JPH0830677A - Method and method for project management processing - Google Patents

Method and method for project management processing

Info

Publication number
JPH0830677A
JPH0830677A JP15986394A JP15986394A JPH0830677A JP H0830677 A JPH0830677 A JP H0830677A JP 15986394 A JP15986394 A JP 15986394A JP 15986394 A JP15986394 A JP 15986394A JP H0830677 A JPH0830677 A JP H0830677A
Authority
JP
Japan
Prior art keywords
work
charge
person
progress
individual
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP15986394A
Other languages
Japanese (ja)
Inventor
Junji Kumashiro
淳治 熊城
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Fujitsu Ltd
Original Assignee
Fujitsu Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Fujitsu Ltd filed Critical Fujitsu Ltd
Priority to JP15986394A priority Critical patent/JPH0830677A/en
Priority to US08/499,683 priority patent/US5974391A/en
Publication of JPH0830677A publication Critical patent/JPH0830677A/en
Priority to US09/208,472 priority patent/US6240395B1/en
Priority to US09/208,458 priority patent/US6282514B1/en
Pending legal-status Critical Current

Links

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02PCLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
    • Y02P90/00Enabling technologies with a potential contribution to greenhouse gas [GHG] emissions mitigation
    • Y02P90/30Computing systems specially adapted for manufacturing

Landscapes

  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

PURPOSE:To provide the system which can maintain the consistency between information on a supervisor's side and information on the side of staffs in charge when the supervisor optionally adds or corrects operation or changes staffs in charge. CONSTITUTION:A supervisor processor 1 generates individual operation data by the staffs from an operation plan and passes them to a staff processor 2. The staff processor 2 inputs progression information individually and reports it to the supervisor processor 1. The supervisor processor l stores alteration information by the staffs when the operation plan is corrected or added, and manages the latest operation data together with the report information from the staff processor 2. New operation data are handed over to the staff processor 2 again.

Description

【発明の詳細な説明】Detailed Description of the Invention

【0001】[0001]

【産業上の利用分野】本発明は,プロジェクト管理にお
ける各担当者の進捗報告処理の方式に関するものであ
る。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a method of progress report processing by each person in charge of project management.

【0002】現在,プロジェクト管理における進捗管理
システムに対する要求は増加する傾向にある。進捗情報
を管理する際,各担当者が何時でも都合のいいときに自
己の進捗状況の報告を行うことが可能な環境を提供する
ことが重要である。また管理者側も,何時でも進捗状況
を把握でき,かつプロジェクト中の作業の予定修正・作
業追加を行いながら進捗の管理を行えることが重要であ
る。
At present, the demand for a progress management system in project management tends to increase. When managing progress information, it is important for each person in charge to provide an environment in which he / she can report his / her own progress status whenever it is convenient. It is also important for the manager to be able to grasp the progress status at any time and to manage the progress while making revisions and additions to the work in the project.

【0003】また,管理者がある作業の担当者を別の担
当者と変更する場合には,旧担当者のファイルと新担当
者のファイルとの整合性を崩さず進捗管理を行えること
が重要である。
When the administrator changes the person in charge of a certain task to another person, it is important to manage the progress without breaking the consistency between the file of the old person in charge and the file of the new person in charge. Is.

【0004】[0004]

【従来の技術】図10は従来技術の例を示す。従来のプ
ロジェクト管理においては,図10(A)に示すような
システムにより,管理者が所有する進捗情報管理装置1
00の1マシンに,各担当者の進捗情報を入力し,進捗
情報を結合する際には全担当者の進捗情報を揃えて一度
に結合する方法や,図10(B)に示すようなシステム
により,各担当者に個人進捗ファイルを渡して管理し
て,各担当者の個人進捗ファイルを管理者用処理装置1
10で結合する方法を用いて進捗情報の管理を行ってい
た。
2. Description of the Related Art FIG. 10 shows an example of the prior art. In conventional project management, a progress information management device 1 owned by an administrator is used by a system as shown in FIG.
The progress information of each person in charge is input to one machine of 00, and when the progress information is combined, the progress information of all the persons in charge are aligned and combined at once, or a system as shown in FIG. Thus, the personal progress file is passed to each person in charge and managed, and the personal progress file of each person in charge is processed by the management processor 1
The progress information was managed using the method of combining in 10.

【0005】しかし,1マシンで進捗情報を管理する方
法は担当者が自由に進捗情報の報告を行うことができな
い。またファイルを渡して進捗情報を管理する方法で
は,管理者が作業を変更したり,担当者を変更した場合
には,必ず個人進捗ファイルを回収して変更を加えるよ
うな処理を施さなければファイル間の整合性が崩れると
いった事態が生じるという問題があった。
However, in the method of managing the progress information with one machine, the person in charge cannot freely report the progress information. In addition, in the method of passing the file and managing the progress information, if the administrator changes the work or changes the person in charge, the individual progress file must be collected and the change must be performed. There was a problem in that the situation in which the consistency between the two was lost would occur.

【0006】[0006]

【発明が解決しようとする課題】以上のように,図10
(A)のような1マシンで運用した場合,担当者が進捗
情報の報告を行いたい場合でも,マシンが他の用途で利
用されているときにはマシンを使用することができず,
進捗報告を行えないという問題が生じていた。
As described above, FIG.
When operating with one machine like (A), even if the person in charge wants to report progress information, the machine cannot be used when it is used for other purposes,
There was a problem that progress reports could not be made.

【0007】また,図10(B)に示すような方法で運
用した場合にも,管理者が作業の修正・追加を行った場
合に,担当者の個人進捗ファイルに変更点が反映されな
いことがあり,そのため整合性がとれないことがあると
いう問題が生じていた。
Even when the method shown in FIG. 10 (B) is used, the changes may not be reflected in the personal progress file of the person in charge when the administrator corrects / adds work. Therefore, there was a problem that the consistency might not be obtained.

