JPH08295490A - Wiring structure of bridle and bail for jib crane - Google Patents

Wiring structure of bridle and bail for jib crane

Info

Publication number
JPH08295490A
JPH08295490A JP10363195A JP10363195A JPH08295490A JP H08295490 A JPH08295490 A JP H08295490A JP 10363195 A JP10363195 A JP 10363195A JP 10363195 A JP10363195 A JP 10363195A JP H08295490 A JPH08295490 A JP H08295490A
Authority
JP
Japan
Prior art keywords
boom
sheave block
bail
jib
bridle
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP10363195A
Other languages
Japanese (ja)
Other versions
JP2796515B2 (en
Inventor
Yoshitaka Amitani
義隆 網谷
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Sumitomo SHI Construction Machinery Co Ltd
Original Assignee
Sumitomo SHI Construction Machinery Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Sumitomo SHI Construction Machinery Co Ltd filed Critical Sumitomo SHI Construction Machinery Co Ltd
Priority to JP10363195A priority Critical patent/JP2796515B2/en
Publication of JPH08295490A publication Critical patent/JPH08295490A/en
Application granted granted Critical
Publication of JP2796515B2 publication Critical patent/JP2796515B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Abstract

PURPOSE: To shorten a luffing jib assembling time by a method wherein a seal block is transferred to a bracket arranged on a boom and a link arranged on the jib side and even in such a state that a luffing jib is not attached, wiring of a bridle and bail is practicable. CONSTITUTION: A sheave block (h) is removably mounted on a bracket 1 fixed on a boom (b). The bracket 1 is formed in such a manner that a base plate 4 is fixed to a stay 3 erected on a mounting plate 2 fixed to the boom (b) and a pin 6 is rotatably supported between support plates 5 and 5 erected on both sides of the base plate 4. A rise and fall rope (c) is arranged on the boom (b) between the sheave block (h) and a bail (g). Simultaneously, a jig is attached to the tip of the boom (b). The pin 6 in the sheave block (h) is pulled out. After the sheave block (h) is suspended by an auxiliary crane, it is matched with unwinding of the rise and fall rope, and the sheave block (h) is pivotally supported and coupled to the tip of a link on the jib side.

Description

【発明の詳細な説明】Detailed Description of the Invention

【0001】[0001]

【産業上の利用分野】本発明はジブクレ−ンに於けるブ
ライドル・ベイルのワイヤリング構造に関するものであ
る。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a bridle-bail wiring structure for a jib crane.

【0002】[0002]

【従来の技術】図1を参照して説明する。従来ジブクレ
−ンにおいて、ブライドル・ベイルのワイヤリング方法
は、まずラフイングジブaをブ−ムbの先端に取り付け
る。次に俯仰ロ−プcをリヤポストdの先端に設けたシ
−ブeに掛け回し、この掛け回した俯仰ロ−プcによっ
てブライドルfとベイルgの間のワイヤリングをしてい
る。この構造であると、俯仰ロ−プcをリヤポスト先端
のシ−ブeに掛けるため、まずラフイングジブaをブ−
ムbに取り付けた状態でないと不可能であった。
2. Description of the Related Art A description will be given with reference to FIG. In the conventional jib crane, in the bridle bail wiring method, the roughing jib a is first attached to the tip of the boom b. Next, the elevation rope c is hung around the sheave e provided at the tip of the rear post d, and the wiring between the bridle f and the bail g is carried out by the laid elevation rope c. With this structure, the lifting rope c is hung on the sheave e at the tip of the rear post, so that the roughing jib a is first pushed.
It was impossible unless it was attached to the frame b.

