JPH08333723A - Manufacture of precast concrete floor slab and connecting method thereof - Google Patents

Manufacture of precast concrete floor slab and connecting method thereof

Info

Publication number
JPH08333723A
JPH08333723A JP13922695A JP13922695A JPH08333723A JP H08333723 A JPH08333723 A JP H08333723A JP 13922695 A JP13922695 A JP 13922695A JP 13922695 A JP13922695 A JP 13922695A JP H08333723 A JPH08333723 A JP H08333723A
Authority
JP
Japan
Prior art keywords
floor slab
slabs
precast floor
slab
coupler
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP13922695A
Other languages
Japanese (ja)
Inventor
Junichiro Nakahara
淳一郎 中原
Mitsuharu Mikoshiba
光春 御子柴
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Yokogawa Construction Co Ltd
Original Assignee
Yokogawa Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Yokogawa Construction Co Ltd filed Critical Yokogawa Construction Co Ltd
Priority to JP13922695A priority Critical patent/JPH08333723A/en
Publication of JPH08333723A publication Critical patent/JPH08333723A/en
Pending legal-status Critical Current

Links

Abstract

PURPOSE: To make the positional adjustment of connecting part of a threaded main reinforcement embedded in a precast concrete floor slab so as to be correctly performable at all times, and to reduce the width of a connecting joint part as well as to make the connection by a screw thread achievable. CONSTITUTION: Those of threaded main reinforcements 15 of plural pieces of precast concrete floor slabs to be connected are set up as being pierced through three forms 11, 12 and 13 of respective floor slabs in a state of being continued. After concrete 16 is placed and cured in these forms 11, 12 and 13, the main reinforcement 15 to be situated in a void space among respective floor slabs is cut off and temporarily placed there.

Description

【発明の詳細な説明】Detailed Description of the Invention

【0001】[0001]

【産業上の利用分野】本発明は、主に橋梁または道路用
の路面として使用するプレキャスト床版の製作方法およ
び、そのプレキャスト床版の主筋の連結方法に関するも
のである。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a method for producing a precast floor slab mainly used as a road surface for a bridge or a road, and a method for connecting main bars of the precast floor slab.

【0002】[0002]

【従来の技術】使用中の橋梁または道路の床版取り替え
工事においては、車線規制を伴う分割施工により、床版
を取り替えて行くことになるが、この場合縮小車線(縮
小幅員)で交通を開放しており、早期に工事を完了させ
る必要がある。したがって工程短縮を図るため、新床版
にはプレキャスト床版を採用する事が多い。
2. Description of the Related Art When slab replacement work on a bridge or road is in use, the slabs will be replaced by divisional construction with lane restrictions. In this case, traffic is released in a reduced lane (reduced width). It is necessary to complete the construction early. Therefore, precast floor slabs are often used as new floor slabs in order to shorten the process.

【0003】図1の (a)(b)(c) は、この床版取り替
え工事の一例を示す工程説明図であり、片側3車線を有
する橋梁上の床版取り替えの事例である。図中1は橋梁
の橋桁、2は橋桁1上の床版、3は道路中央の分離帯に
設けたブロック、4はそのブロック3上に設置したクレ
ーン軌条、5は道路の外側に設置したクレーン軌条、6
は軌条4,5間にかけ渡したクレーン、7は吊り下げ運
搬用のフックである。
1A, 1B, and 1C are process explanatory views showing an example of this floor slab replacement work, and are examples of floor slab replacement on a bridge having three lanes on each side. In the figure, 1 is a bridge girder of a bridge, 2 is a floor slab on the bridge girder, 3 is a block provided in a separation zone at the center of the road, 4 is a crane rail installed on the block 3, and 5 is a crane installed outside the road. Rail, 6
Is a crane spanning between rails 4 and 5, and 7 is a hook for suspending and carrying.

【0004】床版2の取り替えを行うには、図1の
(a)に示すように、まず3車線の外側の1車線を通行
止めとして、その部分の旧床版を取り外すと共に新床版
8を敷設する。つぎに図1の(b)に示すように、中央
の1車線を通行止めとして、その部分の旧床版を取り外
すと共に新床版9を敷設し、最後に図1の(c)に示す
ように、内側の1車線を通行止めとして、その部分の旧
床版を取り外すと共に新床版10を敷設する。
In order to replace the floor slab 2, as shown in FIG. 1 (a), first, one lane outside the three lanes is blocked, the old slab of that portion is removed, and the new slab 8 is removed. Lay. Next, as shown in FIG. 1 (b), the first lane in the center is blocked, the old slab of that part is removed, and a new slab 9 is laid, and finally, as shown in FIG. 1 (c). , The inner one lane is blocked, the old slab of that part is removed, and the new slab 10 is laid.

