JPH081057B2 - How to build artificial ground - Google Patents

How to build artificial ground

Info

Publication number
JPH081057B2
JPH081057B2 JP17590393A JP17590393A JPH081057B2 JP H081057 B2 JPH081057 B2 JP H081057B2 JP 17590393 A JP17590393 A JP 17590393A JP 17590393 A JP17590393 A JP 17590393A JP H081057 B2 JPH081057 B2 JP H081057B2
Authority
JP
Japan
Prior art keywords
members
pile
floor plate
precast girder
starting
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
JP17590393A
Other languages
Japanese (ja)
Other versions
JPH0711620A (en
Inventor
充 恒藤
Original Assignee
日本テトラポッド株式会社
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 日本テトラポッド株式会社 filed Critical 日本テトラポッド株式会社
Priority to JP17590393A priority Critical patent/JPH081057B2/en
Publication of JPH0711620A publication Critical patent/JPH0711620A/en
Publication of JPH081057B2 publication Critical patent/JPH081057B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Description

【発明の詳細な説明】Detailed Description of the Invention

【0001】[0001]

【産業上の利用分野】この発明は、人工地盤の構築方法
に関するものであり、一層詳細には、桟橋構造物などを
含む人工地盤の構築方法に関するものである。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a method for constructing artificial ground, and more particularly to a method for constructing artificial ground including a jetty structure.

【0002】[0002]

【従来の技術および発明が解決すべき課題】一般に、沿
岸水域等に設置される桟橋構造物などの人工地盤は、ま
ず所定間隔で鋼管杭を打設した後、これらの鋼管杭上に
縦横の梁部材を架設配置し、ついでこれらの梁部材上に
上部工としての床板部材を現場打ちコンクリートあるい
は鋼板部材などによって順次形成していくことにより構
築されている。しかるに、このような構築方法では、構
築作業が大規模になって工期も長期に亘り、費用も嵩む
など種々の解決すべき課題が指摘されていた。
2. Description of the Related Art Generally, artificial ground such as a jetty structure installed in a coastal water area is first constructed by placing steel pipe piles at predetermined intervals, and then vertically and horizontally on these steel pipe piles. It is constructed by arranging beam members, and then sequentially forming floor plate members as superstructures on these beam members by using cast-in-place concrete or steel plate members. However, in such a construction method, various problems such as a large-scale construction work, a long construction period, and a high cost have been pointed out to be solved.

【0003】[0003]

【課題の解決手段】そこでこの発明では、このような人
工地盤を形成しようとする施工現場において発進部を形
成し、発進部上に載置した作業台車に装備される杭打装
置を使用してこの発進部から所定距離離間した位置に次
段部用の支持杭部材を杭打配設し、次に一端部側に支持
杭部材の頭部挿入孔と支持用段部を有するプレキャスト
製桁部材を発進部における端部杭部材と前記支持杭部材
間に架設固定し、次いでこれらのプレキャスト製桁部材
間に横桁を有する床板部材を嵌め込んで一体化すること
により次段部を形成し、さらにこのようにして形成した
次段部上に作業台車を移動して支持杭部材の打設、プレ
キャスト製桁部材の架設固定および床板部材の嵌め込み
作業を行って次段部以降を順次形成することにより構築
作業の容易化とともに構築費用の低減化を図ろうとする
ものである。
According to the present invention, therefore, a pile driving device is used which is provided on a work carriage which forms a starting portion and is placed on the starting portion at a construction site where such an artificial ground is to be formed. A precast girder member having a support pile member for the next stage is piled at a position separated from the starting part by a predetermined distance, and then has a head insertion hole of the support pile member and a support stage on one end side. Is fixedly installed between the end pile member and the support pile member in the starting portion, and then the next step portion is formed by fitting and integrating a floor plate member having a cross girder between these precast girder members, Further, the work carriage is moved onto the next-stage portion formed in this way to drive the support pile members, fix the precast girder members to be erected and fix the floor plate members to form the next-stage portion and thereafter. Makes the construction work easier and It is an attempt is made to reduce the construction cost to.