【0003】[0003]

【発明が解決しようとする課題】ラフイングジブaを組
立てる手順の中にブライドルfとベイルgのワイヤリン
グの作業があるが、上にのべた如く、ワイヤリング作業
はラフイングジブaをブ−ムbに取り付けた後でないと
できない。このためラフイングジブaの取り付け作業後
にワイヤリング作業をすることになり組立時間が長くな
るという問題があった。本発明は、ラフイングジブaを
ブ−ムbに取り付けない状態でもブライドル・ベイルの
ワイヤリング作業を可能とし、ラフイングジブaの組立
時間を短縮し、作業性の向上を図ることを目的とする。
There is a wiring work of the bridle f and the bail g in the procedure for assembling the roughing jib a. As mentioned above, the wiring work is performed after the roughing jib a is attached to the boom b. Otherwise you can't. For this reason, there is a problem that the wiring work is performed after the roughing jib a is attached and the assembling time becomes long. An object of the present invention is to enable bridle bail wiring work even when the roughing jib a is not attached to the boom b, shorten the assembling time of the roughing jib a, and improve workability.

【0004】[0004]

【課題を解決するための手段】ジブクレ−ンにおいて、
ブ−ムb上に設けたブラケット1にピン6を介しシ−ブ
ブロックhを着脱可能にし、他方リヤポストdにリンク
11を設け、該リンク11の先端にピン12で前記シ−
ブブロックhを着脱可能にし、ラフイングジブaなしで
俯仰ロ−プcのワイヤリング作業を可能にした。
[Means for Solving the Problems] In the jib crane,
A sheave block h can be attached to and detached from a bracket 1 provided on a boom b via a pin 6, while a link 11 is provided on a rear post d, and a pin 12 is provided at the tip of the link 11 to form the sheave.
The block h can be attached and detached, and the wiring work of the elevation rope c can be performed without the roughing jib a.

【0005】[0005]

【作用】ブ−ム上でシ−ブブロックhとベイルgの間で
俯仰ロ−プcをワイヤリングする。同時にジブaをブ−
ムbの先端に取付ける。シ−ブブロックhのピン6を抜
き、補助クレ−ンでシ−ブブロックhを吊り上げる。し
かるのち俯仰ロ−プcの巻出しにあわせて、シ−ブブロ
ックhをリンク11まで移動し、シ−ブブロックhをリ
ンク11の先端にピン12で連結するようにした。
Function: The elevation loop c is wired between the sheave block h and the bail g on the boom. At the same time, jib a
Attach it to the tip of the hole b. The pin 6 of the sheave block h is pulled out, and the sheave block h is lifted by the auxiliary crane. After that, the sheave block h was moved to the link 11 in accordance with the unwinding of the elevation rope c, and the sheave block h was connected to the tip of the link 11 by the pin 12.

【0006】[0006]

【実施例】図2と図3で説明する。図2でhはブ−ムb
上に設けたシ−ブブロックである。このシ−ブブロック
hはブ−ムb上に固着したブラケット1に対し着脱可能
に取り付けられている。このブラケット1はブ−ムbに
固着した取付板2と、取付板2に立設した支柱3と、支
柱3上に固設した基板4と、基板4の両側に立設した支
持板5,5にピン6で回動可能に枢支されている。
Embodiments will be described with reference to FIGS. In FIG. 2, h is a boom b
It is a sheave block provided above. The sheave block h is detachably attached to the bracket 1 fixed on the boom b. The bracket 1 includes a mounting plate 2 fixed to a boom b, a support 3 standing upright on the mounting plate 2, a substrate 4 fixed on the support 3, and support plates 5 standing upright on both sides of the substrate 4. 5 is pivotally supported by a pin 6.

【0007】シ−ブブロックhは前記ピン6が挿入され
る中空軸7と、その両側端に固着した2枚の側板8,8
と、2枚の側板8,8に支持される軸9とシ−ブ10で
構成されている。11はリヤポストdに設けたリンク
で、その先端にピン12によってシ−ブブロックhが着
脱可能に取付けられる。
The sheave block h has a hollow shaft 7 into which the pin 6 is inserted, and two side plates 8 and 8 fixed to both ends thereof.
The shaft 9 and the sheave 10 are supported by the two side plates 8 and 8. Reference numeral 11 denotes a link provided on the rear post d, and a sheave block h is detachably attached to the tip of the link by a pin 12.