【0008】本発明は,各担当者が任意に何時でも進捗
報告を行うことができ,さらに管理者側も任意に作業計
画の修正・追加(担当者変更も含めて)を行いながら,
何時でも進捗状況を把握することができるようにするこ
とを目的とする。
According to the present invention, each person in charge can arbitrarily make a progress report at any time, and further, the manager side arbitrarily corrects / adds a work plan (including change of person in charge),
The purpose is to be able to keep track of the progress at any time.

【0009】[0009]

【課題を解決するための手段】図1は,本発明の構成例
を示すブロック図である。図1中,1はパーソナルコン
ピュータ等による管理者用処理装置,2,2’,…はそ
れぞれパーソナルコンピュータ等による担当者用処理装
置,3は作業計画データ取得処理部,4は個別作業デー
タ作成処理部,5は作業計画修正・追加処理部,6は作
業データ結合処理部,7,7’,…は個別進捗管理部を
表す。
FIG. 1 is a block diagram showing a configuration example of the present invention. In FIG. 1, reference numeral 1 is a processor for a personal computer or the like, 2, 2 ', ... Are processors for a person using a personal computer or the like, 3 is a work plan data acquisition processing section, and 4 is individual work data creation processing. Reference numeral 5 indicates a work plan correction / addition processing unit, reference numeral 6 indicates a work data combination processing unit, reference numerals 7, 7 '... Represent an individual progress management unit.

【0010】管理者用処理装置1における作業計画デー
タ取得処理部3は,プロジェクト全体の作業計画に関す
る作業データを取得する処理手段である。個別作業デー
タ作成処理部4は,作業計画に関する作業データをもと
に,各担当者用処理装置2に対して引き渡す個別作業デ
ータを作成する処理手段である。また,個別作業データ
作成処理部4は,作業データ結合処理部6による処理結
果から,再度,個別作業データを作成して各担当者用処
理装置2に配布することも行う。
The work plan data acquisition processing unit 3 in the management processor 1 is a processing means for acquiring work data related to the work plan of the entire project. The individual work data creation processing unit 4 is a processing unit that creates individual work data to be handed over to each person-in-charge processing device 2 based on work data related to a work plan. The individual work data creation processing unit 4 also creates individual work data again from the processing result by the work data combination processing unit 6 and distributes the work data to each person-in-charge processing device 2.

【0011】作業計画修正・追加処理部5は,作業計画
の修正・追加情報を入力し,修正・追加された作業の内
容を変更情報として保存する処理手段である。ここで,
作業計画修正・追加処理部5により入力する作業計画の
修正・追加情報としては,担当者に割り当てる作業の変
更情報またはある作業に対する担当者の変更情報などが
ある。
The work plan correction / addition processing unit 5 is a processing means for inputting the correction / addition information of the work plan and storing the contents of the corrected / added work as change information. here,
The work plan correction / addition information input by the work plan correction / addition processing unit 5 includes work change information assigned to a person in charge or change information of a person in charge for a certain work.

【0012】作業データ結合処理部6は,担当者用処理
装置2,2’,…からの個別作業データの返還または進
捗報告を受けて,各担当者ごとの進捗情報と修正・追加
された作業の内容とをマージし,作業データに反映する
処理手段である。
The work data combination processing unit 6 receives the return of the individual work data or the progress report from the person-in-charge processing devices 2, 2 ′, ..., And the progress information for each person in charge and the corrected / added work. Is a processing means for merging the contents with the above and reflecting them in the work data.

【0013】各担当者用処理装置2,2’,…における
個別進捗管理部7,7’,…は,管理者用処理装置1か
ら渡された個別作業データをもとに,その作業の進捗情
報を入力し,管理者用処理装置1に個別作業データの返
還または進捗の報告を行う処理手段である。
The individual progress management units 7, 7 ′, ... In the respective processing units 2, 2 ′, for the persons in charge, based on the individual work data passed from the processing unit 1 for manager, the progress of the work. It is a processing means for inputting information and returning the individual work data or reporting the progress to the management processing device 1.

【0014】[0014]

【作用】本発明は,管理者用処理装置1により,プロジ
ェクト全体の作業計画に関する作業データをもとに,各
担当者ごとの個別作業データを作成して,それぞれ各担
当者用処理装置2,2’,…に配布し,各担当者用処理
装置2,2’,…により,管理者用処理装置1から渡さ
れた個別作業データをもとに,その作業の進捗情報を入
力し,管理者用処理装置1に返還または報告する。
According to the present invention, the manager processing device 1 creates individual work data for each person in charge based on the work data relating to the work plan of the entire project, and the respective processor devices 2, 2 for each person in charge. 2 ', ..., and each processing unit 2,2', ... for each person in charge inputs and manages the progress information of the work based on the individual work data passed from the processing unit 1 for the manager. Return or report to the personal processing device 1.

【0015】一方,管理者用処理装置1では,作業計画
の修正・追加があればその修正・追加情報を入力し,修
正・追加された作業の内容を変更情報として保存し,担
当者用処理装置2,2’,…から個別作業データの返還
または進捗報告があった場合に,各担当者ごとの進捗情
報と修正・追加された作業の内容とをマージして作業デ
ータに反映し,その結果から再度各担当者ごとの個別作
業データを作成して,それぞれ各担当者用処理装置2,
2’,…に配布する処理を繰り返す。
On the other hand, in the management processor 1, if there is a correction / addition to the work plan, the correction / addition information is input, the contents of the corrected / added work are saved as change information, and the processing for the person in charge is performed. When there is a return of individual work data or a progress report from the devices 2, 2 ', ..., the progress information for each person in charge and the contents of corrected / added work are merged and reflected in the work data, and Based on the results, individual work data for each person in charge is created again, and the processing device for each person in charge 2,
Repeat the process of distributing to 2 '...

