JPH0799020B2 - Cast-in-place prestressed concrete pile and its construction method - Google Patents
Cast-in-place prestressed concrete pile and its construction methodInfo
- Publication number
- JPH0799020B2 JPH0799020B2 JP4248879A JP24887992A JPH0799020B2 JP H0799020 B2 JPH0799020 B2 JP H0799020B2 JP 4248879 A JP4248879 A JP 4248879A JP 24887992 A JP24887992 A JP 24887992A JP H0799020 B2 JPH0799020 B2 JP H0799020B2
- Authority
- JP
- Japan
- Prior art keywords
- steel wire
- reinforcing bar
- concrete
- pile
- cast
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Lifetime
Links
Landscapes
- Piles And Underground Anchors (AREA)
Description
【0001】[0001]
【産業上の利用分野】本発明は場所打ちプレストレスト
コンクリート杭及びその構築工法に関するものである。BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a cast-in-place prestressed concrete pile and its construction method.
【0002】[0002]
【従来の技術】場所打ちコンクリート杭を構造物の基礎
として用いる場合、地震時等における水平外力や鉛直外
力を考慮する必要がある。この水平耐力を増大させる方
法として、杭頭部の径を大きくしたり、或は杭頭部の鉄
筋を多くしたりする方法がある。しかし、これらの方法
は設計・施工上、打設杭間隔や主鉄筋間隔との関連で水
平耐力の限度があるとともに、引抜抵抗時に杭体にひび
割れを発生させてしまうという問題があった。When using the Related Art place concrete pile as the basis of the structure, it is necessary to consider the horizontal external force or vertical force on Earthquake or the like. Those who increase this horizontal bearing capacity
As a method, increase the diameter of the pile head or
There are ways to increase the muscles. But there were these methods on design and construction, a problem that Kuitai to generate cracks when related to the extent there Rutotomoni the lateral strength, stresses before resistance with the hit設杭interval and the main reinforcement spacing .
【0003】そこで近年は、場所打ちコンクリート杭の
頭部を鋼管で補強したり、或は杭全体又は杭頭部にのみ
プレストレスを付与する方法が考えられている。 このう
ち杭全体にプレストレスを付与する杭は、掘削孔内への
鉄筋籠の建込みと共に、該鉄筋籠内にPC鋼線を挿入し
てコンクリートを打設し、該コンクリートの硬化後に前
記PC鋼線を杭頭部において緊張定着して構築するもの
である。Therefore, in recent years , cast- in- place concrete piles have been used.
The head is reinforced with steel pipes, or the entire pile or only the head of the pile
Methods of applying prestress have been considered. This
The pile that applies pre-stress to the entire pile is constructed by inserting a PC steel wire into the reinforcement cage and placing concrete with the reinforcement cage built in the excavation hole. The wire is tensioned and fixed on the pile head.
【0004】[0004]
【発明が解決しようとする課題】しかし、上記のような
場所打ちプレストレストコンクリート杭は鉄筋籠を建込
んだ後にPC鋼線を挿入しているが、この方法はPC鋼
線の設定位置の確保が困難であるとともに、PC鋼線が
コンクリートの打設時に移動するため設計位置にプレス
トレスを付与できないという問題があった。 また、コン
クリートの打設時にPC鋼線の外被が破損して鋼線が露
出してしまうという問題もあった。本発明は上記のよう
な問題に鑑みてなされたものであり、その目的は、PC
鋼線を所定の位置へ容易に設置できるとともに、所定の
位置に設置したPC鋼線がコンクリートの打設時に移動
したり、浮き上がったり、またPC鋼線の外被が破損し
たりするのを防止することである。However, the above-mentioned cast-in-place prestressed concrete pile is constructed with a reinforcing bar cage.
After inserting the PC steel wire, this method is PC steel
It is difficult to secure the wire setting position, and PC steel wire
Pressed at the designed position to move when placing concrete
There was a problem that the tress could not be added. In addition,
When the cleat is placed, the outer cover of the PC steel wire is damaged and the steel wire is exposed.
There was also the problem of putting it out. The present invention has been made in view of the above problems, and an object thereof is a PC.
The steel wire can be easily installed in the specified position and
PC steel wire installed at the position moves when pouring concrete
Or, floated or, also is possible to prevent the envelope of the PC steel wire is damaged.
