JPH0842139A - Sleeper receiving structure in timbering - Google Patents

Sleeper receiving structure in timbering

Info

Publication number
JPH0842139A
JPH0842139A JP6197804A JP19780494A JPH0842139A JP H0842139 A JPH0842139 A JP H0842139A JP 6197804 A JP6197804 A JP 6197804A JP 19780494 A JP19780494 A JP 19780494A JP H0842139 A JPH0842139 A JP H0842139A
Authority
JP
Japan
Prior art keywords
wedge
base
holes
hole
sleeper
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP6197804A
Other languages
Japanese (ja)
Inventor
Takahiro Enoki
孝洋 榎
Kazuo Kato
和雄 加藤
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Nisso Industries Co Ltd
Original Assignee
Nisso Industries Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Nisso Industries Co Ltd filed Critical Nisso Industries Co Ltd
Priority to JP6197804A priority Critical patent/JPH0842139A/en
Publication of JPH0842139A publication Critical patent/JPH0842139A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G25/00Shores or struts; Chocks
    • E04G25/04Shores or struts; Chocks telescopic
    • E04G25/06Shores or struts; Chocks telescopic with parts held together by positive means
    • E04G25/066Shores or struts; Chocks telescopic with parts held together by positive means by a wedge

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)

Abstract

PURPOSE:To provide a sleeper receiving structure in timbering which becomes optimal to support a sleeper being a form side member from below in a stable condition and in which a workability undeteriorating sleeper receiving member is arranged when the sleeper and a form or the like supported with this are removed on the upper end side of the timbering. CONSTITUTION:A sleeper receiving member 6 to support a sleeper has a base stand 10 connected to a height adjusting member, a raising-lowering body 20 which is interposed on the outer peripheral side of the base stand so as to be raised and lowered and supports the sleeper and a wedge 30 connected to the base stand and the raising-lowering body, and the raising-lowering body is constituted on the outer peripheral side of a guide part 12 to constitute the base stand, and a body part 21 is interposed so as to be raised and lowered. A through-hole to insert the wedge is bored, and a pair of main holes 21a and 21b to insert the wedge are bored in a central part in the lateral direction of the body part, and a pair of sub-holes 21c are bored on the upper ends of the main holes, and the wedge has a tip side neck part formed so as to become narrower than the sub-holes and a base end side neck part 34.

Description

【発明の詳細な説明】Detailed Description of the Invention

【0001】[0001]

【産業上の利用分野】この発明は、コンクリート構造物
を築造する際の型枠を支持する支保工における大引受け
構造の改良に関する。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to an improvement of a large undertaking structure in a supporting work for supporting a formwork when constructing a concrete structure.

【0002】[0002]

【従来の技術】近年、コンクリート構造物を築造する際
の型枠を支持する支保工にあっては、パイプサポート等
の支保杭の上端等と、型枠を根太の介在下に下方から支
持する大引と、の間に、所謂ジャッキ操作で伸縮する、
例えば、スクリュジャッキからなる高さ調整部材が配在
されるとしている。
2. Description of the Related Art In recent years, in the support work for supporting a formwork when constructing a concrete structure, the upper end of a support pile such as a pipe support and the formwork are supported from below from the bottom of a joist. Between Daihiki and the so-called jack operation to expand and contract,
For example, a height adjusting member including a screw jack is distributed.

【0003】該高さ調整部材は、コンクリートの打設前
には、その伸縮によって大引に支持される型枠を設定の
高さ位置に配設することを可能にし、コンクリートの打
設後には、その収縮によって型枠の下面側からの大引や
根太の抜き取り及びコンクリート構造物の下面からの型
枠の引き剥し等のための作業空間を形成することを可能
にする。
The height adjusting member makes it possible to dispose a formwork, which is supported largely by expansion and contraction thereof, at a set height position before pouring concrete, and after pouring concrete. By the contraction, it is possible to form a work space for pulling a large amount of joists and joists from the lower surface side of the formwork and peeling the formwork from the lower surface of the concrete structure.

【0004】しかしながら、支保工の利用の実態を看る
と、通常、コンクリートの打設後における高さ調整部材
には極めて大きい荷重が作用しており、従って、該高さ
調整部材がスクリュジャッキからなる場合には、これを
ジャッキ操作で収縮することが容易でなく、甚だしい場
合にはその収縮を実現できないことがある。
However, in view of the actual use of the support work, usually, an extremely large load is applied to the height adjusting member after the concrete is placed, so that the height adjusting member is not connected to the screw jack. In such a case, it is not easy to contract it by jacking, and in extreme cases, the contraction may not be realized.

【0005】そこで、支保杭の上端等に連結される高さ
調整部材と、型枠を根太の介在下に下方から支持する大
引と、の間に、例えば、実開平1−153056号公報
あるいは実開平5−69239号公報に開示されている
ような大引受け部材を配在してなる支保工における大引
受け構造を提案し得ることになる。
Therefore, for example, between the height adjusting member connected to the upper end of the support pile and the Daihiki which supports the formwork from below with the joist interposed, for example, Japanese Utility Model Laid-Open No. 1-153056. Therefore, it is possible to propose a large undertaking structure in a supporting work in which a large undertaking member is distributed as disclosed in Japanese Utility Model Laid-Open No. 5-69239.

【0006】因に、該大引受け部材は、ハンマ打撃等に
よるクサビの所謂抜き出し操作でその収縮が可能になる
ように構成されている。
Incidentally, the large catch member is constructed so that it can be contracted by a so-called pull-out operation of the wedge by hammering or the like.

【0007】それ故、上記の各提案に係る大引受け部材
を配在してなる支保工における大引受け構造によれば、
上方のコンクリート構造物から大きい荷重が作用して高
さ調整部材の収縮が困難になるような場合でも、大引受
け部材が収縮されることで、以降の高さ調整部材の収縮
が容易に可能になり、従って、上記した大引や根太の抜
き取り及び型枠の引き剥し等を容易になし得ることにな
る。
Therefore, according to the large undertaking structure in the supporting work in which the large undertaking members according to the above-mentioned proposals are distributed,
Even if it is difficult to contract the height adjustment member due to a large load from the concrete structure above, the subsequent large adjustment member can be contracted, and the subsequent height adjustment member can be easily contracted. Therefore, it is possible to easily carry out the above-mentioned pulling-out and joisting and peeling-off of the mold.

【0008】[0008]

【発明が解決しようとする課題】しかしながら、上記の
各提案に係る大引受け部材を配在してなる支保工におけ
る大引受け構造にあっては、以下のような不都合が指摘
されている。
However, the following disadvantages have been pointed out in the large undertaking structure in the support work in which the large overtaking members according to the above-mentioned proposals are provided.