【0016】[0016]

【実施例】以下,本発明の実施例を説明する。図2は実
施例における管理者用処理装置と担当者用処理装置との
関係を示す図である。管理者用処理装置1,担当者(1
〜3)用処理装置21〜23は,それぞれパーソナルコ
ンピュータ等によって構成され,LANによって接続さ
れている。なお,LAN等により各処理装置を接続し,
データを送受信する代わりに,ディスク記憶媒体を用い
て,管理者用処理装置1,担当者(1〜3)用処理装置
21〜23間でデータの受け渡しを行うようにしてもよ
い。本実施例では,図2に示すシステムにおいて,以下
のような流れで処理を行う。
EXAMPLES Examples of the present invention will be described below. FIG. 2 is a diagram showing the relationship between the manager processing device and the person-in-charge processing device in the embodiment. Administrator processing device 1, person in charge (1
~ 3) processing devices 21 to 23 are each configured by a personal computer or the like, and are connected by a LAN. In addition, connect each processing unit by LAN etc.,
Instead of transmitting / receiving data, a disk storage medium may be used to transfer data between the manager processing device 1 and the person in charge (1 to 3) processing devices 21 to 23. In this embodiment, in the system shown in FIG. 2, processing is performed according to the following flow.

【0017】 管理者用処理装置1は,作業計画作成
後に作業データ10をもとに各担当者が進捗報告を行う
ためのファイル(以降,個人進捗ファイル31〜33と
いう)を作成する。
After the work plan is created, the management processor 1 creates a file (hereinafter referred to as individual progress files 31 to 33) for each staff to report the progress based on the work data 10.

【0018】 個人進捗ファイル31〜33を各担当
者(1〜3)に渡す。各担当者は,都合のいい時間に,
担当者用処理装置21〜23において,渡された個人進
捗ファイル31〜33に進捗情報の入力を行う。進捗情
報は何度入力してもよい。
The personal progress files 31 to 33 are passed to the persons in charge (1 to 3). Each person, at a convenient time,
In the person-in-charge processing devices 21 to 23, the progress information is input to the passed individual progress files 31 to 33. The progress information may be input any number of times.

【0019】 各担当者用処理装置21〜23は,進
捗を入力した個人進捗ファイル31〜33を管理者用処
理装置1に渡す。管理者用処理装置1では,都合のいい
時間に担当者を選択して進捗情報の結合を行うことがで
きる。(進捗報告を行う必要のない担当者は進捗の結合
を行わない。) 管理者用処理装置1が新たに担当者に作業を追加し
たり,予定量の変更を行った場合には,各担当者ごとに
変更情報11〜13を保存しておく。管理者用処理装置
1に変更情報11〜13を保存しておくことで,各担当
者の個人進捗ファイル31〜33に依存することなく作
業の追加・修正を行うことができる。
Each of the person-in-charge processing devices 21 to 23 passes the individual progress files 31 to 33 in which the progress is input to the administrator processing device 1. In the management processor 1, the person in charge can be selected and the progress information can be combined at a convenient time. (A person in charge who does not need to report the progress does not combine the progresses.) When the management processor 1 newly adds work to the person in charge or changes the planned amount, each person in charge The change information 11 to 13 is stored for each person. By storing the change information 11 to 13 in the manager processing device 1, it is possible to add or correct work without depending on the individual progress files 31 to 33 of each person in charge.

【0020】 進捗情報結合の際に管理者用処理装置
1が変更した情報を作業データ10に反映させる。ま
た,個人進捗情報を結合する際に各担当者の個人進捗フ
ァイル31〜33に作業の追加・修正の情報が反映され
る。
The information changed by the administrator processing device 1 at the time of combining the progress information is reflected in the work data 10. Further, when the individual progress information is combined, the work addition / correction information is reflected in the individual progress files 31 to 33 of each person in charge.

【0021】従って,各担当者の個人進捗ファイル31
〜33を結合した際には管理者用処理装置1が変更した
各担当者の変更情報11〜13も反映され,ファイルと
しての整合性が保たれる。
Therefore, the personal progress file 31 of each person in charge
When 33 to 33 are combined, the change information 11 to 13 of each person in charge changed by the management processor 1 is also reflected, and the consistency as a file is maintained.

【0022】以上のように,個人進捗ファイル31〜3
3は,通常,各担当者が所有するようにし,担当者は自
分の個人進捗ファイル31〜33に進捗情報を入力する
ようにしているので,担当者が進捗情報を入力する場合
には,自分のパーソナルコンピュータ等による担当者
(1〜3)用処理装置21〜23で入力することがで
き,担当者の自由な時間に入力することが可能となる。
As described above, the individual progress files 31 to 3
3 is usually owned by each person in charge, and the person in charge inputs the progress information into his / her individual progress files 31 to 33. Therefore, when the person in charge inputs the progress information, It is possible to input by using the processing devices 21 to 23 for the persons in charge (1 to 3) using a personal computer or the like, and it is possible to input at any time of the person in charge.

【0023】また,管理者側も個人進捗ファイル31〜
33を各担当者に渡した後でも,作業の追加・修正を行
うことができるので,作業計画の追加・修正を実施しな
がら同時に進捗の管理を行うことが可能となる。さら
に,作業進行状況に応じて担当者の変更が必要になった
場合に,自由に担当者を変更することができ,人員配置
の計画も容易に変更できるようになる。
Also, the manager side personal progress files 31-31
Even after giving 33 to each person in charge, the work can be added / modified, so that the progress can be managed at the same time while the work plan is added / modified. Further, when it becomes necessary to change the person in charge according to the work progress situation, the person in charge can be freely changed, and the staffing plan can be easily changed.