【0005】[0005]
【課題を解決するための手段】以上の課題を達成するた
めの本発明の場所打ちプレストレストコンクリート杭
は、場所打ちコンクリート杭本体中に主筋と帯筋とから
なる鉄筋籠が埋設され、該鉄筋籠内側の長さ方向に設け
たスパイラル状の保護筋内に、後端部が前記コンクリー
ト杭の頭部で緊張定着されたPC鋼線が挿入され、該P
C鋼線が異なる位置に配設された複数の定着体にそれぞ
れUターン状に巻き掛けられ、各PC鋼線は芯線と側線
とが内側被覆筒で被覆され、該内側被覆筒の外面に潤滑
剤を介して外側被覆筒が被覆された二重被覆であること
を特徴とする構成にし、また、スパイラル状の保護筋が
内側に備えられた鉄筋籠を掘削孔内に挿入するととも
に、該鉄筋籠の上端部に支持用鉄筋を取り付け、前記保
護筋内に、深さ位置の異なる複数の定着体にそれぞれU
ターン状に巻き付けたPC鋼線を挿入し、該PC鋼線の
上部を保護ホースで被覆して支持用鉄筋に固定した後に
掘削孔内にコンクリートを打設し、該コンクリートの硬
化後に杭頭部をはつって支持用鉄筋を鉄筋籠から取り外
すとともに、保護ホースをPC鋼線から取り外すことを
特徴とする構成にすることである。In the cast- in- place prestressed concrete pile of the present invention for achieving the above-mentioned object, a cast-in-place concrete pile main body is embedded with a reinforced cage consisting of a main bar and a strip, and A PC steel wire, the rear end of which is tension-fixed at the head of the concrete pile, is inserted into a spiral protection line provided in the lengthwise direction of the inside of the protection wire.
The C steel wire is wound around a plurality of fixing bodies arranged at different positions in a U-turn shape, and each PC steel wire has a core wire and a side wire covered with an inner covering cylinder, and the outer surface of the inner covering cylinder is lubricated. It is characterized by a double coating in which the outer coating cylinder is coated with a chemical agent, and when the reinforcing bar cage with spiral protection bars inside is inserted into the drill hole.
To attach the supporting reinforcement to the upper end of the iron muscle cage, the coercive
Within the protective muscle, U is attached to each of the multiple anchors with different depth positions.
Insert the PC steel wire wound around the turn shape, after securing the supporting rebar to cover the upper portion of the PC steel wire with a protective hose
Place concrete in the drill hole and
Remove the support for the rebar from the rebar cage is Hatsu' the pile head after reduction
Together be, it is to the protection hose construction, characterized in that you remove et or PC steel wire.
【0006】[0006]
【作用】後端部がコンクリート杭の頭部で緊張定着され
たPC鋼線を、鉄筋籠内に設けたスパイラル状の保護筋
内に挿入したことにより、コンクリートの打設時におけ
る前記PC鋼線の移動を防止できて所定の箇所に確実に
設置することができるとともに、PC鋼線の挿入をスム
ーズに行える。さらに、前記スパイラル状の保護筋によ
り、定着体近傍のコンクリートを補強できる。また、P
C鋼線が異なる位置に配設された複数の定着体にそれぞ
れUターン状に巻き掛けられたことにより、前記定着体
の周囲における引張応力を分散化できるので定着体近傍
におけるコンクリートのひび割れを防げる。また、PC
鋼線は芯線と側線とが内側被覆筒で被覆され、該内側被
覆筒の外面に潤滑剤を介して外側被覆筒が被覆された二
重被覆としたことにより、コンクリートの打設時におけ
る外側被覆筒の破損による芯線及び側線の露出を防げ
る。また、場所打ちプレストレストコンクリート杭の構
築工法において、深さ位置の異なる定着体にそれぞれU
ターン状に巻き付けたPC鋼線を、鉄筋籠の保護筋内に
挿入したことにより、PC鋼線の挿入がスムーズにでき
るとともに、前記PC鋼線を保護筋内に挿入した後に掘
削孔内にコンクリートを打設したことにより、コンクリ
ートの打設時におけるPC鋼線の浮き上がりを防止でき
る。また、前記スパイラル状の保護筋により、定着体近
傍のコンクリートを補強できる。また、鉄筋籠の上端部
に支持用鉄筋を取り付けたことにより、コンクリートの
打設時において前記支持用鉄筋でPC鋼線の上部を支持
できると共に、PC鋼線の上部を保護ホースで被覆して
コンクリートを掘削孔内に打設したことにより、該コン
クリートが硬化した後の杭頭部のはつり時におけるPC
鋼線の破損を防げる。The PC steel wire has been tensioned the fixing in the head of the working rear end portion child Nkurito pile by inserting into the spiral protection muscles provided in the reinforcing bar cage, the PC steel in striking設時concrete The movement of the wire can be prevented and the wire can be securely installed at a predetermined position, and the PC steel wire can be smoothly inserted. Further, the spiral protection bar can reinforce concrete near the fixing body. Also, P
Since the C steel wire is wound around each of a plurality of fixing bodies arranged at different positions in a U-turn shape, the tensile stress around the fixing body can be dispersed, so that cracking of concrete near the fixing body can be prevented. . Also, PC
The steel wire has a core wire and a side wire covered with an inner coating cylinder, and an outer coating cylinder is coated on the outer surface of the inner coating cylinder with a lubricant to form a double coating. Prevents the core wire and side wires from being exposed due to damage to the cylinder. Also, in the construction method of cast-in-place prestressed concrete piles, U is applied to the anchorages at different depth positions.
