JPH0782890A - Building method of pc structure - Google Patents

Building method of pc structure

Info

Publication number
JPH0782890A
JPH0782890A JP22896693A JP22896693A JPH0782890A JP H0782890 A JPH0782890 A JP H0782890A JP 22896693 A JP22896693 A JP 22896693A JP 22896693 A JP22896693 A JP 22896693A JP H0782890 A JPH0782890 A JP H0782890A
Authority
JP
Japan
Prior art keywords
girder
cable
recessed section
section
cables
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP22896693A
Other languages
Japanese (ja)
Other versions
JP2659329B2 (en
Inventor
Kazuo Shirato
和男 白戸
Tsutomu Nagaura
勉 永浦
Noboru Hamato
昇 浜戸
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
PS Co Ltd
Original Assignee
PS Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by PS Co Ltd filed Critical PS Co Ltd
Priority to JP5228966A priority Critical patent/JP2659329B2/en
Publication of JPH0782890A publication Critical patent/JPH0782890A/en
Application granted granted Critical
Publication of JP2659329B2 publication Critical patent/JP2659329B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Landscapes

  • Rod-Shaped Construction Members (AREA)

Abstract

PURPOSE:To attain weight reduction of PC members, reduction of transport cost, and shortening of a process, by arranging a PC member of recessed section opening upward on a fitting position, wiring PC cables in the recessed section in an out cable system and tensely joining with fitting members. CONSTITUTION:A girder 2 of precast PC is installed on pillars 1. At this time, the girder 2 is worked into a recessed section, and a diaphragm 3 provided with second cable inserting holes 16 and third cable inserting holes 17 is previously executed. Joint mortar is filled in the joint parts between the pillars l and the girder 2. Next the second cables 4 are wired in the girder 2 and tensely joined with the pillars 1. Next the third cables 5 are similarly arranged. Thereafter precast slabs 7 are installed. Finally cast-in-place concrete 6 is placed in the recessed section as girder concrete. At this time, the girder 2 itself serves as a formwork. Hence, the transport vehicle capacity and weight lifting machine capacity can be reduced, the transport and installation cost can decreased, and the process can be shortened.

Description

【発明の詳細な説明】Detailed Description of the Invention

【0001】[0001]

【産業上の利用分野】本発明は、PC構造の建築物の
柱、梁、壁、床等の構築方法に関する。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a method of constructing columns, beams, walls, floors and the like of PC-structured buildings.

【0002】[0002]

【従来の技術】従来のPC構造物はPCケーブルを部材
の断面内に配線し内部応力という形でプレストレスを与
えていた。その場合、部材の断面形状は矩形、I形、T
形断面等が一般的であった。また、場所打ちコンクリー
トによって接合部を一体化していた。
2. Description of the Related Art In a conventional PC structure, a PC cable is laid in the cross section of a member to give prestress in the form of internal stress. In that case, the cross-sectional shape of the member is rectangular, I-shaped, T-shaped.
The cross-section was common. In addition, the joint was integrated by cast-in-place concrete.

【0003】[0003]

【発明が解決しようとする課題】PC構造物を場所打ち
コンクリートで構築する場合は、支保工、型枠、足場等
が必要であり、工程が煩雑で、工期も長かった。また従
来の密実なプレキャストコンクリート部材では部材の重
量が重く、運搬、揚重などの取扱に大きな制約があっ
た。
When constructing a PC structure with cast-in-place concrete, supporting work, formwork, scaffolding, etc. are required, and the process is complicated and the construction period is long. In addition, the conventional solid precast concrete members are heavy in weight, and there are great restrictions on handling such as transportation and lifting.

【0004】本発明は上記問題点を解決することを目的
とするもので、PC構造物の特徴を生かしながら、部材
重量は軽くし、他の部材と容易に接合することができる
PC構造物の構築方法を開発し、これを提供するもので
ある。
An object of the present invention is to solve the above-mentioned problems, and while utilizing the characteristics of the PC structure, the weight of the member can be reduced and the PC structure can be easily joined to other members. It develops a construction method and provides it.

