JPH08134848A - Execution method of steel pipe-concrete composite structure pier - Google Patents

Execution method of steel pipe-concrete composite structure pier

Info

Publication number
JPH08134848A
JPH08134848A JP30157594A JP30157594A JPH08134848A JP H08134848 A JPH08134848 A JP H08134848A JP 30157594 A JP30157594 A JP 30157594A JP 30157594 A JP30157594 A JP 30157594A JP H08134848 A JPH08134848 A JP H08134848A
Authority
JP
Japan
Prior art keywords
steel pipe
concrete
hollow steel
composite structure
concrete composite
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP30157594A
Other languages
Japanese (ja)
Other versions
JP2639361B2 (en
Inventor
Kenichi Ukaji
賢一 宇梶
Toshiaki Kato
敏明 加藤
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Obayashi Corp
Original Assignee
Obayashi Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Obayashi Corp filed Critical Obayashi Corp
Priority to JP6301575A priority Critical patent/JP2639361B2/en
Publication of JPH08134848A publication Critical patent/JPH08134848A/en
Application granted granted Critical
Publication of JP2639361B2 publication Critical patent/JP2639361B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Landscapes

  • Bridges Or Land Bridges (AREA)
  • Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)

Abstract

PURPOSE: To improve the efficiency of the execution of works by a method wherein a hollow steel pipe disposed in upright on a foundation is hung up, a sliding form device is arranged as a bearing base, concrete is placed on the inside of sliding forms and the periphery of the steel pipe is covered with concrete. CONSTITUTION: A hollow steel pipe 2 is installed in upright on a foundation while concrete 21 is placed on the inside of the lower section of the steel pipe 2, and concrete is placed around the steel pipe 2, thus forming a lower body 3a. The segments of the steel pipe 2 are built by a tower crane 7 installed onto concrete 21 and joined. When the steel pipes 2 are piled up up to specified height, a bracket 9 is fixed at the upper end section of the steel pipes 2, and sliding form devices 8 are suspended through wires 41. Reinforcements 5 are arranged around the steel pipes 2, and concrete is placed among forms 11 and the steel pipes 2 while lifting the sliding form devices 8. The driving of concrete, the arrangement of the reinforcements, the disposal of the forms 11 and the placing of concrete are repeated successively, thus forming a body 3.

Description

【発明の詳細な説明】Detailed Description of the Invention

【0001】[0001]

【産業上の利用分野】本発明は、例えば高橋脚に適用さ
れる鋼管・コンクリート複合構造橋脚の施工方法に関す
る。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a method for constructing a steel pipe / concrete composite structure pier applied to, for example, a high pier.

【0002】[0002]

【従来の技術】橋脚を構築するには、従来一般に、基礎
上に配筋される主筋に横筋を組み合わせて鉄筋を施工
し、これの外周に型枠を配置し、コンクリートを打設す
る方法が取られている。
2. Description of the Related Art Conventionally, in order to construct a pier, a method of constructing a reinforcing bar by combining horizontal bars with main bars arranged on a foundation, arranging a formwork on the outer periphery of the reinforcing bar, and placing concrete Has been taken.

【0003】[0003]

【発明が解決しようとする課題】しかしながら、この種
の施工方法では比較的高さが低い橋脚などには適合する
が、高橋脚の施工に適用した場合には、強度を確保する
上で多数の主筋や横方向の鉄筋や隅角部のハンチ筋、あ
るいは組立て用鉄筋などが輻湊し、配筋作業、特に高橋
脚を構築する場合には荷重が大きくなることから主筋が
多数配列されるが、そのときの横鉄筋の組立作業は困難
さを増すとともに、型枠材やセパレータの組立およびそ
の解体撤去、作業足場などの組立や解体撤去などの作業
工数が膨大となり、多人数の熟練労務者を必要とするた
め、短期急速施工の点においても著しく不利であり、建
設コストも極めて高いものとなっていた。型枠の解体作
業を省略するためにプレキャスト型枠等の埋殺し型枠を
用いることもあるが、型枠の組立、継ぎ目処理などの手
間は除去されない。
However, although this type of construction method is suitable for piers having a relatively low height, when applied to construction of high piers, a large number of A large number of main bars are arranged because the main bars, lateral rebars, corner haunch bars, or assembly rebars are congested, and the load becomes large when arranging work, especially when constructing high piers, At that time, the work of assembling the horizontal rebars becomes more difficult, and the man-hours for assembling and dismantling formwork materials and separators, assembling and dismantling work scaffolds, etc. become enormous, and a large number of skilled workers are required. Since it is necessary, it is extremely disadvantageous in terms of short-term rapid construction, and the construction cost is extremely high. Although an embedded mold such as a precast mold may be used in order to omit the work of dismantling the mold, the trouble of assembling the mold and treating the joint is not eliminated.

