JPH0317336A - Structure for construction joint of concrete slab - Google Patents
Structure for construction joint of concrete slabInfo
- Publication number
- JPH0317336A JPH0317336A JP14930689A JP14930689A JPH0317336A JP H0317336 A JPH0317336 A JP H0317336A JP 14930689 A JP14930689 A JP 14930689A JP 14930689 A JP14930689 A JP 14930689A JP H0317336 A JPH0317336 A JP H0317336A
- Authority
- JP
- Japan
- Prior art keywords
- opening
- concrete
- floor slab
- slab
- stop
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
- 238000010276 construction Methods 0.000 title abstract description 5
- 230000002787 reinforcement Effects 0.000 claims description 8
- 238000003466 welding Methods 0.000 abstract description 5
- 238000009434 installation Methods 0.000 abstract description 3
- 238000003780 insertion Methods 0.000 description 8
- 230000037431 insertion Effects 0.000 description 8
- 238000004873 anchoring Methods 0.000 description 6
- 238000005452 bending Methods 0.000 description 3
- 230000000694 effects Effects 0.000 description 2
- 239000000463 material Substances 0.000 description 2
- 229910000831 Steel Inorganic materials 0.000 description 1
- 238000010586 diagram Methods 0.000 description 1
- 238000000034 method Methods 0.000 description 1
- 210000003205 muscle Anatomy 0.000 description 1
- 238000005192 partition Methods 0.000 description 1
- 238000000638 solvent extraction Methods 0.000 description 1
- 239000010959 steel Substances 0.000 description 1
Landscapes
- On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)
- Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)
Abstract
Description
【発明の詳細な説明】
(産業上の利用分野)
本発明は、コンクリートスラブの打継ぎ構造に係り、特
に床スラブに工事施工中の荷役用として開口部を開設し
ている場合、荷揚げ作業完了後その開口部を閉塞するた
めのコンクリートスラブの打継ぎ構造に関するものであ
る。Detailed Description of the Invention (Industrial Field of Application) The present invention relates to a concrete slab pouring structure, and in particular, when the floor slab has an opening for loading and unloading during construction, the unloading operation is completed. This invention relates to a concrete slab pouring structure for later closing the opening.
《従来の技術〉
従来のコンクリートスラブの打継ぎ構造としては、特開
昭61−229051号公報や実公昭62−8295号
公報に記載された技術が知られている。<<Prior Art>> As a conventional concrete slab pouring structure, the techniques described in Japanese Patent Application Laid-Open No. 61-229051 and Japanese Utility Model Publication No. 62-8295 are known.
ここに、資材等の荷揚げのために床スラブ21に開設し
た荷揚げ用開口部22を閉塞して平坦な面一の床を形成
するために、第4図〜第7図に示すように、床スラプ2
1を支持するFデッキ23が架設される梁24上に、床
スラプ21側と開口部22側とを区画してFデッキ23
上に打設されるコンクリートを堰き止める止枠25を着
脱可能に設置し、次いで止枠25に形成した挿通口26
に、床スラブ21側から開口部22側に亘って延出させ
てシヤ・コネクタとして差筋27を配設し、次いでFデ
ッキ23上にコンクリートを打設してコンクリートスラ
プ28を施工し、次いで差筋27の開口部側延出部分2
7aを、荷揚げ作業の陣害とならないように折り曲げ、
荷揚げ作業の完了後、差筋27の開口部側延出部分27
aを開口部22に元のように延長するように伸ばし、そ
の後梁24上に開口部22を塞ぐようにFデッキ23を
架設し、最後に止枠25を除去すると共にFデッキ23
上にコンクリートを打設して、コンクリートスラブ2つ
の打継ぎを行なうようにしている。Here, in order to close the unloading opening 22 opened in the floor slab 21 for unloading materials, etc. and form a flat, flush floor, as shown in FIGS. 4 to 7, the floor is opened. Slap 2
1, on the beam 24 on which the F deck 23 supporting the F deck 23 is constructed, partitioning the floor slab 21 side and the opening 22 side
A stop frame 25 for damming the concrete to be placed above is removably installed, and then an insertion hole 26 formed in the stop frame 25 is installed.
Next, a differential bar 27 is provided extending from the floor slab 21 side to the opening 22 side as a shear connector, and then concrete is poured on the F deck 23 to construct a concrete slab 28. Opening side extension portion 2 of differential reinforcement 27
7a, so as not to interfere with the unloading work,
After the unloading work is completed, the opening side extension portion 27 of the differential reinforcement 27
a to the opening 22 as before, then construct the F deck 23 on the beam 24 so as to close the opening 22, and finally remove the retaining frame 25 and install the F deck 23.