【0005】[0005]

【課題を解決するための手段】本発明は、上記問題点を
解決するために、次の技術手段を講じたことを特徴とす
るPC構造物の構築方法である。すなわち本発明は、上
面を開口した凹形断面のPC部材を製作し、取付位置に
配設した後、前記凹形断面内にPCケーブルをアウトケ
ーブル方式で配線し、このPCケーブルを緊張して取付
部材に接合構築することを特徴とするPC構造物の構築
方法である。
The present invention is a method for constructing a PC structure characterized by taking the following technical means in order to solve the above problems. That is, according to the present invention, a PC member having a concave cross-section with an open upper surface is manufactured, placed at a mounting position, and then a PC cable is laid in the concave cross-section by an out-cable method. A method for constructing a PC structure, characterized by joining and constructing to a mounting member.

【0006】本発明は、アウトケーブルを張設するため
の、上面を開口した凹形断面を有するPC部材を、1次
ケーブルによりプレテンション、又はポストテンション
方式で成形しておき、この凹形断面内に、接合用PCケ
ーブルをアウトケーブル方式で2次、3次ケーブルに分
けて配線し、このPCケーブルを緊張して柱、梁、壁等
の直交する取付部材に接合し、PC構造物を構築する。
According to the present invention, a PC member for tensioning an out cable having a concave cross section with an open upper surface is formed by a pre-tension or post tension method with a primary cable, and the concave cross section is formed. Inside, the PC cable for joining is divided into secondary and tertiary cables by the out-cable method, and the PC cable is tensioned and joined to orthogonal mounting members such as columns, beams, and walls, and the PC structure is formed. To construct.

【0007】[0007]

【作用】本発明では、アウトケーブルを張設する凹形断
面を有するPC部材をプレテンション、又はポストテン
ション方式であらかじめ製作しておき、建築物建設現場
に運搬し架設するまでは、軽量な中間製品のPC部材と
して取り扱い、運搬、揚重、架設等を容易に行えるよう
にし、凹形断面内にPCケーブルを配線し、アウトケー
ブル方式で柱等の直交部材に緊張接合し、その後、凹形
断面内にコンクリートを充填するようにした。従って、
最終断面の形状が大きく、重量が大きい部材でも、架設
段階までは軽量化することが可能で運搬、揚重上の制約
を小さくすることができる。
According to the present invention, a PC member having a concave cross section for tensioning an out cable is preliminarily manufactured by a pre-tension or post-tension method, and is transported to a building construction site until it is erected and is lightweight. As a PC member of the product, it can be easily handled, transported, lifted, erected, etc., the PC cable is laid in the concave section, and it is tension-bonded to the orthogonal member such as a pillar by the out cable method, and then the concave shape The cross section was filled with concrete. Therefore,
Even a member having a large final cross-section and a large weight can be lightened up to the erection stage, and restrictions on transportation and lifting can be reduced.

【0008】PC部材の形状は、部材軸方向については
全長に亙って凹形断面を有する形状としてもよく、端部
のみを密実としたり、PCケーブル挿通孔を設けた壁体
(ダイヤフラム)を部材長手方向の必要な位置に設けた
ものとしてもよい。アウトケーブルを張設する凹形断面
を有する断面形状であれば、形状の如何を問わない。本
発明では、部材の軽量化に伴い、大掛かりな支保工やブ
ラケットが不要となり、またPCケーブルは、凹形断面
内に配線するので、作業が容易である。その上、小梁な
どの取り付け位置や、必要な箇所に設けた壁体(ダイヤ
フラム)の底部近傍にPCケーブル挿通孔を設けること
により、PCケーブルが曲げ下げ配線となり取り付け部
材への接合緊張力のプレストレスによる曲げ上げ力を効
果的にできる。
The shape of the PC member may be a shape having a concave cross section over the entire length in the axial direction of the member, and only the end portion is solid or a wall body (diaphragm) provided with a PC cable insertion hole. May be provided at a required position in the longitudinal direction of the member. Any shape may be used as long as it has a concave cross section in which the out cable is stretched. In the present invention, as the weight of the member is reduced, large-scale support work and brackets are not required, and since the PC cable is wired in the concave cross section, the work is easy. Moreover, by providing a PC cable insertion hole near the bottom of the wall (diaphragm) at the mounting position of the beam or at the required location, the PC cable becomes bent wiring and the tension of joining to the mounting member is reduced. Effective bending up force due to prestress.