【0004】本発明は、上述した事情を考慮してなされ
たもので、十分な曲げ強度およびせん断強度をもつ橋脚
を急速施工可能な鋼管・コンクリート複合構造橋脚の施
工方法を提供することを目的とする。
The present invention has been made in view of the above circumstances, and has as its object to provide a method of constructing a steel pipe / concrete composite structure pier capable of rapidly constructing a pier having sufficient bending strength and shear strength. I do.

【0005】[0005]

【課題を解決するための手段】上記目的を達成するた
め、本発明の鋼管・コンクリート複合構造橋脚の施工方
法は請求項1に記載したように、中空鋼管を基礎に立設
し、次いで、当該中空鋼管を吊り上げ支持台として滑動
型枠装置を配置し、次いで、当該滑動型枠装置に設けた
滑動型枠の内側にコンクリートを打設して前記中空鋼管
の周囲にコンクリートを被覆するものである。
In order to achieve the above object, the method for constructing a steel pipe / concrete composite structure pier according to the present invention is such that a hollow steel pipe is erected on a foundation, and then said A sliding formwork device is arranged as a hoisting support of a hollow steel pipe, and then concrete is placed inside the sliding formwork provided in the sliding formwork device to coat concrete around the hollow steel pipe. .

【0006】また、本発明の鋼管・コンクリート複合構
造橋脚の施工方法は、請求項1のコンクリート打設工程
の前に、前記中空鋼管の外周囲を包囲した状態で構造断
面の表面側に沿ってPCストランドを巻回するものであ
る。
According to the method for constructing a steel pipe / concrete composite structure pier of the present invention, prior to the concrete placing step of claim 1, the hollow steel pipe is surrounded by an outer periphery thereof along the surface side of the structural cross section. The PC strand is wound.

【0007】また、本発明の鋼管・コンクリート複合構
造橋脚の施工方法は、請求項1の中空鋼管内にタワーク
レーンを設置するものである。
The method for constructing a steel pipe / concrete composite structure pier according to the present invention comprises installing a tower crane in the hollow steel pipe of claim 1.

【0008】また、本発明の鋼管・コンクリート複合構
造橋脚の施工方法は、請求項3のタワークレーンに所定
の作業足場を昇降自在に取り付けたものである。
Further, in the method for constructing a steel pipe / concrete composite structure pier according to the present invention, a predetermined work scaffold is attached to the tower crane so as to be able to move up and down.

【0009】[0009]

【作用】本発明の鋼管・コンクリート複合構造橋脚の施
工方法においては、まず、クレーンを用いて中空鋼管の
先行建込みを行い、所定の配筋作業を行った後、中空鋼
管を吊り上げ支持台として滑動型枠装置を配置し、次い
で、当該滑動型枠装置を上昇させながら、滑動型枠の内
側にコンクリートを連続打設していくので、急速施工が
可能となるとともに、スリップフォーム工法の特性上、
足場や型枠の組立、解体並びに撤去の作業が不要とな
る。
In the method for constructing a steel pipe / concrete composite structure pier according to the present invention, first, the hollow steel pipe is erected in advance using a crane, a predetermined reinforcing work is performed, and then the hollow steel pipe is used as a lifting support. Since the sliding form device is arranged and then concrete is continuously poured inside the sliding form while the sliding form device is raised, rapid construction is possible, and the characteristics of the slip form method can be improved. ,
The work of assembling, dismantling, and removing scaffolds and forms is eliminated.

【0010】また、PCストランドを縦筋に巻き付けて
横筋とする場合、上述した急速施工能力はさらに向上す
る。
[0010] When the PC strand is wound around a vertical streak to form a horizontal streak, the above-mentioned rapid construction ability is further improved.

【0011】また、タワークレーンを中空鋼管内に設置
する場合、当該クレーンだけでかなりの領域をカバーす
ることが可能となり、クレーンの設置台数を少なくする
ことができる。
When a tower crane is installed in a hollow steel pipe, a considerable area can be covered by the crane alone, and the number of crane installations can be reduced.

【0012】さらに、タワークレーンに作業足場を昇降
自在に取り付けた場合、中空鋼管のセグメントの接合、
鉄筋保持金具の取付け、ブラケットの盛り替え等の各作
業を安全確実にかつ効率よく行うことができる。
Further, when the work scaffold is attached to the tower crane so as to be able to move up and down, joining of the hollow steel pipe segments,
Each operation such as mounting of the reinforcing metal holding bracket and changing of the bracket can be performed safely and securely and efficiently.

【0013】[0013]

【実施例】以下、本発明の鋼管・コンクリート複合構造
橋脚の施工方法の実施例について、添付図面を参照して
説明する。
DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS An embodiment of a method for constructing a steel pipe / concrete composite structure pier according to the present invention will be described below with reference to the accompanying drawings.

