェイス中の一
表示画面を示す図
FIG. 10 is a diagram showing one display screen in a graphic user interface.

【図11】グラフィックユーザインターフェイス中の一
表示画面を示す図
FIG. 11 is a diagram showing one display screen in the graphic user interface.

【図12】グラフィックユーザインターフェイス中の一
表示画面を示す図
FIG. 12 is a diagram showing one display screen in the graphic user interface.

【図13】グラフィックユーザインターフェイス中の一
表示画面を示す図
FIG. 13 is a diagram showing one display screen in the graphic user interface.

【図14】グラフィックユーザインターフェイス中の一
表示画面を示す図
FIG. 14 is a diagram showing one display screen in a graphic user interface.

【図15】グラフィックユーザインターフェイス中の一
表示画面を示す図
FIG. 15 is a diagram showing one display screen in the graphic user interface.

【図16】グラフィックユーザインターフェイス中の一
表示画面を示す図
FIG. 16 is a diagram showing one display screen in the graphic user interface.

【図17】グラフィックユーザインターフェイス中の一
表示画面を示す図
FIG. 17 is a diagram showing one display screen in the graphic user interface.

【図18】グラフィックユーザインターフェイス中の一
表示画面を示す図
FIG. 18 is a diagram showing one display screen in the graphic user interface.

【図19】グラフィックユーザインターフェイス中の一
表示画面を示す図
FIG. 19 is a diagram showing one display screen in the graphic user interface.

【図20】グラフィックユーザインターフェイス中の一
表示画面を示す図
FIG. 20 is a diagram showing one display screen in the graphic user interface.

【図21】完成日変更の対策立案の手法を示すフロー図FIG. 21 is a flowchart showing a method of planning a measure for changing the completion date.

【符号の説明】[Explanation of symbols]

