JP3518666B2 - Construction method of steel pipe / concrete composite structure pier - Google Patents

Construction method of steel pipe / concrete composite structure pier

Info

Publication number
JP3518666B2
JP3518666B2 JP15199198A JP15199198A JP3518666B2 JP 3518666 B2 JP3518666 B2 JP 3518666B2 JP 15199198 A JP15199198 A JP 15199198A JP 15199198 A JP15199198 A JP 15199198A JP 3518666 B2 JP3518666 B2 JP 3518666B2
Authority
JP
Japan
Prior art keywords
steel pipe
strand
pier
concrete
composite structure
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
JP15199198A
Other languages
Japanese (ja)
Other versions
JPH11323843A (en
Inventor
敏明 加藤
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Obayashi Corp
Original Assignee
Obayashi Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Obayashi Corp filed Critical Obayashi Corp
Priority to JP15199198A priority Critical patent/JP3518666B2/en
Publication of JPH11323843A publication Critical patent/JPH11323843A/en
Application granted granted Critical
Publication of JP3518666B2 publication Critical patent/JP3518666B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Description

【発明の詳細な説明】 【0001】 【発明の属する技術分野】本発明は、主として高さが数
十m程度以下の中低橋脚に適用される鋼管・コンクリー
ト複合構造橋脚の施工方法に関する。 【0002】 【従来の技術】橋脚を構築するには、縦筋及び横筋を配
筋し、その外周に型枠を建て込んだ後、該型枠の内側に
コンクリートを打設する方法が一般的であるが、かかる
方法では、多数の鉄筋が交錯して配筋作業に時間を要す
るほか、型枠の組立及び解体にも多くの手間がかかり、
橋脚の高さが高くなればなるほど急速施工という点では
不利になる。 【0003】かかる状況を打開すべく、本出願人は、先
行して建て込まれた鋼管の頂部近傍に反力台を設置し、
該反力台から滑動型枠を吊り上げつつ該滑動型枠の内側
にコンクリートを連続打設することによって高橋脚でも
急速施工が可能でしかも鋼管による耐震性の向上を図る
ことが可能な施工方法を開発した(特許第259142
2号公報、特許第2536395号公報参照)。 【0004】 【発明が解決しようとする課題】ここで、高さが数十
m、例えば20〜30m程度以下の中低橋脚を構築する
にあたっても、上述した施工方法を適用することによっ
て通常施工による橋脚よりも耐震性を向上させることは
可能であるが、滑動型枠に関連する設備費用が割高とな
るとともに、その設置解体に時間が必要なことから必ず
しも工期を短縮できるとは限らないという問題を生じて
いた。 【0005】本発明は、上述した事情を考慮してなされ
たもので、数十m程度の高さの中低橋脚を急速施工可能
な鋼管・コンクリート複合構造橋脚の施工方法を提供す
ることを目的とする。 【0006】 【課題を解決するための手段】上記目的を達成するた
め、本発明に係る鋼管・コンクリート複合構造橋脚の施
工方法は請求項1に記載したように、先行して立設され
た鋼管の周囲に所定の補強材を配置し、次いで、該補強
材の周囲に型枠パネルを建て込んだ後、該型枠パネルの
内側にコンクリートを打設する鋼管・コンクリート複合
構造橋脚の施工方法であって、前記補強材を縦筋と該縦
筋の周囲に巻き付けられるPCストランドとで構成し、
鉛直軸線廻りに旋回自在な回転台の上にPCストランド
用ドラムが水平軸線廻りに回動自在に保持されてなるP
Cストランド引出し機を前記鋼管の頂部近傍に設置し、
該PCストランド引出し機から前記PCストランドを引
き出すものである。 【0007】 【0008】 【0009】本発明に係る鋼管・コンクリート複合構造
橋脚の施工方法においては、まず、鋼管を基礎等の上に
先行して立設し、次いで該鋼管の周囲に縦筋等の補強材
を配置する。次に、補強材の周囲に型枠パネルを建て込
み、しかる後に該型枠パネル内にコンクリートを打設す
る。 【0010】このようにすると、補強材の取付け及び型
枠パネルの建込みにあたり、先行立設された鋼管から反
力をとることができるのでこれらの作業が容易になると
ともに、スリップフォーム工法では欠かせない吊上げ設
備の設置並びに解体の手間がなくなり、さらに、コンク
リート打設に必要な型枠をパネル状としたことにより、
型枠の組立並びに解体の手間が減少する。 【0011】したがって、数十m程度の高さの橋脚に関
しては、高橋脚には最適であるスリップフォーム工法を
採用するよりも、施工に要するコストと工期を大幅に低
減することができる。そして、本発明に係る施工方法に
よって形成された橋脚は、鋼管とコンクリートとの合成
構造となるとともに、該鋼管に大きな曲げ耐力およびせ
ん断耐力を負担させることが可能となるため、従来のR
C橋脚よりも耐震性の大幅な改善が期待できる。 【0012】鋼管については、太径のものを単一で立設
するようにしてもよいし、細径のものを複数林立させる
ようにしてもよい。ここで、太径の場合には、鉛直方向
及び周方向にセグメント状のものを接合し、最終的に一
本の太径鋼管とすることが考えられるし、細径の場合に
は、鉛直方向にのみ接合していくことが考えられる。ま
た、橋脚の高さが低い場合には、一体製作された鋼管を
現場に搬入して立設することも考えられる。 【0013】鋼管は、主として円形中空断面のものが対
象となるが、角形鋼管等でもよいことは言うまでもな
い。また、橋脚の断面形状については任意であり、特に
複数の鋼管を林立させる場合には橋脚断面を所望の形状
に設定することができる。 【0014】補強材は、従来通り、縦方向及び周方向と
も通常の鉄筋を使用するようにしてもかまわないが、か
かる補強材を縦筋と該縦筋の周囲に巻き付けられるPC
ストランドとで構成するならば、スパイラル筋等を使用
する際に必要となる曲げ加工や該スパイラル筋相互の接
合作業が不要となるとともに、PCストランドが軽量か
つ高引張強度であるがゆえに取付け時の作業性及び所要
ピッチの改善を図ることが可能となり、さらなる急速施
工が可能となる。 【0015】ここで、PCストランドを縦筋に巻き付け
る際、鋼管の周囲に作業足場を構築して該足場に無端軌
道を敷設し、該軌道に沿ってPC鋼線リールスタンドを
周回させながらPCストランドを螺旋状に繰り出すよう
にしてもよいが、鉛直軸線廻りに旋回自在な回転台の上
にPCストランド用ドラムが水平軸線廻りに回動自在に
保持されてなるPCストランド引出し機を前記鋼管の頂
部近傍に設置し、該PCストランド引出し機から前記P
Cストランドを引き出すようにするならば、無端軌道を
敷設するための作業足場を構築する手間や設置スペース
が不要になるとともに、無端軌道をPC鋼線リールスタ
ンドとともにせり上げていくための設備も不要となる。 【0016】 【発明の実施の形態】以下、本発明に係る鋼管・コンク
リート複合構造橋脚の施工方法の実施の形態について、
添付図面を参照して説明する。なお、従来技術と実質的
に同一の部品等については同一の符号を付してその説明
を省略する。 【0017】(第1実施形態)図1は、本実施形態に係
る鋼管・コンクリート複合構造橋脚の施工方法の手順を
示すフローチャートである。本実施形態においては、ま
ず、図2(a) に示すように基礎1上に鋼管2の立ち上が
り部分を立設し、該鋼管内の下部にコンクリート3を打
設して基礎1との一体化を図るとともに、通常の型枠な
どを用いて鋼管2の周囲にコンクリート4を打設し、下
部躯体5aを構築する(図1、ステップ101)。 【0018】次に、図2(b) に示すように鋼管2内のコ
ンクリート3上にタワークレーン6を設置し、次いで、
該タワークレーンを用いて鋼管2の構成要素であるパネ
ル状セグメント2aを所定位置に建て込み、溶接、高力
ボルト等によって高さ方向及び周方向に順次接合してい
く(図1、ステップ102)。セグメント2aの接合に
あたっては、タワークレーン6のポストに昇降自在に取
り付けた作業足場7を利用することができる。なお、鋼
管2のセグメント2aの建込みに伴って、タワークレー
ン6を適宜クライミングさせるとともに、作業足場7も
上方に移動させる。 【0019】次に、図3に示すように鋼管2を所定高さ
まで組み上げた後、鉄筋保持具11を溶接等で該鋼管に
取り付け、次いで、補強材である縦筋12をタワークレ
ーン6を利用して鋼管2の周囲に吊り込み、機械継手、
圧接等によって上方に順次連結しながら鉄筋保持具11
に固定する(図1、ステップ103)。かかる鉄筋保持
具11は、予め地上において鋼管2のセグメント2aに
固着しておいてもよいし、所定位置に建て込んだ後で作
業足場7を利用して取り付けるようにしてもよい。な
お、縦筋12は、例えば数゜ピッチで鋼管2の周囲に配
筋するが、同図(b)では便宜上、両端に見える縦筋のみ
を示してある。 【0020】次に、鋼管2の周囲に構築された作業足場
13に鋼線リールスタンド14を設置し、該鋼線リール
スタンドから補強材であるPCストランド15を繰り出
して縦筋12の周囲に螺旋状に巻き付ける(図1、ステ
ップ104)。鋼線リールスタンド14は、PCストラ
ンド15を繰り出しながら作業足場13のブラケットに
敷設した無端軌道であるレール上を走行し、鋼管2の回
りを周回できるようになっている。 【0021】PCストランド15は、例えば10mm程
度の径のものを縦筋12の回りに数百mmピッチで巻き
付けるのがよい。かかるPCストランド15を巻き付け
ることにより、コンクリートの側方を拘束して当該コン
クリートの圧縮強度を向上させるとともに、コンクリー
トのひび割れ、肌落ちあるいは剥落を防止し、破壊に至
るまでの靱性を大きくして耐震性を向上させることがで
きる。 【0022】次に、PCストランド15の巻付けが終了
した箇所に型枠パネル16を建て込む(図1、ステップ
105)。型枠パネル16は、地上にて地組し、これを
タワークレーン6で吊り込んだ後、例えばセパレータ等
を介して鋼管2から反力をとることで所定位置にしっか
りと固定することができる。 【0023】型枠パネル16は、橋脚躯体が細径であれ
ば、例えば円筒状のものを半割した形状のもので構成す
ることが可能であり、橋脚躯体が太径であれば、その径
に応じて例えば周方向に数十゜ずつ分割したもので構成
することができる。 【0024】ここで、型枠パネル16の背面にはH型
鋼、鋼管等で構成した腹起材17を設けてあり、コンク
リートの圧力を支持できるようになっている。 【0025】次に、型枠パネル16と鋼管2との間にコ
ンクリートを打設し(図1、ステップ106)、強度発
現後、解体して転用に備える。 【0026】このように鋼管2の建込み、縦筋12の取
付け、PCストランド15の巻付け、型枠パネル16の
建込み、コンクリート打設といった一連の工程を上方に
向けて適宜繰り返し、図4に示すような橋脚の中間躯体
5bを構築する。 【0027】最後に、同図に示すように、橋桁21に隣
接する上部躯体5cを構築し、橋脚の躯体5の施工を完
了する。上部躯体5cの構築にあたっては、鋼管2と橋
桁21との一体性を高めるため、鋼管2の上部内側に予
め蓋等(図示せず)を設けておき、当該蓋の上方にコン
クリートを充填するのがよい。 【0028】図5は、上述の手順で施工された躯体5を
横断面図で示したものであり、円形の鋼管2の周囲にコ
ンクリート31が巻き立てられ、該コンクリートの表面
近傍に縦筋12およびPCストランド15が配筋されて
いるのがわかる。 【0029】以上説明したように、本実施形態に係る鋼
管・コンクリート複合構造橋脚の施工方法によれば、縦
筋12やPCストランド15といった補強材の取付け及
び型枠パネル16の建込みにあたり、先行立設された鋼
管2から反力をとることができるのでこれらの作業を容
易に行うことができるとともに、スリップフォーム工法
では欠かせない吊上げ設備の設置並びに解体の手間がな
くなり、さらに、コンクリート打設に必要な型枠をパネ
ル状としたことにより、型枠の組立並びに解体の手間が
減少する。 【0030】したがって、数十m程度の高さの橋脚に関
しては、高橋脚には最適であるスリップフォーム工法を
採用するよりも、施工に要するコストと工期を大幅に低
減することができる。そして、本実施形態に係る施工方
法によって形成された橋脚5は、鋼管2とコンクリート
31との合成構造となるとともに、該鋼管に大きな曲げ
耐力およびせん断耐力を負担させることが可能となるた
め、従来のRC橋脚よりも耐震性の大幅な改善が期待で
きる。 【0031】また、本実施形態に係る鋼管・コンクリー
ト複合構造橋脚の施工方法によれば、補強材を縦筋12
と該縦筋の周囲に巻き付けられるPCストランド15と
で構成したので、縦筋12の周囲にスパイラル筋のよう
な鉄筋を配置する場合に比べて曲げ加工や鉄筋相互の接
合作業が不要となる。また、PCストランド15が軽量
かつ高引張強度であるため、取付け時の作業性や運搬時
の取り扱いが楽になるとともに所要ピッチを拡げること
が可能となり、かくして、さらなる急速施工を実現する
ことができる。 【0032】本実施形態では特に言及しなかったが、鋼
管2の建込み、縦筋12の取付け及びPCストランド1
5の巻付けについては、一度に設計高さまで行い、しか
る後に型枠パネル16の建込み及びコンクリート打設を
1リフトずつ繰り返し行うようにしてもよいし、鋼管2
の建込み等の作業とコンクリート打設に関連した作業と
を並行して行うようにしてもよい。 【0033】また、本実施形態では、分割セグメント2
aを高さ方向及び周方向に順次接合して鋼管2を構成す
るようにしたが、径や肉厚によっては輪切り状のもので
もよいし、橋脚の高さによっては、一体製作されたもの
を現場に搬入し、これを立設するようにしてもよい。 【0034】また、本実施形態では特に言及しなかった
が、型枠パネル16についてはできるだけ大型化を図る
のが施工能率がよいことは言うまでもない。 【0035】(第2実施形態)次に、第2実施形態につ
いて説明する。なお、上述の実施形態と実質的に同一の
部品等については同一の符号を付してその説明を省略す
る。 【0036】本実施形態に係る鋼管・コンクリート複合
構造橋脚の施工方法は、鋼管を単一太径とした第1実施
形態とは異なり、細径のものを複数林立させるととも
に、PCストランド15を引き出す機構についても別の
構成としてある。 【0037】すなわち、本実施形態に係る鋼管・コンク
リート複合構造橋脚の施工方法においては、まず、図6
に示すように基礎41上に4本の鋼管42の立ち上がり
部分を立設する。鋼管42を立設するにあたっては、例
えば図示しない鋼管受架台を予め根切り底に据え付け、
これに立設するようにすればよい。 【0038】次に、鋼管42の周囲に鉄筋保持具11を
溶接等で取り付けるとともに、縦筋12を同図(b)に示
すように鋼管42の周囲に建て込み、鉄筋保持具11に
固定する。 【0039】次に、鋼管42の頂部にPCストランド引
出し機43を設置し、該PCストランド引出し機からP
Cストランド15を引き出してこれを縦筋12の周囲に
巻き付け、しかる後に深礎コンクリートを打設して鋼管
42を定着固定する。 【0040】図7は、PCストランド引出し機43を示
した全体斜視図、図8はその側面図及び正面図である。
これらの図でわかるように、PCストランド引出し機4
3は、架台44の上に鉛直軸線廻りに旋回自在に回転台
45を取り付けるとともにかかる回転台45の上に4つ
のアンダーローラ47を載せ、さらに該アンダーローラ
でPCストランド15を巻いたPCストランド用ドラム
46の鍔を受けるように構成してあり、かかる構成によ
って、PCストランド用ドラム46を水平及び鉛直両軸
線廻りに回動可能な状態で保持できるようになってい
る。 【0041】ここで、回転台45には図8(a)に示すよ
うに、該回転台を手動で回転させるための回転操作アー
ム49を取り付けてあるとともに、架台44と回転台4
5との間にはディスクブレーキ48を装備してあり、該