【0004】この場合、発進部は、杭打装置によって少
なくとも4本の発進部用支持杭部材を杭打配設し、次に
両端部側に支持杭部材の頭部挿入孔と支持用段部を有す
る発進部用プレキャスト製桁部材をこれらの発進部用支
持杭部材間に架設固定し、さらに前記発進部用プレキャ
スト製桁部材間に横桁を有する床板部材を嵌め込むこと
により形成するのが好ましい。
In this case, the starting portion is provided with at least four supporting portion supporting pile members for the starting portion by the pile driving device, and then the head insertion hole of the supporting pile member and the supporting step portion are provided at both ends. The precast girder member for the starting portion having the above is fixedly installed between the support pile members for the starting portion, and further formed by fitting the floor plate member having the transverse girder between the precast girder members for the starting portion. preferable.

【0005】また、プレキャスト製桁部材間に床板部材
を嵌め込む際、幅決め機構によってこれらのプレキャス
ト製桁部材の離間距離を予め保持した状態で床板部材を
落とし込むようにすれば、床板部材の嵌め込み作業を効
率よく行うことができる。
Further, when the floor plate member is fitted between the precast girder members, if the floor plate member is dropped while the distance between the precast girder members is held in advance by the width determining mechanism, the floor plate member is fitted. Work can be done efficiently.

【0006】さらに、各部のプレキャスト製桁部材およ
び床板部材上には現場コンクリートを打設して仕上げる
のが好適であるが、この現場コンクリートの打設は各部
毎に打設したりあるいはある程度纏めて打設することも
できる。
Further, it is preferable that the on-site concrete is cast and finished on the precast girder member and the floor plate member of each part, but this on-site concrete is cast by each part or collectively to some extent. It can also be set.

【0007】[0007]

【作用】この発明に係る方法によれば、あらかじめ工場
や施工現場近傍の製作ヤードにおいて製造しておいた支
持杭部材、プレキャスト製桁部材および横桁を有する床
板部材を現場に搬入し、杭打装置で打設した支持杭部材
間にこれらのプレキャスト製桁部材を架設固定した後、
横桁を有する床板部材を嵌め込んで一体化するだけで人
工地盤を構築することができるものである。
According to the method of the present invention, a supporting pile member, a precast girder member and a floorboard member having a cross girder, which have been manufactured in advance in a manufacturing yard near a factory or a construction site, are carried into the site and piled. After fixing these precast girder members between the supporting pile members placed by the device,
The artificial ground can be constructed only by fitting the floor plate member having the cross girder and integrating them.

【0008】[0008]

【実施例】次に、本発明に係る人工地盤の構築方法の好
適な実施例として桟橋構造物の構築方法を例示し、添付
図面を参照しながら以下詳細に説明する。
DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS Next, a preferred embodiment of the method of constructing an artificial ground according to the present invention will be described in detail with reference to the accompanying drawings, illustrating a method of constructing a pier structure.

【0009】まず、桟橋構造物10を構築するに際して
は、陸部Lに隣接して発進部12を構築する。具体的に
は、陸部Lに配置した作業台車14に装備した杭打装置
によって4本の発進部用支持杭部材16を杭打配設し、
次に両端部側に支持杭部材の頭部挿入孔18と支持用段
部20を有する発進部用プレキャスト製桁部材22を前
記発進部用支持杭部16の頭部に装着して架設固定し、
さらに前記発進部用プレキャスト製桁部材22、22間
に横桁24を有する床板部材26を嵌め込むことにより
形成する(図1参照)。なおこの場合、各支持杭部材1
6の頭部にはキャップ部材を装着しておき、また発進部
用プレキャスト製桁部材22は、その上面長手方向にウ
エブ部材28の一部を露呈させた形状に構成したものを
使用してこのウエブ部材28下面に支持杭部材16の頭
部が当接した状態で固定保持されるように構成する。
First, when constructing the jetty structure 10, the starting portion 12 is constructed adjacent to the land portion L. Specifically, four pile supporting devices 16 for starting section are piled by a pile driving device equipped on the work carriage 14 arranged on the land L,
Next, the precast girder member 22 for the starting portion, which has the head insertion hole 18 of the supporting pile member and the supporting step portion 20 on both end sides, is mounted on the head of the starting portion support pile portion 16 and fixed by erection. ,
Further, it is formed by fitting a floor plate member 26 having a horizontal girder 24 between the precast girder members 22 for the starting portion (see FIG. 1). In this case, each support pile member 1
A cap member is attached to the head portion of 6, and the precast girder member 22 for the starting portion is formed by exposing a part of the web member 28 in the longitudinal direction of the upper surface thereof. The lower surface of the web member 28 is fixed and held in contact with the head of the support pile member 16.