1…リードタイム予測装置 2…MRP制御
装置 3…作業量計算装置 4…生産能力調
整装置 5…完成日調整装置 6…代替ショッ
プ調整装置 7…問題点解析装置 8…MRP展開
装置 9…過負荷量 10…生産計画
実行判定結果 11…データ記憶装置 12…データ入
出力装置 13…生産能力 14…リードタ
イム 15…生産能力調整指示 16…完成日調
整指示 17…代替ショップ調整指示 18…MRP実
行指示 19…問題点解析結果 20…問題点解
析指示 21…MRP実行結果 22…生産能力調整結果とMRP実行指示 23…完成日調整結果とMRP実行指示 24…代替ショップ調整結果とMRP実行指示 25…作業量計算指示 26…作業量 27…作業量解析装置 28…MRP計
算データ 29…リードタイム予測指示 30…MRP展
開指示 31…作業着手順序調整指示 32…作業着手順序調整結果とMRP実行指示 33…作業着手順序調整装置 34…生産量調
整指示 35…受注状況 36…納期回答 37…在庫状況、生産工程状況 38…製造指示 39…生産量調整結果表示とMRP実行指示 40…生産量調整装置 41…「問題解析」コマンドメニュー 42…問題区間表示表 43…着手遅れ
注文一覧表 44…「注文一覧」メニュー 45…「選択」
メニュー 46…注番/日付別問題発生箇所表示表 47…詳細情報一覧表 48…「詳細」
メニュー 49…「品目一覧」メニュー 50…着手遅れ
品目一覧表 51…「調整」メニュー 52…「終了」
ボタン 53…問題経路表示部 54…生産能力
表示部 55…完成日変更モード切り替えメニュー 56…代替ショップモード切り替えメニュー 57…能力調整モード切り替えメニュー 58…MRP実行指示モード切り替えメニュー 59…生産能力変更開始時点設定ダイアル 60…生産能力変更終了時点設定ダイアル 61…生産能力設定ダイアル 62…負荷状況 63…生産能力線 64…生産能力
変更開始点 65…生産能力変更開終了点 66…生産能力
変更対象区間枠 67…問題経路表示部 68…遅れ/余
裕表示部 69…完成日変更モード切り替えメニュー 70…代替ショップモード切り替えメニュー 71…能力調整モード切り替えメニュー 72…MRP実行指示モード切り替えメニュー 73…注番変更ダイアル 74…完成日変
更ダイアル 75…注番表示 76…余裕表示 77…遅れ表示 78…納期表示 79…遅れ/余裕棒グラフ 80…問題経路
表示部 81…代替ショップ表示部 82…完成日変更モード切り替えメニュー 83…代替ショップモード切り替えメニュー 84…能力調整モード切り替えメニュー 85…MRP実行指示モード切り替えメニュー 91…残業設定部 92…残業取消し部 93…対策プロポ−ザルモード切り替えメニュー 94…問題経路表示部 95…対策プロポ−ザルモード表示部 100…対策立案装置 101…生産計
画実行判定装置 102…計画削除指示 103…計画削
除結果とMRP実行指示 104…計画削除装置 105…対策支
援指示 1000…生産計画システム 1100…受注処理システム 1200…製造システム 1300…見込生産計画システム
1 ... Lead time prediction device 2 ... MRP control device 3 ... Work load calculation device 4 ... Production capacity adjustment device 5 ... Completion date adjustment device 6 ... Alternative shop adjustment device 7 ... Problem analysis device 8 ... MRP development device 9 ... Overload Quantity 10 ... Production plan execution determination result 11 ... Data storage device 12 ... Data input / output device 13 ... Production capacity 14 ... Lead time 15 ... Production capacity adjustment instruction 16 ... Completion date adjustment instruction 17 ... Alternative shop adjustment instruction 18 ... MRP execution instruction 19 ... Problem analysis result 20 ... Problem analysis instruction 21 ... MRP execution result 22 ... Production capacity adjustment result and MRP execution instruction 23 ... Completion date adjustment result and MRP execution instruction 24 ... Alternative shop adjustment result and MRP execution instruction 25 ... Work Quantity calculation instruction 26 ... Work quantity 27 ... Work quantity analysis device 28 ... MRP calculation data 29 ... Lead time prediction instruction 30 ... MRP Open instruction 31 ... Work start order adjustment instruction 32 ... Work start order adjustment result and MRP execution instruction 33 ... Work start order adjustment device 34 ... Production amount adjustment instruction 35 ... Order status 36 ... Delivery reply 37 ... Stock status, production process status 38 ... Manufacturing instruction 39 ... Production amount adjustment result display and MRP execution instruction 40 ... Production amount adjusting device 41 ... "Problem analysis" command menu 42 ... Problem section display table 43 ... Launch start order list 44 ... "Order list" menu 45 ... "Choice"
Menu 46 ... Problem point display table by order number / date 47 ... Detailed information list 48 ... "Details"
Menu 49… “Item list” menu 50… Delayed item list 51… “Adjustment” menu 52… “End”
Button 53 ... Problem route display 54 ... Production capacity display 55 ... Completion date change mode switching menu 56 ... Alternative shop mode switching menu 57 ... Capacity adjustment mode switching menu 58 ... MRP execution instruction mode switching menu 59 ... Production capacity change start time Setting dial 60 ... Production capacity change end point Setting dial 61 ... Production capacity setting dial 62 ... Load situation 63 ... Production capacity line 64 ... Production capacity change start point 65 ... Production capacity change end point 66 ... Production capacity change target section frame 67 ... Problem route display section 68 ... Delay / margin display section 69 ... Completion date change mode switching menu 70 ... Alternative shop mode switching menu 71 ... Capability adjustment mode switching menu 72 ... MRP execution instruction mode switching menu 73 ... Note number change dial 74 ... Completion date change die Al 75 ... Order number display 76 ... Margin display 77 ... Delay display 78 ... Delivery date display 79 ... Delay / margin bar graph 80 ... Problem route display 81 ... Alternative shop display 82 ... Completion date change mode switching menu 83 ... Alternative shop mode switching Menu 84 ... Ability adjustment mode switching menu 85 ... MRP execution instruction mode switching menu 91 ... Overtime setting section 92 ... Overtime cancellation section 93 ... Countermeasure proposal mode switching menu 94 ... Problem route display section 95 ... Countermeasure proposal mode display section 100 ... Countermeasure planning device 101 ... Production plan execution determination device 102 ... Plan deletion instruction 103 ... Plan deletion result and MRP execution instruction 104 ... Plan deletion device 105 ... Countermeasure support instruction 1000 ... Production planning system 1100 ... Order processing system 1200 ... Manufacturing system 1300 ... Expected Production planning system

