JPH0814161B2 - Concrete slab joint structure - Google Patents
Concrete slab joint structureInfo
- Publication number
- JPH0814161B2 JPH0814161B2 JP14930689A JP14930689A JPH0814161B2 JP H0814161 B2 JPH0814161 B2 JP H0814161B2 JP 14930689 A JP14930689 A JP 14930689A JP 14930689 A JP14930689 A JP 14930689A JP H0814161 B2 JPH0814161 B2 JP H0814161B2
- Authority
- JP
- Japan
- Prior art keywords
- opening
- stop frame
- floor slab
- concrete
- slab
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Landscapes
- On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)
- Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)
Description
【発明の詳細な説明】 《産業上の利用分野》 本発明は、コンクリートスラブの打継ぎ構造に係り、
特に床スラブに工事施工中の荷役用として開口部を開設
している場合、荷揚げ作業完了後その開口部を閉塞する
ためのコンクリートスラブの打継ぎ構造に関するもので
ある。DETAILED DESCRIPTION OF THE INVENTION << Field of Industrial Application >> The present invention relates to a jointing structure for a concrete slab,
Particularly, the present invention relates to a splicing structure of a concrete slab for closing the opening after the completion of the unloading work when the floor slab has an opening for cargo handling during construction.
《従来の技術》 従来のコンクリートスラブの打継ぎ構造としては、特
開昭61−229051号公報や実公昭62−8295号公報に記載さ
れた技術が知られている。<< Prior Art >> As a conventional joint structure for concrete slabs, the technologies described in JP-A-61-290551 and JP-B-62-8295 are known.
ここに、資材等の荷揚げのために床スラブ21に開設し
た荷揚げ用開口部22を閉塞して平坦な面一の床を形成す
るために、第4図〜第7図に示すように、床スラブ21を
支持するFデッキ23が架設される梁24上に、床スラブ21
側と開口部22側とを区画してFデッキ23上に打設される
コンクリートを堰き止める止枠25を着脱可能に設置し、
次いで止枠25に形成した挿通口26に、床スラブ21側から
開口部22側に亘って延出させてシヤ・コネクタとして差
筋27を配設し、次いでFデッキ23上にコンクリートを打
設してコンクリートスラブ28を施工し、次いで差筋27の
開口部側延出部分27aを、荷揚げ作業の障害とならない
ように折り曲げ、荷揚げ作業の完了後、差筋27の開口部
側延出部分27aを開口部22に元のように延長するように
伸ばし、その後梁24上に開口部22を塞ぐようにFデッキ
23を架設し、最後に止枠25を除去すると共にFデッキ23
上にコンクリートを打設して、コンクリートスラブ29の
打継ぎを行なうようにしている。Here, in order to close the unloading opening 22 formed in the floor slab 21 for unloading materials, etc., to form a flat flush floor, as shown in FIG. 4 to FIG. The floor slab 21 is placed on the beam 24 on which the F deck 23 supporting the slab 21 is erected.
Side and the opening 22 side are divided and a stop frame 25 for damming the concrete placed on the F deck 23 is detachably installed,
Next, the insertion hole 26 formed in the stop frame 25 is extended from the floor slab 21 side to the opening 22 side to provide the differential line 27 as a shear connector, and then concrete is placed on the F deck 23. Then, the concrete slab 28 is constructed, and then the opening side extending portion 27a of the differential bar 27 is bent so as not to hinder the unloading work, and after the unloading work is completed, the opening side extending part 27a of the differential bar 27 is formed. The F deck so that it extends back to the opening 22 and then closes the opening 22 on the beam 24.
23 is erected, the stop frame 25 is removed at the end, and the F deck 23
Concrete is placed on the top of the concrete slab 29 for jointing.
《発明が解決しようとする課題》 しかし、上述したコンクリートスラブの打継ぎ作業に
あっては、止枠25の設置とその除去,止枠25に対する差
筋挿通用の挿通口26の形成,差筋27の挿通口26への挿通
並びに差筋27の2回に亘る曲げ伸ばしというように様々
な作業があり、様々な職種の作業者によって煩雑な作業
を実施しなければならないという問題があった。<< Problems to be Solved by the Invention >> However, in the above-mentioned concrete slab splicing work, installation and removal of the stop frame 25, formation of the insertion port 26 for inserting the differential line to the stop frame 25, and the differential line There are various works such as inserting 27 into the insertion opening 26 and bending and stretching the differential line 27 twice, and there has been a problem that complicated works must be carried out by workers of various occupations.