【0005】上述のように、取り替えた新床版8,9,
10は、それぞれ連結して床版として一体化する必要が
ある。従来この連結方法としては、主筋を重ね継手によ
り連結すると共に、配力筋等を配置し、現場打ちコンク
リートにより一体化する方法、または、鉄筋による継ぎ
手は行わず、プレストレス力のみにより一体化する方法
等が用いられていた。
As described above, the new slabs 8, 9
It is necessary to connect 10 to be integrated as a floor slab. Conventionally, as this connection method, main bars are connected by lap joints, and distribution bars, etc. are arranged and integrated by cast-in-place concrete, or joints by reinforcing bars are not used and they are integrated only by prestressing force. The method etc. were used.

【0006】[0006]

【発明が解決しようとする課題】しかしながら上述した
従来の連結方法の前者は、現場配筋作業および現場打ち
コンクリートの施工面積が多いため、それが工期および
品質と施工の面でマイナスとなる。この主筋の重ね継ぎ
による欠点を除くため主筋にねじを形成して、対向する
主筋をカプラー等によって螺合連結する方法も考えられ
るが、従来のプレキャスト床版の主筋の位置は施工上ば
らつきがあるため、カプラー等による螺合連結はむずか
しいという問題点があった。
However, the former of the above-mentioned conventional connecting methods has a large construction area for on-site reinforcement work and cast-in-place concrete, which is negative in terms of construction period, quality and construction. It is possible to form a screw on the main bar to eliminate the defect due to the lap joint of the main bar, and connect the opposing main bars by screwing with a coupler etc., but the position of the main bar of the conventional precast floor slab varies in construction. Therefore, there is a problem that it is difficult to screw and connect with a coupler or the like.

【0007】また後者の場合は、目地部に発生する曲げ
モーメントに対してコンクリートに引っ張り力が発生し
ないようフルプレストレスを導入する必要があるため、
主筋方向にPC鋼材を密に配置しなければならないか
ら、多くの工数がかかるという問題点があった。
In the latter case, it is necessary to introduce full prestress to prevent the tensile force from being generated in the concrete against the bending moment generated in the joints.
Since the PC steel materials must be densely arranged in the direction of the main bars, there is a problem in that many man-hours are required.

【0008】[0008]

【課題を解決するための手段】上述の問題点を解決する
ため本発明においては、連結すべき複数のプレキャスト
床版を製造するにあたっては各床版の型枠を貫通してね
じ付き主筋を連続して配置した状態で、各型枠内にコン
クリートを打設養生した後、各床版間の空所に位置する
前記主筋を切断して仮り置きするようにしてプレキャス
ト床版を製作する。
In order to solve the above-mentioned problems, in the present invention, when manufacturing a plurality of precast floor slabs to be connected, a threaded main bar is continuously penetrated through the form of each floor slab. After the concrete is placed and cured in each of the molds, the precast floor slab is manufactured by cutting and temporarily placing the main bar located in the space between the floor slabs.

【0009】また前記した第1発明の方法によって製作
したプレキャスト床版に使用時においてプレストレスを
導入する場合は、仮り置きしてある同じグループのプレ
キャスト床版にも略同時に同方向のプレストレスを導入
しておくようにするのがよい。
When introducing prestress to the precast floor slab produced by the method of the first invention at the time of use, prestress slabs of the same group, which are temporarily placed, are prestressed in the same direction at substantially the same time. It is better to install it.

【0010】また本発明のプレキャスト床版の主筋の連
結方法は、前記した第1,第2発明の方法によって製作
した各プレキャスト床版を製作時の関係位置に配置し
て、対向するねじ付き主筋の一方にロックナットとカプ
ラーを螺合すると共に、他方のねじ付き主筋にロックナ
ットを螺合して置き、一方のねじ付き主筋に螺合したカ
プラーを他方のねじ付き主筋にも略半分螺合した状態
で、このカプラーの両側のロックナットをカプラーに締
めつけてロックする。
Further, the method of connecting the main bars of the precast floor slab of the present invention is such that the precast floor slabs manufactured by the above-mentioned first and second inventions are arranged at the relevant positions at the time of manufacturing, and the main bars with screws facing each other are arranged. The lock nut and coupler are screwed together on one side, and the lock nut is screwed on the other threaded main bar, and the coupler screwed onto one threaded main bar is screwed onto the other threaded main bar approximately half. Then, lock the lock nuts on both sides of this coupler by tightening them on the coupler.

【0011】[0011]

【作用】上述のように本発明においては、連結すべき複
数のプレキャスト床版のねじ付き主筋を連続した状態で
各床版の型枠を貫通して配置してから、各型枠内にコン
クリートを打設養生した後、各床版間の空所に位置する
前記主筋を切断して仮り置きするようにしてプレキャス
ト床版を製作するようにしたから、隣接した位置に敷設
されるプレキャスト床版の製作時期が一致するため、隣
接するプレキャスト床版の材令が等しくなって、コンク
リートの乾燥収縮およびクリープ現象もすべて同じにな
る。
As described above, in the present invention, the threaded main bars of a plurality of precast floor slabs to be connected are continuously arranged so as to pass through the formwork of each slab, and then the concrete is placed in each formwork. After casting and curing, the precast floor slabs were laid at adjacent positions because the precast floor slabs were manufactured by cutting and temporarily placing the main bars located in the spaces between the floor slabs. Since the production times of the two are the same, the ages of the adjacent precast floor slabs are the same, and the drying shrinkage and creep phenomenon of the concrete are all the same.