Claims (10)

【特許請求の範囲】[Claims] 【請求項1】ユーザの要求する完成品目の完成日、数量
等を示した完成スケジュールに対して、前記完成品目を
構成する品目の製造工程を少なくとも1つのショップと
して取り扱い、かつ前記ショップにおける前記品目の製
造可能な期間を算出して前記完成品目を完成するまでの
生産スケジュールを決定する生産計画システムにおい
て、 前記ショップが備える作業能力量と、前記作業能力量と
前記ショップに与えられる作業負荷量とから導かれる前
記ショップの余剰能力量とを管理する手段と、 前記完成スケジュールに規定される完成日を満足する生
産スケジュールを作成できない場合、前記ショップの余
剰能力量から前記品目に必要な作業量を確保できる期日
を判断する手段と、 前記各ショップについて判断された期日に基づいて前記
完成品目の生産可能日を算出する手段とを備えることを
特徴とする生産計画システム。
1. A manufacturing process of items constituting the completed item is treated as at least one shop for a completion schedule indicating a completion date, quantity, etc. of the completed item requested by a user, and the item in the shop is treated. In the production planning system for calculating the manufacturable period of the above and determining the production schedule until the completion of the finished item, the work capacity provided in the shop, the work capacity and the work load given to the shop, Means for managing the surplus capacity of the shop derived from, and when it is not possible to create a production schedule that satisfies the completion date specified in the completion schedule, from the surplus capacity of the shop, the work required for the item Means for determining the due date that can be secured, and the completion date based on the determined date for each shop. Production planning system, characterized in that it comprises means for calculating an item of producible day.
【請求項2】ユーザの要求する完成品目の完成日、数量
等を示した完成スケジュールに対して、前記完成品目を
構成する品目の製造工程を少なくとも1つのショップと
して取り扱い、かつ前記ショップにおける前記品目の製
造可能な期間を算出して前記完成品目を完成するまでの
生産スケジュールを決定する生産計画システムにおい
て、 完成スケジュールによる各完成品目の完成日に遅延が発
生しないように、製造品目の完成日を基準に各品目の作
業着手日を設定する生産計画作成手段と、 取り扱う各品目の現在庫量及び将来の入庫予定量を管理
する在庫量管理手段と、 前記生産計画作成手段により作成された生産計画を対象
として、品目毎には日別所要量と在庫量及び入庫予定量
の関係を、ショップ毎には日別作業量と能力との関係を
解析し、当該品目の不足時期/量、余剰時期/量や、当
該ショップの過負荷時期/量、余裕時期/量を算出する
生産計画状況解析手段と、 生産計画に問題が存在する場合に、選択した完成品目ロ
ットに対して、生産計画状況解析手段により得られる特
徴量を基に、生産可能日を立案する対策立案手段と、 対策立案手段により得られた結果を表示することにより
ユーザがその対策を実施するかどうかの意思決定を行う
ことが可能な対策案提示手段とを有することを特徴とす
る生産計画システム。
2. The manufacturing process of the items constituting the completed item is treated as at least one shop with respect to the completion schedule indicating the completion date, quantity, etc. of the completed item requested by the user, and the item in the shop is handled. In the production planning system that calculates the manufacturable period of the above and determines the production schedule until the completion of the finished item, the completion date of the manufactured item is set so that there is no delay in the completion date of each finished item due to the completion schedule. Production plan creation means for setting the work start date of each item as a standard, inventory quantity management means for managing the current stock quantity and future planned stock quantity of each item handled, and the production plan created by the production plan creation means For each item, the relationship between the daily requirement amount, the inventory amount and the planned storage amount is analyzed, and for each shop, the relationship between the daily work amount and the capacity is analyzed. However, if there is a problem in the production plan, the production plan status analysis means that calculates the shortage / amount, the surplus time / amount of the item, the overload time / amount, and the surplus time / amount of the shop. Based on the feature quantity obtained by the production plan status analysis means for the completed finished product lot, the user can take countermeasures by displaying the measure production means for formulating the producible date and the result obtained by the measure production means. A production planning system comprising: a measure proposal presenting means capable of making a decision as to whether or not to implement.
【請求項3】請求項2記載の生産計画システムであっ
て、 前記生産計画状況解析手段は、外部より調達する品目に
関しては、完成スケジュールに基づいて生成された生産
計画における日別の所要量と、在庫量及び入庫予定量を
管理する手段により与えられる日別の使用可能量とを、
現在から将来に向けて順次差引き計算を行い、特定期間
内の総使用可能量よりも総所要量の方が多く不足が発生
する品目に対しては、不足が発生する期間とその量を、
現在手配を行った場合に将来納入される日までの期間内
で余剰が発生する品目に対しては、余剰が発生する期間