【0024】図3は,本発明の実施例における進捗情報
の追加・作業項目変更処理のフローチャートである。図
3中,管理者用処理装置は管理者と,担当者用処理装置
は担当者と記す。
FIG. 3 is a flow chart of the progress information addition / work item change processing in the embodiment of the present invention. In FIG. 3, the processor for the administrator is referred to as the administrator, and the processor for the person in charge is referred to as the person in charge.

【0025】図3のステップS1の処理で,作業項目テ
ーブル41から作業項目名,担当者,予定量を取得す
る。なお,作業項目テーブル41は,管理者による作業
計画作成時の入力情報に基づいて事前に作成される。
In step S1 of FIG. 3, the work item name, the person in charge, and the planned amount are acquired from the work item table 41. The work item table 41 is created in advance based on the input information when the work plan is created by the administrator.

【0026】ステップS2の処理で,作業項目テーブル
41から取得したデータをもとに,各担当者が進捗の報
告を行うための個人進捗ファイルを作成し,各担当者へ
渡す。図3の例では,担当者1に対して『作業A,予定
量10』というデータを,担当者1の個人進捗ファイル
31により渡している。進捗量は『0』である。
In the process of step S2, based on the data acquired from the work item table 41, an individual progress file for each person in charge to report the progress is created and passed to each person in charge. In the example of FIG. 3, the data “work A, planned amount 10” is passed to the person in charge 1 by the personal progress file 31 of the person in charge 1. The amount of progress is “0”.

【0027】ステップS3の処理で,担当者は,自分の
端末から個人進捗ファイルに進捗情報を入力する。ここ
では,渡された個人進捗ファイル31に対して,進捗量
『5』を入力している。進捗情報の入力が完了したなら
ば,個人進捗ファイルを管理者へ返還する。進捗情報の
入力は,各担当者の都合のいい時間に行うことができ
る。
In step S3, the person in charge inputs the progress information into the personal progress file from his terminal. Here, the progress amount “5” is input to the passed personal progress file 31. When the input of progress information is completed, the personal progress file is returned to the administrator. The progress information can be input at a time convenient for each person in charge.

【0028】一方,管理者は,個人進捗ファイルを各担
当者に渡した後,作業計画の追加・修正が必要であれ
ば,ステップS4の判定の後,ステップS5〜S7の処
理を実行する。プロジェクトの進行状況等によっては,
担当者に個人進捗ファイルを渡した後であっても,作業
計画の追加・更新をすぐに行わなければならない場合が
あり,このようなときに担当者に渡した個人進捗ファイ
ルを回収せずに,ステップS5〜S7により作業計画の
変更を行う。
On the other hand, after passing the individual progress file to each person in charge, if the work plan needs to be added / corrected, the manager executes the processes of steps S5 to S7 after the determination of step S4. Depending on the progress of the project, etc.
Even after passing the individual progress file to the person in charge, it may be necessary to add / update the work plan immediately, and without collecting the individual progress file passed to the person in charge at such a time. The work plan is changed in steps S5 to S7.

【0029】ステップS5の処理で,各担当者に割り当
てる新たな作業を作成し,既存作業の予定量の変更等の
処理を行う。ステップS6の処理で,管理者が作業,予
定量を変更した場合の変更情報を保存する。例えば,担
当者1に関する変更情報11として,作業Aの予定量を
『10』から『20』に変更した(作業A’とする)変
更情報を,担当者1の変更情報ファイルとして保存す
る。ステップS7の処理で,管理者は結合する担当者を
選択する。ここでは,担当者1〜3のうち,作業の予定
量を変更した担当者1を選択する。
In the process of step S5, a new work to be assigned to each person in charge is created, and a process such as changing the planned amount of existing work is performed. In the process of step S6, the change information when the administrator changes the work amount and the planned amount is saved. For example, as the change information 11 regarding the person in charge 1, the change information in which the planned amount of the work A is changed from “10” to “20” (work A ′) is saved as the change information file of the person in charge 1. In the process of step S7, the administrator selects a person in charge to combine. Here, among the persons in charge 1 to 3, the person in charge 1 who has changed the planned work amount is selected.

【0030】ステップS8の処理で,選択した担当者1
の個人進捗ファイルと変更情報の内容を作業項目テーブ
ル41に反映させる。ここでは,担当者1の進捗情報を
入力済みの個人進捗ファイル31と管理者により変更し
た変更情報11が用いられ,作業項目テーブル41’の
ように更新される。
The person in charge 1 selected in the process of step S8
The contents of the individual progress file and the change information are reflected in the work item table 41. Here, the personal progress file 31 in which the progress information of the person in charge 1 has been input and the change information 11 changed by the administrator are used and updated as in the work item table 41 ′.

【0031】ステップS9の処理で,担当者1に個人進
捗ファイル31’を返還し,担当者1の変更情報11の
ファイルを削除する。個人進捗ファイル31’におい
て,作業名は『作業A’』に,予定量は『20』に変更
されている。
In the process of step S9, the personal progress file 31 'is returned to the person in charge 1 and the file of the change information 11 of the person in charge 1 is deleted. In the personal progress file 31 ', the work name is changed to "work A'" and the planned amount is changed to "20".