本発明は、上述のような問題点を解決するために創案
されたものであり、職種乃至は工数を削減して省力化と
コストダウンを達成しつつ、十分なアンカー作用を確保
できるコンクリートスラブの打継ぎ構造を提供すること
を目的とする。The present invention was created in order to solve the above-mentioned problems, and while achieving labor saving and cost reduction by reducing the type of work or man-hours, a concrete slab that can secure a sufficient anchoring action. The purpose is to provide a splice structure.
《課題を解決するための手段》 本発明は、梁上に設置した止枠により床スラブに区画
形成した荷揚げ用開口部に、該床スラブ側からシヤ・コ
ネクタを延出しコンクリートを打設することで、該床ス
ラブに対し、該開口部を塞ぐコンクリートスラブを打ち
継ぐようにしたコンクリートスラブの打継ぎ構造におい
て、上記梁上に上記止枠を接合すると共に、該止枠に、
略梁幅相当の寸法を有するリング筋で形成されて、上記
止枠を挟んで上記床スラブ側および上記開口部側双方へ
突出されるシヤ・コネクタを接合したことを特徴とす
る。<< Means for Solving the Problem >> The present invention is to extend a shear connector from the floor slab side into a unloading opening sectioned and formed in the floor slab by a stop frame installed on a beam, and to pour concrete. With respect to the floor slab, in the splicing structure of the concrete slab that splices the concrete slab that blocks the opening, while joining the stop frame to the beam, the stop frame,
A shear connector formed by a ring streak having a dimension substantially equivalent to a beam width and protruding toward both the floor slab side and the opening side with the stop frame interposed is joined.
《作用》 本発明の作用について述べると、止枠を梁上に接合す
ることにより止枠の設置とその除去作業を廃止できる。
また床スラブ側および開口部側双方へ突出されるシヤ・
コネクタを、止枠を挟んでこれに接合することにより、
止枠に対する挿通口の形成及び挿通口への挿通作業を廃
止できる。更にシヤ・コネクタを略梁幅相当の寸法を有
するリング筋で形成して、かつ止枠を挟んで床スラブ側
および開口部側双方へ突出させるようにしたので、シヤ
・コネクタは梁よりやや外方へ張り出す程度であり、こ
のシヤ・コネクタが荷揚げ作業の障害となることはな
く、2回に亘る曲げ伸ばし作業を廃止できる。このよう
に、リング筋で形成したシヤ・コネクタ並びに止枠の接
合作業を主体として打継ぎ作業を実施できる。他方、シ
ヤ・コネクタはリング状であるので、短い長さで相当の
定着表面積を嫁ぐことができ、長い差筋と同等のアンカ
ー機能を発揮する。<< Operation >> To describe the operation of the present invention, by installing the stop frame on the beam, installation and removal of the stop frame can be eliminated.
In addition, the shear that is projected to both the floor slab side and the opening side
By connecting the connector to the connector by sandwiching the stop frame,
It is possible to eliminate the formation of the insertion opening for the stop frame and the insertion work into the insertion opening. Furthermore, since the shear connector is formed by a ring streak having a dimension substantially equivalent to the beam width, and is made to project to both the floor slab side and the opening side with the stop frame sandwiched between them, the shear connector is slightly outside the beam. The shear connector does not hinder the unloading work, and the bending and stretching work twice can be eliminated. As described above, the splicing work can be performed mainly by the joining work of the shear connector and the stop frame formed by the ring streak. On the other hand, since the shear connector is ring-shaped, it can bear a considerable fixing surface area with a short length, and exhibits an anchor function equivalent to that of a long differential streak.
《実施例》 以下、本発明の好適実施例を図面を参照しながら詳述
する。<Example> Hereinafter, a preferred embodiment of the present invention will be described in detail with reference to the drawings.
第1図は本発明のコンクリートスラブの打継ぎ構造の
開口部開放時の側断面図、第2図は第1図におけるII−
II線矢視断面図、第3図はコンクリートスラブ打継ぎ後
の側断面図である。FIG. 1 is a side sectional view of the concrete slab splicing structure of the present invention when the opening is opened, and FIG. 2 is II- in FIG.
A sectional view taken along the line II and FIG. 3 are side sectional views after the concrete slab is spliced.