【0014】図1は、本実施例の鋼管・コンクリート複
合構造橋脚の施工方法の手順を示すフローチャートであ
る。本実施例においては、まず、図2(a) に示すように
基礎1上に中空鋼管2の立ち上がり部分を立設し、当該
中空鋼管2の下部内側にコンクリート21を打設して基
礎1との一体化を図るとともに、通常の型枠などを用い
て中空鋼管2の周囲にコンクリート22を打設し、下部
躯体3aを構築する(図1、ステップ101)。
FIG. 1 is a flow chart showing the procedure of a method for constructing a steel pipe / concrete composite structure pier according to this embodiment. In this embodiment, first, as shown in FIG. 2 (a), a rising portion of a hollow steel pipe 2 is erected on a foundation 1 and concrete 21 is cast inside the lower part of the hollow steel pipe 2 to form a connection with the foundation 1. And a concrete 22 is cast around the hollow steel pipe 2 using a normal formwork or the like to construct the lower skeleton 3a (FIG. 1, step 101).

【0015】ここで、中空鋼管2は、例えば径が数m、
厚みが10数mm程度のものを使用するが、径や肉厚に
応じて所定の大きさのセグメントに予め分割しておき、
これらを溶接や高力ボルト接合によって現場で接合して
いくのがよい。かかるセグメントは、高さ方向に継いで
いく輪切り状のものでもよいし、当該輪切り状のものを
さらに周方向に分割したパネル状のものでもよい。
The hollow steel pipe 2 has a diameter of several meters, for example.
A thickness of about 10 and a few mm is used, but it is divided into segments of a predetermined size according to the diameter and the wall thickness,
It is advisable to join these on-site by welding or high-strength bolt joining. Such a segment may be in the shape of a round slice that continues in the height direction, or may be in the form of a panel that is further divided in the circumferential direction.

【0016】次に、図2(b) に示すように中空鋼管2内
のコンクリート21の上にタワークレーン7を設置し、
次いで、当該タワークレーン7を用いて中空鋼管のパネ
ル状セグメント2aを所定位置に建て込み、溶接等によ
って順次接合する(図1、ステップ102)。セグメン
ト2aの接合にあたっては、タワークレーン7のポスト
に昇降自在に取り付けた作業足場42を利用して行う。
なお、中空鋼管のセグメント2aの建込みに伴って、タ
ワークレーン7を適宜クライミングさせるとともに、作
業足場42も上方に移動させる。
Next, as shown in FIG. 2 (b), the tower crane 7 is set on the concrete 21 in the hollow steel pipe 2,
Next, the panel-shaped segment 2a of the hollow steel pipe is erected at a predetermined position by using the tower crane 7, and sequentially joined by welding or the like (FIG. 1, step 102). The joining of the segments 2a is performed using a work scaffold 42 attached to the post of the tower crane 7 so as to be able to move up and down.
In addition, the tower crane 7 is appropriately climbed along with the installation of the hollow steel pipe segment 2a, and the work platform 42 is also moved upward.

【0017】次に、図3(a) に示すように中空鋼管2を
所定高さまで組み上げた後、その上端付近にブラケット
9を固着し、PC鋼線等で形成したワイヤー41を介し
て滑動型枠装置8を吊り下げる(図1、ステップ10
3)。すなわち、中空鋼管2は、滑動型枠装置8を支持
しながらこれを吊り上げていくための吊り上げ支持台と
して機能する。
Next, as shown in FIG. 3 (a), after assembling the hollow steel pipe 2 to a predetermined height, a bracket 9 is fixed near the upper end thereof, and a sliding die is formed via a wire 41 formed of a PC steel wire or the like. The frame device 8 is suspended (FIG. 1, step 10).
3). That is, the hollow steel pipe 2 functions as a hoisting support base for hoisting the sliding formwork device 8 while supporting it.

【0018】なお、建て込みが終わった中空鋼管2に
は、後述する縦筋を所定位置において固定するための鉄
筋保持金具12を溶接等で取り付ける。かかる鉄筋保持
金具12は、予め地上において中空鋼管2のセグメント
2aに固着しておいてもよいし、所定位置に建て込んだ
後で作業足場42を利用して取り付けるようにしてもよ
い。
The hollow steel pipe 2 that has been built up is fitted with a reinforcing bar holding metal fitting 12 for fixing a vertical bar to be described later at a predetermined position by welding or the like. The rebar holding metal fitting 12 may be fixed to the segment 2a of the hollow steel pipe 2 on the ground in advance, or may be mounted at a predetermined position and then attached using the work scaffold 42.