【0008】(ワイヤリングの方法) (1)シ−ブブロックhとベイルgの間で俯仰ロ−プc
をワイヤリングする(図2)。 (2)ワイヤリングと同時に、ジブaをブ−ムbの先端
に取り付ける。 (3)シ−ブブロックhのピン6(図2(b))を抜く。
補助クレ−ン13でシ−ブブロックhを吊り上げる。 (4)俯仰ロ−プcの巻出しにあわせて、シ−ブブロッ
クhをリンク11まで移動する(図3(a)一点鎖線参
照)。 (5)シ−ブブロックhをリンク11の先端にピン12
で連結する。
(Wiring Method) (1) The elevation loop c between the sheave block h and the bail g.
Wire (Fig. 2). (2) At the same time as wiring, the jib a is attached to the tip of the boom b. (3) Pull out the pin 6 (FIG. 2B) of the sheave block h.
The sheave block h is lifted by the auxiliary crane 13. (4) The sheave block h is moved to the link 11 in accordance with the unwinding of the elevation loop c (see the alternate long and short dash line in FIG. 3A). (5) Attach the sheave block h to the tip of the link 11 with the pin 12
Connect with.

【0009】[0009]

【効果】ブ−ムb上に設けたブラケット1と、ジブa側
に設けたリンク11とにシ−ブブロックhを移し替え、
ラフイングジブaを取付けない状態でもブライドル・ベ
イルのワイヤリングを可能にした。このようにしたの
で、ラフイングジブaの組立時間を短縮することがで
き、作業性が一段と向上した。
[Effect] The sheave block h is transferred to the bracket 1 provided on the boom b and the link 11 provided on the jib a side,
The bridle bail can be wired even without the roughing jib a. Since this is done, the assembly time of the roughing jib a can be shortened and the workability is further improved.

【図面の簡単な説明】[Brief description of drawings]

【図1】公知ジブクレ−ンのブライドル・ベイルのワイ
ヤリング方法を示す。
FIG. 1 illustrates a known jib crane bridle bail wiring method.

【図2】本発明のワイヤリング構造におけるブ−ムに着
脱可能なシ−ブブロック。
FIG. 2 is a sheave block detachable from a boom in the wiring structure of the present invention.

【図3】本発明を用いたワイヤリング方法の説明図。FIG. 3 is an explanatory diagram of a wiring method using the present invention.

【符号の説明】[Explanation of symbols]

a ラフイングジブ b ブ−ム c 俯仰ロ−プ d リヤポスト e シ−ブ f ブライドル g ベイル h シ−ブブロック 1 ブラケット 2 取付板 3 支柱 4 基板 5 支持板 6 ピン 7 中空軸 8 側板 9 軸 10 シ−ブ 11 リンク 12 ピン 13 補助クレ−ン a roughing jib b boom c elevation rope d rear post e sheave f bridle g bail h sheave block 1 bracket 2 mounting plate 3 support 4 substrate 5 support plate 6 pin 7 hollow shaft 8 side plate 9 shaft 10 sheave 11 Link 12 pin 13 Auxiliary crane

Claims (1)

