JPH10183533A - Bridge girder, bridge girder component, and work execution method for bridge girder - Google Patents

Bridge girder, bridge girder component, and work execution method for bridge girder

Info

Publication number
JPH10183533A
JPH10183533A JP30784797A JP30784797A JPH10183533A JP H10183533 A JPH10183533 A JP H10183533A JP 30784797 A JP30784797 A JP 30784797A JP 30784797 A JP30784797 A JP 30784797A JP H10183533 A JPH10183533 A JP H10183533A
Authority
JP
Japan
Prior art keywords
bridge girder
bridge
top plate
concrete
main body
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP30784797A
Other languages
Japanese (ja)
Inventor
Yoshinori Sakatani
良典 酒谷
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
FUJISEN KYORYO DOBOKU KK
Original Assignee
FUJISEN KYORYO DOBOKU KK
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by FUJISEN KYORYO DOBOKU KK filed Critical FUJISEN KYORYO DOBOKU KK
Priority to JP30784797A priority Critical patent/JPH10183533A/en
Priority to EP97308931A priority patent/EP0841434A1/en
Publication of JPH10183533A publication Critical patent/JPH10183533A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D2/00Bridges characterised by the cross-section of their bearing spanning structure
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D2101/00Material constitution of bridges
    • E01D2101/20Concrete, stone or stone-like material
    • E01D2101/24Concrete
    • E01D2101/26Concrete reinforced
    • E01D2101/268Composite concrete-metal
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D2101/00Material constitution of bridges
    • E01D2101/20Concrete, stone or stone-like material
    • E01D2101/24Concrete
    • E01D2101/26Concrete reinforced
    • E01D2101/28Concrete reinforced prestressed
    • E01D2101/285Composite prestressed concrete-metal

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Bridges Or Land Bridges (AREA)

Abstract

PROBLEM TO BE SOLVED: To facilitate conveyance and work execution, shorten the construction term, lower the manufacture and construction cost, and provide a bridge girder with high rigidity and high durability. SOLUTION: A bridge girder 5 is constituted of a bridge girder component 10 constituted of a square cylindrical main body 9 which is composed of a top flange 11 having holes 17 formed therein, a bottom flange 13, and a web 15, and a stud dowel 19 provided inside face of the web 15, an additional board for connecting to bridge girder components 10 to each other, reinforcements 22, 23 arranged in the bridge component 10, and concrete placed in the bridge component 10. The load bearing strength is further increased if adding a PC steel material thereto.

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【発明の属する技術分野】本発明は、橋桁、橋桁を構成
する橋桁構成体及び橋桁の施工方法に関する。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a bridge girder, a bridge girder constructing the bridge girder, and a method of constructing the bridge girder.

【0002】[0002]

【従来の技術】一般に橋梁は、橋台及び橋脚の上に橋桁
を渡し、その上に床版を設け、さらに床版の上にアスフ
ァルトを敷設等して構成される。従来の橋桁には、鈑
桁、箱桁及びプレビーム桁が用いられている。鈑桁は、
上フランジと下フランジとが1枚のウェブで連結されて
いる。また、箱桁は、上フランジと下フランジとが2枚
のウェブで連結されており、上フランジ、下フランジ及
び2枚のウェブで囲まれた部位は中空となっている。こ
の鈑桁及び箱桁は、ともに鋼材のみで構成されている。
プレビーム桁は、鈑桁の周囲にコンクリートを打設して
構成されている。
2. Description of the Related Art Generally, a bridge is constructed by passing a bridge girder on an abutment and a pier, providing a floor slab thereon, and laying asphalt on the floor slab. Conventional bridge girders include sheet girders, box girders, and pre-beam girders. Sheet girder
The upper flange and the lower flange are connected by one web. In the box girder, an upper flange and a lower flange are connected by two webs, and a portion surrounded by the upper flange, the lower flange, and the two webs is hollow. The sheet girder and the box girder are both made of only steel.
The prebeam girder is constructed by casting concrete around a sheet girder.

【0003】しかしながら、鈑桁、箱桁は鋼材のみで構
成されているため材料費が嵩み、製作コストが高いもの
となっている。また、プレビーム桁は、コンクリートを
打設するための型枠を組み、コンクリートが固化した後
に型枠を取り外す作業が必要であるため、製作コストが
非常に高いという問題もある。
[0003] However, since the sheet girder and the box girder are made of only the steel material, the material cost is increased and the manufacturing cost is high. Further, the pre-beam girder has a problem that the production cost is extremely high because it is necessary to assemble a formwork for placing concrete and to remove the formwork after the concrete is solidified.

【0004】鈑桁、箱桁及びプレビーム桁等の従来の橋
桁は、いずれも非常に大型で、しかも相当な重量がある
ため、運搬や施工作業が非常に大変であるという問題が
ある。特に、橋桁を橋台または橋脚に載せる作業には、
橋台と橋脚または橋脚と橋脚との間に、一時的に橋桁を
支持する仮設材を設ける必要がある。このため、相当な
手間と労力が必要となり、施工コストが非常に高いばか
りか、工期も長いものとなってしまう。
Conventional bridge girders such as sheet girder, box girder, and pre-beam girder are all very large and have a considerable weight, so that there is a problem that transportation and construction work are very difficult. In particular, when placing a bridge girder on an abutment or pier,
It is necessary to provide temporary materials to temporarily support the bridge girder between the abutment and the pier or between the pier and the pier. For this reason, considerable labor and labor are required, and not only the construction cost is extremely high, but also the construction period becomes long.

【0005】また、従来の橋桁は、大きさや重量の割に
剛性が小さいため、橋脚を短い間隔で配置しなければな
らない。このため、橋脚の数が多くなる分コストが高い
という問題もある。なお、鈑桁及び箱桁の上フランジ及
び下フランジとウェブとは溶接で連結されているが、溶
接時の熱により鋼材が変性して、鈑桁及び箱桁の耐久性
に悪影響を及ぼすおそれもある。
[0005] In addition, conventional bridge girders have low rigidity for their size and weight, so that the piers must be arranged at short intervals. For this reason, there is also a problem that the cost is high as the number of piers increases. Although the upper and lower flanges of the sheet girder and the box girder are connected to the web by welding, the heat generated during welding may denature the steel material and adversely affect the durability of the plate girder and the box girder.

【0006】[0006]

【発明が解決しようとする課題】本発明は上記従来の問
題点に着目してなされたものであり、運搬や施工作業が
容易で、工期が短く、製作及び施工コストが低くて、し
かも大きな剛性をもっており、さらに高い耐久性を備え
た橋桁、この橋桁を構成する橋桁構成体及びこの橋桁の
施工方法を提供することを目的とする。
SUMMARY OF THE INVENTION The present invention has been made in view of the above-mentioned conventional problems, and it is easy to carry and carry out work, has a short construction period, has low production and construction costs, and has a large rigidity. It is another object of the present invention to provide a bridge girder having higher durability, a bridge girder constructing the bridge girder, and a method of constructing the bridge girder.