【0010】次に、発進部用プレキャスト製桁部材22
のウエブ部材28をレールとして使用する作業台車14
を前記発進部12上に移動して固定した後、杭打装置を
使用してこの発進部12から所定距離離間した位置に次
段の支持杭部材30、30を杭打配設し、次いで一端部
側に支持杭部材の頭部挿入孔18と支持用段部20を有
するプレキャスト製桁部材32を、発進部用プレキャス
ト製桁部材22の支持用段部20と支持杭部材30間に
架設するとともにこのプレキャスト製桁部材32の発進
部側と発進部用プレキャスト製桁部材22とを適宜の手
段で連結固定する。なお、この連結固定に際しては、各
桁部材の所定箇所に相互に嵌合する臍部を形成してこの
臍部を通しボルトにより緊締するなどの手段を使用する
ことができる。
Next, the precast girder member 22 for the starting portion
Trolley 14 using the web member 28 of FIG.
Is moved to and fixed on the starting portion 12, the supporting pile members 30, 30 of the next stage are piled and arranged at a position separated from the starting portion 12 by a predetermined distance by using a pile driving device, and then one end The precast girder member 32 having the head insertion hole 18 of the support pile member and the supporting step portion 20 on the part side is installed between the supporting step portion 20 and the supporting pile member 30 of the starting portion precast girder member 22. At the same time, the starting portion side of the precast girder member 32 and the starting portion precast girder member 22 are connected and fixed by an appropriate means. At the time of connecting and fixing, it is possible to use means such as forming umbilicus portions that are fitted to each other at predetermined positions of the respective girder members and tightening the umbilicus portions with through bolts.

【0011】そしてプレキャスト製桁部材32を架設固
定したら、横桁24を有する床板部材34を吊り上げて
これらのプレキャスト製桁部材32、32間に嵌め込ん
で一体化することにより次段部36を形成する。この場
合、床板部材34は横桁24を設けた側縁部と隣接する
他方の対向する両側縁部に連結用取付板を突設してお
き、この連結用取付板とプレキャスト製桁部材32のウ
エブ部材28とを溶接などにより連結しておくのが好ま
しい。また、床板部材34の上面には吊り環38を配設
しておき吊り上げ時の便宜に供するようにする(図2参
照)。
After the precast girder members 32 are erected and fixed, the floor plate member 34 having the transverse girders 24 is lifted and fitted between these precast girder members 32, 32 to form a next step portion 36. To do. In this case, the floor plate member 34 has a connecting mounting plate projectingly provided on the other opposing side edge portion adjacent to the side edge portion provided with the horizontal girder 24, and the connecting mounting plate and the precast girder member 32 are provided. It is preferable to connect the web member 28 by welding or the like. Further, a suspension ring 38 is provided on the upper surface of the floor plate member 34 so as to be conveniently used for lifting (see FIG. 2).

【0012】なお、平行するプレキャスト製桁部材3
2、32間に床板部材34を嵌め込むに際しては、例え
ば、油圧機構によって伸縮操作される位置決めロッドを
備える幅決め機構を使用してプレキャスト製桁部材3
2、32の離間距離を予め保持してから床板部材34を
落とし込むようにすれば、この床板部材34の嵌め込み
作業を効率よく行うことができる。また、隣接する床板
部材34同士も適宜の手段によって連結するようにす
る。
The parallel precast girder members 3
When the floor plate member 34 is fitted between the 2 and 32, for example, a precast girder member 3 is used by using a width determining mechanism including a positioning rod that is expanded and contracted by a hydraulic mechanism.
If the floor plate member 34 is dropped after the separation distance of 2 and 32 is held in advance, the work of fitting the floor plate member 34 can be efficiently performed. Further, adjacent floor plate members 34 are also connected to each other by an appropriate means.