By inserting the PC steel wire wound in a turn shape into the protection bar of the rebar cage, the PC steel wire can be smoothly inserted, and after the PC steel wire is inserted into the protection bar, concrete is put in the excavation hole. By pouring, it is possible to prevent the PC steel wire from rising when pouring concrete. In addition, the spiral protection bar can reinforce concrete near the fixing body. Further, by attaching the supporting rebar to the upper end portion of the rebar cage, the upper part of the PC steel wire can be supported by the supporting rebar at the time of placing concrete, and the upper part of the PC steel wire is covered with the protective hose. By placing concrete in the excavation hole, the PC at the time of chipping the pile head after the concrete has hardened
Prevents damage to steel wire.
【0007】[0007]
【実施例】以下、本発明の場所打ちプレストレストコン
クリート杭及びその構築工法の一実施例を図面に基づい
て詳細に説明する。図1は全体にプレストレスが付与さ
れた場所打ちプレストレストコンクリート杭の断面図、
図2はプレストレストコンクリート杭の横断面図、図3
は保護筋に挿入した定着体の正面図、図4は掛止金具の
平面図、図5は同側面図、図6は支圧金具の平面図、図
7は定着体が挿入された保護筋の横断面図、図8はPC
鋼線の横断面図である。DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS An embodiment of the cast-in-place prestressed concrete pile and its construction method of the present invention will be described in detail below with reference to the drawings. Figure 1 shows the whole is prestressed
Cross section of a cast-in-place prestressed concrete pile ,
Figure 2 is transverse cross-sectional view of a prestressed concrete pile, Figure 3
4 is a front view of the fixing member inserted in the protection bar, FIG. 4 is a plan view of the latch, FIG. 5 is a side view of the same, FIG. 6 is a plan view of the bearing member , and FIG. 7 is a protection bar in which the fixing member is inserted . Cross-sectional view of the PC, Figure 8 is a PC
It is a transverse sectional view of the steel wire.
【0008】図1の(1)は全体にプレストレスが付与
された場所打ちプレストレストコンクリート杭1であ
り、主筋2aと帯筋2bとからなる鉄筋籠2内の長さ方
向の全長にわたって保護筋3が配筋され、該保護筋3内
に、深さ位置の異なる4つの定着体5にそれぞれ巻き掛
けられたPC鋼線4が挿入されている。 前記保護筋3は
PC鋼線4を保護するものであり、5〜10cmピッチ
でスパイラル状に形成され、かつ前記定着体5が挿入可
能な径を備えている。尚、上記保護筋3は5〜10cm
ピッチに限定されるものではなく、また定着体5も4個
に限定されるものではない。また図1の(2)は杭頭部
にプレストレスが付与された場所打ちプレストレストコ
ンクリート杭1であり、杭頭部に配筋された保護筋3内
に前記と同様のPC鋼線4が挿入されている。 In FIG . 1 (1), prestress is applied to the whole.
With cast-in-place prestressed concrete pile 1
The length of the rebar cage 2 consisting of main bars 2a and stirrups 2b
The protective muscles 3 are arranged over the entire length in the
The four fixing members 5 with different depth positions.
The scraped PC steel wire 4 is inserted. The protective muscle 3 are of even that protects the PC steel wire 4 is formed in a spiral shape in 5~10cm pitch, and the fixing member 5 is provided with an insertable diameter. The protective muscle 3 is 5 to 10 cm.
Not limited to pitch, also it is not limited to four also fixing member 5. Moreover, (2) of FIG. 1 is a pile head.
Place pre-stressed toco
Inside the pile 1, which is inside the protective bar 3 arranged on the pile head.
A PC steel wire 4 similar to the above is inserted in the.
【0009】定着体5は図3に示すように、PC鋼線4
をUターン状に掛け回して深さ位置を違えた状態で束ね
られている。 この定着体5はPC鋼線4が掛け回される
掛止金具6に円筒状のカプラー7が 接続されて構成され
ている。 前記掛止金具6の先端部にはU字状の凹溝6a
が形成され、この凹溝6aの上部にフランジ8が一体形
成され、該フランジ8にPC鋼線4を引っ掛けるガイド
溝8aが放射状配置に凹欠されている(図4及び図5参
照)。このガイド溝8aは少なくとも同一掘削孔1aに
おけるPC鋼線4の導出本数以上形成されものであり、
本実施例においては8本形成されている。 [0009] The fixing member 5 as shown in FIG. 3, PC steel wire 4
U-turn around and bundle with different depth positions
Has been. The PC steel wire 4 is wound around the fixing body 5.