【0007】[0007]

【課題を解決するための手段】請求項1の発明は、橋梁
の橋桁を構成する橋桁構成体であって、筒状の本体と、
前記本体に形成され内部に連通する穴が形成されている
ことを特徴とする橋桁構成体である。
The invention of claim 1 is a bridge girder constructing a bridge girder of a bridge, comprising: a tubular main body;
A bridge girder structure wherein a hole formed in the main body and communicating with the inside is formed.

【0008】請求項2の発明は、請求項1記載の橋桁構
成体において、本体は鋼材によって構成されていること
を特徴とする橋桁構成体である。
According to a second aspect of the present invention, there is provided the bridge girder structure according to the first aspect, wherein the main body is made of a steel material.

【0009】請求項3の発明は、請求項2記載の橋桁構
成体において、本体は、天板と側板と底板とが連結され
て角筒状に形成され、且つ、穴は前記天板に形成されて
いることを特徴とする橋桁構成体である。
According to a third aspect of the present invention, in the bridge girder structure according to the second aspect, the main body is formed in a rectangular tube shape by connecting the top plate, the side plate, and the bottom plate, and the hole is formed in the top plate. It is a bridge girder structure characterized by being done.

【0010】請求項4の発明は、請求項3記載の橋桁構
成体において、天板と側板と底板とが組立分解可能な連
結手段によって連結されていることを特徴とする橋桁構
成体である。
According to a fourth aspect of the present invention, there is provided the bridge girder structure according to the third aspect, wherein the top plate, the side plates, and the bottom plate are connected by connecting means that can be assembled and disassembled.

【0011】請求項5の発明は、請求項4記載の橋桁構
成体において、穴は複数形成され且つ所定の間隔を空け
て配置されていることを特徴とする橋桁構成体である。
According to a fifth aspect of the present invention, there is provided the bridge girder structure according to the fourth aspect, wherein a plurality of holes are formed and arranged at predetermined intervals.

【0012】請求項6の発明は、請求項5記載の橋桁構
成体において、側板の内側面に鉄筋を支持する支持部材
が設けられていることを特徴とする橋桁構成体である。
According to a sixth aspect of the present invention, there is provided a bridge girder structure according to the fifth aspect, wherein a support member for supporting a reinforcing bar is provided on an inner surface of the side plate.

【0013】請求項7の発明は、筒状の本体を有し外壁
を構成する橋桁構成体と、前記橋桁構成体どうしを連結
する連結手段と、前記橋桁構成体内に配置された鉄筋
と、前記橋桁構成体内に流し込まれたコンクリートとか
らなることを特徴とする橋桁である。
According to a seventh aspect of the present invention, there is provided a bridge girder structure having a cylindrical main body and constituting an outer wall, connecting means for connecting the bridge girder structures with each other, a reinforcing bar disposed in the bridge girder structure, A bridge girder comprising a concrete poured into a bridge girder configuration body.

【0014】請求項8の発明は、請求項7記載の橋桁に
おいて、橋桁構成体の本体内に、コンクリートが流入し
ない空間を形成するための中空部材を備えたことを特徴
とする橋桁である。
According to an eighth aspect of the present invention, there is provided the bridge girder according to the seventh aspect, wherein a hollow member for forming a space into which concrete does not flow is provided in the main body of the bridge girder structure.

【0015】請求項9の発明は、請求項7又は8に記載
の橋桁において、橋桁構成体内にPC鋼材を設け、この
PC鋼材にテンションをかけることで橋桁構成体内のコ
ンクリートにプレストレスを与えたことを特徴とする橋
桁である。
According to a ninth aspect of the present invention, in the bridge girder according to the seventh or eighth aspect, a PC steel material is provided in the bridge girder structure, and a tension is applied to the PC steel material to prestress concrete in the bridge girder structure. It is a bridge girder characterized by the following.

【0016】請求項10の発明は、筒状の本体を有し且
つ穴が形成されており橋桁の外壁を構成する橋桁構成体
を橋台または橋脚に載せる工程と、前記橋桁構成体どう
しを連結する工程と、前記橋桁構成体内に鉄筋を配置す
る工程と、前記橋桁構成体に形成された穴からコンクリ
ートを流し込む工程とからなることを特徴とする橋桁の
施工方法である。
According to a tenth aspect of the present invention, a step of mounting a bridge girder structure having a tubular main body and having a hole formed thereon and constituting an outer wall of the bridge girder on an abutment or a pier, and connecting the bridge girder structures with each other. A method of constructing a bridge girder, comprising: a step; a step of arranging a reinforcing bar in the bridge girder body; and a step of pouring concrete through a hole formed in the bridge girder body.

【0017】請求項11の発明は、天板と側板と底板と
が組立分解可能な連結手段によって連結されており且つ
前記天板に穴が形成されている本体を有する橋桁構成体
の複数の底板どうしを互いに連結する工程と、前記連結
された複数の底板を橋台または橋脚に載せる工程と、前
記橋台または橋脚に載せられた底板に側板及び天板を連
結して橋桁構成体を形成する工程と、前記橋桁構成体ど
うしを連結する工程と、前記橋桁構成体内に鉄筋を配置
する工程と、前記橋桁構成体の天板に形成されている穴
からコンクリートを流し込む工程とからなることを特徴
とする橋桁の施工方法である。
According to an eleventh aspect of the present invention, a plurality of bottom plates of a bridge girder structure having a main body in which a top plate, side plates, and a bottom plate are connected by connecting means that can be assembled and disassembled, and a hole is formed in the top plate. Connecting the two to each other, mounting the plurality of connected bottom plates on an abutment or a pier, and connecting a side plate and a top plate to the bottom plate mounted on the abutment or a pier to form a bridge girder structure. Connecting the bridge girder structures to each other, arranging a reinforcing bar in the bridge girder structure, and pouring concrete through a hole formed in a top plate of the bridge girder structure. This is the construction method of the bridge girder.

【0018】請求項12の発明は、筒状の本体を有し且
つ穴が形成されており橋桁の外壁を構成する橋桁構成体
を橋台または橋脚に載せる工程と、前記橋桁構成体どう
しを連結する工程と、前記橋桁構成体内に鉄筋を配置す
る工程と、橋桁構成体の天板に形成されている複数の穴
のうち少なくとも1つを残して、前記残した穴以外の穴
からコンクリートを流し込む工程とからなることを特徴
とする橋桁の施工方法である。
According to a twelfth aspect of the present invention, a step of mounting a bridge girder construct having a cylindrical main body and having a hole formed thereon and constituting an outer wall of the bridge girder on an abutment or a pier, and connecting the bridge girder constructs to each other. A step of arranging a reinforcing bar in the bridge girder structure, and a step of pouring concrete from holes other than the remaining holes, leaving at least one of a plurality of holes formed in a top plate of the bridge girder structure. A method for constructing a bridge girder, comprising:

【0019】請求項13の発明は、天板と側板と底板と
が組立分解可能な連結手段によって連結されており且つ
前記天板に穴が形成されている本体を有する橋桁構成体
の複数の底板どうしを互いに連結する工程と、前記連結
された複数の底板を橋台または橋脚に載せる工程と、前
記橋台または橋脚に載せられた底板に側板及び天板を連
結して橋桁構成体を形成する工程と、前記橋桁構成体ど
うしを連結する工程と、前記橋桁構成体内に鉄筋を配置
する工程と、橋桁構成体の天板に形成されている複数の
穴のうち少なくとも1つを残して、前記残した穴以外の
穴からコンクリートを流し込む工程とからなることを特
徴とする橋桁の施工方法である。
According to a thirteenth aspect of the present invention, a plurality of bottom plates of a bridge girder having a main body in which a top plate, side plates, and a bottom plate are connected by connecting means that can be assembled and disassembled, and the top plate has a hole formed therein. Connecting the two to each other, mounting the plurality of connected bottom plates on an abutment or a pier, and connecting a side plate and a top plate to the bottom plate mounted on the abutment or a pier to form a bridge girder structure. Connecting the bridge girder members together, arranging reinforcing bars in the bridge girder members, and leaving at least one of a plurality of holes formed in a top plate of the bridge girder members. And a step of pouring concrete from holes other than the holes.

【0020】請求項14の発明は、請求項10から13
に記載の橋桁の施工方法のいずれかにおいて、コンクリ
ートが流入しない空間を形成するための中空部材を橋桁
構成体の内部の所定位置に配置する工程を具備すること
を特徴とする橋桁の施工方法である。
The invention according to claim 14 is the invention according to claims 10 to 13
The method of constructing a bridge girder according to any of the methods for constructing a bridge girder according to any one of claims 1 to 3, further comprising a step of disposing a hollow member for forming a space into which concrete does not flow in at a predetermined position inside the bridge girder structure. is there.

【0021】請求項15の発明は、請求項10から14
に記載の橋桁の施工方法のいずれかにおいて、橋桁構成
体内にPC鋼材を設けてこれにテンションをかけること
で橋桁構成体内のコンクリートにプレストレスを与える
工程を具備することを特徴とする橋桁の施工方法であ
る。
The invention of claim 15 is the invention of claims 10 to 14
Any of the methods for constructing a bridge girder described in (1) above, comprising the step of providing a PC steel material in the bridge girder structure and applying tension to the steel to prestress concrete in the bridge girder structure. Is the way.

【0022】[0022]

【発明の実施の形態】本発明の実施の形態にかかる橋
桁、橋桁構成体及び橋桁の施工方法を図面に従って説明
する。図1から図9は第一の実施の形態にかかる橋桁5
を示すものである。先ず、橋桁5を備えた橋梁1の構成
について説明する(図1参照)。符号3は橋脚を示し、
この橋脚3上に橋桁5が設置され、橋桁5の両端部は橋
台2に支持されている。2本の橋脚5上には複数の床版
7が設置され、さらに床版7上にはアスファルトが敷設
され、且つ、欄干等が設けられる。橋桁5の外壁は、複
数の橋桁構成体10が連結されて構成されている。
DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS A bridge girder, a bridge girder structure and a method for constructing a bridge girder according to an embodiment of the present invention will be described with reference to the drawings. 1 to 9 show a bridge girder 5 according to the first embodiment.
It shows. First, the configuration of the bridge 1 including the bridge girder 5 will be described (see FIG. 1). Reference numeral 3 indicates a pier,
A bridge girder 5 is installed on the pier 3, and both ends of the bridge girder 5 are supported by the abutment 2. A plurality of floor slabs 7 are installed on the two piers 5, and asphalt is laid on the floor slab 7, and a balustrade or the like is provided. The outer wall of the bridge girder 5 is formed by connecting a plurality of bridge girder constructs 10.

【0023】図2及び図3によって橋桁構成体10の構
成について説明する。符号9は角筒状の本体を示し、こ
の本体9は天板としての上フランジ11、底板としての
下フランジ13及び側板としての2枚のウェブ15とか
ら構成されている。また、上フランジ11、下フランジ
13、ウェブ15はいずれも鋼材によって構成されてい
る。上フランジ11には、ボルト挿通穴28が形成さ
れ、下フランジ13には、ボルト挿通穴30が形成され
ている。2枚のウェブ15の上端部14及び下端部16
は、直角に折り曲げられており、この上端部14及び下
端部16には、ボルト挿通穴26が形成されている。
The construction of the bridge girder structure 10 will be described with reference to FIGS. Reference numeral 9 denotes a rectangular cylindrical main body, which is composed of an upper flange 11 as a top plate, a lower flange 13 as a bottom plate, and two webs 15 as side plates. The upper flange 11, the lower flange 13, and the web 15 are all made of steel. A bolt insertion hole 28 is formed in the upper flange 11, and a bolt insertion hole 30 is formed in the lower flange 13. Upper end 14 and lower end 16 of two webs 15
Is bent at a right angle, and a bolt insertion hole 26 is formed in the upper end portion 14 and the lower end portion 16.

【0024】ウェブ15の上端部14には、上フランジ
11が接合され、ボルト21がボルト挿通穴26、28
に挿通され、このボルト21にナット20が取り付けら
れて、上フランジ11とウェブ15とが連結されてい
る。ウェブ15の下端部16には、下フランジ13が接
合され、ボルト21がボルト挿通穴26、30に挿通さ
れ、このボルト21にナット20が取り付けられて、下
フランジ13とウェブ15とが連結されている。これら
ボルト21、ナット20及びボルト挿通穴26、28、
30によって上フランジ11と、ウエブ15と、下フラ
ンジ13とを組立分解可能に連結する連結手段が構成さ
れている。
The upper flange 11 is joined to the upper end 14 of the web 15, and the bolt 21 is inserted into the bolt insertion holes 26 and 28.
The upper flange 11 and the web 15 are connected to each other with a nut 20 attached to the bolt 21. The lower flange 13 is joined to the lower end 16 of the web 15, the bolt 21 is inserted into the bolt insertion holes 26 and 30, the nut 20 is attached to the bolt 21, and the lower flange 13 and the web 15 are connected. ing. These bolts 21, nuts 20, and bolt insertion holes 26, 28,
A connection means 30 connects the upper flange 11, the web 15, and the lower flange 13 so that they can be assembled and disassembled.

【0025】上フランジ11には、3つの楕円形の穴1
7が形成されている。この穴17は互いに一定の間隔を
空けて配置されている。ウェブ15の内側面には、鉄筋
を支持する支持部材としてのスタットジベル19が複数
設けられている。この複数のスタットジベル19は、互
いに対向する方向へ突出している。また、橋桁構成体1
0の両端部には、複数のボルト挿通穴12が形成されて
いる。橋桁5は後述するように、複数の橋桁構成体10
が連結され、この内部に鉄筋22、23が配置され、更
にコンクリート24が充填されて構成されている。
The upper flange 11 has three oval holes 1.
7 are formed. The holes 17 are arranged at a certain interval from each other. On the inner surface of the web 15, a plurality of stat dowels 19 are provided as support members for supporting the reinforcing bar. The plurality of stat dowels 19 project in directions facing each other. In addition, bridge girder construct 1
A plurality of bolt insertion holes 12 are formed at both ends of the zero. The bridge girder 5 includes a plurality of bridge girder structures 10 as described later.
Are connected, rebars 22 and 23 are arranged inside, and concrete 24 is filled.