【0012】したがって、上述のようにして製作した隣
接するプレキャスト床版は、常に同じような状態におか
れる。しかもこのプレキャスト床版内に埋設されるねじ
付き主筋は、隣接する床版を貫通する連続主筋として設
けられ、床版のコンクリートが硬化した後、各床版間の
空所に位置する部分を切断するようにしたから、後にプ
レキャスト床版を定位置に敷設した場合に、この隣接す
るねじ付き主筋が常にずれることなく、正しく整合す
る。したがって後述するねじによる主筋の接続を無理な
く行うことができる。
Therefore, the adjacent precast floor slabs produced as described above are always placed in the same state. Moreover, the threaded main bar embedded in this precast floor slab is provided as a continuous main bar that penetrates the adjacent floor slabs, and after the concrete of the floor slabs hardens, cut the part located in the space between each floor slab. Therefore, when the precast floor slab is laid in place later, the adjacent threaded main bars do not always shift and are correctly aligned. Therefore, it is possible to easily connect the main bars with the screws described later.

【0013】また前記した方法によって製作したプレキ
ャスト床版に使用時においてプレストレスを導入する場
合は、仮り置きしてあるプレキャスト床版にも略同時に
プレストレスを導入しておくようにすれば、プレストレ
スによるプレキャスト床版の変形も隣接する床版間にお
いて差がなくなる。
When prestress is introduced into the precast floor slab manufactured by the above-mentioned method during use, the prestress is introduced into the precast floor slab temporarily placed at about the same time. The deformation of the precast floor slab due to stress is also the same between adjacent floor slabs.

【0014】さらに前記した方法によって製作したプレ
キャスト床版の主筋を連結する場合に、本発明において
は、各プレキャスト床版を製作時の関係位置に配置し
て、対向するねじ付き主筋の一方にロックナットとカプ
ラーを螺合すると共に、他方のねじ付き主筋にロックナ
ットを螺合して置き、一方のねじ付き主筋に螺合したカ
プラーを他方のねじ付き主筋にも略半分螺合した状態
で、このカプラーの両側のロックナットをカプラーに締
めつけるようにしたから、従来の主筋の重ね継ぎ手によ
る連結方法と比べて、その連結に要する床版間の連結用
目地部の幅を著しく狭くすることができる。実例とし
て、例えば従来の重ね継ぎ手による場合は60cm以上の
目地の幅を要したものが、本発明によれば21cmの幅で
足りるようになる。
Further, in the case of connecting the main bars of the precast floor slab manufactured by the above-mentioned method, in the present invention, each precast floor slab is arranged at a related position at the time of manufacturing and locked to one of the opposing threaded main bars. With the nut and coupler screwed together, the lock nut is screwed onto the other threaded main bar, and the coupler screwed onto the one threaded main bar is screwed onto the other threaded main bar almost half as well. Since the lock nuts on both sides of this coupler are tightened to the coupler, the width of the joint for connecting the floor slabs required for the connection can be significantly narrowed compared to the conventional connecting method using the lap joint of the main bar. . As an example, a conventional lap joint requires a joint width of 60 cm or more, but according to the present invention, a width of 21 cm is sufficient.

【0015】したがって本発明によれば、床版間の連結
用目地部の打設コンクリートが著しく少なくなる上に、
重ね継ぎ手幅を少なくする際に必要とする溶接作業が不
要となるから、現場での作業量が少なくなると共に、作
業工種も少なくなって省力化を促進することができる。
またねじによる連結作業は熟練を要せず誰にでもできる
上に、施工精度の確保および品質管理も容易になる。ま
た本発明によれば、溶接作業が不要になると共に、目地
部におけるコンクリートの打設面積が少なくなることか
ら、雨天においても少ない設備と対策で作業が可能にな
る。
Therefore, according to the present invention, the amount of cast concrete at the joints for connection between floor slabs is significantly reduced, and
Since the welding work required when reducing the width of the lap joint is not necessary, the amount of work at the site is reduced, and the work types are also reduced, so that labor saving can be promoted.
In addition, anyone can perform connection work using screws without requiring skill, and it is easy to secure construction accuracy and quality control. Further, according to the present invention, the welding work becomes unnecessary and the area where the concrete is placed in the joint portion is reduced. Therefore, even in rainy weather, the work can be performed with a small amount of equipment and measures.

【0016】[0016]

【実施例】以下、図面について本発明の実施例を説明す
る。図2および図3は本発明のプレキャスト床版の製作
方法を示すもので、図中11は前記した図1の新床版8
に相当するプレキャスト床版用の型枠、12は図1の新
床版9に相当するプレキャスト床版用の型枠、13は図
1の新床版10に相当するプレキャスト床版用の型枠、
14は型枠移動用の架台である。
Embodiments of the present invention will be described below with reference to the drawings. 2 and 3 show a method for manufacturing the precast floor slab of the present invention, in which 11 is the new floor slab 8 of FIG.
Formwork for a precast floor slab corresponding to No. 12, 12 is a formwork for a precast slab corresponding to the new slab 9 in FIG. 1, and 13 is a formwork for a precast slab corresponding to the new slab 10 in FIG. ,
Reference numeral 14 is a mount for moving the formwork.