【0013】このように形成された次段部36上には前
述と同様に作業台車14を移動して固定した後、杭打装
置による支持杭部材30の打設、プレキャスト製桁部材
32の架設固定および床板部材34の嵌め込み作業を行
って次々段部40を形成し、さらに同様の手順によって
次々段部以降を順次形成していく(図3参照)。
After the work carriage 14 is moved and fixed on the next-stage portion 36 formed as described above in the same manner as described above, the support pile member 30 is driven by the pile driving device and the precast girder member 32 is erected. The steps of fixing and fitting the floor plate member 34 are performed to form the next step 40, and the steps after step 1 are sequentially formed by the same procedure (see FIG. 3).

【0014】また、発進部12を含め各段部36、4
0、…の隙間部分にはモルタルを充填するとともに床板
部材26、34と桁部材22、32のウエブ部材28と
の間には補助鉄筋を配置して現場打ちコンクリート42
によって仕上げをするが、この仕上げ作業は各段部毎に
打設しても、あるいはある程度纏めて打設しても良いこ
とは言うまでもない。
Further, each step portion 36, 4 including the starting portion 12
The space between 0, ... Is filled with mortar, and auxiliary reinforcing bars are arranged between the floor plate members 26 and 34 and the web members 28 of the girder members 22 and 32 so that the cast-in-place concrete 42.
The finishing work may be done by each step, or it may be done collectively as a whole.

【0015】[0015]

【発明の効果】先に述べたように、本発明に係る人工地
盤の構築方法によれば、工場や施工現場近傍の製作ヤー
ドにおいて予め製造しておいたプレキャスト製桁部材お
よび床板部材などのユニット部材を、作業台車に設けた
杭打装置によって打設した支持杭部材間に装着固定した
のち、嵌め込みさらに現場打ちコンクリートで一体化す
るだけなので、構築作業を迅速にかつ容易に行うことが
でき、また工期も短縮できるので構築費用の低減を図る
ことができる等種々の利点を有するものである。
As described above, according to the method for constructing the artificial ground according to the present invention, the units such as the precast girder member and the floor board member which are manufactured in advance in the manufacturing yard near the factory or the construction site. After the members are mounted and fixed between the supporting pile members placed by the pile driving device provided on the work cart, they are simply fitted and integrated with the cast-in-place concrete, so the construction work can be performed quickly and easily, Further, since the construction period can be shortened, the construction cost can be reduced and various advantages can be obtained.

【0016】以上、本発明に係る人工地盤の構築方法の
好適な実施例として桟橋構造物の構築方法を例示して説
明したが、本発明方法は、この実施例に限定されるもの
ではなく、例えば、護岸岸壁などの港湾施設、軟弱地盤
上などに土地造成を行う場合にもも好適に採用すること
ができ、本発明の精神を逸脱しない範囲内において種々
の変更をなし得ることは勿論である。
Although the construction method of the jetty structure has been illustrated and described as a preferred embodiment of the method for constructing an artificial ground according to the present invention, the method of the present invention is not limited to this embodiment. For example, it can be suitably used also when harbor facilities such as seawalls, on land on soft ground, and the like, and can be variously modified without departing from the spirit of the present invention. is there.

【図面の簡単な説明】[Brief description of drawings]

【図1】本発明に係る人工地盤の構築方法の実施例とし
ての桟橋構造物の構築手順の一部であって、aは発進部
の構築手順を示す平面説明図、bはaの側面説明図であ
る。
FIG. 1 is a part of a procedure for constructing a jetty structure as an embodiment of a method for constructing an artificial ground according to the present invention, in which a is a plan view showing a procedure for constructing a starting portion, and b is a side view of a. It is a figure.