【0026】橋桁5の施工方法について説明する。橋桁
構成体10を連結する工程について説明する。図4に示
すように複数の橋桁構成体10の本体9の端面どうしを
接合し、この接合部分にボルト挿通穴32が形成された
添設板31を当接させる。添設板31は本体9の内面側
と外面側の双方に配置する。そしてボルト33を添設板
31のボルト挿通穴32と本体9のボルト挿通穴12に
挿通し、さらにボルト33にナット35を取り付けて締
め付け、橋桁構成体10の本体9どうしを連結する。本
体9の両端部に形成されたボルト挿通穴12、添設板3
1、ボルト33及びナット35によって、橋桁構成体1
0どうしを連結する連結手段が構成されている。
A method for constructing the bridge girder 5 will be described. A process of connecting the bridge girder members 10 will be described. As shown in FIG. 4, the end faces of the main bodies 9 of the plurality of bridge girders 10 are joined together, and an attached plate 31 having a bolt insertion hole 32 is brought into contact with the joined portion. The attachment plates 31 are arranged on both the inner surface and the outer surface of the main body 9. Then, the bolts 33 are inserted through the bolt insertion holes 32 of the attachment plate 31 and the bolt insertion holes 12 of the main body 9, and nuts 35 are attached to the bolts 33 and tightened to connect the main bodies 9 of the bridge girder structure 10 together. Bolt insertion holes 12 formed at both ends of main body 9, attached plate 3
1, the bridge 33 and the nut 35
A connecting means for connecting the zeros is configured.

【0027】橋桁構成体10を橋台2または橋脚3の上
に載せて、連結する工程について説明する。上記のよう
にして3つの橋桁構成体10を連結し、これを図5、図
6に示すようにクレーン41によって吊り上げ、橋台2
または橋脚3の上に設置する。橋桁構成体10は角筒状
で軽量であるため、橋桁構成体10をクレーン41で吊
り上げて載せる作業は、比較的容易に行うことができ
る。そして、橋台2または橋脚3の上に設置した橋桁構
成体10どうしを図4で説明した方法と同様にして連結
する。
The step of mounting the bridge girder structure 10 on the abutment 2 or the pier 3 and connecting them will be described. The three bridge girder constructs 10 are connected as described above, and this is lifted by the crane 41 as shown in FIGS.
Or install it on pier 3. Since the bridge girder structure 10 is rectangular and lightweight, the work of lifting and placing the bridge girder structure 10 with the crane 41 can be performed relatively easily. Then, the bridge girder constructs 10 installed on the abutment 2 or the pier 3 are connected to each other in the same manner as described with reference to FIG.

【0028】橋桁構成体10内に鉄筋22及び鉄筋23
を配置する工程について説明する。鉄筋22の両端部を
スタットジベル19に載せて配置する。次に、複数の鉄
筋23を鉄筋22上に載せ、橋桁構成体10の長手方向
に延びる方向に配置し、鉄筋22と鉄筋23との交差部
分を針金等で結ぶ。なお、鉄筋23は、一定の間隔を空
けて配置しても良く、また不定間隔で配置しても良い。
The reinforcing bar 22 and the reinforcing bar 23 are provided in the bridge girder structure 10.
Will be described. Both ends of the reinforcing bar 22 are placed on the stat dowel 19. Next, the plurality of reinforcing bars 23 are placed on the reinforcing bars 22, arranged in a direction extending in the longitudinal direction of the bridge girder structure 10, and intersecting portions between the reinforcing bars 22 and the reinforcing bars 23 are connected by wire or the like. The reinforcing bars 23 may be arranged at regular intervals or at irregular intervals.

【0029】コンクリート24を流し込む工程について
説明する(図7参照)。橋台2及び橋脚3上に載せられ
た複数の橋桁構成体10の一番端の穴17から、コンク
リート24を流し込み、この穴17に対応する部分がコ
ンクリート24で満たされたら、蓋25によって穴17
を塞ぐ。そして、蓋25によって塞いだ穴17の隣の穴
17へコンクリート24を流し込む。このコンクリート
24の流し込みを順次行い、橋桁構成体10の内部全体
をコンクリート24によって満たす。コンクリート24
を順次流し込む際、橋桁構成体10内の空気は、コンク
リート24を流し込んでいる穴17以外の穴17から抜
けるので、コンクリート24を橋桁構成体10内へスム
ーズに供給することができる。
The step of pouring the concrete 24 will be described (see FIG. 7). Concrete 24 is poured from the end hole 17 of the plurality of bridge girder structures 10 placed on the abutment 2 and the pier 3, and when a portion corresponding to the hole 17 is filled with the concrete 24, the hole 25 is closed by the lid 25.
Close up. Then, the concrete 24 is poured into the hole 17 next to the hole 17 closed by the lid 25. The concrete 24 is poured sequentially, and the entire inside of the bridge girder structure 10 is filled with the concrete 24. Concrete 24
In the bridge girder structure 10, the air in the bridge girder structure 10 flows out of the holes 17 other than the holes 17 into which the concrete 24 is poured, so that the concrete 24 can be smoothly supplied into the bridge girder structure 10.

【0030】コンクリート24が固化すると、コンクリ
ート24、橋桁構成体10及び鉄筋22、23が一体化
して合成構造となり、大きな剛性をもち、しかも、従来
の橋桁に比べて、小型で、且つ軽量なものとできるの
で、従来の橋桁を使用した場合より橋脚3の間隔を長く
でき、橋脚の数を少なくすることができる。尚、スタッ
トジベル19がコンクリート24に埋設された状態とな
るので、ウェブ15とコンクリート24とがより強固に
連結されることになる。また、橋桁構成体10の本体9
が、橋桁5の外壁を構成することになるので、コンクリ
ート型枠を組んだり、これを外したりする必要がない。
さらに、仮設材を設けずに橋桁5を施工することが可能
となる。
When the concrete 24 is solidified, the concrete 24, the bridge girder structure 10 and the reinforcing bars 22, 23 are integrated to form a composite structure, which has high rigidity and is smaller and lighter than the conventional bridge girder. Therefore, the interval between the piers 3 can be made longer than when a conventional bridge girder is used, and the number of piers can be reduced. Since the stat dowel 19 is buried in the concrete 24, the web 15 and the concrete 24 are connected more firmly. Also, the main body 9 of the bridge girder structure 10
However, since it constitutes the outer wall of the bridge girder 5, it is not necessary to form or remove the concrete formwork.
Further, the bridge girder 5 can be constructed without providing a temporary material.