It is configured by connecting a cylindrical coupler 7 to the latch 6
ing. A U-shaped groove 6a is formed at the tip of the hook 6.
Is formed, and the flange 8 is integrally formed on the upper portion of the groove 6a.
A guide for hooking the PC steel wire 4 on the flange 8
The grooves 8a are recessed in a radial arrangement (see FIGS. 4 and 5).
See). This guide groove 8a is at least in the same drill hole 1a.
The number of PC steel wires 4 is more than the
In this embodiment, eight are formed.
【0010】よって、このガイド溝8aには凹溝6aで
Uターン状に巻き掛けられたPC鋼線4が嵌合される。 Therefore, the guide groove 8a has a concave groove 6a.
The PC steel wire 4 wound in a U-turn shape is fitted.
【0011】またカプラー7の後端部には、図6に示す
ような支圧金具10が嵌合され、該支圧金具10に前記
ガイド溝8aと同数のガイド溝10aが放射状配置に凹
欠されている。よって、各定着体5に掛け止めされたP
C鋼線4は、図7に示すように、各定着体5におけるガ
イド溝8a、10aにそれぞれ嵌入されてワイヤー9で
束ねられている。 したがって、図7の(1)に示すよ
う、最上部の定着体5におけるフランジ8及び支圧金具
10の凹溝8a、10aには全てPC鋼線4が嵌合され
ている。 [0011] The rear end portion of the coupler 7, is fitted Bearing bracket 10 as shown in FIG. 6, concave radially arranged before Symbol guide groove 8a as many guide grooves 10a is in said supporting圧金tool 10 Is missing. Therefore, P fixed to each fixing body 5
As shown in FIG. 7, the C steel wire 4 is provided with a guide for each fixing member 5.
Wires 9 are inserted into the id grooves 8a and 10a, respectively.
It is bundled. Therefore, as shown in (1) of FIG.
The flange 8 and the pressure bearing fitting in the uppermost fixing member 5
The PC steel wire 4 is fitted in all of the recessed grooves 8a and 10a of 10
ing.
【0012】前記PC鋼線4は撚り線であり、これらの
撚り線の心線4aと側線4bとが内側被覆筒4cでそれ
ぞれ被覆され、該内側被覆筒4cの外面に潤滑剤4dを
介して外側被覆筒4eが被覆された、いわゆる二重被覆
である。 The PC steel wire 4 is a stranded wire, and the core wire 4a and the side wire 4b of the stranded wire are covered with an inner covering cylinder 4c, respectively, and the outer surface of the inner covering cylinder 4c is covered with a lubricant 4d. So-called double coating in which the outer coating cylinder 4e is coated
Is.
【0013】以下、上記のような場所打ちプレストレス
トコンクリート杭の構築工法の一例について説明する。
まず、図9に示すようにケーシング11を用いて削孔機
20により掘削孔1aを掘削する。次に、図10に示す
ように、現場で複数の鉄筋籠2を接続するが、その内面
には4箇所に長さ方向に伸びる保護筋3が形成される。
次に、この鉄筋籠2をクレーンで吊り上げて掘削孔に挿
入し、その下端が孔底に着かないようにケーシングの上
端部に一旦吊り下げるとともに、鉄筋籠2の上端部に縦
筋12aと補強筋12bとからなる支持用鉄筋12を取
り付ける。 An example of the construction method for the above-mentioned cast-in-place prestressed concrete pile will be described below.
Also not a, drilling borehole 1a by drilling machine 20 with the casing 11 as shown in FIG. Next, as shown in FIG. 10, a plurality of rebar cages 2 are connected on site, but the inner surface
The protective muscles 3 extending in the lengthwise direction are formed at four positions in the.
Next, hoist this rebar cage 2 with a crane and insert it into the excavation hole.
The bottom of the casing so that its bottom edge does not reach the bottom of the hole.
Suspend once at the end and vertically at the upper end of the rebar cage 2.
The supporting reinforcing bar 12 including the reinforcing bar 12a and the reinforcing bar 12b is removed.
Attach
【0014】次に、鉄筋籠2の各保護筋3内に、深さ位
置を違えた定着体5にそれぞれ巻き掛けられたPC鋼線
4を挿入するとともに、該PC鋼線4の支持用鉄筋12
における箇所を保護ホース13で被覆して、そこを支持
用鉄筋12に番線等で固定す(図12参照)。 この保護
ホース13内側の上部及び下部は、発泡ウレタン13a
で被覆されている。しかし、これは発泡ウレタン13a
に限らず、その他の材料で被覆しても良い(図13参
照)。 Next, in each protection bar 3 of the rebar cage 2, the depth position is set.