【0017】本実施例においては、架台14上に、型枠
11,12,13を所定の位置に配置すると共に、これ
ら連結すべき複数のプレキャスト床版のねじ付き主筋
(ねじふし鉄筋)15を一本物とした状態で、図4の
(a)に示すように、各床版の型枠11,12,13を
貫通して配置してから、図4の(b)示すように、各型
枠11,12,13内にコンクリート16を打設して、
図5の (a)(b) で示すように、打設したコンクリート
16を養生した後、図6の(b)に示すように、各床版
8,9,10間の空所に位置する前記主筋15を所定の
位置で切断して仮り置きするようにする。
In this embodiment, the molds 11, 12 and 13 are arranged on the pedestal 14 at predetermined positions, and a plurality of threaded main bars (screw bars) 15 of the precast floor slabs to be connected are arranged. As shown in FIG. 4 (a), the molds 11, 12 and 13 of the floor slabs are arranged so as to pass through the molds in a single state, and then each mold is placed as shown in FIG. 4 (b). Concrete 16 is placed in the frames 11, 12, and 13,
After curing the cast concrete 16 as shown in FIGS. 5 (a) and 5 (b), it is located in the space between the floor slabs 8, 9 and 10 as shown in FIG. 6 (b). The main bar 15 is cut at a predetermined position and temporarily placed.

【0018】図2の(a)〜(f)は、プレキャスト床
版の製作サイクルの一例を床版8について示すもので、
先ず架台14上に、床版8用の型枠11を底型枠11
a,側型枠11b,11cによって結構し、この型枠1
1および図3に示した型枠12,13を貫通してねじ付
き主筋15を所定の位置に配置すると共に、これらの主
筋15を配力筋17によって連結し、その後コンクリー
トを打設して所定の期間養生する。
2 (a) to 2 (f) show an example of the production cycle of the precast floor slab for the floor slab 8.
First, on the pedestal 14, the formwork 11 for the floor slab 8 is placed on the bottom formwork 11.
a, the side molds 11b, 11c, and the mold 1
1 and FIG. 3, the threaded main bars 15 are arranged at predetermined positions by penetrating the molds 12 and 13, and the main bars 15 are connected by the force distribution bars 17, and then concrete is poured to the predetermined shape. Be cured for a period of.

【0019】つぎに図2の(b)に示すように、養生が
完了した床版8から、両側枠11b,11cを取り外し
た状態で、底型枠11aと共に床版8を架台14上を
(a)の矢印Aのように移動させて、(b)の位置にセ
ットする。ついで(c)に示すように、架台14上の床
版8との隣接位置に、底型枠11aと側型枠11cをセ
ットする。
Next, as shown in FIG. 2B, the floor slab 8 is placed on the pedestal 14 together with the bottom mold 11a in a state where both side frames 11b and 11c are removed from the floor slab 8 which has been completely cured. It is moved as shown by arrow A in a) and set at the position of (b). Then, as shown in (c), the bottom formwork 11a and the side formwork 11c are set at positions adjacent to the floor slab 8 on the pedestal 14.

【0020】つぎに図2の(d)に示すように、型枠1
1内に主筋15と連結筋17よりなる鉄筋を配置すると
共に、床版8の側面8aに剥離剤を塗布してから、
(e)に示すように型枠11内にコンクリート16を打
設する。ついで(f)に示すように、打設コンクリート
の養生が完了したならば、前に製作した床版(二点鎖
線)8を架台14上より外して仮り置きすると共に、実
線で示す床版8を矢印Bのように、(b)に示す状態に
して、前記操作を繰り返すようにする。
Next, as shown in FIG. 2D, the mold 1
After arranging the reinforcing bar consisting of the main bar 15 and the connecting bar 17 in 1 and applying the release agent to the side surface 8a of the floor slab 8,
As shown in (e), concrete 16 is placed in the mold 11. Then, as shown in (f), when the curing of the cast concrete is completed, the floor slab (two-dot chain line) 8 produced previously is removed from the pedestal 14 and temporarily placed, and at the same time, the floor slab 8 shown by the solid line is shown. Is set to the state shown in (b) as indicated by arrow B, and the above operation is repeated.

【0021】また前記した方法によって製作したプレキ
ャスト床版8,9,10に、使用時においてプレストレ
スを導入する場合は、図7に示すように、仮り置きして
あるプレキャスト床版8,9,10にも略同時に、緊張
索18によってプレストレスを導入しておくようにす
る。
When prestress is introduced into the precast floor slabs 8, 9 and 10 produced by the above-described method during use, as shown in FIG. 7, the precast floor slabs 8, 9 and 10 are temporarily placed. At about the same time as in 10, the prestress is introduced by the tension cord 18.