ブレーキを操作レバー56(図7)で操作することによ
って回転台45の回転速度を調整できるようになってい
る。また、回転台45には図8(b)に示すように、アン
ダーローラ47の回転速度を調整するための回転速度調
整用ブレーキ50と、該ブレーキを操作する操作レバー
51とを設けてある。 【0042】ここで、4つのアンダーローラ47は、図
7でよくわかるように回転軸57を介して2つずつ連結
して前後に配置してあり、回転速度調整用ブレーキ50
は、図8(b)に示すようにそれらの一方の側に装備して
ある。 【0043】また、回転台45の一方の縁部には、PC
鋼線引出し用フレーム52を立設して該フレームの上方
に一対の縦ローラ53a、53aと一対の横ローラ53
b、53bとを井桁状に配設し、PCストランド用ドラ
ム46から引き出されたPCストランド15を縦ローラ
53a及び横ローラ53bで囲まれた開口である出線口
54に通すようになっており、かかる構成によってPC
ストランド15をスムーズに引き出すことができるよう
になっている。 【0044】また、回転台45には、ケージ状の保護カ
バー55を取外し自在に設置してあり、PCストランド
15の引出し作業中においてはPCストランド用ドラム
46の飛び出し(アンダーローラ47からの脱落)を防
止するとともに、PCストランド15がなくなったとき
には新しいPCストランド用ドラム46に交換できるよ
うになっている。 【0045】かかるPCストランド引出し機43を用い
てPCストランド15を縦筋12の周囲に巻き付けるに
は、PCストランド引出し機43から引き出されたPC
ストランド15の端部を例えば基礎41(図6)の上に
固定し、次いで、PCストランド15をPCストランド
引出し機43から引き出しながら下方から上方に向けて
螺旋状に縦筋12に巻き付けていけばよい。 【0046】このとき、PCストランド用ドラム46が
アンダーローラ47の作用によって水平軸線廻りに回動
するとともに、回転台45の作用によって鉛直軸線廻り
に旋回するので、PCストランド15を引き出しながら
縦筋12に螺旋状に巻き付けることができる。また、縦
ローラ53a及び横ローラ53bの摩擦低減作用によ
り、PCストランド15は、PCストランド用ドラム4
6からスムーズに引き出すことができる。なお、PCス
トランド15の引き出し速度に応じて操作レバー51を
操作しアンダーローラ47の回転速度を適宜調整すると
ともに、PCストランド15の巻回速度に応じて操作レ
バー56を操作し回転台45の回転速度を適宜調整す
る。 【0047】PCストランド引出し機43を用いたPC
ストランド15の巻付け及び鋼管42の定着固定が終了
したならば、PCストランド引出し機43をいったん取
り外した後、図9(a)に示すように鋼管42を鉛直方向
に継ぎ足し、しかる後に継ぎ足した鋼管42の頂部にP
Cストランド引出し機43を盛り替える。 【0048】次に、縦筋12を鋼管42の周囲に建て込
んで下方から延びる縦筋12に圧接継手、機械継手等に
よって連結しつつ鉄筋保持具11に固定し、次いで、該
縦筋の周囲に上述したと同様にしてPCストランド引出
し機43から引き出されたPCストランド15を巻き付
ける。 【0049】次に、PCストランド15の巻付けが終了
した箇所に型枠パネル16を建て込む。型枠パネル16
は、第1実施形態と同様、地上にて地組し、これをタワ
ークレーンで吊り込んだ後、例えばセパレータ等を介し
て鋼管42から反力をとることによって所定位置にしっ
かりと固定することができる。型枠パネル16について
の他の説明については第1実施形態と同様であるので、
ここではその説明を省略する。 【0050】次に、型枠パネル16と鋼管42との間に
コンクリートを打設し、強度発現後、解体して転用に備
える。図9(b)は、継ぎ足された鋼管42の頂部近傍ま
でコンクリートを打設して橋脚躯体の一段目の構築を終
えた様子を示した図である。 【0051】二段目についても一段目と同様の手順で構
築を行えばよい。図10は、上述した手順を繰り返し
て、PCストランド引出し機43の仮撤去、鋼管42の
継ぎ足し、PCストランド引出し機43の盛替え、縦筋
12の取付け及びPCストランド15の巻付けを終えた
様子、図11は、型枠パネル16と鋼管42との間にコ
ンクリートを打設して橋脚躯体の二段目の構築を終えた
様子をそれぞれ示した図である。 【0052】以上説明したように、本実施形態に係る鋼
管・コンクリート複合構造橋脚の施工方法によれば、第
1実施形態と同様、縦筋12やPCストランド15とい
った補強材の取付け及び型枠パネル16の建込みにあた
り、先行立設された鋼管42から反力をとることができ
るのでこれらの作業を容易に行うことができるととも
に、スリップフォーム工法では欠かせない吊上げ設備の
設置並びに解体の手間がなくなり、さらに、コンクリー
ト打設に必要な型枠をパネル状としたことにより、型枠
の組立並びに解体の手間が減少する。 【0053】したがって、数十m程度の高さの橋脚に関
しては、高橋脚には最適であるスリップフォーム工法を
採用するよりも施工に要するコストと工期を大幅に低減
することができる。そして、本実施形態に係る施工方法
によって形成された橋脚は、鋼管42とコンクリートと
の合成構造となるとともに、該鋼管に大きな曲げ耐力お
よびせん断耐力を負担させることが可能となるため、従
来のRC橋脚よりも耐震性の大幅な改善が期待できる。 【0054】また、本実施形態に係る鋼管・コンクリー
ト複合構造橋脚の施工方法によれば、補強材を縦筋12
と該縦筋の周囲に巻き付けられるPCストランド15と
で構成したので、縦筋12の周囲にスパイラル筋のよう
な鉄筋を配置する場合に比べて曲げ加工や鉄筋相互の接
合作業が不要となる。また、PCストランド15が軽量
かつ高引張強度であるため、取付け時の作業性や運搬時
の取り扱いが楽になるとともに所要ピッチを拡げること
が可能となり、かくして、さらなる急速施工を実現する
ことができる。 【0055】また、本実施形態に係る鋼管・コンクリー
ト複合構造橋脚の施工方法によれば、鉛直軸線廻りに旋
回自在な回転台45の上にPCストランド用ドラム46
が水平軸線廻りに回動自在に保持されてなるPCストラ
ンド引出し機43を鋼管42の頂部近傍に設置し、該P
Cストランド引出し機からPCストランド15を引き出
すようにしたので、無端軌道を敷設するための作業足場
を構築する手間や設置スペースが不要になるとともに、
無端軌道をPC鋼線リールスタンドとともにせり上げて
いくための設備も不要となる。 【0056】本実施形態では特に言及しなかったが、鋼
管42の建込み、縦筋12の取付け及びPCストランド
15の巻付けについては一度に設計高さまで行い、しか
る後に型枠パネル16の建込み及びコンクリート打設を
1リフトずつ繰り返し行うようにしてもよい。 【0057】 【発明の効果】以上述べたように、本発明に係る鋼管・
コンクリート複合構造橋脚の施工方法によれば、補強材
の取付け及び型枠パネルの建込みにあたり、先行立設さ
れた鋼管から反力をとることができるのでこれらの作業
を容易に行うことができるとともに、スリップフォーム
工法では欠かせない吊上げ設備の設置並びに解体の手間
がなくなり、さらに、コンクリート打設に必要な型枠を
パネル状としたことにより、型枠の組立並びに解体の手
間が減少する。 【0058】したがって、数十m程度の高さの橋脚に関
しては、高橋脚には最適であるスリップフォーム工法を
採用するよりも、施工に要するコストと工期を大幅に低
減することができる。そして、本発明に係る施工方法に
よって形成された橋脚は、鋼管とコンクリートとの合成
構造となるとともに、該鋼管に大きな曲げ耐力およびせ
ん断耐力を負担させることが可能となるため、従来のR
C橋脚よりも耐震性の大幅な改善が期待できる。 【0059】また、本発明に係る鋼管・コンクリート複
合構造橋脚の施工方法によれば、縦筋の周囲にスパイラ
ル筋のような鉄筋を配置する場合に比べて曲げ加工や鉄
筋相互の接合作業が不要となる。また、PCストランド
が軽量かつ高引張強度であるため、取付け時の作業性や
運搬時の取り扱いが楽になるとともに所要ピッチを拡げ
ることが可能となり、かくして、さらなる急速施工を実
現することができるという効果も奏する。 【0060】また、本発明に係る鋼管・コンクリート複
合構造橋脚の施工方法によれば、無端軌道を敷設するた
めの作業足場を構築する手間や設置スペースが不要にな
るとともに、無端軌道をPC鋼線リールスタンドととも
にせり上げていくための設備も不要となるという効果も
奏する。 【0061】
Description: BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a method for constructing a steel pipe / concrete composite structure pier mainly applied to a low-middle pier having a height of about several tens of meters or less. 2. Description of the Related Art In order to construct a pier, a method of arranging vertical and horizontal bars, laying a formwork on the outer periphery thereof, and then pouring concrete inside the formwork is generally used. However, in such a method, a large number of reinforcing bars are interlaced, and it takes time to arrange the reinforcing bars, and it takes much time to assemble and disassemble the formwork.
The higher the height of the pier, the more disadvantageous it is in terms of rapid construction. [0003] In order to overcome this situation, the present applicant has installed a reaction table near the top of a steel pipe previously erected,
By constructing concrete continuously inside the sliding formwork while lifting the sliding formwork from the reaction table, rapid construction is possible even on high piers and an improvement in seismic resistance using steel pipes is provided. Developed (Patent No. 259142)
No. 2, Japanese Patent No. 2536395). [0004] Here, even when constructing a middle-low bridge pier having a height of several tens of meters, for example, about 20 to 30 m or less, the above-mentioned construction method is applied to make a normal construction. Although it is possible to improve the seismic resistance compared to a pier, the problem is that the construction time associated with the sliding formwork is relatively expensive and the time required for installation and dismantling is not always shortened. Was occurring. The present invention has been made in consideration of the above circumstances, and has as its object to provide a method of constructing a steel pipe / concrete composite structure pier capable of rapidly constructing a low-middle pier having a height of about several tens of meters. And [0006] In order to achieve the above object, a method for constructing a steel pipe / concrete composite structure pier according to the present invention is, as set forth in claim 1, a steel pipe erected in advance. A predetermined reinforcing material is placed around the surroundings, and then a formwork panel is built around the reinforcing material, and then concrete is poured inside the formwork panel. The reinforcing member is composed of a vertical streak and a PC strand wound around the vertical streak,
The PC strand drum is rotatably held about a horizontal axis on a turntable that can be turned about a vertical axis.
Installing a C strand drawing machine near the top of the steel pipe;
The PC strand is drawn from the PC strand drawer. In the method of constructing a steel pipe / concrete composite structure pier according to the present invention, first, a steel pipe is first erected on a foundation or the like, and then a vertical streak or the like is provided around the steel pipe. Place reinforcements. Next, a form panel is erected around the reinforcement, and then concrete is poured into the form panel. [0010] In this way, since the reaction force can be taken from the steel pipe that has been erected before mounting the reinforcing material and installing the formwork panel, these operations are facilitated, and the slip-form method is indispensable. By eliminating the need for installation and dismantling of lifting equipment that can not be done, and by making the formwork required for concrete casting into a panel shape,
