JPH0874201A - Improvement of railroad ground - Google Patents

Improvement of railroad ground

Info

Publication number
JPH0874201A
JPH0874201A JP21453994A JP21453994A JPH0874201A JP H0874201 A JPH0874201 A JP H0874201A JP 21453994 A JP21453994 A JP 21453994A JP 21453994 A JP21453994 A JP 21453994A JP H0874201 A JPH0874201 A JP H0874201A
Authority
JP
Japan
Prior art keywords
ballast
flexible bag
bag body
flexible
ground
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP21453994A
Other languages
Japanese (ja)
Other versions
JP3473998B2 (en
Inventor
Hisashi Tarumi
尚志 垂水
Masaru Tateyama
勝 舘山
Makoto Sunaga
誠 須長
Hiroshi Iwasa
弘 岩佐
Yoshitomo Kinoshita
吉友 木下
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Railway Technical Research Institute
Raito Kogyo Co Ltd
Original Assignee
Railway Technical Research Institute
Raito Kogyo Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Railway Technical Research Institute, Raito Kogyo Co Ltd filed Critical Railway Technical Research Institute
Priority to JP21453994A priority Critical patent/JP3473998B2/en
Publication of JPH0874201A publication Critical patent/JPH0874201A/en
Application granted granted Critical
Publication of JP3473998B2 publication Critical patent/JP3473998B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Abstract

PURPOSE: To easily correct disturbance in the case when a railroad changes in ground. CONSTITUTION: A flexible bag body 10 is provided along the longitudinal direction under a sleeper 3 on a roadway ground provided with the sleeper 3 on track bed ballast 2 of the roadway ground. A filler containing ballast 11 is filled in the inside of it, and the track bed ballast 2 is laid between these flexible bag bodies 10 and under them. When sinking of a rail 4 is caused or there is a danger o sinking, an amount of sinking is compensated by supplementally filling the filler in the flexible bag bodies 10.

Description

【発明の詳細な説明】Detailed Description of the Invention

【0001】[0001]

【産業上の利用分野】本発明は、線路地盤の改良工法に
関する。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to an improved construction method for track ground.

【0002】[0002]

【従来の技術】線路地盤は、一般的には、路盤上に道床
バラストを敷設し、その上部に枕木を介してレールを設
けた構造を有する。
2. Description of the Related Art A track ground generally has a structure in which a ballast ballast is laid on the roadbed and rails are provided above the ballast via sleepers.

【0003】しかし、この線路構造では、列車による繰
り返し荷重を受ける宿命を有する。
However, this line structure has the fate of being subjected to repeated loads by the train.

【0004】したがって、初期の段階では、敷設した道
床バラストの間隙が列車振動により密になり安定化する
過程で、軌道の沈下を生じ、その後、繰り返し荷重およ
び振動により、道床バラストが側方に流れ出すことによ
っても軌道の沈下がある。したがって、定期的に新規バ
ラストを補充して、突き固めの作業が必要となり、この
保線作業に多大な手間を要する。
Therefore, in the initial stage, the track sunk in the course of the process in which the gaps between the laid ballast ballasts are made dense and stabilized by train vibration, and then the track ballasts flow laterally due to repeated loads and vibrations. There are also orbital subsidences. Therefore, it is necessary to periodically replenish the ballast and tamper with it, and this track maintenance work requires a great deal of labor.

【0005】この軌道の沈下問題に対して、近年多くの
改良が加えられてきた。すなわち、その第1の方法は、
開業から多年を経過し沈下が安定している線路地盤にお
いて、枕木を大版のプレストレスコンクリート枕木に代
え、かつ道床バラストの上部内にアスファルト類を注入
し、道床バラスト部分の表面を雨水の遮断のためにアス
ファルト舗装するものである。
Many improvements have been made in recent years to the settlement problem of the orbit. That is, the first method is
In the track ground where the settlement has been stable for many years since the opening of the business, the sleepers were replaced with large-scale prestressed concrete sleepers, and asphalt was injected into the upper part of the ballast ballast to block rainwater from the surface of the ballast ballast. For asphalt pavement.