【0019】滑動型枠装置8には、センターホールジャ
ッキ等の油圧ジャッキ(図示せず)を備えてあり、ワイ
ヤー41を反力として装置全体を上昇させることができ
るようになっている。
The sliding formwork device 8 is provided with a hydraulic jack (not shown) such as a center hole jack so that the entire device can be lifted by using the wire 41 as a reaction force.

【0020】次に、図3(b) に示すように、縦筋5aを
吊り込んで鉄筋保持金具12に位置決めするとともに、
機械継手、圧接等によって先行施工された縦筋に連結す
る(図1、ステップ104)。縦筋5aの吊込みにあた
っては、ある程度地上で先組しておくのがよい。
Next, as shown in FIG. 3 (b), the vertical bar 5a is suspended and positioned on the reinforcing bar holding fitting 12, and
It is connected to the pre-constructed vertical streak by mechanical joint, pressure welding, etc. (FIG. 1, step 104). Before suspending the vertical streaks 5a, it is preferable to assemble them on the ground to some extent.

【0021】一方、縦筋5aの建込みが終了したところ
から、図4の詳細図に示すように、滑動型枠装置8の作
業足場10に設置された鋼線リールスタンド13からP
Cストランド5bを繰り出し、これを自動巻き付け機1
4によって縦筋5aに所定のピッチで螺旋状に巻き付け
ていく(図1、ステップ105)。鋼線リールスタンド
13は、PCストランド5bを繰り出しながら作業足場
10に設けたレール上を走行し、中空鋼管2の回りを周
回できるようになっている。
On the other hand, after the vertical streaks 5a have been erected, as shown in the detailed view of FIG.
The C strand 5b is unwound, and is wound by the automatic winding machine 1
4, the wire is spirally wound around the vertical streak 5a at a predetermined pitch (step 105 in FIG. 1). The steel wire reel stand 13 travels on the rails provided on the work scaffold 10 while paying out the PC strand 5b, and can orbit the hollow steel pipe 2.

【0022】PCストランド5bは、例えば10mm程
度の径のものを縦筋5aの回りに数百mmピッチで巻き
付けるのがよい。かかるPCストランド5bを巻き付け
ることにより、コンクリートの側方を拘束して当該コン
クリートの圧縮強度を向上させるとともに、コンクリー
トのひび割れ、肌落ちあるいは剥落を防止し、破壊に至
るまでの靱性を大きくして耐震性を向上させることがで
きる。
The PC strand 5b is preferably wound, for example, with a diameter of about 10 mm around the vertical streak 5a at a pitch of several hundred mm. By winding such PC strands 5b, the lateral sides of the concrete are restrained to improve the compressive strength of the concrete, and at the same time, cracking, skin drop or peeling of the concrete is prevented, and the toughness up to the destruction is increased to increase the earthquake resistance. It is possible to improve the sex.

【0023】次に、図3(b) に示すように上述したジャ
ッキを作動させて滑動型枠装置8を上昇させつつ、当該
滑動型枠装置8に設けた型枠11と中空鋼管2との間に
コンクリートを連続打設する(図1、ステップ10
6)。
Next, as shown in FIG. 3 (b), the above-described jack is operated to raise the sliding form device 8, and at the same time, the form 11 and the hollow steel pipe 2 provided on the sliding form device 8 are connected. Continuously cast concrete in between (Fig. 1, Step 10)
6).

【0024】なお、橋脚断面形状に合わせてほぼ円形に
形成した腹起材を型枠11の背面に取り付けておき、当
該腹起材によってコンクリートの圧力を支持するように
構成しておくのがよい。
It is preferable that a bellows formed in a substantially circular shape in accordance with the cross-sectional shape of the pier is attached to the back of the formwork 11 so that the pressure of the concrete is supported by the bellows. .

【0025】かかる手順を繰り返すことによって図5に
示す橋脚の中間躯体3bを構築する。なお、橋脚の高さ
があまり高くない場合には、中空鋼管2を一度に設計高
さまで組み上げた後で滑動型枠装置を配置してコンクリ
ート打設を行い、橋脚が高い場合には、中空鋼管の建込
み作業をコンクリート打設に先行させながら並行して行
い、必要に応じてブラケット9を上方に盛り替えるよう
にしてもよい。
By repeating this procedure, an intermediate skeleton 3b of the pier shown in FIG. 5 is constructed. If the height of the pier is not so high, the hollow steel pipe 2 is assembled to the design height at a time, and then the sliding formwork device is placed and concrete is cast. If the pier is high, the hollow steel pipe is used. May be performed in parallel with the concrete placing, and the bracket 9 may be rearranged upward if necessary.