【0022】また上述の方法によって製作した各プレキ
ャスト床版8,9,10の主筋15を連結する方法とし
ては、各プレキャスト床版8,9,10を製作時の関係
位置に配置して、図8に示すように、対向するねじ付き
主筋15の一方(図8の右側の主筋15)にロックナッ
ト19とカプラー20を螺合すると共に、他方のねじ付
き主筋15(図8の左側の主筋15)にロックナット1
9を螺合して置き、図8の下方に示したように、一方の
ねじ付き主筋15に螺合したカプラー20を他方のねじ
付き主筋15にも略半分螺合した状態で、このカプラー
20の両側のロックナット19をカプラー20に締めつ
けてロックする。なおこのねじによる締結後、カプラー
20に設けた孔20aよりグラウトを注入する。
Further, as a method of connecting the main bars 15 of the precast floor slabs 8, 9 and 10 produced by the above-mentioned method, the precast floor slabs 8, 9 and 10 are arranged at the relevant positions at the time of production and As shown in FIG. 8, the lock nut 19 and the coupler 20 are screwed into one of the opposing threaded main bars 15 (the right main bar 15 in FIG. 8) and the other threaded main bar 15 (the left main bar 15 in FIG. 8). ) To lock nut 1
9 is screwed together, and as shown in the lower part of FIG. 8, the coupler 20 screwed to one threaded main bar 15 is also screwed to the other threaded main bar 15 in a substantially half way. Tighten the lock nuts 19 on both sides of the connector to the coupler 20 to lock. After fastening with this screw, grout is injected through a hole 20a provided in the coupler 20.

【0023】図9の(a)〜(e)は、上述した本発明
によって、図1の(a)〜(c)の手順で施工するプレ
キャスト床版の取り替え工法を示すものである。すなわ
ち(a)は、旧床版を撤去して、その後へ新床版8を敷
設し、その外側部の拡幅床版部21aに間詰めコンクリ
ートを打設して、(b)に示すように、拡幅床版21を
形成する。
FIGS. 9 (a) to 9 (e) show a method of replacing the precast floor slab according to the present invention described above, which is carried out by the procedure of FIGS. 1 (a) to 1 (c). That is, in (a), the old floor slab is removed, the new floor slab 8 is laid after that, and the widening floor slab portion 21a on the outer side of the old floor slab is poured with the filling concrete, as shown in (b). The widening floor slab 21 is formed.

【0024】つぎに(a)の旧床版2を撤去すると共
に、その後へ(b)に示すように、新床版9を設置し、
新床版8,9の間の対向する主筋15同士を図8に示し
たカプラー20によって螺合連結すると共に、そのカプ
ラー20の両側をロックナット19によってロックす
る。また主筋15と同様に、床版8,9に貫通したPC
鋼棒22同士もねじによって連結する。そしてこの床版
8,9間の目地部23aに膨張コンクリートを打設する
と共に、PC鋼棒22に矢印Cで示すように一次プレス
トレスを導入する。また(c)に示すように、目地床版
23を形成した後、前記PC鋼棒22に矢印Dで示すよ
うに、隣接している旧床版を撤去した後、二次プレスト
レスを導入する。
Next, while removing the old floor slab 2 of (a), a new floor slab 9 is installed thereafter as shown in (b),
The opposing main bars 15 between the new slabs 8 and 9 are screwed and coupled by the coupler 20 shown in FIG. 8, and both sides of the coupler 20 are locked by the lock nuts 19. Also, like the main bar 15, a PC that penetrates the floor slabs 8 and 9
The steel rods 22 are also connected by screws. Then, expansive concrete is placed in the joint portion 23a between the floor slabs 8 and 9, and a primary prestress is introduced into the PC steel rod 22 as shown by an arrow C. Further, as shown in (c), after forming the joint floor slab 23, after removing the adjacent old floor slab to the PC steel rod 22 as shown by the arrow D, the secondary prestress is introduced. .

【0025】つぎに(d)に示すように、新床版9に隣
接している旧床版を撤去した位置へ新床版10を設置
し、新床版9,10間の主筋15およびPC鋼棒をカプ
ラー20によって連結し、前記と同様に(e)に示すよ
うに、床版9,10間に目地床版24を形成すると共
に、PC鋼棒22に矢印Eのようにプレストレスを導入
する。
Next, as shown in (d), the new floor slab 10 is installed at a position where the old floor slab adjacent to the new floor slab 9 is removed, and the main bar 15 and the PC between the new floor slabs 9 and 10 are installed. The steel rods are connected by the coupler 20, and the joint floor slab 24 is formed between the floor slabs 9 and 10 as shown in (e) in the same manner as described above, and the PC steel rod 22 is prestressed as indicated by the arrow E. Introduce.