【特許請求の範囲】[Claims] 【請求項1】 ジブクレ−ンにおいて、ブ−ム(b)上に
設けたブラケット(1)にピン(6)を介しシ−ブブロック
(h)を着脱可能にし、他方リヤポスト(d)の一端にシ−
ブブロック(h)を連結するリンク(11)を設け、該リンク
(11)の先端にピン(12)で前記シ−ブブロック(h)を着脱
可能にし、ラフイングジブ(a)なしで俯仰ロ−プ(c)の
ブライドル・ベイルへのワイヤリング作業を可能にした
ことを特徴とするジブクレ−ンに於けるブライドル・ベ
イルのワイヤリング構造。
1. A jib crane in which a sheave block is mounted on a bracket (1) provided on a boom (b) through a pin (6).
(h) can be attached and detached, and on the other hand, one end of the rear post (d) has a seal.
A link (11) for connecting the block block (h) is provided, and the link
The sheave block (h) can be attached to and detached from the tip of (11) with a pin (12), and wiring work to the bridle bail of the elevation rope (c) can be performed without the roughing jib (a). Bridle bail wiring structure in the characteristic jib crane.
JP10363195A 1995-04-27 1995-04-27 Wiring structure of bridle bail in jib crane Expired - Fee Related JP2796515B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP10363195A JP2796515B2 (en) 1995-04-27 1995-04-27 Wiring structure of bridle bail in jib crane

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP10363195A JP2796515B2 (en) 1995-04-27 1995-04-27 Wiring structure of bridle bail in jib crane

Publications (2)

Publication Number Publication Date
JPH08295490A true JPH08295490A (en) 1996-11-12
JP2796515B2 JP2796515B2 (en) 1998-09-10

Family

ID=14359124

Family Applications (1)

Application Number Title Priority Date Filing Date
JP10363195A Expired - Fee Related JP2796515B2 (en) 1995-04-27 1995-04-27 Wiring structure of bridle bail in jib crane

Country Status (1)

Country Link
JP (1) JP2796515B2 (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104817025A (en) * 2015-04-30 2015-08-05 徐工集团工程机械股份有限公司 Roller device, integrally-mounted transportation bracket and crane
US9371215B2 (en) * 2007-10-29 2016-06-21 Liebherr-Werk Ehingen Gmbh Method for erecting a crane boom

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US9371215B2 (en) * 2007-10-29 2016-06-21 Liebherr-Werk Ehingen Gmbh Method for erecting a crane boom
CN104817025A (en) * 2015-04-30 2015-08-05 徐工集团工程机械股份有限公司 Roller device, integrally-mounted transportation bracket and crane

Also Published As

Publication number Publication date
JP2796515B2 (en) 1998-09-10

Similar Documents

Publication Publication Date Title
JP2007302352A (en) Crane, and crane boom derricking device
KR100493248B1 (en) Tie rod installation method and device of tower jib crane
RU97120577A (en) METHOD AND DEVICE FOR INSTALLING TOWERS OF THE LOADING ARROW OF THE TOWER CRANE
JP2004075294A (en) Jib strut self-assembling method for tower crane
JP4415643B2 (en) crane
JPH08295490A (en) Wiring structure of bridle and bail for jib crane
JP2001220088A (en) Winch attaching/detaching apparatus of mobile crane
JP4064935B2 (en) Temporary arm and assembly method of arm bracket in transmission line tower using this temporary arm
JP3009375B2 (en) Jib attachment / detachment device for crane beam
JP2824032B2 (en) Boom head attachment / detachment device
JP2005248585A6 (en) Temporary arm and assembly method of arm bracket in transmission line tower using this temporary arm
JP2002255478A (en) Luffing jib crane and method of assembling it
JPH1160165A (en) Rear post pendant rope connection device of crane and rear post pendant pore connection method therefor
JPH10120371A (en) Bridle moving device
JPH07187574A (en) Jib device of crane
JP2001310895A (en) Counter weight detaching/attaching device for crawler crane
JP3110703B2 (en) Crane rear post pendant rope connection device and rear post pendant rope connection method
JP3234883B2 (en) Luffing jib crane boom suspension structure
JP3174454B2 (en) Method and device for installing and removing leader from pile driver
JPH06298491A (en) Jib crane and assembling method therefor
JP3268062B2 (en) crane
JP2018048015A (en) Method for assembling mobile crane
JPH1135284A (en) Mobile crane
JPH0355593Y2 (en)
JPS592193Y2 (en) hydraulic excavator work equipment

Legal Events

Date Code Title Description
R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

LAPS Cancellation because of no payment of annual fees