本発明は基本的には、梁1上に設置した止枠2により
床スラブ3に区画形成した荷揚げ用開口部4に、床スラ
ブ3側からシヤ・コネクタを延出しコンクリートを打設
することで、床スラブ3に対し、開口部4を塞ぐコンク
リートスラブ6を打ち継ぐようにしたコンクリートスラ
ブの打継ぎ構造において、梁1上に止枠2を接合すると
共に、止枠2に、略梁幅相当の寸法を有するリング筋5
で形成されて、止枠2を挟んで床スラブ3側および開口
部4側双方へ突出されるシヤ・コネクタを接合して構成
される。The present invention basically comprises extending a shear connector from the floor slab 3 side into a unloading opening 4 defined in the floor slab 3 by a stop frame 2 installed on the beam 1 and pouring concrete. In a splicing structure of a concrete slab that splices a concrete slab 6 that closes the opening 4 with respect to the floor slab 3, the stop frame 2 is joined onto the beam 1 and the stop frame 2 is approximately equivalent to the beam width. Ring muscle 5 with dimensions
And a shear connector that is formed on the floor slab 3 side and the opening 4 side with the stop frame 2 interposed therebetween.
図示するように、この実施例のコンクリートスラブの
打継ぎ構造は、梁1上に溶接されて床スラブ3に荷揚げ
用開口部4を区画形成すると共に、この開口部4周りに
床スラブ3を形成すべく打設されるコンクリートを堰き
止める止枠2と、この止枠2の開口部4側及び床スラブ
3側両側にU字筋5aの開放端が溶接されて形成されるシ
ヤ・コネクタたるリング筋5とで主に構成されている。As shown in the figure, in the concrete slab joint construction of this embodiment, the floor slab 3 is welded on the beam 1 to define the unloading opening 4 in the floor slab 3 and the floor slab 3 is formed around the opening 4. A stop frame 2 for damming the concrete to be cast as much as possible, and a shear connector barrel ring formed by welding the open ends of the U-shaped streaks 5a to both sides of the opening 4 side and the floor slab 3 side of the stop frame 2. Mainly composed of the muscle 5.
具体的には止枠2は、梁1及びリング筋5と溶接接合
できるように鉄板で構成される。そして、この止枠2の
両側面には、予め製作されたU字筋5aの開放端が止枠2
の高さ方向上下に溶接接合され、それらの折返し端が梁
1のフランジ1aよりやや外方まで張り出している。殊に
本実施例にあっては、これらU字筋5aで構成されるリン
グ筋5が止枠2の高さ方向に配置されているため、折返
し端をフランジ1aの端縁外方に張出すようにしても、U
字筋5aを水平方向に配置する場合に比べて荷揚げ作業の
障害となることは殆どない。またリング筋5は、短い外
形寸法ながら折返されて相当の定着表面積を有してお
り、コンクリート内に埋め込まれた際に十分なアンカー
機能を発揮するようになっている。Specifically, the stop frame 2 is made of an iron plate so as to be welded to the beam 1 and the ring reinforcement 5. Then, on both side surfaces of the stop frame 2, the open ends of the U-shaped streaks 5a which are manufactured in advance are provided.
Are welded to each other in the vertical direction in the height direction, and their folded ends project slightly outward from the flange 1a of the beam 1. In particular, in this embodiment, since the ring streaks 5 composed of these U-shaped streaks 5a are arranged in the height direction of the stop frame 2, the folded-back end is extended to the outside of the end edge of the flange 1a. Even if I try
Compared to the case where the streak 5a is arranged in the horizontal direction, there is almost no obstacle to the unloading work. Further, the ring streak 5 is folded back in spite of its short outer dimension and has a considerable fixing surface area, so that it exhibits a sufficient anchoring function when it is embedded in concrete.
他方止枠2は、Fデッキ7の施工に際して、梁1のフ
ランジ1aの中心線に沿って溶接により取付けられる。F
デッキ7は、板材に断面三角形状のリブ7aを形成して構
成されている。このFデッキ7は、床スラブ3側及び開
口部4を閉塞する際に梁1間に架設される。On the other hand, the stop frame 2 is attached by welding along the center line of the flange 1a of the beam 1 when constructing the F deck 7. F
The deck 7 is configured by forming ribs 7a having a triangular cross section on a plate material. The F deck 7 is installed between the beams 1 when closing the floor slab 3 side and the opening 4.
次に、上述のように構成されるコンクリートスラブの
打継ぎ構造の構築について説明する。Next, the construction of the jointing structure of the concrete slab configured as described above will be described.
先ず、開口部4を囲むように配設された梁1の外側に
床スラブ3側のFデッキ7を架設すると共に、この開口
部4を区画するように梁1上に止枠2を溶接固定する。
その後、この止枠2の開口部4側及び床スラブ3側にU
字筋5aの開放端を溶接接合して、止枠2を挟んで床スラ
ブ3側および開口部4側双方へ突出される、略梁幅相当
の寸法を有するリング筋5を形成する。次いで、床スラ
ブ3側のFデッキ7上にコンクリートを打設し、リング
筋5をその中に埋め込んだ状態で床スラブ3を形成す
る。First, the F deck 7 on the floor slab 3 side is installed outside the beam 1 arranged so as to surround the opening 4, and the stop frame 2 is welded and fixed on the beam 1 so as to partition the opening 4. To do.