【0031】図8、図9によって、橋桁構成体10を橋
台2、橋脚3上に設置する他の方法について説明する。
下フランジ13どうしのみを、上記したように添設板3
1、ボルト33及びナット35とによって連結し、この
連結した下フランジ13のみを橋台2、橋脚3上に載
せ、その後に下フランジ13に、ウェブ15さらに上フ
ランジ11をボルト21とナット20を用いて組み付け
て、橋桁構成体10を完成させる。この方法によれば、
橋桁構成体10を分解した状態で、構成部材毎、クレー
ン41で容易に吊り上げることできるので、吊り上げ重
量の比較的小さいクレーンでも作業することができるよ
うになる。
Another method of installing the bridge girder structure 10 on the abutment 2 and the pier 3 will be described with reference to FIGS.
Only the lower flanges 13 are attached to each other as described above.
1, the bolt 33 and the nut 35 are connected, and only the connected lower flange 13 is placed on the abutment 2 and the pier 3. Then, the lower flange 13 is connected to the web 15 and the upper flange 11 using the bolt 21 and the nut 20. To complete the bridge girder structure 10. According to this method,
Since the bridge girder structure 10 can be easily lifted by the crane 41 for each component in a state where the bridge girder structure 10 is disassembled, it is possible to work even with a crane having a relatively small lifting weight.

【0032】図10は第二の実施の形態にかかる橋桁5
1を示す断面図である。同図において符号53は中空部
材としての丸パイプを示し、この丸パイプ53は所謂ス
パイラル管等によって構成する。丸パイプ53は脚部5
5によって支持されており、橋桁構成体10内の略中央
に配置されている。
FIG. 10 shows a bridge girder 5 according to the second embodiment.
FIG. In the figure, reference numeral 53 denotes a round pipe as a hollow member, and the round pipe 53 is constituted by a so-called spiral pipe or the like. Round pipe 53 has leg 5
5 and is disposed substantially at the center of the bridge girder structure 10.

【0033】この橋桁51では、丸パイプ53内にコン
クリート24が流れ込まず、丸パイプ53の内部にコン
クリート24の無い空間が形成される。従って、橋桁5
1は、より軽量化されることになる。但し、橋桁51の
上フランジ11と下フランジ13付近は、コンクリート
24が満たされた状態となっている。橋桁51は、上方
から床版7等による荷重がかかるので、上フランジ11
付近と下フランジ13付近に大きな応力が発生すること
なる。従って、丸パイプ53によってコンクリート24
の無い空間が形成されても、橋桁51の強度に悪影響を
及ぼすことはない。
In the bridge girder 51, the concrete 24 does not flow into the round pipe 53, and a space without the concrete 24 is formed inside the round pipe 53. Therefore, bridge girder 5
1 will be lighter. However, the vicinity of the upper flange 11 and the lower flange 13 of the bridge girder 51 is in a state where the concrete 24 is filled. Since the bridge girder 51 receives a load from the floor slab 7 or the like from above, the upper flange 11
A large stress is generated in the vicinity and near the lower flange 13. Therefore, the concrete 24 is formed by the round pipe 53.
Even if a space having no gap is formed, the strength of the bridge girder 51 is not adversely affected.

【0034】図11は図10に示す橋桁の変形例61を
示すものである。この橋桁61は、橋桁構成体10内の
略中央に角パイプ63を、脚部55によって支持して配
置したものである。この橋桁61も、橋桁51と同様に
軽量化を図ることができる。
FIG. 11 shows a modification 61 of the bridge girder shown in FIG. In this bridge girder 61, a square pipe 63 is disposed at substantially the center in the bridge girder structure 10 and supported by legs 55. The bridge girder 61 can be reduced in weight similarly to the bridge girder 51.

【0035】図12及び図13は本発明の第三の実施の
形態にかかる橋桁71を示すものであり、この橋桁71
においては、内部にPC鋼材を通し、このPC鋼材にテ
ンションをかけることでコンクリート24にプレストレ
スを与えている。
FIGS. 12 and 13 show a bridge girder 71 according to a third embodiment of the present invention.
In the above, a prestress is given to the concrete 24 by passing a PC steel material inside and applying tension to the PC steel material.

【0036】同図において、73は、PC鋼棒、PC鋼
より線、PC鋼線、PC硬鋼線等のPC鋼材を示す。こ
のPC鋼材73は、橋桁71の長手方向に沿って延びる
向きでコンクリート24内を通されており、左右5列上
下3段に配置されている。そして、PC鋼材73には、
長さを縮めようとする強い力を持つように予めテンショ
ンをかけてある。このテンションの掛け方は、コンクリ
ートが硬化した後に行うポストテンション方式、又は、
コンクリートが硬化する前に行うプレテンション方式の
いずれであっても良い。(図面にはポストテンション方
式による施工例を示してある。)
In the figure, reference numeral 73 denotes a PC steel material such as a PC steel rod, a PC steel strand, a PC steel wire, a PC hard steel wire, and the like. The PC steel material 73 is passed through the concrete 24 in a direction extending along the longitudinal direction of the bridge girder 71, and is arranged in five rows on the right and left and three levels in the top and bottom. And in the PC steel 73,
It is pre-tensioned to have a strong force to shorten the length. How to apply this tension, post tension method to be performed after the concrete is hardened, or
Any of the pretensioning methods performed before the concrete hardens may be used. (The drawing shows an example of construction using the post tension method.)

【0037】しかして、このPC鋼材73の収縮力によ
ってコンクリート24に圧縮力が加えられ、この圧縮力
により、橋桁71にかかる死荷重や活荷重によって生じ
る引っ張り応力が減殺される。
Thus, a compressive force is applied to the concrete 24 by the contraction force of the PC steel material 73, and the compressive force reduces the tensile stress generated by the dead load and the live load applied to the bridge girder 71.

【0038】以上、本発明の実施の形態について詳述し
てきたが、具体的な構成はこの実施の形態に限られるも
のではなく、本発明の要旨を逸脱しない範囲における設
計の変更などがあっても本発明に含まれる。例えば、上
記実施の形態にかかる橋桁構成体10の本体9は、上フ
ランジ11、下フランジ13及びウェブ15をボルト2
1、ナット20を用いて連結して構成されているが、本
発明は、これに限定されず溶接によって連結することも
可能である。
Although the embodiment of the present invention has been described in detail above, the specific configuration is not limited to this embodiment, and there is a change in design without departing from the gist of the present invention. Are also included in the present invention. For example, the main body 9 of the bridge girder structure 10 according to the above-described embodiment includes the upper flange 11, the lower flange 13, and the web 15 connected to the bolt 2.
1. Although the connection is made by using the nut 20, the present invention is not limited to this, and the connection can be made by welding.