【0006】第2の方法は、既存の枕木および道床バラ
ストを利用し、道床下部にモルタル類を充填するいわゆ
る填充道床構造とするものである。第3の方法は、いわ
ゆるスラブ軌道構造とするものである。
The second method is a so-called filling roadbed structure in which the existing sleepers and ballast ballast are used to fill the lower part of the roadbed with mortar. The third method is a so-called slab track structure.

【0007】[0007]

【発明が解決しようとする課題】前記の第1〜第3の方
法は、経済性および施工性と効果または信頼性との両立
が困難で、それぞれ一長一短を有する。
The above-mentioned first to third methods are difficult to combine economical efficiency and workability with effects or reliability, and each has advantages and disadvantages.

【0008】したがって、本発明の課題は、線路地盤の
変状が生じた場合において、簡易にその修正を行うこと
ができるようにすることにある。
[0008] Therefore, an object of the present invention is to make it possible to easily correct the deformation of the track ground when it occurs.

【0009】[0009]

【課題を解決するための手段】上記課題は、線路地盤の
道床バラストに枕木を設けた線路地盤において、枕木の
下部にその長手方向に沿って可撓性袋体を設け、その内
部にバラストを含む充填材を充填し、この可撓性袋体の
間および下方に道床バラストを敷設し、レールの沈下が
生じたときまたは沈下の虞れがあるとき、可撓性袋体内
に充填材を補充充填して、沈下分を補償することで解決
できる。
[Means for Solving the Problems] The above problem is that, in a track ground in which a sleeper is provided on a ballast of a track ground, a flexible bag is provided at the lower part of the sleeper along the longitudinal direction thereof, and the ballast is provided inside the flexible bag. Filling the filling material containing, and laying ballast ballast between and below this flexible bag body, when the sinking of the rail occurs or there is a risk of sinking, the filling material is replenished in the flexible bag body. It can be solved by filling and compensating for the subsidence.

【0010】また、線路地盤の道床バラストに枕木を設
けた線路地盤において、枕木の下部にその長手方向に沿
って可撓性袋体を設け、その内部にバラストを含む充填
材を充填し、この可撓性袋体の間および下方に道床バラ
ストを敷設し、前記可撓性袋体とは別に、少なくともそ
の上方の枕木との間または可撓性袋体の下方に可撓性袋
体をさらに設け、レールの沈下が生じたときまたは沈下
の虞れがあるとき、可撓性袋体内に充填材を補充充填し
て、沈下分を補償することでも解決できる。
Further, in the track ground in which sleepers are provided on the ballast of the track ground, a flexible bag is provided in the lower part of the sleepers along the longitudinal direction thereof, and a filling material containing ballast is filled inside the bag. A ballast ballast is laid between and below the flexible bags, and apart from the flexible bags, the flexible bags are further provided at least between the sleepers above or below the flexible bags. When the rail subsidence occurs or there is a risk of subsidence, it is also possible to supplement the filling material in the flexible bag to compensate for the subsidence.

【0011】[0011]

【作用】本発明では、レールの沈下が生じたときまたは
沈下の虞れがあるとき、可撓性袋体内に充填材を補充充
填して、沈下分を補償するので、一旦設置した充填材を
充填した袋体全体を取り替える必要がなく、当該袋体内
にあるいは少なくともその袋体の上下一方に設けた副袋
体内に充填材を充填することで、レールの沈下を防止
し、その補償を図ることができる。したがって、線路地
盤の改良を迅速かつ確実に行うことができ、経済的なも
のとなる。
In the present invention, when subsidence of the rail occurs or there is a risk of subsidence, the filling material is replenished and filled in the flexible bag to compensate for the subsidence. It is not necessary to replace the entire filled bag, but by filling the bag with the filling material in the bag or at least in the sub-bags provided on the upper and lower sides of the bag, it is possible to prevent the rail from sinking and to compensate for it. You can Therefore, the railway ground can be improved quickly and reliably, which is economical.