After that, U is applied to the opening 4 side of the stop frame 2 and the floor slab 3 side.
The open ends of the character-shaped streaks 5a are welded to each other to form the ring streaks 5 having a dimension substantially equivalent to the beam width and protruding toward both the floor slab 3 side and the opening 4 side with the stop frame 2 interposed therebetween. Next, concrete is placed on the F deck 7 on the floor slab 3 side to form the floor slab 3 with the ring reinforcement 5 embedded therein.
このように床スラブ3が形成された状態において、開
設された開口部4から荷揚げ作業を実施する。この際、
開口部4側でリング筋5を構成するU字筋5aはその折返
し端が梁1のフランジ1aよりやや外方に張り出す程度な
ので、荷揚げ作業の障害となることはない。また本実施
例では、リング筋5は高さ方向上下に折返されているの
で、仮に荷がリング筋5に接触しても、荷はリング筋5
の湾曲した折返し端に案内されて円滑に引き上げられる
ことになる。With the floor slab 3 thus formed, the unloading work is carried out from the opened opening 4. On this occasion,
The U-shaped streak 5a forming the ring streak 5 on the side of the opening 4 has a folded end that extends slightly outward from the flange 1a of the beam 1, and therefore does not hinder the unloading work. In addition, in this embodiment, since the ring streak 5 is folded back up and down in the height direction, even if the load contacts the ring streak 5, the load is still loaded.
It will be smoothly pulled up by being guided by the curved folded end of the.
荷揚げ作業完了後には、この開口部4を閉塞するよう
に梁1上に開口部4側のFデッキ7を架設する。その後
このFデッキ7上にコンクリートを打設して、リング筋
5をその中に埋め込んだ状態で床スラブ3に対してコン
クリートスラブ6を打ち継ぐことにより、床スラブ3に
開設した荷揚げ用開口部4を閉塞して平坦な面一の床を
形成できるようになっている。After the unloading work is completed, the F deck 7 on the side of the opening 4 is erected on the beam 1 so as to close the opening 4. After that, concrete is poured on the F deck 7, and the concrete slab 6 is spliced to the floor slab 3 with the ring reinforcement 5 embedded therein. 4 can be closed to form a flat and flush floor.
《発明の効果》 以上要するに本発明によれば、次のような優れた効果
を発揮する。<< Effects of the Invention >> In short, according to the present invention, the following excellent effects are exhibited.
止枠を梁上に接合したことにより止枠の設置とその除
去作業を廃止することができる。また床スラブ側および
開口部側双方へ突出されるシヤ・コネクタを、止枠を挟
んでこれに接合したことにより、止枠に対する挿通口の
形成及び挿通口への挿通作業を廃止することができる。
更にシヤ・コネクタを略梁幅相当の寸法を有するリング
筋で形成して、かつ止枠を挟んで床スラブ側および開口
部側双方へ突出させるようにしたので、シヤ・コネクタ
は梁よりやや外方へ張り出す程度であり、このシヤ・コ
ネクタが荷揚げ作業の障害となることはなく、2回に亘
る曲げ伸ばし作業を廃止することができる。そしてこの
ように、リング筋で形成したシヤ・コネクタ並びに止枠
の接合作業を主体として打継ぎ作業を実施することがで
きる。他方、シヤ・コネクタはリング状であるので、短
い長さで相当の定着表面積を稼ぐことができ、従来の長
い差筋と遜色のないアンカー機能を確保することができ
る。By installing the stop frame on the beam, the installation and removal work of the stop frame can be eliminated. Further, the shear connector protruding toward both the floor slab side and the opening side is joined to the stop frame by sandwiching the stop frame, so that the formation of the insertion opening for the stop frame and the insertion work into the insertion opening can be eliminated. .
Furthermore, since the shear connector is formed by a ring streak having a dimension substantially equivalent to the beam width, and is made to project to both the floor slab side and the opening side with the stop frame sandwiched between them, the shear connector is slightly outside the beam. The shear connector does not hinder the unloading work, and the bending and stretching work twice can be eliminated. As described above, the splicing work can be performed mainly by the joining work of the shear connector and the stop frame formed by the ring streak. On the other hand, since the shear connector has a ring shape, a considerable fixing surface area can be obtained with a short length, and an anchor function comparable to the conventional long streak can be secured.