【0039】また、コンクリート24を穴17に流し込
む場合、本体9内の空気を抜くことができれば、複数の
穴17に同時にコンクリート24を流し込むようにして
もよい。本体9は、角筒状に限られるものではなく、他
の形状、例えば円筒状でも良い。また、穴17は楕円形
に限られるものではなく、円形や矩形でも良い。
When the concrete 24 is poured into the holes 17, the concrete 24 may be poured into the plurality of holes 17 at the same time if the air in the main body 9 can be released. The main body 9 is not limited to a rectangular tube shape, but may have another shape, for example, a cylindrical shape. The hole 17 is not limited to an elliptical shape, but may be a circular or rectangular shape.

【0040】[0040]

【発明の効果】以上のように本発明によれば、従来の鈑
桁や箱桁と異なり、鋼材とコンクリートとによって構成
されているので、材料費を低く抑えることが可能とな
る。また、プレビーム桁と異なり、コンクリートを打設
するための型枠を組んだり、外したりする必要がない。
従って、従来の橋桁より製作コストの低減化を図ること
ができる。そして、本発明の橋桁の施工方法にあって
は、橋桁の外壁を構成する橋桁構成体を一個づつ又は数
個一組みの形に連結してから橋脚や橋台に載せてそれを
順次連結して行くか、又は、橋桁構成体を構成する底板
だけを先に連結しておいてその後で側板や天板を組み立
てて行くようにしたので、従来の橋桁の施工方法より大
幅に小型且つ軽量な状態での運搬等を行うことができ、
従って、橋桁の運搬作業や施工作業を容易に行うことが
できる。さらに、橋桁の運搬作業や施工作業を容易に行
うことができるために、工期を短くすることが可能とな
る。
As described above, according to the present invention, unlike conventional sheet girders and box girders, the present invention is made of steel and concrete, so that material costs can be reduced. Unlike the pre-beam girder, there is no need to form or remove a formwork for placing concrete.
Therefore, the manufacturing cost can be reduced as compared with the conventional bridge girder. And, in the method of constructing a bridge girder of the present invention, the bridge girder constructing the outer wall of the bridge girder is connected one by one or several sets, and then placed on a pier or abutment and sequentially connected. Going, or connecting only the bottom plate that constitutes the bridge girder first, and then assembling the side plate and top plate, so it is significantly smaller and lighter than the conventional bridge girder construction method Transportation, etc.,
Therefore, it is possible to easily carry and carry the bridge girder. Further, since the work of transporting and constructing the bridge girder can be easily performed, the construction period can be shortened.

【0041】橋桁構成体、鉄筋及びコンクリートが一体
化し合成構造となるので、大きな剛性を得ることができ
るようになる。従って、橋脚を長い間隔で配置すること
が可能となり、従来よりも橋脚の数を減らすことができ
るようになり、橋梁のコストを低く抑えることが可能に
なる。
Since the bridge girder structure, the reinforcing bar and the concrete are integrated to form a composite structure, a large rigidity can be obtained. Therefore, the piers can be arranged at long intervals, and the number of piers can be reduced as compared with the related art, so that the cost of the bridge can be reduced.

【0042】橋桁構成体を構成する天板、底板および側
板を溶接以外の手段によって締結すれば、溶接時の熱に
よる鋼材の変性をなくすことができ、橋梁の耐久性に悪
影響を及ぼすおそれもなくなる。
If the top plate, the bottom plate and the side plates constituting the bridge girder are fastened by means other than welding, the deformation of the steel material due to heat during welding can be eliminated, and there is no risk of adversely affecting the durability of the bridge. .

【0043】橋桁構成体内にPC鋼材を通し、このPC
鋼材にテンションをかけることで橋桁構成体内のコンク
リートにプレストレスを与えれば、重量をほとんど増や
さないで耐荷重強度を高めることができる。
A PC steel material is passed through the bridge girder structure,
By prestressing the concrete in the bridge girder structure by applying tension to the steel material, the load bearing strength can be increased without increasing the weight substantially.

【図面の簡単な説明】[Brief description of the drawings]

【図1】本発明の第一の実施の形態にかかる橋桁を使用
した橋梁を示す要部斜視図である。
FIG. 1 is a perspective view of a main part showing a bridge using a bridge girder according to a first embodiment of the present invention.

【図2】本発明の実施の形態にかかる橋桁構成体を、内
部に鉄筋を配置した状態で示す斜視図である。
FIG. 2 is a perspective view showing the bridge girder structure according to the embodiment of the present invention in a state in which a reinforcing bar is arranged inside.

【図3】図2のA−A線に沿って切断した拡大断面図で
ある。
FIG. 3 is an enlarged sectional view taken along the line AA of FIG. 2;

【図4】図2に示す橋桁構成体を2個連結した状態で示
す一部切欠要部斜視図である。
FIG. 4 is a partially cutaway perspective view showing a main part of the bridge girder structure shown in FIG.

【図5】本発明の橋桁の施工方法における初期段階を示
す模式図である。
FIG. 5 is a schematic diagram showing an initial stage in the method for constructing a bridge girder of the present invention.

【図6】本発明の橋桁の施工方法における最終段階を示
す模式図である。
FIG. 6 is a schematic diagram showing a final stage in the method for constructing a bridge girder of the present invention.

【図7】本発明の橋桁の施工方法におけるコンクリート
を流し込む工程を示す摸式図である。
FIG. 7 is a schematic view showing a step of pouring concrete in the method for constructing a bridge girder of the present invention.

【図8】本発明にかかる橋桁の施工方法の別の例を示す
模式図である。
FIG. 8 is a schematic view showing another example of the method for constructing a bridge girder according to the present invention.

【図9】図8に示す橋桁の施工方法によって完成した状
態の橋桁を示す模式図である。
9 is a schematic view showing a bridge girder in a state completed by the bridge girder construction method shown in FIG. 8;

【図10】本発明の第二の実施の形態にかかる橋桁の断
面図である。
FIG. 10 is a sectional view of a bridge girder according to the second embodiment of the present invention.

【図11】図10に示す橋桁の変形例を示す断面図であ
る。
11 is a sectional view showing a modification of the bridge girder shown in FIG.

【図12】本発明の第三の実施の形態にかかる橋桁の要
部垂直断面図である。
FIG. 12 is a vertical sectional view of a main part of a bridge girder according to a third embodiment of the present invention.

【図13】図12のB−B線に沿って切断した拡大断面
図である。
FIG. 13 is an enlarged sectional view taken along line BB of FIG.