【0012】[0012]

【実施例】以下本発明を図面を参照しながら実施例によ
りさらに詳説する。 (第1実施例)図1および図2は第1実施例を示したも
ので、路盤1上に道床バラスト2が敷き詰められ、その
上部に枕木3が設けられており、これにレール4が敷設
されている。本発明の枕木3は、木材のほか、コンクリ
ート枕木も当然に含むものである。
The present invention will be described in more detail by way of examples with reference to the drawings. (First Embodiment) FIGS. 1 and 2 show a first embodiment, in which a roadbed ballast 2 is laid on a roadbed 1 and sleepers 3 are provided on an upper portion thereof, and rails 4 are laid on it. Has been done. The sleepers 3 of the present invention naturally include concrete sleepers in addition to wood.

【0013】本発明では、枕木3の下部に可撓性袋体1
0(以下、単に袋体という。)が設けられる。この袋体
10としては、ゴム製、布製、それらの複合材など適宜
のものが用いられる。また、充填材がバラストなどの粒
状体である場合には、その粒径よりも小さな目合いのネ
ットでも良い。この場合、均一に半径方向に伸長し、逆
に長手方向に伸びないように、袋体の端部を強化したり
することができる。直径は一様であることに限定され
ず、長手方向の途中がやや小径となっているものであっ
てもよい。
In the present invention, the flexible bag 1 is provided under the sleeper 3.
0 (hereinafter, simply referred to as a bag) is provided. As the bag body 10, an appropriate material such as rubber, cloth, or a composite material thereof is used. Further, when the filler is a granular material such as ballast, a net having a mesh smaller than the particle diameter may be used. In this case, the end portion of the bag body can be reinforced so that it uniformly extends in the radial direction and does not extend in the longitudinal direction. The diameter is not limited to be uniform, and the diameter may be slightly smaller in the longitudinal direction.

【0014】いずれにしても、袋体10内にはバラスト
11が充填される。当初に充填するバラスト11として
は、良質のものを用いることが、クッション性を高める
上で好ましい。
In any case, the bag body 10 is filled with the ballast 11. As the ballast 11 to be initially filled, it is preferable to use a high quality one in order to improve the cushioning property.

【0015】その施工に際しては、袋体10の設置部分
の既存バラストを除去するとともに、レール4を公知の
支持ブロックで支持しておき、袋体10を線路を横断す
る方向に挿入することができる。その後に、予め形成し
ておいた袋体10端部の充填口10aを開けて、新規バ
ラスト11を内部に充填することができる。また、余り
好ましい方法ではないが、予めバラスト11を充填した
袋体10を枕木3の下部に挿入設置することもできる。
At the time of the construction, the existing ballast at the installation portion of the bag body 10 is removed, the rail 4 is supported by a known support block, and the bag body 10 can be inserted in the direction traversing the line. . After that, the filling port 10a formed at the end portion of the bag body 10 formed in advance can be opened and the new ballast 11 can be filled inside. Although not a very preferable method, the bag body 10 in which the ballast 11 is previously filled can be inserted and installed in the lower portion of the sleeper 3.

【0016】かかるバラスト11を充填した袋体10
は、列車荷重に対して、袋体10全体で支持するので、
長期に渡って、レール4の沈下を防止できる。また、列
車通過による振動に対しては、内部のバラスト11が良
好なクッション効果を示す。また、現在入手が困難にな
りつつある良質のバラスト11を使用したとしても、袋
体10の外部に流出することがない。
Bag body 10 filled with such ballast 11
Supports the entire bag body 10 against the train load,
It is possible to prevent the rail 4 from sinking over a long period of time. Further, the internal ballast 11 exhibits a good cushioning effect against vibrations due to train passage. Further, even if a good quality ballast 11 which is becoming difficult to obtain at present is used, it does not flow out of the bag body 10.