【0032】以下,担当者側ではステップS3の処理,
管理者側ではステップS4〜S9の処理が繰り返され
る。以上の処理は,担当者に渡した個人進捗ファイルを
回収しないで,管理者側だけで作業計画の変更を行った
場合に,担当者側との整合性がとれない事態が発生しな
いようにするための対策である。担当者に渡した個人進
捗ファイルとの整合性をとるために,担当者ごとの変更
情報ファイルを作成し保存している。このファイルに
は,管理者が新たに担当者に課した作業名,担当者名,
予定量の情報があり,担当者名をキーワードにして個人
進捗ファイルとリンクされている。なお,変更情報ファ
イルが各担当者ごとに用意されるにもかかわらず,レコ
ード中に担当者名の項目があるのは,担当者名が変更さ
れた場合に元の担当者の情報を残すためである。
Hereinafter, on the side of the person in charge, the processing of step S3,
The administrator repeats the processing of steps S4 to S9. The above process does not collect the personal progress file passed to the person in charge, and prevents the situation where the person in charge is inconsistent when the work plan is changed only by the administrator. This is a measure for To maintain consistency with the personal progress file passed to the person in charge, a change information file for each person in charge is created and saved. This file contains the work name, person's name,
There is information on the planned amount, which is linked to the personal progress file using the name of the person in charge as a keyword. Even though a change information file is prepared for each person in charge, there is an item for the person in charge in the record because the information of the original person in charge remains when the person in charge changes. Is.

【0033】図4は,本発明の実施例における担当者変
更処理のフローチャートである。図4中,管理者用処理
装置は管理者と,担当者用処理装置は担当者と記す。図
4のステップS11の処理で,作業項目テーブル41か
ら作業項目名,担当者,予定量を取得する。ステップS
12の処理で,取得したデータをもとに各担当者の個人
進捗ファイルを作成し,各担当者へ渡す。図4の例で
は,担当者1に対して担当者1の個人進捗ファイル31
を,担当者2に対して担当者2の個人進捗ファイル32
を渡している。
FIG. 4 is a flowchart of the person-in-charge change processing in the embodiment of the present invention. In FIG. 4, the processor for the administrator is referred to as the administrator, and the processor for the person in charge is referred to as the person in charge. In the process of step S11 of FIG. 4, the work item name, the person in charge, and the planned amount are acquired from the work item table 41. Step S
In the process of 12, the personal progress file of each person in charge is created based on the acquired data and passed to each person in charge. In the example of FIG. 4, the person 1's personal progress file 31
To the person in charge 2, the personal progress file 32 of the person in charge 2
Is passing.

【0034】ステップS13の処理で,各担当者は,自
分の端末から個人進捗ファイルにそれぞれ進捗情報を入
力する。ここで,担当者1の個人進捗ファイル31に,
作業Aおよび作業Bの進捗量として,それぞれ『5』が
入力され,担当者2の個人進捗ファイル32に,作業C
の進捗量として『10』が入力されている。進捗情報の
入力が完了すると,個人進捗ファイルは管理者に返還さ
れる。進捗情報の入力は,各担当者の都合のいい時間に
行うことができる。
In the process of step S13, each person in charge inputs the progress information into the personal progress file from his terminal. Here, in the personal progress file 31 of the person in charge 1,
“5” is entered as the progress amount of work A and work B, respectively, and work C is entered in the personal progress file 32 of the person in charge 2.
“10” is input as the progress amount of. When the input of the progress information is completed, the personal progress file is returned to the administrator. The progress information can be input at a time convenient for each person in charge.

【0035】管理者は,担当者に個人進捗ファイルを渡
した後でも,作業の状況に応じて担当者の変更を行わな
ければならない場合がある。この場合,管理者は担当者
の個人進捗ファイルを回収しないで担当者の変更を行
う。しかし,管理者側だけで変更を行うと担当者側との
整合性がとれない事態が生じるので,以下のように担当
者ごとに変更情報ファイルを作成する。
The administrator may have to change the person in charge in accordance with the status of the work even after passing the individual progress file to the person in charge. In this case, the administrator changes the person in charge without collecting the individual progress file of the person in charge. However, if changes are made only on the manager side, it may not be consistent with the person in charge. Therefore, a change information file is created for each person in charge as follows.

【0036】まず,ステップS14の処理で,管理者
は,担当者の変更が必要であるかどうかを判定し,変更
が必要な場合にはステップS15〜S17の処理を行
い,不要な場合にはステップS18の処理へ進む。
First, in the process of step S14, the manager determines whether or not the person in charge needs to be changed. If the change is necessary, the process of steps S15 to S17 is performed. The process proceeds to step S18.

【0037】ステップS15の処理で,作業項目テーブ
ル41を参照し,作業データ上で旧担当者と新担当者の
変更の処理を行う。ステップS16の処理で,管理者が
作業,予定量を変更した場合の変更情報を残すファイル
を作成する。このファイルには,例えば担当者1に関す
る変更情報11として,作業Aの担当者を『担当者1』
から『担当者2』に変更したことを示す変更情報を保存
する。ステップS17の処理で,管理者は結合する担当
者を選択する。この例では,作業Aの担当者を『担当者
1』から『担当者2』に変更しているので,担当者1〜
3のうち,担当者1,担当者2を選択する。
In the process of step S15, the work item table 41 is referred to, and the process of changing the old person and the new person is performed on the work data. In the process of step S16, a file is created which retains the change information when the administrator changes the work and the planned amount. In this file, for example, as the change information 11 about the person in charge 1, the person in charge of the work A is "person in charge 1".
The change information indicating that the change has been made to “person in charge 2” is saved. In the process of step S17, the administrator selects a person in charge to be combined. In this example, since the person in charge of work A is changed from "person in charge 1" to "person in charge 2", persons in charge 1 to 1
From among 3, the person in charge 1 and the person in charge 2 are selected.

【0038】ステップS18の処理で,選択した担当者
1,担当者2の個人進捗ファイルと変更情報の内容を作
業項目テーブル41に反映させる。ここでは,進捗情報
を入力済みの担当者1,2の個人進捗ファイル31,3
2と,管理者により変更した変更情報11が用いられ,
作業項目テーブル41’のように更新される。
In the processing of step S18, the contents of the personal progress files and change information of the selected person in charge 1 and person in charge 2 are reflected in the work item table 41. Here, the personal progress files 31, 3 of the persons 1 and 2 who have entered the progress information.
2 and the change information 11 changed by the administrator are used,
The work item table 41 'is updated.