とその量を算出することを特徴とする生産計画システ
ム。
3. The production planning system according to claim 2, wherein the production planning situation analysis means, for items procured from the outside, includes the daily requirement amount in the production plan generated based on the completion schedule. , The daily usable amount given by the means for managing the inventory amount and the planned storage amount,
For items for which a shortage occurs in which the total required amount is larger than the total available amount within a specific period, subtraction calculation is performed sequentially from the present to the future.
A production planning system characterized by calculating the period and amount of surplus for items that will be surplus within the period up to the date of future delivery if the items are currently ordered.
【請求項4】請求項2記載の生産計画システムであっ
て、 生産計画状況解析手段は、各製造ショップに関して、完
成スケジュールに基づいて生成された生産計画における
在庫引当後の日別作業負荷量と、日別能力とを時系列に
差引き計算することにより、当該ショップの能力に対す
る作業負荷量が過剰になる期間とその作業負荷量を、ま
た当該ショップの能力に対して作業負荷量が少なく能力
的な余裕が存在する期間とその能力量を明確にすること
を特徴とする生産計画システム。
4. The production planning system according to claim 2, wherein the production planning situation analyzing means relates to each manufacturing shop and a daily workload amount after inventory allocation in the production planning generated based on the completion schedule. , The daily capacity is calculated in time series to calculate the period and the workload that the workload is excessive with respect to the capacity of the shop, and the capacity that the workload is less than the capacity of the shop. Production planning system characterized by clarifying the period and the capacity for which there is a margin.
【請求項5】請求項2記載の生産計画システムであっ
て、 対策立案手段は、完成スケジュールに既定された完成日
を変更する完成品目ロット、あるいは追加で生産しよう
とする完成品目ロットに対して、当該完成品目ロットを
構成する品目の引当状況、あるいはその製造ショップに
おける作業負荷状況に関して、請求項2及び3記載の生
産計画状況解析手段により得られる各種特徴量に基づい
て、各状況が計画変更前に比較し問題量が増加すること
なく、対象ロットの生産が可能な最早の日を立案するこ
とを特徴とする生産計画システム。
5. The production planning system according to claim 2, wherein the measure planning means is for a finished item lot of which the completion date specified in the completion schedule is changed or for a finished item lot of which additional production is to be performed. With respect to the allocation status of the items constituting the finished product lot or the workload status of the manufacturing shop, each status is a plan change based on various characteristic amounts obtained by the production plan status analysis means according to claims 2 and 3. A production planning system characterized by planning the earliest possible day for the production of the target lot without increasing the problem amount compared to the previous case.
【請求項6】請求項2記載の生産計画システムであっ
て、 対策案提示手段は、請求項4記載の対策立案手段により
得られた結果をその他関連情報と合わせて表示すること
を特徴とする生産計画システム。
6. The production planning system according to claim 2, wherein the measure proposal presenting means displays the result obtained by the measure planning means according to claim 4 together with other related information. Production planning system.
【請求項7】ユーザの要求する完成品目の完成日、数量
等を示した完成スケジュールに対して、前記完成品目を
構成する品目の製造工程を少なくとも1つのショップと
して取り扱い、かつ前記ショップにおける前記品目の製
造可能な期間を算出して前記完成品目を完成するまでの
生産スケジュールを決定する生産計画方法において、 前記ショップが備える作業能力と前記ショップに与えら
れる作業負荷量とから前記ショップの余剰能力を累積値
として管理しておき、 前記完成スケジュールに規定される完成日を満足する生
産スケジュールを作成できない場合、前記ショップの余
剰能力の累計値から前記品目に必要な作業量を確保でき
る期日を判断することで前記完成品目の生産可能日を算
出することを特徴とする生産計画方法。
7. The manufacturing process of the items constituting the completed item is treated as at least one shop with respect to the completion schedule indicating the completion date, quantity, etc. of the completed item requested by the user, and the item in the shop is handled. In the production planning method for calculating the manufacturable period of the above and determining the production schedule until the completion of the finished item, the surplus capacity of the shop is calculated from the work capacity provided in the shop and the workload amount given to the shop. If it is not possible to create a production schedule that satisfies the completion date specified in the completion schedule by managing it as a cumulative value, then determine the date when the necessary work amount for the item can be secured from the cumulative value of the surplus capacity of the shop. The production planning method is characterized by calculating the production available date of the completed item.