【0026】最後に、同図に示すように、橋桁4に隣接
する上部躯体3cを構築し、橋脚の躯体3の施工を完了
する。上部躯体3cの構築にあたっては、中空鋼管2と
橋桁4との一体性を高めるため、中空鋼管2の上部内側
に予め蓋等(図示せず)を設けておき、当該蓋の上方に
コンクリートを充填するのがよい。
Finally, as shown in the figure, the upper frame 3c adjacent to the bridge girder 4 is constructed, and the construction of the frame 3 of the pier is completed. In order to increase the integrity of the hollow steel pipe 2 and the bridge girder 4 in constructing the upper skeleton 3c, a lid or the like (not shown) is previously provided inside the upper portion of the hollow steel pipe 2 and concrete is filled above the lid. Good to do.

【0027】図6は、上述の手順で施工された躯体3を
示したものであり、ほぼ円形の中空鋼管2の周囲にコン
クリート31が被覆され、さらに、当該コンクリート3
1の表面近傍には、縦筋5aおよび横筋としてのPCス
トランド5bからなる鉄筋5が配筋されている。
FIG. 6 shows the skeleton 3 constructed by the above-mentioned procedure. The substantially circular hollow steel pipe 2 is covered with concrete 31, and the concrete 3 is further covered.
In the vicinity of the surface 1, a reinforcing bar 5 composed of a vertical bar 5 a and a PC strand 5 b as a horizontal bar is arranged.

【0028】以上説明したように、本実施例の鋼管・コ
ンクリート複合構造橋脚の施工方法によれば、まず、中
空鋼管を先行建て込みし、所定の配筋を行った後、当該
中空鋼管に反力をとって滑動型枠装置を上昇させながら
コンクリートを連続的に打設するようにしたので、短期
間に橋脚の躯体を構築することができ、高さのある橋脚
の急速施工が可能となるとともに、スリップフォーム工
法の特性上、作業足場や型枠の組立、解体並びに撤去が
不要となる。
As described above, according to the method for constructing a steel pipe / concrete composite structure pier of the present embodiment, first, a hollow steel pipe is erected first, a predetermined reinforcing arrangement is performed, and then the hollow steel pipe is countered to the hollow steel pipe. Since the concrete is continuously poured while the sliding form device is raised with the force, it is possible to build the pier frame in a short period of time, enabling rapid construction of tall piers. At the same time, due to the characteristics of the slip-form method, there is no need to assemble, disassemble, or remove the work scaffold or formwork.

【0029】特に、フープ筋であるPCストランドを自
動巻き付け機等を用いて縦筋に巻回するようにすれば、
その急速施工能力はさらに向上する。
In particular, if the PC strand, which is a hoop line, is wound around a vertical line using an automatic winding machine or the like,
Its rapid construction ability is further improved.

【0030】そして、当該方法によって形成された橋脚
は、中空鋼管とコンクリートとの合成構造となり、当該
中空鋼管に大きな曲げ耐力およびせん断耐力を負担させ
ることができる。
The pier formed by this method has a composite structure of a hollow steel pipe and concrete, and the hollow steel pipe can bear a large bending strength and a shear strength.

【0031】また、中空鋼管内にタワークレーンを設置
するようにしたので、当該タワークレーン1台の作業半
径でかなりの領域をカバーすることが可能となり、従来
のように、橋脚の近傍に2台、3台と設置する必要がな
くなる。
Since the tower crane is installed in the hollow steel pipe, it is possible to cover a considerable area with the working radius of one tower crane. There is no need to install three units.

【0032】また、当該タワークレーンに昇降自在に作
業足場を取り付けるようにしたので、中空鋼管のセグメ
ントの接合、滑動型枠装置を吊持するためのブラケット
の取付けおよび取り外し、並びに鉄筋保持金具の取付け
を安全確実にかつ効率よく行うことが可能となる。
Also, since the work scaffold is attached to the tower crane so as to be able to move up and down, the joining of the segments of the hollow steel pipe, the attachment and detachment of the bracket for suspending the sliding formwork apparatus, and the attachment of the reinforcing steel holding bracket. Can be performed securely and efficiently.

【0033】本実施例では、縦筋5aを配筋するように
したが、曲げ耐力等をすべて中空鋼管2に負担させ、主
筋5aを実質的に省略できる場合には、縦筋の配筋工程
を省略してもよい。かかる構成の場合には、煩雑な縦筋
の配筋作業を省いて全体の工期をさらに短縮することが
できる。
In the present embodiment, the longitudinal bars 5a are arranged. However, if all the bending strength and the like are borne by the hollow steel pipe 2 and the main bars 5a can be substantially omitted, the process of arranging the longitudinal bars is performed. May be omitted. In the case of such a configuration, it is possible to further shorten the entire construction period by omitting complicated arrangement work of the vertical streaks.