【0039】ステップS19の処理で,新しい作業項目
テーブル41’をもとに作成した担当者1の個人進捗フ
ァイル31’と担当者2の個人進捗ファイル32’を,
それぞれ各担当者1,2に返還し,担当者1の変更情報
11のファイルを削除する。担当者1の個人進捗ファイ
ル31’の作業項目は,作業Bだけになり,担当者2の
個人進捗ファイル32’の作業項目は,作業C,作業A
になる。
In step S19, the personal progress file 31 'of the person in charge 1 and the personal progress file 32' of the person in charge 2 created based on the new work item table 41 'are
Each of them is returned to each person in charge 1 and 2, and the file of the change information 11 of the person in charge 1 is deleted. The work item of the personal progress file 31 ′ of the person in charge 1 is only work B, and the work items of the personal progress file 32 ′ of the person 2 is work C and work A.
become.

【0040】以上のように,担当者の進捗報告完了後,
管理者は個人進捗ファイルの結合を行う。この結合で
は,担当者の報告した進捗情報と管理者が変更した変更
情報とをマージする。マージしたデータは,作業項目テ
ーブル,個人進捗ファイルに反映され,再度,個人進捗
ファイルが各担当者に渡される。
As described above, after the completion of the progress report of the person in charge,
The administrator combines the individual progress files. In this combination, the progress information reported by the person in charge and the change information changed by the administrator are merged. The merged data is reflected in the work item table and personal progress file, and the personal progress file is passed again to each person in charge.

【0041】図5ないし図9は,本発明の実施例におい
て表示装置に表示される表示画面の例を示す。管理者用
処理装置1において,作業項目テーブルから作業項目,
担当者,予定量等を取得した後の進捗管理の画面(図3
に示すステップS1の処理後の表示画面)は,例えば図
5に示すような画面である。各作業ごとに予定や進捗情
報と,工程線表とが表示されている。
5 to 9 show examples of display screens displayed on the display device in the embodiment of the present invention. In the management processor 1, the work item from the work item table,
Screen for progress management after acquiring the person in charge, planned amount, etc. (Fig. 3
The display screen after the processing of step S1) is a screen as shown in FIG. 5, for example. Schedules and progress information and process line charts are displayed for each work.

【0042】また,図3に示すステップS2において,
管理者用処理装置1が個人進捗ファイルを作成するとき
の画面は,図6に示すような画面である。個人進捗ファ
イル選択画面61から,個人進捗ファイルを作成する担
当者を選択する。図6の例では,担当者1を選択してい
るが,すべての担当者を選択して一度に全担当者の個人
進捗ファイルを作成することもできる。
Further, in step S2 shown in FIG.
The screen when the management processor 1 creates the personal progress file is as shown in FIG. From the individual progress file selection screen 61, the person in charge who creates the individual progress file is selected. In the example of FIG. 6, the person in charge 1 is selected, but it is also possible to select all the persons in charge and create personal progress files for all the persons in charge at one time.

【0043】図7は,担当者用処理装置2において,管
理者から渡された個人進捗ファイルに担当者が進捗情報
を入力するときの画面を示している。報告入力/更新画
面71で,報告日,報告期間,進捗量を入力する。図7
の画面は,図3に示すステップS3において,担当者1
が進捗情報を入力するときの画面を示しており,予定量
『10』に対して,進捗量『5』を入力している。
FIG. 7 shows a screen when the person in charge inputs progress information to the personal progress file passed from the administrator in the processor 2 for person in charge. On the report input / update screen 71, the report date, report period, and progress amount are input. Figure 7
Is displayed in step S3 shown in FIG.
Shows a screen when the progress information is input, and the progress amount “5” is input for the planned amount “10”.

【0044】図8は,管理者用処理装置1において,作
業の修正・追加処理を行うときの画面を示している。詳
細作業項目登録画面81で,修正または追加を行う作業
を選択し,該当する項目に入力する。図8の画面は,図
3に示すステップS5において,担当者1の作業Aを変
更するときの画面を示しており,特にここでは,作業A
を作業A’とし,予定量(予定生産量)を『20』に変
更している。
FIG. 8 shows a screen when the work correction / addition process is performed in the management processor 1. On the detailed work item registration screen 81, the work to be corrected or added is selected and input in the corresponding item. The screen of FIG. 8 shows a screen when the work A of the person in charge 1 is changed in step S5 shown in FIG.
Is designated as work A ', and the planned amount (planned production amount) is changed to "20".

【0045】図9は,管理者用処理装置1において,個
人進捗ファイル等の結合を行ったときの進捗管理の画面
(図3のステップS8の処理後の画面)を示している。
担当者用処理装置から返還された個人進捗ファイルに基
づいて,進捗量が工程線表上に表示されている。
FIG. 9 shows a progress management screen (a screen after the processing of step S8 in FIG. 3) when the personal progress files and the like are combined in the management processor 1.
The amount of progress is displayed on the process line chart based on the individual progress file returned from the processor for person in charge.

【0046】[0046]

【発明の効果】以上説明したように,本発明によれば,
管理者用処理装置とは独立して,各担当者用処理装置に
おいて任意に何時でも進捗情報を入力または更新するこ
とができる。また,管理者用処理装置も,任意に作業計
画の修正または追加,担当者の変更等の処理を行うこと
が可能となり,常時,進捗状況の把握を行うことができ
る。さらに,各担当者ごとの変更情報を保持することに
より,個人進捗ファイルとの整合性を維持することがで
きる。
As described above, according to the present invention,
It is possible to input or update progress information at any time in each processing unit for each person independently of the processing unit for manager. Further, the processor for the administrator can also arbitrarily perform processing such as correction or addition of the work plan and change of the person in charge, and can always grasp the progress status. Further, by holding the change information for each person in charge, it is possible to maintain the consistency with the individual progress file.