Concrete is poured on top and the two concrete slabs are poured together.
(発明が解決しようとする課題)
しかし、上述したコンクリートスラブの打継ぎ作業にあ
っては、止枠25の設置とその除去,止枠25に対する
差筋挿通用の挿通口26の形戊,差筋27の挿通口26
への挿通並びに差筋27の2回に亘る曲げ伸ばしという
ように様々な作業があり、様々な職種の作業者によって
煩雑な作業を実施しなければならないという問題があっ
た。(Problem to be Solved by the Invention) However, in the above-mentioned concrete slab pouring work, the installation and removal of the stop frame 25, the shape of the insertion hole 26 for inserting the reinforcement into the stop frame 25, and the difference Insertion port 26 of muscle 27
There are various operations such as insertion into the rebar 27 and bending and straightening the rebar 27 twice, and there is a problem in that the complicated operations must be performed by workers of various occupations.
本発明は、上述のような問題点を解決するために創案さ
れたものであり、職種乃至は工数を削減して省力化とコ
ストダウンを達成しつつ、十分なアンカー作用を確保で
きるコンクリートスラブの打継ぎ構造を提供することを
目的とする。The present invention was devised to solve the above-mentioned problems, and it provides a concrete slab that can ensure sufficient anchoring action while reducing the number of jobs and man-hours to achieve labor savings and cost reduction. The purpose is to provide a spliced structure.
〈課題を解決するための手段}
本発明は、梁上に設置した止枠によって区画されて床ス
ラブに開口形成された荷揚げ用開口部に、止枠を介して
床スラブからシヤ・コネクタを延出しコンクリートを打
設して、床スラブにコンクリートスラブを打ち継ぐよう
にしたコンクリートスラブの打継ぎ構造において、止枠
を梁に接合すると共に、シヤ・コネクタを、止枠を介し
て床スラブから開口部に亘って略梁幅で延出されるリン
グ筋で形成して止枠に接合したことを特徴とする。<Means for Solving the Problems> The present invention extends a shear connector from a floor slab through a stop frame to a loading opening formed in the floor slab and partitioned by a stop frame installed on a beam. In a concrete slab joint structure in which poured concrete is poured and the concrete slab is connected to the floor slab, the stop frame is connected to the beam, and the shear connector is opened from the floor slab through the stop frame. It is characterized in that it is formed of a ring line that extends approximately the width of the beam over the entire length and is connected to the retaining frame.
《作 用)
本発明の作用について述べると、止枠を梁に接合するこ
とにより止枠の設置とその除去作業を廃止できる。また
シヤ・コネクタを止枠に接合することにより、止枠に対
する挿通口の形成及び挿通口への挿通作業を廃止できる
。更にシヤ・コネクタを、止枠を介して床スラブから開
口部に亘って略梁幅で延出されるリング筋で形成するこ
とにより、シヤ・コネクタが荷揚げ作業の障害となるこ
とはなく、2回に亘る曲げ伸ばし作業を廃止できる。こ
のように、リング筋で形成したシヤ・コネクタ並びに止
枠の接合作業を主体として打継ぎ作業を実施できる。他
方、シヤ・コネクタはリング状であるので、短い長さで
相当の定着表面積を稼ぐことができ、長い差筋と同等の
アンカー機能を発揮する。<<Function>> Describing the function of the present invention, by joining the stop frame to the beam, the installation and removal work of the stop frame can be eliminated. Furthermore, by joining the shear connector to the stop frame, it is possible to eliminate the work of forming an insertion hole in the stop frame and inserting it into the insertion hole. Furthermore, by forming the shear connector with a ring striation that extends approximately the width of the beam from the floor slab to the opening via the retaining frame, the shear connector will not become an obstacle to unloading operations, and This eliminates the need for bending and stretching work. In this way, the piecing work can be carried out mainly by joining the shear connector and the stopper frame formed by the ring threads. On the other hand, since the shear connector is ring-shaped, it can gain a considerable anchoring surface area with a short length, and exhibits the same anchoring function as a long shear connector.
{実 施 例}
以下.、本発明の好適実施例を図面を参照しながら詳述
する。{Implementation example} Below. , preferred embodiments of the present invention will be described in detail with reference to the drawings.
第1図は本発明のコンクリートスラブの打継ぎ構造の開
口部開放時の側断面図、第2図はその正面図、第3図は
コンクリートスラブ打継ぎ後の側断面図である。FIG. 1 is a side sectional view of the concrete slab splicing structure of the present invention when the opening is open, FIG. 2 is a front view thereof, and FIG. 3 is a side sectional view after the concrete slab is spliced.