【0017】しかるに、この改良体の使用が長期にわた
るときは、周辺の道床バラスト2の変状を生じたり、改
良体自体も若干の形状変化を示し、レールの沈下または
その虞れがある場合がある。そこで、この場合には、充
填口10aから補充用バラストを充填することで、その
沈下分を補償することができる。補充用バラストとして
は、良質であることを要しない。
However, when the improved body is used for a long period of time, the surrounding ballast ballast 2 may be deformed or the improved body itself may show a slight change in shape, which may lead to the sinking of the rail or the risk thereof. is there. Therefore, in this case, the subsidence can be compensated by filling the supplementary ballast from the filling port 10a. The ballast for replenishment does not need to be of good quality.

【0018】また、当初からあるいは沈下防止用の補充
バラストとともに、砂または適宜の骨材類も充填するこ
とができる。さらに、袋体10の端部からの補充用バラ
ストの充填が困難であるときは、図3に示すように、長
手方向の適宜の位置に複数充填口10A,10B,10
Cを形成しておき、これらを介して充填することができ
る。
Also, from the beginning or together with supplementary ballast for preventing subsidence, sand or appropriate aggregates can be filled. Further, when it is difficult to fill the refill ballast from the end of the bag body 10, as shown in FIG. 3, the plural filling ports 10A, 10B, 10 are provided at appropriate positions in the longitudinal direction.
C can be formed in advance and filled through them.

【0019】(第2実施例)一方、第1実施例において
は、バラストを補充することで、沈下を防止しようとす
るものである。これに対して、図4に示すように、予め
または沈下防止の企図時において、注入管20を袋体1
0内に挿入し、この注入管20を通して、セメントミル
クなどの固化材料21を内部に注入することにより、沈
下分を補償することができる。
(Second Embodiment) On the other hand, in the first embodiment, the sinking is prevented by supplementing the ballast. On the other hand, as shown in FIG. 4, the injection pipe 20 is attached to the bag body 1 in advance or when the sinking prevention is attempted.
It is possible to compensate for the subsidence by inserting the solidified material 21 such as cement milk through the injection pipe 20 and inserting the solidified material 21 therein.

【0020】この場合、固化材料21を袋体10内全体
に行き渡らせることが難しいので、長手方向に複数の注
入口を有する注入管を用いることができる。たとえば、
図5に示すように、長手方向に複数の注入口22a,2
2a…を有する注入スリーブ管22を袋体10内に挿入
するとともに、各注入口22a,22a…を包囲して可
撓性スリーブ23を設けるとともに、前記注入スリーブ
管22内に、前後の可撓性パッカー24A,24Aを有
する注入内管24を挿入し、外部からの液圧でパッカー
24A,24Aを注入スリーブ管22内壁面に膨出、密
着させた状態で、この注入内管24内に圧送した固化材
料21を、注入内管24におけるパッカー24A,24
Aの間に形成した注入口(図示せず)から吐出させた
後、注入口22aからスリーブ23を拡径しながら周辺
の袋体10内に注入することができる。注入が終了する
と、スリーブ23がその復原力により注入口22aを閉
塞させるので、注入材料が注入スリーブ管22内に逆戻
りすることはない。他の注入口22aから注入する場合
には、注入内管24を長手方向に移動させて、注入を行
うことができる。
In this case, since it is difficult to spread the solidified material 21 in the entire bag body 10, an injection pipe having a plurality of injection ports in the longitudinal direction can be used. For example,
As shown in FIG. 5, a plurality of injection ports 22a, 2 are provided in the longitudinal direction.
The injection sleeve tube 22 having 2a ... Is inserted into the bag body 10 and the flexible sleeve 23 is provided so as to surround each injection port 22a, 22a. The inner injection pipe 24 having the property packers 24A, 24A is inserted, and the packers 24A, 24A are swelled and closely adhered to the inner wall surface of the injection sleeve pipe 22 by hydraulic pressure from the outside, and are fed into the inner injection pipe 24 under pressure. The solidified material 21 thus obtained is packed into the packers 24A, 24A in the injection inner tube 24.
After being discharged from an injection port (not shown) formed between A, it is possible to inject it into the bag body 10 around the sleeve 23 while expanding the diameter of the sleeve 23 from the injection port 22a. When the injection is completed, the sleeve 23 closes the injection port 22a by its restoring force, so that the injection material does not return to the inside of the injection sleeve tube 22. When injecting from the other injection port 22a, the injection can be performed by moving the injection inner tube 24 in the longitudinal direction.