【図面の簡単な説明】[Brief description of drawings]

【図1】本発明の構成例を示すブロック図である。FIG. 1 is a block diagram showing a configuration example of the present invention.

【図2】実施例における管理者用処理装置と担当者用処
理装置との関係を示す図である。
FIG. 2 is a diagram showing a relationship between a management processing device and a person-in-charge processing device in the embodiment.

【図3】実施例における作業計画の追加・修正処理のフ
ローチャートである。
FIG. 3 is a flowchart of work plan addition / correction processing according to an embodiment.

【図4】実施例における担当者変更処理のフローチャー
トである。
FIG. 4 is a flowchart of a person-in-charge changing process according to the embodiment.

【図5】管理者用処理装置において作業項目テーブルか
ら作業項目,担当者,予定量等を取得した後の進捗管理
の表示画面の例を示す図である。
FIG. 5 is a diagram showing an example of a progress management display screen after a work item, a person in charge, a planned amount, etc. are acquired from a work item table in the manager processing device.

【図6】管理者用処理装置において個人進捗ファイルを
作成するときの表示画面の例を示す図である。
FIG. 6 is a diagram showing an example of a display screen when an individual progress file is created in the administrator processing device.

【図7】担当者用処理装置において担当者が進捗情報を
入力するときの表示画面の例を示す図である。
FIG. 7 is a diagram showing an example of a display screen when a person in charge inputs progress information in the processor for a person in charge.

【図8】管理者用処理装置において作業の修正・追加処
理を行うときの表示画面の例を示す図である。
FIG. 8 is a diagram showing an example of a display screen when a work correction / addition process is performed in the management processing device.

【図9】管理者用処理装置において個人進捗ファイルを
結合した後の進捗管理の表示画面の例を示す図である。
FIG. 9 is a diagram showing an example of a progress management display screen after combining individual progress files in the administrator processing apparatus.

【図10】従来技術の例を示す図である。FIG. 10 is a diagram showing an example of a conventional technique.

【符号の説明】 1 管理者用処理装置 2,2’ 担当者用処理装置 3 作業計画データ取得処理部 4 個別作業データ作成処理部 5 作業計画修正・追加処理部 6 作業データ結合処理部 7,7’ 個別進捗管理部[Explanation of reference signs] 1 processor for processing 2, 2'processor for staff 3 work plan data acquisition processing section 4 individual work data creation processing section 5 work plan correction / addition processing section 6 work data combination processing section 7, 7'Individual progress management department

Claims (3)

【特許請求の範囲】[Claims] 【請求項1】 プロジェクト管理における全体の作業の
管理を行う管理者用処理装置と,各担当者に対して割り
当てられた各作業の進捗情報を管理する担当者用処理装
置とからなるプロジェクト管理処理システムであって,
前記管理者用処理装置は,プロジェクト全体の作業計画
に関する作業データを取得する作業計画データ取得手段
と,作業計画に関する作業データをもとに,前記各担当
者用処理装置に対して引き渡す個別作業データを作成す
る個別作業データ作成手段と,作業計画の修正・追加情
報を入力し,修正・追加された作業の内容を変更情報と
して保存する作業計画修正・追加手段と,前記担当者用
処理装置からの個別作業データの返還または進捗報告を
受けて,各担当者ごとの進捗情報と修正・追加された作
業の内容とをマージし,作業データに反映する作業デー
タ結合手段とを備え,前記各担当者用処理装置は,前記
管理者用処理装置から渡された個別作業データをもと
に,その作業の進捗情報を入力し,前記管理者用処理装
置に個別作業データの返還または進捗の報告を行う個別
進捗管理手段を備え,前記管理者用処理装置における個
別作業データ作成手段は,前記作業データ結合手段によ
る処理結果から,再度,個別作業データを作成して前記
各担当者用処理装置に配布するようにしたことを特徴と
するプロジェクト管理処理システム。
1. A project management process comprising a processing unit for managers who manages all works in project management and a processing unit for staffs who manages progress information of each work assigned to each staff member. A system,
The management processor is a work plan data acquisition unit that acquires work data related to the work plan of the entire project, and individual work data to be handed over to each of the responsible processors based on the work data related to the work plan. From the individual processing data creating means for creating the work plan, the work plan correction / addition means for inputting the work plan correction / addition information, and saving the contents of the work corrected / added as change information In response to the return of individual work data or progress report, the progress information of each person in charge is merged with the contents of the corrected / added work, and the work data combining means for reflecting the work data is provided. The personal processing device inputs progress information of the work based on the individual work data passed from the manager processing device, and the individual work data is input to the manager processing device. An individual progress management means for reporting a return or progress is provided, and the individual work data creation means in the manager processing device creates individual work data again from the processing result by the work data combination means and is in charge of each of the persons in charge. A project management processing system characterized in that the project management processing system is distributed to a processing device for personnel.
【請求項2】 請求項1記載のプロジェクト管理処理シ
ステムにおいて,前記作業計画修正・追加手段により入
力する作業計画の修正・追加情報は,担当者に割り当て
る作業の変更情報またはある作業に対する担当者の変更
情報であることを特徴とするプロジェクト管理処理シス
テム。
2. The project management processing system according to claim 1, wherein the work plan correction / addition information input by the work plan correction / addition means is work change information assigned to a person in charge or a person in charge for a certain work. A project management processing system characterized by change information.
【請求項3】 プロジェクト管理における全体の作業の
管理を行う管理者用処理装置と,各担当者に対して割り
当てられた各作業の進捗情報を管理する担当者用処理装
置とを用いてプロジェクトを管理するプロジェクト管理
処理方法であって,前記管理者用処理装置により,プロ
ジェクト全体の作業計画に関する作業データをもとに,
各担当者ごとの個別作業データを作成して,それぞれ前
記各担当者用処理装置に配布し,前記各担当者用処理装
置により,前記管理者用処理装置から渡された個別作業
データをもとに,その作業の進捗情報を入力し,前記管
理者用処理装置に返還または報告し,一方,前記管理者
用処理装置では,作業計画の修正・追加があればその修
正・追加情報を入力し,修正・追加された作業の内容を
変更情報として保存し,前記担当者用処理装置から個別
作業データの返還または進捗報告があった場合に,各担
当者ごとの進捗情報と修正・追加された作業の内容とを
マージして作業データに反映し,その結果から再度各担
当者ごとの個別作業データを作成して,それぞれ前記各
担当者用処理装置に配布する処理を繰り返すことを特徴
とするプロジェクト管理処理方法。
3. A project using a management processor for managing the entire work in project management and a processor for managing the progress information of each work assigned to each staff. A project management processing method for managing, wherein the management processor is used to generate work data based on work data relating to a work plan of the entire project.
Individual work data for each person in charge is created and distributed to each of the person-in-charge processing devices. Based on the individual work data passed from the manager-side processing device by each person-in-charge processing device. , The progress information of the work is input and returned or reported to the management processor. On the other hand, in the management processor, if there is correction / addition of the work plan, the correction / addition information is input. , The contents of the modified / added work are saved as change information, and when there is a return of individual work data or a progress report from the processing unit for the person in charge, the progress information and correction / addition for each person in charge It is characterized in that the contents of the work are merged and reflected in the work data, the individual work data for each person in charge is created again from the result, and the processing of distributing the individual work data to the person-in-charge processing devices is repeated. project Management processing method.
JP15986394A 1994-07-12 1994-07-12 Method and method for project management processing Pending JPH0830677A (en)