本発明は基本的には、梁1上に設置した止枠2によって
区画されて床スラブ3に開口形威された荷揚げ用開口部
4に、止枠2を介して床スラブ3からシヤ・コネクタを
延出しコンクリートを打設して、床スラブ3にコンクリ
ートスラブ6を打ち継ぐようにしたコンクリートスラブ
の打継ぎ構造において、止枠2を梁1に接合すると共に
、シヤ・コネクタを、止枠2を介して床スラブ3がら開
口部4に亘って略梁幅で延出されるリング筋5で形成し
て止枠2に接合して構成される。Basically, the present invention connects a shear connector from the floor slab 3 via the stop frame 2 to a loading opening 4 defined by a stop frame 2 installed on a beam 1 and opened in the floor slab 3. In the concrete slab joint structure in which the concrete slab 6 is poured onto the floor slab 3 by extending concrete and pouring concrete, the stop frame 2 is joined to the beam 1, and the shear connector is connected to the stop frame 2. It is formed by a ring striation 5 extending from the floor slab 3 to the opening 4 by approximately the width of the beam, and is joined to the stop frame 2.
図示するように、この実施例のコンクリートスラブの打
継ぎ構造は、梁1上に溶接されて床スラプ3に荷揚げ用
開口部4を区画形成すると共に、この開口部4周りに床
スラブ3を形威すべく打設されるコンクリートを堰き止
める止枠2と、この止枠2の開口部4側及び床スラブ3
側両側にU字筋5aの開放端が溶接されて形成されるシ
ヤ・コネクタたるリング筋5とで主に構成されている。As shown in the figure, the concrete slab pouring structure of this embodiment is welded onto a beam 1 to define an opening 4 for unloading in the floor slab 3, and to form the floor slab 3 around this opening 4. A retaining frame 2 for damming concrete to be poured, the opening 4 side of this retaining frame 2, and the floor slab 3.
It is mainly composed of ring striations 5 which are shear connectors formed by welding the open ends of U-shaped striations 5a on both sides.
具体的には止枠2は、梁1及びリング筋5と溶接接合で
きるように鉄板で構或される。そして、この止枠2の両
側面には、予め製作されたU字筋5aの開放端が止枠2
の高さ方向上下に溶接接合され、それらの折返し端が梁
1のフランジ1aと略同じ幅乃至はこれよりやや外方ま
で張り出している。殊に本実施例にあっては、これらU
字筋5aで構成されるリング筋5が止枠2の高さ方向に
配置されているため、折返し端をフランジ1aの端縁外
方に張出すようにしても、U字筋5aを水平方向に配置
する場合に比べて荷揚げ作業の障害となることは殆どな
い。またリング筋5は、短い外形寸法ながら折返されて
相当の定着表面積を有しており、コンクリート内に埋め
込まれた際に十分なアンカー機能を発揮するようになっ
ている。Specifically, the stop frame 2 is made of a steel plate so that it can be welded to the beam 1 and the ring reinforcement 5. Then, on both sides of this stop frame 2, the open ends of the U-shaped strips 5a manufactured in advance are attached to the stop frame 2.
are welded together vertically in the height direction, and their folded ends extend to approximately the same width as the flange 1a of the beam 1 or to a slightly more outward extent than the flange 1a. In particular, in this embodiment, these U
Since the ring striations 5 made up of the U-shaped striations 5a are arranged in the height direction of the retaining frame 2, even if the folded end extends outward from the edge of the flange 1a, the U-shaped striations 5a cannot be moved horizontally. This poses almost no obstacle to unloading operations compared to the case where the Further, although the ring reinforcement 5 has a short external dimension, it is folded back and has a considerable anchoring surface area, so that it exhibits a sufficient anchoring function when embedded in concrete.
他方止枠2は、Fデッキ7の施工に際して、梁1のフラ
ンジ1aの中心線に沿って溶接により取付けられる。F
デッキ7は、板材に断面三角形状のリプ7aを形成して
構成されている。このFデッキ7は、床スラブ3側及び
開口部4を閉塞する際に梁1間に架設される。On the other hand, the retaining frame 2 is attached by welding along the center line of the flange 1a of the beam 1 when constructing the F deck 7. F
The deck 7 is constructed by forming a lip 7a having a triangular cross section on a plate material. This F deck 7 is constructed between the beams 1 when closing the floor slab 3 side and the opening 4.
次に、上述のように構成されるコンクリートスラブの打
継ぎ構造の構築について説明する。Next, construction of the concrete slab pouring structure constructed as described above will be explained.