【0021】この図5の例においては、注入した固化材
料21が硬化し、ある長期間放置しておいた場合、列車
荷重により、その固化材料21にクラックを生じるの
で、再度沈下の虞れがあるとき、袋体10内に埋設放置
しておいた注入管22を介して改めて固化材料21を注
入することができる。この場合、スリーブ23が各注入
口22a,22a…の閉塞を防止するので、再注入が可
能である。
In the example of FIG. 5, when the injected solidified material 21 is hardened and left for a certain period of time, the solidified material 21 is cracked by the load of the train, so that the solidified material 21 may sink again. At some time, the solidified material 21 can be injected again through the injection pipe 22 that has been left buried in the bag body 10. In this case, since the sleeve 23 prevents the injection ports 22a, 22a ... from being blocked, reinjection is possible.

【0022】(第3実施例)上記各例は、一つの枕木3
に対して一つの袋体10を設けた例であるが、経時の伴
う沈下防止を図る時期において、その袋体10を改良す
るのではなく、隣接する袋体を用いて改良することもで
きる。
(Third Embodiment) In each of the above examples, one sleeper 3 is used.
However, it is an example in which one bag body 10 is provided, but it is also possible to improve the bag body 10 by using an adjacent bag body instead of improving the bag body 10 at the time of preventing the sinking over time.

【0023】たとえば、図6に示すように、バラスト1
1を充填した袋体10の下部に可撓性袋体30を、予め
または沈下防止時に挿入して設置し、当初平坦である袋
体30内に補充用バラスト、好ましくは固化材料21を
充填することができる。なお、図6に示されているよう
に、袋体10、30の両端に擁壁31を設けて、高さ方
向のみの膨出を図ることができる。
For example, as shown in FIG. 6, ballast 1
1. A flexible bag body 30 is inserted and installed in the lower portion of the bag body 10 filled with 1 in advance or at the time of prevention of sinking, and a refilling ballast, preferably a solidified material 21, is filled in the bag body 30 which is initially flat. be able to. As shown in FIG. 6, retaining walls 31 may be provided at both ends of the bags 10 and 30 to allow bulging only in the height direction.

【0024】他方、図7に示すように、袋体30は袋体
10と枕木3との間であってもよく、かつ袋体30は補
修回数ごと順に使用するように複数であってもよい。ま
た、図8に示すように、袋体40Aの側部および下部を
包むようにさらに袋体40Bを形成した疑似二重袋体4
0であってもよい。
On the other hand, as shown in FIG. 7, the bag body 30 may be located between the bag body 10 and the sleeper 3, and the bag body 30 may be plural so as to be used in sequence for each number of repairs. . Further, as shown in FIG. 8, a pseudo double bag body 4 in which a bag body 40B is further formed so as to wrap the side portion and the lower portion of the bag body 40A.
It may be 0.

【0025】(その他)前記の固化材料としては、セメ
ントミルク、セメントモルタル、アスファルト乳材など
を用いることができる。充填材として、非固化性材料で
もよく、この場合には、前述に若干ふれたように、砂
類、スラグ類、骨材類、プラスチックビーズなど適宜の
ものを用いることができる。
(Others) As the solidifying material, cement milk, cement mortar, asphalt dairy material and the like can be used. As the filler, a non-solidifying material may be used, and in this case, appropriate materials such as sands, slags, aggregates, and plastic beads can be used as mentioned above.

【0026】[0026]

【発明の効果】以上の通り、本発明によれば、線路地盤
の変状が生じた場合において、容易にその修正を行うこ
とができるなどの利点がもたらされる。
As described above, according to the present invention, it is possible to easily correct the deformation of the track ground when it occurs.

【図面の簡単な説明】[Brief description of drawings]

【図1】第1実施例における線路地盤のレールを横断す
る方向の断面図である。
FIG. 1 is a cross-sectional view in a direction crossing a rail of a track ground in a first embodiment.