【0009】即ち、実開平1−153056号公報に開
示の大引受け部材にあっては、その収縮時の収縮長さ
が、最大限、クサビの体高分のみとなる。
That is, in the large catch member disclosed in Japanese Utility Model Laid-Open No. 1-153056, the contraction length when contracted is at most the height of the wedge.

【0010】ところで、一般に、支保工の上端側から大
引や型枠等を撤去する際には、少なくとも、該大引等を
自由に所謂抜き挿し等できる程度のスペース、即ち、少
なくとも、上記クサビの体高分以上のスペースが必要で
ある。
By the way, generally, at the time of removing a haul or a mold from the upper end side of the support work, at least a space where the haul or the like can be freely inserted and removed, that is, at least the above wedges. Space more than body height is required.

【0011】それ故、上記提案に係る大引受け部材にお
いて、クサビの体高分に相当する収縮が実現されるのみ
では、大引等の抜き挿し等に必要なスペースを確保でき
ず、大引等の撤去作業を支障なく行い得ないことにな
る。
Therefore, in the large catch receiving member according to the above-mentioned proposal, if only the contraction corresponding to the height of the wedge is realized, the space required for removing and inserting the large draw cannot be secured. The removal work will not be possible without any hindrance.

【0012】のみならず、上記提案では、大引受け部材
を収縮した上で、さらに、ジャッキ操作をして高さ調整
部材をも収縮しなければ、必要なスペースを確保でき
ず、所謂手間がかかる欠点もある。
In addition to the above, in the above proposal, the required space cannot be secured unless the large catch member is contracted and then the height adjusting member is contracted by the jack operation, which is so-called troublesome. There are also drawbacks.

【0013】一方、実開平5−69239号公報に開示
の大引受け部材にあっては、上記した従来例に比較して
大きいストロークでの収縮が可能になるが、クサビによ
る上方部材の支持位置が大引受け部材における左右方向
の中心位置になく、所謂偏芯した位置とされている。
On the other hand, in the large catch member disclosed in Japanese Utility Model Laid-Open No. 5-69239, the contraction with a larger stroke is possible as compared with the above-mentioned conventional example, but the supporting position of the upper member by the wedge is It is located at a so-called eccentric position, not at the center position in the horizontal direction of the large catch member.

【0014】従って、クサビは、大引受け部材における
縦方向となる軸芯位置から横に外れた位置で上方からの
荷重を支えることになり、大引受け部材自体が所謂グラ
ツキ易くなるのは勿論のこと、甚だしい場合には、大引
受け部材が横方向にはじき出されるような事態になっ
て、支保工における大引受け構造の崩壊が招来されるこ
とになる危惧がある。
Therefore, the wedge supports the load from above at a position laterally displaced from the axial center position of the large catch member, which is the longitudinal direction, and the large catch member itself is, of course, so-called loose. In the extreme case, there is a fear that the large undertaking member may be pushed out in the lateral direction and the collapse of the large undertaking structure in the supporting work may be caused.

【0015】そして、この危険を予め回避するについて
は、所謂控えを採る等のさらなる手当てが必要になる不
具合ある。
In order to avoid this danger in advance, there is a problem that it is necessary to take further measures such as taking a so-called copy.

【0016】この発明は、前記した事情に鑑みて創案さ
れたものであって、その目的とするところは、型枠側部
材たる大引を下方から安定した状態で支持するに最適と
なると共に、爾後に、上記大引やこれが支持する型枠等
を支保工の上端側で撤去等するに際して、その作業性を
低下させないようにするに最適となる大引受け部材を配
在する支保工における大引受け構造を提供することであ
る。
The present invention was devised in view of the above-mentioned circumstances, and its object is to optimally support a large pull which is a mold side member from below in a stable state, and After that, when removing the above-mentioned large pull or the formwork etc. which it supports on the upper end side of the support work, etc., the large support member in the support work where the optimum large support member is arranged so as not to deteriorate the workability Is to provide the structure.

【0017】[0017]

【課題を解決するための手段】上記した目的を達成する
ため、この発明の構成を、下端が支保杭の上端等に配設
の高さ調整部材に連結されながら上端で型枠の下面に根
太の配在下に隣設される大引を支持する大引受け部材を
有してなり、該大引受け部材が高さ調整部材に連結され
る基台と、該基台の外周側に昇降可能に介装され大引を
支持する昇降体と、上記基台及び昇降体に横方向から出
没可能に連繋されるクサビと、を有してなる支保工にお
ける大引受け構造において、基台を構成するガイド部の
外周側に昇降体を構成し筒状に形成された本体部が昇降
可能に介装されてなる一方で、ガイド部の横方向の中央
部にクサビを挿通させる透孔が開穿されてなり、本体部
の横方向の中央部に上記透孔に照準されるように形成さ
れてクサビを挿通させる一対の主孔が開穿されてなると
共に該各主孔の上端に連通して該主孔より細幅寸法に形
成されながら上方に適宜の長さに延在される一対の副孔
が開穿されてなり、クサビが上記副孔より細幅となるよ
うに形成された尖端側頚部及び基端側頚部を有してな
り、クサビの後退時に尖端側頚部及び基端側頚部が上記
各副孔内に臨在されて昇降体が基台に対して下降される
ように形成されてなるとする。
In order to achieve the above-mentioned object, the structure of the present invention is constructed such that the lower end is connected to a height adjusting member disposed at the upper end of a support pile or the like while the lower end of the formwork is tied to the lower face of the formwork. A large base member that supports a large bar, which is provided adjacent to the base, and the large base member is connected to the height adjusting member; A guide part constituting a base in a large catching structure in a supporting work, which comprises an elevating body mounted to support a large pull, and a wedge connected to the base and the elevating body so as to be retractable from the lateral direction. On the outer peripheral side of the body, a cylindrical body that constitutes an elevating body is interposed so that it can move up and down, while a through hole for inserting wedges is opened in the lateral center of the guide. Insert the wedge in the center of the body in the horizontal direction so that it is aimed at the through hole. A pair of main holes are formed, and a pair of sub-holes communicating with the upper ends of the main holes and having a narrower width than the main holes and extending upward by an appropriate length are formed. The wedge has a tip side neck and a base side neck which are formed so that the wedge is narrower than the sub-hole, and when the wedge retreats, the tip side neck and the base side neck have the above-mentioned sub-sides. It is assumed that the elevating body is formed so as to be present in the hole and be lowered with respect to the base.