PC steel wire wrapped around the fixing body 5 with different placement
4 is inserted, and a reinforcing bar 12 for supporting the PC steel wire 4 is inserted.
Is covered with a protective hose 13 to support it
Fix it to the reinforcing bar 12 with a numbered wire (see FIG. 12). This protection
The upper and lower parts inside the hose 13 are made of urethane foam 13a.
It is covered with. However, this is urethane foam 13a
However, it may be covered with other materials (see FIG. 13).
See).
【0015】次に、このように保護筋3内にPC鋼線4
が挿入された鉄筋籠2を、再びクレーンで吊り上げてケ
ーシングから取り外すとともに、掘削孔1a内に落とし
込む(図14参照)。そして、図15に示すように、ト
レミー管15で掘削孔1a内にコンクリート16を打設
する。この際、PC鋼線4は保護筋3内に挿入され、か
つ二重被覆であるためコンクリート16の打設による浮
き上がりや、外被の破損による撚線の露出が防げる。 Next, in this way , the PC steel wire 4 is placed in the protection bar 3.
Ke but the rebar cage 2 that has been inserted, and lifting in again crane
It is removed from the housing and dropped into the excavation hole 1a (see FIG. 14). Then, as shown in FIG. 15, concrete 16 is placed in the excavation hole 1a by the tremie pipe 15. At this time, the PC steel wire 4 is inserted into the protection bar 3,
One double coating a is for upper-out floating <br/> by pouring concrete 16 rear, prevent the exposure of the stranded wire according to the envelope of the damage.
【0016】そして、図16の(1)及び(2)に示す
ように、コンクリート16が硬化したら、杭頭部をはつ
って支持用鉄筋12を鉄筋籠2の上部から取り外すとと
もに、保護ホース13をPC鋼線4から取り外す。次
に、同図の(3)に示すように、基礎の配筋をするとと
もにPC鋼線4にスリーブ管17を嵌挿してその中にセ
メントミルク及び防錆油等を充填した後、基礎コンクリ
ート18を打設する。 16 (1) and 16 (2).
As such, When the concrete 16 is cured, and removing the support for rebar 12 Hatsu' the pile head from the top of the rebar cage 2 door
Also, remove the protection hose 13 from the PC steel wire 4. Next
, As shown in (3) in the figure, when the reinforcement of the foundation DOO
After filling the cell <br/> placement milk and rust-preventive oil and the like therein monitor PC steel wire 4 fitted a sleeve 17, a concrete foundation 18 for pouring.
【0017】そして、この基礎コンクリート18が硬化
したらPC鋼線4を基礎19上部で緊張定着する。この
ことによりプレストレストを付与した場所打ちプレスト
レストコンクリート杭1が構築されるとともに、該杭1
が基礎19に接続される。よって、地震等の水平力によ
る曲げモーメントによって杭頭部の崩壊及び、引抜力に
よる杭体のひび割れが防止できるとともに、基礎スラブ
と杭との接続もできる。 Then, the basic concrete 18 is hardened.
Once you tension fixing PC steel wire 4 in the foundation 19 the top. this
With cast-in-place prestressed concrete piles 1 impart prestressed is constructed by, 該杭1
There is connected to the base 19. Therefore, the bending moment due to horizontal force such as an earthquake may cause the pile head to collapse and pull out.
The pile slab can be prevented from cracking and the foundation slab
You can also connect to the pile.
【0018】後端部がコンクリート杭の頭部で緊張定着
されたPC鋼線を、鉄筋籠内に設けたスパイラル状の保
護筋内に挿入したことにより、コンクリートの打設時に
おける前記PC鋼線の移動を防止できて所定の箇所に確
実に設置することができるとともに、PC鋼線の挿入を
スムーズに行える。さらに、前記スパイラル状の保護筋
により、定着体近傍のコンクリートを補強できる。The rear end child Nkurito pile of tension The fixed PC steel wire in the head, by inserting into the spiral protection muscles provided in the reinforcing bar cage, the PC steel in striking設時concrete The movement of the wire can be prevented and the wire can be securely installed at a predetermined position, and the PC steel wire can be smoothly inserted. Further, the spiral protection bar can reinforce concrete near the fixing body.
【0019】PC鋼線が異なる位置に配設された複数の
定着体にそれぞれUターン状に巻き掛けられたことによ
り、前記定着体の周囲における引張応力を分散化できる
ので定着体近傍におけるコンクリートのひび割れを防げ
る。Since the PC steel wire is wound around each of a plurality of fixing bodies arranged at different positions in a U-turn shape, the tensile stress around the fixing body can be dispersed, so that the concrete strength in the vicinity of the fixing body can be improved. Prevents cracking.