【0009】PC部材を取付部材に接合する場合、例え
ば梁を柱に接合する場合、直交する取付部材に個々に接
合してもよく、PC部材が連続する場合は、結合部材を
挟んで多数のPC部材を連続的に接合することとしても
よい。PC部材は凹形断面内を跡埋めしないでそのまま
構造部材とすることもできるが、アウトケーブル方式に
よりPC構造物を構築した後、凹形断面内にコンクリー
トを充填し、密実な合成部材とすることもできる。
When the PC member is joined to the mounting member, for example, when the beam is joined to the column, it may be individually joined to the orthogonal mounting members. When the PC members are continuous, a large number of members are sandwiched by the joining members. The PC members may be joined continuously. The PC member can be used as it is as a structural member without filling in the concave cross section, but after constructing the PC structure by the out cable method, concrete is filled in the concave cross section to form a solid composite member. You can also do it.

【0010】本発明に係るPC構造は、プレストレスを
段階的に付与することにより、構築途中で部材にオーバ
ーストレスによるダメージを与えることなく、大きなプ
レストレスを導入できるので、通常の建築物でも大きな
メリットがあるが、特に積載荷重1,000kg/m2
以上の倉庫、人工台地などの重載荷構造物には非常に有
効である。
In the PC structure according to the present invention, by applying prestress stepwise, a large prestress can be introduced without damaging the members during construction due to overstress, so that even a normal building is large. There are merits, but especially the loading capacity is 1,000 kg / m 2
It is very effective for the above heavy-duty structures such as warehouses and artificial plateaus.

【0011】[0011]

【実施例】図1、図2は本発明の実施例の建築用のPC
構造物の構築工程を示す図である。実施例の施工方法を
図面に従って説明する。 (a)柱1の建方を行う。 (b)大梁2を架設する。大梁2は、プレキャストPC
梁であって、凹形断面を有する断面形状となっているの
で軽量で、これを支持するために柱1に小さなブラケッ
トをつけておけば、容易に梁を支持することができる。
このブラケットは柱自身に設けた切り欠きであってもよ
い。
DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS FIGS. 1 and 2 are construction PCs according to an embodiment of the present invention.
It is a figure which shows the construction process of a structure. The construction method of the embodiment will be described with reference to the drawings. (A) Build the pillar 1. (B) The girder 2 is installed. Large beam 2 is a precast PC
Since the beam is a cross-sectional shape having a concave cross-section, it is lightweight, and if a small bracket is attached to the pillar 1 to support the beam, the beam can be easily supported.
This bracket may be a notch provided in the pillar itself.

【0012】大梁2又は小梁11などのPC部材の断面
形状は、例えば、図3に示すようなものでよい。図3は
断面がU字形をなす梁2である。このU字形断面の梁2
は、1次ケーブル15を用いてプレテンション方式でプ
レキャストを成形したもので、2次ケーブル挿通孔1
6、3次ケーブル挿通孔17を備えたダイヤフラム3を
あらかじめ形成しておくとよい。
The cross-sectional shape of the PC member such as the large beam 2 or the small beam 11 may be as shown in FIG. 3, for example. FIG. 3 shows a beam 2 having a U-shaped cross section. This U-shaped beam 2
Is a precast formed by the pretensioning method using the primary cable 15, and the secondary cable insertion hole 1
6, the diaphragm 3 having the tertiary cable insertion hole 17 may be formed in advance.