The work of assembling and dismantling the formwork is reduced. Therefore, for a pier having a height of about several tens of meters, the cost and the construction period required for the construction can be significantly reduced as compared with the case where a slip pier construction method which is optimal for a high pier is adopted. The bridge pier formed by the construction method according to the present invention has a composite structure of steel pipe and concrete, and allows the steel pipe to bear large bending strength and shear strength.
Great improvement in seismic resistance can be expected compared to the C pier. As for the steel pipe, a large diameter pipe may be erected alone, or a plurality of small diameter pipes may be erected. Here, in the case of a large diameter, it is conceivable to join segments in the vertical direction and the circumferential direction and finally form a single large-diameter steel pipe, and in the case of a small diameter, It is conceivable that they are joined only to Further, when the height of the pier is low, it is conceivable to carry the integrally manufactured steel pipe to the site and stand it. The steel pipe mainly has a circular hollow cross section, but it goes without saying that a square steel pipe or the like may be used. Further, the cross-sectional shape of the pier is arbitrary. In particular, when a plurality of steel pipes are erected, the pier cross-section can be set to a desired shape. As the reinforcing member, a normal reinforcing bar may be used in the longitudinal direction and the circumferential direction as in the past, but the reinforcing member may be wound around the longitudinal bar and the PC around which the reinforcing bar is wound.
If it is composed of strands, the bending work required when using spiral streaks and the joining work of the spiral streaks is not required, and the PC strands are lightweight and have high tensile strength, so that they can be used during installation. The workability and the required pitch can be improved, and further rapid construction is possible. Here, when the PC strand is wound around a vertical streak, a work scaffold is constructed around the steel pipe, an endless track is laid on the scaffold, and the PC strand is wound around the PC steel wire reel stand along the track. May be spirally wound, but a PC strand unwinding machine in which a PC strand drum is rotatably held about a horizontal axis on a turntable that can be turned about a vertical axis is used as the top of the steel pipe. Installed in the vicinity, and the PC strand drawer
If the C strand is pulled out, the labor and installation space for constructing a work scaffold for laying the endless track is not required, and no equipment is needed to lift the endless track together with the PC steel reel stand. It becomes. DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS Hereinafter, an embodiment of a method for constructing a steel pipe / concrete composite structure pier according to the present invention will be described.
This will be described with reference to the accompanying drawings. In addition, the same reference numerals are given to components and the like that are substantially the same as those in the related art, and description thereof is omitted. (First Embodiment) FIG. 1 is a flowchart showing a procedure of a method of constructing a steel pipe / concrete composite structure pier according to the present embodiment. In this embodiment, first, as shown in FIG. 2 (a), a rising portion of a steel pipe 2 is erected on a foundation 1, and concrete 3 is poured into a lower portion of the steel pipe to be integrated with the foundation 1. At the same time, concrete 4 is cast around the steel pipe 2 using a normal formwork or the like to construct the lower skeleton 5a (FIG. 1, step 101). Next, as shown in FIG. 2B, a tower crane 6 is set on the concrete 3 in the steel pipe 2, and then,
Using the tower crane, the panel-shaped segment 2a, which is a component of the steel pipe 2, is erected at a predetermined position, and sequentially joined in the height direction and the circumferential direction by welding, high-strength bolts, and the like (FIG. 1, step 102). . In joining the segments 2a, a work scaffold 7 attached to a post of a tower crane 6 so as to be able to move up and down can be used. In addition, the tower crane 6 is appropriately climbed along with the erection of the segment 2a of the steel pipe 2, and the work platform 7 is also moved upward. Next, as shown in FIG. 3, after assembling the steel pipe 2 to a predetermined height, a reinforcing bar holder 11 is attached to the steel pipe by welding or the like, and then a vertical bar 12 as a reinforcing material is used using a tower crane 6. And hang it around the steel pipe 2
Reinforcing bar holder 11 while being sequentially connected upward by pressure welding or the like
(Step 103 in FIG. 1). Such a reinforcing bar holder 11 may be fixed to the segment 2a of the steel pipe 2 on the ground in advance, or may be installed at a predetermined position and then attached using the work scaffold 7. The vertical streaks 12 are arranged around the steel pipe 2 at a pitch of, for example, several ゜, but for convenience, only the vertical streaks visible at both ends are shown in FIG. Next, a steel wire reel stand 14 is installed on the work scaffold 13 constructed around the steel pipe 2, and a PC strand 15 as a reinforcing material is fed out from the steel wire reel stand and spirally wound around the vertical streak 12. (Step 104 in FIG. 1). The steel wire reel stand 14 runs on a rail, which is an endless track laid on the bracket of the work platform 13, while extending the PC strand 15, and can go around the steel pipe 2. The PC strand 15 having a diameter of, for example, about 10 mm is preferably wound around the vertical streak 12 at a pitch of several hundred mm. By winding the PC strand 15, the side of the concrete is constrained to improve the compressive strength of the concrete, prevent cracking, skin falling or peeling of the concrete, and increase the toughness up to the destruction, thereby improving the seismic resistance. Performance can be improved. Next, the form panel 16 is erected at the place where the winding of the PC strand 15 is completed (FIG. 1, step 105). The formwork panel 16 is laid on the ground, suspended by a tower crane 6, and then firmly fixed at a predetermined position by taking a reaction force from the steel pipe 2 via a separator or the like. The formwork panel 16 can be constituted by, for example, a half of a cylindrical one if the pier frame is small in diameter, and if the pier frame is large in diameter, it can be formed by For example, it can be configured by dividing into several tens of squares in the circumferential direction. Here, a webbing 17 made of H-shaped steel, steel pipe, or the like is provided on the back surface of the form panel 16 so as to support the pressure of concrete. Next, concrete is cast between the form panel 16 and the steel pipe 2 (step 106 in FIG. 1). After the strength is developed, the concrete is dismantled and prepared for diversion. As described above, a series of steps such as the installation of the steel pipe 2, the installation of the vertical bar 12, the winding of the PC strand 15, the installation of the form panel 16, and the concrete placement are appropriately repeated upward, as shown in FIG. The intermediate skeleton 5b of the pier as shown in FIG. Finally, as shown in the figure, the upper skeleton 5c adjacent to the bridge girder 21 is constructed, and the construction of the pier skeleton 5 is completed. In constructing the upper skeleton 5c, a lid or the like (not shown) is provided in advance on the inside of the upper