【図2】レール方向の縦断面図である。FIG. 2 is a vertical cross-sectional view in the rail direction.

【図3】充填口を長手方向に複数有する例の袋体の正面
図である。
FIG. 3 is a front view of a bag body having a plurality of filling ports in the longitudinal direction.

【図4】第2実施例における注入管の設置例の縦断面図
である。
FIG. 4 is a vertical sectional view of an installation example of an injection pipe in a second embodiment.

【図5】他の注入管の設置例の要部縦断面図である。FIG. 5 is a vertical cross-sectional view of a main part of another installation example of the injection pipe.

【図6】第3実施例の横断面図である。FIG. 6 is a transverse sectional view of the third embodiment.

【図7】他の例の横断面図である。FIG. 7 is a cross-sectional view of another example.

【図8】袋体構造を異にする例の横断面図である。FIG. 8 is a cross-sectional view of an example in which the bag structure is different.

【符号の説明】[Explanation of symbols]

1…路盤、2…道床バラスト、3…枕木、4…レール、
10・30…袋体、11…バラスト、20…注入管、2
1…固化材料、22…注入管。
1 ... Roadbed, 2 ... Ballast ballast, 3 ... Sleepers, 4 ... Rails,
10.30 ... bag body, 11 ... ballast, 20 ... injection tube, 2
1 ... Solidified material, 22 ... Injection tube.

フロントページの続き (72)発明者 須長 誠 東京都国分寺市光町二丁目8番地38 財団 法人鉄道総合技術研究所内 (72)発明者 岩佐 弘 東京都千代田区九段北4丁目2番35号 ラ イト工業株式会社内 (72)発明者 木下 吉友 東京都千代田区九段北4丁目2番35号 ラ イト工業株式会社内Front page continuation (72) Inventor Makoto Sunaga 38-8, Hikarimachi, Kokubunji, Tokyo 38 Railroad Research Institute of Japan (72) Hiroshi Iwasa 4-35 Kudankita 4-chome, Chiyoda-ku, Tokyo Light Industrial Co., Ltd. (72) Inventor Yoshitomo Kinoshita 4-35, Kudankita 4-chome, Chiyoda-ku, Tokyo Inside Light Industrial Co., Ltd.

Claims (2)

【特許請求の範囲】[Claims] 【請求項1】線路地盤の道床バラストに枕木を設けた線
路地盤において、 枕木の下部にその長手方向に沿って可撓性袋体を設け、
その内部にバラストを含む充填材を充填し、この可撓性
袋体の間および下方に道床バラストを敷設し、 レールの沈下が生じたときまたは沈下の虞れがあると
き、可撓性袋体内に充填材を補充充填して、沈下分を補
償することを特徴とする線路地盤の改良工法。
1. A track ground in which a sleeper is provided on a ballast of a track ground, and a flexible bag body is provided at a lower part of the sleeper along a longitudinal direction thereof.
The inside of the flexible bag is filled with a filling material containing ballast, and a ballast ballast is laid between and below the flexible bag when rail subsidence occurs or there is a risk of subsidence. An improved construction method for the track ground, which is characterized in that the subsidence is compensated by replenishing and filling the ground with filler.
【請求項2】線路地盤の道床バラストに枕木を設けた線
路地盤において、 枕木の下部にその長手方向に沿って可撓性袋体を設け、
その内部にバラストを含む充填材を充填し、この可撓性
袋体の間および下方に道床バラストを敷設し、 前記可撓性袋体とは別に、少なくともその上方の枕木と
の間または可撓性袋体の下方にさらに可撓性袋体を設
け、 レールの沈下が生じたときまたは沈下の虞れがあると
き、可撓性袋体内に充填材を補充充填して、沈下分を補
償することを特徴とする線路地盤の改良工法。
2. A railroad ground in which a sleeper is provided on a ballast of a trackbed ballast, and a flexible bag body is provided at a lower portion of the sleeper along a longitudinal direction thereof.
The inside of the flexible bag is filled with a filler containing ballast, and a ballast ballast is laid between and below the flexible bags, and apart from the flexible bags, at least between the sleepers above the flexible bags or the flexible sleepers. A flexible bag is provided below the flexible bag, and when the rail sinks or there is a risk of sinking, the flexible bag is replenished with a filler to compensate for the sink. An improved construction method for track grounds, which is characterized in that
JP21453994A 1994-09-08 1994-09-08 Improvement method of track ground Expired - Fee Related JP3473998B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP21453994A JP3473998B2 (en) 1994-09-08 1994-09-08 Improvement method of track ground