【0013】(c)柱1と、大梁2の接合部に目地モル
タルを充填し、大梁2に2次ケーブル4及びシースに収
納した3次ケーブル5を配設し、この2次ケーブル4を
緊張して柱1と大梁2を接合する。大梁2が柱1を挾ん
で連続して場合には、2次ケーブル4はこれらを貫通さ
せて、これらを同時に結合することができる。3次ケー
ブル5も同様に配設しておく。その後、小梁11、プレ
キャストスラブ7を架設する。
(C) The joint between the pillar 1 and the girder 2 is filled with joint mortar, and the girder 2 is provided with a secondary cable 4 and a tertiary cable 5 housed in a sheath, and the secondary cable 4 is tensioned. Then, the pillar 1 and the girder 2 are joined. If the girder 2 is continuous with the pillar 1 sandwiched between them, the secondary cable 4 can penetrate them and simultaneously bond them. The tertiary cable 5 is also arranged in the same manner. After that, the beam 11 and the precast slab 7 are installed.

【0014】2次ケーブル4は、小梁11、プレキャス
トスラブ7などの自重や作業荷重を負担するものであ
り、大梁2及び小梁11の必要な位置に、図3に示すよ
うに、ダイヤフラム3の底部近傍に2次ケーブル挿通孔
16を設けることにより、緊張力による曲げ上げ力を付
与することができ合理的な構造とすることが可能とな
る。3次ケーブル5は地震、積載荷重などの外部荷重に
対抗するものである。
The secondary cable 4 bears the weight and work load of the beam 11, the precast slab 7, etc., and the diaphragm 3 is provided at the required positions of the beam 2 and beam 11, as shown in FIG. By providing the secondary cable insertion hole 16 in the vicinity of the bottom portion of the, the bending-up force due to the tension force can be applied and a rational structure can be obtained. The tertiary cable 5 resists an external load such as an earthquake or a load.

【0015】(d)2次ケーブル4が緊張され、3次ケ
ーブル5が配線されプレキャストスラブ7が架設された
状態である。大梁2が柱1を挾んで連続して接合されて
いる。 (e)凹形断面内に場所打ちで大梁コンクリート6を打
設する。このとき、大梁2が自身が型枠となるので、型
枠や支保工を必要としない。
(D) The secondary cable 4 is tensioned, the tertiary cable 5 is wired, and the precast slab 7 is installed. A large beam 2 sandwiches a pillar 1 and is continuously joined. (E) Placing the girder concrete 6 by cast-in-place within the concave cross section. At this time, since the girder 2 itself serves as a formwork, no formwork or supporting work is required.

【0016】図5がここまでの工程のPC構造物の平面
図であり、図6は図5のA−A矢視図である。柱1、1
…の間に大梁2を架設し、大梁2、2のダイヤフラム3
の位置に小梁11を架設、その後プレキャストスラブ7
を配設する。小梁11の大梁2への接合は、図6に示す
ように大梁2の柱1の接合と同様な方法で行う。 (f)3次ケーブル5を緊張し、グラウトを施す。さら
に必要なら、トップコンクリート8を打設する。
FIG. 5 is a plan view of the PC structure in the steps up to here, and FIG. 6 is a view taken along the line AA of FIG. Pillars 1, 1
The girder 2 is erected between the ... and the diaphragm 3 of the girders 2 and 2.
The beam 11 is installed at the position of, and then the precast slab 7
To arrange. The beam 11 is joined to the girder 2 in the same manner as the column 1 of the girder 2 is joined, as shown in FIG. (F) Tension the tertiary cable 5 and grout it. If necessary, top concrete 8 is placed.