第1図は本発明のコンクリートスラブの打継ぎ構造の開
口部開放時の側断面図、第2図は第1図におけるII−II
線矢視断面図、第3図はコンクリートスラブ打継ぎ後の
側断面図、第4図〜第7図は従来のコンクリートスラブ
の打継ぎ構造の構築を説明する図である。 1…梁、2…止枠 3…床スラブ、4…荷揚げ用開口部 5…リング筋、6…コンクリートスラブFIG. 1 is a side sectional view of the concrete slab splicing structure of the present invention when the opening is opened, and FIG. 2 is II-II in FIG.
Fig. 3 is a sectional view taken along the line of arrows, Fig. 3 is a side cross-sectional view after concrete slab jointing, and Figs. 4 to 7 are views for explaining the construction of a conventional joint joint structure for concrete slabs. 1 ... Beam, 2 ... Stop frame 3 ... Floor slab, 4 ... Unloading opening 5 ... Ring reinforcement, 6 ... Concrete slab
Claims (1)
形成した荷揚げ用開口部に、該床スラブ側からシヤ・コ
ネクタを延出しコンクリートを打設することで、該床ス
ラブに対し、該開口部を塞ぐコンクリートスラブを打ち
継ぐようにしたコンクリートスラブの打継ぎ構造におい
て、上記梁上に上記止枠を接合すると共に、該止枠に、
略梁幅相当の寸法を有するリング筋で形成されて、上記
止枠を挟んで上記床スラブ側および上記開口部側双方へ
突出されるシヤ・コネクタを接合したことを特徴とする
コンクリートスラブの打継ぎ構造。Claim: What is claimed is: 1. By extending a shear connector from the floor slab side and placing concrete in the unloading opening sectioned and formed on the floor slab by a stop frame installed on the beam, to the floor slab, In a splicing structure of a concrete slab for striking a concrete slab that blocks the opening, while joining the stop frame to the beam, the stop frame,
A concrete slab is formed by joining a shear connector which is formed by a ring streak having a size substantially equivalent to a beam width and which is projected to both the floor slab side and the opening side with the stop frame interposed therebetween. Joint structure.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP14930689A JPH0814161B2 (en) | 1989-06-14 | 1989-06-14 | Concrete slab joint structure |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP14930689A JPH0814161B2 (en) | 1989-06-14 | 1989-06-14 | Concrete slab joint structure |
Publications (2)
Publication Number | Publication Date |
---|---|
JPH0317336A JPH0317336A (en) | 1991-01-25 |
JPH0814161B2 true JPH0814161B2 (en) | 1996-02-14 |
Family
ID=15472255
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP14930689A Expired - Fee Related JPH0814161B2 (en) | 1989-06-14 | 1989-06-14 | Concrete slab joint structure |
Country Status (1)
Country | Link |
---|---|
JP (1) | JPH0814161B2 (en) |
-
1989
- 1989-06-14 JP JP14930689A patent/JPH0814161B2/en not_active Expired - Fee Related
Also Published As
Publication number | Publication date |
---|---|
JPH0317336A (en) | 1991-01-25 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
JP2001342611A (en) | Bridge girder | |
JPH07292783A (en) | Connective structure of prestressed concrete members | |
JPH0814161B2 (en) | Concrete slab joint structure | |
JPH0826600B2 (en) | Concrete slab joint structure | |
JP6638885B2 (en) | Concrete assembly structure | |
JPH06146219A (en) | Joint structure for concrete precast floor board | |
JPH11192613A (en) | Steel base formwork and floor plate | |
JPS6137695Y2 (en) | ||
JPH06158715A (en) | Joint construction of precast concrete circumferential girder | |
JPH0642039A (en) | Joining method of end of precast concrete beam to precast concrete girder, and joining construction thereof | |
JP3008795B2 (en) | Joint structure of reinforced concrete beams | |
JP2021031902A (en) | Joint structure for concrete precast member | |
JPS6310021Y2 (en) | ||
JPH0497052A (en) | Deck plate | |
CN210439450U (en) | Concatenation formula house | |
US4020132A (en) | Construction joint for reinforced concrete structures | |
CN220203131U (en) | Building floor and building floor assembly | |
JPS6310020Y2 (en) | ||
JPH0417727Y2 (en) | ||
JPS6310019Y2 (en) | ||
JPS6312987B2 (en) | ||
CN219241008U (en) | Floor structure | |
JP2864905B2 (en) | Precast wall joining method | |
JPH0432181B2 (en) | ||
JPH06146439A (en) | Joining method for precast wall |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
LAPS | Cancellation because of no payment of annual fees |