part of the steel pipe 2 in order to enhance the integration between the steel pipe 2 and the bridge girder 21, and concrete is filled above the lid. Is good. FIG. 5 is a cross-sectional view of the skeleton 5 constructed in the above-described procedure. Concrete 31 is wound around a circular steel pipe 2 and a vertical streak 12 is formed near the surface of the concrete. It can be seen that the PC strands 15 are arranged. As described above, according to the method for constructing a steel pipe / concrete composite structure pier according to the present embodiment, the installation of the reinforcing members such as the vertical bars 12 and the PC strands 15 and the installation of the form panel 16 are performed in advance. Since the reaction force can be taken from the erected steel pipe 2, these operations can be performed easily, and the installation and dismantling of the lifting equipment, which is indispensable in the slip-form method, is eliminated. By making the formwork necessary for the panel into a panel shape, labor for assembling and dismantling the formwork is reduced. Therefore, with regard to a pier having a height of about several tens of meters, the cost and construction period required for the construction can be significantly reduced as compared with the case where a slip pier method which is optimal for a high pier is adopted. The bridge pier 5 formed by the construction method according to the present embodiment has a composite structure of the steel pipe 2 and the concrete 31 and also allows the steel pipe to bear a large bending strength and a shear strength. It is expected that the seismic resistance will be greatly improved compared to the RC piers. In addition, according to the method of constructing a steel pipe / concrete composite structure pier according to the present embodiment, the reinforcing material is
And the PC strands 15 wound around the vertical streaks, there is no need for bending work or joint work between the reinforcing bars as compared with a case where a reinforcing bar such as a spiral streak is arranged around the vertical streaks 12. Further, since the PC strand 15 is lightweight and has high tensile strength, the workability at the time of mounting and the handling at the time of transportation are facilitated, and the required pitch can be increased. Thus, further rapid construction can be realized. Although not specifically mentioned in the present embodiment, the steel pipe 2 is installed, the vertical bar 12 is attached, and the PC strand 1 is mounted.
The winding of No. 5 may be performed to the design height at a time, and then the form panel 16 may be repeatedly laid and concrete poured one lift at a time.
And the work related to concrete placing may be performed in parallel. In this embodiment, the segment 2
a was sequentially joined in the height direction and the circumferential direction to form the steel pipe 2, but may be a ring-shaped shape depending on the diameter and thickness, or may be an integrally manufactured one depending on the height of the pier. You may carry in to a site and erect this. Although not particularly mentioned in the present embodiment, it is needless to say that the construction efficiency of the form panel 16 should be increased as much as possible. (Second Embodiment) Next, a second embodiment will be described. It is to be noted that the same reference numerals are given to components and the like that are substantially the same as those in the above-described embodiment, and description thereof will be omitted. The method for constructing a steel pipe / concrete composite structure pier according to the present embodiment differs from the first embodiment in which the steel pipe has a single large diameter, and a plurality of small diameter pipes are erected and the PC strand 15 is pulled out. There is another configuration for the mechanism. That is, in the method for constructing a steel pipe / concrete composite structure pier according to the present embodiment, first, FIG.
As shown in (1), rising portions of four steel pipes 42 are erected on the foundation 41. When the steel pipe 42 is erected, for example, a steel pipe receiving stand (not shown) is previously installed on the root bottom,
It may be set up on this. Next, the reinforcing bar holder 11 is attached around the steel pipe 42 by welding or the like, and the vertical bar 12 is built around the steel pipe 42 as shown in FIG. . Next, a PC strand drawer 43 is installed on the top of the steel pipe 42, and the PC strand drawer 43
The C strand 15 is drawn out and wound around the longitudinal streak 12, and then deep concrete is cast and the steel pipe 42 is fixedly fixed. FIG. 7 is an overall perspective view showing the PC strand drawer 43, and FIG. 8 is a side view and a front view thereof.
As can be seen from these figures, the PC strand drawer 4
Reference numeral 3 denotes a PC strand on which a rotary table 45 is mounted on a gantry 44 so as to be pivotable about a vertical axis, and four under rollers 47 are mounted on the rotary table 45, and the PC strand 15 is wound by the under rollers. The flange of the drum 46 is configured to receive the flange. With this configuration, the PC strand drum 46 can be held so as to be rotatable about both horizontal and vertical axes. Here, as shown in FIG. 8A, a rotating operation arm 49 for manually rotating the rotating table is attached to the rotating table 45, and the gantry 44 and the rotating table 4 are rotated.
A disc brake 48 is provided between the rotary table 5 and the drive lever 5, and the rotation speed of the turntable 45 can be adjusted by operating the brake with an operation lever 56 (FIG. 7). As shown in FIG. 8B, the turntable 45 is provided with a rotation speed adjustment brake 50 for adjusting the rotation speed of the under roller 47 and an operation lever 51 for operating the brake. As shown in FIG. 7, the four under rollers 47 are connected two by two via a rotating shaft 57 and are arranged in front and rear.
Are installed on one side of them as shown in FIG. 8 (b). Also, one edge of the turntable 45 has a PC
A steel wire drawing frame 52 is erected and a pair of vertical rollers 53a, 53a and a pair of horizontal rollers 53 are provided above the frame.
b and 53b are arranged in a grid pattern, and the PC strand 15 drawn from the PC strand drum 46 is passed through an outlet port 54 which is an opening surrounded by the vertical roller 53a and the horizontal roller 53b. , PC
The strand 15 can be pulled out smoothly. Further, the cage-shaped protective cover 55 is detachably mounted on the turntable 45, and the PC strand drum 46 jumps out (drops off from the under roller 47) during the work of pulling out the PC strand 15. And when the PC strand 15 runs out, it can be replaced with a new PC strand drum 46. In order to wind the PC strand 15 around the longitudinal streak 12 using the PC strand drawer 43, the PC strand drawn from the PC strand drawer 43 is used.
The ends of the strands 15 are fixed on, for example, a foundation 41 (FIG. 6), and then the PC strands 15 are pulled out from the PC strand drawer 43 and wrapped around the vertical streaks 12 spirally from below to above. Good. At this time, the PC strand drum 46 pivots around the horizontal axis by the action of the under roller 47 and pivots around the vertical axis by the action of the turntable 45. Can be wound spirally. Further, the PC strand 15 is moved by the PC strand drum 4 by the friction reducing action of the vertical roller 53a and the horizontal roller 53b.