【0017】(g)図2(g)は、柱に大梁2を接合
し、2次ケーブル、3次ケーブルを配設してプレキャス
トスラブ7、トップコンクリート8を施工した部分詳細
図である。大梁2の自重を負担する1次ケーブル15、
小梁11、プレキャストスラブ7、トップコンクリート
8などの自重及び構築のための作業荷重、梁・柱の接合
のための緊張力を負担する2次ケーブル、完成構造形に
作用する外部荷重を負担する3次ケーブルが合理的に配
置され、強靭で軽量な構造物が構築可能となる。
(G) FIG. 2 (g) is a detailed view of a part in which the girder 2 is joined to the column, the secondary cable and the tertiary cable are arranged, and the precast slab 7 and the top concrete 8 are installed. Primary cable 15 that bears the weight of the girder 2,
It bears the weight of the beam 11, precast slab 7, top concrete 8 etc. and the work load for construction, the secondary cable that bears the tension force for joining the beam and column, and the external load that acts on the completed structure. The tertiary cables are rationally arranged, and a strong and lightweight structure can be constructed.

【0018】図4には、1形断面の複数の桁22の組合
わせによる凹形断面PC部材を例示した。桁22は1次
ケーブル15でプレテンション方式でプレキャスト形成
され、複数本を並設してその桁22の下部フランジの間
に目地コンクリート23とダイヤフラム3を施工し、ア
ウトケーブルを配設することができるようにしたもので
ある。
FIG. 4 illustrates a concave cross-section PC member formed by combining a plurality of girders 22 each having a one-section cross section. The girder 22 is precast by the pretension method with the primary cable 15, and a plurality of girders are arranged side by side, and the joint concrete 23 and the diaphragm 3 are installed between the lower flanges of the girder 22 to arrange the out cable. It was made possible.

【0019】このように、本発明が用いるPC部材は、
アウトケーブルを張設するための凹形断面を有する断面
形状であれば、形状の如何を問わない。
Thus, the PC member used in the present invention is
The shape does not matter as long as it has a concave cross section for stretching the out cable.

【0020】[0020]

【発明の効果】本発明によれば、PC構造物が軽量とな
るので、運搬車輌能力や揚重機能力の軽減と運搬コスト
の低減に寄与する。また、型枠、支保工の省略とブラケ
ットの簡素化が可能となり、中詰めコンクリートは高強
度コンクリートを必要とせず、さらに、2次ケーブルの
張設が容易となり、曲げ上げもできるので、架設コスト
の低減、工程の短縮を図ることができる。
According to the present invention, the weight of the PC structure is reduced, which contributes to the reduction of the vehicle capacity and the lifting function and the reduction of the transportation cost. In addition, omission of formwork and supporting work and simplification of brackets are possible, high-strength concrete is not required for filling concrete, and secondary cables can be stretched easily and can be bent up. Can be reduced and the number of steps can be shortened.

【図面の簡単な説明】[Brief description of drawings]

【図1】実施例のPC構造物の構築方法を示す工程図で
ある。
FIG. 1 is a process drawing showing a method for constructing a PC structure of an example.

【図2】実施例のPC構造物の構築方法を示す工程図で
ある。
FIG. 2 is a process drawing showing a method for constructing a PC structure of an example.

【図3】実施例の梁の断面図である。FIG. 3 is a cross-sectional view of a beam of an example.

【図4】実施例の梁の断面図である。FIG. 4 is a cross-sectional view of a beam of an example.

【図5】実施例の柱と梁の配列を示す平面図である。FIG. 5 is a plan view showing an arrangement of columns and beams according to the embodiment.

【図6】図5のA−A矢視図である。6 is a view taken along the line AA of FIG.

【符号の説明】[Explanation of symbols]

1 柱 2 大梁 3 ダイヤフラム 4 2次ケーブ
ル 5 3次ケーブル 6 大梁コンク
リート 7 プレキャストスラブ 8 トップコン
クリート 11 小梁 15 1次ケーブル 16 2次ケーブ
ル挿通孔 17 3次ケーブル挿通孔 22 桁 23 目地コンクリート
1 pillar 2 girder 3 diaphragm 4 secondary cable 5 tertiary cable 6 girder concrete 7 precast slab 8 top concrete 11 girder 15 primary cable 16 secondary cable insertion hole 17 tertiary cable insertion hole 22 girder 23 joint concrete

Claims (1)