【符号の説明】[Explanation of symbols]

1 橋梁 2 橋台 3 橋脚 5 橋桁 9 本体 10 橋桁構成体 11 天板 13 底板 15 側板 17 穴 19 鉄筋を支持する支持部材 20、21、26、28、30 連結手段 22 鉄筋 23 鉄筋 24 コンクリート 51 橋桁 53 中空部材 61 橋桁 63 中空部材 71 橋桁 73 PC鋼材 DESCRIPTION OF SYMBOLS 1 Bridge 2 Abutment 3 Bridge pier 5 Bridge girder 9 Main body 10 Bridge girder structure 11 Top plate 13 Bottom plate 15 Side plate 17 Hole 19 Support member 20 for supporting a reinforcing bar 20, 21, 26, 28, 30 Connecting means 22 Reinforcing bar 23 Reinforcing bar 24 Concrete 51 Bridge beam 53 Hollow member 61 Bridge girder 63 Hollow member 71 Bridge girder 73 PC steel

Claims (15)

【特許請求の範囲】[Claims] 【請求項1】橋梁の橋桁を構成する橋桁構成体であっ
て、筒状の本体と、前記本体に形成され内部に連通する
穴が形成されていることを特徴とする橋桁構成体。
1. A bridge girder constructing a bridge girder of a bridge, comprising a cylindrical main body and a hole formed in the main body and communicating with the inside thereof.
【請求項2】請求項1記載の橋桁構成体において、本体
は鋼材によって構成されていることを特徴とする橋桁構
成体。
2. The bridge girder structure according to claim 1, wherein the main body is made of a steel material.
【請求項3】請求項2記載の橋桁構成体において、本体
は、天板と側板と底板とが連結されて角筒状に形成さ
れ、且つ、穴は前記天板に形成されていることを特徴と
する橋桁構成体。
3. The bridge girder structure according to claim 2, wherein the main body is formed in a rectangular tube shape by connecting a top plate, a side plate, and a bottom plate, and a hole is formed in the top plate. The bridge girder structure that is the feature.
【請求項4】請求項3記載の橋桁構成体において、天板
と側板と底板とが組立分解可能な連結手段によって連結
されていることを特徴とする橋桁構成体。
4. The bridge girder structure according to claim 3, wherein the top plate, the side plate and the bottom plate are connected by connecting means that can be assembled and disassembled.
【請求項5】請求項4記載の橋桁構成体において、穴は
複数形成され且つ所定の間隔を空けて配置されているこ
とを特徴とする橋桁構成体。
5. The bridge girder structure according to claim 4, wherein a plurality of holes are formed and are arranged at predetermined intervals.
【請求項6】請求項5記載の橋桁構成体において、側板
の内側面に鉄筋を支持する支持部材が設けられているこ
とを特徴とする橋桁構成体。
6. The bridge girder structure according to claim 5, wherein a support member for supporting a reinforcing bar is provided on an inner side surface of the side plate.
【請求項7】筒状の本体を有し外壁を構成する橋桁構成
体と、前記橋桁構成体どうしを連結する連結手段と、前
記橋桁構成体内に配置された鉄筋と、前記橋桁構成体内
に流し込まれたコンクリートとからなることを特徴とす
る橋桁。
7. A bridge girder having a cylindrical main body and constituting an outer wall, connecting means for connecting the bridge girder structures, a reinforcing bar disposed in the bridge girder structure, and pouring into the bridge girder structure. A bridge girder made of recycled concrete.
【請求項8】請求項7記載の橋桁において、橋桁構成体
の本体内に、コンクリートが流入しない空間を形成する
ための中空部材を備えたことを特徴とする橋桁。
8. The bridge girder according to claim 7, further comprising a hollow member for forming a space into which concrete does not flow, in the main body of the bridge girder structure.
【請求項9】請求項7又は8に記載の橋桁において、橋
桁構成体内にPC鋼材を設け、このPC鋼材にテンショ
ンをかけることで橋桁構成体内のコンクリートにプレス
トレスを与えたことを特徴とする橋桁。
9. The bridge girder according to claim 7, wherein a PC steel material is provided in the bridge girder structure, and prestress is applied to concrete in the bridge girder structure by applying tension to the PC steel material. Bridge girder.
【請求項10】筒状の本体を有し且つ穴が形成されてお
り橋桁の外壁を構成する橋桁構成体を橋台または橋脚に
載せる工程と、前記橋桁構成体どうしを連結する工程
と、前記橋桁構成体内に鉄筋を配置する工程と、前記橋
桁構成体に形成された穴からコンクリートを流し込む工
程とからなることを特徴とする橋桁の施工方法。
10. A step of mounting a bridge girder construct having a cylindrical main body and having a hole formed therein and constituting an outer wall of the bridge girder on an abutment or a pier; a step of connecting the bridge girder constructs to each other; A method for constructing a bridge girder, comprising a step of arranging a reinforcing bar in a constituent body and a step of pouring concrete through a hole formed in the bridge girder constituent body.
【請求項11】天板と側板と底板とが組立分解可能な連
結手段によって連結されており且つ前記天板に穴が形成
されている本体を有する橋桁構成体の複数の底板どうし
を互いに連結する工程と、前記連結された複数の底板を
橋台または橋脚に載せる工程と、前記橋台または橋脚に
載せられた底板に側板及び天板を連結して橋桁構成体を
形成する工程と、前記橋桁構成体どうしを連結する工程
と、前記橋桁構成体内に鉄筋を配置する工程と、前記橋
桁構成体の天板に形成されている穴からコンクリートを
流し込む工程とからなることを特徴とする橋桁の施工方
法。
11. A plurality of bottom plates of a bridge girder comprising a top plate, side plates and a bottom plate which are connected by connecting means which can be disassembled and disassembled, and having a main body having a hole formed in said top plate. A step of mounting the plurality of connected bottom plates on an abutment or pier; a step of connecting a side plate and a top plate to the bottom plate mounted on the abutment or pier to form a bridge girder structure; A method for constructing a bridge girder, comprising: a step of connecting together, a step of arranging a reinforcing bar in the bridge girder body; and a step of pouring concrete through a hole formed in a top plate of the bridge girder body.
【請求項12】筒状の本体を有し且つ穴が形成されてお
り橋桁の外壁を構成する橋桁構成体を橋台または橋脚に
載せる工程と、前記橋桁構成体どうしを連結する工程
と、前記橋桁構成体内に鉄筋を配置する工程と、橋桁構
成体の天板に形成されている複数の穴のうち少なくとも
1つを残して、前記残した穴以外の穴からコンクリート
を流し込む工程とからなることを特徴とする橋桁の施工
方法。
12. A step of mounting a bridge girder structure having a cylindrical main body and having a hole formed thereon and constituting an outer wall of the bridge girder on an abutment or a pier; a step of connecting the bridge girder structures to each other; Arranging a reinforcing bar in the component body, and leaving at least one of a plurality of holes formed in the top plate of the bridge girder component, and pouring concrete through holes other than the remaining holes. Characteristic bridge girder construction method.
【請求項13】天板と側板と底板とが組立分解可能な連
結手段によって連結されており且つ前記天板に穴が形成
されている本体を有する橋桁構成体の複数の底板どうし
を互いに連結する工程と、前記連結された複数の底板を
橋台または橋脚に載せる工程と、前記橋台または橋脚に
載せられた底板に側板及び天板を連結して橋桁構成体を
形成する工程と、前記橋桁構成体どうしを連結する工程
と、前記橋桁構成体内に鉄筋を配置する工程と、橋桁構
成体の天板に形成されている複数の穴のうち少なくとも
1つを残して、前記残した穴以外の穴からコンクリート
を流し込む工程とからなることを特徴とする橋桁の施工
方法。
13. A plurality of bottom plates of a bridge girder comprising a top plate, side plates, and a bottom plate which are connected by connecting means capable of being disassembled and disassembled, and having a main body having a hole formed in said top plate. A step of mounting the plurality of connected bottom plates on an abutment or pier; a step of connecting a side plate and a top plate to the bottom plate mounted on the abutment or pier to form a bridge girder structure; Connecting together, arranging a reinforcing bar in the bridge girder structure, leaving at least one of a plurality of holes formed in a top plate of the bridge girder structure, and removing holes from holes other than the remaining holes. A method for constructing a bridge girder, comprising a step of pouring concrete.
【請求項14】請求項10から13に記載の橋桁の施工
方法のいずれかにおいて、コンクリートが流入しない空
間を形成するための中空部材を橋桁構成体の内部の所定
位置に配置する工程を具備することを特徴とする橋桁の
施工方法。
14. A method for constructing a bridge girder according to any one of claims 10 to 13, further comprising the step of disposing a hollow member for forming a space into which concrete does not flow in at a predetermined position inside the bridge girder structure. A method of constructing a bridge girder characterized by the following.
【請求項15】請求項10から14に記載の橋桁の施工
方法のいずれかにおいて、橋桁構成体内にPC鋼材を設
けてこれにテンションをかけることで橋桁構成体内のコ
ンクリートにプレストレスを与える工程を具備すること
を特徴とする橋桁の施工方法。
15. A method according to claim 10, wherein a prestress is applied to concrete in the bridge girder structure by providing a PC steel material in the bridge girder structure and applying tension thereto. A method for constructing a bridge girder, comprising:
JP30784797A 1996-11-11 1997-10-21 Bridge girder, bridge girder component, and work execution method for bridge girder Pending JPH10183533A (en)