【0018】そして、好ましくは、ガイド部は、本体部
に相似する筒状に形成されてなるとし、副孔は、その上
下方向の長さをクサビの体高以上とするように設定され
てなるとし、昇降体を構成する大引受部は、大引の収容
を許容する角U字状の断面を有する樋状に形成されてな
るとし、クサビは、大引の延在方向を横切る方向に沿っ
て出没可能とされてなるとする。
Preferably, the guide portion is formed in a cylindrical shape similar to the main body portion, and the auxiliary hole is set so that its vertical length is equal to or higher than the body height of the wedge. , The girder receiving portion constituting the elevating body is formed in a gutter shape having a square U-shaped cross section that allows accommodating of the grab, and the wedge extends along a direction transverse to the extending direction of the grab. It is assumed that it can appear and disappear.

【0019】[0019]

【作用】それ故、大引受け部材は、その下端が支保杭の
上端等に配在の高さ調整部材に連結された状態下にその
上端で大引を保持する。
Therefore, the grab pull receiving member holds the grab pull at its upper end in a state where its lower end is connected to the height adjusting member disposed at the upper end of the support pile or the like.

【0020】その際に、大引受け部材を構成する基台の
基部が高さ調整部材に連結され、基台のガイド部の外周
側に大引受け部材を構成する昇降体の本体部が昇降可能
に介装され、昇降体の大引受部が大引を収容状態に保持
する。
At this time, the base part of the base forming the large catch member is connected to the height adjusting member, and the main body of the lifting body forming the large catch member can be moved up and down on the outer peripheral side of the guide part of the base. It is interposed, and the grab receiving part of the elevating body holds the grab in the accommodated state.

【0021】そして、クサビは、ガイド部とその外周側
に介装の本体部にこれを貫通する状態に連繋され、その
前進状態時に、該大引受け部材を伸長状態に維持し、そ
の後退時に、該大引受け部材を収縮化させる。
The wedge is connected to the guide portion and the main body portion of the outer peripheral side of the wedge portion so as to penetrate therethrough, maintains the large catch member in the extended state during the forward movement thereof, and during the backward movement thereof. The large underwriting member is contracted.

【0022】上記クサビは、ガイド部の横方向の中央部
に開穿の透孔に挿通されると共に、該透孔に照準される
ように本体部に開穿された主孔に挿通されているとき、
該大引受け部材の伸長状態を維持する。
The wedge is inserted into a through hole which is opened at the center of the guide portion in the lateral direction, and is inserted into a main hole which is opened in the main body so as to be aimed at the through hole. When
The extended state of the large catch member is maintained.

【0023】また、上記クサビに形成の尖端側頚部及び
基端側頚部を主孔に連続形成された副孔に臨在させると
き、該大引受け部材が収縮状態になる。
Further, when the apical side neck and the proximal side neck formed on the wedge are made to exist in the auxiliary hole continuously formed in the main hole, the large catch member is contracted.

【0024】そして、該大引受け部材が収縮するストロ
ークは、上記副孔の縦長さの設定如何で決定され、好ま
しくは、その長さがクサビの所謂体高以上に設定され
る。
The stroke of contraction of the large catch member is determined by how the vertical length of the sub-hole is set, and preferably the length is set to be equal to or greater than the so-called body height of the wedge.

【0025】[0025]

【実施例】以下、図示した実施例に基づいてこの発明を
説明するが、図1に示すように、この発明の一実施例に
係る支保工における大引受け構造は、支保杭1の上端に
配在されるスクリュジャッキからなる高さ調整部材2
と、型枠3の下面に隣接される根太4を下方から支持す
る大引5と、の間に配在される大引受け部材6を有する
構成とされている。
BEST MODE FOR CARRYING OUT THE INVENTION The present invention will be described below with reference to the illustrated embodiments. As shown in FIG. 1, the large undercarriage structure in the supporting work according to one embodiment of the present invention is arranged at the upper end of the supporting pile 1. Height adjustment member 2 consisting of existing screw jack
And a large pulling member 6 that supports the joists 4 adjacent to the lower surface of the formwork 3 from below, and a large pulling receiving member 6 disposed between them.

【0026】そして、該大引受け部材6は、図2乃至図
4に示すように、基台10と、昇降体20と、クサビ3
0と、を有してなり、基台10に対して昇降体20が上
昇された状態のときに、この両者10,20に連繋され
ているクサビ30が図示する前進状態におかれているこ
とで伸長状態に維持される(図2参照)。
As shown in FIGS. 2 to 4, the large catch member 6 includes a base 10, a lifting body 20, and a wedge 3.
0, and when the elevating body 20 is raised with respect to the base 10, the wedge 30 linked to the both 10 and 20 is in the forward state shown in the figure. Is maintained in a stretched state (see FIG. 2).

【0027】また、該大引受け部材6は、図5に示すよ
うに、クサビ30が図示する後退状態におかれて基台1
0に対して昇降体20が下降された状態のときに収縮状
態になる。
Further, as shown in FIG. 5, the large catch member 6 is placed in the retracted state in which the wedge 30 is illustrated, and the base 1 is
When the elevating body 20 is lowered with respect to 0, the contracted state is established.

【0028】基台10は、平板状に形成された基部11
と、丸筒状に形成されて基部11の中央上面に起立する
ガイド部12と、を有してなり、該ガイド部12の外周
側に昇降体20の下端側を昇降可能に介装させ、該ガイ
ド部12にクサビ30を挿通させるとしている。
The base 10 has a base 11 formed in a flat plate shape.
And a guide portion 12 which is formed in a round tubular shape and stands upright on the central upper surface of the base portion 11, and the lower end side of the elevating body 20 is interposed on the outer peripheral side of the guide portion 12 so as to be capable of moving up and down. The wedge 30 is supposed to be inserted into the guide portion 12.

【0029】基部11は、前記高さ調整部材2に連結さ
れるもので、図示例にあっては、平面視で正方形を呈す
るように形成されているが、これに代えて、平面視で円
形やその他の多角形を呈するように形成されているとし
ても良く、要は、上記高さ調整部材2の上端に安定状態
に連結できる形態に形成されていれば足りる。
The base 11 is connected to the height adjusting member 2 and is formed to have a square shape in a plan view in the illustrated example, but instead of this, it is circular in a plan view. It may be formed so as to have a polygonal shape or other polygons, and the point is that it is sufficient if it is formed in a shape that can be stably connected to the upper end of the height adjusting member 2.

【0030】尚、基部11は、図示例のように、その四
隅部に該基台10の上記高さ調整部材2への連結の際の
ボルト等の連結具(図示せず)を挿通させる孔11aを
開穿しているのが好ましい。
As shown in the figure, the base portion 11 has holes at its four corners through which connecting tools (not shown) such as bolts are inserted when the base 10 is connected to the height adjusting member 2. It is preferable that 11a is opened.