【請求項8】請求項7記載の生産計画方法であって、 前記品目は外部より調達する外部品目を含み、 前記外部品目の在庫量及び入庫予定量を管理することで
日別の使用可能量を算出し、 完成スケジュールに基づいて生成された生産スケジュー
ルにおける日別の所要量と、前記日別の使用可能量とを
現在から将来に向けて順次差引き計算を行い、 前記計算結果から、総使用可能量よりも総所要量の方が
多い不足品目に対しては、不足が発生する期間とその量
を算出し、 現在手配を行った場合に将来納入される日までの期間内
で総使用可能量よりも総所要量の方が少ない余剰品目に
対しては、余剰が発生する期間とその量を算出し、 完成スケジュールに既定された完成日を変更する完成品
目、あるいは追加で生産しようとする完成品目がある場
合、前記算出結果に基づいて、前記完成品目を構成する
品目の引当状況、あるいはその製造ショップにおける作
業負荷状況の各状況が前記変更、追加前に比較して問題
量が増加することなく前記完成品目の生産が可能な最早
の日を立案することを特徴とする生産計画方法。
8. The production planning method according to claim 7, wherein the item includes an external item to be procured from outside, and the daily usable amount is managed by managing the inventory amount and the planned storage amount of the external item. Then, the daily requirement amount in the production schedule generated based on the completion schedule and the daily available amount are sequentially subtracted from the present to the future, and from the calculation result, the total amount is calculated. For shortage items that have more total requirements than the available amount, calculate the shortage period and the amount, and if you make the current arrangement, total use within the period up to the date of future delivery. For surplus items whose total required amount is less than possible, calculate the period and amount of surplus, and try to change the completion date specified in the completion schedule or to produce additional items. There is a finished item to In this case, based on the calculation result, the allocation status of the items constituting the completed item or the respective workload statuses in the manufacturing shop are changed and the completion is performed without increasing the problem amount compared to before the addition. A production planning method, characterized in that the earliest possible date of production of an item is planned.
【請求項9】請求項7記載の生産計画方法であって、 各製造ショップに関して、完成スケジュールに基づいて
生成された生産スケジュールにおける在庫引当後の日別
作業負荷量と、その日別能力とを時系列に差引き計算
し、 前記ショップの能力に対する作業負荷量が過剰になる期
間とその作業負荷量と、また当該ショップの能力に対し
て作業負荷量が少なく能力的な余裕が存在する期間とそ
の能力量とを算出し、 完成スケジュールに既定された完成日を変更する完成品
目、あるいは追加で生産しようとする完成品目がある場
合、前記算出結果に基づいて、前記完成品目を構成する
品目の引当状況、あるいはその製造ショップにおける作
業負荷状況の各状況が前記変更、追加前に比較して問題
量が増加することなく前記完成品目の生産が可能な最早
の日を立案することを特徴とする生産計画方法。
9. The production planning method according to claim 7, wherein, for each manufacturing shop, the daily workload amount after inventory allocation in the production schedule generated based on the completion schedule and the daily capacity thereof are set. Calculated by deduction in series, the period when the workload for the capacity of the shop becomes excessive and its workload, and the period when the workload is small and the capacity of the shop exists and its margin If there is a completed item whose capacity is calculated and the completion date specified in the completion schedule is changed, or there is a completed item to be additionally produced, the allocation of the items constituting the completed item is calculated based on the calculation result. It is possible to produce the finished item without the situation or each situation of the workload in the manufacturing shop increasing the problem amount compared to before the change or addition. Production planning method which is characterized in that to develop a longer day.
【請求項10】請求項7、8及び9記載の立案結果をそ
の他関連情報と合わせて表示することを特徴とする生産
計画方法。
10. A production planning method, wherein the planning result according to claim 7, 8 and 9 is displayed together with other related information.
JP28130395A 1995-10-30 1995-10-30 Production planning method and system using it Pending JPH09128440A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP28130395A JPH09128440A (en) 1995-10-30 1995-10-30 Production planning method and system using it