6 can be pulled out smoothly. In addition, the operating lever 51 is operated in accordance with the pull-out speed of the PC strand 15 to appropriately adjust the rotation speed of the under roller 47, and the operating lever 56 is operated in accordance with the winding speed of the PC strand 15 to rotate the turntable 45. Adjust the speed appropriately. PC using PC strand drawer 43
When the winding of the strand 15 and the fixing of the steel pipe 42 are completed, the PC strand drawer 43 is once removed, and then the steel pipe 42 is vertically extended as shown in FIG. P on top of 42
The C strand drawer 43 is replaced. Next, the vertical bar 12 is erected around the steel pipe 42 and fixed to the reinforcing bar holder 11 while being connected to the vertical bar 12 extending from below by a pressure welding joint, a mechanical joint or the like. In the same manner as described above, the PC strand 15 drawn from the PC strand drawer 43 is wound. Next, the form panel 16 is erected at the place where the winding of the PC strand 15 is completed. Formwork panel 16
In the same manner as in the first embodiment, after grounding on the ground and suspending it with a tower crane, it can be firmly fixed at a predetermined position by taking a reaction force from the steel pipe 42 via, for example, a separator. it can. Other descriptions of the formwork panel 16 are the same as those of the first embodiment,
Here, the description is omitted. Next, concrete is poured between the form panel 16 and the steel pipe 42, and after the strength is developed, the concrete is dismantled and prepared for diversion. FIG. 9 (b) is a view showing a state where concrete has been poured to the vicinity of the top of the steel pipe 42 that has been added and the first-stage construction of the pier body has been completed. The second stage may be constructed according to the same procedure as the first stage. FIG. 10 shows a state in which the above-described procedure has been repeated to temporarily remove the PC strand drawer 43, add the steel pipe 42, rearrange the PC strand drawer 43, attach the vertical bar 12, and wind the PC strand 15. FIG. 11 is a view showing a state in which concrete is poured between the formwork panel 16 and the steel pipe 42 to complete the second-stage construction of the pier frame. As described above, according to the method for constructing a steel pipe / concrete composite structure pier according to the present embodiment, as in the first embodiment, the mounting of the reinforcing material such as the vertical bars 12 and the PC strands 15 and the forming panel. At the time of the construction of No. 16, since the reaction force can be taken from the steel pipe 42 erected in advance, these operations can be easily performed, and the installation and dismantling of the lifting equipment and dismantling which are indispensable in the slip form method are required. In addition, since the formwork required for concrete casting is formed in a panel shape, labor for assembling and dismantling the formwork is reduced. Therefore, with respect to a pier having a height of about several tens of meters, the cost and construction period required for the construction can be significantly reduced as compared with the case where a slip form method which is optimal for a high pier is adopted. The bridge pier formed by the construction method according to the present embodiment has a composite structure of the steel pipe 42 and the concrete, and also allows the steel pipe to bear a large bending strength and a shear strength. Great improvement in seismic resistance can be expected compared to piers. Further, according to the method for constructing a steel pipe / concrete composite structure pier according to the present embodiment, the reinforcing material is
And the PC strands 15 wound around the vertical streaks, there is no need for bending work or joint work between the reinforcing bars as compared with a case where a reinforcing bar such as a spiral streak is arranged around the vertical streaks 12. Further, since the PC strand 15 is lightweight and has high tensile strength, the workability at the time of mounting and the handling at the time of transportation are facilitated, and the required pitch can be increased. Thus, further rapid construction can be realized. Further, according to the method for constructing a steel pipe / concrete composite structure pier according to the present embodiment, the PC strand drum 46 is placed on the turntable 45 which can turn around the vertical axis.
Is installed near the top of the steel pipe 42 so as to be rotatable about a horizontal axis.
Since the PC strand 15 is pulled out from the C strand drawer, the labor and installation space for constructing a work scaffold for laying the endless track is not required, and
Equipment for lifting the endless track together with the PC steel wire reel stand is not required. Although not particularly mentioned in the present embodiment, the installation of the steel pipe 42, the installation of the vertical bar 12, and the winding of the PC strand 15 are performed at one time to the design height, and thereafter the installation of the form panel 16 is performed. Alternatively, the concrete placement may be repeatedly performed one lift at a time. As described above, the steel pipe according to the present invention
According to the method of constructing a concrete composite structure pier, a reaction force can be taken from a steel pipe that has been erected in advance in attaching a reinforcing material and building a formwork panel, so that these operations can be performed easily. In addition, there is no need to install and disassemble lifting equipment, which is indispensable in the slip form method. Further, since the formwork required for concrete casting is formed into a panel, the time required for assembling and dismantling the formwork is reduced. Therefore, with respect to a pier having a height of about several tens of meters, the cost and construction period required for the construction can be significantly reduced as compared with the case where a slip pier method which is most suitable for a high pier is adopted. The bridge pier formed by the construction method according to the present invention has a composite structure of steel pipe and concrete, and allows the steel pipe to bear large bending strength and shear strength.
Great improvement in seismic resistance can be expected compared to the C pier. Further, according to the method for constructing a steel pipe / concrete composite structure pier according to the present invention, the bending work and the joint work between the reinforcing bars are not required as compared with a case where a reinforcing bar such as a spiral bar is arranged around the vertical bar. It becomes. In addition, since the PC strand is lightweight and has high tensile strength, the workability at the time of installation and the handling at the time of transportation are easy, and the required pitch can be widened, and thus, further rapid construction can be achieved. Also play. Further, according to the method for constructing a steel pipe / concrete composite structure pier according to the present invention, the labor and installation space for constructing a work scaffold for laying an endless track are not required, and the endless track is connected to a PC steel wire. This also has the effect of eliminating the need for equipment for lifting with the reel stand. [0061]