Priority Applications (2)

Application Number Priority Date Filing Date Title
JP30784797A JPH10183533A (en) 1996-11-11 1997-10-21 Bridge girder, bridge girder component, and work execution method for bridge girder
EP97308931A EP0841434A1 (en) 1996-11-11 1997-11-06 Bridge girder, bridge girder part and process for constructing bridge girder

Applications Claiming Priority (3)

Application Number Priority Date Filing Date Title
JP31562496 1996-11-11
JP8-315624 1996-11-11
JP30784797A JPH10183533A (en) 1996-11-11 1997-10-21 Bridge girder, bridge girder component, and work execution method for bridge girder

Publications (1)

Publication Number Publication Date
JPH10183533A true JPH10183533A (en) 1998-07-14

Family

ID=26565294

Family Applications (1)

Application Number Title Priority Date Filing Date
JP30784797A Pending JPH10183533A (en) 1996-11-11 1997-10-21 Bridge girder, bridge girder component, and work execution method for bridge girder

Country Status (2)

Country Link
EP (1) EP0841434A1 (en)
JP (1) JPH10183533A (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20060061000A (en) * 2004-12-01 2006-06-07 공강주 Construction method of charge type steel box a fabric
KR100720730B1 (en) 2006-03-23 2007-05-21 승화프랜트산업 (주) Concrete filled composite double tube and method connecting the tube with the other
KR100785907B1 (en) 2004-09-17 2007-12-17 조현준 An hollow hybrid girder
CN103194978A (en) * 2013-04-16 2013-07-10 中铁十七局集团第三工程有限公司 Erecting method for last three-span box girders in railway bridging

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
FR2795438B1 (en) * 1999-06-28 2001-08-03 Dumez Gtm STRUCTURE OF A CONCRETE-STEEL MIXED BRIDGE OR GATEWAY, PARTICULARLY A MIXED TWO-GATE APRON BRIDGE

Family Cites Families (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US2731824A (en) * 1956-01-24 hadley
JPS5016570B1 (en) * 1967-07-03 1975-06-13
AT286583B (en) * 1970-01-23 1970-12-10 Johann Meier Reinforced concrete beams
DE2156017A1 (en) * 1971-11-11 1973-05-17 Dyckerhoff & Widmann Ag PRE-TENSIONED STEEL COMPOSITE BEAM
US4993095A (en) * 1989-11-09 1991-02-19 Armco Inc. Splice for a structural member

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100785907B1 (en) 2004-09-17 2007-12-17 조현준 An hollow hybrid girder
KR20060061000A (en) * 2004-12-01 2006-06-07 공강주 Construction method of charge type steel box a fabric
KR100720730B1 (en) 2006-03-23 2007-05-21 승화프랜트산업 (주) Concrete filled composite double tube and method connecting the tube with the other
CN103194978A (en) * 2013-04-16 2013-07-10 中铁十七局集团第三工程有限公司 Erecting method for last three-span box girders in railway bridging

Also Published As

Publication number Publication date
EP0841434A1 (en) 1998-05-13

Similar Documents

Publication Publication Date Title
KR100609304B1 (en) Precast Composition I-Beam with Concrete Panel and Corrugated Steel Web Girder
JP5442421B2 (en) Half precast slab and slab construction method using the same
KR101270733B1 (en) Prestressed Concrete Box Girder Integrated with Steel Deck and Constructing Method of Bridge using Such Girder
WO2009011516A2 (en) Form with reinforcing bars, non-support form system and non-support construction method using the same
JPH09221717A (en) Steel-concrete composite floor-slab bridge and construction method thereof
KR100343960B1 (en) Steel concrete structure
KR101582599B1 (en) Bridge construction method for forming continuous point part of pier using copping for connecting girder
JP3396610B2 (en) Hollow slab bridge and method of construction
KR20100007300A (en) A steel composite bridge having steel plates connected by using concrete cross beams and its constructing method
KR20140125754A (en) Bridge construction method for forming continuous point part of pier using copping for connecting girder
KR100593664B1 (en) Construction Method for prestressed composite slab
JPH10183533A (en) Bridge girder, bridge girder component, and work execution method for bridge girder
JPH04228710A (en) Road slab for bridge
JP3973577B2 (en) Bridge, bridge structure and bridge construction method
JPS5834607B2 (en) Erection method of prefabricated prestressed steel girder
JP4607785B2 (en) Continuous viaduct
KR101402620B1 (en) Construction method of slab type rahmen birdge using Half-PC slab for slab bridge
JPH0434161A (en) Centrifugally molded hollow pc concrete column and column construction method
JP2006183286A (en) Connection structure of corrugated steel web for corrugated steel web u-shaped component bridge
JPH10110498A (en) Half-precast floor slab and construction method of hollow flat slab making use thereof
JP3579333B2 (en) Floor slab structure and construction method of floor slab
JP2943111B1 (en) Bridge girder, bridge girder construct and bridge girder construction method
KR102712398B1 (en) Reinforced bridge top structure
KR100868865B1 (en) Method of constructuring prestressed concrete composite beam bridge continuation structure having haunch block located at columm part thereof and structure using same
JP2659329B2 (en) Construction method of PC structure