先ず、開口部4を囲むように配設された梁1の外側に床
スラブ3側のFデツキ7を架設すると共に、この開口部
4を区画するように梁1上に止枠2を溶接固定する。そ
の後、この止枠2の開口部4側及び床スラブ3側にU字
筋5aの開放端を溶接接合して、止枠2を介して床スラ
ブ3側から開口部4側に亘って略梁幅で延出されるリン
グ筋5を形成する。次いで、床スラブ3側のFデツキ7
上にコンクリートを打設し、リング筋5をその中に埋め
込んだ状態で床スラブ3を形成する。First, the F deck 7 on the floor slab 3 side is erected on the outside of the beam 1 arranged so as to surround the opening 4, and the retaining frame 2 is welded and fixed onto the beam 1 so as to partition this opening 4. do. Thereafter, the open end of the U-shaped bar 5a is welded to the opening 4 side of the stopper frame 2 and the floor slab 3 side, and a substantially beam is formed from the floor slab 3 side to the opening 4 side via the stopper frame 2. A ring line 5 extending in width is formed. Next, F deck 7 on the floor slab 3 side
A floor slab 3 is formed by pouring concrete on top and embedding ring reinforcements 5 therein.
このように床スラブ3が形成された状態において、開設
された開口部4から荷揚げ作業を実施する。この際、開
口部4側でリング筋5はその折返し端が梁1のフランジ
1aと略同じ幅乃至はこれよりやや外方に張り出す程度
なので、荷揚げ作業の障害となることはない。また本実
施例では、リング筋5は高さ方向上下に折返されている
ので、仮に荷がリング筋5に接触しても、荷はリング筋
5の湾曲した折返し端に案内されて円滑に引き上げられ
ることになる。With the floor slab 3 thus formed, unloading work is carried out through the opened opening 4. At this time, the folded ends of the ring striations 5 on the side of the opening 4 have approximately the same width as the flange 1a of the beam 1, or extend slightly outward from the flange 1a of the beam 1, so that they do not become an obstacle to the unloading work. Furthermore, in this embodiment, since the ring striations 5 are folded up and down in the height direction, even if a load comes into contact with the ring striations 5, the load will be guided by the curved folded ends of the ring striations 5 and pulled up smoothly. It will be done.
荷揚げ作業完了後には、この開口部4を閉塞するように
梁1上に開口部4側のFデツキ7を架設する。その後こ
のFデッキ7上にコンクリートを打設して、リング筋5
をその中に埋め込んだ状態で床スラプ3に対してコンク
リートスラブ6を打ち継ぐことにより、床スラブ3に開
設した荷揚げ用開口部4を閉塞して平坦な面一の床を形
成できるようになっている。After the unloading work is completed, the F deck 7 on the opening 4 side is constructed on the beam 1 so as to close the opening 4. After that, concrete is poured on this F deck 7, and ring reinforcement 5
By pouring a concrete slab 6 onto the floor slab 3 with the concrete embedded therein, it becomes possible to close the unloading opening 4 made in the floor slab 3 and form a flat, flush floor. ing.
(発明の効果〉
以上要するに本発明によれば、次のような優れた効果を
発揮する。(Effects of the Invention) In summary, according to the present invention, the following excellent effects are achieved.
止枠を梁に接合したことにより止枠の設置とその除去作
業を廃止することができる。またシヤ・コネクタを止枠
に接合したことにより、止枠に対する挿通口の形成及び
挿通口への挿通作業を廃止することができる。更にシヤ
・コネクタを、止枠を介して床スラブから開口部に亘っ
て略梁幅で延出されるリング筋で形成したことにより、
シヤ・コネクタが荷揚げ作業の障害となることはなく、
2回に亘る曲げ伸ばし作業を廃止することができる。そ
してこのように、リング筋で形戊したシヤ・コネクタ並
びに止枠の接合作業を主体として打継ぎ作業を実施する
ことができる。他方、シヤ・コネクタはリング状である
ので、短い長さで相当の定着表面積を稼ぐことができ、
従来の長い差筋と遜色のないアンカー機能を確保するこ
とができる。By joining the stop frame to the beam, it is possible to eliminate the work of installing and removing the stop frame. Furthermore, by joining the shear connector to the stop frame, it is possible to eliminate the work of forming an insertion hole in the stop frame and inserting the work into the insertion hole. Furthermore, by forming the shear connector with a ring striation that extends from the floor slab to the opening through the stopper frame,
Shear connectors do not become an obstacle to unloading operations,
It is possible to eliminate the bending and stretching work that takes place twice. In this way, it is possible to carry out the splicing work, mainly the work of joining the shear connector and the stopper frame formed with ring threads. On the other hand, since the shear connector is ring-shaped, it can gain considerable anchoring surface area with a short length.