【0031】ガイド部12は、その上端側にクサビ30
を挿通させるとしており、該基台10にクサビ30が連
繋された状態のときに、該クサビ30を、例えば、ハン
マ打撃する際の操作性を良好にすると共に、昇降体20
の下降時のストロークを確保できるようにしている。
The guide portion 12 has a wedge 30 on its upper end side.
When the wedge 30 is connected to the base 10, the operability when hitting the wedge 30, for example, with a hammer, is improved, and the lifting body 20 is inserted.
It is designed to secure the stroke when the is descending.

【0032】そして、該ガイド部12は、その上端側に
開穿された透孔12a,12bにクサビ30を挿通させ
るとしており、該透孔12a,12bは、図示例にあっ
て、ガイド部12が筒状に形成されていることから、図
2中で左右方向となるクサビ30の出没方向に一対とな
る形態に形成されているが、ガイド部12が所謂充実体
で形成される場合には、単一の透孔に設定されること勿
論である。
The guide portion 12 is configured such that the wedge 30 is inserted through the through holes 12a and 12b formed on the upper end side thereof, and the through holes 12a and 12b are the guide portions 12 in the illustrated example. 2 are formed in a cylindrical shape, they are formed in a pair in the protruding and retracting direction of the wedge 30 which is the left-right direction in FIG. 2, but when the guide portion 12 is formed of a so-called solid body. Of course, a single through hole is set.

【0033】ただ、図示例のように、ガイド部12が筒
状に形成される場合には、該基台10における全体重量
の低減化が可能になり、また、透孔12a,12bの開
穿が容易になる点で有利となる。
However, when the guide portion 12 is formed in a tubular shape as in the illustrated example, the total weight of the base 10 can be reduced, and the through holes 12a and 12b are opened. Is advantageous in that it becomes easier.

【0034】そして、透孔12a,12bは、ガイド部
12における横方向の中央部(図3参照)に開穿されて
なるもので、これによって、クサビ30が基台10の平
面視で中央部となる軸芯部を横方向から貫通する状況に
設定できる。
The through-holes 12a and 12b are formed in the lateral center portion of the guide portion 12 (see FIG. 3), whereby the wedge 30 is centrally viewed in plan view of the base 10. It is possible to set the situation in which the shaft core part that becomes

【0035】また、透孔12a,12bは、その上端位
置が同レベルとされるに対して、その下端位置が互いに
ずれる、即ち、クサビ30における下端の傾斜に一致す
るように設定されている。
Further, the through holes 12a and 12b are set so that their upper end positions are at the same level but their lower end positions are displaced from each other, that is, they coincide with the inclination of the lower end of the wedge 30.

【0036】尚、該透孔12a,12bは、クサビ30
を挿通させるに十分な幅寸法を有してなること勿論であ
る。
The through holes 12a and 12b are formed by wedges 30.
Needless to say, it has a width dimension sufficient to allow the insertion.

【0037】昇降体20は、丸筒状に形成された本体部
21と、断面角U字状に形成されて本体部21の上端に
連設された大引受部22と、を有してなり、本体部21
を基台10におけるガイド部12の外周側に臨在させる
と共に、大引受部22で前記大引5を保持するとしてい
る。
The elevating body 20 has a body portion 21 formed in a round tube shape, and a large receiving portion 22 formed in a U-shaped cross section and connected to the upper end of the body portion 21. , Body 21
Is made to exist on the outer peripheral side of the guide part 12 in the base 10, and the large pulling part 22 holds the large pulling part 5.

【0038】本体部21は、その下端側に基台10にお
けるガイド部12に開穿の透孔12a,12bに照準さ
れる主孔21a,21bを有してなると共に、その上半
側に各主孔21a,21bに連通する一対の副孔21c
を有してなる。
The main body portion 21 has main holes 21a and 21b, which are aimed at the through holes 12a and 12b opened in the guide portion 12 of the base 10 on the lower end side thereof, and the main holes 21a and 21b on the upper half side thereof. A pair of sub-holes 21c communicating with the main holes 21a and 21b
To have.

【0039】各主孔21a,21bが本体部21の下端
側に配在されることで、該本体部21、即ち、昇降体2
0の下降時のストロークを確保できることになる。
By disposing the main holes 21a and 21b on the lower end side of the main body portion 21, the main body portion 21, that is, the lift 2
It is possible to secure the stroke at the time of 0 descent.

【0040】そして、各主孔21a,21bは、上記透
孔12a,12bがクサビ30の出没方向に一対となる
形態に形成されていることから、同じく、クサビ30の
出没方向に一対となる形態に形成されている(図2参
照)。
Since each of the main holes 21a and 21b is formed in such a manner that the through holes 12a and 12b form a pair in the protruding / retracting direction of the wedge 30, the pair of main holes 21a, 21b also forms a pair in the protruding / retracting direction of the wedge 30. (See FIG. 2).

【0041】また、各主孔21a,21bは、その大き
さがクサビ30の挿通を許容するように設定されている
こと勿論であるが、図示例にあっては、その上端位置が
同レベルとされるに対して、その下端位置が互いにずれ
る、即ち、クサビ30における下端の傾斜に相応するよ
うに設定されている。
Of course, the size of each of the main holes 21a and 21b is set so as to allow the wedge 30 to be inserted, but in the illustrated example, the upper end positions thereof are at the same level. On the other hand, the lower end positions are displaced from each other, that is, the lower end positions of the wedges 30 are set to correspond to each other.

【0042】尚、上記各主孔21a,21bの所謂縦方
向の大きさについては、実施例のように異なるように設
定しなくても良いが、実施例のように大小異なるよう
に、即ち、前記各透孔12a,12bに相応するように
設定することで、クサビ30を連繋状態にするについ
て、所謂挿し込みミスが招来されなくなり、操作性を良
くする点で有利となる。
The so-called vertical size of each of the main holes 21a and 21b need not be set differently as in the embodiment, but may be different in size as in the embodiment, that is, By setting so as to correspond to the through holes 12a and 12b, so-called insertion error does not occur when the wedges 30 are connected, which is advantageous in improving operability.

【0043】一対の副孔21cは、各主孔21a,21
bの上端に連通して該主孔21a,21bより細幅寸法
に形成されながら上方、即ち、本体部21の上半側に適
宜の長さに延在されている。
The pair of sub-holes 21c are the main holes 21a, 21
It is connected to the upper end of b and is formed in a narrower width than the main holes 21a and 21b, and extends upward, that is, on the upper half side of the main body portion 21 with an appropriate length.