【図面の簡単な説明】 【図1】第1実施形態に係る鋼管・コンクリート複合構
造橋脚の施工方法の手順を示したフローチャート。 【図2】第1実施形態に係る鋼管・コンクリート複合構
造橋脚の施工方法に従って橋脚を構築していく様子を示
した図であり、(a)は下部躯体を構築している様子を示
した断面図、(b)はその上に鋼管を立設している様子を
示した側面図。 【図3】引き続き橋脚を構築していく様子を示した図で
あり、(a)は立設された鋼管の周囲への縦筋の吊込み、
該縦筋へのPCストランドの巻付け及び型枠パネルの配
置を行っている様子を示した断面図、(b)は同じく側面
図。 【図4】構築が終了した橋脚を示した図であり、(a)は
断面図、(b)は側面図。 【図5】図4のA―A線に沿う水平断面図。 【図6】第2実施形態に係る鋼管・コンクリート複合構
造橋脚の施工方法に従って橋脚を構築していく様子を示
した図であり、(a)は下部躯体を構築している様子を示
した側面図、(b)はB―B線に沿う水平断面図。 【図7】第2実施形態の施工方法で使用するPCストラ
ンド引出し機43の全体斜視図。 【図8】同じくPCストランド引出し機43の側面図及
び正面図。 【図9】引き続き橋脚を構築していく様子を示した図で
あり、(a)は立設された鋼管の周囲への縦筋の吊込み、
該縦筋へのPCストランドの巻付け及び型枠パネルの配
置を行っている様子を示した側面図、(b)はコンクリー
ト打設を行って一段目の構築を終えた様子を示した側面
図。 【図10】引き続き橋脚の二段目を構築している様子を
示した側面図。 【図11】二段目の構築を終えた様子を示した側面図。 【符号の説明】 2、42 鋼管 5 橋脚 12 縦筋(補強材) 14 PC鋼線リールス
タンド 15 PCストランド 16 型枠パネル 43 PCストランド引
出し機 44 架台 45 回転台 46 PCストランド用
ドラム
BRIEF DESCRIPTION OF THE DRAWINGS FIG. 1 is a flowchart showing a procedure of a method for constructing a steel pipe / concrete composite structure pier according to a first embodiment. FIG. 2 is a view showing a state in which a pier is being constructed in accordance with a method of constructing a steel pipe / concrete composite structure pier according to the first embodiment, and FIG. 2 (a) is a cross-section showing a state in which a lower skeleton is being constructed; FIG. 2 (b) is a side view showing a state where a steel pipe is erected thereon. FIG. 3 is a view showing a state in which a pier is continuously constructed, and (a) shows suspension of a vertical streak around a standing steel pipe;
FIG. 3B is a cross-sectional view showing a state where the PC strand is wound around the vertical streaks and the form panel is being arranged, and FIG. FIGS. 4A and 4B are diagrams showing a completed pier, wherein FIG. 4A is a cross-sectional view and FIG. FIG. 5 is a horizontal sectional view taken along line AA of FIG. 4; FIG. 6 is a view showing a state in which a pier is being constructed in accordance with a method of constructing a steel pipe / concrete composite structure pier according to the second embodiment, and FIG. 6 (a) is a side view showing a state in which a lower skeleton is being constructed. FIG. 3B is a horizontal sectional view along the line BB. FIG. 7 is an overall perspective view of a PC strand drawer 43 used in the construction method of the second embodiment. FIG. 8 is a side view and a front view of the PC strand drawer 43; FIG. 9 is a view showing a state in which a pier is continuously constructed, and (a) is a diagram in which a vertical streak is suspended around a standing steel pipe;
A side view showing a state in which the PC strand is wound around the vertical streaks and a form panel is being arranged, and (b) is a side view showing a state in which the first-stage construction has been completed by performing concrete casting. . FIG. 10 is a side view showing a state where the second stage of the pier is continuously constructed. FIG. 11 is a side view showing a state where the second-stage construction has been completed. [Description of Signs] 2, 42 Steel Pipe 5 Bridge Pier 12 Vertical Bar (Reinforcing Material) 14 PC Steel Wire Reel Stand 15 PC Strand 16 Formwork Panel 43 PC Strand Extractor 44 Mount 45 Turntable 46 Drum for PC Strand