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP21453994A JP3473998B2 (en) 1994-09-08 1994-09-08 Improvement method of track ground

Publications (2)

Publication Number Publication Date
JPH0874201A true JPH0874201A (en) 1996-03-19
JP3473998B2 JP3473998B2 (en) 2003-12-08

Family

ID=16657419

Family Applications (1)

Application Number Title Priority Date Filing Date
JP21453994A Expired - Fee Related JP3473998B2 (en) 1994-09-08 1994-09-08 Improvement method of track ground

Country Status (1)

Country Link
JP (1) JP3473998B2 (en)

Cited By (14)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH10131169A (en) * 1996-10-30 1998-05-19 Sanshin Kensetsu Kogyo Kk Current-place subgrade reinforcing method of existing pavement
JP2002256501A (en) * 2001-03-05 2002-09-11 Mitsubishi Rayon Co Ltd Joint part ballast reinforcing track and construction method therefor
JP2004011131A (en) * 2002-06-03 2004-01-15 Ems Japan Kk Construction method of reinforcing structure
KR100809001B1 (en) * 2006-11-16 2008-03-05 임규동 Earth reinforcement method based on the control for settlement of the concrete pavement comprising reinforced concrete slab
JP2008095413A (en) * 2006-10-13 2008-04-24 Hokkaido Railway Co Ballast repairing method for ballasted track
WO2008136313A1 (en) 2007-04-27 2008-11-13 Central Japan Railway Company Ballast stopping work, bedded track
JP4664537B2 (en) * 2001-07-04 2011-04-06 株式会社アレン Elastic pad for track and elastic method for track
JP2012077452A (en) * 2010-09-30 2012-04-19 Sumitomo Osaka Cement Co Ltd Roadbed improvement method
JP2012077453A (en) * 2010-09-30 2012-04-19 Sumitomo Osaka Cement Co Ltd Roadbed improvement method
JP2012180633A (en) * 2011-02-28 2012-09-20 Allen:Kk Variable pad, rail height adjustment method, and resin feeder
US8720792B2 (en) 2008-08-05 2014-05-13 Central Japan Railway Company Ballast retaining structure, tool jig, and bedded track
KR101468245B1 (en) * 2007-04-24 2014-12-03 헤네케 게엠베하 Method and device for foaming ballast beds
KR20170067422A (en) * 2015-12-08 2017-06-16 한국철도기술연구원 Self-recovery module and method for constructing thereof
CN114182576A (en) * 2021-12-08 2022-03-15 中铁第一勘察设计院集团有限公司 Adjustable plate type ballastless track suitable for area with large foundation deformation risk