【0034】[0034]

【発明の効果】以上述べたように、本発明の鋼管・コン
クリート複合構造橋脚の施工方法によれば、中空鋼管を
基礎に立設し、次いで、当該中空鋼管を吊り上げ支持台
として滑動型枠装置を配置し、次いで、当該滑動型枠装
置に設けた滑動型枠の内側にコンクリートを打設して前
記中空鋼管の周囲にコンクリートを被覆するようにした
ので、十分な曲げ強度およびせん断強度をもつ橋脚を急
速施工することが可能となる。
As described above, according to the method for constructing a steel pipe / concrete composite structure pier of the present invention, a hollow steel pipe is erected on a foundation, and then the hollow steel pipe is used as a hoisting support stand for a sliding formwork device. Then, concrete was placed inside the sliding formwork provided in the sliding formwork device to coat the surroundings of the hollow steel pipe with concrete, so that it has sufficient bending strength and shear strength. It enables rapid construction of bridge piers.

【0035】[0035]

【図面の簡単な説明】[Brief description of drawings]

【図1】本実施例の鋼管・コンクリート複合構造橋脚の
施工方法の手順を示したフローチャート。
FIG. 1 is a flowchart illustrating a procedure of a method for constructing a steel pipe / concrete composite structure pier according to the present embodiment.

【図2】(a)は、中空鋼管の立ち上がり部分を構築する
様子を示した図、(b)は、中空鋼管のセグメントをコン
クリート打設に先行して建て込んでいく様子を示した
図。
FIG. 2 (a) is a diagram showing how a rising portion of a hollow steel pipe is constructed, and FIG. 2 (b) is a diagram showing how a segment of the hollow steel pipe is built prior to concrete pouring.

【図3】(a) は、建て込んだ中空鋼管を吊り上げ支持台
として滑動型枠装置を上昇させコンクリートを連続打設
していく様子を示した断面図、(b) は同じく側面図。
FIG. 3 (a) is a cross-sectional view showing a state in which a sliding form device is lifted up by using a built-in hollow steel pipe as a lifting support and concrete is continuously poured, and FIG. 3 (b) is a side view of the same.

【図4】同じく側面詳細図。FIG. 4 is a detailed side view of the same.

【図5】(a) は本実施例に係る鋼管・コンクリート複合
構造橋脚の施工方法によって形成された橋脚を橋軸方向
から見た断面図、(b) は同じく橋軸に直交する方向から
見た側面図。
FIG. 5A is a cross-sectional view of a pier formed by the method of constructing a steel pipe / concrete composite structure pier according to the present embodiment, viewed from the bridge axis direction, and FIG. Side view.

【図6】図5のA―A線に沿う水平断面図。FIG. 6 is a horizontal sectional view taken along line AA of FIG. 5;

【符号の説明】[Explanation of symbols]

101 中空鋼管立ち上がり部分の構築工程 102 中空鋼管建込み工程 103 滑動型枠配置工程 104 配筋工程 105 PCストランド巻き付け工程 106 コンクリート打設工程 1 基礎 2 中空鋼管 3 躯体 4 橋桁 5 鉄筋 5a 縦筋 5b PCストランド 8 滑動型枠装置 9 ブラケット 12 鉄筋保持金具 21、22、31 コンクリート 101 Building process of hollow steel pipe rising part 102 Hollow steel pipe building process 103 Sliding form placing process 104 Reinforcing process 105 PC strand winding process 106 Concrete placing process 1 Foundation 2 Hollow steel tube 3 Body 4 Bridge girder 5 Reinforcing bar 5a Vertical bar 5b PC Strand 8 Sliding formwork device 9 Bracket 12 Reinforcing metal fittings 21, 22, 31 Concrete

Claims (4)

【特許請求の範囲】[Claims] 【請求項1】 中空鋼管を基礎に立設し、次いで、当該
中空鋼管を吊り上げ支持台として滑動型枠装置を配置
し、次いで、当該滑動型枠装置に設けた滑動型枠の内側
にコンクリートを打設して前記中空鋼管の周囲にコンク
リートを被覆することを特徴とする鋼管・コンクリート
複合構造橋脚の施工方法。
1. A hollow steel pipe is erected on a foundation, then a sliding formwork device is arranged by using the hollow steel pipe as a lifting support, and concrete is then placed inside the sliding formwork provided in the sliding formwork device. A method for constructing a steel pipe / concrete composite structure pier, which comprises casting and coating concrete around the hollow steel pipe.
【請求項2】 前記コンクリート打設工程の前に、前記
中空鋼管の外周囲を包囲した状態で構造断面の表面側に
沿ってPCストランドを巻回する請求項1記載の鋼管・
コンクリート複合構造橋脚の施工方法。
2. The steel pipe according to claim 1, wherein before the concrete pouring step, the PC strand is wound along the surface side of the structural cross section while surrounding the outer periphery of the hollow steel pipe.
Construction method of concrete composite structure pier.
【請求項3】 前記中空鋼管内にタワークレーンを設置
した請求項1記載の鋼管・コンクリート複合構造橋脚の
施工方法。
3. The method for constructing a steel pipe / concrete composite structure pier according to claim 1, wherein a tower crane is installed in the hollow steel pipe.
【請求項4】 前記タワークレーンに所定の作業足場を
昇降自在に取り付けた請求項3記載の鋼管・コンクリー
ト複合構造橋脚の施工方法。
4. The method for constructing a steel pipe / concrete composite structure pier according to claim 3, wherein a predetermined work scaffold is attached to the tower crane so as to be able to move up and down.
JP6301575A 1994-11-10 1994-11-10 Construction method of steel pipe / concrete composite structure pier Expired - Fee Related JP2639361B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP6301575A JP2639361B2 (en) 1994-11-10 1994-11-10 Construction method of steel pipe / concrete composite structure pier