【0044】因に、副孔21cの長さ、即ち、高さ寸法
については、クサビ30の体高以上に設定されるのが好
ましいが、その理由については後述する。
Incidentally, the length of the sub-hole 21c, that is, the height dimension, is preferably set to be equal to or higher than the body height of the wedge 30. The reason will be described later.

【0045】大引受部22は、大引5を保持し得るよう
に形成されていれば足りるが、図示例のように、角U字
状の断面を有する樋状に形成されてなる場合には、図2
中で左右方向となるクサビ30の出没方向に沿う大引5
のズレや転倒が招来されなくなる点で有利となる。
It suffices that the large catching portion 22 is formed so as to hold the large catch 5, but when the large catching portion 22 is formed in a gutter shape having a square U-shaped cross section as shown in the drawing. , Fig. 2
Large pull 5 along the protruding / retracting direction of wedge 30 which is the left / right direction
It is advantageous in that it does not cause a shift or a fall.

【0046】尚、大引受部22における立ち上り部22
a(図2参照)の立ち上り高さ寸法を小さくして、該大
引受部22が浅い角U字状の樋状に形成される場合に
は、該大引受部22、即ち、昇降体20の下降時に、上
記大引5をクサビ30の出没方向に移動させるようにし
て大引受部22上から撤去することも可能になる点で有
利となる。
The rising portion 22 in the large underwriting portion 22
In the case where the rising height dimension of a (see FIG. 2) is reduced and the large catching portion 22 is formed in a gutter shape having a shallow corner U-shape, the large catching portion 22, that is, the lifting body 20 is This is advantageous in that it is also possible to move the large puller 5 in the direction in which the wedges 30 appear and disappear and remove it from the large catch receiving portion 22 when descending.

【0047】クサビ30は、前記基台10におけるガイ
ド部12及び昇降体20における本体部21に対して横
方向から出没可能に挿通されるように形成されてなると
するもので、図示例にあっては、これが大引5の延在方
向を横切る方向に沿って出没可能に連繋されてなるとす
る。
The wedge 30 is formed so as to be inserted into and retractable from the guide portion 12 of the base 10 and the main body portion 21 of the elevating body 20 in the lateral direction. It is assumed that this is connected so as to be able to appear and disappear along a direction that intersects the extending direction of the large pull 5.

【0048】クサビ30が大引5の延在方向を横切る方
向に出没されるように設定されることで、該クサビ30
を、例えば、ハンマ打撃する際の操作性が大引5の配在
で所謂邪魔されなくなる点で有利となる。
By setting the wedge 30 so as to be projected and retracted in a direction transverse to the extending direction of the hauling 5, the wedge 30 is set.
Is advantageous, for example, in that the operability when hitting with a hammer is not disturbed by the distribution of the large puller 5.

【0049】そして、該クサビ30は、尖端部31と、
基端部32と、尖端部31に隣接するように形成された
尖端側頚部33と、基端部32に隣接するように形成さ
れた基端側頚部34と、尖端側頚部33と基端側頚部3
4との間に位置決められた中間部35と、を有してな
る。
The wedge 30 has a tip 31 and
A proximal end portion 32, a distal end neck portion 33 formed adjacent to the distal end portion 31, a proximal end neck portion 34 formed adjacent to the proximal end portion 32, a distal end neck portion 33 and a proximal end side. Neck 3
4 and an intermediate portion 35 positioned between the two.

【0050】尖端部31,基端部32及び中間部35
は、前記透孔12a,12b及び主孔21a,21bへ
の自由な挿通を可能にする幅寸法を有するように形成さ
れ、尖端側頚部33と基端側頚部34は、前記副孔21
cより細幅となる幅寸法を有するように形成されてい
る。
Pointed portion 31, base portion 32 and intermediate portion 35
Is formed so as to have a width dimension that allows free insertion into the through holes 12a and 12b and the main holes 21a and 21b, and the apical side neck portion 33 and the proximal side neck portion 34 have the auxiliary hole 21a.
It is formed to have a width dimension that is narrower than c.

【0051】そして、基端部32及び中間部35が、ク
サビ30の前進(図2に示す状態)時に、上記各透孔1
2a,12b及び主孔21a,21b内に臨在されるこ
とになり、このとき、本体部21、即ち、昇降体20の
ガイド部12、即ち、基台10に対する下降が阻止され
る伸長状態におかれることになる。
Then, the base end portion 32 and the intermediate portion 35 are arranged such that when the wedge 30 is advanced (the state shown in FIG. 2), the through holes 1 are formed.
2a, 12b and the main holes 21a, 21b are present, and at this time, the main body 21, that is, the guide portion 12 of the elevating body 20, that is, the extended state in which the lowering of the base 10 is blocked. Will be punished.

【0052】また、尖端側頚部33及び基端側頚部34
が、クサビ30の後退(図5に示す状態)時に、上記各
副孔21c内に臨在されることになり、このとき、本体
部21、即ち、昇降体20がガイド部12、即ち、基台
10に対して下降することを許容する収縮状態になる。
The apical side neck 33 and the proximal side neck 34
However, when the wedge 30 is retracted (state shown in FIG. 5), it will be present in each of the sub-holes 21c, and at this time, the main body portion 21, that is, the elevating body 20 is guided by the guide portion 12, that is, the base. It is in a contracted state that allows it to descend with respect to 10.

【0053】尚、上記尖端側頚部33及び基端側頚部3
4の平面視における幅寸法は、尖端部31,基端部32
及び中間部35における幅寸法より小さくなるように設
定されていること勿論で(図4参照)、これによって、
該大引受け部材6の収縮時にも、荷重の作用位置が所謂
中心になり、収縮時においたも、該大引受け部材6に所
謂グラツキが招来されないことになる。
The apical side neck 33 and the proximal side neck 3 are provided.
The width dimension in plan view of 4 is the pointed portion 31, the base end portion 32.
And, of course, it is set so as to be smaller than the width dimension in the intermediate portion 35 (see FIG. 4).
Even when the large catch member 6 contracts, the position where the load acts becomes the so-called center, and even when the large contract member 6 contracts, the large catch member 6 does not suffer from so-called graffiti.

【0054】以上のように形成されたこの実施例に係る
大引受け部材6は、所謂組み立られた状態で、支保工1
の上端に配設の高さ調整部材2に連結されることで、こ
の発明に係る支保工における大引受け構造を構成する。
The large catch member 6 according to this embodiment, which is formed as described above, is in a so-called assembled state, and in the support work 1
By being connected to the height adjusting member 2 arranged at the upper end of the, the large undertaking structure in the supporting work according to the present invention is configured.