【0026】[0026]

【発明の効果】上述のように本発明においては、連結す
べき複数のプレキャスト床版8,9,10のねじ付き主
筋15を連続した状態で各床版8,9,10の型枠1
1,12,13を貫通して配置してから、各型枠11,
12,13内にコンクリート16を打設養生した後、各
床版間の空所に位置する前記主筋15を切断して仮り置
きするようにしてプレキャスト床版8,9,10を製作
するようにしたから、隣接した位置に敷設されるプレキ
ャスト床版の製作時期が一致するため、隣接するプレキ
ャスト床版の材令が等しくなって、コンクリートの乾燥
収縮およびクリープ現象もすべて同じになる。
As described above, according to the present invention, the formwork 1 of each floor slab 8, 9, 10 is continuously connected with the threaded main bar 15 of the plurality of precast floor slabs 8, 9, 10 to be connected.
After arranging through 1,12,13, each form 11,
After the concrete 16 is set and cured in the 12, 13, the precast floor slabs 8, 9 and 10 are manufactured by cutting and temporarily placing the main bar 15 located in the space between the floor slabs. Therefore, since the production times of the precast slabs laid adjacent to each other are the same, the ages of the adjacent precast slabs are the same, and the drying shrinkage and the creep phenomenon of the concrete are all the same.

【0027】したがって上述のようにして製作した隣接
するプレキャスト床版は、常に同じような状態におかれ
る。しかもこのプレキャスト床版内に埋設されるねじ付
き主筋15は、隣接する床版を貫通する連続主筋として
設けられ、床版のコンクリートが硬化した後、各床版間
の空所に位置する部分を切断するようにしたから、後に
プレキャスト床版を定位置に敷設した場合に、この隣接
するねじ付き主筋15が常にずれることなく、正しく整
合する。したがって後述するねじによる主筋15の接続
を無理なく行うことができるようになる。
Therefore, the adjacent precast floor slabs produced as described above are always placed in the same state. Moreover, the threaded main bar 15 embedded in this precast floor slab is provided as a continuous main bar that penetrates the adjacent floor slabs, and after the concrete of the floor slabs hardens, the portion located in the space between the floor slabs is Since it is cut, when the precast floor slab is laid in place later, the adjacent threaded main bars 15 are always aligned without misalignment. Therefore, it becomes possible to connect the main bar 15 with a screw described later without difficulty.

【0028】また前記した方法によって製作したプレキ
ャスト床版に使用時においてプレストレスを導入する場
合は、仮り置きしてあるプレキャスト床版にも略同時に
プレストレスを導入しておくようにすれば、プレストレ
スによるプレキャスト床版の変形も隣接する床版間にお
いて差がなくなる。
When prestress is introduced into the precast floor slab manufactured by the above-mentioned method during use, the prestress is introduced into the temporarily placed precast floor slab at substantially the same time. The deformation of the precast floor slab due to stress is also the same between adjacent floor slabs.

【0029】さらに前記した方法によって製作したプレ
キャスト床版の主筋15を連結する場合に、本発明にお
いては、各プレキャスト床版を製作時の関係位置に配置
して、対向するねじ付き主筋15の一方にロックナット
19とカプラー20を螺合すると共に、他方のねじ付き
主筋15にロックナット19を螺合して置き、一方のね
じ付き主筋15に螺合したカプラー20を他方のねじ付
き主筋15にも略半分螺合した状態で、このカプラー2
0の両側のロックナット19をカプラー20に締めつけ
るようにしたから、従来の主筋の重ね継ぎ手による連結
方法と比べて、その連結に要する床版間の連結用目地部
の幅を著しく狭くすることができる。実例として、例え
ば従来の重ね継ぎ手による場合は60cm以上の目地部の
幅を要したものが、本発明によれば21cmの幅で足りる
ようになる。
Further, in the case of connecting the main bars 15 of the precast floor slabs manufactured by the above-mentioned method, in the present invention, one of the facing main bars 15 with screws is arranged by arranging the respective precast floor slabs at the relevant positions at the time of manufacturing. The lock nut 19 and the coupler 20 are screwed together, the lock nut 19 is screwed on the other threaded main bar 15, and the coupler 20 screwed onto one threaded main bar 15 is attached to the other threaded main bar 15. This coupler 2 with almost half screwed
Since the lock nuts 19 on both sides of 0 are fastened to the coupler 20, it is possible to remarkably narrow the width of the joint for connecting the floor slabs required for the connection, as compared with the conventional connection method using the lap joint of the main bar. it can. By way of example, a conventional lap joint which requires a joint width of 60 cm or more, but a width of 21 cm is sufficient according to the present invention.

【0030】したがって本発明によれば、床版間の連結
用目地部の打設コンクリートが著しく少なくなる上に、
重ね継ぎ手幅を少なくする場合に必要とした溶接作業が
不要となるから、現場での作業量が少なくなると共に、
作業工種も少なくなって省力化を促進することができ
る。またねじによる連結作業は熟練を要せず誰れにでも
できる上に、施工精度の確保および品質管理も容易にな
る。また本発明によれば、溶接作業が不要になると共
に、目地部におけるコンクリートの打設面積が少なくな
ることから、雨天においても作業が可能になる等、本発
明によれば多くのすぐれた効果が得られる。
Therefore, according to the present invention, the amount of cast concrete at the joints for connection between floor slabs is significantly reduced, and
Since the welding work required when reducing the width of the lap joint is not necessary, the amount of work on site is reduced and
The number of work processes is reduced and labor saving can be promoted. In addition, the screw connection work can be done by anyone without requiring any skill, and the construction accuracy and quality control are facilitated. Further, according to the present invention, welding work becomes unnecessary, and since the area for placing concrete in the joints is reduced, it is possible to work even in rainy weather. can get.