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP6301575A JP2639361B2 (en) 1994-11-10 1994-11-10 Construction method of steel pipe / concrete composite structure pier

Publications (2)

Publication Number Publication Date
JPH08134848A true JPH08134848A (en) 1996-05-28
JP2639361B2 JP2639361B2 (en) 1997-08-13

Family

ID=17898600

Family Applications (1)

Application Number Title Priority Date Filing Date
JP6301575A Expired - Fee Related JP2639361B2 (en) 1994-11-10 1994-11-10 Construction method of steel pipe / concrete composite structure pier

Country Status (1)

Country Link
JP (1) JP2639361B2 (en)

Cited By (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP2241431A1 (en) * 2009-04-17 2010-10-20 General Electric Company Vertical manufacturing of composite wind turbine tower
CN106049286A (en) * 2016-06-15 2016-10-26 中交公局桥隧工程有限公司 Integral lifting and installation construction method for prefabricated temporary steel pipe brackets
CN106337368A (en) * 2016-08-25 2017-01-18 中国十七冶集团有限公司 Construction bracket for ultrahigh thin-wall pier template
CN106930192A (en) * 2017-04-21 2017-07-07 中交公局第工程有限公司 Assembled variable cross-section contracture sliding mode system and its construction method
CN107794932A (en) * 2017-11-06 2018-03-13 固远晨通科技发展有限公司 A kind of light-weight foamed concrete backfill bridge pier structure
CN108149577A (en) * 2017-12-05 2018-06-12 上海建工七建集团有限公司 A kind of steel bracket system and its installation method
CN109056506A (en) * 2018-07-27 2018-12-21 北京市政路桥管理养护集团有限公司 Plug-in type post-tensioning prestressing without bondn section assembling concrete pier of steel tube
CN114164763A (en) * 2021-11-10 2022-03-11 中交第四航务工程局有限公司 Construction method of bridge pier column system
CN114411568A (en) * 2022-03-02 2022-04-29 四川省交通建设集团股份有限公司 Asynchronous construction method for steel tube concrete lattice hollow pier
CN114482555A (en) * 2021-12-27 2022-05-13 新泰市建筑安装工程有限公司 Concrete circulating pouring device and using method thereof
CN114908675A (en) * 2022-05-26 2022-08-16 中交路桥华东工程有限公司 Hollow thin-wall high pier construction method
CN118004904A (en) * 2024-04-08 2024-05-10 中铁三局集团有限公司 Hoisting type construction work platform

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH06306817A (en) * 1993-04-20 1994-11-01 Ohbayashi Corp Cooling method of concrete in bridge pier construction method
JPH073727A (en) * 1993-06-18 1995-01-06 Nippon Steel Corp Pedestal structure body and its construction

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH06306817A (en) * 1993-04-20 1994-11-01 Ohbayashi Corp Cooling method of concrete in bridge pier construction method
JPH073727A (en) * 1993-06-18 1995-01-06 Nippon Steel Corp Pedestal structure body and its construction