Claims (1)

(57)【特許請求の範囲】 【請求項1】 先行して立設された鋼管の周囲に所定の
補強材を配置し、次いで、該補強材の周囲に型枠パネル
を建て込んだ後、該型枠パネルの内側にコンクリートを
打設する鋼管・コンクリート複合構造橋脚の施工方法で
あって、前記補強材を縦筋と該縦筋の周囲に巻き付けら
れるPCストランドとで構成し、鉛直軸線廻りに旋回自
在な回転台の上にPCストランド用ドラムが水平軸線廻
りに回動自在に保持されてなるPCストランド引出し機
を前記鋼管の頂部近傍に設置し、該PCストランド引出
し機から前記PCストランドを引き出すことを特徴とす
る鋼管・コンクリート複合構造橋脚の施工方法。
(57) [Claims] [Claim 1] A predetermined reinforcing material is arranged around a steel pipe erected in advance, and then a form panel is built around the reinforcing material. A method of constructing a steel pipe / concrete composite structure pier for casting concrete inside the formwork panel, wherein the reinforcing material is composed of a vertical streak and a PC strand wound around the vertical streak, and around a vertical axis. A PC strand drawer in which a PC strand drum is rotatably held about a horizontal axis on a turntable that can be turned around is installed near the top of the steel pipe, and the PC strand is pulled out from the PC strand drawer. Construction method of steel pipe / concrete composite structure pier characterized by drawing.
JP15199198A 1998-05-15 1998-05-15 Construction method of steel pipe / concrete composite structure pier Expired - Fee Related JP3518666B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP15199198A JP3518666B2 (en) 1998-05-15 1998-05-15 Construction method of steel pipe / concrete composite structure pier