【特許請求の範囲】[Claims] 【請求項1】 上面を開口した凹形断面のPC部材を製
作し、取付位置に配設した後、前記凹形断面内にPCケ
ーブルをアウトケーブル方式で配線し、該PCケーブル
を緊張して取付部材に接合構築することを特徴とするP
C構造物の構築方法。
1. A PC member having a concave cross-section with an open upper surface is manufactured, placed at a mounting position, and a PC cable is laid out in the concave cross-section by an out-cable method, and the PC cable is tensioned. P characterized by being jointed and constructed to a mounting member
C Structure construction method.
JP5228966A 1993-09-14 1993-09-14 Construction method of PC structure Expired - Fee Related JP2659329B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP5228966A JP2659329B2 (en) 1993-09-14 1993-09-14 Construction method of PC structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP5228966A JP2659329B2 (en) 1993-09-14 1993-09-14 Construction method of PC structure

Publications (2)

Publication Number Publication Date
JPH0782890A true JPH0782890A (en) 1995-03-28
JP2659329B2 JP2659329B2 (en) 1997-09-30

Family

ID=16884661

Family Applications (1)

Application Number Title Priority Date Filing Date
JP5228966A Expired - Fee Related JP2659329B2 (en) 1993-09-14 1993-09-14 Construction method of PC structure

Country Status (1)

Country Link
JP (1) JP2659329B2 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2014237951A (en) * 2013-06-07 2014-12-18 鹿島建設株式会社 Precast member set and press method for precast member

Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS5130118A (en) * 1974-09-06 1976-03-15 Oriental Concrete Co KONKURIITOGOSEIHARINOSEKOHO

Patent Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS5130118A (en) * 1974-09-06 1976-03-15 Oriental Concrete Co KONKURIITOGOSEIHARINOSEKOHO

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2014237951A (en) * 2013-06-07 2014-12-18 鹿島建設株式会社 Precast member set and press method for precast member

Also Published As

Publication number Publication date
JP2659329B2 (en) 1997-09-30

Similar Documents

Publication Publication Date Title
US4023315A (en) Prefabricated buildings
JP6685570B1 (en) PC basic structure and construction method thereof
JP2011149265A (en) Beam member and building structure
JPH0882002A (en) Rc structure and its constructing method
JP2659329B2 (en) Construction method of PC structure
JPH0434161A (en) Centrifugally molded hollow pc concrete column and column construction method
JP2006183286A (en) Connection structure of corrugated steel web for corrugated steel web u-shaped component bridge
JPH04368528A (en) Frame construction using void beam
JPH06158716A (en) Construction method of building with precast concrete member
JPH0468140A (en) Construction of beam
JPH11190068A (en) Building structure
JPH0718734A (en) Constructing method for reinforced concrete building structure
JP2641836B2 (en) Precast prestressed concrete U-beam
JPH10183533A (en) Bridge girder, bridge girder component, and work execution method for bridge girder
JP2002364072A (en) Beam for hybrid-structure frame
JP3187618B2 (en) How to assemble beam reinforcement
JP2000160686A (en) Composite structure of reinforced concrete column and steel frame beam, and its execution
KR100868865B1 (en) Method of constructuring prestressed concrete composite beam bridge continuation structure having haunch block located at columm part thereof and structure using same
JPH02282572A (en) Erection method for precast concrete pillar
JPH07139054A (en) Joining method for precast concrete wall plate
JPH084107A (en) Connecting method for column/beam connection
JPH032435A (en) Construction method for jointing column and steel frame reinforced-concrete beam to each other
JPH066823B2 (en) Precast structural members
JPH1150540A (en) Connecting method and connecting device for column and beam
JPH06316966A (en) Construction of joint section between column and beam

Legal Events

Date Code Title Description
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 19970520

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

S531 Written request for registration of change of domicile

Free format text: JAPANESE INTERMEDIATE CODE: R313531

R350 Written notification of registration of transfer

Free format text: JAPANESE INTERMEDIATE CODE: R350

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20100606

Year of fee payment: 13

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20130606

Year of fee payment: 16

LAPS Cancellation because of no payment of annual fees