【0020】PC鋼線は芯線と側線とが内側被覆筒で被
覆され、該内側被覆筒の外面に潤滑剤を介して外側被覆
筒が被覆された二重被覆としたことにより、コンクリー
トの打設時における外側被覆筒の破損による芯線及び側
線の露出を防げる。The PC steel wire has a core wire and a side wire covered with an inner coating cylinder, and an outer coating cylinder is coated on the outer surface of the inner coating cylinder with a lubricant to form a double coating. It is possible to prevent the core wire and the side wire from being exposed due to breakage of the outer covering cylinder at the time.
【0021】場所打ちプレストレストコンクリート杭の
構築工法において、深さ位置の異なる定着体にそれぞれ
Uターン状に巻き付けたPC鋼線を、鉄筋籠の保護筋内
に挿入したことにより、PC鋼線の挿入がスムーズにで
きるとともに、前記PC鋼線を保護筋内に挿入した後に
掘削孔内にコンクリートを打設したことにより、コンク
リートの打設時におけるPC鋼線の浮き上がりを防止で
きる。また、前記スパイラル状の保護筋により、定着体
近傍のコンクリートを補強できる。さらに、鉄筋籠の上
端部に支持用鉄筋を取り付けたことにより、コンクリー
トの打設時において前記支持用鉄筋でPC鋼線の上部を
支持できると共に、PC鋼線の上部を保護ホースで被覆
してコンクリートを掘削孔内に打設したことにより、該
コンクリートが硬化した後の杭頭部のはつり時における
PC鋼線の破損を防げる。In the construction method for cast-in-place prestressed concrete piles, PC steel wires wound in U-turns around anchorages having different depth positions were inserted into the protection bars of the rebar cage to insert the PC steel wires. In addition, the PC steel wire can be made smooth, and the PC steel wire can be prevented from being lifted up when the concrete is placed by placing the concrete in the excavation hole after inserting the PC steel wire into the protection bar. In addition, the spiral protection bar can reinforce concrete near the fixing body. Furthermore, by attaching a supporting rebar to the upper end of the rebar cage, the upper part of the PC steel wire can be supported by the supporting rebar at the time of placing concrete, and the upper part of the PC steel wire is covered with a protective hose. By placing the concrete in the excavation hole, it is possible to prevent the PC steel wire from being damaged when the pile head is chipped after the concrete is hardened.
【図1】(1)は杭全体にプレストレスを付与した場所
打ちプレストレストコンクリート杭の断面図、(2)は
杭頭部にプレストレスを付与した場所打ちプレストレス
トコンクリート杭の断面図である。FIG. 1 is a cross-sectional view of a cast-in-place prestressed concrete pile in which prestressing is applied to the entire pile, and FIG. 1B is a cross-sectional view of a cast-in-place prestressed concrete pile in which a pile head is prestressed.
【図2】場所打ちプレストレストコンクリート杭の横断
面図である。 [Figure 2] Crossing of cast-in-place prestressed concrete piles
It is a side view.
【図3】保護筋に挿入した定着体の正面図である。FIG. 3 is a front view of a fixing member inserted in a protective muscle.
【図4】掛止金具の平面図である。FIG. 4 is a plan view of a latch.
【図5】同側面図である。FIG. 5 is a side view of the same.
【図6】支圧金具の平面図である。FIG. 6 is a plan view of a bearing member.
【図7】(1)は図3のA−A線断面図、(2)は同図
のB−B線断面図、(3)は同図のC−C線断面図、
(4)は同図のD−D線断面図である。 7 (1) is a sectional view taken along the line AA of FIG. 3, and (2) is the same drawing.
BB line sectional view of (3) is a CC line sectional view of the same figure,
(4) is the DD sectional view taken on the line of the same figure.
【図8】PC鋼線の拡大横断面図である。FIG. 8 is an enlarged cross-sectional view of a PC steel wire.
【図9】掘削孔の断面図である。FIG. 9 is a cross-sectional view of a drill hole.
【図10】鉄筋籠をケーシングに吊り下げた断面図であ
る。FIG. 10 is a cross-sectional view in which a rebar cage is suspended in a casing .
【図11】支持用鉄筋の斜視図である。FIG. 11 is a perspective view of a supporting reinforcing bar.
【図12】保護筋にPC鋼線を挿入した断面図である。FIG. 12 is a cross-sectional view in which a PC steel wire is inserted into a protection bar.
【図13】PC鋼線に取り付けた保護ホースの断面図で
ある。FIG. 13 is a cross-sectional view of a protective hose attached to a PC steel wire .