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP28130395A JPH09128440A (en) 1995-10-30 1995-10-30 Production planning method and system using it

Publications (1)

Publication Number Publication Date
JPH09128440A true JPH09128440A (en) 1997-05-16

Family

ID=17637203

Family Applications (1)

Application Number Title Priority Date Filing Date
JP28130395A Pending JPH09128440A (en) 1995-10-30 1995-10-30 Production planning method and system using it

Country Status (1)

Country Link
JP (1) JPH09128440A (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH11102399A (en) * 1997-07-28 1999-04-13 Canon Inc System and method for component ordering, component management system, device and method for order reception and ordering management, and recording medium
US6795742B1 (en) 2003-04-03 2004-09-21 Renesas Technology Corp. Production management method in a plurality of production lines
JP2014016805A (en) * 2012-07-09 2014-01-30 Hitachi Ltd Production plan adjustment support device, production plan adjustment support method, and production plan adjustment support program
CN112101711A (en) * 2020-06-17 2020-12-18 浙江中控技术股份有限公司 Flow control method for preventing manual feeding from being mistaken in intermittent production
CN113895935A (en) * 2021-09-14 2022-01-07 北京机科国创轻量化科学研究院有限公司 Control method and control system for full-automatic intelligent feeding equipment for chemical fiber POY (polyester pre-oriented yarn) spindles

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH11102399A (en) * 1997-07-28 1999-04-13 Canon Inc System and method for component ordering, component management system, device and method for order reception and ordering management, and recording medium
US6795742B1 (en) 2003-04-03 2004-09-21 Renesas Technology Corp. Production management method in a plurality of production lines
JP2014016805A (en) * 2012-07-09 2014-01-30 Hitachi Ltd Production plan adjustment support device, production plan adjustment support method, and production plan adjustment support program
CN112101711A (en) * 2020-06-17 2020-12-18 浙江中控技术股份有限公司 Flow control method for preventing manual feeding from being mistaken in intermittent production
CN113895935A (en) * 2021-09-14 2022-01-07 北京机科国创轻量化科学研究院有限公司 Control method and control system for full-automatic intelligent feeding equipment for chemical fiber POY (polyester pre-oriented yarn) spindles
CN113895935B (en) * 2021-09-14 2024-01-26 北京机科国创轻量化科学研究院有限公司 Full-automatic intelligent chemical fiber POY wire ingot feeding equipment control method and control system

Similar Documents

Publication Publication Date Title
JP3447286B2 (en) Production plan creation system and production plan creation method
US5826236A (en) Method for allocating resources and processes for design and production plan scheduling
US8989879B2 (en) System and method for a demand driven lean production control system
US8965539B2 (en) System and method for a demand driven lean production control system
US7369910B2 (en) Method for the optimizing of a production process
JPS63288634A (en) Device and method of assembling part
JP3610581B2 (en) Production plan adjustment device
JP2004310290A (en) Production managing method for plurality of production lines
JP3240237B2 (en) Production planning system
JPH08212261A (en) Starting plan forming device
Doctor et al. Scheduling for machining and assembly in a job-shop environment
JPH11120248A (en) System and method for scheduling production
JPS59214964A (en) Conversational scheduling system
JPH09128440A (en) Production planning method and system using it
Li Proposing an architectural framework of a hybrid knowledge‐based system for production rescheduling
JP3195385B2 (en) Production planning system and production planning method
JPH06203037A (en) Device and method for devising production planning
Pritsker et al. Production scheduling using FACTOR
JPH04347769A (en) Process management device
JP2000010606A (en) System for generating production plan
JP2721561B2 (en) Production progress prediction method and production progress prediction simulator
Watson et al. Generating component release plans with backward simulation
JPH0710486B2 (en) Multi-product production schedule creation device
JPH04184602A (en) System and method for preparation of production schedule
JP2778457B2 (en) Production planning equipment