【図2】図1に示す桟橋構造物における発進部に続く次
段部の構築手順であって、aは平面説明図、bはaの側
面説明図である。
FIG. 2 is a plan explanatory view of a plan view and b is a side explanatory view of a in a procedure of constructing a next-stage part following the starting part in the jetty structure shown in FIG.

【図3】図1に示す桟橋構造物における次段部に続く次
々段部以降の構築手順であって、aは平面説明図、bは
aの側面説明図である。
FIG. 3 is a plan view for explaining a plan view of the pier structure shown in FIG.

【符号の説明】[Explanation of symbols]

10 桟橋構造物、 12 発進部、 14
作業台車、16 発進部用支持杭部材、
18 頭部挿入孔、20 支持用段部、
22 発進部用プレキャスト製桁部材、24 横桁、
26 床板部材、 28 ウエブ部材、
30 支持杭部材、 32 プレキャスト製桁部
材、34 床板部材、 36 次段部、
38 吊り環、40 次々段部、 42 現場打
ちコンクリート、
10 Pier structure, 12 Starting section, 14
Work trolley, support pile member for 16 starting parts,
18 head insertion hole, 20 support step,
22 Precast girder member for starting part, 24 girder,
26 floor plate member, 28 web member,
30 support pile members, 32 precast girder members, 34 floor plate members, 36 next step,
38 suspension ring, 40 next step, 42 cast-in-place concrete,

Claims (4)

【特許請求の範囲】[Claims] 【請求項1】 人工地盤を形成しようとする施工現場に
おいて発進部を形成し、発進部上に載置した作業台車に
装備される杭打装置を使用してこの発進部から所定距離
離間した位置に次段部用の支持杭部材を杭打配設し、次
に一端部側に支持杭部材の頭部挿入孔と支持用段部を有
するプレキャスト製桁部材を発進部における端部杭部材
と前記支持杭部材間に架設固定し、次いでこれらのプレ
キャスト製桁部材間に横桁を有する床板部材を嵌め込ん
で一体化することにより次段部を形成し、さらにこのよ
うにして形成した次段部上に作業台車を移動して支持杭
部材の打設、プレキャスト製桁部材の架設固定および床
板部材の嵌め込み作業を行って次段部以降を順次形成す
ることを特徴とする人工地盤の構築方法。
1. A position at which a starting portion is formed at a construction site where an artificial ground is to be formed, and a predetermined distance is provided from the starting portion by using a pile driving device mounted on a work carriage mounted on the starting portion. A support pile member for the next step is piled up in the pile, and then a precast girder member having a head insertion hole for the support pile member and a supporting step at one end is used as an end pile member at the starting portion. The next step is formed by fixing the support pile members between the support pile members, and then inserting and integrating the floor plate member having the transverse girders between these precast girder members to form the next step, and the next step formed in this way. A construction method for constructing an artificial ground, characterized in that a work carriage is moved onto a part to drive a support pile member, a precast girder member is erected and fixed, and a floor plate member is fitted to sequentially form the next step and thereafter. .
【請求項2】 発進部は、杭打装置によって少なくとも
4本の発進部用支持杭部材を杭打配設し、次に両端部側
に支持杭部材の頭部挿入孔と支持用段部を有する発進部
用プレキャスト製桁部材をこれらの発進部用支持杭部材
間に架設固定し、さらに前記発進部用プレキャスト製桁
部材間に横桁を有する床板部材を嵌め込むことにより形
成することを特徴とする請求項1に記載の人工地盤の構
築方法。
2. The starting portion has at least four supporting-pile members for the starting portion piled therein by a pile driving device, and then a head insertion hole and a supporting step portion of the supporting pile member are provided on both end sides. The precast girder member for starting part having is fixed by erection between the support pile members for starting part, and further formed by fitting a floor plate member having a transverse girder between the precast girder members for starting part. The method for constructing an artificial ground according to claim 1.
【請求項3】 プレキャスト製桁部材間に床板部材を嵌
め込む際、幅決め機構によってこれらのプレキャスト製
桁部材の離間距離を予め保持した状態で床板部材を落と
し込むことを特徴とする請求項1または請求項2に記載
の人工地盤の構築方法。
3. The floor plate member is dropped while the floor plate member is fitted between the precast girder members with a width-determining mechanism preliminarily maintaining a distance between these precast girder members. The method for constructing an artificial ground according to claim 2.
【請求項4】 各部のプレキャスト製桁部材および床板
部材上に現場コンクリートを打設して仕上げることを特
徴とする請求項1〜請求項3のいずれかに記載の人工地
盤の構築方法。
4. The method for constructing an artificial ground according to claim 1, wherein on-site concrete is placed on the precast girder member and the floor plate member of each part to finish.
JP17590393A 1993-06-24 1993-06-24 How to build artificial ground Expired - Fee Related JPH081057B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP17590393A JPH081057B2 (en) 1993-06-24 1993-06-24 How to build artificial ground