It is possible to secure an anchor function that is comparable to that of conventional long crossbars.
第1図は本発明のコンクリートスラブの打継ぎ構造の開
口部開放時の側断面図、第2図はその正面図、第3図は
コンクリートスラブ打継ぎ後の側断面図、第4図〜第7
図は従来のコンクリートスラブの打継ぎ構造の構築を説
明する図である。Fig. 1 is a side sectional view of the concrete slab splicing structure of the present invention when the opening is open, Fig. 2 is its front view, Fig. 3 is a side sectional view after the concrete slab is spliced, and Figs. 7
The figure is a diagram illustrating the construction of a conventional concrete slab pour joint structure.
Claims (1)
形成された荷揚げ用開口部に、上記止枠を介して上記床
スラブからシヤ・コネクタを延出しコンクリートを打設
して、上記床スラブにコンクリートスラブを打ち継ぐよ
うにしたコンクリートスラブの打継ぎ構造において、上
記止枠を上記梁に接合すると共に、上記シヤ・コネクタ
を、上記止枠を介して上記床スラブから上記開口部に亘
って略梁幅で延出されるリング筋で形成して上記止枠に
接合したことを特徴とするコンクリートスラブの打継ぎ
構造。A shear connector is extended from the floor slab through the stop frame and concrete is poured into the unloading opening defined by the stop frame installed on the beam and formed in the floor slab. In a concrete slab joint structure in which concrete slabs are joined to each other, the stop frame is joined to the beam, and the shear connector is connected from the floor slab to the opening via the stop frame. A concrete slab pouring structure characterized in that it is formed of ring reinforcement extending approximately in width of the beam and is connected to the above-mentioned retaining frame.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP14930689A JPH0814161B2 (en) | 1989-06-14 | 1989-06-14 | Concrete slab joint structure |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP14930689A JPH0814161B2 (en) | 1989-06-14 | 1989-06-14 | Concrete slab joint structure |
Publications (2)
Publication Number | Publication Date |
---|---|
JPH0317336A true JPH0317336A (en) | 1991-01-25 |
JPH0814161B2 JPH0814161B2 (en) | 1996-02-14 |
Family
ID=15472255
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP14930689A Expired - Fee Related JPH0814161B2 (en) | 1989-06-14 | 1989-06-14 | Concrete slab joint structure |
Country Status (1)
Country | Link |
---|---|
JP (1) | JPH0814161B2 (en) |
-
1989
- 1989-06-14 JP JP14930689A patent/JPH0814161B2/en not_active Expired - Fee Related
Also Published As
Publication number | Publication date |
---|---|
JPH0814161B2 (en) | 1996-02-14 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
JP2001342611A (en) | Bridge girder | |
CN111188508A (en) | Supplement plate of existing cantilever floor slab of building structure and construction method thereof | |
JPH0317336A (en) | Structure for construction joint of concrete slab | |
JPH0317335A (en) | Structure for construction joint of concrete slab | |
CN210421625U (en) | Cast-in-place combination beam structure of assembled | |
CN212002420U (en) | Cantilever structure patch board | |
JP3466961B2 (en) | Reinforcement method for existing load-bearing walls with openings | |
JPH0642039A (en) | Joining method of end of precast concrete beam to precast concrete girder, and joining construction thereof | |
JPS60133146A (en) | Construction of synthetic large beam using u-shaped precast beam material | |
JP2618671B2 (en) | SRC precast beam and beam-column joint structure | |
JPS59192145A (en) | Fixing of iron pillar | |
JP2003049409A (en) | Arch rib erection method | |
JPS6137695Y2 (en) | ||
JPS63533A (en) | Slope frame construction work | |
JPS6310021Y2 (en) | ||
JPH11140863A (en) | Joint member of steel pipe sheet pile, joint structure, and steel pipe sheet pile foundation using the same | |
JPH0443526Y2 (en) | ||
JP2694715B2 (en) | Joint structure of underground wall | |
JP2000038839A (en) | Form method of concrete placing joint in beam | |
JPS607397Y2 (en) | Joint structure of concrete sheet piles | |
JPH0874312A (en) | Box culvert | |
JPH0339573A (en) | Construction method of underground wall of structure | |
JPS58164848A (en) | Connection structure of pc small beam | |
JPS6310020Y2 (en) | ||
JPS59177445A (en) | Semi-pc slab construction method and semi-pc panel used therein |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
LAPS | Cancellation because of no payment of annual fees |