【図面の簡単な説明】[Brief description of drawings]

【図1】(a)は、路面の床版取り替え工事の第1工程
を示す立面図であり、(b)は、その第2工程を示す立
面図であり、(c)は、その第3工程を示す立面図であ
る。
FIG. 1 (a) is an elevation view showing a first step of floor slab replacement work on a road surface, (b) is an elevation view showing a second step thereof, and (c) is an elevation view thereof. It is an elevation view showing a 3rd process.

【図2】(a)〜(f)は、プレキャスト床版の製作サ
イクルの一例を示す説明用側面図である。
2 (a) to (f) are explanatory side views showing an example of a production cycle of a precast floor slab.

【図3】プレキャスト床版の製作工程を示す正面図であ
る。
FIG. 3 is a front view showing a manufacturing process of a precast floor slab.

【図4】(a)(b)は、プレキャスト床版の製作工程
を示す平面図である。
4A and 4B are plan views showing a manufacturing process of a precast floor slab.

【図5】(a)(b)は、プレキャスト床版の製作工程
を示す平面図である。
5A and 5B are plan views showing a manufacturing process of a precast floor slab.

【図6】(a)(b)は、プレキャスト床版の製作工程
を示す平面図である。
6 (a) and 6 (b) are plan views showing a manufacturing process of a precast floor slab.

【図7】(a)は、仮り置き時にプレキャスト床版に道
路の長手方向のプレストレスを導入する状態を示す平面
図であり、(b)は、その側面図である。
FIG. 7 (a) is a plan view showing a state in which prestress in the longitudinal direction of the road is introduced into the precast floor slab when temporarily placed, and FIG. 7 (b) is a side view thereof.

【図8】プレキャスト床版に埋設したねじ付き主筋の連
結方法を示す断面図である。
FIG. 8 is a cross-sectional view showing a method of connecting threaded main bars embedded in a precast floor slab.

【図9】(a)〜(e)は、プレキャスト床版の取り替
え工法の工程説明図である。
9A to 9E are process explanatory views of a precast floor slab replacement construction method.

【符号の説明】[Explanation of symbols]

1 橋桁 2 床版 3 ブロック 4,5 クレーン軌条 6 クレーン 7 フック 8,9,10 新床版(プレキャスト床版、床版) 11,12,13 型枠 14 架台 15 ねじ付き主筋(主筋) 16 コンクリート 17 配力筋 18 緊張索 19 ロックナット 20 カプラー 21 拡幅床版 22 PC鋼棒 23,24 目地床版 1 Bridge girder 2 Floor slab 3 Block 4,5 Crane rail 6 Crane 7 Hook 8, 9, 10 New floor slab (precast floor slab, floor slab) 11, 12, 13 Formwork 14 Frame 15 Threaded main bar (main bar) 16 Concrete 17 Distribution Muscle 18 Tension Rope 19 Lock Nut 20 Coupler 21 Widening Floor Slab 22 PC Steel Rod 23, 24 Joint Floor Slab

Claims (3)

【特許請求の範囲】[Claims] 【請求項1】 連結すべき複数のプレキャスト床版を製
造するにあたっては各床版の型枠を貫通してねじ付き主
筋を連続して配置した状態で、各型枠内にコンクリート
を打設養生した後、各床版間の空所に位置する前記主筋
を切断して仮り置きするようにしたことを特徴とするプ
レキャスト床版の製作方法。
1. When producing a plurality of precast floor slabs to be connected, concrete is placed and cured in each form while the threaded main bars are continuously arranged through the form of each slab. After that, the method for producing a precast floor slab is characterized in that the main bar located in the space between the floor slabs is cut and temporarily placed.
【請求項2】 請求項1記載の方法によって製作したプ
レキャスト床版に使用時においてプレストレスを導入す
る場合は、仮り置きしてある同じグループのプレキャス
ト床版にも略同時に同方向のプレストレスを導入してお
くことを特徴とするプレキャスト床版の製作方法。
2. When introducing prestress to the precast floor slab produced by the method according to claim 1 during use, prestress slabs of the same group that are temporarily placed are also prestressed in the same direction at substantially the same time. A method of manufacturing a precast floor slab characterized by being introduced.
【請求項3】 請求項1,2記載の方法によって製作し
た各プレキャスト床版を製作時の関係位置に配置して、
対向するねじ付き主筋の一方にロックナットとカプラー
を螺合すると共に、他方のねじ付き主筋にロックナット
を螺合して置き、一方のねじ付き主筋に螺合したカプラ
ーを他方のねじ付き主筋にも略半分螺合した状態で、こ
のカプラーの両側のロックナットをカプラーに締めつけ
ることを特徴とするプレキャスト床版の連結方法。
3. Pre-cast floor slabs produced by the method according to claim 1 or 2 are arranged at a relative position at the time of production,
The lock nut and coupler are screwed onto one of the opposite threaded main bars, and the lock nut is screwed onto the other threaded main bar, and the coupler screwed onto one threaded main bar is attached to the other threaded main bar. A method for connecting precast floor slabs, characterized in that the lock nuts on both sides of this coupler are tightened to the coupler while being screwed in approximately half.
JP13922695A 1995-06-06 1995-06-06 Manufacture of precast concrete floor slab and connecting method thereof Pending JPH08333723A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP13922695A JPH08333723A (en) 1995-06-06 1995-06-06 Manufacture of precast concrete floor slab and connecting method thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP13922695A JPH08333723A (en) 1995-06-06 1995-06-06 Manufacture of precast concrete floor slab and connecting method thereof