【0055】その際には、基台10における基部11が
高さ調整部材2の上端に連結されるもので、該連結にあ
っては、通常、ボルト・ナット等の適宜の連結具が利用
されて、基台10の高さ調整部材2に対する横ズレ等が
招来されないようにする。
At this time, the base 11 of the base 10 is connected to the upper end of the height adjusting member 2, and in the connection, appropriate connecting tools such as bolts and nuts are usually used. Thus, the lateral displacement of the base 10 with respect to the height adjusting member 2 is prevented.

【0056】次に、昇降体20の上端、即ち、大引受部
22に大引5を載置するようにするが、大引受部22が
断面角U字状の樋状に形成されているから、該大引受部
22と大引5との間に連結手段の利用による連結状態を
確保しなくても済む。
Next, the large pull 5 is placed on the upper end of the lifting / lowering body 20, that is, on the large pull receiving part 22, because the large pull receiving part 22 is formed in a gutter shape having a U-shaped cross section. Therefore, it is not necessary to secure the connection state between the large pulling receiving portion 22 and the large pulling portion 5 by using the connecting means.

【0057】上記の状態から、昇降体20における本体
部21を基台10におけるガイド部12に沿って上昇さ
せるようにし、本体部21の所定の高さまでの上昇時
に、即ち、本体部21における主孔21a,21bにガ
イド部12における透孔12a,12bが照準される状
態になったときに、クサビ30を前進させて、上記昇降
体20の上昇状態を維持するようにする。
From the above state, the main body portion 21 of the lifting body 20 is raised along the guide portion 12 of the base 10, and when the main body portion 21 is raised to a predetermined height, that is, the main body portion 21 When the through holes 12a, 12b in the guide portion 12 are in the state of being aimed at the holes 21a, 21b, the wedge 30 is advanced to maintain the lifted state of the elevating body 20.

【0058】クサビ30の連繋によって、大引受け部材
6の収縮が阻止される状況になったときに、下方の高さ
調整部材2あるいは要する場合に支保杭1を伸長させる
ことで、昇降体20の上端に載置の大引5が根太4の介
在下に型枠3の下面側に隣設され、該大引受け部材6に
よる型枠3の所定の支持が可能になる。
When the large catch member 6 is prevented from contracting due to the connection of the wedges 30, the lower height adjusting member 2 or the supporting pile 1 if necessary is extended so that the elevating body 20 can be extended. A large pull 5 placed on the upper end is adjacently provided on the lower surface side of the form 3 with an interposition of the joists 4, so that the large pull receiving member 6 can support the form 3 in a predetermined manner.

【0059】このとき、この実施例に係る大引受け部材
6にあっては、その所謂中心部にクサビ30を連繋させ
るように構成されているので、クサビ30による支持位
置が中心位置から偏芯されているような状態にならず、
従って、安定した支持状態が実現されることになる。
At this time, in the large catch member 6 according to this embodiment, since the wedge 30 is connected to the so-called central portion thereof, the support position of the wedge 30 is eccentric from the central position. It does not become like
Therefore, a stable support state is realized.

【0060】そして、型枠3上に打設されたコンクリー
トが固化した後に、型枠3をコンクリート構造物C(図
1参照)からの引き剥しの際には、クサビ30の尖端部
31をハンマ打撃する等して、図2に示す状態から図中
右行させるように、該クサビ30を後退させて所謂解除
状態にする。
After the concrete cast on the formwork 3 is solidified, when the formwork 3 is peeled off from the concrete structure C (see FIG. 1), the tip 31 of the wedge 30 is hammered. By hitting or the like, the wedge 30 is retracted to a so-called released state so that the state shown in FIG. 2 is moved to the right in the figure.

【0061】尚、クサビ30における尖端部31の幅寸
法を昇降体20に開穿の主孔21bの幅寸法より大きく
設定する場合には、上記ハンマ打撃等によってクサビ3
0を打撃する際にも、該クサビ30の昇降体20からの
飛び出し状態での所謂抜けが効果的に阻止される点で有
利となる。
When the width of the pointed portion 31 of the wedge 30 is set to be larger than the width of the main hole 21b to be opened in the lifting body 20, the wedge 3 is hit by the hammer or the like.
Even when hitting 0, it is advantageous in that the so-called slip-out of the wedge 30 in the protruding state from the elevating body 20 is effectively prevented.

【0062】上記のクサビ30の後退で、各側頚部3
3,34が副孔21cの下端に臨在されることになり、
従って、昇降体20の下降が許容されて該大引受け部材
6が図5に示すように収縮化された形態になる。
When the wedge 30 is retracted as described above, each side neck 3
3,34 will be present at the lower end of the sub-hole 21c,
Therefore, the elevating body 20 is allowed to descend, and the large catch member 6 is contracted as shown in FIG.

【0063】このとき、該大引受け部材6の上方には、
昇降体20の下降によってクサビ30が臨在される副孔
21cにおける縦長さに等しいストローク分の空間が形
成されることになり、該大引受け部材6の上端からの大
引5の抜き取りやコンクリート構造物Cからの型枠3の
引き剥し等の各作業が何等の支障なく行えることにな
る。
At this time, above the large catch member 6,
A space for a stroke equal to the vertical length in the auxiliary hole 21c in which the wedge 30 is present is formed by the lowering of the elevating / lowering body 20, and extraction of the large pull 5 from the upper end of the large pull receiving member 6 or a concrete structure. Each work such as peeling of the mold 3 from C can be performed without any trouble.

【0064】そして、上記の形成される空間の高さにつ
いては、昇降体20における副孔21cの高さの設定如
何で自由に設定できることになり、副孔21cの高さが
所謂大き目に設定される場合には、下方の高さ調整部材
2や支保杭1等を収縮させる作業を要しないで、上記し
た大引5の抜き取りや型枠3の引き剥し等の各作業を実
行できることになる。
The height of the space formed above can be freely set by setting the height of the sub-hole 21c in the lifting body 20, and the height of the sub-hole 21c is set to a so-called large height. In this case, the work of contracting the height adjusting member 2 and the support piles 1 below and the like is not required, and each work such as the withdrawal of the large pull 5 and the peeling of the form 3 can be performed.