【図14】鉄筋籠を建込んだ断面図である。FIG. 14 is a cross-sectional view in which a reinforcing bar cage is installed.
【図15】掘削孔にコンクリートを打設した断面図であ
る。FIG. 15 is a cross-sectional view in which concrete is placed in an excavation hole.
【図16】(1)はPC鋼線に保護ホースを嵌挿した柱
頭部の断面図、(2)はPC鋼線から保護ホースを取り
外した柱頭部の断面図、(3)はPC鋼線を基礎に緊張
定着した柱頭部の断面図である。FIG. 16 (1) is a sectional view of a stilt head in which a protective hose is inserted into a PC steel wire, (2) is a sectional view of a stilt head in which a protective hose is removed from the PC steel wire, and (3) is a PC steel wire. FIG. 3 is a cross-sectional view of a stigma that is strained and fixed on the basis of FIG.
1 場所打ちプレストレストコンクリート杭 1a 掘削孔 2 鉄筋籠 3 保護筋 4 PC鋼線 5 定着体 1 Cast-in-place prestressed concrete pile 1a Excavation hole 2 Reinforcing bar cage 3 Protective bar 4 PC steel wire 5 Anchoring body
───────────────────────────────────────────────────── フロントページの続き (72)発明者 原 郁正 埼玉県朝霞市三原1−18−50 (72)発明者 田辺 恵三 埼玉県蓮田市馬込1889−2 (56)参考文献 特開 昭57−21622(JP,A) 特開 昭48−2908(JP,A) 特開 昭61−10622(JP,A) 特開 昭61−31523(JP,A) 特公 昭47−29244(JP,B1) 特公 昭47−51161(JP,B1) 特公 昭53−41893(JP,B1) 特公 昭56−23492(JP,B2) 特公 昭61−47930(JP,B2) ─────────────────────────────────────────────────── ─── Continuation of the front page (72) Inventor Ikumasa Hara 1-18-50 Mihara, Asaka-shi, Saitama Prefecture (72) Inventor Keizo Tanabe 1889-2 Magome, Hasuda-shi, Saitama (56) Reference JP-A-57-21622 (JP, A) JP 48-2908 (JP, A) JP 61-10622 (JP, A) JP 61-31523 (JP, A) JP 47-29244 (JP, B1) JP JP-B 47-51161 (JP, B1) JP-B 53-41893 (JP, B1) JP-B 56-23492 (JP, B2) JP-B 61-47930 (JP, B2)
Claims (2)
帯筋とからなる鉄筋籠が埋設され、該鉄筋籠内側の長さ
方向に設けたスパイラル状の保護筋内に、後端部が前記
コンクリート杭の頭部で緊張定着されたPC鋼線が挿入
され、該PC鋼線が異なる位置に配設された複数の定着
体にそれぞれUターン状に巻き掛けられ、各PC鋼線は
芯線と側線とが内側被覆筒で被覆され、該内側被覆筒の
外面に潤滑剤を介して外側被覆筒が被覆された二重被覆
であることを特徴とする場所打ちプレストレストコンク
リート杭。1. A reinforcing bar cage comprising a main reinforcement <br/> girdle muscular and in-place concrete pile in the body is buried, iron muscle basket length of the inner
Insert the PC steel wire whose rear end is tension-fixed at the head of the concrete pile into the spiral protection line provided in the direction.
The PC steel wire is wound around a plurality of fixing bodies arranged at different positions in a U-turn shape, and each PC steel wire has a core wire and a side wire covered with an inner covering cylinder, A cast-in-place prestressed concrete pile, characterized in that it is a double coating with an outer coating cylinder coated on the outer surface with a lubricant.
た鉄筋籠を掘削孔内に挿入するとともに、該鉄筋籠の上
端部に支持用鉄筋を取り付け、前記保護筋内に、深さ位
置の異なる複数の定着体にそれぞれUターン状に巻き付
けたPC鋼線を挿入し、該PC鋼線の上部を保護ホース
で被覆して支持用鉄筋に固定した後に掘削孔内にコンク
リートを打設し、該コンクリートの硬化後に杭頭部をは
つって支持用鉄筋を鉄筋籠から取り外すとともに、保護
ホースをPC鋼線から取り外すことを特徴とする場所打
ちプレストレストコンクリート杭の構築工法。2. A reinforcing bar cage having spiral-shaped protective bars inside is inserted into the excavation hole, and a supporting reinforcing bar is attached to the upper end of the reinforcing bar cage , and a depth position is provided in the protective bars.