Publications (1)

Publication Number Publication Date
JPH08333723A true JPH08333723A (en) 1996-12-17

Family

ID=15240436

Family Applications (1)

Application Number Title Priority Date Filing Date
JP13922695A Pending JPH08333723A (en) 1995-06-06 1995-06-06 Manufacture of precast concrete floor slab and connecting method thereof

Country Status (1)

Country Link
JP (1) JPH08333723A (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2007154544A (en) * 2005-12-06 2007-06-21 Ps Mitsubishi Construction Co Ltd Floor board structure using precast concrete plate
JP2007239228A (en) * 2006-03-06 2007-09-20 Pc Bridge Co Ltd Precast floor slab for floor slab replacing work of composite girder, bearing plate of this floor slab and replacing construction method of cast-in-place rc floor slab of composite girder
CN103362062A (en) * 2013-01-08 2013-10-23 韩志群 Connector girder
JP2014177767A (en) * 2013-03-13 2014-09-25 Kumagai Gumi Co Ltd Stepwise construction method of concrete precast floor slab for bridge
JP2015151768A (en) * 2014-02-14 2015-08-24 株式会社高速道路総合技術研究所 Change-over method of concrete slab for highway road, and change-over pc slab by the method
JP2021067052A (en) * 2019-10-21 2021-04-30 鹿島建設株式会社 Joining structure and joining method

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2007154544A (en) * 2005-12-06 2007-06-21 Ps Mitsubishi Construction Co Ltd Floor board structure using precast concrete plate
JP2007239228A (en) * 2006-03-06 2007-09-20 Pc Bridge Co Ltd Precast floor slab for floor slab replacing work of composite girder, bearing plate of this floor slab and replacing construction method of cast-in-place rc floor slab of composite girder
CN103362062A (en) * 2013-01-08 2013-10-23 韩志群 Connector girder
JP2014177767A (en) * 2013-03-13 2014-09-25 Kumagai Gumi Co Ltd Stepwise construction method of concrete precast floor slab for bridge
JP2015151768A (en) * 2014-02-14 2015-08-24 株式会社高速道路総合技術研究所 Change-over method of concrete slab for highway road, and change-over pc slab by the method
JP2021067052A (en) * 2019-10-21 2021-04-30 鹿島建設株式会社 Joining structure and joining method

Similar Documents

Publication Publication Date Title
US6857156B1 (en) Modular bridge structure construction and repair system
US4972537A (en) Orthogonally composite prefabricated structural slabs
US6588160B1 (en) Composite structural member with pre-compression assembly
JP5266291B2 (en) Construction method of bridge deck and joint structure of precast deck
US3577504A (en) Method of manufacturing a girder with a web of reinforced and/or prestressed concrete
KR100991869B1 (en) Single and continuous prestressed concrete girder bridge and the construction method
US20110194897A1 (en) Apparatus And Method For On Site Pouring Of Pre-Stressed Concrete Structures
JPH08333723A (en) Manufacture of precast concrete floor slab and connecting method thereof
KR100631029B1 (en) Precasted concrete plate assembly and the construction method using thereof
JPH11293629A (en) Cast-in-place concrete block construction
JP2948149B2 (en) Structure and construction method of concrete protection fence
CN214925420U (en) Concrete bridge deck slab prefabricated steel formwork side form structure and side form comprising same
JPH05106339A (en) Precast concrete mold for jointing concrete
JPH0790933A (en) Construction method of structure
CN113681676A (en) High-temperature steam-curing construction method for UHPC steel-concrete composite beam prefabricated bridge deck without coarse aggregate
JPH07109711A (en) Continuous feeding method of concrete slab
KR100616533B1 (en) Construction method for p.s.c. girder bridges and bridges production it
JPH09273117A (en) Joint construction of floor slab
CN211142798U (en) Plate-beam connecting assembly
JP2000104220A (en) Erection of combined truss bridge
CN110820512B (en) Plate-girder transverse connecting device and construction method thereof
KR100278118B1 (en) Cross beam construction method of concrete beam bridge
JP2006169730A (en) Concrete bridge girder and method of forming the same
JPS6151524B2 (en)
CN213448967U (en) Local cast-in-place type connected node of assembled concrete interior wall