【0065】前記した実施例にあっては、基体10のガ
イド部12及び昇降体20の本体部21が共に円筒状に
形成されてなるとしたが、これに代えて、それぞれが角
筒状に形成されているとしても良く、その場合には、透
孔12a,12bや主孔21a,21b、さらには副孔
21cの開穿にあって、その位置決めや開穿作業が容易
になる点で有利となる利点がある。
In the embodiment described above, both the guide portion 12 of the base body 10 and the main body portion 21 of the elevating body 20 are formed in a cylindrical shape, but instead of this, each is formed in a rectangular tube shape. However, in that case, it is advantageous in that the through holes 12a and 12b, the main holes 21a and 21b, and the sub-hole 21c are opened, and the positioning and the opening work are facilitated. There are advantages.

【0066】[0066]

【発明の効果】以上のように、この発明によれば、型枠
等に隣設される大引を支保杭で下方から支持するように
した支保工において、支保杭の上端等に配設のジャッキ
構造の高さ調整部材と大引との間にクサビ構造に形成さ
れてその大きいストロークでの収縮化を可能にする大引
受け部材が配在されてなるとするので、支保工を構成す
る際の利用に最適となるのは勿論のこと、爾後に、その
収縮化によって大引や型枠等を支保工の上端側で撤去等
するに際して、その作業を容易に行わせ、その作業性を
低下させないことになる利点がある。
As described above, according to the present invention, in a supporting work in which a large haul adjacent to a formwork or the like is supported from below by a supporting pile, it is arranged at the upper end of the supporting pile or the like. Since a large catching member that is formed in a wedge structure and enables contraction with a large stroke is arranged between the height adjusting member of the jack structure and the large pulling, it is necessary to configure the support work. Not only is it most suitable for use, but it also facilitates the work when removing large pulls, forms, etc. on the upper end side of the support work due to shrinkage, and does not reduce workability. There are some advantages.

【0067】そして、この発明によれば、ガイド部が本
体部に相似する筒状に形成されてなることで、該ガイド
部を有する基台における全体重量の低減化が可能にな
り、また、ガイド部における透孔の開穿が容易になる点
で有利となる。
Further, according to the present invention, since the guide portion is formed in a cylindrical shape similar to the main body portion, the total weight of the base having the guide portion can be reduced, and the guide can be reduced. This is advantageous in that it is easy to open the through hole in the portion.

【0068】また、この発明によれば、副孔がその上下
方向の長さをクサビの体高以上とするように設定されて
なるとすることで、下方の高さ調整部材や支保杭等を収
縮させる作業を要しないで、支保工の上端側における大
引の抜き取りや型枠の引き剥し等の各作業を容易に実行
できることになる利点がある。
Further, according to the present invention, since the auxiliary hole is set so that its vertical length is equal to or greater than the body height of the wedge, the lower height adjusting member and the supporting piles are contracted. There is an advantage that each work such as pulling out the large pull and peeling off the form on the upper end side of the supporting work can be easily performed without requiring work.

【0069】さらに、この発明によれば、昇降体を構成
する大引受部が大引の収容を許容する角U字状の断面を
有する樋状に形成されてなるとすることで、大引受部と
大引との間に連結手段の利用による連結状態を確保しな
くても、クサビの出没方向に沿う外力作用があっても、
大引のズレや転倒が招来されなくなる利点がある。
Further, according to the present invention, the large overhanging portion constituting the lifting body is formed in the shape of a gutter having a square U-shaped cross section that allows the large uplift to be accommodated. Even if the connecting state is not secured by using the connecting means with Daihiki, even if there is an external force acting along the direction in which the wedges appear and disappear,
It has the advantage of not causing a big slip or a fall.

【0070】またさらに、この発明によれば、クサビが
大引の延在方向を横切る方向に沿って出没可能とされて
なるとすることで、クサビを、例えば、ハンマ打撃する
際の操作性が大引の配在で所謂邪魔されなくなる利点が
ある。
Furthermore, according to the present invention, the wedges are capable of appearing and retracting along a direction transverse to the extension direction of the hajiki, so that the operability when hitting the wedges with a hammer is great. There is an advantage of being undisturbed by the distribution of toki.

【0071】そしてさらに、この発明によれば、クサビ
は、前進時及び後退時のいずれにあっても、その配在位
置が上下方向に変化されず、従って、特に、ハンマ打撃
でクサビを前進状態におくような場合に、クサビを手指
で支えるような操作を不要にして所謂操作性に優れるこ
とになる利点もある。
Furthermore, according to the present invention, the distribution position of the wedge does not change in the vertical direction during forward movement and backward movement, and therefore the wedge is advanced by hammering. In this case, there is also an advantage that the so-called operability is excellent because the operation of supporting the wedge with fingers is unnecessary.

【図面の簡単な説明】[Brief description of drawings]

【図1】この発明の一実施例に係る支保工における大引
受け構造の利用状態を一部断面で示す部分正面図であ
る。
FIG. 1 is a partial front view showing, in a partial cross-section, a utilization state of a large catching structure in a supporting work according to an embodiment of the present invention.

【図2】大引受け部材を一部断面で示す正面図である。FIG. 2 is a front view showing the large catch member in a partial cross section.

【図3】大引受け部材を示す側面図である。FIG. 3 is a side view showing a large catch member.

【図4】図2中のX−X線で示す大引受け部材の横断面
図である。
FIG. 4 is a cross-sectional view of the large catch member taken along the line XX in FIG.

【図5】大引受け部材を収縮した状態を一部破断して示
す部分縦断面図である。
FIG. 5 is a partial vertical cross-sectional view showing a partially retracted state of the large catch member in a contracted state.

【符号の説明】[Explanation of symbols]

1 支保杭 2 高さ調整部材 3 型枠 4 根太 5 大引 6 大引受け部材 10 基台 12 ガイド部 12a,12b 透孔 20 昇降体 21 本体部 21a,21b 主孔 21c 副孔 22 大引受部 30 クサビ 33 尖端側頚部 34 基端側頚部 1 Support Pile 2 Height Adjusting Member 3 Form 4 4 joist 5 Large Pull 6 Large Pulling Member 10 Base 12 Guides 12a, 12b Through Hole 20 Lifting Body 21 Main Body 21a, 21b Main Hole 21c Sub Hole 22 Large Pulling Section 30 Wedge 33 Apical neck 34 Proximal neck

Claims (5)