Insert the different fixing bodies PC steel wire wound around the U-turn shape respectively of location, Conch drilling hole after securing the supporting rebar upper part covered with a protective hose of the PC steel wire
REITs were Da設, the supporting reinforcing bar Hatsu' the pile head after hardening of the concrete with detached from reinforcing bar cage, cast-in-place prestressed concrete piles, characterized in that you remove the protection hose et or PC steel wire Construction method.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP4248879A JPH0799020B2 (en) | 1992-08-26 | 1992-08-26 | Cast-in-place prestressed concrete pile and its construction method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP4248879A JPH0799020B2 (en) | 1992-08-26 | 1992-08-26 | Cast-in-place prestressed concrete pile and its construction method |
Publications (2)
Publication Number | Publication Date |
---|---|
JPH06220847A JPH06220847A (en) | 1994-08-09 |
JPH0799020B2 true JPH0799020B2 (en) | 1995-10-25 |
Family
ID=17184796
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP4248879A Expired - Lifetime JPH0799020B2 (en) | 1992-08-26 | 1992-08-26 | Cast-in-place prestressed concrete pile and its construction method |
Country Status (1)
Country | Link |
---|---|
JP (1) | JPH0799020B2 (en) |
Families Citing this family (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US5739867A (en) * | 1997-02-24 | 1998-04-14 | Paradise Electronics, Inc. | Method and apparatus for upscaling an image in both horizontal and vertical directions |
Family Cites Families (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPS5341893A (en) * | 1976-09-27 | 1978-04-15 | Inoue Japax Res Inc | Wire cut discharge processing apparatus |
US4266726A (en) * | 1979-04-11 | 1981-05-12 | Alco Foodservice Equipment Company | Flow valve arrangement for beverage dispenser |
JPS5721622A (en) * | 1980-07-14 | 1982-02-04 | Shinkouzou Gijutsu Kk | Construction of large-diameter pile in site |
JPS6110622A (en) * | 1984-06-26 | 1986-01-18 | Hasegawa Komuten Co Ltd | Method of constructing cast-in-place concrete pile |
JPS6131523A (en) * | 1984-07-21 | 1986-02-14 | Hasegawa Komuten Co Ltd | Method of forming cast-in-place concrete pile |
JPS6147930A (en) * | 1984-08-14 | 1986-03-08 | Asahi Glass Co Ltd | Liquid crystal electrooptic device |
-
1992
- 1992-08-26 JP JP4248879A patent/JPH0799020B2/en not_active Expired - Lifetime
Also Published As
Publication number | Publication date |
---|---|
JPH06220847A (en) | 1994-08-09 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
AU748723B2 (en) | Method, member and tendon for constructing an anchoring device | |
US3987636A (en) | Methods and apparatus for anchoring a submerged structure to a waterbed | |
KR20060092552A (en) | The non-strut down framework construction method of having used cast in place concrete pile | |
JP5150596B2 (en) | Anchor device and anchor construction method | |
JP4852450B2 (en) | Reinforcing method of existing building and reinforcing structure of existing building | |
JP3756385B2 (en) | Composite pile and its construction method | |
JP4147101B2 (en) | Steel bar for cast-in-place concrete pile | |
US4171176A (en) | Flexible bar reinforced concrete pile and method of construction | |
JPH0799020B2 (en) | Cast-in-place prestressed concrete pile and its construction method | |
JP3713678B2 (en) | Cast-in-place pile, underground wall and its construction method | |
JP4432597B2 (en) | Joint structure of foundation pile head and upper foundation | |
JP2618850B2 (en) | Construction method of high strength pile | |
CN214614049U (en) | Prestressed anchor cable structure | |
CN214940104U (en) | Prestressed anchorage cable device of deep foundation pit | |
JPH0959973A (en) | Cast-in-place concrete pile and execution method thereof | |
JP2005082995A (en) | Pile head connection structure | |
JP3892153B2 (en) | Seismic reinforcement structure for existing columns and seismic reinforcement method for existing columns | |
CN1268603A (en) | Recoverable prestressed reinforced concrete revetment pile work method | |
JPH07158062A (en) | Concrete pile and joint construction method for the pile and foundation slab | |
JPS6319649B2 (en) | ||
JP7007691B1 (en) | Casting method for spring spacers, reinforcing bar cages and underground piles | |
CN113123344B (en) | Anchor point structure of foundation pit support and setting method thereof | |
JP5677736B2 (en) | Rock fall protection net device and rock fall protection net anchor | |
CN220888634U (en) | Anti-floating anchor rod | |
JP3684539B2 (en) | Flexible rebar fixing method |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20081025 Year of fee payment: 13 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20091025 Year of fee payment: 14 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20091025 Year of fee payment: 14 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20101025 Year of fee payment: 15 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20101025 Year of fee payment: 15 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20111025 Year of fee payment: 16 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20111025 Year of fee payment: 16 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20121025 Year of fee payment: 17 |
|
EXPY | Cancellation because of completion of term |