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP15199198A JP3518666B2 (en) 1998-05-15 1998-05-15 Construction method of steel pipe / concrete composite structure pier

Publications (2)

Publication Number Publication Date
JPH11323843A JPH11323843A (en) 1999-11-26
JP3518666B2 true JP3518666B2 (en) 2004-04-12

Family

ID=15530681

Family Applications (1)

Application Number Title Priority Date Filing Date
JP15199198A Expired - Fee Related JP3518666B2 (en) 1998-05-15 1998-05-15 Construction method of steel pipe / concrete composite structure pier

Country Status (1)

Country Link
JP (1) JP3518666B2 (en)

Families Citing this family (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104120656B (en) * 2014-07-30 2017-01-18 中交一公局第四工程有限公司 Method for automatically controlling bridge high pier construction perpendicularity
CN109267493B (en) * 2018-11-06 2020-05-26 北京市市政二建设工程有限责任公司 Construction method for installing steel cover beam crossing river channel
CN109722984B (en) * 2019-01-18 2024-02-06 福建工程学院 Semi-assembled thin-wall pier and assembly method thereof
CN109930488B (en) * 2019-03-06 2020-09-15 安徽省公路桥梁工程有限公司 Construction method of inclined cable tower construction structure system
CN111535183B (en) * 2020-04-09 2022-03-18 焦刘霞 Bridge pile foundation construction equipment of water conservancy construction environmental protection
CN114411568B (en) * 2022-03-02 2023-08-15 四川省交通建设集团股份有限公司 Asynchronous construction method for hollow pier of concrete filled steel tube lattice

Also Published As

Publication number Publication date
JPH11323843A (en) 1999-11-26

Similar Documents

Publication Publication Date Title
JP5629316B2 (en) Telescopic tower assembly and method
US8281546B2 (en) Slip formed concrete wind turbine tower
EP2479430B1 (en) Method for assembling shell segments for forming tower sections of a hybrid wind turbine tower
CN109577534A (en) Tool-based hanging die assembly type composite floor slab and construction method
JP2008038463A (en) Bridge girder erection method
US3897182A (en) Slip form apparatus for constructing circular structures
JP3518666B2 (en) Construction method of steel pipe / concrete composite structure pier
JP2639361B2 (en) Construction method of steel pipe / concrete composite structure pier
JP2750368B2 (en) Construction method of reactor containment top slab
CN110230397A (en) A kind of construction method of building space dislocation overhanging balcony
CN107816209B (en) The large-scale Roof Truss construction technology of installation is lifted across outer two sides
JP3013688B2 (en) Construction method of concrete structure
JP3158383U (en) Body reinforcement assembly jig
CN109944164A (en) Jack up hollow thin-walled high pier roller die system and its construction method
JPH1054010A (en) Steel pipe and concrete composite construction bridge pier
JP2007217108A (en) Method of supporting tower crane
JPH08134847A (en) Erection method of steel-pipe arch
CN117248524A (en) Pile foundation dado umbrella formula movable mould board
CN212024599U (en) Column cantilever crane convenient to transportation
CN211971561U (en) Install stable column cantilever crane
CN215442343U (en) Can expand available building area's three-layer steel construction of encorbelmenting
CN113668688B (en) Three-layer overhanging steel structure with quick construction and land saving and construction method thereof
JP2768285B2 (en) Steel pipe / concrete composite pier
CN215254340U (en) Wallboard appurtenance in prefabrication
CN115110576B (en) Integral forming construction method for frame column and base layer of underground garage

Legal Events

Date Code Title Description
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20040108

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20040121

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20080206

Year of fee payment: 4

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20090206

Year of fee payment: 5

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20100206

Year of fee payment: 6

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20100206

Year of fee payment: 6

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20110206

Year of fee payment: 7

S531 Written request for registration of change of domicile

Free format text: JAPANESE INTERMEDIATE CODE: R313531

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20110206

Year of fee payment: 7

R350 Written notification of registration of transfer

Free format text: JAPANESE INTERMEDIATE CODE: R350

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20120206

Year of fee payment: 8

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20130206

Year of fee payment: 9

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20130206

Year of fee payment: 9

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20140206

Year of fee payment: 10

LAPS Cancellation because of no payment of annual fees