【特許請求の範囲】[Claims] 【請求項1】 下端が支保杭の上端等に配設の高さ調整
部材に連結されながら上端で型枠の下面に根太の配在下
に隣設される大引を支持する大引受け部材を有してな
り、該大引受け部材が高さ調整部材に連結される基台
と、該基台の外周側に昇降可能に介装され大引を支持す
る昇降体と、上記基台及び昇降体に横方向から出没可能
に連繋されるクサビと、を有してなる支保工における大
引受け構造において、基台を構成するガイド部の外周側
に昇降体を構成し筒状に形成された本体部が昇降可能に
介装されてなる一方で、ガイド部の横方向の中央部にク
サビを挿通させる透孔が開穿されてなり、本体部の横方
向の中央部に上記透孔に照準されるように形成されてク
サビを挿通させる一対の主孔が開穿されてなると共に該
各主孔の上端に連通して該主孔より細幅寸法に形成され
ながら上方に適宜の長さに延在される一対の副孔が開穿
されてなり、クサビが上記副孔より細幅となるように形
成された尖端側頚部及び基端側頚部を有してなり、クサ
ビの後退時に尖端側頚部及び基端側頚部が上記各副孔内
に臨在されて昇降体が基台に対して下降されるように形
成されてなる支保工における大引受け構造
1. A large pulling receiving member for supporting a large pulling which is adjacently provided under the distribution of joists on the lower surface of the formwork at the upper end while the lower end is connected to the height adjusting member disposed at the upper end of the support pile or the like. And a base for which the large catch member is connected to the height adjusting member, an elevating body for supporting the large draw which is vertically movable on the outer periphery of the base, and the base and the elevating body. In a large undercarriage structure in a supporting work that has a wedge that is connected so as to be able to project and retract from the lateral direction, in a main body formed in a tubular shape that constitutes an elevating body on the outer peripheral side of the guide part that constitutes the base. While being inserted so that it can be raised and lowered, a through hole for inserting wedges is opened in the lateral center of the guide part so that the through hole is aimed at the lateral center of the body part. A pair of main holes formed on the upper surface for inserting wedges, and connected to the upper ends of the main holes. A pair of sub-holes, which are formed to have a smaller width than the main hole and extend upward with a proper length, are opened, and the wedge side is formed to have a narrower width than the sub-hole. It has a cervical part and a proximal end cervical part, and is formed so that when the wedge retreats, the apical side cervical part and the proximal end cervical part are present in each of the sub-holes and the elevating body is lowered with respect to the base. Large undertaking structure for support
【請求項2】 ガイド部が本体部に相似する筒状に形成
されてなることを特徴とする請求項1の支保工における
大引受け構造
2. A large undercarriage structure for supporting work according to claim 1, wherein the guide portion is formed in a cylindrical shape similar to the main body portion.
【請求項3】 副孔がその上下方向の長さをクサビの体
高以上とするように設されてなることを特徴とする請求
項1の支保工における大引受け構造
3. The large undercarriage structure for supporting work according to claim 1, wherein the auxiliary hole is provided so that its vertical length is equal to or greater than the height of the wedge.
【請求項4】 昇降体を構成する大引受部が大引の収容
を許容する角U字状の断面を有する樋状に形成されてな
ることを特徴とする請求項1の支保工における大引受け
構造
4. The large undercarriage in the support work according to claim 1, wherein the large overhanging portion forming the lifting body is formed in a gutter shape having a square U-shaped cross section which allows the accommodation of the large updraft. Construction
【請求項5】 クサビが大引の延在方向を横切る方向に
沿って出没可能とされてなることを特徴とする請求項1
の支保工における大引受け構造
5. The wedge is capable of appearing and retracting along a direction transverse to the extending direction of the Daihiki.
Undertaking structure for supporting work
JP6197804A 1994-07-29 1994-07-29 Sleeper receiving structure in timbering Pending JPH0842139A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP6197804A JPH0842139A (en) 1994-07-29 1994-07-29 Sleeper receiving structure in timbering

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP6197804A JPH0842139A (en) 1994-07-29 1994-07-29 Sleeper receiving structure in timbering

Publications (1)

Publication Number Publication Date
JPH0842139A true JPH0842139A (en) 1996-02-13

Family

ID=16380631

Family Applications (1)

Application Number Title Priority Date Filing Date
JP6197804A Pending JPH0842139A (en) 1994-07-29 1994-07-29 Sleeper receiving structure in timbering

Country Status (1)

Country Link
JP (1) JPH0842139A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2006200162A (en) * 2005-01-19 2006-08-03 Horii Engineering Kk Jack base and method of constructing form timbering
JP2020533506A (en) * 2017-09-12 2020-11-19 イアヴィラール ピーティーワイ リミティッド Building construction method

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2006200162A (en) * 2005-01-19 2006-08-03 Horii Engineering Kk Jack base and method of constructing form timbering
JP4623570B2 (en) * 2005-01-19 2011-02-02 ホリー株式会社 Construction method of jack base and formwork support
JP2020533506A (en) * 2017-09-12 2020-11-19 イアヴィラール ピーティーワイ リミティッド Building construction method

Similar Documents

Publication Publication Date Title
US8348221B2 (en) Formwork system for constructing a structural concrete floor with projecting floor beams
US20040211147A1 (en) Building construction shores
JP6532908B2 (en) Construction method of column cutting beam
CN205558262U (en) Floor concrete form strutting arrangement
JP6899571B1 (en) Abdominal upright correction jig and mountain retaining wall construction method
JPH0842139A (en) Sleeper receiving structure in timbering
JP6076271B2 (en) Caisson press-fitting device and caisson press-fitting method
JP3072176B2 (en) Jack for construction work
JP2741259B2 (en) Reverse construction method and multifunctional work floor using multifunctional work floor
KR20090107472A (en) A sheet pile pulling apparatus
JP3518308B2 (en) Basic structure of cylindrical tower structure
JP3981469B2 (en) Construction method of concrete structure
JP3387915B1 (en) Push-pull device for arch ring construction by lowering method and arch ring construction method by lowering method using the push-pull device
CN116254888A (en) Synchronous deviation correcting construction method for inserting and driving PHC inclined piles with ultra-large diameter
CN220847580U (en) Auxiliary device is pour to foundation ditch crown beam
CN218406791U (en) Sleeve type precast concrete wire pole
KR960016752B1 (en) Apparatus for forcing piles out of the ground
JP2966765B2 (en) Underground construction members burying method
JPH012994A (en) Tower crane for construction of RC high-rise buildings
JPH11210224A (en) Self-lifting type form device
CN214116595U (en) Mole type taper locking sleeve die capable of rapidly withdrawing die
CN218234298U (en) Scaffold connecting structure for constructional engineering
CN221919567U (en) High-rise building vertical component cuts, rises and entangles device of toppling and prevent toppling
CN213448504U (en) A construction platform for foundation ditch crown beam upper portion
CN220767754U (en) Auxiliary device for pushing construction of lower-bearing steel truss arch bridge

Legal Events

Date Code Title Description
A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20040113

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20040203

A02 Decision of refusal

Free format text: JAPANESE INTERMEDIATE CODE: A02

Effective date: 20040615