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP17590393A JPH081057B2 (en) 1993-06-24 1993-06-24 How to build artificial ground

Publications (2)

Publication Number Publication Date
JPH0711620A JPH0711620A (en) 1995-01-13
JPH081057B2 true JPH081057B2 (en) 1996-01-10

Family

ID=16004254

Family Applications (1)

Application Number Title Priority Date Filing Date
JP17590393A Expired - Fee Related JPH081057B2 (en) 1993-06-24 1993-06-24 How to build artificial ground

Country Status (1)

Country Link
JP (1) JPH081057B2 (en)

Families Citing this family (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP4800716B2 (en) * 2005-09-12 2011-10-26 株式会社間組 Artificial ground
JP2010265739A (en) * 2009-05-14 2010-11-25 Kiyoshi Watanabe Method of constructing moving work-platform
CN103967322B (en) * 2014-05-29 2016-03-02 李明超 A kind of multipurpose artificial water reservoirs on the ground
CN111441528B (en) * 2020-03-09 2021-09-14 浙江巍华新型建材有限公司 Integrated prefabricated wallboard with inorganic artificial stone decorative surface and manufacturing process thereof

Also Published As

Publication number Publication date
JPH0711620A (en) 1995-01-13

Similar Documents

Publication Publication Date Title
JP4343606B2 (en) Bridge construction method
CN112695696A (en) Integrated construction equipment for superstructure of high-pile wharf and construction method thereof
CN114457668A (en) Large-span spatial special-shaped arch rib flying-swallow type basket steel box arch bridge and rapid construction method
JP2004285735A (en) Method of constructing temporary landing bridge by using truss frame
JPH081057B2 (en) How to build artificial ground
JP4685341B2 (en) Viaduct construction method
JP2004316100A (en) Construction method for building
JP2003313813A (en) Construction method of overhead crossing, overhead crossing and bridge pier structure
CN215329670U (en) Integrated construction equipment for superstructure of high-pile wharf
CN114922132A (en) High-pile wharf upper structure part materialized construction method based on combined inclined piles
JP4422978B2 (en) Steel shell for footing foundation, bridge structure, bridge construction method, and three-dimensional intersection bridge construction method
JP4004423B2 (en) Road three-dimensional intersection construction method and pier connection structure
JP4094416B2 (en) Construction method of multilevel intersection
JPH10331272A (en) Construction method of building frame constituted of reinforced concrete column, core wall, uppermost wall beam, and slab
JP2008274567A (en) Circular steel pipe prefabricated bridge and its construction method
JP3852686B2 (en) Three-dimensional intersection construction method and three-dimensional intersection
JP2003003420A (en) Supporting member for prefabricated bridge
JP4233025B2 (en) How to construct a three-dimensional intersection
JPH08165662A (en) Construction method of underground structure
JP2632795B2 (en) How to build artificial ground
JP3567387B2 (en) How to build an underground skeleton
JP2003147705A (en) Constructing method for divided bridge body type traffic road
JP2004169318A (en) Construction method for bridge pier of viaduct
JP2615344B2 (en) Foundation using expanded polystyrene and its construction method
JP2936130B2 (en) Construction method of steel frame concrete structure