Cited By (16)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH10131169A (en) * 1996-10-30 1998-05-19 Sanshin Kensetsu Kogyo Kk Current-place subgrade reinforcing method of existing pavement
JP2002256501A (en) * 2001-03-05 2002-09-11 Mitsubishi Rayon Co Ltd Joint part ballast reinforcing track and construction method therefor
JP4664537B2 (en) * 2001-07-04 2011-04-06 株式会社アレン Elastic pad for track and elastic method for track
JP2004011131A (en) * 2002-06-03 2004-01-15 Ems Japan Kk Construction method of reinforcing structure
JP2008095413A (en) * 2006-10-13 2008-04-24 Hokkaido Railway Co Ballast repairing method for ballasted track
KR100809001B1 (en) * 2006-11-16 2008-03-05 임규동 Earth reinforcement method based on the control for settlement of the concrete pavement comprising reinforced concrete slab
KR101468245B1 (en) * 2007-04-24 2014-12-03 헤네케 게엠베하 Method and device for foaming ballast beds
US8240580B2 (en) 2007-04-27 2012-08-14 Central Japan Railroad Company Ballast retaining structure, bedded track
WO2008136313A1 (en) 2007-04-27 2008-11-13 Central Japan Railway Company Ballast stopping work, bedded track
EP3098348A1 (en) 2007-04-27 2016-11-30 Central Japan Railway Company Ballast retaining structure
US8720792B2 (en) 2008-08-05 2014-05-13 Central Japan Railway Company Ballast retaining structure, tool jig, and bedded track
JP2012077452A (en) * 2010-09-30 2012-04-19 Sumitomo Osaka Cement Co Ltd Roadbed improvement method
JP2012077453A (en) * 2010-09-30 2012-04-19 Sumitomo Osaka Cement Co Ltd Roadbed improvement method
JP2012180633A (en) * 2011-02-28 2012-09-20 Allen:Kk Variable pad, rail height adjustment method, and resin feeder
KR20170067422A (en) * 2015-12-08 2017-06-16 한국철도기술연구원 Self-recovery module and method for constructing thereof
CN114182576A (en) * 2021-12-08 2022-03-15 中铁第一勘察设计院集团有限公司 Adjustable plate type ballastless track suitable for area with large foundation deformation risk

Also Published As

Publication number Publication date
JP3473998B2 (en) 2003-12-08

Similar Documents

Publication Publication Date Title
JP3473998B2 (en) Improvement method of track ground
CN106087629B (en) Without the prefabricated baffle foam concrete light road bank structure of conical slope and construction method
KR100768777B1 (en) Earth reinforcement method for railway track on the concrete base
CA1336424C (en) Railroad roadway for high speed rail-mounted vehicles
KR101076029B1 (en) Replacing Method of Old Train Track using Twin-Block Type Train Track
KR100838227B1 (en) Structure of high-strength and rapidly-hardening prepacked concrete track for carrying out mechanization and working method thereof
KR20160001011U (en) Precast Concrete Panel for Concrete Ballast of the Railway
JP7107665B2 (en) Roadbed improvement method
JP6170268B1 (en) Ballast track subbase formation method
JP3520294B2 (en) How to build a sleeper track
JP3432302B2 (en) Construction method and repair method of track
CN108708290A (en) The case crane span structure hollow structure and cast-in-situ construction method of minor radius railway curve unit
KR101580521B1 (en) railway concrete roadbed anti-crack sleepers and it's construction method
CN110629617A (en) Combined type bottom-plate-free box type roadbed and roadbed construction method
CN111809470A (en) Structure and method for preventing cracks of road base layer and road subbase layer
CN1732315B (en) Method for constructing a rigid pavement, and a rigid pavement carriageway
JP2604476B2 (en) How to build a slab track
CN206090197U (en) Prefabricated baffle foam concrete light embankment structure of no conical slope
CN109853624A (en) A kind of enlarging construction method for existing highway rectangle culvert
CN206127789U (en) Structure of making an uproar falls in highway tunnel driving damping
KR102097122B1 (en) Precast mold for platform on piles system and concrete slab track construction method therewith
CN106283956B (en) Medium-and low-speed maglev two-wire excavation location pile foundation combined type support rail beam transition section structure
CN106283973B (en) Medium-and low-speed maglev traffic engineering two-wire excavation location independence pier stud type support rail beam transition section structure
CN106283946B (en) The compound framing type support rail beam transition section structure of medium-and low-speed maglev two-wire excavation location pile foundation
KR20150009243A (en) railway concrete roadbed anti-crack sleepers and it's construction method

Legal Events

Date Code Title Description
R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

FPAY Renewal fee payment (prs date is renewal date of database)

Year of fee payment: 6

Free format text: PAYMENT UNTIL: 20090919

LAPS Cancellation because of no payment of annual fees