Priority Applications (4)

Application Number Priority Date Filing Date Title
JP15986394A JPH0830677A (en) 1994-07-12 1994-07-12 Method and method for project management processing
US08/499,683 US5974391A (en) 1994-07-12 1995-07-07 Device and method for project management
US09/208,472 US6240395B1 (en) 1994-07-12 1998-12-10 Device and method for project management
US09/208,458 US6282514B1 (en) 1994-07-12 1998-12-10 Device and method for project management

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP15986394A JPH0830677A (en) 1994-07-12 1994-07-12 Method and method for project management processing

Publications (1)

Publication Number Publication Date
JPH0830677A true JPH0830677A (en) 1996-02-02

Family

ID=15702869

Family Applications (1)

Application Number Title Priority Date Filing Date
JP15986394A Pending JPH0830677A (en) 1994-07-12 1994-07-12 Method and method for project management processing

Country Status (1)

Country Link
JP (1) JPH0830677A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP0892960A1 (en) * 1996-01-25 1999-01-27 Task Solutions Pty. Ltd. Task management system
US7167835B2 (en) * 2001-03-15 2007-01-23 Milliken & Company Method of providing project and product information to a purchaser of floor covering materials
CN111754081A (en) * 2020-05-29 2020-10-09 深圳瑞捷工程咨询股份有限公司 Engineering entity quality data management system and method

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP0892960A1 (en) * 1996-01-25 1999-01-27 Task Solutions Pty. Ltd. Task management system
EP0892960A4 (en) * 1996-01-25 2003-08-06 Taskey Pty Ltd Task management system
US7167835B2 (en) * 2001-03-15 2007-01-23 Milliken & Company Method of providing project and product information to a purchaser of floor covering materials
CN111754081A (en) * 2020-05-29 2020-10-09 深圳瑞捷工程咨询股份有限公司 Engineering entity quality data management system and method

Similar Documents

Publication Publication Date Title
US5265010A (en) Method and apparatus for performing patient documentation
US20060053034A1 (en) System and method for providing a real-time status for managing encounters in health care settings
US20020080189A1 (en) Electronic system for collecting and communicating clinical order information in an acute care setting
US20030139955A1 (en) Task support system and program and method for the same
US20070300229A1 (en) Configurable application integrating service request and fulfillment process
JPH0830677A (en) Method and method for project management processing
Fowell et al. The Welsh Collaborative Care Pathway Project: implementing an integrated care pathway for the dying patient in Wales
JP2004178144A (en) Control method, program, and recording medium of workflow server and workflow system
JPH1196248A (en) Work flow system and storage medium
JP4567861B2 (en) Patient information management method and hospital information system
US20180268374A1 (en) Electronic change planning manager
JP3200897B2 (en) Business alerting device and business performance recording device
JP5445759B2 (en) Report creation system and report creation method
JP2989940B2 (en) Schedule management method
JP2017102694A (en) Gantt chart generation program, gantt chart generation apparatus and gantt charge generation method
JPH06161956A (en) Joint work support system
JPH07192045A (en) Staff arrangement plan preparation expert system
JP2002297853A (en) Project management device and project management program
JP2005267521A (en) Method and system for placing nurse
JP2004021369A (en) Sales planning management system, sales planning management method, and sales planning management program
JPH0916668A (en) Method and device for drafting working plan and method for calculating wages
JP2002297849A (en) Schedule preparation support device and schedule preparation support system
Rasmi Zakiah et al. The Development of Web-Based Clinical Information in Polyclinic at University of Lampung
Heybrock et al. ``Extended World Wide Web support for softwaredevelopment projects’’
JP2004039000A (en) Personnel rating system, storage medium, and program

Legal Events

Date Code Title Description
A02 Decision of refusal

Free format text: JAPANESE INTERMEDIATE CODE: A02

Effective date: 20020205