Cited By (19)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101920538A (en) * 2009-04-17 2010-12-22 通用电气公司 The vertical manufacturing of composite wind turbine tower
US7927445B2 (en) 2009-04-17 2011-04-19 General Electric Company Vertical manufacturing of composite wind turbine tower
EP2241431A1 (en) * 2009-04-17 2010-10-20 General Electric Company Vertical manufacturing of composite wind turbine tower
CN106049286A (en) * 2016-06-15 2016-10-26 中交公局桥隧工程有限公司 Integral lifting and installation construction method for prefabricated temporary steel pipe brackets
CN106049286B (en) * 2016-06-15 2017-12-01 中交一公局桥隧工程有限公司 A kind of prefabricated interim steel pipe support integral hoisting construction method of installation
CN106337368A (en) * 2016-08-25 2017-01-18 中国十七冶集团有限公司 Construction bracket for ultrahigh thin-wall pier template
CN106337368B (en) * 2016-08-25 2018-06-29 中国十七冶集团有限公司 A kind of hypervelocity Thin-Wall Piers template construction stent
CN106930192A (en) * 2017-04-21 2017-07-07 中交公局第工程有限公司 Assembled variable cross-section contracture sliding mode system and its construction method
CN107794932B (en) * 2017-11-06 2023-10-03 固远晨通科技发展有限公司 Pier structure is backfilled to foam lightweight concrete
CN107794932A (en) * 2017-11-06 2018-03-13 固远晨通科技发展有限公司 A kind of light-weight foamed concrete backfill bridge pier structure
CN108149577A (en) * 2017-12-05 2018-06-12 上海建工七建集团有限公司 A kind of steel bracket system and its installation method
CN109056506A (en) * 2018-07-27 2018-12-21 北京市政路桥管理养护集团有限公司 Plug-in type post-tensioning prestressing without bondn section assembling concrete pier of steel tube
CN114164763A (en) * 2021-11-10 2022-03-11 中交第四航务工程局有限公司 Construction method of bridge pier column system
CN114482555A (en) * 2021-12-27 2022-05-13 新泰市建筑安装工程有限公司 Concrete circulating pouring device and using method thereof
CN114411568A (en) * 2022-03-02 2022-04-29 四川省交通建设集团股份有限公司 Asynchronous construction method for steel tube concrete lattice hollow pier
CN114411568B (en) * 2022-03-02 2023-08-15 四川省交通建设集团股份有限公司 Asynchronous construction method for hollow pier of concrete filled steel tube lattice
CN114908675A (en) * 2022-05-26 2022-08-16 中交路桥华东工程有限公司 Hollow thin-wall high pier construction method
CN114908675B (en) * 2022-05-26 2023-05-05 中交路桥华东工程有限公司 Hollow thin-wall high pier construction method
CN118004904A (en) * 2024-04-08 2024-05-10 中铁三局集团有限公司 Hoisting type construction work platform

Also Published As

Publication number Publication date
JP2639361B2 (en) 1997-08-13

Similar Documents

Publication Publication Date Title
EP2479430B1 (en) Method for assembling shell segments for forming tower sections of a hybrid wind turbine tower
JP2639361B2 (en) Construction method of steel pipe / concrete composite structure pier
CN210975503U (en) Large-span prefabricated assembled bent cap and pier stand connection structure
JP4252177B2 (en) Steel / concrete composite structure pier construction method
KR20070010449A (en) Construction method for arched bridge
CN105780922A (en) Construction method for segmental formwork hoisting system of large-span steel reinforced concrete transfer truss
JP2750368B2 (en) Construction method of reactor containment top slab
CN112814163B (en) Construction method of building without template
JPH09317183A (en) Construction method of building
JPH1054010A (en) Steel pipe and concrete composite construction bridge pier
JPH07300817A (en) Concrete-filled steel pipe truss pier and construction method
JP4476096B2 (en) Construction method of large high-rise wind farm
JPH0657956A (en) Construction of concrete structure
JP3399873B2 (en) How to build a dome structure
JP3518666B2 (en) Construction method of steel pipe / concrete composite structure pier
CN108797350B (en) Tower column inner and outer stiff skeleton device and construction method thereof
JP2536395B2 (en) Construction method of steel pipe / concrete composite structure pier
JP2001295404A (en) Method for driving hollow pipe into reinforced permanent form
JP2768285B2 (en) Steel pipe / concrete composite pier
JP2591422B2 (en) Steel pipe / concrete composite pier
JPH08326014A (en) Structure and method of reinforcing stud made of steel
JP2002037583A (en) Position-holding jig also used for hanging reinforced basket
JPH08165662A (en) Construction method of underground structure
JPH03125755A (en) Constructing method for cylindrical multistoried structure
JPH108725A (en) Constructing method for building frame

Legal Events

Date Code Title Description
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 19970325

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20080425

Year of fee payment: 11

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20090425

Year of fee payment: 12

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20100425

Year of fee payment: 13

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20100425

Year of fee payment: 13

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20110425

Year of fee payment: 14

S531 Written request for registration of change of domicile

Free format text: JAPANESE INTERMEDIATE CODE: R313531

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20110425

Year of fee payment: 14

R350 Written notification of registration of transfer

Free format text: JAPANESE INTERMEDIATE CODE: R350

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20110425

Year of fee payment: 14

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20120425

Year of fee payment: 15

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20120425

Year of fee payment: 15

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20130425

Year of fee payment: 16

LAPS Cancellation because of no payment of annual fees